MONTHYEARML24277A1012024-10-0303 October 2024 Closure of Interim Report of a Potential Deviation or Failure to Comply Associated with Bentley Systems Incorporated Autopipe Software ML24241A1682024-09-23023 September 2024 Transmittal Letter Amendment No. 13 to Materials License No. Special Nuclear Material-2506 for the Prairie Island Independent Spent Fuel Storage Installation 05000282/LER-2024-001, Auxiliary Building Special Ventilation System Inoperable During Movement of Irradiated Fuel Assemblies2024-09-16016 September 2024 Auxiliary Building Special Ventilation System Inoperable During Movement of Irradiated Fuel Assemblies IR 05000282/20243012024-09-13013 September 2024 NRC Initial License Examination Report 05000282/2024301 and 05000306/2024301 IR 05000282/20240052024-08-28028 August 2024 Updated Inspection Plan and Assessment Follow-Up Letter for Prairie Island Nuclear Generating Plant, Units 1 and 2 (Report 05000282/2024005 and 05000306/2024005) L-PI-24-040, Post-Submittal Package Letter2024-08-23023 August 2024 Post-Submittal Package Letter IR 05000282/20245012024-08-0505 August 2024 Emergency Preparedness Inspection Report 05000282/2024501 and 05000306/2024501 ML24213A1592024-07-31031 July 2024 Operator Licensing Examination Approval - Prairie Island Nuclear Generating Plant IR 05000282/20240022024-07-30030 July 2024 Integrated Inspection Report 05000282/2024002 and 05000306/2024002 ML24208A1502024-07-26026 July 2024 Independent Spent Fuel Storage Installation - Submittal of Quality Assurance Topical Report (NSPM-1) ML24197A2012024-07-15015 July 2024 Notification of NRC Baseline Inspection and Request for Information; Inspection Report 05000282/2024004 L-PI-24-036, – Preparation and Scheduling of Operator Licensing Examinations2024-06-28028 June 2024 – Preparation and Scheduling of Operator Licensing Examinations IR 05000282/20240102024-06-28028 June 2024 Comprehensive Engineering Team Inspection Report 05000282/2024010 and 05000306/2024010 ML24158A5912024-06-0606 June 2024 CFR 50.46 LOCA Annual Report L-PI-24-031, Independent Spent Fuel Storage Installation, Supplement to License Amendment Request to Revise Independent Spent Fuel Storage Installation (ISFSI) License Conditions 23(a), 24(A)(2), and 24(B)(2)2024-06-0505 June 2024 Independent Spent Fuel Storage Installation, Supplement to License Amendment Request to Revise Independent Spent Fuel Storage Installation (ISFSI) License Conditions 23(a), 24(A)(2), and 24(B)(2) L-PI-24-014, License Amendment Request to Revise the Technical Specification Definition of Reactor Trip System (RTS) Response Time and Apply Response Time Testing to RTS Trip Functions with Time Delay Assumption2024-06-0303 June 2024 License Amendment Request to Revise the Technical Specification Definition of Reactor Trip System (RTS) Response Time and Apply Response Time Testing to RTS Trip Functions with Time Delay Assumption ML24155A1952024-05-31031 May 2024 Reactor Trip and Auto-Start Actuation of Auxiliary Feedwater Due to Loss of Suction to the 22 Main Feedwater Pump ML24155A1922024-05-31031 May 2024 Refueling Outage Unit 2 R33 Owners Activity Report for Class 1, 2, 3 and Mc Inservice Inspections ML24149A3712024-05-29029 May 2024 (Ping) - Information Request for the Cyber-Security Baseline Inspection, Notification to Perform Inspection ML24262A1992024-05-29029 May 2024 L-PI-24-018 PINGP 75 Day Letter L-PI-24-030, Response to Request for Additional Information Regarding License Amendment Request to Revise Technical Specification 3.8.12024-05-22022 May 2024 Response to Request for Additional Information Regarding License Amendment Request to Revise Technical Specification 3.8.1 ML24141A1292024-05-22022 May 2024 Northern States Power Company - Use of Encryption Software for Electronic Transmission of Safeguards Information ML24141A0452024-05-20020 May 2024 Information Request to Support the NRC Annual Baseline Emergency Action Level and Emergency Plan Changes Inspection ML24128A2572024-05-16016 May 2024 ISFSI A13 Acceptance Letter IR 05000282/20240012024-05-15015 May 2024 Integrated Inspection Report 05000282/2024001 and 05000306/2024001 ML24130A2392024-05-0909 May 2024 2023 Annual Radioactive Effluent Report ML24130A2362024-05-0909 May 2024 Independent Spent Fuel Storage Installation - 2023 Annual Radiological Environmental Monitoring Program Report ML24071A1162024-05-0101 May 2024 Issuance of Amendment Nos. 244 and 232 Revise TS 3.7.8, Cooling Water (Cl) System ML24128A0882024-04-30030 April 2024 Submittal of Updated Safety Analysis Report (Usar), Revision 38 ML24089A2382024-04-29029 April 2024 Summary of Nuclear Property Insurance ML24121A0432024-04-29029 April 2024 Reactor Trip and Auto-Start Actuation of Auxiliary Feedwater Due to Loss of Suction to the 22 Main Feedwater Pump IR 05000282/20244012024-04-25025 April 2024 – Security Baseline Inspection Report 05000282/2024401 and 05000306/2024401 ML24100A8042024-04-24024 April 2024 – Alternative Request RR-09 for Safety Injection and Volume Control System Category C Check Valve Inservice Testing ML24114A0882024-04-23023 April 2024 Annual Report of Individual Monitoring for the Prairie Island Nuclear Generating Plant (PINGP) ML24113A1182024-04-12012 April 2024 NRC Letter Re NRC Office of Investigations Report No. 3-2023-004 ML24100A1212024-04-0909 April 2024 Submittal of Revised Pressure and Temperature Limits Report L-PI-24-012, Independent Spent Fuel Storage Installation - License Amendment Request: Revise Independent Spent Fuel Storage Installation (ISFSI) License Conditions 23(a), 24(A)(2), and 24(B)(2)2024-04-0202 April 2024 Independent Spent Fuel Storage Installation - License Amendment Request: Revise Independent Spent Fuel Storage Installation (ISFSI) License Conditions 23(a), 24(A)(2), and 24(B)(2) ML24093A2832024-04-0202 April 2024 Nuclear Material Transaction Report ML24089A2402024-03-29029 March 2024 Guarantee of Payment of Deferred Premiums ML24060A1232024-03-27027 March 2024 to Request 1-RR-5-10 and 2-RR-5-10 Regarding Reactor Pressure Vessel Welds and Nozzle Welds ML24081A1532024-03-21021 March 2024 Reactor Trip, Auxiliary Feedwater and Emergency Service Water System Actuation Due to Electrical Transient in DC Control Power Cables ML24262A1512024-03-15015 March 2024 L-PI-24-011 150 Day Letter 2024 PINGP ILT NRC Exam ML24010A0582024-03-0505 March 2024 Amendment No. 12 to Materials License No. Special Nuclear Material-2506 for the Prairie Island Independent Spent Fuel Storage Installation L-PI-24-004, Independent Spent Fuel Storage Installation - Annual Effluent Report, January Through December 20232024-02-29029 February 2024 Independent Spent Fuel Storage Installation - Annual Effluent Report, January Through December 2023 IR 05000282/20230062024-02-28028 February 2024 Annual Assessment Letter for Prairie Island Nuclear Generating Plant, Units 1 and 2 (Report 05000282/2023006 and 05000306/2023006) ML24088A1102024-02-25025 February 2024 Fairbanks Morse (Fm) Part 21 Notification Report Number 23-01 Re Asco Stainless Steel Solenoid Valves L-PI-24-009, Response to Request for Additional Information Prairie Island Nuclear Generating Plant, Unit 2, Alternative RR-09 Safety Injection System and Volume Control System Category C Check Valve Quarterly Testing2024-02-13013 February 2024 Response to Request for Additional Information Prairie Island Nuclear Generating Plant, Unit 2, Alternative RR-09 Safety Injection System and Volume Control System Category C Check Valve Quarterly Testing ML24040A1712024-02-0909 February 2024 Interim Report of a Potential Deviation or Failure to Comply Associated with Bentley Systems Incorporated Autopipe Software IR 05000282/20230042024-02-0101 February 2024 Integrated Inspection Report 05000282/2023004 and 05000306/2023004 ML23356A1232024-01-29029 January 2024 Exemption from Select Requirements of 10 CFR Part 73 (Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting) 2024-09-23
[Table view] Category:Inspection Plan
MONTHYEARIR 05000282/20240052024-08-28028 August 2024 Updated Inspection Plan and Assessment Follow-Up Letter for Prairie Island Nuclear Generating Plant, Units 1 and 2 (Report 05000282/2024005 and 05000306/2024005) IR 05000282/20230062024-02-28028 February 2024 Annual Assessment Letter for Prairie Island Nuclear Generating Plant, Units 1 and 2 (Report 05000282/2023006 and 05000306/2023006) IR 05000282/20230052023-08-30030 August 2023 Updated Inspected Plan for Prairie Island Nuclear Generating Plant Report 05000282/2023005 and 05000306/2023005 IR 05000282/20220062023-03-0101 March 2023 Annual Assessment Letter for Prairie Island Nuclear Generating Plant, Units 1 and 2 (Report, Units 1 and 2 (Report 05000282/2022006 and 05000306/2022006) ML23055B0562023-02-27027 February 2023 Request for Information for NRC Commercial Grade Dedication Inspection Inspection Report 05000282/2023010 and 05000306/2023010 IR 05000282/20220052022-08-29029 August 2022 Updated Inspection Plan for Prairie Island Nuclear Generating Plant (Report 05000282/2022005; 05000306/2022005) ML22007A1542022-01-0707 January 2022 Notification of NRC Fire Protection Team Inspection Request for Information Inspection Report 05000282/2022010 and 05000306/2022010 ML21363A0542021-12-29029 December 2021 Prairie Nuclear Generating Plant - Request for Information for an NRC Triennial Heat Exchanger/Sink Performance Inspection and Request for Information; Inspection Report 05000282/2022002 05000306/2022002 IR 05000282/20210052021-09-0101 September 2021 Updated Inspection Plan for Prairie Island Nuclear Generating Plant Units 1 and 2 (Report 05000282/2021005 and 05000306/2021005) IR 05000282/20200062021-03-0404 March 2021 Annual Assessment Letter for the Prairie Island Nuclear Generating Plant (Report 05000282/2020006 and 05000306/2020006) ML21062A0532021-03-0202 March 2021 Information Request to Support Upcomng Problem Identification and Resolution (Pi&R) Inspection at the Prairie Island Nuclear Generating Plant IR 05000282/20200052020-09-0101 September 2020 Updated Inspection Plan for Prairie Island Nuclear Generating Plant, Units 1 and 2 (Report 05000282/2020005 and 05000306/2020005) ML20189A1782020-07-0606 July 2020 Notification of NRC Baseline Inspection and Request for Information; Inspection Report 05000282/2020004; 05000306/2020004 IR 05000282/20190062020-03-0303 March 2020 Annual Assessment Letter for Prairie Island Nuclear Generating Plant, Units 1 and 2 (Report 05000282/2019006 and 05000306/2019006) IR 05000282/20190052019-08-28028 August 2019 Updated Inspection Plan for Prairie Island Nuclear Generating Plant, Units 1 and 2 (Report 05000282/2019005; 05000306/2019005) ML19136A1562019-05-15015 May 2019 Information Request to Support the NRC Annual Baseline Emergency Action Level and Emergency Plan Changes Inspection (Garza) ML19071A3532019-03-12012 March 2019 Ltr. 03/12/19 Prairie Island Nuclear Generating Plant, Units 1 and 2 - Notification of NRC Triennial Fire Protection Baseline Inspection Request for Information; Inspection Report 05000282/2019012; 05000306/2019012 (DRS-A.Dahbur) IR 05000282/20180062019-03-0404 March 2019 Annual Assessment Letter for Prairie Island Nuclear Generating Plant, Units 1 and 2 (Report 05000282/2018006 and 05000306/2018006) ML18324A6122018-11-20020 November 2018 Ltr. 11/20/18 Prairie Island Nuclear Generating Plant, Units 1 and 2 - Notification of an NRC Triennial Heat Sink Performance Inspection and Request for Information; Inspection Report 05000282/2019001 and 05000306/2019001 (DRS-N.Feliz-Adorn IR 05000282/20180052018-08-28028 August 2018 Updated Inspection Plan for Prairie Island Nuclear Generating Plant, Units 1 and 2 (Report 05000282/2018005 and 05000286/2018005) ML18156A5532018-06-0505 June 2018 Notification of NRC Baseline Inspection and Request for Information; Inspection Report 05000282/2018004; 05000306/2018004 (DRS-M.Holmberg) IR 05000282/20170062018-03-0202 March 2018 Annual Assessment Letter for Prairie Island Nuclear Generating Plant, Units 1 and 2 (Report 05000282/2017006; 05000306/2017006) IR 05000282/20170052017-08-28028 August 2017 Updated Inspection Plan (Report 05000282/2017005 and 05000306/2017005) IR 05000282/20160062017-03-0101 March 2017 Annual Assessment Letter for Prairie Island Nuclear Generating Plant, Units 1 and 2 (Report 05000282/2016006) ML16265A1652016-09-20020 September 2016 Notification of an NRC Triennial Heat Sink Performance Inspection and Request for Information; Inspection Report 05000282/2016004; 05000306/2016004 (Gfo) IR 05000282/20160052016-08-31031 August 2016 Mid-Cycle Assessment Letter for Prairie Island Nuclear Generating Plant, Units 1 and 2 (Report 05000282/2016005; 05000306/2016005) ML16222A7022016-08-0909 August 2016 Notification of NRC Supplemental Inspection (95001) and Request for Information IR 05000282/20150062016-03-0202 March 2016 Annual Assessment Letter for Prairie Island Nuclear Generating Plant, Units 1 and 2 (Inspection Report 05000282/2015006 and 05000306/2015006) ML15261A7182015-09-15015 September 2015 Ltr. 09/15/2015 Prairie Island Nuclear Generating Plant, Units 1 and 2 - Notification of NRC Triennial Fire Protection Baseline Inspection Request for Information 05000282/2016008; 05000306/2016008. (Dxs) IR 05000282/20150052015-09-0101 September 2015 Mid-Cycle Assessment Letter for Prairie Island Nuclear Generating Plant, Units 1 and 2 (Report 05000282/2015005; 05000306/2015005) IR 05000282/20140012015-03-0404 March 2015 Annual Assessment Letter for Prairie Island Nuclear Generating Plant, Units 1 and 2, (Report 05000282/2014001 and 05000306/2014001) ML14245A2012014-09-0202 September 2014 Mid-Cycle Assessment Letter for Prairie Island Nuclear Generating Plant, Units 1 and 2 ML14209A9342014-07-28028 July 2014 Notification of NRC Inspection and Request for Information IR 05000282/20130012014-03-0404 March 2014 Annual Assessment Letter for Prairie Island Nuclear Generating Plant, Units 1 and 2(Report 05000282/2013001; 05000306/2013001) ML13246A2392013-09-0303 September 2013 2013 Prairie Island MOC Letter Combined ML13203A2862013-07-22022 July 2013 Notification of Baseline Inspection and Information Request ML13077A4742013-03-18018 March 2013 Information Request for a Post-approval Site Inspection for License Renewal IR 05000282/20120012013-03-0404 March 2013 Annual Assessment Letter for Prairie Island Nuclear Generating Plant, Units 1 and 2 (Report 05000282/2012001 and 05000306/2012001) ML12249A4252012-09-0404 September 2012 Mid-Cycle Assessment Letter for Prairie Island Nuclear Generating Plant, Units 1 and 2 IR 05000282/20110072012-03-0505 March 2012 Annual Assessment Letter for Prairie Island Nuclear Generating Plant, Units 1 and 2 (Report 05000282/2011007 and 05000306/2011007) IR 05000282/20110062011-09-0101 September 2011 Mid-Cycle Letter for Prairie Island Nuclear Plant, Units 1 and 2, 05000282-11-006; 05000306-11-006 ML1106203132011-03-0404 March 2011 EOC Annual Assessment Letter and Inspection/Activity Plan ML1024400922010-09-0101 September 2010 Mid-Cycle Performance Review and Inspection Plan - Prairie Island Nuclear Power Plant IR 05000282/20100012010-03-0303 March 2010 Prairie Island Power Plant EOC Assessment Letter (05000282-10-001; 05000306-10-001) ML0924403672009-09-0101 September 2009 Prairie Island - Mid-Cycle Performance Review and Inspection Plan IR 05000282/20090012009-03-0404 March 2009 Annual Assessment Letter - Prairie Island Nuclear Generating Plant, Units 1 and 2 (05000282-09-001 and 050000306-09-001) ML0824603142008-09-0202 September 2008 Prairie Island, Units 1 & 2 - Mid-Cycle Performance Review and Inspection Plan IR 05000282/20080012008-03-0303 March 2008 Prairie Island, EOC Annual Assessment Letter (Inspection Report 05000282-08-001 and 05000306-08-001) ML0735402802007-12-19019 December 2007 Change to the Inspection Plan 1/1/08 - 12/31/08 ML0724302372007-08-31031 August 2007 8/31/07 Prairie Island - Mid-Cycle Performance Review and Inspection Plan 2024-08-28
[Table view] |
Text
UNITED STATES NUCLEAR REGULATORY COMMISSION REGION III 2443 WARRENVILLE ROAD, SUITE 210 LISLE, IL 60532
-4352 March 18, 2013 Mr. Jim Lynch Site Vice President Prairie Island Nuclear Generating Plant Northern States Power Company, Minnesota 1717 Wakonade Drive East Welch, MN 55089
SUBJECT:
PRAIRIE ISLAND NUCLEAR GENERATING PLANT, UNIT 1 , INFORMATION REQUEST FOR A POST
-APPROVAL SITE INSPECTION FOR LICENSE RENEWAL
Dear Mr. Lynch:
On May 20, 201 3, the U. S. Nuclear Regulatory Commission (NRC) will begin a Post
-Approval Site Inspection for License Renewal at Prairie Island Nuclear Generating Plant Unit 1. A team of five inspectors will perform this 3
-week inspection in accordance with NRC Inspection Procedure (IP) 71003. The inspection will include two weeks on
-site, the week of May 20, 2013
, and the week of June 10, 2013
. This inspection will focus on verifying that license conditions added as part of the renewed license, license renewal commitments, and selected Aging Management Programs are implemented in accordance with Title 10 of the Code of Federal Regulations (CFR) Part 54, "Requirements for the Renewal of Operating Licenses for Nuclear Power Plants." In order to minimize the inspection impact on the site and to ensure a productive inspection for both parties, we have enclosed a request for information needed for the inspection. It is important that all of these documents are up to date and complete in order to minimize the number of additional documents requested during the preparation and/or the on
-site portions of the inspection. Insofar as possible, this information should be provided electronically to the lead inspector. The information request has been divided into two groups:
The first group lists information necessary for our initial inspection scoping and in
-office preparation activities. During the in
-office preparation activities, the team will identify the activities to be reviewed during the inspection and additional information needed to support the inspection.
This information should be provided to the lead inspector by May 6, 201 3. The second group includes the additional information required for the team to review the selected activities. This information should be available to the team on
-site May 20 , 2013. It is also requested that corrective action documents and/or questions developed during the inspection be provided to the lead inspector as the documents are generated. The lead inspector for this inspection is Mr. Tom Bilik. We understand that our licensing contact for this inspection is M r. Dale Vincent of your organization. If there are any questions about the inspection or the material requested in the enclosure, please contact the lead inspector at (630) 829-97 44 or via e-mail at tom.bilik@nrc.gov
.
J. Lynch This letter does not contain new or amended information collection requirements subject to the Paperwork Reduction Act of 1995 (44 U.S.C. 3501 et seq.). Existing information collection requirements were approved by the Office of Management and Budget, control number 3150
-0011. The NRC may not conduct or sponsor, and a person is not required to respond to, a request for information or an information collection requirement unless the requesting document displays a currently valid Office of Management and Budget control number.
In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter and its enclosure will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS), accessible from the NRC Web site at http://www.nrc.gov/reading
-rm/adams.html (the Public Electronic Reading Room).
Sincerely, /RA/ Ann Marie Stone, Chief Engineering Branch 2 Division of Reactor Safety Docket No. 50
-282 License No. DPR
-42
Enclosure:
Post-Approval Site Inspection for License Renewal Request for Information cc w/encl:
Distribution via ListServŽ POST-APPROVAL SITE INSPECTION LICENSE RENEWAL REQUEST FOR INFORMATION 1 Enclosure Inspection Report:
05000 2 82/20 1 3 008 Inspection Dates:
May 10, 201 3 - June 14, 201 3 Inspection Procedure:
Inspection Procedure (IP) 71003 "Post
-Approval Site Inspection for License Renewal" Lead Inspector:
Tom Bilik, Lead Inspector (630) 829-97 44 tom.bilik@nrc.gov I. Information Requested Prior to the On
-site Inspection Week The following information is requested by May 6, 201 3, or sooner, to facilitate inspection preparation.
If you have any questions regarding this information, please call the team leader as soon as possible. (Please provide the information electronically in "pdf" files, Excel, or other searchable formats, preferably on some portable electronic media (e.g.
, CDROM, DVD, etc.). The portable electronic media should contain descriptive names, and be indexed and hyperlinked to facilitate ease of use. Information in "lists" should contain enough information to be easily understood by someone who has knowledge of light water reactor technology).
- 1. Provide a list of your license renewal commitments with the completion status of each. If a commitment is not complete, please provide an anticipated completion date. 2. For each complete commitment, please provide documentation demonstrating that the commitment has been completed.
- 3. For any commitment that has been changed, please provide documentation of the commitment change process, and any associated justification.
- 4. Provide a list of your Aging Management Programs (AMPs), copies of the program basis documents for each, and a listing of the action tracking items for each. 5. For AMPS that are one
-time inspection programs, provide a list of completed work order numbers for inspections that have been completed. This may be incorporated with the previous item.
- 6. Provide a list of any "newly identified" structures, systems and components (SSCs) pursuant to 10 CFR 54.37(b) and RIS
-2007-16. 7. Provide a copy of your Updated Final Safety Analysis Report (UFSAR), or UFSAR update
, which includes descriptions of your AMPs.
POST-APPROVAL SITE INSPECTION LICENSE RENEWAL REQUEST FOR INFORMATION 2 Enclosure 8. Provide a copy of any self
-assessment that you have completed related to license renewal.
- 9. Provide current management and license renewal organizational charts.
II. Information Requested t o be Available When the Inspectors Arrive On
-Site o n May 20, 2013 , and During the Inspection. 1. Documentation demonstrating completion of license renewal commitments that are complete as of the inspection date. For example, this may be in the form of a binder for each commitment
, which includes the implementing documentation and references.
- 2. Copies of any corrective action documents generated as a result of the team's questions or queries during this inspection.
- 3. Copies of the list of questions submitted by the team members and the status/resolution of the information requested (provide daily during the inspection to each team member).
If you have questions regarding the information requested, please contact the lead inspector.
It may also help to review the IP 71003 frequently asked questions
, which are available at:
http://www.nrc.gov/reactors/operating/licensing/renewal/introduction/inspections/faq
-ip71003.html
J. Lynch This letter does not contain new or amended information collection requirements subject to the Paperwork Reduction Act of 1995 (44 U.S.C. 3501 et seq.). Existing information collection requirements were approved by the Office of Management and Budget, control number 3150
-0011. The NRC may not conduct or sponsor, and a person is not required to respond to, a request for information or an information collection requirement unless the requesting document displays a currently valid Office of Management and Budget control number.
In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter and its enclosure will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS), accessible from the NRC Web site at http://www.nrc.gov/reading
-rm/adams.html (the Public Electronic Reading Room).
Sincerely, /RA/ Ann Marie Stone, Chief Engineering Branch 2 Division of Reactor Safety Docket No. 50
-282 License No. DPR
-42
Enclosure:
Post-Approval Site Inspection for License Renewal Request for Information cc w/encl:
Distribution via ListServŽ
DOCUMENT NAME: G:\DRS\Work in Progress
\Misc Boilers
\con 5.doc -Publicly Available -Sensitive To receive a copy of this document, indicate in the concurrence box "C" = Copy without attach/encl "E" = Copy with attach/encl "N" = No copy OFFICE RIII RIII NAME TBilik:ls AMStone DATE 03/18/13 03/18/13 OFFICIAL RECORD COPY Letter to Mr. Jim Lynch from Ms. Ann Marie Stone dated March 18, 2013.
SUBJECT:
PRAIRIE ISLAND NUCLEAR GENERATING PLANT, UNIT 1 INFORMATION REQUEST FOR A POST
-APPROVAL SITE INSPECTION FOR LICENSE RENEWAL DISTRIBUTION:
John Cassidy RidsNrrPMPrairieIsland Resource RidsNrrDorlLpl3
-1 Resource RidsNrrDirsIrib Resource Chuck Casto Cynthia Pederson Steven Orth Allan Barker Christine Lipa Carole Ariano Linda Linn DRPIII DRSIII Patricia Buckley Tammy Tomczak