Similar Documents at Fermi |
---|
Category:MONTHLY OPERATING ANALYSIS REPORT
MONTHYEARNRC-99-0095, Monthly Operating Rept for Sept 1999 for Fermi 2.With1999-09-30030 September 1999 Monthly Operating Rept for Sept 1999 for Fermi 2.With NRC-99-0067, Monthly Operating Rept for Aug 1999 for Fermi 2.With1999-08-31031 August 1999 Monthly Operating Rept for Aug 1999 for Fermi 2.With NRC-99-0065, Monthly Operating Rept for July 1999 for Fermi 2.With1999-07-31031 July 1999 Monthly Operating Rept for July 1999 for Fermi 2.With NRC-99-0064, Monthly Operating Rept for June 1999 for Fermi 2.With1999-06-30030 June 1999 Monthly Operating Rept for June 1999 for Fermi 2.With NRC-99-0062, Monthly Operating Rept for May 1999 for Fermi 2.With1999-05-31031 May 1999 Monthly Operating Rept for May 1999 for Fermi 2.With NRC-99-0022, Monthly Operating Rept for Apr 1999 for Fermi 2.With1999-04-30030 April 1999 Monthly Operating Rept for Apr 1999 for Fermi 2.With ML20205P9721999-03-31031 March 1999 Monthly Operating Rept for Mar 1999 for Fermi 2 ML20204D0361999-02-28028 February 1999 Monthly Operating Rept for Feb 1999 for Fermi 2 ML20205Q9621998-12-31031 December 1998 Revised Monthly Operating Rept for Dec 1998 for Fermi 2 NRC-99-0005, Monthly Operating Rept for Dec 1998 for Fermi 2.With1998-12-31031 December 1998 Monthly Operating Rept for Dec 1998 for Fermi 2.With NRC-98-0153, Monthly Operating Rept for Nov 1998 for Fermi 2.With1998-11-30030 November 1998 Monthly Operating Rept for Nov 1998 for Fermi 2.With NRC-98-0160, Monthly Operating Rept for Oct 1998 for Fermi 2.With1998-10-31031 October 1998 Monthly Operating Rept for Oct 1998 for Fermi 2.With NRC-98-0139, Monthly Operating Rept for Sept 1998 for Fermi,Unit 2.With1998-09-30030 September 1998 Monthly Operating Rept for Sept 1998 for Fermi,Unit 2.With NRC-98-0111, Monthly Operating Rept for Aug 1998 for Fermi 2.With1998-08-31031 August 1998 Monthly Operating Rept for Aug 1998 for Fermi 2.With NRC-98-0109, Monthly Operating Rept for July 1998 for Fermi 21998-07-31031 July 1998 Monthly Operating Rept for July 1998 for Fermi 2 NRC-98-0097, Monthly Operating Rept for June 1998 for Fermi,Unit 21998-06-30030 June 1998 Monthly Operating Rept for June 1998 for Fermi,Unit 2 NRC-98-0079, Monthly Operating Rept for May 1998 for Fermi 21998-05-31031 May 1998 Monthly Operating Rept for May 1998 for Fermi 2 NRC-98-0076, Monthly Operating Rept for Apr 1998 for Fermi 21998-04-30030 April 1998 Monthly Operating Rept for Apr 1998 for Fermi 2 NRC-98-0072, Monthly Operating Rept for Mar 1998 for Fermi 21998-03-31031 March 1998 Monthly Operating Rept for Mar 1998 for Fermi 2 NRC-98-0050, Monthly Operating Rept for Feb 1998 for Fermi 21998-02-28028 February 1998 Monthly Operating Rept for Feb 1998 for Fermi 2 NRC-98-0019, Monthly Operating Rept for Jan 1998 for Fermi 21998-01-31031 January 1998 Monthly Operating Rept for Jan 1998 for Fermi 2 ML20205Q9601997-12-31031 December 1997 Revised Monthly Operating Rept for Dec 1997 for Fermi 2 NRC-98-0015, Monthly Operating Rept for Dec 1997 for Fermi 21997-12-31031 December 1997 Monthly Operating Rept for Dec 1997 for Fermi 2 NRC-97-0131, Monthly Operating Rept for Nov 1997 for Fermi 21997-11-30030 November 1997 Monthly Operating Rept for Nov 1997 for Fermi 2 NRC-97-0117, Monthly Operating Rept for Oct 1997 for Fermi 21997-10-31031 October 1997 Monthly Operating Rept for Oct 1997 for Fermi 2 NRC-97-0099, Monthly Operating Rept for Sept 1997 for Fermi 21997-09-30030 September 1997 Monthly Operating Rept for Sept 1997 for Fermi 2 ML20210V0441997-08-31031 August 1997 Monthly Operating Rept for Aug 1997 for Fermi 2 ML20210V0521997-07-31031 July 1997 Revised MOR for July 1997 for Fermi 2 NRC-97-0079, Monthly Operating Rept for Jul 1997 for Fermi 21997-07-31031 July 1997 Monthly Operating Rept for Jul 1997 for Fermi 2 NRC-97-0068, Monthly Operating Rept for June 1997 for Fermi,Unit 21997-06-30030 June 1997 Monthly Operating Rept for June 1997 for Fermi,Unit 2 NRC-97-0063, Monthly Operating Rept for May 1997 for Fermi 21997-05-31031 May 1997 Monthly Operating Rept for May 1997 for Fermi 2 NRC-97-0057, Monthly Operating Rept for Apr 1997 for Fermi 21997-04-30030 April 1997 Monthly Operating Rept for Apr 1997 for Fermi 2 NRC-97-0044, Monthly Operating Rept for Mar 1997 for Fermi 21997-03-31031 March 1997 Monthly Operating Rept for Mar 1997 for Fermi 2 NRC-97-0023, Monthly Operating Rept for Feb 1997 for Fermi 21997-02-28028 February 1997 Monthly Operating Rept for Feb 1997 for Fermi 2 ML20134L7851997-01-31031 January 1997 Monthly Operating Rept for Jan 1997 for Fermi 2 ML20134L8421996-12-31031 December 1996 Revised Monthly Operating Rept for Dec 1996 for Fermi 2 NRC-97-0011, Monthly Operating Rept for Dec 1996 for Fermi 21996-12-31031 December 1996 Monthly Operating Rept for Dec 1996 for Fermi 2 ML20134L8381996-11-30030 November 1996 Revised Monthly Operating Rept for Nov 1996 for Fermi 2 NRC-96-0139, Monthly Operating Rept for Nov 1996 for Fermi 21996-11-30030 November 1996 Monthly Operating Rept for Nov 1996 for Fermi 2 ML20134L8301996-10-31031 October 1996 Revised Monthly Operating Rept for Oct 1996 for Fermi 2 NRC-96-0102, Monthly Operating Rept for Oct 1996 for Fermi 21996-10-31031 October 1996 Monthly Operating Rept for Oct 1996 for Fermi 2 ML20134L8221996-09-30030 September 1996 Revised Monthly Operating Rept for Sept 1996 for Fermi 2 NRC-96-0080, Monthly Operating Rept for Sept 1996 for Fermi 21996-09-30030 September 1996 Monthly Operating Rept for Sept 1996 for Fermi 2 ML20134L8081996-08-31031 August 1996 Revised Monthly Operating Rept for Aug 1996 for Fermi 2 NRC-96-0077, Monthly Operating Rept for Aug 1996 for Fermi 21996-08-31031 August 1996 Monthly Operating Rept for Aug 1996 for Fermi 2 ML20134L8011996-07-31031 July 1996 Revised Monthly Operating Rept for Jul 1996 for Fermi 2 NRC-96-0073, Monthly Operating Rept for Ju1 1996 for Fermi 21996-07-31031 July 1996 Monthly Operating Rept for Ju1 1996 for Fermi 2 ML20134L7981996-06-30030 June 1996 Revised Monthly Operating Rept for June 1996 for Fermi 2 NRC-96-0070, Monthly Operating Rept for June 1996 for Fermi 21996-06-30030 June 1996 Monthly Operating Rept for June 1996 for Fermi 2 ML20134L7911996-05-31031 May 1996 Revised Monthly Operating Rept for May 1996 for Fermi 2 1999-09-30
[Table view] Category:TEXT-SAFETY REPORT
MONTHYEARML20217N4381999-10-25025 October 1999 Safety Evaluation Supporting Amend 17 to License DPR-9 ML20217P3551999-10-22022 October 1999 LER 99-S01-00:on 990922,loaded 9mm Handgun Was Discovered on Truck Cargo Area of Vehicle Inside Protected Area.Caused by Inadequate Vehicle Search.Guidance in Procedures & Security Training to Address Multiple Vehicle Searches Was Provided NRC-99-0095, Monthly Operating Rept for Sept 1999 for Fermi 2.With1999-09-30030 September 1999 Monthly Operating Rept for Sept 1999 for Fermi 2.With NRC-99-0067, Monthly Operating Rept for Aug 1999 for Fermi 2.With1999-08-31031 August 1999 Monthly Operating Rept for Aug 1999 for Fermi 2.With NRC-99-0065, Monthly Operating Rept for July 1999 for Fermi 2.With1999-07-31031 July 1999 Monthly Operating Rept for July 1999 for Fermi 2.With NRC-99-0088, Detroit Edison Co Enrico Fermi Atomic Power Plant,Unit 1 Annual Rept for Period 980701-990630. with1999-06-30030 June 1999 Detroit Edison Co Enrico Fermi Atomic Power Plant,Unit 1 Annual Rept for Period 980701-990630. with NRC-99-0064, Monthly Operating Rept for June 1999 for Fermi 2.With1999-06-30030 June 1999 Monthly Operating Rept for June 1999 for Fermi 2.With NRC-99-0062, Monthly Operating Rept for May 1999 for Fermi 2.With1999-05-31031 May 1999 Monthly Operating Rept for May 1999 for Fermi 2.With ML20206J9301999-05-10010 May 1999 SER Concluding That Util Adequately Addressed Actions Requested in GL 95-07, Pressure Locking & Thermal Binding of Safety-Related Powered-Operated Gate Valves ML20206G5081999-05-0505 May 1999 Safety Evaluation Approving Request for Relief PR-8,Rev 2 on Basis That Licensee Committed to Meet All Related Requirements of ASME OM-6 Std & PR-12 on Basis That Proposed Alternative Will Provide Acceptable Level of Safety NRC-99-0022, Monthly Operating Rept for Apr 1999 for Fermi 2.With1999-04-30030 April 1999 Monthly Operating Rept for Apr 1999 for Fermi 2.With ML20205Q7141999-04-15015 April 1999 Safety Evaluation Supporting Amend 16 to License DPR-9 ML20205P9721999-03-31031 March 1999 Monthly Operating Rept for Mar 1999 for Fermi 2 ML20204E0371999-03-17017 March 1999 Safety Evaluation Accepting Licensee Request for NRC Approval of Alternative Rv Weld Exam,Per Provisions of 10CFR50.55a(a)(3)(i) & 10CFR50.55a(g)(6)(ii)(A)(5) for Plant,Unit 2 for 40-month Period ML20204D0361999-02-28028 February 1999 Monthly Operating Rept for Feb 1999 for Fermi 2 ML20198S3341999-01-0606 January 1999 Safety Evaluation Supporting Amend 15 to License DPR-9 NRC-99-0005, Monthly Operating Rept for Dec 1998 for Fermi 2.With1998-12-31031 December 1998 Monthly Operating Rept for Dec 1998 for Fermi 2.With ML20207B7491998-12-31031 December 1998 1998 Annual Operating Rept for Fermi 2 ML20205Q9621998-12-31031 December 1998 Revised Monthly Operating Rept for Dec 1998 for Fermi 2 NRC-99-0021, 1998 Annual Financial Rept for Detroit Edison Co. with1998-12-31031 December 1998 1998 Annual Financial Rept for Detroit Edison Co. with NRC-98-0153, Monthly Operating Rept for Nov 1998 for Fermi 2.With1998-11-30030 November 1998 Monthly Operating Rept for Nov 1998 for Fermi 2.With NRC-98-0160, Monthly Operating Rept for Oct 1998 for Fermi 2.With1998-10-31031 October 1998 Monthly Operating Rept for Oct 1998 for Fermi 2.With ML20154R2331998-10-21021 October 1998 Safety Evaluation Supporting Amend 13 to License DPR-9 ML20154L1031998-10-14014 October 1998 Safety Evaluation Accepting Licensee Response to NRC Bulletin 95-002, Unexpected Clogging of Residual Heat Removal Pump Strainer While Operating in Suppression Pool Cooling Mode NRC-98-0139, Monthly Operating Rept for Sept 1998 for Fermi,Unit 2.With1998-09-30030 September 1998 Monthly Operating Rept for Sept 1998 for Fermi,Unit 2.With ML20154H8161998-09-30030 September 1998 Rev 0 to COLR Cycle 7 for Fermi 2 ML20153B8811998-09-18018 September 1998 Safety Evaluation Accepting Request for Relief from Certain Requirements of ASME Boiler & Pressure Vessel Code,Section Xi,For Plant,Unit 2 ML20151X0651998-09-11011 September 1998 Safety Evaluation Re Inservice Testing Program Relief Request VR-63 for Plant NRC-98-0111, Monthly Operating Rept for Aug 1998 for Fermi 2.With1998-08-31031 August 1998 Monthly Operating Rept for Aug 1998 for Fermi 2.With ML20153B7921998-08-31031 August 1998 Rev 0 to Fermi 1 Sar ML20237E1171998-08-25025 August 1998 Safety Evaluation Accepting Licensee Relief Requests for First 10-yr Interval Inservice Insp Nondestructive Exam Program ML20236X8611998-08-0505 August 1998 SER Related to Revised Feedwater Nozzle Analysis to Facility Operating License NPF-43,Enrico Fermi Nuclear Power Plant, Unit 2 NRC-98-0109, Monthly Operating Rept for July 1998 for Fermi 21998-07-31031 July 1998 Monthly Operating Rept for July 1998 for Fermi 2 ML20236K3261998-07-0101 July 1998 SER Accepting Licensee Response Related to Revised Feedwater Nozzle Analysis to License NPF-43 for Enrico Fermi Nuclear Power Plant,Unit 2 NRC-98-0097, Monthly Operating Rept for June 1998 for Fermi,Unit 21998-06-30030 June 1998 Monthly Operating Rept for June 1998 for Fermi,Unit 2 NRC-98-0127, Annual Rept for Period 970701-9806301998-06-30030 June 1998 Annual Rept for Period 970701-980630 NRC-98-0079, Monthly Operating Rept for May 1998 for Fermi 21998-05-31031 May 1998 Monthly Operating Rept for May 1998 for Fermi 2 NRC-98-0076, Monthly Operating Rept for Apr 1998 for Fermi 21998-04-30030 April 1998 Monthly Operating Rept for Apr 1998 for Fermi 2 NRC-98-0072, Monthly Operating Rept for Mar 1998 for Fermi 21998-03-31031 March 1998 Monthly Operating Rept for Mar 1998 for Fermi 2 NRC-98-0050, Monthly Operating Rept for Feb 1998 for Fermi 21998-02-28028 February 1998 Monthly Operating Rept for Feb 1998 for Fermi 2 NRC-98-0019, Monthly Operating Rept for Jan 1998 for Fermi 21998-01-31031 January 1998 Monthly Operating Rept for Jan 1998 for Fermi 2 ML20198L4241998-01-0808 January 1998 Safety Evaluation Accepting Proposed Rev 2 to Relief Request VR-51 Under Fermi 2 Pump & Valve Inservice Testing Program Per 10CFR50.55a(f)(6)(i) for First 10-yr Interval NRC-98-0015, Monthly Operating Rept for Dec 1997 for Fermi 21997-12-31031 December 1997 Monthly Operating Rept for Dec 1997 for Fermi 2 ML20217N3821997-12-31031 December 1997 Annual Operating Rept for 970101-1231 NRC-98-0053, 1997 Annual Financial Rept for Detroit Edison Company1997-12-31031 December 1997 1997 Annual Financial Rept for Detroit Edison Company ML20205Q9601997-12-31031 December 1997 Revised Monthly Operating Rept for Dec 1997 for Fermi 2 NRC-97-0141, Deficiency Rept Re Malfunction of EDG Number 11 Automatic Voltage Regulator (AVR) Printed Circuit Board Rev B,Due to Failure of Operational Amplifier U8 Chip.Avr Board Rev B Was Sent Offsite to Independent Engineering Facility1997-12-23023 December 1997 Deficiency Rept Re Malfunction of EDG Number 11 Automatic Voltage Regulator (AVR) Printed Circuit Board Rev B,Due to Failure of Operational Amplifier U8 Chip.Avr Board Rev B Was Sent Offsite to Independent Engineering Facility ML20197A9921997-12-15015 December 1997 Rev 0 to Efp,Unit 1 Fermi 1 Sar NRC-97-0131, Monthly Operating Rept for Nov 1997 for Fermi 21997-11-30030 November 1997 Monthly Operating Rept for Nov 1997 for Fermi 2 ML20248H1151997-10-31031 October 1997 Rev 1 to Colr,Cycle 6 for Fermi 2 1999-09-30
[Table view] |
Text
- - -
DOCKET No 50-341
. UNIT FERMI-2 DATE 06/03/86 COMPLETED BY L.P. Bregni TELEPHONE (313) 586-5313 OPERATING STATUS GROSS HOURS IN REPORTING PERIOD N/A
- 1. REPORTING PERIOD _May
- 2. CURRENTLY AUTHORIZED POWER LEVEL (K4t)165 MAX DEPEND CAPACITY (MJeNet)
DESIGN ELECTRICAL RATING (MRe Net) 1150
- 3. POWER LEVEL TO WHICH RESTRICTED (IF ANY) (KJe Net) 57.5
- 4. REASONS FOR RESTRICTION (IF ANY) Confirmatory Action Letter dated July 16, 1985 restricts power from exceeding 5% until authorized by NRC.
THIS MONTH YR TO DATE CUMULATIVE
- 5. NUMBER OF HOURS REACIOR WAS CRITICAL 0 0 1912.5
- 6. REACTOR RESERVE SHUIDOWN HOURS 0 0 0 O O O
- 7. HOURS GENERATOR ON LINE
- 8. UNIT RESERVE SHUTDOWN HOURS 0 0 0
- 9. GROSS THERMAL ENERGY CENERATED (KJH) 0 0 105.861_6
- 10. GROSS ELECTRICAL ENERGY GENERATED (KJH) 0 0 0
- 11. NET ELECTRICAL ENERGY GENERATED (MJH) 0 0 0
- 12. REACTOR SERVICE FACTOR N/A N/A N/A
- 13. REACTOR AVAILABILITY FACTOR N/A N/A _N/A
- 14. UNIT SERVICE FACTOR N/A N/A _N/ A
- 15. UNIT AVAILABILITY FACTOR N/A N/A N/A
- 16. UNIT CAPACITY FACTOR (Using MDC) N/A N/A N/A
- 17. UNIT CAPACITY FACTOR (Using Design K4e) N/A N/A N/A
- 18. UNIT FORCED OUTAGE RATE N/A N/A N/A
- 19. SHUTDOWNS SCHEDULED OVER NEXT 6 PONTHS (TYPE, DATE AND DURATION OF EACH)
- 20. IF SHUT DOWN AT END OF REPORT PERIOD, ESTIMATED DATE OF STARTUP 07/23/86 FORECAST ACHIEVED
- 21. UNITS IN TEST STATUS (PRIOR TO COMMERCIAL OPERATION)
INITIAL CRITICALITY 06/20/85 06/21/86 INITIAL ELECTRICITY 09/01/86 COMMERCIAL OPERATION 05/01/87_
0 1 IF9f
%B1hD a 'It
( _
AVERAGE DA1LY UNIT POWER LEVEL DOCKET No. 50-341 UNIT TERMI-2 DATE 06/03[86' COMPLETED BY L.P. Bregni .
TELEPHONE (313) 586- 5313 NONTH May DAY AVERAGE DAILY POWER LEVEL DAY AVERAGE DAILY PO'n'ER LEVEL
($'e-Ne t ) (E'e-Ne t )
17 0 1 0 0 18 0 2
0 19 0 3
20 0 4 0 0 21 0 5
0 22 0 6
23 0 7 0 0 24 0 8
0 25 0 9
0 26 0 lo 0 27 0 11 28 0 12 0 0 0 13 29 0 30 0
14 0
15 0 33 l
0 16 l
l l
I l
L
DOCKET NO. 50-341 , ,
UNIT SHUTDOWNS AND POWER REDUCTIONS UNIT NAME Fermi - 2 DATE 06/03/86 COMPLETED BY L.P. Bregni May TELEPHONE (313) 586. c;912 REPORT MONTH i . i m m s; o ; = .uz;
- - - o. mo mmi !
i
- i. i n o.<. mc . m momm.
- l l NR om A: EgI hl- =ss52: l
. . , c . mo . .o m s so.
NO I DATE ! 5
"" l ~z 5o l 02 l @8$$E '
CORRECTIVE ACTIONS / COMMENTS l l l : l l ;P moR: I
- ; ; ; ; ; ; l
, . . . . e . .
l 1 l 860501 ! s l* 744.0 l H l 4 l Plant has been shut down since l ,.
, l l l l l October 11, 1985 for a scheduled l 3
l l l maintenance outage and is still in !
' l the outage at this time !
3 l l l l
- 3 . e e e e s 3 . e a a i
- e.
e e i e a 3 i a e i e e 3 e 3 . . s e a e 3 . . . e e a 3 . . . . e e a a
3 . . . i e 3 e e. i 8
3 .e e i e e e 3 . . i e e e
e a e e a 3 i e e e s 3 e i 3 . e i e s e e e s 3 i 3 .i e e : 8
- i. e.
e e i e s 8
. . e e e e s
. . . a e i e 8
. . . .e .e .s l
. . . . e i
. . e ,
. i e s * ,
(1) REASONS A. EQUIPMENT FAILURE (EXPLAIN) E. OPERATOR TRAINING AND LICENSE EXAMINATION B. MAINT OR TEST F. ADMINISTRATIVE C. REFUELING G. OPERATIONAL ERnG2 (EXPIAIN)
D. REGULATORY RESTRICTION H. OTHER (EXPLAIN)
(2) METHOD .
- 1. MANUAL 3. AUTOMATIC SCRAM
- 2. MANUAL SCRAM 4. OTHER (EXPLAIN)
$N0!na'g7/"
s' Y i'nn oon. s,gn y hu 3, 1%6 Edison amte 'ee "P860249 r U. S. Nuclear Regulatory Commission Attention: Director, Office of Resource Management Washington, D.C. 20555 Gentlemen:
Reference:
Fermi 2 NRC Docket No. 50-341 NRC Operating License No. NPF-43
Subject:
Monthly Operating Status Report for May. 1986 Enclosed for your information and use is the Fermi 2 Monthly Operating Status Report for lay, 1986. This report includes the Operating Data Report, Average Daily Unit Power Level, and the Sun 7ary of Unit Shutdowns and Power Reductions identified in NRC Regulatory Guide 1.16 and Fermi 2 Technical Specification 6.9.1.6.
If you have any questions, please contact us.
Sincerely, R. S. Lenart Plant Manager Enclosure l
l cc: M.D. Lynch USNRC Document Control Desk W.G. Rogers Washington, D.C. 20555 G.C. Wright l
l Regional Administrator Mr. Dennis Hahn l USNRC Region III Division of Radiological Health 799 Roosevelt Rd. Michigan Department of Health Glen Ellyn, IL 60137 3500 North Logan P.O. Box 30033 Lansing, MI 48909 Mr. Jon Eckert Monroe City-County Office of Civil Preparedness I 965 South Raisinville Road 0'd
! Monroe, MI 48161
! /
l \\