Revision of Schedule for the Conduct of Review of the Kewaunee Power Station License Renewal Application
ML092790585
Person / Time
Site: Kewaunee Dominion icon.png
Issue date: 10/13/2009
From: Hernandez-Quinones S
License Renewal Projects Branch 1
To: Heacock D
Dominion Energy Kewaunee
Hernandez S, NRR/DLR, 415-4049
References
TAC MD9408
Download: ML092790585 (5)


Text

October 13, 2009 Mr. David A. Heacock President and Chief Nuclear Officer Dominion Energy Kewaunee, Inc.

Innsbrook Technical Center - 2SW 5000 Dominion Blvd.

Glen Allen, VA 23060-6711

SUBJECT:

REVISION OF SCHEDULE FOR THE CONDUCT OF REVIEW OF THE KEWAUNEE POWER STATION LICENSE RENEWAL APPLICATION (TAC NO. MD9408)

Dear Mr. Heacock:

Enclosed is a revised review schedule for the Kewaunee Power Station license renewal application (LRA). This schedule has been revised to reflect the impacts on the conduct of the review by the U.S. Nuclear Regulatory Commission (NRC or the staff) as a result of a recent amendment that included substantial changes to the information presented in the LRA.

The amendment was submitted in response to a public meeting that the staff conducted with representatives from Dominion Energy Kewaunee, Inc. (DEK) on July 28, 2009; regarding the use of an aging management program (AMP) for which the staff needed additional information to complete its review. During the meeting, DEK indicated that it intended to amend the LRA to make the AMP in question consistent with the recommendations contained in the Generic Aging Lessons Learned Report. A summary of the July 28, 2009 meeting is available in the NRCs Agencywide Documents Access and Management System (ADAMS) under accession number ML092100612. The ADAMS Public Electronic Reading Room is accessible at http://adamswebsearch.nrc.gov/dologin.htm.

If you have any questions on the revised schedule, please contact me by telephone at 301-415-4049 or by e-mail at Samuel.Hernandez@nrc.gov.

Sincerely,

/RA/

Samuel Hernandez, Project Manager Projects Branch 1 Division of License Renewal Office of Nuclear Reactor Regulation Docket No. 50-305

Enclosure:

As stated cc w/encl: See next page

October 13, 2009 Mr. David A. Heacock President and Chief Nuclear Officer Dominion Energy Kewaunee, Inc.

Innsbrook Technical Center - 2SW 5000 Dominion Blvd.

Glen Allen, VA 23060-6711

SUBJECT:

REVISION OF SCHEDULE FOR THE CONDUCT OF REVIEW OF THE KEWAUNEE POWER STATION LICENSE RENEWAL APPLICATION (TAC NO. MD9408)

Dear Mr. Heacock:

Enclosed is a revised review schedule for the Kewaunee Power Station license renewal application (LRA). This schedule has been revised to reflect the impacts on the conduct of the review by the U.S. Nuclear Regulatory Commission (NRC or the staff) as a result of a recent amendment that included substantial changes to the information presented in the LRA.

The amendment was submitted in response to a public meeting that the staff conducted with representatives from Dominion Energy Kewaunee, Inc. (DEK) on July 28, 2009; regarding the use of an aging management program (AMP) for which the staff needed additional information to complete its review. During the meeting, DEK indicated that it intended to amend the LRA to make the AMP in question consistent with the recommendations contained in the Generic Aging Lessons Learned Report. A summary of the July 28, 2009 meeting is available in the NRCs Agencywide Documents Access and Management System (ADAMS) under accession number ML092100612. The ADAMS Public Electronic Reading Room is accessible at http://adamswebsearch.nrc.gov/dologin.htm.

If you have any questions on the revised schedule, please contact me by telephone at 301-415-4049 or by e-mail at Samuel.Hernandez@nrc.gov.

Sincerely,

/RA/

Samuel Hernandez, Project Manager Projects Branch 1 Division of License Renewal Office of Nuclear Reactor Regulation Docket No. 50-305

Enclosure:

As stated cc w/encl: See next page DISTRIBUTION:

See next page ADAMS ACCESSION No: ML092790585 OFFICE PM:RPB1:DLR LA:RPOB:DLR PM:RPB1:DLR BC:RPB1:DLR PM:RPB1:DLR NAME SHernandez SFigueroa V.Perin B.Pham SHernandez (SHernandez for) (Signature)

DATE 10/09/09 10/09/09 10/09/09 10/09/09 10/13/09 OFFICIAL RECORD COPY

Letter to David A. Heacock from Samuel Hernandez dated October 13, 2009

SUBJECT:

REVISION OF SCHEDULE FOR THE CONDUCT OF REVIEW OF THE KEWAUNEE POWER STATION LICENSE RENEWAL APPLICATION (TAC NO. MD9408)

DISTRIBUTION:

HARD COPY:

DLR RF E-MAIL:

PUBLIC RidsNrrDlr Resource RidsNrrDlrRpb1 Resource RidsNrrDlrRpb2 Resource RidsNrrDlrRer1 Resource RidsNrrDlrRer2 Resource RidsNrrDlrRerb Resource RidsNrrDlrRpob Resource RidsNrrDciCvib Resource RidsNrrDciCpnb Resource RidsNrrDraAfpb Resource RidsNrrDeEmcb Resource RidsNrrDeEeeb Resource RidsNrrDssSrxb Resource RidsNrrDssSbpb Resource RidsNrrDssScvb Resource RidsOgcMailCenter Resource

________

S. Hernandez V. Perin P. Tam S. Burton K. Barclay M. Kunowski V. Mitlyng I. Couret S. Uttal, OGC

KEWAUNEE POWER STATION LICENSE RENEWAL APPLICATION UPDATED REVIEW SCHEDULE Milestone Scheduled Actual Receive license renewal application (LRA) 08/14/08 08/14/08 Publish Federal Register Notice (FRN) - LRA availability 08/26/08 08/29/08 Publish FRN - acceptance and opportunity for hearing 10/01/08 10/01/08 Publish FRN - intent to conduct environmental scoping 10/08/08 10/09/08 Public Meeting - license renewal overview / environmental scoping meeting 10/22/08 10/22/08 Deadline for filing hearing requests and petitions for intervention 12/01/08 12/01/08 Environmental scoping period ends 12/08/08 12/08/08 Audit - Scoping & Screening Methodology 03/09/09 03/09/09 Audit - Environmental 05/26/09 05/26/09 Audit - Aging Management 06/08/09 06/08/09 Audit - Aging Management 10/19/09 Issue draft Supplemental Environmental Impact Statement (SEIS) 12/04/09 Publish FRN - draft SEIS available for comments 12/11/09 Public Meeting - draft SEIS meeting 01/13/10 End of draft SEIS comment period 02/16/10 Issue Safety Evaluation Report (SER) with open items 06/04/10 Advisory Committee on Reactor Safeguards (ACRS) Subcommittee meeting 07/12/10 Issue final SEIS 06/01/10 U.S. EPA FRN Published - availability of final SEIS 06/11/10 Issue final SER 11/05/10 ACRS full committee meeting 12/06/10 Decision - Director NRR (30 months) 02/14/11 ENCLOSURE

Kewaunee Power Station cc:

Resident Inspectors Office Mr. Paul C. Aitken U.S. Nuclear Regulatory Commission Supervisor - License Renewal Project N490 Hwy 42 Innsbrook Technical Center - 3NE Kewaunee, WI 54216-9510 5000 Dominion Boulevard Glen Allen, VA 23060-6711 Mr. Chris L. Funderburk Director, Nuclear Licensing and Mr. David A. Sommers Operations Support Supervisor - Nuclear Engineering Dominion Resources Services, Inc. Innsbrook Technical Center - 2SE Innsbrook Technical Center - 2SE 5000 Dominion Boulevard 5000 Dominion Boulevard Glen Allen, VA 23060-6711 Glen Allen, VA 23060-6711 Ms. Lillian M. Cuoco, Esq.

Mr. Thomas L. Breene Senior Counsel Dominion Energy Kewaunee, Inc. Dominion Resources Services, Inc.

Kewaunee Power Station 120 Tredegar Street N490 Highway 42 Riverside 2 Kewaunee, WI 54216 Richmond, VA 23219 Mr. Michael J. Wilson, Director Mr. Stephen E. Scace Nuclear Safety & Licensing Site Vice President Dominion Energy Kewaunee, Inc. Dominion Energy Kewaunee, Inc.

Kewaunee Power Station Kewaunee Power Station N490 Highway 42 N490 Highway 42 Kewaunee, WI 54216 Kewaunee, WI 54216 Mr. William R. Matthews Mr. David R. Lewis Senior Vice President - Nuclear Operations Pillsbury Winthrop Shaw Pittman, LLP Innsbrook Technical Center - 2SE 2300 N Street, N.W.

5000 Dominion Boulevard Washington, DC 20037-1122 Glen Allen, VA 23060-6711 Mr. Ken Paplham Mr. Alan J. Price E 4095 Sandy Bay Rd.

Vice President - Nuclear Engineering Kewaunee, WI 54216 Innsbrook Technical Center - 2SE 5000 Dominion Boulevard Mr. Jeff Kitsembel, P.E.

Glen Allen, VA 23060-6711 Public Service Commission of Wisconsin P.O. Box 7854 Mr. William D. Corbin Madison, WI 53707-7854 Director - Nuclear Engineering Innsbrook Technical Center - 3NE 5000 Dominion Boulevard Glen Allen, VA 23060-6711