LER 97-012-00:on 971028,loss of Power to Latching Mechanism on Several Doors Occurred.Caused by Tripping of Breaker in Security Distribution Panel in Central Alarm Station (CAS) Panel.Breakers in Affected CAS Panel ResetML18153A197 |
Person / Time |
---|
Site: |
Surry |
---|
Issue date: |
11/26/1997 |
---|
From: |
Christian D VIRGINIA POWER (VIRGINIA ELECTRIC & POWER CO.) |
---|
To: |
|
---|
Shared Package |
---|
ML18153A196 |
List: |
---|
References |
---|
LER-97-012, LER-97-12, NUDOCS 9712120375 |
Download: ML18153A197 (5) |
|
Similar Documents at Surry |
---|
Category:LICENSEE EVENT REPORT (SEE ALSO AO
MONTHYEARML18152B4411999-08-27027 August 1999 LER 99-005-00:on 990731,effluent Radiation Monitors Were Declared Inoperable.Caused by Degraded Heat Trace Circuits for Monitors Sample Suction Line.Degraded Heat Trace Circuit Was Replaced & Addl Heat Trace Is Being Installed ML18152B4421999-08-27027 August 1999 LER 99-006-00:on 990802,determined That Plant Was Outside of App R Design Basis Due to Fire Barrier Deficiencies. Caused by Original Plant Design Deficiencies.Fire Watches Were Established & Mods Have Been Completed.With 990827 Ltr ML18152B3771999-08-13013 August 1999 LER 99-004-00:on 990714,TS Violation Due to non-safety Related Fans Effect on CR Boundary Was Noted.Cause of Event Has Not Yet Been Determined.Cable Spreading Room Doors Were Operned to Reduce Pressure in Rooms ML18152B4181999-05-18018 May 1999 LER 99-002-00:on 990425,MSSVs Tested Out of Tolerance for as Found Setpoint.Caused by Minor Setpoint Drift.No Immediate Action Required.Deviation Rept Submitted for Each Valve.With 990518 Ltr ML18152B4111999-04-28028 April 1999 LER 99-003-00:on 990331,potential Loss of Charging Pumps Was Noted.Caused by Main CR Fire.Station Deviation Was Issued on 990331.With 990428 Ltr ML18153A2741999-03-29029 March 1999 LER 99-002-00:on 990301,prematurely Released Fire Watches Resulted in Violation of TS 3.21.B.7.Caused by Inadequate Procedure.Procedure for Opening & Sealing Fire Stops Was Revised on 990212 ML18153A2681999-03-19019 March 1999 LER 98-013-01:on 981122,turbine/reactor Tripped on High Due to Short Circuit in Summator for MSL C Loop Channel III Flow Transmitter.Replaced 1-MS-FT1494 Summator & Module Repair Procedure Revised.With 9903190 Ltr ML18152B7261999-01-21021 January 1999 LER 99-001-00:on 981222,auxiliary Feedwater Pipe Support Missed Surveillance.Caused by Personnel Error.Station Deviation Rept Was Submitted.Two Supports in Question Received Required Code Insp & Were Found Acceptable ML18152B5811998-12-16016 December 1998 LER 98-013-00:on 981122,turbine/reactor Trip on High SG Level Occurred.Caused by Instrument Failure.Control Room Operators Placed Unit in Safe,Shutdown Condition ML18152B5781998-12-16016 December 1998 LER 98-014-00:on 981126,manual Reactor Trip in Response to Main Feedwater Regulating Valve Failure Occurred.Caused by Dislocation of Retaining Clip in Positioner.Control Room Operators Placed Unit in Safe,Shutdown Condition ML18152B7121998-12-0404 December 1998 LER 98-S01-00:on 981105,noted Failure to Deactivate Station Access Badge.Caused by Human Error.Licensee Will Now Deactivate Station Badges Before Clearance Is Revoked & Process for Badge Deactivations Have Been Strengthened ML18152B7041998-12-0101 December 1998 LER 98-012-00:on 981102,noted That EDGs Were Concurrently Inoperable.Caused by Required Testing Per TS 3.16.B.1.a.2. Redundant EDG Was Returned to Svc within Two Hour Period, Following Satisfactory Testing.With 981201 Ltr ML18152B6161998-11-0606 November 1998 LER 98-011-00:on 981008,diesel Driven Fire Pump Failed to Start During Performance of Monthly Operability Test.Caused by Faulty Overspeed Trip Device Failure.Diesel Driven Fire Pump Declared Inoperable ML18152B6081998-10-23023 October 1998 LER 98-010-01:on 980715,intake Canal Level Probes Were Inoperable Due to Marine Growth.Caused by Design of Canal Level Instrumentation.Canal Level Probes Will Continue to Be Monitored More Closely ML18152B7811998-07-31031 July 1998 LER 98-010-00:on 980715,low Intake Canal Level Instrument Channel I Was Declared Inoperable to Allow Testing of Intake Canal Level Probe 1-CW-LE-102.Subject Probe Was Cleaned by Diver,Tested & Channel I Was Returned to Operable Status ML18153A2581998-06-0303 June 1998 LER 98-009-00:on 980509,nonisolable Leak of Reactor Coolant Pump Seal Injection Line Weld,Was Discovered.Caused by Lack of Fusion or Thermal Fatigue Coupled W/Vibration Stress Due to Loose Rod Hanger.Rcp Seal Injection Line Removed ML18152B8241998-05-22022 May 1998 LER 98-008-00:on 980228,auxiliary Ventilation Fans Were Noted in Condition Outside of Design Basis.Caused by Failure to Recognize Potential Impact of Certain Design Basis Accident Scenarios.No Corrective Actions Needed ML18152B7951998-04-29029 April 1998 LER 98-007-00:on 980330,radiation Monitors Were Declared Inoperable.Caused by Change in Operating Temperature Range. Preplanned Alternate Method of Monitoring Was Initiated IAW TS Table 3.7-6 ML18153A2521998-04-22022 April 1998 LER 98-005-01:on 980212,fire Watch Insp Exceeded One Hour. Caused by Lack of Attention to Detail by Individual Involved.Individual Involved Was Coached on Requirement to Perform Fire Watch Patrols within Required Time Frame ML18153A2511998-04-22022 April 1998 LER 98-006-00:on 980324,unisolable Through Wall Leak of RCP Thermowell Was Noted.Cause of Leak Is Unknown.Rtd Will Be Replaced ML18153A2391998-03-13013 March 1998 LER 98-005-00:on 980212,fire Watch Insp Frequency Exceeded One H Occurred.Category 2 Root Cause Evaluation Being Conducted to Determine Cause of Event.Station Deviation Issued ML18153A2341998-03-0909 March 1998 LER 98-003-00:on 980226,no Procedural Guidance for Maintaining EDG Minimum Fuel Supply During Loop,Was Identified.Caused by Absence of Procedural Instructions. Deviation Rept Submitted to Document Deviating Condition ML18153A2301998-03-0606 March 1998 LER 98-004-00:on 980206,fire Watch Was Released Prematurely Resulting in Violation of Ts.Caused by Inadequate Planning of Repair Activity.Work Orders Will Include Ref to Applicable Procedures Developed to Assist in Repairs ML18153A2251998-03-0404 March 1998 LER 98-002-00:on 980202,automatic Turbine Trip Resulted in Automatic Reactor Trip.Caused Degraded Generator Voltage Regulator sub-component Failure.Placed Plant in Safe Hot SD & Replaced Intermittent Relay & Relay Socket ML18153A2201998-02-0606 February 1998 LER 98-001-00:on 980108,deficient Test Due to Faulty Test Equipment Resulted in TS Violation.Caused by Faulty Vibration Analyzer Cable or Loose Connection.Station Deviation Rept Was submitted.W/980206 Ltr ML18153A2071998-01-13013 January 1998 LER 97-012-01:on 971028,loss of Power to Latching Mechanism on Several Doors Occurred.Caused by Tripping of Two Breakers in Security Distribution Panel.Reset Affected Breakers Which Restored Power to Security Systems & Affected Doors ML18153A2101998-01-13013 January 1998 LER 97-009-01:on 971014,declared Intake Canal Level Probes Inoperable Due to Marine Growth.Caused by Inadequate Maint of Intake Canal Level Probes.Subject Probes Were Cleaned, Tested Satisfactorily & Returned to Operable Status ML18153A1911997-11-26026 November 1997 LER 97-011-00:on 971030,determined That Periodic Test Procedures for Testing Reactor Trip Bypass Breakers Did Not Test Manual Undervoltage Trip.Caused by mis-interpretation of Term in-service. Procedures Revised ML18153A1971997-11-26026 November 1997 LER 97-012-00:on 971028,loss of Power to Latching Mechanism on Several Doors Occurred.Caused by Tripping of Breaker in Security Distribution Panel in Central Alarm Station (CAS) Panel.Breakers in Affected CAS Panel Reset ML18153A1921997-11-25025 November 1997 LER 97-010-00:on 971028,discovered Missed Fire Protection Surveillance Pt.Caused by Personnel Error.Satisfactorily Completed PT Procedure 0-OPT-FP-009 & Diesel Driven Fire Pump 1-FP-P-2 Declared operable.W/971125 Ltr ML18153A1831997-11-12012 November 1997 LER 97-009-00:on 971014,declared Intake Canal Level Probes Inoperable Due to Marine Growth.Cause Indeterminate.Divers Inspected,Cleaned & Returned Probes to Operable Status & Initiated Interdepartmental Team to Investigate Cause ML18153A1791997-11-0707 November 1997 LER 97-008-00:on 971011,invalid Actuation of ESF Occurred. Caused by Personnel Errors.Main CR Bottled Air Sys Isolated & Containment Hydrogen Analyzer Heat Tracing Actuation Signal Reset ML18153A1721997-10-30030 October 1997 LER 97-007-00:on 970930,determined That Plant Was Outside App R Design Basis Due to Vital Bus Isolation Issue.Caused by Personnel Error.Installed Circuit Protective Device During Oct 1997 Refueling Outage ML18153A1421997-06-10010 June 1997 LER 97-001-01:on 970123,shutdown Occurred Due to Drain Line Weld Leak.Inspected & Tested Turbine Trip Actuation circuitry.W/970610 Ltr ML18153A1391997-05-28028 May 1997 LER 97-005-00:on 970502,Unit 1 Power Range Nuclear Instrumentation Was Inoperable Due to Personnel Error.Sro & STA That Were Involved in Event Were Counseled ML18153A1291997-04-18018 April 1997 LER 97-006-00:on 970320,loss of Refueling Integrity Due to Inadequate Containment Closure Process & Verification.Fuel Movement Stopped IAW Action Statement Requirements of TS 3.10.B.W/970418 Ltr ML18153A1281997-04-15015 April 1997 LER 97-004-00:on 970317,main Steam Safety Valve Was Outside as Found Setpoint Tolerance.Specific Cause Unknown,However, Minor Setpoint Drift Can Be Expected.No Immediate Corrective Actions performed.W/970415 Ltr ML18153A1241997-04-0808 April 1997 LER 97-002-01:on 970116,one Train of Auxiliary Ventilation Sys Was Inoperable Outside of Ts.Caused by Personnel Error. Submitted Deviation Rept Re Reverse Rotation of Fan & Work Request to Adjust linkage.W/970408 Ltr ML18153A1191997-03-19019 March 1997 LER 97-001-00:on 970218,manual Reactor Trip & ESF Actuation Occurred Due to Loss of EHC Control Power.Caused by Momentary Short.Relay Card Was replaced.W/970319 Ltr ML18153A1201997-03-19019 March 1997 LER 97-003-00:on 970219,loss of Pressurizer Heaters Resulted in Manual U1 Trip & U2 ESF Actuation.Caused by Loss of Group C Pressurizer Proportional Heaters.Reactor Trip Breakers Were Verified open.W/970319 Ltr ML18153A1131997-02-20020 February 1997 LER 97-001-00:on 970123,shutdown Occurred Due to Steam Drain Line Weld Leak.Management Was Notified & Shift Supervisor Invoked Requirements of TS 4.15.C.1.W/undtd Ltr ML18153A1101997-02-13013 February 1997 LER 97-002-00:on 970116,one Train of Auxiliary Ventilation Sys Declared Inoperable.Caused by Personnel Error.Properly Adjusted Damper 1-VS-MOD-58B & Exited Seven Day LCO on 970116.W/970214 Ltr ML18153A0951997-01-0202 January 1997 LER 97-002-00:on 961213,automatic Reactor Trip Occurred During Planned Shutdown.Caused by Steam Flow/Feedwater Flow Mismatch.Rps Functioned as Designed & Plant Placed in Hot Shutdown ML18153A0931996-12-12012 December 1996 LER 96-008-00:on 961112,water Gas Decay Tank Oxygen Analyzer Pressure Sensors Inoperable Due to Vendor Supplied Equipment Not Meeting Procurement specifications.Post-implementation Procedures Revised & Transducers replaced.W/961212 Ltr ML18153A0691996-09-19019 September 1996 LER 96-007-00:on 960821,failed to Complete Fire Detection Zone Inspections within Required Time Period.Caused by Personnel Error.Counseled Personnel Re Fire Detection Zone Inspections & Revised Fire Watch training.W/960920 Ltr ML18153A0481996-08-26026 August 1996 LER 96-005-00:on 960803,manual Reactor Trip.Caused by Loss of Electro Hydraulic Control Pressure.Repaired Two Compression Fitting Union Connections on Leaking Fitting & Performed Evaluations on Other tubing.W/960826 Ltr ML18153A0521996-08-20020 August 1996 LER 96-004-01:on 960510,discovered Hydrogen Analyzers Inoperable.Caused by Procedural Deficiencies.Implemented Permanent Changes to Hydrogen Analyzer Instrument Calibr Procedures.W/960820 Ltr ML18153A0321996-07-30030 July 1996 LER 96-006-01:on 960618,anti-corrosion Coating Had Not Been Reapplied to Station Battery 2B.Caused by Procedural Error in That Verbatim TS Compliance Not Reflected in Procedures. Coating Was Applied to batteries.W/960730 Ltr ML18153A0281996-07-17017 July 1996 LER 96-006-00:on 960618,failed to Apply anti-corrosion Coating to Station Battery 2B.Caused by Procedural Error. Applied anti-corrosion Coating to Batteries & Revised TS 4.6.C.1.f Re Battery Coating requirements.W/960717 Ltr ML18153A0141996-07-0202 July 1996 LER 96-004-00:on 960606,turbine/reactor Trip Occurred.Caused by High Level in Steam Generator B.Placed Plant in Hot Shutdown Condition,Calculated Shutdown Margin & Monitored Critical Safety Function Status trees.W/960702 Ltr 1999-08-27
[Table view] Category:RO)
MONTHYEARML18152B4411999-08-27027 August 1999 LER 99-005-00:on 990731,effluent Radiation Monitors Were Declared Inoperable.Caused by Degraded Heat Trace Circuits for Monitors Sample Suction Line.Degraded Heat Trace Circuit Was Replaced & Addl Heat Trace Is Being Installed ML18152B4421999-08-27027 August 1999 LER 99-006-00:on 990802,determined That Plant Was Outside of App R Design Basis Due to Fire Barrier Deficiencies. Caused by Original Plant Design Deficiencies.Fire Watches Were Established & Mods Have Been Completed.With 990827 Ltr ML18152B3771999-08-13013 August 1999 LER 99-004-00:on 990714,TS Violation Due to non-safety Related Fans Effect on CR Boundary Was Noted.Cause of Event Has Not Yet Been Determined.Cable Spreading Room Doors Were Operned to Reduce Pressure in Rooms ML18152B4181999-05-18018 May 1999 LER 99-002-00:on 990425,MSSVs Tested Out of Tolerance for as Found Setpoint.Caused by Minor Setpoint Drift.No Immediate Action Required.Deviation Rept Submitted for Each Valve.With 990518 Ltr ML18152B4111999-04-28028 April 1999 LER 99-003-00:on 990331,potential Loss of Charging Pumps Was Noted.Caused by Main CR Fire.Station Deviation Was Issued on 990331.With 990428 Ltr ML18153A2741999-03-29029 March 1999 LER 99-002-00:on 990301,prematurely Released Fire Watches Resulted in Violation of TS 3.21.B.7.Caused by Inadequate Procedure.Procedure for Opening & Sealing Fire Stops Was Revised on 990212 ML18153A2681999-03-19019 March 1999 LER 98-013-01:on 981122,turbine/reactor Tripped on High Due to Short Circuit in Summator for MSL C Loop Channel III Flow Transmitter.Replaced 1-MS-FT1494 Summator & Module Repair Procedure Revised.With 9903190 Ltr ML18152B7261999-01-21021 January 1999 LER 99-001-00:on 981222,auxiliary Feedwater Pipe Support Missed Surveillance.Caused by Personnel Error.Station Deviation Rept Was Submitted.Two Supports in Question Received Required Code Insp & Were Found Acceptable ML18152B5811998-12-16016 December 1998 LER 98-013-00:on 981122,turbine/reactor Trip on High SG Level Occurred.Caused by Instrument Failure.Control Room Operators Placed Unit in Safe,Shutdown Condition ML18152B5781998-12-16016 December 1998 LER 98-014-00:on 981126,manual Reactor Trip in Response to Main Feedwater Regulating Valve Failure Occurred.Caused by Dislocation of Retaining Clip in Positioner.Control Room Operators Placed Unit in Safe,Shutdown Condition ML18152B7121998-12-0404 December 1998 LER 98-S01-00:on 981105,noted Failure to Deactivate Station Access Badge.Caused by Human Error.Licensee Will Now Deactivate Station Badges Before Clearance Is Revoked & Process for Badge Deactivations Have Been Strengthened ML18152B7041998-12-0101 December 1998 LER 98-012-00:on 981102,noted That EDGs Were Concurrently Inoperable.Caused by Required Testing Per TS 3.16.B.1.a.2. Redundant EDG Was Returned to Svc within Two Hour Period, Following Satisfactory Testing.With 981201 Ltr ML18152B6161998-11-0606 November 1998 LER 98-011-00:on 981008,diesel Driven Fire Pump Failed to Start During Performance of Monthly Operability Test.Caused by Faulty Overspeed Trip Device Failure.Diesel Driven Fire Pump Declared Inoperable ML18152B6081998-10-23023 October 1998 LER 98-010-01:on 980715,intake Canal Level Probes Were Inoperable Due to Marine Growth.Caused by Design of Canal Level Instrumentation.Canal Level Probes Will Continue to Be Monitored More Closely ML18152B7811998-07-31031 July 1998 LER 98-010-00:on 980715,low Intake Canal Level Instrument Channel I Was Declared Inoperable to Allow Testing of Intake Canal Level Probe 1-CW-LE-102.Subject Probe Was Cleaned by Diver,Tested & Channel I Was Returned to Operable Status ML18153A2581998-06-0303 June 1998 LER 98-009-00:on 980509,nonisolable Leak of Reactor Coolant Pump Seal Injection Line Weld,Was Discovered.Caused by Lack of Fusion or Thermal Fatigue Coupled W/Vibration Stress Due to Loose Rod Hanger.Rcp Seal Injection Line Removed ML18152B8241998-05-22022 May 1998 LER 98-008-00:on 980228,auxiliary Ventilation Fans Were Noted in Condition Outside of Design Basis.Caused by Failure to Recognize Potential Impact of Certain Design Basis Accident Scenarios.No Corrective Actions Needed ML18152B7951998-04-29029 April 1998 LER 98-007-00:on 980330,radiation Monitors Were Declared Inoperable.Caused by Change in Operating Temperature Range. Preplanned Alternate Method of Monitoring Was Initiated IAW TS Table 3.7-6 ML18153A2521998-04-22022 April 1998 LER 98-005-01:on 980212,fire Watch Insp Exceeded One Hour. Caused by Lack of Attention to Detail by Individual Involved.Individual Involved Was Coached on Requirement to Perform Fire Watch Patrols within Required Time Frame ML18153A2511998-04-22022 April 1998 LER 98-006-00:on 980324,unisolable Through Wall Leak of RCP Thermowell Was Noted.Cause of Leak Is Unknown.Rtd Will Be Replaced ML18153A2391998-03-13013 March 1998 LER 98-005-00:on 980212,fire Watch Insp Frequency Exceeded One H Occurred.Category 2 Root Cause Evaluation Being Conducted to Determine Cause of Event.Station Deviation Issued ML18153A2341998-03-0909 March 1998 LER 98-003-00:on 980226,no Procedural Guidance for Maintaining EDG Minimum Fuel Supply During Loop,Was Identified.Caused by Absence of Procedural Instructions. Deviation Rept Submitted to Document Deviating Condition ML18153A2301998-03-0606 March 1998 LER 98-004-00:on 980206,fire Watch Was Released Prematurely Resulting in Violation of Ts.Caused by Inadequate Planning of Repair Activity.Work Orders Will Include Ref to Applicable Procedures Developed to Assist in Repairs ML18153A2251998-03-0404 March 1998 LER 98-002-00:on 980202,automatic Turbine Trip Resulted in Automatic Reactor Trip.Caused Degraded Generator Voltage Regulator sub-component Failure.Placed Plant in Safe Hot SD & Replaced Intermittent Relay & Relay Socket ML18153A2201998-02-0606 February 1998 LER 98-001-00:on 980108,deficient Test Due to Faulty Test Equipment Resulted in TS Violation.Caused by Faulty Vibration Analyzer Cable or Loose Connection.Station Deviation Rept Was submitted.W/980206 Ltr ML18153A2071998-01-13013 January 1998 LER 97-012-01:on 971028,loss of Power to Latching Mechanism on Several Doors Occurred.Caused by Tripping of Two Breakers in Security Distribution Panel.Reset Affected Breakers Which Restored Power to Security Systems & Affected Doors ML18153A2101998-01-13013 January 1998 LER 97-009-01:on 971014,declared Intake Canal Level Probes Inoperable Due to Marine Growth.Caused by Inadequate Maint of Intake Canal Level Probes.Subject Probes Were Cleaned, Tested Satisfactorily & Returned to Operable Status ML18153A1911997-11-26026 November 1997 LER 97-011-00:on 971030,determined That Periodic Test Procedures for Testing Reactor Trip Bypass Breakers Did Not Test Manual Undervoltage Trip.Caused by mis-interpretation of Term in-service. Procedures Revised ML18153A1971997-11-26026 November 1997 LER 97-012-00:on 971028,loss of Power to Latching Mechanism on Several Doors Occurred.Caused by Tripping of Breaker in Security Distribution Panel in Central Alarm Station (CAS) Panel.Breakers in Affected CAS Panel Reset ML18153A1921997-11-25025 November 1997 LER 97-010-00:on 971028,discovered Missed Fire Protection Surveillance Pt.Caused by Personnel Error.Satisfactorily Completed PT Procedure 0-OPT-FP-009 & Diesel Driven Fire Pump 1-FP-P-2 Declared operable.W/971125 Ltr ML18153A1831997-11-12012 November 1997 LER 97-009-00:on 971014,declared Intake Canal Level Probes Inoperable Due to Marine Growth.Cause Indeterminate.Divers Inspected,Cleaned & Returned Probes to Operable Status & Initiated Interdepartmental Team to Investigate Cause ML18153A1791997-11-0707 November 1997 LER 97-008-00:on 971011,invalid Actuation of ESF Occurred. Caused by Personnel Errors.Main CR Bottled Air Sys Isolated & Containment Hydrogen Analyzer Heat Tracing Actuation Signal Reset ML18153A1721997-10-30030 October 1997 LER 97-007-00:on 970930,determined That Plant Was Outside App R Design Basis Due to Vital Bus Isolation Issue.Caused by Personnel Error.Installed Circuit Protective Device During Oct 1997 Refueling Outage ML18153A1421997-06-10010 June 1997 LER 97-001-01:on 970123,shutdown Occurred Due to Drain Line Weld Leak.Inspected & Tested Turbine Trip Actuation circuitry.W/970610 Ltr ML18153A1391997-05-28028 May 1997 LER 97-005-00:on 970502,Unit 1 Power Range Nuclear Instrumentation Was Inoperable Due to Personnel Error.Sro & STA That Were Involved in Event Were Counseled ML18153A1291997-04-18018 April 1997 LER 97-006-00:on 970320,loss of Refueling Integrity Due to Inadequate Containment Closure Process & Verification.Fuel Movement Stopped IAW Action Statement Requirements of TS 3.10.B.W/970418 Ltr ML18153A1281997-04-15015 April 1997 LER 97-004-00:on 970317,main Steam Safety Valve Was Outside as Found Setpoint Tolerance.Specific Cause Unknown,However, Minor Setpoint Drift Can Be Expected.No Immediate Corrective Actions performed.W/970415 Ltr ML18153A1241997-04-0808 April 1997 LER 97-002-01:on 970116,one Train of Auxiliary Ventilation Sys Was Inoperable Outside of Ts.Caused by Personnel Error. Submitted Deviation Rept Re Reverse Rotation of Fan & Work Request to Adjust linkage.W/970408 Ltr ML18153A1191997-03-19019 March 1997 LER 97-001-00:on 970218,manual Reactor Trip & ESF Actuation Occurred Due to Loss of EHC Control Power.Caused by Momentary Short.Relay Card Was replaced.W/970319 Ltr ML18153A1201997-03-19019 March 1997 LER 97-003-00:on 970219,loss of Pressurizer Heaters Resulted in Manual U1 Trip & U2 ESF Actuation.Caused by Loss of Group C Pressurizer Proportional Heaters.Reactor Trip Breakers Were Verified open.W/970319 Ltr ML18153A1131997-02-20020 February 1997 LER 97-001-00:on 970123,shutdown Occurred Due to Steam Drain Line Weld Leak.Management Was Notified & Shift Supervisor Invoked Requirements of TS 4.15.C.1.W/undtd Ltr ML18153A1101997-02-13013 February 1997 LER 97-002-00:on 970116,one Train of Auxiliary Ventilation Sys Declared Inoperable.Caused by Personnel Error.Properly Adjusted Damper 1-VS-MOD-58B & Exited Seven Day LCO on 970116.W/970214 Ltr ML18153A0951997-01-0202 January 1997 LER 97-002-00:on 961213,automatic Reactor Trip Occurred During Planned Shutdown.Caused by Steam Flow/Feedwater Flow Mismatch.Rps Functioned as Designed & Plant Placed in Hot Shutdown ML18153A0931996-12-12012 December 1996 LER 96-008-00:on 961112,water Gas Decay Tank Oxygen Analyzer Pressure Sensors Inoperable Due to Vendor Supplied Equipment Not Meeting Procurement specifications.Post-implementation Procedures Revised & Transducers replaced.W/961212 Ltr ML18153A0691996-09-19019 September 1996 LER 96-007-00:on 960821,failed to Complete Fire Detection Zone Inspections within Required Time Period.Caused by Personnel Error.Counseled Personnel Re Fire Detection Zone Inspections & Revised Fire Watch training.W/960920 Ltr ML18153A0481996-08-26026 August 1996 LER 96-005-00:on 960803,manual Reactor Trip.Caused by Loss of Electro Hydraulic Control Pressure.Repaired Two Compression Fitting Union Connections on Leaking Fitting & Performed Evaluations on Other tubing.W/960826 Ltr ML18153A0521996-08-20020 August 1996 LER 96-004-01:on 960510,discovered Hydrogen Analyzers Inoperable.Caused by Procedural Deficiencies.Implemented Permanent Changes to Hydrogen Analyzer Instrument Calibr Procedures.W/960820 Ltr ML18153A0321996-07-30030 July 1996 LER 96-006-01:on 960618,anti-corrosion Coating Had Not Been Reapplied to Station Battery 2B.Caused by Procedural Error in That Verbatim TS Compliance Not Reflected in Procedures. Coating Was Applied to batteries.W/960730 Ltr ML18153A0281996-07-17017 July 1996 LER 96-006-00:on 960618,failed to Apply anti-corrosion Coating to Station Battery 2B.Caused by Procedural Error. Applied anti-corrosion Coating to Batteries & Revised TS 4.6.C.1.f Re Battery Coating requirements.W/960717 Ltr ML18153A0141996-07-0202 July 1996 LER 96-004-00:on 960606,turbine/reactor Trip Occurred.Caused by High Level in Steam Generator B.Placed Plant in Hot Shutdown Condition,Calculated Shutdown Margin & Monitored Critical Safety Function Status trees.W/960702 Ltr 1999-08-27
[Table view] Category:TEXT-SAFETY REPORT
MONTHYEARML18152A2811999-10-12012 October 1999 Technical Basis for Elimination of Nozzle Inner Radius Insps (for Nozzles Other than Reactor Vessel),Technical Basis for ASME Section XI Code Case N-619. ML18152B3531999-09-30030 September 1999 Monthly Operating Repts for Sept 1999 for Surry Power Station,Units 1 & 2.With 991012 Ltr ML18152B6651999-08-31031 August 1999 Monthly Operating Repts for Aug 1999 for Surry Power Station Units 1 & 2.With 990915 Ltr ML18152B4421999-08-27027 August 1999 LER 99-006-00:on 990802,determined That Plant Was Outside of App R Design Basis Due to Fire Barrier Deficiencies. Caused by Original Plant Design Deficiencies.Fire Watches Were Established & Mods Have Been Completed.With 990827 Ltr ML18152B4411999-08-27027 August 1999 LER 99-005-00:on 990731,effluent Radiation Monitors Were Declared Inoperable.Caused by Degraded Heat Trace Circuits for Monitors Sample Suction Line.Degraded Heat Trace Circuit Was Replaced & Addl Heat Trace Is Being Installed ML18151A3981999-08-13013 August 1999 SPS Unit 2 ISI Summary Rept for 1999 Refueling Outage. ML18152B3771999-08-13013 August 1999 LER 99-004-00:on 990714,TS Violation Due to non-safety Related Fans Effect on CR Boundary Was Noted.Cause of Event Has Not Yet Been Determined.Cable Spreading Room Doors Were Operned to Reduce Pressure in Rooms ML18152B3791999-07-31031 July 1999 Monthly Operating Repts for July 1999 for Surry Power Station,Units 1 & 2.With 990811 Ltr ML18152B3911999-06-30030 June 1999 Monthly Operating Repts for June 1999 for Surry Power Station,Units 1 & 2.With 990713 Ltr ML18152B4341999-05-31031 May 1999 Monthly Operating Repts for May 1999 for Surry Power Station,Units 1 & 2.With 990614 Ltr ML20195E2401999-05-31031 May 1999 Rev 2 to COLR for SPS Unit 2 Cycle 16 Pattern Ag ML18152B4181999-05-18018 May 1999 LER 99-002-00:on 990425,MSSVs Tested Out of Tolerance for as Found Setpoint.Caused by Minor Setpoint Drift.No Immediate Action Required.Deviation Rept Submitted for Each Valve.With 990518 Ltr ML18152B4161999-04-30030 April 1999 Monthly Operating Repts for Apr 1999 for Surry Power Station Units 1 & 2.With 990512 Ltr ML18152B4111999-04-28028 April 1999 LER 99-003-00:on 990331,potential Loss of Charging Pumps Was Noted.Caused by Main CR Fire.Station Deviation Was Issued on 990331.With 990428 Ltr ML18152B6511999-03-31031 March 1999 Monthly Operating Repts for Mar 1999 for Surry Power Station Units 1 & 2 ML18153A2741999-03-29029 March 1999 LER 99-002-00:on 990301,prematurely Released Fire Watches Resulted in Violation of TS 3.21.B.7.Caused by Inadequate Procedure.Procedure for Opening & Sealing Fire Stops Was Revised on 990212 ML18153A2681999-03-19019 March 1999 LER 98-013-01:on 981122,turbine/reactor Tripped on High Due to Short Circuit in Summator for MSL C Loop Channel III Flow Transmitter.Replaced 1-MS-FT1494 Summator & Module Repair Procedure Revised.With 9903190 Ltr ML18152B7331999-02-28028 February 1999 Monthly Operating Repts for Feb 1999 for Surry Power Station,Units 1 & 2.With 990310 Ltr ML18152B5421999-01-31031 January 1999 Monthly Operating Repts for Jan 1999 for Surry Power Station,Units 1 & 2.With 990210 Ltr ML18151A3031999-01-29029 January 1999 ISI Summary Rept for 1998 Refueling Outage,Including Form NIS-1, Owners Rept for ISIs & Form NIS-2, Owners Rept for Repairs & Replacements. ML18152B7261999-01-21021 January 1999 LER 99-001-00:on 981222,auxiliary Feedwater Pipe Support Missed Surveillance.Caused by Personnel Error.Station Deviation Rept Was Submitted.Two Supports in Question Received Required Code Insp & Were Found Acceptable ML18152B6011998-12-31031 December 1998 Monthly Operating Repts for Dec 1998 for Surry Power Station,Units 1 & 2.With 990115 Ltr ML18152B5781998-12-16016 December 1998 LER 98-014-00:on 981126,manual Reactor Trip in Response to Main Feedwater Regulating Valve Failure Occurred.Caused by Dislocation of Retaining Clip in Positioner.Control Room Operators Placed Unit in Safe,Shutdown Condition ML18152B5811998-12-16016 December 1998 LER 98-013-00:on 981122,turbine/reactor Trip on High SG Level Occurred.Caused by Instrument Failure.Control Room Operators Placed Unit in Safe,Shutdown Condition ML18152B7121998-12-0404 December 1998 LER 98-S01-00:on 981105,noted Failure to Deactivate Station Access Badge.Caused by Human Error.Licensee Will Now Deactivate Station Badges Before Clearance Is Revoked & Process for Badge Deactivations Have Been Strengthened ML18152B7041998-12-0101 December 1998 LER 98-012-00:on 981102,noted That EDGs Were Concurrently Inoperable.Caused by Required Testing Per TS 3.16.B.1.a.2. Redundant EDG Was Returned to Svc within Two Hour Period, Following Satisfactory Testing.With 981201 Ltr ML18152B7081998-11-30030 November 1998 Rev 0 to COLR for Surry 1 Cycle 16,Pattern Un. ML18152B5721998-11-30030 November 1998 Monthly Operating Repts for Nov 1998 for Surry Power Station,Units 1 & 2.With 981214 Ltr ML18152B6161998-11-0606 November 1998 LER 98-011-00:on 981008,diesel Driven Fire Pump Failed to Start During Performance of Monthly Operability Test.Caused by Faulty Overspeed Trip Device Failure.Diesel Driven Fire Pump Declared Inoperable ML18152B6241998-10-31031 October 1998 Monthly Operating Repts for Oct 1998 for Surry Power Station Units 1 & 2.With 981111 Ltr ML18152B6081998-10-23023 October 1998 LER 98-010-01:on 980715,intake Canal Level Probes Were Inoperable Due to Marine Growth.Caused by Design of Canal Level Instrumentation.Canal Level Probes Will Continue to Be Monitored More Closely ML18152B6881998-09-30030 September 1998 Monthly Operating Repts for Sept 1998 for Surry Power Station Units 1 & 2.With 981012 Ltr ML18153A3271998-08-31031 August 1998 Monthly Operating Repts for Aug 1998 for Surry Power Station,Units 1 & 2 ML18152B7811998-07-31031 July 1998 LER 98-010-00:on 980715,low Intake Canal Level Instrument Channel I Was Declared Inoperable to Allow Testing of Intake Canal Level Probe 1-CW-LE-102.Subject Probe Was Cleaned by Diver,Tested & Channel I Was Returned to Operable Status ML18153A3161998-07-31031 July 1998 Monthly Operating Repts for July 1998 for Surry Power Station Units 1 & 2.W/980807 Ltr ML18152B7621998-06-30030 June 1998 Monthly Operating Repts for June 1998 for Surry Power Station,Units 1 & 2.W/980707 Ltr ML18153A2581998-06-0303 June 1998 LER 98-009-00:on 980509,nonisolable Leak of Reactor Coolant Pump Seal Injection Line Weld,Was Discovered.Caused by Lack of Fusion or Thermal Fatigue Coupled W/Vibration Stress Due to Loose Rod Hanger.Rcp Seal Injection Line Removed ML20248F7441998-05-31031 May 1998 Reactor Vessel Working Group,Response to RAI Regarding Reactor Pressure Vessel Integrity ML18153A3141998-05-31031 May 1998 Monthly Operating Repts for May 1998 for Surry Power Station,Units 1 & 2.W/980610 ML18152B8241998-05-22022 May 1998 LER 98-008-00:on 980228,auxiliary Ventilation Fans Were Noted in Condition Outside of Design Basis.Caused by Failure to Recognize Potential Impact of Certain Design Basis Accident Scenarios.No Corrective Actions Needed ML18152B8161998-04-30030 April 1998 Monthly Operating Repts for Apr 1998 for Surry Power Station Units 1 & 2.W/980508 Ltr ML18152B7951998-04-29029 April 1998 LER 98-007-00:on 980330,radiation Monitors Were Declared Inoperable.Caused by Change in Operating Temperature Range. Preplanned Alternate Method of Monitoring Was Initiated IAW TS Table 3.7-6 ML18153A2511998-04-22022 April 1998 LER 98-006-00:on 980324,unisolable Through Wall Leak of RCP Thermowell Was Noted.Cause of Leak Is Unknown.Rtd Will Be Replaced ML18153A2521998-04-22022 April 1998 LER 98-005-01:on 980212,fire Watch Insp Exceeded One Hour. Caused by Lack of Attention to Detail by Individual Involved.Individual Involved Was Coached on Requirement to Perform Fire Watch Patrols within Required Time Frame ML20217P9941998-04-0707 April 1998 Safety Evaluation Granting Licensee Third 10-yr Inservice Insp Program Relief Requests SR-018 - Sr-024 ML18153A2951998-03-31031 March 1998 Monthly Operating Repts for Mar 1998 for Sps,Units 1 & 2.W/ 980408 Ltr ML18153A2391998-03-13013 March 1998 LER 98-005-00:on 980212,fire Watch Insp Frequency Exceeded One H Occurred.Category 2 Root Cause Evaluation Being Conducted to Determine Cause of Event.Station Deviation Issued ML18153A2341998-03-0909 March 1998 LER 98-003-00:on 980226,no Procedural Guidance for Maintaining EDG Minimum Fuel Supply During Loop,Was Identified.Caused by Absence of Procedural Instructions. Deviation Rept Submitted to Document Deviating Condition ML18153A2301998-03-0606 March 1998 LER 98-004-00:on 980206,fire Watch Was Released Prematurely Resulting in Violation of Ts.Caused by Inadequate Planning of Repair Activity.Work Orders Will Include Ref to Applicable Procedures Developed to Assist in Repairs ML18153A2251998-03-0404 March 1998 LER 98-002-00:on 980202,automatic Turbine Trip Resulted in Automatic Reactor Trip.Caused Degraded Generator Voltage Regulator sub-component Failure.Placed Plant in Safe Hot SD & Replaced Intermittent Relay & Relay Socket 1999-09-30
[Table view] |
Text
- %:~~~....,.-. *-=-- -~ *__ --*-*-->>--
=====
- U. . CLEAR REGULATORY COMMISSION APPROVED BY* 0MB NO; 3150-0104 .
,(+95) __,, . - EXPIRES 4/30/98 ESTIMAlED BURDEN PER RESPONSE 10 COMPLY WITH THIS MANDAlORY INFORMATION COLLECTION REQUEST: 50.0 HRS.
' REPORTED LESSONS LEARNED ARE INCORPORAlED IN10 THE
~ICEN$EE EVENT;.~r::PORT (LER} :: , . ** LICENSING PROCESS AND FE_D BACK 10 INDUSTRY. **FORWARD COMMENTS: REGARDING BURDEN ESTIMATE 10 THE INFORMATION AND RECORDS MANAGEMENT BRANCH (T-6 F33),
U.S. NUCLEAR REGULATORY COMMISSION, WASHINGTON, DC (See reverse for required number of digits.lcharacters for each block) 205S0001, AND TO THE PAPERWORK REDUCTION PROJECT
, ' ' .J (3150-0104),
- OFFICE OF MANAGEMENT* AND - 'BUDGET,
. WASHINGTON, DC 20503. ' ..
FACILITY NAME (1) DOCKET NUMBER (2) PAGE (3)
SURRY POWERSTATION.,.Unit.t", 05000 - 280 1 OF5 TITLE(4)
EQ Unar:iaivzed Condition/Outside A* . RDesi -* n Basis Due to Unlatched Doors*-:.
EVENT DATE (5) LEA NUMBER OTHER FACILITIES INVOLVED 8)
SEQUENTIAL '. ,REVISIQN FA~IUTYNA¥E: . . , -. .. , .*,, i
- DOCUMENT: NUMBER MONTH DAY YEAR YEAR MONTH*,, DAY YEAR' 1
- . NUMBER
- NUMBER Surry Power Station, Unit 2 05000-281 FACILITY NAME DOCUMENT NUMBER 10 28 97 97 -- 012 -- 00 11 26 97 05000-OPERATING THIS REPORT1S SUBMITTED PURSUANT TO THE REQUIREMENTS OF 10 CFR §: (Check one or more) (11)
MODE(9) N 20.2201(b) 20.2203(a)(2)(v) 50.73(a)(2)(i) 50.73(a)(2)(viii)
POWER *20.2203(a)(1) i. * * * * . 20;2203(a)(3)(i) x 50.73(a)(2)(ii) . 50.73(a)(2)(x)
LEVEL (10) , 100 % 20.2203(a)(2)(i) ., . _ *,20.2203(a)(3)(ii) "*
20.2203(a)(2)(ii). . , .. 20.2203(a)(4) ** .50.73(a)(2)(iv) . - . OTHER 20.2203(a)(2)(iii) 50.36(c)(1) 50.73(a)(2)(v) .Specify In Abstract below 20.2203(a)(2)(iv) . 50.36(c)(2) 50.73(~)(2)(vii) . . . or lh NRC Form 366A LICENSEE CONTACT FOR THIS LER (12 NAME TELEPHONE NUMBER (Include Area Code)
D. A. Christian, Station Manager COMPLETE ONE LINE FOR EACH COMPONENT FAILURE DESCRIBED IN THIS REPORT l13l I(757) 365-2000 CAUSE SYSTEM COMPONENT MANUFACTURER - REPORTABLE CAUSE SYSTEM COMPONENT MANUFACTURER REPORTABLE TONPRDS TONPRDS NA NA NA NA NA SUPPLEMENTAL REPORT EXPECTED (14) EXPECTED MONTH *DAY YEAR SUBMISSION YES JxJNO DATE I (If yes, complete EXPECTED SUBMISSION DATE).
ABSTRACT (Limit to 1400 spaces, i.e., approximately 15 single-spaced typewritten lines) (16)
On October 27, 1997, the tripping of two breakers in a security distribution panel resulted in a
_ le>ss_of power to secl!rl!Y__ syste_rns,_~~-~~ILJ:t~_~Jo~s otpov.rer._tQ_Jh~J~tcbil}g m_~c~~nj_~m on several doors, which caused the doors to become unlatched. The affected doors have securiJy, environmental qualification (EQ), and/or fire protection functions. At the time of occurrence, Unit 1 was at 100% power and Unit 2 was at intermediate shutdown in the process of starting up following completion of a scheduled refueling outage. Compensatory measures were implemented, as required, including security provisions. It was determined that having multiple EQ doors in an unlatched condition simultaneously resulted in an unanalyzed condition; the unanalyzed condition resulted because the defined allowed outage times for the EQ doors assume no simultaneous EQ door breaches. It was also concluded that fire doors being unlatched resulted in being outside the 10CFR50 Appendix R design basis because the unlatched doors may not have prevented the spread of a fire from one fire area to other fire areas. A design change to revise the power failure mode on the affected doors from energized-to-latch to energized-to-unlatch has been implemented. This report is being
.r;r.:-
9712120375 c,71 126 1 -
,:DR ADOCK 0500028 PDR0
- .,---*** ---~~v,,_,.~---......,__ ---~--*-*---,..,,__ . _..,__._._,.,__ ,. __ * . . . -*.--*" -. * ....~.. ._.,.,. .. ____ _
~ ====*=-=*=--=**="~=-=~=================**=*===============
.e . ' ... . ' . ; . *.*: ::;'9.s.
r;==.
NRC FORM 366A NUCLEARREGULATORYCOMMISSION (4-95)
-"t ..
. -.. . .. .1'*: ~ ' . '.*
. . LICENSEE *EVENT *REPORT (LER) * ~.,. I
- ' J"*
... 1. *'* '. *;*.
.*
- TEXT CONTINUATION .. 'o:.. _;
i !_, \ 'i
' FACILITYNAME(1) .I _,,,'
DOCKET LEA NUMBER (6) PAGE (3l
. ' . .- ~ .*. . ... .. YEAR I SEQUENTIAL NUMBER I REVISION NUMBER
. Surry Power'Statlori *unit 1 05000-280 97 -012-- 00 20F5 TEXT (If more space is required, use additional copies of NRC Form 366A) (17) *
. . _: :.r .' .
1.0 DESCRIPTION
OF THE EVENT On October.:27,, 1997* at 1625 t:iour$, *with*_ Unit,.J at 100% power ~md. Unit 2 af
- intermediate*.shutdown in the process .of .starting up following. completion of a scheduied refueling outage, a loss of power occurred to security systems due to a circuit breaker
- '*tripping. Compensatory measures were implemented within ten minutes to address the',
- loss of the* security systems. Specifically, the compensatory measures* were for the loss of protected. and .yital area alarm~ * .loss of closed, circµit television, . loss, of radio commuoicatio.ns, a'nd:loss of eJectron{c,qpntrol access:;.- *.) **,, . ** ... ' ...
Subsequently, the door between the Turbine Building and the Emergency Switchgear
- Room* (2-BS-DR-21) was found unlatched; this'* c;too( is a non-vital security controlled door, a:n* environmental qualification (EQ) door, and a fire* door. Shortly thereafter, a second door - the door between the Emergency Switchgear Room and the back stairway to the Main Control Room (2-BS-DR-20) - was also found unlatched; this door is a non-vital security controlled door and a fire door; As a result of these doors being found unlatched, other doors were checked. It was discovered that the following doors were also unlatched:
- Between Emergency Diesel Generator Rooms and Turbine Building (1-BS-DR-1, 2-BS-DR-2, 1-BS-DR-3) ., non-vital secutity controlled, EQ, and fire doors
- Between Unit 2 Switchgear Room and Stairway to Control Room (2-BS-DR-45) -
non-vital security controlled and fire door
- Between Unit 2 Cable Spreading Room and Turbine Building (2-BS-DR-49) - non-vital security controlled and fire door The identified doors becoming unlatched was the result of a second circuit breaker
_ tripping. In the unlatched condition, the fire doors were considered inoperable and, as
- - - required by Technical Specifications,- posting-*of fire watches for-ttie--affected fire doors --~
was initiated. While in the process of posting the required fire watches, the fire doors identified above were verified to be latching properly, after power was restored by
- resetting the breakers. Therefore, the fire watches were secured. At that time, it was suspected that the loss of power to the security systems resulted in the doors becoming
In parallel with the actions taken from the security and fire protection perspectives, it was determined that an EQ watch was not necessary since a watch would serve no purpose because the doors would not perform their EQ function in an unlatched condition.
However, an assessment of the unlatched doors on EQ was subsequently initiated. On October 28, 1997, it was determined that having multiple EQ doors in an unlatched condition simultaneously resulted in an unanalyzed condition; the unanalyzed condition resulted because the defined allowed outage times for the EQ doors assume no NRr. FORM AA/IA /4,!l!i\
~~-~*:_:_,, . ~---'-'-"=*-- ~ *-*-*--* .* ._ .. ___~=-~':.:.:-.......___'.:*:*-:: -
~~-~W~*-**-**-**~-*
- --***-- . - -* . * - .. -*-***-- ---~*-----~ --- - - --~ -
. NRC FORM 366A
!-," . . . . ..* - . : .S; NUCLEAR*REGULATORY COMMISSION (4-95)
.* ....~*-, - -- - - ~ .: >. *-*1 * *
- LICENSEE EVENT. REPORT (LER) ... . (' ~l
.. *:,: ,, '-~ 8, I
.. I, *. :_-,i* -~, _,.J_,;- TEXT CONTINUATION-*;, .. -, ...... *'
' FACILl"fX NAME'(1)
. : '. ,.. ' ' . : ~:_ ;,. ' . :
DOCKET LEA NUMBER (6) PAGE (3)
. . : ' '. ; ! ' YEAR I SWuUJ:~Al;-1 ~~~~~
- surrv Power' Station Unit 1 05000 - 280 97 -012-- 00 30F5 TEXT (If more space is required, use additional copies of NRC Form 366A) (17) 1.0 DESCRIPTIOf*i OF _THE. EVENT (continued) ' ...
sirnultaneous:,;EQ door.*breaches, *, -A non.;emergency one ho_ur report to .th~ NRC was
.. -~-conipletecr *-. r.at 1 *1 a25 .-.. -hours r=:.,*on 1 October' : * :28, 1.-997 - ..in ~accordance . With.
_1OCFRSO. 72(b)(1 )(ii)(A}.
' ; * ' *.* !11' Additional walkdowns and testing were performed by Engineering and Security personnel to verify Jhe; PQW~J:. failure mod~. of the fire door Jatc.he~! *, As the energiz~d-to-latch configuration:;_{:Le:;.*;unlatch on.*loss of, power) was identified, fire watqhes were. again posted. Upon further review,*'. it was subsequently determined that fire doors in an
. unlatched condition due to the loss of power resulted in being outside the 10CFRSO
- * **** *" Appe'ndix. R d~sign , basis. This conclusion ,was
- reached *because the doors in an unlatched position may not have provided thei(assumed fire rating and, therefore, may not have prevented the spread of a fire from one fire area to:other fire areas. .
This report is being submitted pursuant to the requirements of 10CFRSO. 73(a}(2)(ii)(A}
for being in an unanalyzed condition due to multiple EQ doors in an unlatched condition simultaneously, as well as pursuant to the requirements of 10CFR50.73(a){2){ii){B} for being outside the 10CFRSO Appendix R design basis due to fire doors being in an unlatched condition as a result of a loss of power.
2.0 SIGNIFICANT SAFETY CONSEQUENCES AND IMPLICATIONS The loss of power to the door latching mechanisms existed for a short duration
{i.e., approximately 90 minutes}. During this short period of time, the unlatched doors would not have performed their EQ function; similarly, the unlatched doors may not have provided their assumed fire rating and, therefore, may not have prevented the spread of
_ -__ a fire fr<>rn_9ne__ fir~_ areaJQ_othe_r fir~_~r~~-s. How~-~er._a _ condition_r~quiringJhe doors to_
perform their EQ or fire protection function did not occur. Therefore, this incident did nqt result in a condition adverse to nuclear safety, and the health and safety of the public .
were not affected.
3.0 CAUSE OF THE EVENT The loss of power to the security systems was the result of the tripping of one of the breakers in a security distribution panel in the Central Alarm Station (CAS}. The identified doors becoming unlatched was the result of the tripping of a second breaker in the same CAS panel. Interviews with Security and Operations personnel revealed that the breakers tripped near the completion of the monthly periodic test (PT} being performed on the security diesel generator. The breaker trips are believed to have occurred when the alternate AC input to the inverter transferred from the diesel generator NRr. FORM AARA 14-!l!;l
.~-, ---,.~=-.--**"-'-
___'-'-*~-"'..- -
=
.,;; NRG FORM 366A . . NUCLEAR REGULATORY COMMISSION (4-95L.
LICENSEE EVENT REPORT (LER)
.. .* . . . *.!I '
- FACILITY NAME (1) * *I *** ,, DOCKET LEA NUMBER (6) PAGE(3)
YEAR I SEQUENTIAL NUMBER I REVISION NUMBER Surrv Power Station.Unit 1 05000-280 97 -012-- 00 40F5 TEXT (If more space is required, use addition.al copies of NRG Form 366A) (17)
.. . .!; ~
3.0 CAUSE OF THE EVENT(continued) to the* :normal* power :,source;*
- Engineering has evaluated the breaker trips. It is recognized 'that the capacity of the breaker that resulted in the loss of power to the security systems needs to be increased. The second breaker affecting the doors is believed to. be near its design loading.
4.0 IMMEDIATE CORRECTIVE ACTIONCS)
Upon the loss of power to the security systems, the Security staff implemented compensatory measures within ten minutes. Specifically, the compensatory measures were for the loss of protected and vital area alarms, loss of closed circuit television, loss of radio communications, and loss of electronic control access. These compensatory measures remained in place until power was restored and testing was performed by Security to verify the operability of the security systems.
Upon recognition of fire doors *being in the unlatched condition and, therefore, considered inoperable, posting of fire watches for the affected fire doors was initiated, as required by Technical Specifications. While in the process of posting the required fire watches, the fire doors identified above were verified to be latching properly. Therefo"re, the fire watches were secured.
The breakers in the affected CAS panel were reset, restoring power to the security systems and to the affected doors.
An assessment of the unlatched doors on EQ was initiated when it was determined that an EQ watch was not necessary since a watch would serve no purpose because the
_-_doors. would no.t p_er:{c;>rm th.eir J::QJ11nc:ti<:>ri_ln_ar1 ur:il~tched c:onditior:i. ________ *----- ___ ._.
5.0 ADDITIONAL CORRECTIVE ACTIONS On October, 28, 1997, the EQ assessment was completed, and it was concluded that having multiple EQ doors in an unlatched condition simultaneously resulted in an unanalyzed condition; the unanalyzed ~ondition resulted because the defined allowed outage times for the EQ doors assume no simultaneous EQ door breaches. A non-emergency one-hour report to the NRC was completed at 1825 hours0.0211 days <br />0.507 hours <br />0.00302 weeks <br />6.944125e-4 months <br /> on October 28, 1997 in accordance with 10CFR50.72(b)(1)(ii)(A).
Additional walkdowns and testing were performed by Engineering and Security personnel to verify the power failure mode of the fire door latches. As the energized-to-latch configuration (i.e., unlatch on loss of power) was identified, fire watches were again posted; these fire watches remained in place until modifications were performed. Upon NRC: FORM AAllA 14-R!i\
11*::;.-:::* --t -- --------- *--------- *- - -* *---***-* .. *- ----- - ---*** - -____ ----*~-- *. _- - - - --~-----*---* _____:_______ - -- ---
NRC FORM 366A . . NUCLEAR REGULATORY COMMISSION (4-9SL LICENSEE EVENT REPORT. (LER)
TEXT CONTINUATION
- FACILITY NAME (1) '"' ' *,. * ' 1 * * :, '
- DOCKET LEA NUMBER (6) PAGE(3)
YEAR I SEQUENTIAL NUMBER I REVISION NUMBER Surry Power Station Unit 1 05000-280 97 -012-- 00 50F5 TEXT (If more space is requir~. use additional copies of NRC Form 366A) (17) 5.0 ADDITIONAL CORRECTIVE ACTIONS (continued)
.*. ;; .._*'.. "i further review, it was determined that fire doors in an unlatched condition due to the loss of power resulted *ih' *being outside the 10CFR50 Appendix R design basis; this conclusion was reached because the doors in an unlatched position may not have provided their assumed fire rating and, therefore, may not have preven~ed the spread of a fire from one fire area to other fire areas.
On November 7, 1997, another PT was performed on the security diesel generator. This PT differs from the monthly PT performed on October 27, 1997 in the way it is initiated (i.e., feeder breaker being opened versus security diesel generator transfer switch placed in test position). Therefore, the PT performed on November 7, 1997 closely resembles a loss of power event that would require operation of the security diesel generator. The November 7, 1997 PT was performed successfully with no breakers tripping. In addition, the scheduled monthly PT was performed satisfactorily with no breakers tripping on November 24, 1997.
6.0 ACTIONS TO PREVENT RECURRENCE A design change package (DCP) was initiated to change the power failure mode for the affected doors from energized-to-latch to energized-to-unlatch. This change in failure mode eliminates the impact of the breaker tripping incident on the Surry Appendix R and EQ Programs because the door latches now lock upon a loss of power, thereby ensuring that the functional requirements for the doors will be met. This DCP has been completed on the affected doors with respect to the non"'.vital security controlled, EQ, and fire protection functional requirements.
- Both break_~r~Jba! trii:>p_eQ "YillQ~_!~Rf~q_ec::J_~--~~ _____________________________ _
7.0 SIMILAR EVENTS None.
8.0 MANUFACTURER/MODEL NUMBER Not applicable.
9.0 ADIDITIONAL INFORMATION None.
NRr. FOFlM !-!AAA 14-!l/i\