ONS-2014-040, 2013 Annual Commitment Change Report

From kanterella
Revision as of 06:06, 4 November 2019 by StriderTol (talk | contribs) (Created page by program invented by StriderTol)
(diff) ← Older revision | Latest revision (diff) | Newer revision → (diff)
Jump to navigation Jump to search
2013 Annual Commitment Change Report
ML14092A363
Person / Time
Site: Oconee  Duke Energy icon.png
Issue date: 03/31/2014
From: Batson S
Duke Energy Corp
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
ONS-2014-040
Download: ML14092A363 (3)


Text

IUKE Scott L. Batson ENERGY E N ERGY.Oconee Vice President Nuclear Station Duke Energy ONO1VP I 7800 Rochester Hwy Seneca, SC 29672 o: 864.873.3274 t 864.873.4208 Scott.Batson@duke-energy.com ONS-2014-040 March 31, 2014 Document Control Desk U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

Subject:

Duke Energy LLC Oconee Nuclear Station Docket Nos. 50-269, 50-270 and 50-287 2013 Annual Commitment Change Report Attached is a summary report of commitment changes for Oconee Nuclear Station completed during the 2013 calendar year. These changes were made per the guidance defined in NEI 99-04, "Guidelines for Managing NRC Commitments," and have no adverse effect on compliance with NRC rules or regulations.

Should there be any questions concerning this report please contact Judy E. Smith, Oconee Regulatory Affairs, at 864-873-4309.

Sincerely, Scott L. Batson Vice President Oconee Nuclear Station Attachment coo www.duke-energy.com

U. S. Nuclear Regulatory Commission March 31, 2014 Page 2 xc:

Mr. Victor McCree, Regional Administrator U.S. Nuclear Regulatory Commission, Region II Marquis One Tower 245 Peachtree Center Ave., NE, Suite 1200 Atlanta, GA 30303-1257 Mr. Eddy Crowe NRC Senior Resident Inspector Oconee Nuclear Station Mr. Richard Guzman Senior Project Manager U.S. Nuclear Regulatory Commission 11555 Rockville Pike Mail Stop O-8C2 Rockville, MD 20852

Attachment Oconee Nuclear Station Commitment Change Summary Docket Nos. 50-269, 50-270 and 50-287 NUMBER SOURCE ORIGINAL COMMITMENT MODIFIED COMMITMENT DOCUMENT 2013-0-002 Selected License Reactor Coolant System (RCS) Delete Oconee Selected Commitment (SLC) unidentified leakage shall be License Commitment (SLC) 16.5.6 limited to: 16.5.6 because the mitigation

a. < 0.1 gpm above previous daily of the Pressurizer Nozzle reading butt welds is complete.
b. < 0.25 gpm above baseline value APPLICABILITY:

Applicable on Units 2 and 3 only until mitigation of the Pressurizer Nozzle butt welds is complete.

MODES 1, 2, 3, and 4.