IR 05000016/2024001

From kanterella
Jump to navigation Jump to search
Enrico Fermi Atomic Power Plant, Unit 1, NRC Inspection Report 05000016/2024001
ML24306A138
Person / Time
Site: Fermi 
Issue date: 11/01/2024
From: Dave Hills
NRC/RGN-III/DRSS
To: Peter Dietrich
DTE Electric Company
References
IR 2024001
Download: ML24306A138 (1)


Text

SUBJECT:

ENRICO FERMI ATOMIC POWER PLANT, UNIT 1 - NRC INSPECTION REPORT NO. 050-00016/2024-001

Dear Pete Dietrich:

On October 8, 2024, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at Enrico Fermi Atomic Power Plant, Unit 1 (Fermi 1). On October 8, 2024, the NRC inspectors discussed the results of this inspection with Derek Etue, Manager, Operations, and other members of your staff. The results of this inspection are documented in the enclosed report.

During the inspection period, the NRC inspector reviewed the following aspects of onsite activities: safety reviews, design changes and modifications; problem identification and resolution; fire protection; decommissioning performance; occupational radiation exposure; radiological surveys; radioactive waste treatment, effluent, and environmental monitoring; and waste management and transportation. The inspection consisted of an examination of activities at the site as they relate to safety and compliance with the Commissions rules and regulations.

No violations of more than minor safety significance were identified during this inspection.

November 1, 2024 This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with Title 10 of the Code of Federal Regulations (CFR) 2.390, Public Inspections, Exemptions, Requests for Withholding.

Sincerely, David E. Hills, Chief Decommissioning, Reactor, ISFSI HP Branch Division of Radiological Safety and Security Docket No.50-016 License No. DPR-9

Enclosure:

IR No. 05000016/2024001

REGION III==

Docket No:

50-016 License No:

DPR-9 Report No:

05000016/2024001 Licensee:

DTE Electric Company Facility:

Enrico Fermi Atomic Power Plant, Unit 1 Location:

Newport, MI Dates:

November 7, 2023, to October 8, 2024 Inspector:

Peter J Lee, Reactor Inspector (Decom), Ph.D., CHP Approved by:

David E. Hills, Chief Decommissioning, Reactor, ISFSI HP Branch Division of Radiological Safety and Security

EXECUTIVE SUMMARY Enrico Fermi Atomic Power plant, Unit 1 NRC Inspection Report Nos. 05000016/2024001 This U.S. Nuclear Regulatory Commission (NRC) inspection was a routine, announced inspection of decommissioning activities being conducted at the facility. A brief summary of the areas reviewed are described below. Based on the results of the inspection no violations of more than minor safety significance were identified.

Safety Reviews, Design Changes, and Modifications

The inspector determined that licensee had not performed any design changes that warranted a safety evaluation per Title 10 of the Code of Federal Regulations (CFR) 50.59.

Problem Identification and Resolution

Issues were identified by the licensee at appropriate thresholds and entered into the Corrective Action Program (CAP). Issues were screened and prioritized commensurate with safety significance. Licensee evaluations determined the significance of issues and included appropriate remedial corrective actions.

Fire Protection Program at Permanently Shutdown Reactors

The program is inspected by the NRC through the Reactor Oversight Process (ROP) for Unit 2.

Decommissioning Performance and Status Review

The inspectors determined that decommissioning activities were in accordance with the regulations and license requirements.

Occupational Radiation Exposure

The inspector determined that the licensee had not conducted any radiological work that resulted in worker exposures this past year.

Radioactive Waste Treatment, and Effluent and Environmental Monitoring

The liquid and gaseous effluent sampling program was effective at quantifying radioactive effluent releases and the radiological environmental monitoring program (REMP) and groundwater protection initiative (GPI) were implemented in accordance with applicable procedures.

Solid Radioactive Waste Management and Transportation of Radioactive Materials The licensee effectively processed, handled, stored, and transported radioactive material.

Report Details Summary of Facility Status Enrico Fermi Atomic Power Plant, Unit 1 (FERMI 1) is a permanently shut-down and defueled power reactor maintained in a Safe Storage (SAFSTOR) condition. During this inspection period, the licensee continued to maintain Fermi 1 in a passive monitoring SAFSTOR status; therefore, no physical decommissioning activities have been conducted. Since the last NRC inspection of Fermi 1, the licensee continued to conduct the technical specification monitoring surveillances, removal of standing water from the facility, and the groundwater monitoring. This facility is co-located with an operation reactor; thus, inspection activities were focused on program elements not assessed under the reactor oversight process for the operating unit.

1.0 Safety Reviews, Design Changes, and Modifications at Permanently Shutdown Reactors (IP 37801)

1.1 Inspection Scope The purpose of this portion of the inspection was to verify that the licensees safety review process was in accordance with the requirements of 10 CFR 50.59, Changes, tests, and experiments such that license amendments were obtained when required.

1.2 Observations and Findings During the inspection, the inspector confirmed there were no changes to the decommissioning facility that required a safety evaluation according to the provisions of 10 CFR 50.59. This was consistent with the annual report filed by the licensee in June 2024 (ADAMS Accession Number ML24243A019).

No findings of significance were identified.

1.3 Conclusions The licensee had not performed any design changes that warranted a safety evaluation per 10 CFR 50.59.

2.0 Problem Identification and Resolution at Permanently Shutdown Reactors (IP 40801)

2.1 Inspection Scope The purpose of this portion of the inspection was to evaluate:

1) the effectiveness of licensee controls to identify, resolve, and correct issues, 2) the audit and assessment program and 3) management reviews of the safety conscious work environment.

2.2 Observations and Findings The inspector reviewed all issues the licensee entered into the CAP since the last inspection. The inspector reviewed the licensees audit of its semi-annual technical specification monitoring surveillances of Audit 23-0112 conducted from October 30, 2023, through November 01, 2023, and Audit 24-0104 conducted from May 06, 2024, through May 09, 2024. Selected corrective action work orders associated with identified deficiencies were also reviewed. The technical specification monitoring surveillances included weekly and monthly facility inspections, and quarterly radiation surveys. The audits of technical specification monitoring surveillances were appropriately focused in both scope and level of detail, and the licensee initiated appropriate corrective actions to resolve the audit findings.

No findings of significance were identified.

2.3 Conclusions Issues were identified by the licensee at appropriate thresholds and entered into the CAP. Issues were screened and prioritized commensurate with safety significance.

Licensee evaluations determined the significance of issues and included appropriate remedial corrective actions.

3.0 Fire Protection Program at Permanently Shutdown Reactors (IP 64704)

3.1 Inspection Scope The purpose of this portion of the inspection was to evaluate the effectiveness of the fire protection program to ensure adequate protection from fire-induced release of radioactive material.

3.2 Observations and Findings The fire protection program was inspected by the NRCs Reactor Oversight Process (ROP). The licensees fire protection program is documented in the Fermi Integrated Inspection Report (ADAMS Accession Number ML23244A212).

No findings of significance were identified.

3.3 Conclusions This program is inspected by the NRC through the ROP for Unit 2.

4.0 Decommissioning Performance and Status Review (IP 71801)

4.1 Inspection Scope The purpose of this portion of the inspection was to evaluate the status of decommissioning and to verify the decommissioning activities are in accordance with regulatory and license requirements.

4.2 Observations and Findings The inspector performed walkdowns, reviewed documents, and interviewed plant personnel to assess the licensees performance in the following areas:

Weekly and monthly facility inspection, and quarterly radiation surveillance;

The postings and boundaries for contamination control;

Control of the final status survey areas; and

The status of standing water and leaking roof in FARB The general condition of the facility was found to be well maintained and consistent with good housekeeping practices. The postings and boundaries for contamination control were well maintained. Final status survey (FSS) areas were adequately isolated and posted. There were no unexpected radiation readings detected. The radiation readings were consistent with the measurements taken to support the licensees return of Fermi 1 in early 2012 from active decommissioning to a passive monitoring SAFSTOR status (ADAMS Accession Number ML12090A151).

On June 15, 2023, the licensee discovered a partial collapse at the FARB high roof, NE corner. The licensee performed a structural assessment and planned for the roof repairment in this coming fall. The FARB was roped off with safety barriers at all entrances identifying the roof hazard.

The only standing water left was in the sumps of the maintenance pit from the FARB. As described in Section 6.2, the licensee had pumped the water to the sanitary sewer system due to no detectable licensed materials identified.

No findings of significance were identified.

4.3 Conclusions The inspectors determined that decommissioning activities were in accordance with the regulations and license requirements.

5.0 Occupational Radiation Exposure at Permanently Shutdown Reactors (IP 83750)

5.1 Inspection Scope The purpose of this portion of the inspection was to evaluate the effectiveness of the licensees occupational radiation safety program to adequately protect worker health and safety from exposure to radiation or radioactive material.

5.2 Observations and Findings Based on the discussion with the licensee, there was no radiological work associated with worker exposures this past year. This was consistent with the annual report filed by the licensee in June 2024 (ADAMS Accession Number ML24243A019).

No findings of significance were identified.

5.3 Conclusions The inspector determined that the licensee had not conducted any radiological work that resulted in worker exposures this past year.

6.0 Radioactive Waste Treatment, and Effluent and Environmental Monitoring IP 84750)

6.1 Inspection Scope The purpose of this portion of the inspection was to evaluate the effectiveness of the licensees liquid and gaseous effluent sampling program to quantify radioactive effluent releases and to verify that the radiological environmental monitoring program and groundwater protection initiative were effectively implemented.

6.2 Observations and Findings The inspector performed walkdowns, reviewed documents, and interviewed plant personnel to assess the licensees performance in the following areas:

Analyses of ground water from Fermi1 active sumps;

Analyses of ground water from Fermi1 monitoring wells;

Analyses of standing water from the FARB; and

Analyses of water recirculated through filter from the hot sump.

As noted in Sections 4.2, the licensee had removed the standing water from the maintenance pit sumps in the FARB, pumping it into the sanitary sewer system. The inspector reviewed analytical sampling results associated with those releases, as well as those from pertinent sumps to ensure no licensed materials were released. Fermi 1 sumps were sampled semi-annually in accordance with Surveillance Performance Form, Event FI 98. The inspector also reviewed the groundwater analytical sampling results from monitoring wells. Based on the review of the analytical sampling results, the inspector determined that only natural occurring radioactive materials were identified.

The groundwater sampling result was consistent with the annual report filed by the licensee in June 2024 (ADAMS Accession Number ML24243A019).

The licensee had recirculated the water from the hot sump through filters until no licensed materials identified then discharged water from the hot sump to the sumps of the maintenance pit from the FARB. The inspector reviewed the sampling results and determined that no licensed materials were identified in the water of hot sump.

No findings of significance were identified.

6.3 Conclusions The liquid and gaseous effluent sampling program was effective at quantifying radioactive effluent releases and the REMP and GPI were implemented in accordance with applicable procedures.

7.0 Solid Radioactive Waste Management and Transportation of Radioactive Materials

(IP 86750)

7.1 Inspection Scope The purpose of this portion of the inspection was to evaluate the effectiveness of the licensees programs for processing, handling, storage, and transportation of radioactive material.

7.2 Observations and Findings During the inspection, the inspector found that radioactive material was controlled in accordance with requirements. The inspector interviewed plant personnel and determined that no shipments of radioactive material occurred since the last inspection.

This was consistent with the annual report filed by the licensee in June 2024 (ADAMS Accession Number ML24243A019).

No findings of significance were identified.

7.3 Conclusions The licensee effectively processed, handled, stored, and transported radioactive material.

8.0 Exit Meeting The inspector presented the inspection results to Derek Etue and the other members of the Fermi1 staff at the conclusion of the inspection on October 8, 2024. The licensee acknowledged the results presented and did not identify any of the information discussed as proprietary.

ATTACHMENT: SUPPLEMENTAL INFORMATION

SUPPLEMENTAL INFORMATION PARTIAL LIST OF PERSONS CONTACTED

  • Derek Etue - Manager, Operations
  • Patrick McMahon - Supervisor, Nuclear Fire Marshal and Operations Support
  • Eric Frank - Manager, Nuclear Licensing
  • Greg Anderson - Licensing
  • Present at the October 8, 2024, exit meeting.

INSPECTION PROCEDURES (IPs) USED IP 37801 Safety Reviews, Design Changes, and Modifications at Permanently Shutdown Reactors IP 40801 Self-Assessment, Auditing, and Corrective Action at Permanently Shutdown Reactors IP 64704 Fire Protection Program at Permanently Shutdown Reactors IP 71801 Decommissioning Performance and Status Reviews at Permanently Shutdown Plants IP 83750 Occupational Radiation Exposure IP 84750 Radioactive Waste Treatment, and Effluent and Environmental Monitoring IP 86750 Solid Radioactive Waste Management and Transportation of Radioactive Materials ITEMS OPENED, CLOSED, AND DISCUSSED Opened Type Summary None Closed Type Summary None DOCUMENTS REVIEWED Licensee documents reviewed and utilized during the course of this inspection are specifically identified in the Report Details

LIST OF ACRONYMS USED ADAMS Agencywide Document Access and Management System CAP Corrective Action Program CFR Code of Federal Regulations DRSS Division of Nuclear Radiological Safety and Security FSS Final Status Survey FARB Fuel and Repair Building IP Inspection Procedure NRC U.S. Nuclear Regulatory Commission SAFSTOR Safe Storage TS Technical Specification