MONTHYEARML0514701152005-05-27027 May 2005 RAI, Response to Generic Letter 2004-02 Project stage: RAI ML0603704402006-02-0909 February 2006 RAI - Response to Generic Letter 2004-02, Potential Impact of Debris Blockage on Emergency Recirculation During Design-Basis Accident at Pressurized-Water Reactors Project stage: RAI ML0722706242007-08-15015 August 2007 MR-I-07-0018: Dominion Promotes David Christian to President/Chief Nuclear Officer Project stage: Request ML0729706052007-10-24024 October 2007 Exigent License Amendment Request Re Alternative Containment Analysis Methodology Supporting Information - Gothic Model Input Files Project stage: Request ML0731905532007-11-15015 November 2007 Request for Extension of Completion Dates for Corrective Actions Regarding NRC Generic Letter 2004-02 Project stage: Request ML0734505942007-12-13013 December 2007 Approval of Extension of Completion Dates for Corrective Actions of Generic Letter 2004-02 Project stage: Other ML0806505632008-02-29029 February 2008 Supplemental Response to NRC GL-04-002, Potential Impact of Debris Blockage on Emergency Recirculation During Design Basis Accidents at Pressurized-Water Reactors Project stage: Request ML0806505622008-02-29029 February 2008 Supplemental Response to NRC GL-2004-02, Potential Impact of Debris Blockage on Emergency Recirculation During Design Basis Accidents at Pressurized-Water Reactors Project stage: Request ML0806503142008-02-29029 February 2008 NRC Generic Letter 2004-02 Supplemental Response, Potential Impact of Debris Blockage on Emergency Recirculation During Design Basis Accidents at Pressurized-Water Reactors Project stage: Request ML0814905722008-05-29029 May 2008 Request for Extension of Completion Dates for Generic Letter 2004-02 Corrective Actions Project stage: Other ML0818302472008-07-0101 July 2008 Request for Extension of Completion Dates for Generic Letter 2004-02 Corrective Actions Project stage: Other ML0917406412009-06-22022 June 2009 Transmits Draft RAI on Generic Letter 2004-02 Re. Potential Impact of Debris Blockage of PWR Sumps Project stage: Draft RAI ML0917406492009-06-22022 June 2009 Draft RAI on Generic Letter 2004-02 Re. Potential Impact of Debris Blockage of PWR Sumps Project stage: Draft RAI ML0920400062009-08-14014 August 2009 RAI, Regarding Response to Generic Letter 2004-02 (Tac No. MC4691) Project stage: RAI ML0923801712009-08-28028 August 2009 Notice of Telephone Conference Meeting with Dominion Energy Kewaunee, to Discuss Licensees Proposed Response to Request Regarding Generic Letter 2004-02 Project stage: Meeting ML0926006432009-09-15015 September 2009 Handout 3 - Kewaunee Power Station, Agenda Setting Meeting 09/15/09 Project stage: Meeting ML0926003762009-09-15015 September 2009 Handout 2 - Drawings, Analyzed RCS - Not Limiting Break Project stage: Other ML0926000182009-09-15015 September 2009 Handout 1 - GSI-191 Resolution for Kewaunee Power Station Project stage: Other ML0926008992009-09-28028 September 2009 (KPS) - Summary of 9/15/09 Meeting Regarding the Licensees Proposed Response to the Request for Additional Information on Generic Letter 2004-02 Project stage: RAI ML0928702112009-10-14014 October 2009 Revised Questions 4, 6, 7, and 12 of Formal RAI Dated 08/14/2009 GL 2004-02 Project stage: RAI ML1011707792010-04-30030 April 2010 Notice of Meeting with Kewaunee Personnel to Discuss Kewaunees Proposed Response to an RAI Regarding Generic Letter 2004-02 Project stage: RAI ML1014005072010-05-19019 May 2010 E-mail Handouts for the 5/20/2010 Kewaunee Public Meeting Project stage: Meeting ML1014106432010-06-0909 June 2010 May 20, 2010 Summary of Meeting Regarding the Licensees Proposed Response to the Request for Additional Information on Generic Letter 2004-02 Project stage: RAI 2008-07-01
[Table View] |
Text
UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 August 28, 2009 MEMORANDUM TO:
Lois M. James, Chief Plant Licensing Branch 111-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation
- x
FROM:
Peter S. Tam, Senior Project Manag~.-r <<"
Plant Licensing Branch 111-1
/LN),}.
{tv....,
Division of Operating Reactor Licens' Office of Nuclear Reactor Regulation
SUBJECT:
FORTHCOMING MEETING BY TELEPHONE CONFERENCE WITH DOMINION ENERGY KEWAUNEE, INC. (TAC NO. MC4691)
DATE & TIME:
Tuesday, September 15, 2009 9:00 a.m. - 3:00 p.m. (Eastern Time)
LOCATION:
This is a meeting conducted by teleconference. Participation is solely by telephone. See "Category" below.
PURPOSE:
The purpose of this meeting is to discuss the licensee's proposed response to a Request for Additional Information dated August 14, 2009 (Agencywide Documents Access and Management System Accession No. ML092040006) regarding Generic Letter 2004-02, "Potential Impact of Debris Blockage on Emergency Recirculation during Design Basis Accidents at Pressurized-Water Reactors."
CATEGORY:
This is a Category 1* meeting via telephone conference. As such, the public is invited to listen to this call, and will have an opportunity to communicate with the NRC staff after the business portion, but before the call is adjourned. To participate, call 1-888-603-7090 using passcode 18838.
The NRC provides reasonable accommodation to individuals with disabilities where appropriate.
If you need reasonable accommodation to participate in a meeting, or need a meeting notice or a transcript or other information from a meeting in another format (e.g., Braille, large print),
please notify the NRC's meeting contact (identified below). Determinations on requests for reasonable accommodation will be made on a case-by-case basis.
MEETING CONTACT:
Peter Tam, NRR 301-415-1451 peter. tam@nrc.gov
- Commission's Policy Statement, "Enhancing Public Participation in !\\IRC Meetings" (67 FR 36920), May 28, 2002.
L. M. James PARTICIPANTS:
Docket No. 50-305
Enclosure:
Agenda
- 2 Participants from the NRC include members of the Office of Nuclear Reactor Regulation (NRR).
NRC P. Tam, NRR M. Scott, NRR R. Architzel, NRR S. Smith, NRR P. Klein, NRR et al.
cc w/enclosure: Distribution via ListServ DEK J. Gadzala T. Breene et al.
MEETING AGENDA FOR CONFERENCE CALL WITH DEK REGARDING KEWAUNEE POWER STATION GENERIC LETTER 2004-02 September 15, 2009 9:00 a.m. - 3:00 p.m. (ending time is only approximate)
- 1.
Introductions
- 2.
Overview of Kewaunee's GL 2004-02 Program
- 3.
Overview of Items Remaining to be Accomplished
- 4.
Discussion of Proposed Responses to NRC's August 14, 2009, Request for Additional Information
- 5.
Comments by members of the public (if any)
- 6.
Adjourn Enclosure
ML092380171 OFFICE DORL/LPL3-1/PM DORL/LPL3-1/LA DSS/SSIB/BC DORL/LPL3-1/BC NAME PTam BTully MScott*
LJames DATE 8/28/09 8/26/09 8/25/09*
8/28/09
- Concurrence bye-mail on the date shown