Summary of Telephone Conference Call on December 9, 2009, Between Dominion Energy Kewaunee Inc., and U.S. NRC to Discuss Tables Referenced in the Work Control Process Amendment Letter
ML093431339
Person / Time
Site: Kewaunee Dominion icon.png
Issue date: 12/16/2009
From: Hernandez-Quinones S
License Renewal Projects Branch 1
To:
Dominion Energy Kewaunee
Hernandez S, NRR/DLR, 415-4049
References
TAC MD9408
Download: ML093431339 (4)


Text

December 16, 2009 LICENSEE: Dominion Energy Kewaunee, Inc.

FACILITY: Kewaunee Power Station

SUBJECT:

SUMMARY

OF TELEPHONE CONFERENCE CALL ON DECEMBER 14, 2009, BETWEEN DOMINION ENERGY KEWAUNEE, INC. AND U.S. NUCLEAR REGULATORY COMMISSION TO DISCUSS TABLES REFERENCED IN THE WORK CONTROL PROCESS AMENDMENT LETTER (TAC NO. MD9408)

On December 14, 2009, the U.S. Nuclear Regulatory Commission (NRC or the staff) conducted a telephone conference call (teleconference) with representatives from Dominion Energy Kewaunee, Inc (DEK). The purpose of the teleconference was to discuss the information presented by DEK on several tables of their Work Control Process Amendment letter dated September 25, 2009.

During the teleconference, the staff stated that information is missing from tables 3.3.2-6, 3.3.2-8, 3.3.2-14, 3.3.2-15, 3.3.2-19, 3.3.2-20, 3.3.2-22, 3.3.2-26, 3.3.2-27, 3.3.2-28, 3.4.2-1, 3.4.2-9, 3.4.2-10, 3.4.2-12, and 3.5.2-4. Specifically, the above mentioned tables make reference to footnotes that are not defined in the license renewal application (LRA) or the amendment letter.

In addition, the staff noted that inconsistencies had been made while assigning numbers to several RAIs that were sent to DEK in letters dated November 20, 2009, and December 3, 2009. The staff asked that DEK update their records to reflect the correct numbers for the RAIs as follows. The updated numbers for RAIs B2.1.3-4a, B2.1.31-5, and 3.3.2.3-1 are now B2.1.31-4a, B2.1.31-5a, and 3.4.2.3-1, respectively.

As a result of the discussions, DEK indicated that they will amend the affected tables and that the information to be referenced in the amended tables would be available on the LRA. A list of teleconference participants is enclosed.

/RA/

Samuel Hernandez, Project Manager Projects Branch 1 Division of License Renewal Office of Nuclear Reactor Regulation Docket No. 50-305

Enclosure:

As stated cc w/ encl: See next page

ML093431339 OFFICE PM:RPB1:DLR LA:RPOB:DLR BC:RPB1:DLR PM:DLR:RPB1 NAME SHernandez SFigueroa BPham SHernandez (Signature)

DATE 12/14/09 12/11/09 12/16/09 12/16/09

Memorandum to Dominion Energy Kewaunee, Inc. from Samuel Hernandez dated December 16, 2009

SUBJECT:

SUMMARY

OF TELEPHONE CONFERENCE CALL ON DECEMBER 14, 2009, BETWEEN DOMINION ENERGY KEWAUNEE, INC. AND U.S. NUCLEAR REGULATORY COMMISSION TO DISCUSS TABLES REFERENCED IN THE WORK CONTROL PROCESS AMENDMENT LETTER (TAC NO. MD9408)

DISTRIBUTION:

HARD COPY:

DLR RF E-MAIL:

PUBLIC RidsNrrDlr Resource RidsNrrDlrRpb1 Resource RidsNrrDlrRpb2 Resource RidsNrrDlrRarb Resource RidsNrrDlrRasb Resource RidsNrrDlrRapb Resource RidsNrrDlrRerb Resource RidsNrrDlrRpob Resource RidsNrrDciCvib Resource RidsNrrDciCpnb Resource RidsNrrDraAfpb Resource RidsNrrDeEmcb Resource RidsNrrDeEeeb Resource RidsNrrDssSrxb Resource RidsNrrDssSbpb Resource RidsNrrDssScvb Resource RidsOgcMailCenter Resource

________

S. Hernandez J. Daily V. Perin P. Tam S. Burton, RIII K. Barclay, RIII M. Kunowski, RIII V. Mitlyng, RIII I. Couret, OPA S. Uttal, OGC

LIST OF PARTICIPANTS TELEPHONE CONFERENCE CALL DOMINION ENERGY KEWAUNEE, INC.

KEWAUNEE POWER STATION December 9, 2009 PARTICIPANTS AFFILIATION Samuel Hernandez U.S. Nuclear Regulatory Commission (NRC)

On Yee NRC Paul Aitken Dominion Energy Kewaunee, Inc. (Dominion)

Mark Hotchkiss Dominion Stu Thickman Dominion ENCLOSURE

Kewaunee Power Station cc:

Resident Inspectors Office Mr. Paul C. Aitken U.S. Nuclear Regulatory Commission Supervisor - License Renewal Project N490 Hwy 42 Innsbrook Technical Center - 3NE Kewaunee, WI 54216-9510 5000 Dominion Boulevard Glen Allen, VA 23060-6711 Mr. Chris L. Funderburk Director, Nuclear Licensing and Mr. David A. Sommers Operations Support Supervisor - Nuclear Engineering Dominion Resources Services, Inc. Innsbrook Technical Center - 2SE Innsbrook Technical Center - 2SE 5000 Dominion Boulevard 5000 Dominion Boulevard Glen Allen, VA 23060-6711 Glen Allen, VA 23060-6711 Ms. Lillian M. Cuoco, Esq.

Mr. Thomas L. Breene Senior Counsel Dominion Energy Kewaunee, Inc. Dominion Resources Services, Inc.

Kewaunee Power Station 120 Tredegar Street N490 Highway 42 Riverside 2 Kewaunee, WI 54216 Richmond, VA 23219 Mr. Michael J. Wilson, Director Mr. Stephen E. Scace Nuclear Safety & Licensing Site Vice President Dominion Energy Kewaunee, Inc. Dominion Energy Kewaunee, Inc.

Kewaunee Power Station Kewaunee Power Station N490 Highway 42 N490 Highway 42 Kewaunee, WI 54216 Kewaunee, WI 54216 Mr. William R. Matthews Mr. David R. Lewis Senior Vice President - Nuclear Operations Pillsbury Winthrop Shaw Pittman, LLP Innsbrook Technical Center - 2SE 2300 N Street, N.W.

5000 Dominion Boulevard Washington, DC 20037-1122 Glen Allen, VA 23060-6711 Mr. Ken Paplham Mr. Alan J. Price E 4095 Sandy Bay Rd.

Vice President - Nuclear Engineering Kewaunee, WI 54216 Innsbrook Technical Center - 2SE 5000 Dominion Boulevard Mr. Jeff Kitsembel, P.E.

Glen Allen, VA 23060-6711 Public Service Commission of Wisconsin P.O. Box 7854 Mr. William D. Corbin Madison, WI 53707-7854 Director - Nuclear Engineering Innsbrook Technical Center - 3NE 5000 Dominion Boulevard Glen Allen, VA 23060-6711

Kewaunee Power Station cc:

Mr. David A. Heacock President and Chief Nuclear Officer Dominion Energy Kewaunee, Inc.

Innsbrook Technical Center - 2SW 5000 Dominion Boulevard Glen Allen, VA 23060-6711