ML20083C014

From kanterella
Revision as of 07:27, 26 September 2022 by StriderTol (talk | contribs) (StriderTol Bot change)
(diff) ← Older revision | Latest revision (diff) | Newer revision → (diff)
Jump to navigation Jump to search
Forwards Addl Info to Support Review of License Amend Request Entitled Replacement of Selected Analog Leak Detection Sys Instruments W/Ge Numac Leak Detection Monitors
ML20083C014
Person / Time
Site: Perry FirstEnergy icon.png
Issue date: 05/05/1995
From: Shelton D
CENTERIOR ENERGY
To:
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
Shared Package
ML20083C018 List:
References
NUDOCS 9505150072
Download: ML20083C014 (1)


Text

p _

?

L i CENTEntOR

~

ENERGY PERRY NUCLEAR POWER PLANT Mail Address: DOnsld C. SheltOn G CENTER ROAD SENIOR VICE PRESIDENT RRY, O 10 44081 PERRY, OHIO 44081 NUCLEAR (216) 259 3737 ,

May 5, 1995 PY-CEI/NRR-1949L United States Nuclear Regulatory Commission Document Control Desk Vashington, D.C. 20555 Perry Nuclear Power Plant '

l Docket No. 50-440 Submittel of EMI/RFI and Seismic Analyses to support NUMAC License Amendment Request Gentlemen: ,

l Enclosed is additional information to support review of a license l amendment request dated November 22, 1993 (PY-CEI/NRR-1654L) entitled ,

" Replacement of Selected Analog Leak Detection System Instruments with GE l NUMAC Leak Detection Monitors". ]

Engineering reports are enclosed which summarize Electromagnetic Interference / Radio-frequency Interference (EMI/RFI) and seismic analyses performed in support of the Leak Detection System design change. When combined with previously submitted information, these reports show that j implementation of the design change at the Perry Nuclear Power Plant is  !

I acceptable. The Significant Hazard and Environmental Considerations provided in the November 22, 1993 letter have been reviewed, and were .

l determined to bound the additional information provided in thir, submittal.  !

Also note that the new Leak Detection System monitor design vill reflect License Amendment 59: specifically, delta-temperature isolation of the Reactor Core Isolation Cooling system (see page 31 of Attachment 1 to the i 11/22/93 letter) is not included, but the alarm function is maintained. l l

If you have questions or require additional information, please contact i Mr. James D. Kloosterman, Managet - Regulatory Affairs at (216) 280-5833.

Very truly yours, l l

w ,. twh p Donald'D. Shelton BSF:sc Enclosures 12C002 )