MONTHYEARIR 05000341/20240032024-11-0606 November 2024 Integrated Inspection Report 05000341/2024003 IR 05000341/20240122024-11-0101 November 2024 Commercial Grade Dedication Inspection Report 05000341/2024012 IR 05000016/20240012024-11-0101 November 2024 Enrico Fermi Atomic Power Plant, Unit 1, NRC Inspection Report 05000016/2024001 IR 05000341/20245012024-10-0808 October 2024 – Emergency Preparedness Inspection Report 05000341/2024501 ML24276A2032024-10-0303 October 2024 FEMA Level 1 Finding Transmittal Letter ML24268A0992024-10-0101 October 2024 Power Plant – Audit Summary for License Amendment Request and Regulatory Exemptions for a Risk Informed Approach to Address ECCS Strainer Performance IR 05000341/20240132024-09-30030 September 2024 Phase 2 Post Approval License Renewal Report 05000341/2024013 ML24240A1692024-09-18018 September 2024 Cy 2023 Summary of Decommissioning Trust Fund Status ML24257A1652024-09-13013 September 2024 FEMA Region 5 Fermi 2 Nuclear Power Plant Level 1 Finding September 2024 ML24254A3562024-09-0909 September 2024 FEMA Level 1 Finding for Fermi 2024 Biennial Exercise ML24240A3532024-08-27027 August 2024 Inservice Testing (IST) Program for the Fourth 10-Year Inspection Interval Update IR 05000341/20240052024-08-22022 August 2024 Updated Inspection Plan for Fermi Power Plant, Unit 2 (Report 05000341/2024005) IR 05000341/20244042024-08-21021 August 2024 Public-Fermi Power Plant, Unit 2 - Material Control and Accounting Program Inspection Report 05000341/2024404 IR 05000341/20240022024-08-14014 August 2024 Integrated Inspection Report 05000341/2024002 ML24199A2182024-07-25025 July 2024 Enrico Fermi Atomic Power Plant, Unit 1 - NRC Position on Continuation of Possession-Only License No. DPR-9 Past the Current Expiration Date (Docket No. 50-016) ML24169A4092024-07-18018 July 2024 Relief Request RR-A25, Alternative to Reactor Vessel Circumferential Shell Weld Examination IR 05000341/20243022024-07-0909 July 2024 NRC Initial License Reexamination Report 05000341/2024302 ML24173A1012024-06-14014 June 2024 Retake Exam Post-Exam Cover Letter & Comments ML24155A0852024-06-11011 June 2024 Operator Licensing Reexamination Approval Letter - Fermi Power Plant, June 2024 ML24151A6482024-06-0303 June 2024 Changes in Reactor Decommissioning Branch Project Management Assignments for Some Decommissioning Facilities IR 05000341/20244022024-05-30030 May 2024 Security Baseline Inspection Report 05000341/2024402 ML24143A1852024-05-29029 May 2024 – Regulatory Audit in Support of LAR to Adopt TSTF-505, Rev. 2, TSTF-439, Rev. 2, and TSTF-591, Rev. 0 ML24141A2072024-05-20020 May 2024 Plant—Information Request to Support the NRC Annual Baseline Emergency Action Level and Emergency Plan Changes Inspection 05000341/LER-2024-002, Primary Containment Isolation Valve Declared Inoperable for a Period Prohibited by Technical Specifications2024-05-16016 May 2024 Primary Containment Isolation Valve Declared Inoperable for a Period Prohibited by Technical Specifications 05000341/LER-2024-001, Automatic RPS Scram on High RPV Pressure While Attempting to Lower Generator Output During RF-222024-05-15015 May 2024 Automatic RPS Scram on High RPV Pressure While Attempting to Lower Generator Output During RF-22 IR 05000341/20240102024-05-0606 May 2024 NRC Inspection Report 05000341/2024010 ML24052A2772024-04-30030 April 2024 Issuance of Amendment No. 229 Regarding Revision of Technical Specification 3.8.1, AC Sources - Operating, Surveillance Requirement SR 3.8.1.12 IR 05000341/20240012024-04-30030 April 2024 Integrated Inspection Report 05000341/2024001 ML24107B1372024-04-18018 April 2024 Confirmation of Initial License Reexamination June 2024 ML24101A3732024-04-11011 April 2024 Request for Information for NRC Commercial Grade Dedication Inspection: Inspection Report 05000341/2024012 ML24100A8422024-04-0909 April 2024 Request for Information for an NRC Post-Approval Site Inspection for License Renewal Inspection: Inspection Report 05000341/2024013 IR 05000341/20234022024-04-0808 April 2024 Reissue - Fermi Power Plant, Unit 2 - Cyber Security Inspection Report 05000341/2023402 (Public) ML24088A2162024-04-0404 April 2024 Change in Estimated Review Schedule and Level of Effort for License Amendment Request for Risk Informed Approach to ECCS Strainer Performance ML24086A5732024-04-0101 April 2024 Response to Disputed Non-Cited Violation Documents in Fermi Power Plant, Unit 2 - Cyber Security Inspection Report 05000341/2023402-01 Withdrawal of Non-Cited Violation (Public) IR 05000341/20243012024-04-0101 April 2024 NRC Initial License Examination Report 05000341/2024301 IR 05000341/20244012024-03-22022 March 2024 – Security Baseline Inspection Report 05000341/2024401 (Public) IR 05000341/20240112024-03-0808 March 2024 Nbsp;Safety Conscious Work Environment Issue of Concern Follow-up Inspection Report 05000341/2024011 ML24002B1812024-03-0404 March 2024 Issuance of Amendment No. 228 Regarding Revision of Non-Conservative Technical Specification 3.4.5, RCS Pressure Isolation Valve (PIV) Leakage IR 05000341/20230062024-02-28028 February 2024 Annual Assessment Letter for Fermi Power Plant, Unit 2 (Report 05000341/2023006) ML24019A1842024-02-16016 February 2024 Exemption from Select Requirements of 10 CFR Part 73 Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting ML24045A1602024-02-14014 February 2024 Operator Licensing Examination Approval - Fermi Power Plant, February 2024 IR 05000341/20230042024-02-0505 February 2024 Integrated Inspection Report 05000341/2023004 ML23310A1492023-12-0808 December 2023 Issuance of Amendment No. 227 Regarding Revision of Technical Specification 3.8.1, AC Sources - Operating, Emergency Diesel Generator Voltage and Frequency Surveillance Requirements IR 05000341/20230102023-12-0808 December 2023 Nbsp;Biennial Problem Identification and Resolution Inspection Report 05000341/2023010 ML23341A1852023-12-0808 December 2023 Acknowledgement of Response to NRC Inspection Report 05000341/2023402 and Disputed Non-Cited Violation IR 05000016/20230012023-12-0101 December 2023 NRC Inspection Report No. 050-00016/2023-001 (Drss) - Enrico Fermi Atomic Power Plant, Unit 1 ML23334A1902023-12-0101 December 2023 Request for Information for an NRC Post-Approval Site Inspection for License Renewal Inspection Report 05000341/2024010 ML23335A0062023-12-0101 December 2023 Notification of NRC Baseline Inspection and Request for Information; Inspection Report 05000341/2024002 IR 05000341/20230032023-11-0707 November 2023 Integrated Inspection Report 05000341/2023003 and 07200071/2023001 ML23297A0512023-10-30030 October 2023 Issuance of Amendment No. 226 Regarding Revision of Technical Specifications 3.8.1, AC Sources - Operating (Exigent Circumstances) 2024-09-09
[Table view] Category:Request for Additional Information (RAI)
MONTHYEARML24141A2072024-05-20020 May 2024 Plant—Information Request to Support the NRC Annual Baseline Emergency Action Level and Emergency Plan Changes Inspection ML24080A3912024-03-20020 March 2024 NRR E-mail Capture - Fermi 2 - Request for Additional Information for License Amendment Request Regarding Risk-Informed ECCS Strainer Performance Evaluation (Final) (L-2023-LLA-0092) ML24080A3902024-03-19019 March 2024 NRR E-mail Capture - (External_Sender) Fermi 2 - Request for Additional Information for License Amendment Request Regarding Risk-Informed ECCS Strainer Performance Evaluation (DRAFT)(L-2023-LLA-0092) ML23335A0062023-12-0101 December 2023 Notification of NRC Baseline Inspection and Request for Information; Inspection Report 05000341/2024002 ML23276A0052023-10-0202 October 2023 NRR E-mail Capture - (External_Sender) Fermi EDG Crankcase Trip LAR RAI Response ML23250A2732023-09-0707 September 2023 NRR E-mail Capture - Fermi 2 - Request for Additional Information for License Amendment Request to Revise TS 3.8.1, AC Sources - Operating, Surveillance Requirement 3.8.1.12 ML23241B0162023-08-24024 August 2023 Exigent License Amendment Request for Additional Information RAI-12 (EPID L-2023-LLA-0112) (Email) ML23235A1822023-08-23023 August 2023 Exigent LAR Request for Additional Information ML23115A1452023-04-25025 April 2023 NRR E-mail Capture - Fermi 2 - Request for Additional Information for Changes to TS 3.8.1, AC Sources - Operating ML22362A0712022-12-28028 December 2022 Notification of NRC Fire Protection Team Inspection Request for Information Inspection Report Numbers 05000341/2023010 ML22130A5162022-05-12012 May 2022 Information Request to Support the NRC Annual Baseline Emergency Action Level and Emergency Plan Changes Inspection ML21214A1492021-08-0202 August 2021 License Amendment Request: Request for Additional Information ML21126A0532021-05-0404 May 2021 NRR E-mail Capture - Fermi 2 - Request for Additional Information for Revised Relief Request RR A-39 ML21099A1012021-04-0909 April 2021 Information Request to Support Upcoming Temporary Instruction 2515/194 Inspection; Inspection Report 05000341/2021013 ML21078A4832021-03-19019 March 2021 Information Request for NRC Triennial Evaluations of Changes, Tests, and Experiments (50.59) Baseline Inspection; Inspection Report 05000341/2021011 ML20303A2872020-10-29029 October 2020 Notification of NRC Design Bases Assurance Inspection (Programs) and Initial Request for Information: Inspection Report 05000341/2021012 ML20239A9682020-08-12012 August 2020 NRR E-mail Capture - Fermi 2 LAR: RAI for Revision to Technical Specifications to Change the Surveillance Intervals to Accommodate a 24-Month Fuel Cycle ML20133K0502020-05-14014 May 2020 Information Request to Support the NRC Annual Baseline Emergency Action Level and Emergency Plan Changes Inspection ML20079J0972020-03-19019 March 2020 Notification of NRC Fire Protection Team Inspection Request for Information; Inspection Report Number 05000341/2020011 ML18206B0632018-07-25025 July 2018 NRR E-mail Capture - Draft Request for Additional Information Regarding Fermi LAR to Adopt TSTF -542 ML18129A3992018-05-0909 May 2018 NRR E-mail Capture - Request for Additional Information Regarding Fermi LAR to Adopt TSTF - 542 ML18065A3962018-03-0606 March 2018 NRR E-mail Capture - Request for Additional Information Regarding Fermi LAR to Adopt TSTF-542 ML18029A1262018-01-29029 January 2018 NRR E-mail Capture - Fermi 2 LAR to Revise TS to Eliminate MSLRM Reactor Trip and PCIS Group 1 Isolation Functions ML18022A9452018-01-22022 January 2018 NRR E-mail Capture - Fermi RAI for LAR Regarding TS to Eliminate Steam Line Radiation ML18022A1092018-01-19019 January 2018 NRR E-mail Capture - Request for Additional Information Regarding Fermi RR-A37 ML17346A8012017-12-12012 December 2017 NRR E-mail Capture - Final Fermi RAI for LAR Regarding Uhc (TS 3.7.2) ML17157B6702017-06-0505 June 2017 Notification of NRC Triennial Fire Protection Baseline Inspection Request for Information 05000341/2017012 ML17087A4572017-03-28028 March 2017 NRR E-mail Capture - RAI for Fermi 2 - LAR Regarding the Availability of HPCI and Rici at Low Pressure Conditions ML16357A1152016-12-22022 December 2016 Notification of NRC Baseline Inspection and Request for Information (Jvb) ML16188A1922016-07-0707 July 2016 Request for Additional Information on Severe Accident Mitigation Alternatives for Review of License Renewal Application Environmental Review ML16125A1742016-05-0303 May 2016 Request for Additional Information - Alternative Request PRR-007, Revision 1 ML16090A1032016-03-29029 March 2016 Ltr. 03/29/16 Fermi Power Plant - Notification of an NRC Triennial Heat Sink Performance Inspection and Request for Information Inspection Report 05000341/2016002 (Maj) ML16011A0442016-01-14014 January 2016 Request for Additional Information for the Review of the Fermi 2 License Renewal Application - Set 38 ML15237A0442015-09-0101 September 2015 Request for Additional Information for the Review of the Fermi, Unit 2, License Renewal Application-Set 37 ML15231A1612015-08-17017 August 2015 Ltr. 08/17/15 Fermi Power Plant - Notification of NRC Inspection and Request for Information (Txb) ML15149A3642015-05-28028 May 2015 Information Request to Support NRC Annual Baseline Emergency Action Level and Emergency Plan Changes Inspection (Mxg) ML15134A0722015-05-21021 May 2015 Request for Additional Information for the Review of the Fermi, Unit 2 License Renewal Application-Set 35 ML15139A4612015-05-20020 May 2015 Request for Additional Information for the Review of the Fermi 2 License Renewal Application-Set 33 ML15132A4272015-05-18018 May 2015 March 27, 2015 Summary of Telephone Conference Call Held Between the U.S. NRC and DTE Electric Company Concerning Requests for Additional Information Pertaining to the Severe Accident Mitigation Alternatives Review of the Fermi, Unit 2 ML15126A0042015-05-15015 May 2015 Requests for Additional Information for the Review of the Fermi 2 License Renewal Application-Set 34 ML15114A3692015-05-0606 May 2015 Request for Additional Information Associated with Near-Term Task Force Recommendation 2.1, Seismic Hazard and Screening Report ML15099A0162015-04-22022 April 2015 Requests for Additional Information for the Review of the Fermi 2 License Renewal Application Set 32 ML15092A9452015-04-0909 April 2015 Request for Additional Information for the Environmental Review of the Fermi 2 License Renewal Application - Severe Accident Mitigation Alternatives ML15085A5132015-04-0202 April 2015 Request for Additional Information for the Review of the Fermi 2 License Renewal Application - Set 31 ML15077A1082015-03-26026 March 2015 Requests for Additional Information for the Review of the Fermi 2 License Renewal Application - Set 27 ML15082A0462015-03-26026 March 2015 Requests for Additional Information for the Review of the Fermi, Unit 2 License Renewal Application - Set 29, ML15078A3372015-03-26026 March 2015 Request for Additional Information for the Review of the Fermi, Unit 2 License Renewal Application - Set 28 ML15072A0812015-03-19019 March 2015 Request for Additional Information for the Review of the Fermi 2 License Renewal Application - Set 25 ML15051A4202015-03-13013 March 2015 Request for Additional Information for the Review of the Fermi 2 License Renewal Application - Set 23 ML15062A3362015-03-13013 March 2015 Request for Additional Information for the Review of the Fermi 2 License Renewal Application - Set 26 2024-05-20
[Table view] |
Text
January 7, 2008 Mr. Jack M. Davis Senior Vice President and Chief Nuclear Officer Detroit Edison Company Fermi 2 - 210 NOC 6400 North Dixie Highway Newport, MI 48166
SUBJECT:
FERMI 2 - REQUEST FOR ADDITIONAL INFORMATION RELATED TO PROPOSED REVISION TO THE RADIOLOGICAL EMERGENCY RESPONSE PREPAREDNESS PLAN (TAC NO. MD5611)
Dear Mr. Davis:
By letter to the Nuclear Regulatory Commission (NRC) dated May 14, 2007, Detroit Edison Company submitted a request to revise the Radiological Emergency Response Preparedness Plan, for Fermi 2.
The NRC staff is reviewing your submittal and has determined that additional information is required to complete the review. The specific information requested is addressed in the enclosure to this letter. During a discussion with your staff on January 7, 2008, it was agreed that you would provide a response within 30 days from the date of this letter.
The NRC staff considers that timely responses to requests for additional information help ensure sufficient time is available for staff review and contribute toward the NRC=s goal of efficient and effective use of staff resources. If circumstances result in the need to revise the requested response date, please contact me at (301) 415-4093.
Sincerely,
/RA/
Adrian Muniz, Project Manager Plant Licensing Branch III-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-341
Enclosure:
Request for Additional Information cc w/encl: See next page
Mr. Jack M. Davis Senior Vice President and Chief Nuclear Officer Detroit Edison Company Fermi 2 - 210 NOC 6400 North Dixie Highway Newport, MI 48166
SUBJECT:
FERMI 2 - REQUEST FOR ADDITIONAL INFORMATION RELATED TO PROPOSED REVISION TO THE RADIOLOGICAL EMERGENCY RESPONSE PREPAREDNESS PLAN (TAC NO. MD5611)
Dear Mr. Davis:
By letter to the Nuclear Regulatory Commission (NRC) dated May 14, 2007, Detroit Edison Company submitted a request to revise the Radiological Emergency Response Preparedness Plan, for Fermi 2.
The NRC staff is reviewing your submittal and has determined that additional information is required to complete the review. The specific information requested is addressed in the enclosure to this letter. During a discussion with your staff on January 7, 2008, it was agreed that you would provide a response within 30 days from the date of this letter.
The NRC staff considers that timely responses to requests for additional information help ensure sufficient time is available for staff review and contribute toward the NRC=s goal of efficient and effective use of staff resources. If circumstances result in the need to revise the requested response date, please contact me at (301) 415-4093.
Sincerely,
/RA/
Adrian Muniz, Project Manager Plant Licensing Branch III-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-341
Enclosure:
Request for Additional Information cc w/encl: See next page DISTRIBUTION:
PUBLIC LPL3-1 R/F RidsNrrDorlLpl3-1 RidsNRRPMAMuniz RidsNrrLATHarris RidsAcrsAcnwMailCenter RidsOgcRp RidsRgn3MailCenter RidsNrrDorlDpr K. Williams, NSIR ADAMS Accession Number: ML073120503 OFFICE LPL3-1/PM LPL3-1/LA NSIR/DPR/DDEP/LIB/BC LPL3-1/(A)BC NAME AMuniz THarris KWilliams CMunson DATE 01/7/08 01/7/08 01/7/08 01/7/08 OFFICIAL RECORD COPY
Fermi 2 cc:
David G. Pettinari Mr. Joseph H. Plona Legal Department Vice President - Nuclear Generation 688 WCB Detroit Edison Company Detroit Edison Company Fermi 2 - 210 NOC 2000 2nd Avenue 6400 North Dixie Highway Detroit, MI 48226-1279 Newport, MI 48166 Michigan Department of Environmental Quality Waste and Hazardous Materials Division Radiological Protection and Medical Waste Section Nuclear Facilities Unit Constitution Hall, Lower-Level North 525 West Allegan Street P.O. Box 30241 Lansing, MI 48909-7741 U.S. Nuclear Regulatory Commission Resident Inspector's Office 6450 N Dixie Highway Newport, MI 48166 Mr. M. V. Yudasz, Jr., Director Monroe County Emergency Management Division 965 South Raisinville Road Monroe, MI 48161 Ronald W. Gaston Manager, Nuclear Licensing Detroit Edison Company Fermi 2 - 200 TAC 6400 North Dixie Highway Newport, MI 48166 Supervisor - Electric Operators Michigan Public Service Commission P.O. Box 30221 Lansing, MI 48909 Wayne County Emergency Management Division 10250 Middlebelt Road Detroit, MI 48242
REQUEST FOR ADDITIONAL INFORMATION FERMI 2 DOCKET NO. 50-341 In reviewing the Detroit Edison Company=s (DeCo) submittal dated May 14, 2007 (Agencywide Documents Access and Management System Accession No. ML071430159), related to the proposed revision of the Fermi 2 (Fermi) Radiological Emergency Response Preparedness (RERP) Plan, the Nuclear Regulatory Commission (NRC) staff has determined that the following information is needed in order to complete its review:
- 1. Proposal 1 would eliminate the requirement for the Station Nuclear Engineer (previously the Reactor Engineer) from reporting to the site within 30 minutes. Part of the justification for this proposed change states that Since the original approval of the RERP plan, training has greatly improved the Shift Technical Advisors [STA] knowledge and capabilities. The STAs expertise allows for the Station Nuclear Engineer/Reactor Engineer requirement to be eliminated from the ERO [Emergency Response Organization] staffing. What are the training and qualification requirements for the Station Nuclear Engineer/Reactor Engineer position and how do these requirements compare to those for the STA position?
- 2. Proposal 1 states in part that The STA can adequately respond to any accident to assure reactor safety until relieved by the Engineering Staff in the TSC [Technical Support Center]. By eliminating the 30-minute reporting requirement for the Station Nuclear Engineer, TSC Engineering Staff may not be available for up to 60 minutes following an Alert or higher declaration. What tasks are performed by the STA position during an emergency in addition to those previously performed by the Station Nuclear Engineer/Reactor Engineer? What was the basis for determining that the STA would be able to effectively perform these tasks for any accident until relieved by TSC Engineering Staff?
- 3. Proposal 3 states that one of two Support Engineers would be eliminated as a 60-minute responder. However, in the Fermi submittal identified as NRC-07-0009, Enclosure 1, Table 2, two Support Engineers are shown as of Revision 3A of the Fermi RERP and only one Support Engineer is shown as of Revision 32, indicating that this change was made in a previous revision to the emergency plan. Additional information is requested to clarify when this change occurred and the basis for the change at the time it was originally made.
- 4. Proposal 3 would provide for one Nuclear Safety Advisor (or Technical Engineer) and one Support Engineer to be available in the TSC within 60 minutes. Describe in more detail how typical technical support functions, such as electrical and mechanical engineering support, are addressed by TSC staffing under the current Fermi RERP.
How would these same technical support functions be addressed under Proposal 3?
ENCLOSURE
- 5. Proposal 4 would eliminate the Emergency Operations Facility (EOF) Coordinator position, which is not an augmented ERO position. However, in the discussion of Proposal 4 it states that the EOF Coordinator position was eliminated in March 1988.
Additional information is requested to clarify the basis for the change at the time it was originally made and why NRC approval is being requested or is necessary now.
- 6. Proposal 4 states that [T]he EOF Coordinator was identified as the person who directed activities in the EOF and that this function is actually performed by the Emergency Officer. The Fermi RERP, Table B-2, Revision 3A, indicates that the EOF Coordinator performed other functions as well, including notifying government emergency response agencies and recommending protective measures to off-site emergency response organizations based on dose assessment. Additional information is requested to clarify how the other tasks that were performed by the EOF Coordinator have been addressed.