Final Significance Determination of White Finding and Notice of Violation, NRC Inspection Report 05000361-12-009 and 05000362-12-009
ML13357A058
Person / Time
Site: San Onofre  Southern California Edison icon.png
Issue date: 12/23/2013
From: Dapas M
Region 4 Administrator
To: Thomas J. Palmisano
Southern California Edison Co
References
EA-13-083 IR-12-009
Download: ML13357A058 (6)


See also: IR 05000361/2012009

Text

December 23, 2013

EA-13-083

Mr. Tom Palmisano

Senior Vice President and

Chief Nuclear Officer

Southern California Edison Company

San Onofre Nuclear Generating Station

P.O. Box 128

San Clemente, CA 92674-0128

SUBJECT: SAN ONOFRE NUCLEAR GENERATING STATION - FINAL SIGNIFICANCE DETERMINATION OF WHITE FINDING AND NOTICE OF VIOLATION, NRC

INSPECTION REPORT 05000361/2012009 AND 05000362/2012009

Dear Mr. Palmisano:

This letter provides you the final results of our significance determination of the preliminary

White finding identified in NRC Inspection Report 05000361/ 2012009; 05000362/ 2012009

(NRC's Agencywide Documents Access and Management System (ADAMS) Accession ML13263A271) dated September 20, 2013. The finding involved the failure to verify the adequacy of the thermal-hydraulic and flow-induced vibration design of the Unit 3 replacement

steam generators, which resulted in significant and unexpected steam generator tube wear and the loss of tube integrity on Unit 3 Steam Generator 3EO-88 after 11 months of operation.

In a letter dated October 21, 2013, (ML13296A018), you provided a response to the NRC staff's preliminary determination regarding this finding. Your response included your agreement that the finding has low-to-moderate safety significance and is, therefore, appropriately

characterized as a White finding. After considering the information developed during the

inspection and the additional information you provided in your letter, the NRC has concluded that the finding is appropriately characterized as White, a finding of low to moderate safety significance.

You have 30 calendar days from the date of this letter to appeal the staff's determination of

significance for the identified White finding. Such appeals will be considered to have merit only

if they meet the criteria given in the IMC 0609, Attachment 2. If you choose to appeal, you must send your appeal to the Regional Administrator, Region IV, 1600 East Lamar Blvd., Arlington, Texas 76011-4511.

The NRC has also determined that the failure to verify the adequacy of the thermal-hydraulic

and flow-induced vibration design of the Unit 3 r

eplacement steam generators is a violation of 10 CFR Part 50, Appendix B, Criterion III, "Design Control," with an associated violation of UNITED STATESNUCLEAR REGULATORY COMMISSIONREGION IV1600 EAST LAMAR BLVDARLINGTON, TEXAS 76011-4511

T. Palmisano - 2 -

Technical Specification 5.5.2.11, "Steam Generator Program." The circumstances surrounding

the violation were described in detail in NRC Inspection Report 05000361/2012009 and

05000362/2012009. In accordance with the NRC Enforcement Policy, this violation is

considered an escalated enforcement action because it is associated with a White finding.

The NRC has concluded that the information regarding the reason for the violation is already adequately addressed on the docket through detailed inspection reports and your response letter dated October 21, 2013. Additional information regarding the reason for the violation is

not required, unless the description therein does not accurately reflect the reasons for the

violation or your position. However, you are required to respond to this letter and provide the

results of your evaluation of the extent of condition related to the reasons for the violation.

Specifically, if you determine that any reason for this violation may apply to work activities during decommissioning and dry cask storage, including oversight of contractor activities, then

for each such reason, your reply should include: (1) the corrective steps that have been taken

and the results achieved, (2) the corrective steps that will be taken, and (3) the date when all associated corrective actions will have been implemented. If you determine that no reason for this violation could reasonably apply to decommissioning or dry cask storage activities, then your reply should include a statement to that effect. You should follow the instructions specified

in the enclosed Notice when preparing your response.

In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter, its enclosure, and your response, will be made available electronically for public inspection in the NRC Public Document Room or from ADAMS, accessible from the NRC Web site at

http://www.nrc.gov/reading-rm/adams.html. To the extent possible, your response should not include any personal privacy, proprietary, or safeguards information so that it can be made available to the public without redaction.

Sincerely, /RA/ Marc L. Dapas

Regional Administrator

Dockets: 50-361, 50-362

Licenses: NPF-10, NPF-15

Enclosure: Notice of Violation

cc w/encl:

Electronic Distribution for San Onofre

Nuclear Generating Station

T. Palmisano - 3 -

cc: Distribution for San Onofre Nuclear Generating Station

RidsOeMailCenter Resource; OEWEB Resource; RidsSecyMailCenter Resource; RidsOcaMailCenter Resource; RidsOgcMailCenter Resource; RidsEdoMailCenter Resource; EDO_Managers RidsOigMailCenter Resource; RidsOiMailCenter Resource; RidsRgn1MailCenter Resource; RidsOcfoMailCenter Resource;

RidsRgn2MailCenter Resource; RidsRgn3MailCenter Resource; NRREnforcement.Resource RidsNrrDirsEnforcement Resource RidsOpaMail Resource;

Marc.Dapas@nrc.gov

Steven.Reynolds@nrc.gov
Karla.Fuller@nrc.gov
Roy.Zimmerman@nrc.gov
Bill.Maier@nrc.gov
Nick.Hilton@nrc.gov
Tom.Blount@nrc.gov
Kriss.Kennedy@nrc.gov
John.Wray@nrc.gov;

Jeff.Clark@nrc.gov

Troy.Pruett@nrc.gov
Robert.Carpenter@nrc.gov;

Heather.Gepford@nrc.gov

Rachel.Browder@nrc.gov
Gerald.Gulla@nrc.gov
Christi.Maier@nrc.gov
Victor.Dricks@nrc.gov
Greg.Werner@nrc.gov
Marisa.Herrera@nrc.gov
Lara.Uselding@nrc.gov
Bob.Hagar@nrc.gov
R4Enforcement;

Ryan.Lantz@nrc.gov

Blair.Spitzberg@nrc.gov
Greg.Warnick@nrc.gov
Carleen.Sanders@nrc.gov
Dori.Willis@nrc.gov
Brett.Rini@nrc.gov

OFFICIAL RECORD COPY T=Telephone E=E-mail F=Fax

S:\RAS\ACES\ENFORCEMENT\_EA CASES - OPEN\SONGS_EA-13-083_SG Tube Integrity White Finding\Final Action\FINAL WHITE_EA-13-083_SONGS_12-13-13.docx ADAMS No Yes SUNSI Review Complete Reviewer Initials: RSB Publicly Available Non-publicly Available Sensitive Non-sensitive Category: KEYWORD: EA-13-083 RIV: BC BC SES:ACES RC BHagar GWerner RLantz RSBrowder

KSFuller /RA/ /RA/ /RA/ /RA/ /RA/ 12/11/13 12/11/13 12/10/13 12/10/13 12/11/13 C:ACES/ORA OE D:DRP DRA RA HJGepford RCarpenter KKennedy SReynolds MLDapas /RA/ /RA/ /RA/ N/A /RA/ 12/12/13 12/12/13 12/16/13 12/23/13

Enclosure NOTICE OF VIOLATION

Southern California Edison Docket No. 50-362 San Onofre Nuclear Generating Station License No. NPF-15

EA-13-083

During an NRC inspection conducted on December 3, 2012, through June 7, 2013, a violation of NRC requirements was identified. In accordance with the NRC Enforcement Policy, the violation is listed below:

10 CFR Part 50, Appendix B, Criterion III, "Design Control," states, in part, that design

control measures shall provide for verifying or checking the adequacy of design, such as

by the performance of design reviews, by the use of alternate or simplified calculational methods, or by the performance of a suitable testing program.

Technical Specification 5.5.2.11, "Steam Generator Program," Section b, "Performance

criteria for SG [steam generator] tube integrity," states, in part, that steam generator tube integrity shall be maintained by meeting the performance criteria for tube structural integrity and accident induced leakage.

Technical Specification 5.5.2.11 b.1, "Structural integrity performance criterion,"

states, in part, that all in-service steam generator tubes shall retain structural

integrity over the full range of normal operating conditions, to include retaining a safety factor of 3.0 against burst under normal steady state full power operation primary-to-secondary differential pressure.

Technical Specification 5.5.2.11 b.2, "Accident induced leakage performance

criterion," states, in part, that leakage shall not exceed 0.5 gallons per minute per steam generator for a main steam line break accident.

Contrary to the above, design control measures were not established to provide for

verifying or checking the adequacy of certain designs. Specifically, on January 28 and

April 2, 2008, the licensee's design control measures did not provide for verifying or

checking the adequacy of design Documents L5-04GA504 (SO23-617- 1-C157), "Evaluation of Tube Vibration," Revision 3, and L5-04GA521 (SO23-617-1- C683), "Three-Dimensional Thermal and Hydraulic

Analysis," Revision 3, developed by Mitsubishi, for the flow-induced vibration and thermal-hydraulic designs. As a result, the

licensee did not verify or check the output of the thermal-hydraulic code and input to the

vibration code to be in accordance with ASME Section III, Appendix N, "Dynamic Analysis Methods."

Consequently, the inadequate thermal-hydraulic and flow-induced vibration design

resulted in non-conservative flow conditions, which led to fluid-elastic instability of a

group of tubes in the Unit 3 replacement steam generators. This resulted in one tube

leaking, which prompted the licensee to shut down the plant on January 31, 2012. In March 2012, in-situ pressure testing on Unit 3 steam generator 3EO-88 revealed that eight tubes had failed to meet the performance criteria for structural integrity and

2 accident induced leakage. Specifically, during in-situ pressure testing, tubes R106C78, R102C78, R104C78, R100C80, R107C77, R101C81, R98C80, and R99C81 in steam generator 3EO-88 failed to meet the structural integrity criterion limit of three times the normal steady state primary-to-secondary differential pressure of 5250 psig, with the

tubes failing at test pressures ranging from 2874 psig to 5026 psig. In addition,

tubes R106C78, R102C78, and R104C78 failed to meet the accident-induced leakage

criterion of not exceeding 0.5 gpm leakage per steam generator at a main steam line

break pressure of 3200 psig, with each tube having leakage rates of approximately

4.5 gpm, prior to exceeding 3200 psig.

This violation is associated with a White Significance Determination Process finding.

Pursuant to the provisions of 10 CFR 2.201, Southern California Edison Company is hereby

required to submit a written statement or explanation to the U.S. Nuclear Regulatory Commission, ATTN: Document Control Desk, Washington, DC 20555-0001 with a copy to the

Regional Administrator, Region IV, and a copy to the NRC Resident Inspector at the facility that

is the subject of this Notice, within 30 days of the date of the letter transmitting this Notice of

Violation (Notice). This reply should be clearly marked as a "Reply to a Notice of Violation; EA 13-083." The reply should include a written explanation for the evaluated extent of conditions. Particularly, if you determine that any reason for this violation may apply to work activities during decommissioning and dry cask storage, including oversight of contractor

activities, then for each such reason, your reply should include: (1) the corrective steps that

have been taken and the results achieved, (2) the corrective steps that will be taken, and (3) the

date when all associated corrective actions will have been implemented. If you determine that no reason for this violation could reasonably apply to decommissioning or dry cask storage activities, then your reply should include a statement to that effect.

Your response may reference or include previous docketed correspondence, if the

correspondence adequately addresses the required response. If an adequate reply is not received within the time specified in this Notice, an order or a Demand for Information may be issued as to why the license should not be modified, suspended, or revoked, or why such other

action as may be proper should not be taken. Where good cause is shown, consideration will

be given to extending the response time.

If you contest this enforcement action, you should also provide a copy of your response, with the basis for your denial, to the Director, Office of Enforcement, United States Nuclear Regulatory Commission, Washington, DC 20555-0001.

Because your response will be made available el

ectronically for public inspection in the NRC Public Document Room or from the NRC's Agencywide Documents Management System (ADAMS), accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html , to the extent possible, it should not include any

personal privacy, proprietary, or safeguards information so that it can be made available to the public without redaction. If personal privacy or proprietary information is necessary to provide an acceptable response, then please provide a bracketed copy of your response that identifies the information that should be protected and a

redacted copy of your response that deletes such information.

3 If you request withholding of such material, you must

specifically identify the portions of your response that you seek to have withheld and provide in detail the bases for your claim of withholding (e.g., explain why the disclosure of information will create an unwarranted invasion of personal privacy or provide the information required by 10 CFR 2.390(b) to support a request

for withholding confidential commercial or financial information). If safeguards information is

necessary to provide an acceptable response, please provide the level of protection described

in 10 CFR 73.21.

Dated this 23rd day of December 2013