Forwards Insp Repts 50-317/98-12 & 50-318/98-12 on 981213- 990130 & Notice of Violation Re Failure of Maint Workers to Tighten Bolting for Svc Water Heat Exchanger
ML20207E964
Person / Time
Site: Calvert Cliffs  Constellation icon.png
Issue date: 03/04/1999
From: Barber G
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I)
To: Cruse C
BALTIMORE GAS & ELECTRIC CO.
Shared Package
ML20207E969 List:
References
50-317-98-12, 50-318-98-12, NUDOCS 9903110124
Download: ML20207E964 (3)


See also: IR 05000317/1998012

Text

h it i

March 4, 1999

Mr. Charles H. Cruse

Vice President - Nuclear Energy .

Baltimore Gas and Electric Company (BGE) .

Calvert Cliffs Nuclear Power Plant

1650 Calvert Cliffs Parkway

Lusby, MD 20657 - 4702

i

SUBJECT: . NRC REGION 1 INTEGRATED INSPECTION REPORT NOS. 50-317/98-12 f

50-318/98-12 AND NOTICE OF VIOLATION l

t

Dear Mr. Cruse:  !

.

.

1

. This report transmits the findings of the safety inspection conducted by NRC inspectors at the j

Calvert Cliffs Nuclear Power Plant from December 13 to January 30,1999. The enclosed report i

presents the results of that inspection. At the conclusion of the inspection, these findings were -

discussed with Mr. Katz and others of your staff. l

!

Overall, the NRC has concluded that your facility was operated in a safe manner. Your conduct of  ;

activities was generally characterized by safety-conscious operations, sound engineering and l

maintenance, and careful radiological controls.  !

i

However, the NRC has determined that a violation of NRC requirements occurred. The issue was

the failure of maintenance workers to tighten bolting for the service water heat exchanger  !

strainers prior to returning the strainers after performing corrective maintenance. Tightening the  !

bolting was required by the m intenance procedure to ensure system integrity. Our inspectors  !

identified the loose bolting during a system walkdown a few days after the maintenance.

i

The NRC has concluded that information regarding the reasons for the violation, the corrective  !

action taken and planned to correct the violation and prevent recurrence is already adequately i

addressed in the enclosed report. Therefore, you are not required to respond to this letter unless ' l

the description therein does not accurately reflect your correctiva actions or your position.- In that

case, or if you choose to provide additional information, you should follow the instructions ,

specified in the enclosod notice.  !

l

)i

9903110124 990304 -

'

PDR ADOCK 05000317

G PDR >

0FFICIAL RECORD COPY IE:01

i

- _ _ _ _ - . .-- . - . - - .

_ _ . . _ - _ . . _ _ . . . _ . _ . _ _ _ _ _ _ . _ _ _ - _ . _ _ _ . _ _ - - - . _ _ _ . . _ . - _ _ . - . .

4. -t j

Charles H. Cruse 2

4. We appreciate your cooperation. In accordance with 10 CFR 2.790 of the NRC " Rules of

,

Practice," a copy of this letter and its enclosures will be placed in the NRC Public Document l

Room (PDR).

sincerely,

G. Scott Barber, Acting Chief

Projects Branch 1 j

Division of Reactor Projects

Docket / License Nos.: 50-317/DPR-53 I

50-318/DPR-69

l

Enciosure: NRC Region 1 Integrated Inspection Report Nos. 50-317/98-12 and 50-318/98-12 i

cc w/ encl: l

B. Montgomery, Director, Nuclear Regulatory Matters (CCNPP) i

R. McLean, Administrator, Nuclear Evaluations

J. Walte' ngineering Division, Public Service Commission of Maryland

K. Burgc, Esquire, Maryland People's Counsel'

R. Ochs, Maryland Safe Energy Coalition l

State of Maryland (2) '

l

g j

,

4

!

.

l

l

- .

.. -.- - , . . . . . . .. ..

__ . - - _ . . . _ . _. _ __. _ . _ . _ . . - . _ _ _ .

i i

Charles H. Cruse 3

Distribution w/ encl:

H. Miller, RA/J. Wiggins, DRA (1)

Nuclear Safety Information Center (NSIC)

PUBLIC

NRC Resident inspector

Region i Docket Room (with concurrences)

S. Barber, DRP

W. Cook, DRP-

R. Junod, DRP l

Distribution w/ encl: (VIA E-MAIL)

J. Mitchell, RI EDO Coordinator

S. Stewart - Calvert Cliffs

S. Bajwa, NRR

A. Dromerick, NRR

M. Campion, R1

Inspection Program Brarch, NRR (IPAS)

R. Correia, NRR

DOCDESK

l

l

l

DOCUMENT NAME: G:\ BRANCH 1\CC981212.WPD

To receive a copy of this docum6nt, indicate in the box: "C" = Copy without

attachment / enclosure "E" = Copy with attachment / enclosure "N" = No copy

OFFICE RI /DRP , Id Rl/DRP ,, lM

NAME SStew#6 dh 16 SBarb@

DATE 03/'f /99 03/c//99 03/ /99

OFFICIAL RECORD COPY