NRR E-mail Capture - SONGS - Draft RAI Permanently Defueled Technical Specifications License Amendment Request
ML15042A394
Person / Time
Site: San Onofre  Southern California Edison icon.png
Issue date: 01/23/2015
From: Thomas Wengert
Plant Licensing Branch IV
To: Sterdis A
Southern California Edison Co
References
TAC MF3774, TAC MF3775
Download: ML15042A394 (4)


Text

NRR-PMDAPEm Resource From: Wengert, Thomas Sent: Friday, January 23, 2015 10:59 AM To: andrea.sterdis@sce.com Cc: MARK MORGAN; John.Brabec@sce.com; Broaddus, Doug; Grover, Ravinder

Subject:

SONGS - Draft RAI RE: Permanently Defueled Technical Specifications License Amendment Request (TAC Nos. MF3774 and MF3775)

Attachments: SONGS - Draft STSB RAI Regarding Defueled TS LAR.pdf Ms. Sterdis, By letter dated March 21, 2014 (Agencywide Documents Access and Management System (ADAMS)

Accession No. ML14085A141), as supplemented by letter dated October 1, 2014 (ADAMS Accession No. ML14280A264), Southern California Edison (SCE, the licensee) requested license amendments to revise the Operating License and associated Technical Specifications to reflect the permanent cessation of operation for San Onofre Nuclear Generating Station (SONGS), Units 2 and 3.

Based on the Nuclear Regulatory Commission (NRC) staffs review of SCEs license amendment request submittals, a response to the attached draft request for additional information (RAI) is required to facilitate completion of the staffs technical review. I am sending you this preliminary copy to give you an opportunity to ask clarifying questions if the request is not clear. This RAI will be made publicly available following your review.

Please let me know if SCE would like to have a conference call with the NRC staff to clarify this request. Also, lets discuss the proposed timing for SCEs response.

Tom Wengert Senior Project Manager U.S. Nuclear Regulatory Commission NRR/DORL/LPL4-2 (301) 415-4037 1

Hearing Identifier: NRR_PMDA Email Number: 1870 Mail Envelope Properties (Thomas.Wengert@nrc.gov20150123105900)

Subject:

SONGS - Draft RAI RE: Permanently Defueled Technical Specifications License Amendment Request (TAC Nos. MF3774 and MF3775)

Sent Date: 1/23/2015 10:59:12 AM Received Date: 1/23/2015 10:59:00 AM From: Wengert, Thomas Created By: Thomas.Wengert@nrc.gov Recipients:

"MARK MORGAN" <Mark.Morgan@sce.com>

Tracking Status: None "John.Brabec@sce.com" <John.Brabec@sce.com>

Tracking Status: None "Broaddus, Doug" <Doug.Broaddus@nrc.gov>

Tracking Status: None "Grover, Ravinder" <Ravinder.Grover@nrc.gov>

Tracking Status: None "andrea.sterdis@sce.com" <andrea.sterdis@sce.com>

Tracking Status: None Post Office:

Files Size Date & Time MESSAGE 1242 1/23/2015 10:59:00 AM SONGS - Draft STSB RAI Regarding Defueled TS LAR.pdf 128145 Options Priority: Standard Return Notification: No Reply Requested: No Sensitivity: Normal Expiration Date:

Recipients Received:

DRAFT REQUEST FOR ADDITIONAL INFORMATION DEFUELED TECHNICAL SPECIFICATION LICENSE AMENDMENT REQUEST SAN ONOFRE NUCLEAR GENERATING STATION, UNITS 2 AND 3 SOUTHERN CALIFORNIA EDISON DOCKET NOS. 50-361 AND 50-362 TAC NOS. MF3774 AND MF3775 By letter dated March 21, 2014 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML14085A141), as supplemented by letter dated October 1, 2014 (ADAMS Accession No. ML14280A264), Southern California Edison requested an amendment to the facility operating licenses. The requested amendment would revise the operating licenses and associated Technical Specifications (TSs) to reflect the permanent cessation of reactor operation and the permanently defueled condition of the reactor vessels at San Onofre Nuclear Generating Station (SONGS), Units 2 and 3. The proposed amendment would eliminate most of the previous operating TSs because these TSs are only applicable in operating modes or conditions where fuel is emplaced within the reactor vessel. The proposed license amendment also requested changes to TS definitions and various organizational and program specifications. The following additional information is necessary to complete the Nuclear Regulatory Commission (NRC) staffs technical review:

RAI-STSB-01:

The proposed change in the BACKGROUND section of TS 1.3, Completion Times, replaces the wording operation of the unit, with storage of irradiated fuel (emphasis added). The APPLICABILITY for the renumbered Limiting Condition for Operation (LCO) 3.1.3, Spent Fuel Assembly Storage, states, Whenever any fuel assembly is stored in the fuel storage pool (emphasis added).

Please resolve this apparent discrepancy in wording and ensure that the Permanently Defueled Technical Specifications (PDTS) are consistent with your proposed resolution to the RAI.

RAI-STSB-02:

In renumbered TS 3.1.3, Spent Fuel Assembly Storage, proposed renumbered Surveillance Requirement (SR) 3.1.3.1 states the following:

Verify by administrative means the initial enrichment, burnup, and cooling time of the fuel assembly in accordance with LCO 3.1.3 or Design Features 4.3.1.1, or LCS 4.0.100.

Rev 2, dated 09/27/07.

For clarity, the NRC staff requests the licensee to define the abbreviation for Licensee Controlled Specification (LCS) in this section, since it is used for the first time in this LCO of the PDTS.

RAI-STSB-03:

In renumbered TS 3.1.3, Spent Fuel Assembly Storage, the Frequency for the renumbered SR 3.1.3.1 states the following:

Prior to moving a fuel assembly to any spent fuel pool storage location.

With the docketing of the certification for permanent removal of fuel from the reactor vessel to the spent fuel storage location, there should not be any movement of a fuel assembly into the spent fuel pool. Please explain how the specified Frequency applies to SR 3.1.3.1.

Regulatory Basis 10 CFR 50.90, Application for amendment of license, construction permit, or early site permit states, in part:

Whenever a holder of a license, including a construction permit and operating license under this part, and an early site permit, combined license, and manufacturing license under part 52 of this chapter, desires to amend the license or permit, application for an amendment must be filed with the Commission, as specified in §§ 50.4 or 52.3 of this chapter, as applicable, fully describing the changes desired, and following as far as applicable, the form prescribed for original applications.