Letter Sequence RAI |
---|
|
|
MONTHYEARML0313207692003-07-0101 July 2003 Documentation of a Request for Information Regarding the Licensed Thermal Power Level at Byron Station, Unit 1 Project stage: RAI ML0802801742003-07-0808 July 2003 Licensed Thermal Power, Byron Station, Unit 1 - Request for Additional Information Project stage: RAI ML0312701742003-07-0808 July 2003 Request for Additional Information, RAI Required in Order to Fully Resolve Question of Licensed Power Limit from February 5, 2003 Response to Nrc'S Letter of January 22, 2003 Project stage: RAI ML0402001912004-01-14014 January 2004 Evaluation of Davis Besse Modifications to the High Pressure Injection Pump and Associated Mock-Up Testing Project stage: Acceptance Review ML0401602102004-01-16016 January 2004 Task Interface Agreement (TIA 2003-05); NRC Policy Questions on Technical Specification Adequacy and Related Technical Specification Operability Project stage: Other ML0404902202004-02-0606 February 2004 Response to Task Interface Agreement (TIA) 2003-06 Project stage: Other ML0401503012004-02-0606 February 2004 Response to Task Interface Agreement 2003-06 Project stage: Other ML0402701812004-02-11011 February 2004 Memo, Evaluation of Davis-Besse Modifications to the High Pressure Injection Pump and Associated Mock-Up Testing (TIA No. 2003-04, TAC No. MC0584) Project stage: Acceptance Review ML0417002292004-06-30030 June 2004 May Monthly Report on the Status of Open TIAs Assigned to NRR Project stage: Other ML0822102852004-06-30030 June 2004 Memo to C. Pederson (Riii) from E. Hackett (Nrr), Subject: Request for Technical Assistance (TIA 2003-002) - Review of Licensee'S Response to Concern Regarding Potential for Byron Nuclear Power Station to Exceed Its Licensed Thermal Power L Project stage: Approval 2004-01-16
[Table View] |
Similar Documents at Byron |
---|
Category:Letter
MONTHYEARRS-24-095, Relief Request I4R-19 and I4R-26, Associated with the Fourth and Fifth Inservice Inspection Intervals2024-10-10010 October 2024 Relief Request I4R-19 and I4R-26, Associated with the Fourth and Fifth Inservice Inspection Intervals RS-24-093, Response to Request for Additional Information - Alternative Request to Utilize Code Case OMN-32, Alternative Requirements for Range and Accuracy of Pressure, Flow, and Differential Pressure Instruments Used in Pump Tests2024-10-10010 October 2024 Response to Request for Additional Information - Alternative Request to Utilize Code Case OMN-32, Alternative Requirements for Range and Accuracy of Pressure, Flow, and Differential Pressure Instruments Used in Pump Tests ML24281A1502024-10-0707 October 2024 Request for Information for NRC Commercial Grade Dedication Inspection Report 05000454/2025010 and 05000455/2025010 ML24275A2442024-10-0303 October 2024 Reassignment of the U.S. Nuclear Regulatory Commission Branch Chief, Division of Operating Reactor Licensing ML24263A1272024-09-23023 September 2024 – Request for Additional Information (EPID 2023-LLA-0136) - Non-Proprietary BYRON 2024-0046, Cycle 27 Core Operating Limits Report2024-09-19019 September 2024 Cycle 27 Core Operating Limits Report RS-24-088, Relief Requests Associated with the Fifth Inservice Inspection Interval2024-09-13013 September 2024 Relief Requests Associated with the Fifth Inservice Inspection Interval ML24250A1182024-09-0606 September 2024 Notification of an NRC Biennial Licensed Operator Requalification Program Inspection and Request for Information 05000454/LER-2024-001, Both Trains of Control Room Ventilation Temperature Control System Inoperable2024-09-0505 September 2024 Both Trains of Control Room Ventilation Temperature Control System Inoperable ML24227A0522024-08-29029 August 2024 Audit Plan for LAR to Remove ATWS Mtc Limit IR 05000454/20240052024-08-28028 August 2024 Updated Inspection Plan and Assessment Follow-Up Letter for Byron Station, Units 1 and 2 (Report 05000455/2024005 and 05000454/2024005) ML24222A6772024-08-0909 August 2024 Response to Request for Additional Information for Application to Revise Technical Specifications to Adopt TSTF-591-A, Revise Risk Informed Completion Time (RICT) Program Revision 0 and Revise 10 CFR 50.69 License Condition IR 05000454/20240112024-08-0808 August 2024 Phase 2 Post- Approval License Renewal Report 05000454/2024011 IR 05000454/20240022024-07-26026 July 2024 Integrated Inspection Report 05000454/2024002 and 05000455/2024002, and Exercise of Enforcement Discretion ML24179A3262024-07-23023 July 2024 LTR - Constellation - SG Welds and Nozzles (L-2023-LLR-0053, L-2023-LLR-0054, L-2023-LLR-0055, L-2023-LLR-0056) RS-24-064, Nuclear Radiological Emergency Plan Document Revisions2024-06-28028 June 2024 Nuclear Radiological Emergency Plan Document Revisions RS-24-066, Inservice Testing Interval Extension for Essential Service Water Valves Due to Required Use of Containment Chiller2024-06-25025 June 2024 Inservice Testing Interval Extension for Essential Service Water Valves Due to Required Use of Containment Chiller ML24170A7652024-06-19019 June 2024 Confirmation of Initial License Examination RS-24-061, Constellation Energy Generation, LLC, Response to NRC Regulatory Issue Summary 2024-01, Preparation and Scheduling of Operator Licensing Examinations2024-06-14014 June 2024 Constellation Energy Generation, LLC, Response to NRC Regulatory Issue Summary 2024-01, Preparation and Scheduling of Operator Licensing Examinations RS-24-044, License Amendment to Transition to Framatome Gaia Fuel and Exemptions to 10 CFR 50.46 and 10 CFR 50 Appendix K. Attachments 1 to 11 Enclosed2024-05-28028 May 2024 License Amendment to Transition to Framatome Gaia Fuel and Exemptions to 10 CFR 50.46 and 10 CFR 50 Appendix K. Attachments 1 to 11 Enclosed RS-24-043, Application to Remove Power Distribution Monitoring System (Pdms) Details from Technical Specifications2024-05-24024 May 2024 Application to Remove Power Distribution Monitoring System (Pdms) Details from Technical Specifications ML24079A0762024-05-23023 May 2024 Issuance of Amendments to Adopt TSTF 264 ML24142A3352024-05-21021 May 2024 Quad Cities—Information Request to Support the NRC Annual Baseline Emergency Action Level and Emergency Plan Changes RS-24-055, 2023 Corporate Regulatory Commitment Change Summary Report2024-05-17017 May 2024 2023 Corporate Regulatory Commitment Change Summary Report BYRON 2024-0031, Completion of License Renewal Activities Prior to Entering the Period of Extended Operation2024-05-16016 May 2024 Completion of License Renewal Activities Prior to Entering the Period of Extended Operation IR 05000454/20240012024-05-10010 May 2024 Integrated Inspection Report 05000454/2024001; 05000455/2024001 and 07200068/2024001 BYRON 2024-0028, Annual Radiological Environmental Operating Report (AREOR)2024-05-0909 May 2024 Annual Radiological Environmental Operating Report (AREOR) BYRON 2024-0022, 2023 Regulatory Commitment Change Summary Report2024-05-0202 May 2024 2023 Regulatory Commitment Change Summary Report RS-24-041, Alternative Request to Utilize Code Case OMN-32, Alternative Requirements for Range and Accuracy of Pressure, Flow, and Differential Pressure Instruments Used in Pump Tests2024-04-30030 April 2024 Alternative Request to Utilize Code Case OMN-32, Alternative Requirements for Range and Accuracy of Pressure, Flow, and Differential Pressure Instruments Used in Pump Tests ML24116A1192024-04-25025 April 2024 2023 Annual Radioactive Effluent Release Report (ARERR) RS-24-026, License Amendment to Braidwood Station, Units 1 and 2, and Byron Station, Units 1 and 2, Technical Specifications 5.6.5, Core Operating Limits Report (COLR)2024-04-25025 April 2024 License Amendment to Braidwood Station, Units 1 and 2, and Byron Station, Units 1 and 2, Technical Specifications 5.6.5, Core Operating Limits Report (COLR) ML24113A1272024-04-22022 April 2024 Audit Plan in Support of Review of LAR Revision of TS 3.7.15, 3.7.16, and 4.3.1 (EPID: L-2023-LLA-0136) (Non-Proprietary) ML24113A2892024-04-22022 April 2024 Notification of NRC Baseline Inspection and Request for Information BYRON 2024-0020, Annual Dose Report for 20232024-04-18018 April 2024 Annual Dose Report for 2023 ML24103A2042024-04-12012 April 2024 Constellation Energy Generation, LLC, Application to Revise Technical Specifications to Adopt TSTF-591-A, Revise Risk Informed Completion Time (RICT) Program Revision 0 and Revise 10 CFR 50.69 License Condition BYRON 2024-0021, Registration of Use of Cask to Store Spent Fuel2024-04-11011 April 2024 Registration of Use of Cask to Store Spent Fuel RS-24-034, Annual 10 CFR 50.46 Report of Emergency Core Cooling System Evaluation Model Changes and Errors2024-04-10010 April 2024 Annual 10 CFR 50.46 Report of Emergency Core Cooling System Evaluation Model Changes and Errors IR 05000454/20244012024-04-0303 April 2024 Cyber Security Inspection Report 05000454/2024401 and 05000455/2024401 (Public) RS-24-002, Constellation Energy Generation, LLC - Annual Property Insurance Status Report2024-04-0101 April 2024 Constellation Energy Generation, LLC - Annual Property Insurance Status Report BYRON 2024-0019, Registration of Use of Cask to Store Spent Fuel2024-03-28028 March 2024 Registration of Use of Cask to Store Spent Fuel RS-24-024, Response to Request for Additional Information Regarding Proposed Alternative for Examination of Pressurizer Circumferential and Longitudinal Shell-to-Head Welds and Nozzle-to-Vessel Welds2024-03-22022 March 2024 Response to Request for Additional Information Regarding Proposed Alternative for Examination of Pressurizer Circumferential and Longitudinal Shell-to-Head Welds and Nozzle-to-Vessel Welds IR 05000454/20230112024-03-20020 March 2024 Fire Protection Team Inspection Report 05000454/2023011 and 05000455/2023011 IR 05000454/20240102024-03-15015 March 2024 Comprehensive Engineering Team Inspection Report 05000454/2024010 and 05000455/2024010 IR 05000454/20230062024-02-28028 February 2024 Annual Assessment Letter for Byron Station, Units 1 and 2 (Report 05000455/2023006 and 05000454/2023006) IR 05000454/20230042024-02-0202 February 2024 Integrated Inspection Report 05000454/2023004 and 05000455/2023004 ML24022A2722024-01-23023 January 2024 Request for Information for an NRC Post-Approval Site Inspection for License Renewal Inspection Report 05000454/2024011 ML24018A0362024-01-17017 January 2024 Paragon Energy Solutions, Defect with Detroit Diesel/Mtu Fuel Injectors P/N R5229660 Cat Id 0001390618 ML23320A1762023-12-13013 December 2023 Exemption from Select Requirements of 10 CFR Part 73 (EPID L-2023-LLE-0027 (Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting)) ML23277A0032023-12-11011 December 2023 Issuance of Amendments Regarding Adoption of TSTF-370 ML23318A5102023-12-0101 December 2023 Relief from the Requirements of the ASME Code 2024-09-06
[Table view] Category:Request for Additional Information (RAI)
MONTHYEARML24263A1272024-09-23023 September 2024 – Request for Additional Information (EPID 2023-LLA-0136) - Non-Proprietary ML24250A1182024-09-0606 September 2024 Notification of an NRC Biennial Licensed Operator Requalification Program Inspection and Request for Information ML24197A0162024-07-12012 July 2024 NRR E-mail Capture - Final RAI - Constellation Energy Generation, LLC - Fleet Request - License Amendment Request to Adopt TSTF-591 ML24142A3352024-05-21021 May 2024 Quad Cities—Information Request to Support the NRC Annual Baseline Emergency Action Level and Emergency Plan Changes ML24113A2892024-04-22022 April 2024 Notification of NRC Baseline Inspection and Request for Information ML24053A3382024-02-22022 February 2024 NRR E-mail Capture - Final RAI - Constellation Energy Generation, LLC - Fleet Request - Proposed Alternative for Examination of Pressurizer Circumferential and Longitudinal Shell-to-Head Welds and Nozzle-to-Vessel Welds (L-2023-LLR-0062) ML23297A2352023-10-26026 October 2023 Information Request for the Cyber Security Baseline Inspection, Notification to Perform Inspection ML23209A7242023-07-31031 July 2023 Request for Information on the NRC Quadrennial Comprehensive Engineering Team Inspection: Inspection Report 05000454/2024010 and 05000455/2024010 ML23198A0372023-07-17017 July 2023 Information Request to Support Upcoming Problem Identification and Resolution (PIR) Inspection at Byron Nuclear Plant ML23172A1172023-06-22022 June 2023 Notification of NRC Fire Protection Team Inspection Request for Information ML23110A3202023-04-21021 April 2023 Information Request to Support the NRC Annual Baseline Emergency Action Level and Emergency Plan Changes Inspection ML23069A0342023-03-0606 March 2023 Unit 1 Lr Commitment 10 RAI Set 1 - (Non-Proprietary) ML23069A0332023-03-0606 March 2023 Email to K. Lueshen Byron and Braidwood Commitment 10 - Request for Additional Information Set 1 ML23115A2412023-01-20020 January 2023 NRR E-mail Capture - Preliminary RAIs Related to L-2022-LLA-0131 - Byron, Unit 2, Reinsertion of an Accident Tolerant Fuel Lead Test Assembly ML22237A0272022-08-25025 August 2022 Notification of an NRC Biennial Licensed Operator Requalification Program Inspection and Request for Information ML22271A0772022-05-0606 May 2022 NRR E-mail Capture - Final RAIs 9.1.2021 Constellation Relief Request ML22129A0132022-05-0606 May 2022 NRR E-mail Capture - Draft RAIs for Requests for Alternatives I4R-17, I4R-23, ISI-05-018, I6R-10 ML22116A1272022-04-26026 April 2022 Unit 2 RFI for an NRC Triennial Heat Exchanger/Sink Performance Inspection and RFI IR 05000454/2022002 05000455/2022002 ML22091A0852022-04-0101 April 2022 NRR E-mail Capture - Braidwood and Byron - Final RAI Regarding Proposed Alternative for Various Pressurizer Welds (EPID L-2021-LLR-0035 and 0036) ML22041B5362022-02-10010 February 2022 NRR E-mail Capture - Constellation Energy Generation, LLC - Request for Additional Information Regarding Fleet License Amendment Request to Adopt TSTF-541 ML21273A3312021-10-0404 October 2021 Information Request to Support Upcoming Biennial Problem Identification and Resolution (Pi&R) Inspection at Byron Station ML21256A1902021-09-10010 September 2021 NRR E-mail Capture - Exelon Generation Company, LLC - Request for Additional Information Regarding License Transfer Application ML21203A3112021-07-21021 July 2021 NRR E-mail Capture - Final Byron Permanently Defueled Technical Specifications (PDTS) - Second Round RAI ML21189A1602021-07-0808 July 2021 NRR E-mail Capture - Request for Additional Information - Braidwood, Byron, and Ginna - Amendment to Address the Issues in Westinghouse NSALs ML21189A1612021-07-0808 July 2021 NRR E-mail Capture - Second Round Request for Additional Information - Byron Permanently Defueled Technical Specification Amendment ML21144A2132021-05-24024 May 2021 NRR E-mail Capture - Exelon Generation Company, LLC - Request for Additional Information Regarding License Transfer Application ML21117A0342021-05-0505 May 2021 Request for Additional Information Regarding Proposed Alternative to Use ASME Code Case N-893 ML21062A0652021-03-0101 March 2021 NRR E-mail Capture - Exelon Generation Company, LLC - Request for Additional Information Regarding Proposed Fleet Alternative to Documentation Requirements for Pressure Retaining Bolting ML21049A2572021-02-18018 February 2021 Request for Additional Information Byron/Dresden Proposed Changes to Site Emergency Plans to Support Post-Shutdown and Permanently Defueled Conditions (EPID-2020-LLA-0240 & EPID-2020-LLA-0237) ML21036A1102021-02-0404 February 2021 NRR E-mail Capture - Draft RAIs for Byron Station, Unit Nos. 1 and 2, Proposed Defueled Technical Specifications and Revised License Conditions for Permanently Defueled Condition ML21029A3302021-01-29029 January 2021 NRR E-mail Capture - Exelon Generation Company, LLC - Request for Additional Information Regarding Fleet Alternative Request to Use ASME Code Case N-885 ML21004A1452020-12-30030 December 2020 NRR E-mail Capture - Request for Additional Information Regarding Relief Requests Braidwood I4R-11 and Byron I4R-18 ML20329A4852020-11-24024 November 2020 Notification of NRC Fire Protection Team Inspection Request for Information ML20294A5492020-10-21021 October 2020 Notification of an NRC Biennial Licensed Operator Requalification Program Inspection and Request for Information ML20289A1142020-10-0909 October 2020 NRR E-mail Capture - Preliminary RAIs for LAR Regarding Non-conservative TS EDG Frequency Tolerance ML20077M2212020-03-20020 March 2020 Ti 2515/194 Inspection Documentation Request ML20008D3992020-01-0808 January 2020 Notification of NRC Baseline Inspection and Request for Information; Inspection Report 05000454/2020001 ML19275H1362019-10-0202 October 2019 NRR E-mail Capture - Exelon Generation Company, LLC - Request for Additional Information Regarding Request to Use ASME Code Case N-879 ML19252C1542019-08-22022 August 2019 NRR E-mail Capture - Issuance of the Remainder of Preliminary RAIs for Braidwood/Byron TSTF-505 Application ML19232A2242019-08-0707 August 2019 NRR E-mail Capture - Partial Issuance of Final RAIs for Braidwood/Byron TSTF-505 Application ML19207A0672019-07-26026 July 2019 NRR E-mail Capture - Partial Issuance of Preliminary RAIs for Braidwood/Byron TSTF-505 Application ML19179A0612019-07-19019 July 2019 Three Mile Point 1 - Supplemental Information Needed to Proposed Alternative to Use ASME Code Case N-879 ML19032A1062019-02-0101 February 2019 NRR E-mail Capture - Preliminary RAIs for Byron On--time Extension of Completion Time 3.8.1, A.2 ML19011A3452019-01-11011 January 2019 NRR E-mail Capture - Preliminary RAIs Regarding Byron Request to Use ATF LTAs ML18149A2842018-05-24024 May 2018 NRR E-mail Capture - B/B 50.69 RAI - Potential Typo ML18129A1082018-05-0909 May 2018 NRR E-mail Capture - Preliminary RAIs for Braidwood and Byron Stations 50.69 Amendment ML18067A1482018-03-0808 March 2018 Enclosurequest for Additional Information (Letter to P. R. Simpson Request for Additional Information Regarding Exelon Generating Company, Llc'S Decommissioning Funding Plan Update for Independent Spent Fuel Storage Installation) ML18022A0422018-01-19019 January 2018 18 Byron Station, Units 1 and 2 - Information Request to Support Upcoming Temporary Instruction 2515/194 Inspection (DRS-I.Hafeez) ML17179A2852017-06-28028 June 2017 NRR E-mail Capture - Request for Additional Information Regarding Braidwood and Byron Amendments to Remove Obsolete License and Technical Specification Items ML17159A6292017-06-0707 June 2017 Information Request to Support the NRC Annual Baseline Emergency Action Level and Emergency Plan Changes Inspection (Mxg) 2024-09-06
[Table view] |
Text
July 8, 2003 Mr. John L. Skolds, President Exelon Nuclear Exelon Generation Company, LLC 4300 Winfield Road Warrenville, IL 60555
SUBJECT:
LICENSED THERMAL POWER, BYRON STATION, UNIT 1- REQUEST FOR ADDITIONAL INFORMATION (TAC NO. MB7378)
Dear Mr. Skolds:
The Nuclear Regulatory Commission (NRC) staff is reviewing the February 5, 2003, response of Exelon Company, LLC (Exelon), to the NRCs letter of January 22, 2003. During the review, the staff has determined that it requires additional information in order to fully resolve the question of the licensed power limit for Byron Station, Unit 1. The request for additional information (RAI) is attached.
Based on a discussion of the questions with Exelon staff members on June 20, 2003, we request that the response to the attached RAI be received by August 15, 2003.
Sincerely,
/RA/
George F. Dick, Jr., Project Manager, Section 2 Project Directorate III Division of Licensing Project Management Office of Nuclear Reactor Regulation Docket No. STN 50-454
Enclosure:
As stated cc w/encl: See next page
July 8, 2003 Mr. John L. Skolds, President Exelon Nuclear Exelon Generation Company, LLC 4300 Winfield Road Warrenville, IL 60555
SUBJECT:
LICENSED THERMAL POWER, BYRON STATION, UNIT 1- REQUEST FOR ADDITIONAL INFORMATION (TAC NO. MB7378)
Dear Mr. Skolds:
The Nuclear Regulatory Commission (NRC) staff is reviewing the February 5, 2003, response of Exelon Company, LLC (Exelon), to the NRCs letter of January 22, 2003. During the review, the staff has determined that it requires additional information in order to fully resolve the question of the licensed power limit for Byron Station, Unit 1. The request for additional information (RAI) is attached.
Based on a discussion of the questions with Exelon staff members on June 20, 2003, we request that the response to the attached RAI be received by August 15, 2003.
Sincerely,
/RA/
George F. Dick, Jr., Project Manager, Section 2 Project Directorate III Division of Licensing Project Management Office of Nuclear Reactor Regulation Docket No. STN 50-454
Enclosure:
As stated cc w/encl: See next page Distribution:
PUBLIC PDIII/2 r/f L. Marsh A. Mendiola P. Coates M. Chawla G. Dick OGC, O15B18 ACRS, T2E26 G. Grant, RIII A. Stone, RIII P. Loughheed, RIII D. Hills, RIII W. Lyon P. Rebstock J. Tatum G. Cranston ADAMS Accession Number: ML031270174 *see previous concurrence OFFICE PM:PD3-2 LA:PD3-2 SC:SPLB SC:EEIB SC:SRX SC:PD3-2 B
NAME GDick PCoates DSolorio* AMarinos JUhle LRaghavan for AMendiola DATE 07/01/03 07/01/03 07/04/03 07/01/03 07/02/03 07/08/03 OFFICIAL RECORD COPY
Byron Station Units 1 and 2 cc:
Regional Administrator, Region III 500 S. Second Street U.S. Nuclear Regulatory Commission Springfield, IL 62701 801 Warrenville Road Lisle, IL 60532-4351 Byron Station Manager Exelon Generation Company, LLC Illinois Department of Nuclear Safety 4450 N. German Church Road Office of Nuclear Facility Safety Byron, IL 61010-9794 1035 Outer Park Drive Springfield, IL 62704 Site Vice President - Byron Exelon Generation Company, LLC Document Control Desk-Licensing 4450 N. German Church Road Exelon Generation Company, LLC Byron, IL 61010-9794 4300 Winfield Road Warrenville, IL 60555 Senior Vice President - Nuclear Services Exelon Generation Company, LLC Ms. C. Sue Hauser, Project Manager 4300 Winfield Road Westinghouse Electric Corporation Warrenville, IL 60555 Energy Systems Business Unit Post Office Box 355 Vice President Pittsburgh, PA 15230 Mid-West Operations Support Exelon Generation Company, LLC Joseph Gallo 4300 Winfield Road Gallo & Ross Warrenville, IL 60555 1025 Connecticut Ave., NW, Suite 1014 Washington, DC 20036 Senior Vice President Mid-West Regional Operating Group Howard A. Learner Exelon Generation Company, LLC Environmental Law and Policy 4300 Winfield Road Center of the Midwest Warrenville, IL 60555 35 East Wacker Drive Suite 1300 Chairman Chicago, IL 60601-2110 Will County Board of Supervisors Will County Board Courthouse U.S. Nuclear Regulatory Commission Joliet, Illinois 60434 Byron Resident Inspectors Office 4448 North German Church Road Byron, IL 61010-9750 Ms. Lorraine Creek RR 1, Box 182 Manteno, IL 60950 Chairman, Ogle County Board Post Office Box 357 Oregon, IL 61061 Mrs. Phillip B. Johnson 1907 Stratford Lane Rockford, IL 61107 Attorney General
Byron Station Units 1 and 2 Illinois Emergency Management Agency Division of Disaster Assistance &
Preparedness 110 East Adams Street Springfield, Illinois 62701-1109 Director Licensing Mid-West Regional Operating Group Exelon Generation Company, LLC 4300 Winfield Road Warrenville, IL 60555 Regulatory Assurance Manager - Byron Exelon Generation Company, LLC 4450 N. German Church Road Byron, IL 61010-9794 Senior Counsel, Nuclear Mid-West Regional Operating Group Exelon Generation Company, LLC 4300 Winfield Road Warrenville, IL 60555 Vice President Licensing and Regulatory Affairs Exelon Generation Company, LLC 4300 Winfield Road Warrenville, IL 60555 Manager Licensing - Braidwood and Byron Exelon Generation Company, LLC 4300 Winfield Road Warrenville, IL 60555
REQUEST FOR ADDITIONAL INFORMATION RELATED TO THE BYRON UNIT 1, THERMAL POWER LIMIT EXELON GENERATION COMPANY, LLC BYRON STATION, UNIT 1 DOCKET NO. STN 50-454 The NRC staff is reviewing the licensees response of February 5, 2003, to the NRCs letter of January 22, 2003. During the review, the staff has determined that it requires additional information in order to fully resolve the question of the licensed power limit for Byron Station, Unit 1. The staffs questions or information needs are as follows:
- 1. Questions specific to the licensees February 5, 2003, submittal 1.1 On Page 2 and on Page 5, the licensee identified participation by other than on-site personnel in such activities as detailed review of the installation and re-evaluation of the installation uncertainty calculations of the ultrasonic flow meters (UFMs). Please provide the basis for concluding, that the equipment was performing within specification.
1.2 On Page 9, the licensee identified a MWe evaluation and toward the end of the letter, discussed other parameters associated with the plant secondary side. Please provide a description of observations and conclusions obtained during those or any other evaluations, including any items that may be consistent with a thermal power level being greater than 100 percent. Include any observations relative to the turbine/alternator performance, including but not limited to the overall conversion efficiency of the turbine generator with the assumption that the plant is operating at 100 percent thermal power.
- 2. Questions related to the feedwater flow meters 2.1 Included in topical reports Westinghouse has submitted affirming the accuracy of the AMAG CrossFlow ultrasonic flowmeter at a number of nuclear power plants, are comparisons of feedwater flow readings from the UFM with simultaneous readings from the installed venturi-based FW flow meters. Westinghouse notes that the FW venturis tend to defoul upon return to power following an outage, and that the UFM accuracy can, therefore, be confirmed immediately following start-up.
Please provide all available data showing simultaneous readings or correction factor computations for the venturis and the UFMs upon return to power or at other times when the venturis were known to be clean. Please provide the data, showing the degree of correlation between the two types of flowmeters. If such data do not exist, please provide the staff with information regarding how the data will be obtained. If simultaneous measurements are proposed, the venturi delta-P instruments should be calibrated before taking data, or supplemented with laboratory-grade devices. Please include uncertainty evaluations for the data measurement and acquisition equipment for both the existing data and new data.
2.2 Please provide a complete description of the methodology used to calculate the correction factors. Include the behavior as a function of power.
2.3 Fluctuations in the CF for Byron appear to be greater than at other plants. It was recommended by Westinghouse to run continuous UFM monitoring for a period of six months to possibly identify the root cause of the fluctuations. Please describe how the CF fluctuations at Byron compared with the CF fluctuations at Braidwood, and how indicated power is affected by the level of CF fluctuation. Describe actions that have been taken in response to the Westinghouse recommendation and what was found to be the root cause of this condition. Discuss the status of corrective actions to resolve this condition, and how the CF fluctuations currently compare between the Byron and Braidwood units.
- 3. Question related to the quality of the calorimetric calculations Provide information for Byron and Braidwood Stations regarding the methodology of the plants calorimetric calculations, as well as calibration and uncertainty information for the instrumentation that is used as input to the calorimetric calculation. Include any changes in this information as a result of implementing the power uprate for the units and implementing the UFM for feedwater flow measurement.
- 4. Questions related to other secondary side equipment 4.1 Describe and explain any changes in the turbine efficiencies at Byron prior to and following UFM implementation. Provide the same type of information for Braidwood.
Also describe and explain any differences in turbine efficiencies between the Byron and Braidwood units prior to and following UFM implementation.
4.2 Describe and explain any differences in the turbine governor and throttle valves between the Byron and Braidwood units. Were these valves originally purchased as identical valves for Byron and Braidwood?
4.3 Were any modifications made to the turbine governor or throttle valves (or to the turbines) prior to, in conjunction with, or subsequent to power uprate?