MONTHYEARML20217K9681999-10-19019 October 1999 Ack Receipt of Transmitting Rev 40 to Physical Security Plan for Washington Nuclear Plant 2.Based on Determination That Changes Do Not Decrease Effectiveness of Plan,No NRC Approval Required ML17284A8981999-10-14014 October 1999 Forwards Rev 0 to WNP-2 Cycle 15,COLR 99-15, IAW Requirements of TS 5.6.5 ML17284A9061999-09-24024 September 1999 Forwards Final Rept for 990812 out-of-sequence Drills for Energy Northwest Washington Nuclear Power Project 2 (Lab, Food Control Point & Milk Sampling).No Deficiences & No Areas Requiring C/A Identified in Three Drills ML17284A8881999-09-24024 September 1999 Informs NRC of Change in Schedule Pertaining to Final Implementation of Reactor Stability long-term Solution for WNP-2 ML17292B7591999-09-24024 September 1999 Forwards Rev 24 to WNP-2 Emergency Plan,Iaw 10CFR50.4(b), 50.54(q) & 10CFR50 App E.Detailed Synopsis of Changes,Encl ML17292B7581999-09-22022 September 1999 Forwards NRC Forms 396 & 398 for Nl Hancock,License SOP-50027-3,AR Herrington,License OP-50013-3,WH Sawyer, License SOP-50023-3 & Dl Strote,License SOP-50031-3,for Renewal of Licenses.Without NRC Forms 396 & 398 ML17284A8811999-09-0909 September 1999 Forwards Response to NRC 990623 RAI to Support Review of Pending Request for Amend to Reactor pressure-temp Limit Curve TS GO2-99-168, Forwards Rev 40 to Physical Security Plan.Rev Withheld,Per 10CFR2.790(a)(3)1999-09-0808 September 1999 Forwards Rev 40 to Physical Security Plan.Rev Withheld,Per 10CFR2.790(a)(3) ML17284A8711999-08-30030 August 1999 Informs Staff of Errors in world-wide-web Database Related to WNP-2 Reactor Vessel Structural integrity.Marked-up Pages Containing Errors or Omissions Will Be Forwarded by 991201 ML17284A8751999-08-30030 August 1999 Provides Correct Page from License NPF-21 Marked to Show Rev Addressed in 990729 Application for Amend,Which Included Page That Was Inadvertently Included as Attachment 4.Replace Attachment 4 with Attached Page & Disregard Attachment 5 ML17284A8721999-08-30030 August 1999 Forwards Proprietary Info to Support Review of Request for Amend to License NPF-21,re Min Critical Power Ratio Safety Limits Tss,As Requested During 990816 Conversation. Proprietary Encl Withheld ML17292B7531999-08-24024 August 1999 Requests That Eleven Individuals Listed Below Take BWR Generic Fundamentals Examination to Be Administered on 991006 ML17292B7511999-08-24024 August 1999 Forwards Fitness for Duty (FFD) Semiannual Performance Data Rept for Jan-June 1999,per 10CFR26.71(d) ML17284A8701999-08-19019 August 1999 Forwards NRC Form 396, Certification of Medical Exam by Facility Licensee & NRC Form 398, Personal Qualification Statement - Licensee, for Jd Prescott (License SOP-50262-1).Without Encls ML17292B7501999-08-19019 August 1999 Informs Staff That Licensee Has Completed Review of NRC SER for B&Wog Util Resolution Guidance Document Addressing ECCS Suction Strainer Blockage ML17284A8681999-08-12012 August 1999 Submits Two ISI Program Plan Relief Requests for NRC Review & Approval,Per 10CFR50.55a(a)(3)(i).Proposed Alternatives Provide Acceptable Level of Quality & Safety ML20211A9501999-08-12012 August 1999 Discusses 990720-21 Workshop Conducted in Region IV Ofc,Re Exchange of Info in Area of Use of Risk Insights in Regulatory Activities.List of Attendees,Summary of Topic & Issues,Agenda & Copies of Handouts Encl ML20210L1461999-08-0303 August 1999 Informs That NRC Plans to Administer Gfes of Written Operator Licensing Exam on 991006.Requests Submittal of Ltr Identifying Individuals Taking Exam,Personnel Allowed Access to Exams & Mailing Address for Exams ML17284A8541999-08-0202 August 1999 Forwards Proprietary Addl Info to Support Review of Pending Request for Amend to MCPR Safety Limit Ts.Info Consists of Proprietary Ltr from Abb Combustion Engineering,Inc.Encl Withheld ML17284A8531999-07-30030 July 1999 Forwards Estimate of Number of Licensing Action Requests Planned for Submittal in Future,As Requested in Administrative Ltr 99-02.Twenty-nine Submittals Scheduled for Fy 2000 & Four for Fy 2001 ML17284A8301999-07-22022 July 1999 Clarifies Change of Licensee Name from Wpps to Energy Northwest & Change of Facility Name from Wppss Nuclear Project Number 2 to WNP-2,as Requested in 990719 Telcon with Js Cushing of NRC.Marked-up OL Pages,Encl ML17292B7451999-07-20020 July 1999 Forwards Rev 23 to WNP-2 Emergency Plan,Iaw 10CFR50.4(b) & 50.54(q) & 10CFR50 App E.Rev 23 Provides Updated Description Re Establishment of Separate Emergency Operation Centers for Benton & Franklin Counties ML17292B7391999-07-16016 July 1999 Submits Withdrawal of Request for Amend to Secondary Containment & Standby Gas Treatment Sys Ts.Util Currently Plan to re-submit Amend Request in Entirety by 991112 ML17292B7381999-07-12012 July 1999 Forwards NRC Form 396 & NRC Form 398,for If Sumsion,License OP-50487 & Ga Westergard,License SOP-50415 for Renewal of Operator Licenses.Without Encls ML17292B7171999-07-0606 July 1999 Provides Notification of Early Completion on 990630 of Exception Noted in 990629 Ltr.Equipment within Scope of GL 98-01,Suppl 1, Y2K Readiness of Computer Sys at Nuclear Power Plants, Evaluated & Y2K Ready ML17292B7181999-07-0202 July 1999 Responds to 990623 RAI to Support Review of Evaluation of Planar Indication Found on Weld Number 24RRC(2)A-1 During 1998 RO ML17292B7161999-06-30030 June 1999 Forwards Addl Info Requested in 990513 Ltr to Support Review of Pending Response to GL 95-07, Pressure Locking & Thermal Binding of Safety-Related Power Operated Gate Valves. ML17292B7131999-06-29029 June 1999 Forwards Response to NRC GL 98-01,Suppl 1, Y2K Readiness of Computer Sys at Npps. ML17292B7091999-06-21021 June 1999 Forwards Proprietary Response to NRC 990603 RAI Re Licensee Request for Amend to MCPR Safety Limit Tss.Proprietary Info Withheld IAW Requirements of 10CFR2.790 ML17292B7041999-06-17017 June 1999 Forwards NRC Forms 396 & 398 for Three Individuals Listed Below for Renewal of Operator Licenses.Without Encls ML17292B7031999-06-10010 June 1999 Forwards Response to NRC 990511 RAI Re License Request for Amend to Secondary Containment & SGTS Tss.Results of Addl Benchmark of Gothic Computer Code Performed to Demonstrate Modeling Capability of Drawdown Response,Encl ML17292B6841999-06-0404 June 1999 Forwards Response to NRC 990326 RAI Re WNP-2 GL 96-05 Program for Periodic Verification of design-basis Capability of MOVs ML17292B6851999-06-0101 June 1999 Forwards 1999 Quality Audit of WNP-2 Emergency Preparedness Program, Per NUREG-0654,Section Ii,Criteria P.9.Seven Problem Evaluation Requests & Nine Recommendations for Improvement Were Issued as Result of Audit Activities ML17292B6831999-05-25025 May 1999 Informs That Request for NRC Approval of Changes to Emergency Plan Requesting Reduction in on-shift HP Staffing, Is Retracted.Util Will Resubmit Request with Required Addl Info at Later Date ML17292B6751999-05-25025 May 1999 Forwards Proprietary ABB-CE Ltr Re WNP-2 Cycle 15 SLMCPR & Core Reload Design Rept,Per Util Request for Amend Re MCPR Safety Limits.Proprietary Info Withheld,Per 10CFR2.790 ML20206U4501999-05-19019 May 1999 Ack Receipt of Which Transmitted Rev 39 to Physical Security Plan,Per 10CFR50.54(p).No NRC Approval Is Required,Since Changes Do Not Decrease Effectiveness of Security Plan ML17292B6661999-05-0707 May 1999 Requests Exemption to Requirement in 10CFR55.59(a)(2) Re Annual Operating Test requirements.One-time Exemption from Requirement to Period Not to Exceed 15-months from Last Date of Passing Operating Exam for Licensee at Facility ML17292B6531999-05-0303 May 1999 Forwards Response to NRC 990402 RAI Re Licensed Operator Positive Drug Test.Encl Withheld,Per 10CFR2.790 ML17292B6561999-04-29029 April 1999 Forwards Rev 0 to Calculation ME-02-98-04, Fracture Mechanics Evaluation of N1 Safe End & Calculation Mod Record CMR-98-0243, Fracture Mechanics Evaluation of N1A Nozzle Safe End, as Suppl Info to ISI Exam ML17292B6421999-04-19019 April 1999 Responds to NRC 990319 Ltr Re Violations Noted in Insp Rept 50-397/99-01.Corrective Actions:Provisions Are Presently in Place to Maintain Adequate Level of Security GO2-99-073, Forwards Rev 39 to WNP-2 Physical Security Plan,Per 10CFR50.54(p).Changes Do Not Decrease Effectiveness of Approved Plan.Encl Withheld IAW 10CFR73.21 & 10CFR2.7901999-04-19019 April 1999 Forwards Rev 39 to WNP-2 Physical Security Plan,Per 10CFR50.54(p).Changes Do Not Decrease Effectiveness of Approved Plan.Encl Withheld IAW 10CFR73.21 & 10CFR2.790 ML17292B6401999-04-13013 April 1999 Requests That WNP-2 Operator Requalification Program Be Granted one-time Extension Beyond Requirement in 10CFR55.59(a)(2) for Annual Operating Tests ML17292B6371999-04-12012 April 1999 Forwards Response to NRC 990211 RAI Re Util Request for Amend to Secondary Containment & SBGTS TS ML17292B6281999-04-0606 April 1999 Informs NRC That Insp Interval Ending Date for ISI Program Plan Has Been Extended by One Year to Dec 12,2005 Due to Changes in Plant Refueling Outage Schedule ML20196K6961999-03-30030 March 1999 Ack Receipt of ,Transmitting Rev 38 to Physical Security Plan for Plant.No NRC Approval Is Required,In Accordance with 10CFR50.54(p) GO2-99-060, Submits Rept of Status of WNP-2 Decommissioning Fund as of 981231,IAW 10CFR50.75(f)(1)1999-03-26026 March 1999 Submits Rept of Status of WNP-2 Decommissioning Fund as of 981231,IAW 10CFR50.75(f)(1) ML17292B6131999-03-24024 March 1999 Forwards Rev 0 to Calculation ME-02-98-04, Fracture Mechanics Evaluation of N1 Nozzle Safe End. Info Will Be Used to Assist NRC in Review of WNP-2 ISI Activities Associated with Evaluation of Planar Indication ML20204F0261999-03-19019 March 1999 Forwards Insp Rept 50-397/99-01 on 990201-04 & 0303-05.No Violations Noted.Areas of Physical Security Plan Effectively Implemented with Listed Exceptions ML17292B6001999-03-16016 March 1999 Responds to Weakness Noted in Insp Rept 50-397/98-24. Corrective Actions:Developed Document to Identify Areas Needing Improvement,Assigned Responsibility for Actions & Provided Milestones for Achievement ML17292B5941999-03-16016 March 1999 Forwards NRC Form 396, Certification of Medical Exam by Facility Licensee, & NRC Form 398, Personal Qualification Statement - Licensee, for MD Comstock,Mc Naulty & RR Nelson.Without Encls 1999-09-09
[Table view] Category:EXTERNAL CORRESPONDENCE
MONTHYEARML17284A7431998-09-0101 September 1998 Informs That WNP-2,1998 Emergency Exercise Scenario Has Been Revised to Address Concerns Raised by Both FEMA & Nrc. Revised Section 6 of Scenario Manual,Encl.W/O Encl ML17284A7141998-07-31031 July 1998 Requests Review & Comments Re Scenario Package for 1998 NRC Graded Exercise to Be Conducted on 980916.Revs Were Made Following Discussion W/Good of NRC on 980622 ML17290A6761993-09-0101 September 1993 Forwards Request for Withholding Proprietary GE-NE-523-94-0793,Rev 1, Structural Evaluation of Effects of Adjustable Speed Drive on WNP-2 Main Recirculation Pump & Motor, (Ref 10CFR2.790) ML17290A3431993-05-17017 May 1993 Forwards Supply Sys QA Audit 93-611,dtd 930517,required Under 10CFR.54(t).W/o Encl ML17286B0471991-09-17017 September 1991 Forwards Corporate Licensing & Assurance Audit 91-551 Dtd 910724.W/o Encl ML17286A9371991-06-25025 June 1991 Provides Clarification,In Regards to Discussions Concerning State Recent Review of Plant Emergency Action Levels ML17291A6291987-07-0707 July 1987 Forwards Copy of Itl Rept 87-5-77 on 1 H Nine Inch Heat Flow Path Conducted by TSI in May 1987 GO2-86-106, Advises That Listed Ref Matls for Use in Preparing Operator License Exam for Ja Landon,Scheduled for 870219,shipped to Recipient on 8611241986-12-0505 December 1986 Advises That Listed Ref Matls for Use in Preparing Operator License Exam for Ja Landon,Scheduled for 870219,shipped to Recipient on 861124 ML20107K0151984-10-22022 October 1984 FOIA Request for Three Categories of Documents,Including BPA 840907 Near Term Intertie Access Policy & Facility Antitrust Review ML17277B2931984-01-27027 January 1984 Advises That as-built Stress Analysis of RHR Sys Piping & Evaluation of Burns & Roe Floor Response Amplification Analysis,Not Included in Util Final Assessment Rept,Appear Satisfactory.Mods to Previous Conclusion Unnecessary ML20070H2931982-12-20020 December 1982 Requests Supplemental Pleadings Be Served on Applicant Counsel in Washington,Dc Per ASLB 821215 Order.Pleadings Expected by 830111.Pleadings Served to Util in Richland,Wa Do Not Constitute Svc in Proceeding ML17275A7651980-12-16016 December 1980 Discusses Review of Amend 4 to Environ Rept.Comments on Discussion of Endangered & Threatened Species on Page 6.1-20.Util Should Ensure That Obligations of Endangered Species Act of 1973,as Amended,Have Been Fulfilled ML17275A7001980-11-0606 November 1980 Forwards Sections of FSAR & Plant Design Assessment Rept for Safety Relief Valves & LOCA Loads to Assist in Understanding Nature of Hydrodynamic Loading Phenomenon in Mark II Containments & Use in Facility Buckling Analysis.W/O Encls ML17272A3211979-03-0606 March 1979 Amend 3 to Environ Rept Has Been Reviewed.No Changes to Comments Submitted on 770601 & 780726 1998-09-01
[Table view] |
Text
I GE Nuclear Energy General Electric Company 175 Cunnei Avenue, San Jose, CA 95125 September 1, 1993 Letter WNP-2/ASD/505 Newell S.Porter Manager-ASD/I&C Design Washington Public Power Supply System Plant WNP-2, Bldg.81 (Downstairs)
Richland, WA 99352~Sub'ect: WNP-2 RR ASD Structural Evaluation of the EQ'ccts of the ASD on the WNP-2 Main Recirc Pump&Motor (Report PGE-NE-523-944793, Rev.1, Aug.93)
Dear Newell:
This is thc formal transmittal of the above subject rcport (4 copies).The rcport has been revised to Rev.1 in accordance with the procedure for clarifying"Proprietary Information" in reports that are submitted to thc NRC.Thcrc are no technical changes from Rcv.0.Please note the statement added to the bottom of the second page, LEGAL NOTICES-CHANGES INCORPORATED ON REVISION l.Regards, Roy Daniel WNP-2 ASD Design Project Manager (408)9254709 WRD:rd Daniel-2 Copies: J.Wood D.Kelly N.Horton M.McClain R.Tahvar M.Wuesterfcld WRD LB-KOP (w/o att.)-M/C 462 (w/o att.)-M//C481 (w/o att.)-M/C775 (w/oatt.)-M/C 736 (w/o att.)-M/C264 (w/oatt.)9310140332 931006 PDR ADOCK 05000397 P PDR GE NUCLEAR ENERGY TECHNICAL SERVICES MEMO Plant Licensing Projects TO: J.Arbuckle DATE: September 8, 1993 Washington Public Power Supply System RTH:93-P05 FROM R.T.Hill Plant Licensing Services
SUBJECT:
Proprietary.
Affidavit For WNP-2 ASD Structral Evaluation Document
REFERENCE:
Structural Evaluation of'he Effects of the Ad'ustable S eed Drive on the WNP-2 Main Recirculation Pum and Motor, Revision 1, GE-NE-523-94-0793, GE Proprietary Information Class III, dated August 1993.The attached proprietary affidavit is to be transmitted to the NRC with the referenced document which was sent to N.Porter at the Supply System under separate cover.This affidavit is applicable to Revision 1 only.Revision 0 of the referenced document is valid for your information and is still GE Company Proprietary but is not suitable for transmittal to the NRC because it does not specifically identify (e.g., margin bars)which information is proprietary as required by 10 CFR 2.790.Transmittal of all proprietary information directly related to the referenced document including proprietary responses to any questions which may arise due to NRC (or other)review of the referenced document are also covered by this affidavit.
c ar T.H ll Phone 408-925-3255 MC 481 cc: W.R.Daniel, N.R.Horton, D.M.Kelly, D.J.Robare, B.A.Smith
GENERAL ELECTRIC COMPANY AFFIDAVIT I, DAVID J.ROBARE, being duly sworn, depose and state as follows: (1)I am Manager, Plant Licensing Projects, General Electric Company ("GE")and have been delegated the function of reviewing the information described in paragraph 2 which is sought to be withheld, and have been authorized to apply for its withholding.
(2)(3)The information sought to be withheld is contained in the GE proprietary report GE-NE-523-94-0793,"Structural Evaluation of the Effects of the Adjustable Speed Drive on the WNP-.2 Main Recirculation Pump and Motor", Class III, Revision 1, dated August 1993.This information is delineated by bars marked in the margin adjacent to the specific material.In making this application for withholding of proprietary information of which it is the owner, GE relies upon the exemption from disclosure set forth in the Freedom of Information Act ("FOIA"), 5 USC Sec.552(b)(4), and the Trade Secrets Act, 18 USC Sec.1905, and NRC regulations 10 CFR 9.17(a)(4), 2.790(a)(4), and 2.790(d)(1) for"trade secrets and commercial or financial information obtained from a person and privileged or confidential" (Exemption 4).The material for which exemption from disclosure is here sought is all"confidential commercial information", and some portions also qualify under the narrower definition of"trade secret", within the meanings assigned to those terms for purposes of FOIA Exemption 4 in, respectively, Critical Mass Ener Pro'ect v.Nuclear Re ulator Commission 975F2d871 (DC Cir.1992), and Public Citizen Health Research Grou v.FDA, 704F2d1280 (DC Cir.1983).(4)Some examples of categories of information which fit into the definition of proprietary information are: a 0 Information that discloses a process, method, or apparatus, including supporting data and analyses, where prevention of its use by General Electric's competitors without license from General Electric constitutes a competitive economic advantage over other companies; b.C~d.Information which, if used by a competitor, would reduce his expenditure of resources or improve his competitive position in the design, manufacture, shipment, installation, assurance of quality, or licensing of a similar product;Information which reveals cost or price information, production capacities, budget levels, or commercial strategies of General Electric, its customers, or its suppliersg Information which reveals aspects of past, present, or future General Electric customer-funded development plans and programs, of potential commercial value to General Electric;e.Information which discloses patentable subject matter for which it may be desirable to obtain patent protection.
The information sought to be withheld is considered to be proprietary for the reasons set forth in both paragraphs (4)a.and (4)b., above.(5)The information sought to be withheld is being submitted to NRC in confidence.
The information is of a sort customarily held in confidence by GE, and is in fact so held.Its initial designation as proprietary information, and the subsequent steps taken to prevent its unauthorized disclosure, are as set forth in (6)and (7)following.
The information sought to be withheld has, to the best of my knowledge and belief, consistently been held in confidence by GE, no public disclosure has been made, and it is not available in public sources.All disclosures to third parties including any required transmittals to NRC, have been made, or must be made, pursuant to regulatory provisions or proprietary agreements which provide for maintenance of the information in confidence.
(6)Initial approval of proprietary treatment of a document is made by the manager of the originating component, the person most likely to be acquainted with the value and sensitivity of the information in relation to industry knowledge.
Access to such documents within GE is limited on a"need to know" basis.(7)The procedure for approval of external release of such a document typically requires review by the staff manager, project manager, principal scientist or other equivalent authority, by the manager of the cognizant marketing function (or his delegate), and by the Legal Operation, for technical content, competitive effect, and determination of l"~
the accuracy of the proprietary designation.
Disclosures outside GE are limited to regulatory bodies, customers, and potential customers, and their agents, suppliers, and licensees, and others with a legitimate need for the information, and then only in accordance with appropriate regulatory provisions or proprietary agreements.
(8)The information identified in paragraph (2)is classified as proprietary because it contains detailed results of analytical models, methods and processes, including computer codes, which GE has developed or purchased and applied to evaluate the effect on structural frequencies of the BWR recirculation system pumps and piping due to pulsations in the motor air-gap torque produced by corresponding electrical harmonics in the pump motor.The development and application of the motor air-gap torque pulsation methodology and computer codes used in this analysis was achieved at a significant cost, on the order of one half million dollars, to GE.The development of interpretation and results is derived that constitutes a the evaluation process along with the application of the of the analytical from the extensive experience database major GE asset.(9)Public disclosure of the information sought to be withheld is likely to cause substantial harm to GE's competitive position and foreclose or reduce the availability of profit-making opportunities.
The information is part of GE's comprehensive BWR technology base, and its commercial value extends beyond the original development cost.The value of the technology base goes beyond the extensive physical database and analytical methodology and includes development of the expertise to determine and apply the appropriate evaluation process.The research, development, engineering and analytical costs comprise a substantial investment of time and money by GE.The precise value of the expertise to devise an evaluation process and apply the correct analytical methodology is difficult to quantify, but it clearly is substantial.
GE's competitive advantage will be lost if its competitors are able to use the results of the GE experience to normalize or verify their own process or if they are able to claim an equivalent understanding by demonstrating that they can arrive at the same or similar conclusions.
The value of this information to GE would be lost if the information were disclosed to the public.Making such information available to competitors without.their having been required to undertake a similar expenditure of resources would unfairly provide competitors with a windfall, and deprive GE of the opportunity to exercise its competitive advantage to seek an adequate return on its large investment in developing these very valuable analytical tools.STATE OF CALIFORNIA COUNTY OF SANTA CLARA David J.Robare, being duly sworn, deposes and says: That he has read the foregoing affidavit and the matters stated therein are true and correct to the best of his knowledge, information, and belief.Mp Executed at San Zose, California, this~day of S<~Q+6Q 19~David Z.Robare General Electric Company Subscribed and sworn before me this 4 day of Notary Pub ic, State of California MARY L KENDA1.L COMM.rrr 987854 r",o'g>..Nctory Pubic-Cor1fornlo s SANTA CLARA COUNTY"'y Ccmm.Exprres MAR 26.1997 9/1/93 Jf.a'C i'\d