ML22130A516

From kanterella
Jump to navigation Jump to search
Information Request to Support the NRC Annual Baseline Emergency Action Level and Emergency Plan Changes Inspection
ML22130A516
Person / Time
Site: Fermi DTE Energy icon.png
Issue date: 05/12/2022
From: Patricia Pelke
NRC/RGN-III/DRS/OLB
To: Peter Dietrich
DTE Electric Company
References
Download: ML22130A516 (4)


Text

May 11, 2022 Mr. Peter Dietrich Senior VP and Chief Nuclear Officer DTE Electric Company Fermi 2 - 260 TAC 6400 North Dixie Highway Newport, MI 48166

SUBJECT:

FERMI POWER PLANTINFORMATION REQUEST TO SUPPORT THE NRC ANNUAL BASELINE EMERGENCY ACTION LEVEL AND EMERGENCY PLAN CHANGES INSPECTION

Dear Mr. Dietrich:

This letter is to request information to support the Emergency Action Level and Emergency Plan change inspection that will be conducted during the third and fourth quarters of 2022. This inspection will be performed as an in-office review and in accordance with the U.S. Nuclear Regulatory Commission (NRC) Baseline Inspection Procedure 71114.04. The list of requested documents needed from your staff for this inspection is enclosed. We are requesting that these documents are for the time period specified in the list, as applicable.

The point of contact for this request is Michelle Garza, Region III Emergency Preparedness Inspector, and can be reached at 630-829-9719. We will keep in close communications with the Emergency Preparedness staff at your site regarding this request and the inspection when performed.

This letter does not contain new or amended information collection requirements subject to the Paperwork Reduction Act of 1995 (44 U.S.C. 3501 et seq.). Existing information collection requirements were approved by the Office of Management and Budget, Control Number 3150-0011. The NRC may not conduct or sponsor, and a person is not required to respond to, a request for information or an information collection requirement unless the requesting document displays a currently valid Office of Management and Budget Control Number.

P. Dietrich This letter and its enclosure will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with Title 10 of the Code of Federal Regulations, Part 2.390, Public Inspections, Exemptions, Requests for Withholding.

Sincerely, Signed by Pelke, Patricia on 05/11/22 Patricia Pelke, Chief Operations Branch Division of Reactor Safety Docket No. 50-341 License No. NPF-43

Enclosure:

EAL and Emergency Plan Changes Inspection Document Request cc: Distribution via LISTSERV

P. Dietrich Letter to Peter Dietrich from Patricia Pelke dated May 11, 2022.

SUBJECT:

FERMI POWER PLANTINFORMATION REQUEST TO SUPPORT THE NRC ANNUAL BASELINE EMERGENCY ACTION LEVEL AND EMERGENCY PLAN CHANGES INSPECTION DISTRIBUTION:

Jessie Quichocho Robert Orlikowski RidsNrrDorlLpl3 RidsNrrPMFermi2 Resource RidsNrrDroIrib Resource John Giessner Mohammed Shuaibi Shelbie Lewman Allan Barker DRPIII DRSIII ADAMS Accession Number: ML22130A516 OFFICE RIII RIII NAME MGarza:mb PPelke DATE 05/10/2022 05/11/2022 OFFICIAL RECORD COPY

EAL AND EMERGENCY PLAN CHANGES INSPECTION DOCUMENT REQUEST Please have the documents uploaded to a share file or web-based platform for our inspectors to access no later than July 15, 2022. Contact Michelle Garza with any questions about the electronic submittal.

Documents:

1. Current revision of the Emergency Plan
2. Current Emergency Action Level (EAL) scheme
3. Most recent Safety Evaluation Report for the Emergency Plan and EALs
4. On Shift Staffing Analysis baseline
5. Most recent Evacuation Time Estimate
6. Governing site document for Title 10 of the Code of Federal Regulations (CFR),

Part 50.54(q) evaluation process

7. Title 10 CFR 50.54(q) evaluator training program and qualification records
8. Title 10 CFR 50.54(q) screenings and evaluations for Emergency Plan and EAL changes that were completed between July 1, 2021, and June 30, 2022
9. For each change of the Emergency Plan and EALs, submit the previous revision, proposed revision, and the associated 50.54(q) screening and evaluation (if performed)
10. Corrective Action Program entries related to 50.54(q) screenings, 50.54(q) evaluations, EAL changes and Emergency Plan changes dated between July 1, 2021, and June 30, 2022 Enclosure