MONTHYEARML24297A6392024-10-30030 October 2024 Reassignment of U.S. Nuclear Regulatory Commission Branch Chief in the Division of Operating Reactor Licensing for Plant Licensing Branch IV ML24214A1402024-08-0505 August 2024 July 24, 2024, Summary of the Public Meeting Regarding Clinton Power Station, Unit 1, Partial Site Release ML24135A3712024-05-21021 May 2024 Memo from Awaldron to Skoenick Transmitting Meeting Summary ML24128A2402024-05-0808 May 2024 Entergy Operations, Inc. - Entergy Fleet Project Manager Assignment ML24124A0342024-05-0101 May 2024 Summary of Public Meeting Concerning Annual Assessment of Catawba Nuclear Station Units 1 and 2, McGuire Nuclear Station Units 1 and 2, Oconee Nuclear Station Units 1, 2, and 3, Brunswick Steam Electric Plant Units 1 and 2, Shearon Harris ML24047A2092024-02-22022 February 2024 Calendar Year 2023 Baseline Inspection Completion ML23276A6522023-10-11011 October 2023 Pre-submittal Meeting Summary, September 14, 2023 ML23151A2532023-05-31031 May 2023 Meeting Summary of 2022 Annual Assessment Regarding Brunswick Steam Electric Plant, Docket Nos. 50-325 and 50-324, Meeting Number 20230392 ML23047A3822023-03-21021 March 2023 Summary of December 15, 2022 Periodic Advanced Reactor Stakeholder Public Meeting ML23044A3662023-02-15015 February 2023 Calendar Year 2022 Reactor Oversight Process Baseline Inspection Program Completion - Region III ML22349A5052023-02-0808 February 2023 Results of a Reactor Oversight Process Self Assessment Effectiveness Review of the Recommendations from IP 95003 at Arkansas Nuclear One ML22147A0932022-06-0606 June 2022 2021 Annual Assessment Public Meeting Summary ML22130A0302022-05-0909 May 2022 Summary of Public Meeting on 2021 Annual Assessment Meeting Regarding Brunswick Steam Electric Plant, Docket Nos. 50-325 and 50-324; and Shearon Harris Nuclear Power Plant, Docket No. 50-400, Meeting Number 20220350 ML22034A3932022-02-16016 February 2022 Calendar Year 2021 Security Baseline Completion Memo ML22040A2752022-02-11011 February 2022 NSIR Staff Review of the Duane Arnold Energy Center Security Plan, Training and Qualification Plan, and Safeguards Contingency Plan, for the Verification of ASM EA-02-104 Incorporation ML21277A2472021-11-0505 November 2021 Notification of Significant Licensing Action - Proposed Issuance of Order Approving the Transfer of Licenses for Which a Hearing Has Been Requested - Exelon Generation Company, LLC; Et. Al ML21295A0882021-10-21021 October 2021 Fiscal Year 2021 Research and Test Reactors Inspection Program Completion Status ML21288A0392021-10-18018 October 2021 September 14, 2021, Summary of Public Workshop on Scale/Melcor Source Term Demonstration Project - Pebble-Bed Molten-Salt-Cooled Reactor ML21273A1772021-10-0101 October 2021 Fiscal Year 2021 Research and Test Reactors Inspection Program Completion Status ML21181A3352021-07-0101 July 2021 June 23, 2021, Summary of Public Meeting to Discuss Technology Inclusive Content of Application Project ML21158A2232021-06-0808 June 2021 Meeting Summary for Ticap Workshop 3 ML21140A3892021-05-24024 May 2021 Riv Column 1 EOC 2020 Public Meeting Summary ML21132A2952021-05-14014 May 2021 Summary of Public Meeting to Discuss Technology Inclusive Content of Application Project ML21131A1472021-05-11011 May 2021 Public Meeting Summary 2020 Annual Assessment Meeting Regarding Brunswick Steam Electric Plant, Docket Nos. 50-325 and 50-324; and Shearon Harris Nuclear Power Plant, Docket No. 50-400, Meeting Number 20210385 ML21062A0932021-04-21021 April 2021 Memo to File: Final Ea/Fonsi of 2012 and 2015 Decommissioning Funding Plans for Duane Arnold Energy Center Independent Spent Fuel Storage Installation (2012 and 2015) ML21078A1272021-03-30030 March 2021 Final-LIC-504 Closure Memo - 03/30/2021 ML20315A1172020-12-25025 December 2020 DAEC-LIC504-Immediate-Determination-11-02 ML20337A1572020-12-0808 December 2020 Summary of Teleconference Meeting with Entergy Operations, Inc. to Discuss the Forthcoming Supplemental Response Concerning Generic Letter 2004-02 for Arkansas Nuclear One, Units 1 and 2 ML20150B3182020-11-23023 November 2020 Memo to File: Environmental Assessment and Finding of No Significant Impact and NRC Financial Analysis for Exelon Generation Co., LLC Decommissioning Funding Plan Submitted in Accordance with 10 CFR 72.30(b) and (C) for Quad Cities ISFSI ML20150A2812020-11-23023 November 2020 Memo to File: Environmental Assessment and Finding of No Significant Impact and NRC Financial Analysis for Exelon Generation Co., LLC Decommissioning Funding Plan Submitted in Accordance with 10 CFR 72.30(b) and (C) for Dresden ISFSI ML20150A4212020-11-23023 November 2020 Memo to File: Environmental Assessment and Finding of No Significant Impact and NRC Financial Analysis for Entergy Nuclear Company, LLC Decommissioning Funding Plan Submitted in Accordance with 10 CFR 72.30(b) and (C) for Grand Gulf ISFSI ML20149K5412020-11-23023 November 2020 Memo to File: Environmental Assessment and Finding of No Significant Impact and NRC Financial Analysis for Entergy Operations, Inc. Decommissioning Funding Plan Submitted in Accordance with 10 CFR 72.30(b) and (C) for Arkansas Nuclear One I ML20212L7682020-10-29029 October 2020 Memo to File: Final Environmental Assessment, Finding of No Significant Impacts, NRC Financial Analysis for Exelon Generation Company, Initial Decommissioning Funding Plan Submitted in Accordance with 10 CFR 72.30(B) for Clinton Power Stati ML20239A8252020-08-25025 August 2020 Summary of the August 4, 2020 Public Webinar to Discuss the NRC 2019 End-Of-Cycle Plant Performance Assessment of Clinton Power Station, Unit 1 ML20234A4472020-08-21021 August 2020 Summary of the July 29, 2020 Public Webinar to Discuss the NRC 2019 End-Of-Cycle Plant Performance Assessment of Quad Cities Nuclear Power Station, Units 1 and 2 ML20234A4422020-08-21021 August 2020 Summary of the July 29, 2020 Public Webinar to Discuss the NRC 2019 End-Of-Cycle Plant Performance Assessment of Dresden Nuclear Power Station, Units 2 and 3 ML20233A7902020-08-20020 August 2020 Summary of the July 30, 2020, Public Webinar to Discuss the NRC 2019 End-Of-Cycle Plant Performance Assessment of the Duane Arnold Energy Center and the Point Beach Nuclear Plant ML20136A2222020-05-15015 May 2020 Har - Bru 2019 Aam Meeting Summary ML20098G3132020-04-0707 April 2020 Actions Related to the Requirements for Work Hour Controls During the Coronavirus Disease 2019 Public Health Emergency IR 05000461/20190122019-09-25025 September 2019 NRC Inspection of Temporary Instruction 2515/194, Implementation of Industry Initiative Associated with the Open Phase Condition Design Vulnerabilities in Electric Power Systems Report 05000461/2019012 ML19266A5332019-09-0909 September 2019 (FEMA Memo to NRC 9-9-19) Preliminary Capabilities Assessment - Brunswick Nuclear Plant ML19254B4692019-09-0909 September 2019 (FEMA Letter NRC 09-09-19) Preliminary Capabilities Assessment - Brunswick Nuclear Power Plant ML19204A2972019-07-31031 July 2019 Memo to Management Review Board Arkansas Follow-up FY2019 Proposed Final Report ML19123A3532019-05-0202 May 2019 Public Meeting Summary - Brunswick Steam Electric Plant, Docket Nos. 05000325 and 05000324 ML18173A0082018-06-20020 June 2018 Cancelling Numerous Inspection Report Numbers ML18158A1702018-06-0707 June 2018 Special Inspection Team Charter for Inoperability of the Clinton Power Station Division 1 and Division 2 Emergency Diesel Generators ML18116A1082018-04-26026 April 2018 Summary of Meeting on Annual Assessment Public Meeting Regarding Brunswick Steam Electric Plant, Docket Nos. 05000325 and 05000324 ML17271A0532017-09-29029 September 2017 2017 Summary of Annual Decommissioning Funding Status Reports for Reactors in Decommissioning ML17181A4552017-06-29029 June 2017 Memo 06/29/17 2017 Dresden Generating Station Emergency Response Exercise After-Action Report (Blb) ML17153A0012017-06-0606 June 2017 Staff Observations of Testing for Generic Safety Issue 191 During a May 10 to May 11, 2017, Trip to the Alden Test Facility for Control Components Inc. Strainer Tests 2024-08-05
[Table view] |
Text
September 29, 2004 MEMORANDUM TO: William Ruland, Director Project Directorate III Division of Licensing Project Management Office of Nuclear Reactor Regulation FROM: William A. Macon, Jr., Project Manager, Section 2 /RA/
Project Directorate IV Division of Licensing Project Management Office of Nuclear Reactor Regulation
SUBJECT:
REVIEW OF REQUESTS FOR ADDITIONAL INFORMATION FOR RECENT EXTENDED POWER UPRATES In SECY-02-0115 dated June 27, 2002, the NRR staff committed, in part, to perform an assessment of requests for additional information (RAIs) issued during the NRR staffs review of past extended power uprate (EPU) applications. The NRR staff further committed to use the results of this assessment in the development of the review standard for EPUs and share the results of the assessment with internal and external stakeholders. The NRR staff had previously completed the assessment of the RAIs and used the results in the development of draft Review Standard (RS)-001, "Review Standard for Extended Power Uprates," which was issued in December 2002. The attached listing of RAIs which were issued during the NRR staffs review of the EPU applications for Duane Arnold, Dresden Units 2 and 3, Quad Cities Units 1 and 2, Clinton, Arkansas Nuclear One Unit 2, and Brunswick Units 1 and 2, is being made available in ADAMS under Accession No. ML023290378 to complete the NRR staffs commitment to share this information with internal and external stakeholders.
Attachment:
Requests for Additional Information Issued During NRR Staff Reviews of Recent Extended Power Uprates
September 29, 2004 MEMORANDUM TO: William Ruland, Director Project Directorate III Division of Licensing Project Management Office of Nuclear Reactor Regulation FROM: William A. Macon, Jr., Project Manager, Section 2 /RA/
Project Directorate IV Division of Licensing Project Management Office of Nuclear Reactor Regulation
SUBJECT:
REVIEW OF REQUESTS FOR ADDITIONAL INFORMATION FOR RECENT EXTENDED POWER UPRATES In SECY-02-0115 dated June 27, 2002, the NRR staff committed, in part, to perform an assessment of requests for additional information (RAIs) issued during the NRR staffs review of past extended power uprate (EPU) applications. The NRR staff further committed to use the results of this assessment in the development of the review standard for EPUs and share the results of the assessment with internal and external stakeholders. The NRR staff had previously completed the assessment of the RAIs and used the results in the development of draft Review Standard (RS)-001, "Review Standard for Extended Power Uprates," which was issued in December 2002. The attached listing of RAIs which were issued during the NRR staffs review of the EPU applications for Duane Arnold, Dresden Units 2 and 3, Quad Cities Units 1 and 2, Clinton, Arkansas Nuclear One Unit 2, and Brunswick Units 1 and 2, is being made available in ADAMS under Accession No. ML023290378 to complete the NRR staffs commitment to share this information with internal and external stakeholders.
Attachment:
Requests for Additional Information Issued During NRR Staff Reviews of Recent Extended Power Uprates DISTRIBUTION:
PUBLIC PDIII-1 Reading RidsNrrDlpmPdiv (HBerkow)
RidsNrrDlpmPdiv2 (RGramm)
RidsNrrDlpmPdiii1 (LRaghavan)
RidsNrrPMJStang RidsNrrPMWMacon Accession Nos:
Memo: ML023290363 Attachment (EPU RAIs): ML023290378 Package: ML023290379 OFFICE PDIV-2/PM PDIII-1/PM PDIV-2/LA PDIV-2/SC PDIII-1/SC NAME WMacon JStang EPeyton RGramm LRaghavan DATE 10/04/04 10/04/04 10/04/04 10/05/04 10/05/04 OFFICIAL RECORD COPY