Additional Information Regarding License Amendment Request for Temporary Completion Time for One Keowee Hydro Unit Inoperable for Generator Stator Replacement, License Amendment Request No. 2015-08, Supplement 2
ML17159A526
Person / Time
Site: Oconee  Duke Energy icon.png
Issue date: 06/01/2017
From: Teresa Ray
Duke Energy Carolinas
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
ONS-2017-042
Download: ML17159A526 (6)


Text

el_"-) DUKE *.

~ ENERGY Thomas D:Ray Vice President Oconee Nuclear Station Duke Energy ON01 VP I 7800 Rochester Hwy Seneca, SC 29672 o: 864.873.3274 ONS-2017-042 10 CFR 50.90 f. 864.873.4208 Tom.Ray@duke-energy.com June1,2017 ATIN: Document Control Desk U.S. Nuclear Regulatory Commission Washington, DC 20555-0001 Duke Energy Carolinas, LLC Oconee Nuclear Station (ONS), Units 1, 2, and 3 Docket Numbers 50-269, 50-270, and 50-287 Renewed Operating Licenses DPR-38, DPR-47, and DPR-55

Subject:

Additional Information Regarding License Amendment Request for Temporary Completion Time for One Keowee Hydro Unit Inoperable for Generator Stator Replacement License Amendment Request No. 2015-08, Supplement 2

Reference:

Duke Energy Carolinas, LLC. (Duke Energy) letter to the U.S. Nuclear Regulatory Commission (NRC), "License Amendment Request for a Temporary Technical Specification Change to Add a Required Action Completion Time for One Keowee Hydro Unit Inoperable.for Generator Stator Replacement, License Amendment Request No. 2015-08," dated February 26, 2016.

On February 26, 2016, Duke Energy Carolinas, LLC (Duke Energy) submitted the referenced License Amendment Request (LAR). Duke Energy advised the Nuclear Regulatory Commission (NRC) Project Manager on May 23, 2017, of an inadvertent omission from one of the Technical Specification (TS) marked-up and retyped pages associated with that change.

Specifically, proposed Note 3 to Required Action (RA) C.2.2.5 requires administratively verifying the Standby Shutdown Facility (SSF), Protected Service Water (PSW), and Emergency Feedwater (EFW) Systems are operable prior to entering the extended Completion Time. Note 3 was correctly described in Enclosure 1 of the LAR; however, the TS marked-up page and .

corresponding TS retyped page in Attachments 1 and 2 of the LAR, did not include "PSW" in the Note. The NRC Project Manager requested we supplement the LAR to provide corrected pages.

The corrected TS marked-up and retyped pages are contained in the attachment to this letter.

These two pages replace the corresponding marked-up page and retyped page in Attachments 1 and 2 of the LAR. Duke Energy reviewed the No Significant Hazards Consideration and determined it is not affected by this change.

There are no regulatory commitments made in this submittal. A copy of this LAR supplement is being transmitted to the State of South Carolina in accordance with 10 CFR 50.91 requirements.

License Amendment Request No. 2015-08, Supplement 2 Page 2 June 1, 2017 Inquiries on this LAR supplement should be directed to Boyd Shingleton, ONS Regulatory Affairs Group, at (864) 873-4716.

I declare under penalty of perjury that the foregoing is true and correct. Executed on June1,2017.

Thomas D. Ray Vice President Oconee Nuclear Station

Attachment:

Corrected Technical Specification Marked-Up Page, and Retyped Page

License Amendment Request No. 2015-08, Supplement 2 Page 3 June1,2017 cc w

Attachment:

Ms. Catherine Haney, Administrator, Region II U.S. Nuclear Regulatory Commission Marquis One Tower 245 Peachtree Center Ave., NE, Suite 1200 Atlanta, GA 30303-1257 Ms. Audry Klett, Project Manager (ONS)

(by electronic mail only)

Office of Nuclear Reactor Regulation U.S. Nuclear Regulatory Commission Mail Stop 0-8G9A 11555 Rockville Pike Rockville, Maryland 20852 Mr. Eddy Crowe NRG' Senior Resident Inspector Oconee Nuclear Station Ms. Susan E. Jenkins, Manager, (by electronic mail only: jenkinse@dhec.sc.gov)

Infectious and Radioactive Waste Management, Bureau of Land and Waste Management Department of Health & Environmental Control 2600 Bull Street Columbia, SC 29201

License Amendment Request No. 2015-08, Supplement 2

.*June 1, 2017 ATTACHMENT CORRECTED TECHNICAL SPECIFICATION MARKED-UP PAGE AND RETYPED PAGE

AC Sources - Operating 3.8.1 ACTIONS CONDITION REQUIRED ACTION COMPLETION TIME C. (continued) AND


NOTE------------

1. No di~cretionary maintenance or testing allowed on SSF, FWand PSW, 1--11--_.;...e-ss-e"'""'ntial AC Power Systems.
2. Only applicable one time for each KHU due to eneratod field)

GG1e--Rewi~work and September 30, 2021 administratively stator replacement verified OPERABLE prior to entering the extended Completion

,PSW, Time.

55 D. KHU or its required D.1 Perform SR 3.8.1.4 for 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br /> if not performed underground power OPERABLE KHU. in previous 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> path inoperable.

D.2 Energize either 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> standby bus from LCT via isolated power AND path.

1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br /> from subsequent discovery of deenergized required standby bus (continued)

OCONEE UNITS 1, 2, & 3 3.8.1-6 Amendment Nos. 383, 385, & 384

AC Sources - Operating 3.8.1 ACTIONS CONDITION REQUIRED ACTION COMPLETION TIME C. (continued) AND


NOTE------------

1. No discretionary maintenance or testing allowed on SSF, PSW, EFW and essential AC Power Systems.
2. Only applicable one time for each KHU due to generator I stator replacement work and expires on September 30, 2021.
3. Only applicable if the SSF, PSW, and EFW are administratively

' ' verified OPERABLE prior to entering the extended Completion Time.

55 days from initial inoperability when Condition due to an inoperable KHU to perform generator stator replacement work D. KHU or its required D. 1 Perform SR 3.8.1.4 for 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br /> if not performed underground power OPERABLE KHU. in previous 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> path inoperable.

AND D.2 Energize either 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> standby bus from LCT via isolated power AND path.

1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br /> from subsequent discovery of deenergized required standby bus (continued)

OCONEE UNITS 1, 2, & 3 3.8.1-6 Amendment Nos. xxx, xxx, & xxx