Line 15: |
Line 15: |
|
| |
|
| =Text= | | =Text= |
| {{#Wiki_filter:UNITED STATES NUCLEAR REGULATORY COMMISSION REGION IV 1600 E. LAMAR BLVD. ARLINGTON, TX 76011-4511 August 6, 2015 MEMORANDUM TO: Arkansas Nuclear One Communication Team Members FROM: Troy W. Pruett /RA/ Executive Oversight Manager ANO 95003 Team | | {{#Wiki_filter:UNITED STATES NUCLEAR REGULATORY COMMISSION REGION IV 1600 E. LAMAR BLVD. ARLINGTON, TX 76011-4511 August 6, 2015 MEMORANDUM TO: Arkansas Nuc lear One Communication Team Members FROM: Troy W. Pruett |
| | /RA/ Executive Oversight Manager ANO 95003 Team |
|
| |
|
| ==SUBJECT:== | | ==SUBJECT:== |
| ARKANSAS NUCLEAR ONE INSPECTION PROCEDURE 95003 COMMUNICATION TEAM CHARTER The enclosed team charter establishes the purpose, objectives, and composition of the Arkansas Nuclear One (ANO) Inspection Procedure 95003 Communication Team. This team has been established to ensure that the agency's actions to address the root cause and corrective actions are clearly communicated and documented. This charter also defines the expected outcomes of the oversight process and the team membership. Questions involving the charter should be directed to Neil OKeefe at 817-200-1574 or Neil.OKeefe@nrc.gov. | | ARKANSAS NUCLEAR ONE INSPECTION PROCEDURE 95003 COMMUNICATION TEAM CHARTER The enclosed team charter establishes the purpose, objectives, and composition of the Arkansas Nuclear One (ANO) Inspection Procedure 95003 Communication Team. This team has been established to ensure that the agency's actions to address the root cause and corrective actions are clearly communicated and documented. This charter also defines the expected outcomes of the oversight process and the team membership. Questions involving the charter should be directed to Neil OKeefe at 817-200-1574 or Neil.OKeefe@nrc.gov |
| | . |
|
| |
|
| ==Enclosure:== | | ==Enclosure:== |
| Arkansas Nuclear One Inspection Procedure 95003 Communication Team Charter | | Arkansas Nuclear One Inspection Procedure 95003 Communication Team Charter |
|
| |
|
| SUNSI Review By: ADAMS Yes No Publicly Available Non-Publicly Available Non-Sensitive Sensitive OFFICE RIV/SPE RIV/BC RIV/D NAME NTaylor NOKeefe TPruett SIGNATURE /RA/ /RA/ /RA/ DATE 7/8/15 8/6/15 8/6/15 Enclosure ARKANSAS NUCLEAR ONE INSPECTION PROCEDURE 95003 COMMUNICATION TEAM CHARTER Purpose 1. The Communication Team exists to coordinate important senior management briefings and interface with other Commission officer and external stakeholders as necessary during the conduct of the inspection. Additionally, the team is responsible for coordinating the acquisition of additional resources as necessary to support the overall effort. | | SUNSI Review By: ADAMS Yes No Publicly Available Non-Publicly Available Non-Sensitive Sensitive OFFICE RIV/SPE RIV/BC RIV/D NAME NTaylor NOKeefe TPruett SIGNATURE /RA/ /RA/ /RA/ DATE 7/8/15 8/6/15 8/6/15 Enclosure ARKANSAS NUCLEAR ONE INSPECTION PROCEDURE 95003 COMMUNICATION TEAM CHARTER Purpose 1. The Communication Team exists to coordi nate important senior management briefings and interface with other Commission officer and external stakeholders as necessary during the conduct of the inspection. Additionally, the team is responsible for coordinating the acquisition of additional resources as necessary to support the overall effort. |
| Objectives The Team's duties and planned accomplishments include the following: 1. Create and maintain a public website to ensure effective communication with internal and external stakeholders. | | Objectives |
| : 2. Provide periodic briefings to the keep Communication Team members up to date on the status of licensee improvement activities and NRC inspection outcomes. 3. Seek input on appropriate communications and coordination actions. 4. Identify and develop topics for public meetings and Commission briefings. 5. Provide input for the lessons learned activities defined in Inspection Procedure 95003. Team Membership | | |
| * Troy Pruett, Director, Division of Reactor Projects and Executive Oversight Manager | | The Team's duties and planned accomplishments include the following: |
| | : 1. Create and maintain a public website to ensure effective communication with internal and external stakeholders. |
| | : 2. Provide periodic briefings to the keep Communication Team members up to date on the status of licensee improvement activities and NRC inspection outcomes. |
| | : 3. Seek input on appropriate communications and coordination actions. |
| | : 4. Identify and develop topics for public meetings and Commission briefings. |
| | : 5. Provide input for the lessons learned activities defined in Inspection Procedure 95003. |
| | Team Membership |
| | * Troy Pruett, Director, Division of Reacto r Projects and Executive Oversight Manager |
| * Allen Howe, Deputy Director, Division of Inspection and Regional Support, NRR | | * Allen Howe, Deputy Director, Division of Inspection and Regional Support, NRR |
| * Neil OKeefe, Chief, Branch E, Division of Reactor Projects, Region IV and Team Leader for 95003 | | * Neil OKeefe, Chief, Branch E, Division of Reactor Projects, Region IV and Team Leader for 95003 |
Line 35: |
Line 44: |
| * Andrea George, Project Manager, ANO, NRR/DORL | | * Andrea George, Project Manager, ANO, NRR/DORL |
| * Victor Dricks, Senior Public Affairs Officer, Region IV | | * Victor Dricks, Senior Public Affairs Officer, Region IV |
| * Bill Maier, Regional State Liaison Officer, Region IV The Chief, Branch E, Region IV is responsible for documenting and distributing the team meeting agendas and minutes. | | * Bill Maier, Regional State Liaison Officer, Region IV The Chief, Branch E, Region IV is responsible for documenting and distributing the team meeting agendas and minutes. |
|
| |
|
| }} | | }} |
|
---|
Category:Memoranda
MONTHYEARML24128A2402024-05-0808 May 2024 Entergy Operations, Inc. - Entergy Fleet Project Manager Assignment ML23047A3822023-03-21021 March 2023 Summary of December 15, 2022 Periodic Advanced Reactor Stakeholder Public Meeting ML22349A5052023-02-0808 February 2023 Results of a Reactor Oversight Process Self Assessment Effectiveness Review of the Recommendations from IP 95003 at Arkansas Nuclear One ML22147A0932022-06-0606 June 2022 2021 Annual Assessment Public Meeting Summary ML22034A3932022-02-16016 February 2022 Calendar Year 2021 Security Baseline Completion Memo ML21295A0882021-10-21021 October 2021 Fiscal Year 2021 Research and Test Reactors Inspection Program Completion Status ML21288A0392021-10-18018 October 2021 September 14, 2021, Summary of Public Workshop on Scale/Melcor Source Term Demonstration Project - Pebble-Bed Molten-Salt-Cooled Reactor ML21273A1772021-10-0101 October 2021 Fiscal Year 2021 Research and Test Reactors Inspection Program Completion Status ML21181A3352021-07-0101 July 2021 June 23, 2021, Summary of Public Meeting to Discuss Technology Inclusive Content of Application Project ML21158A2232021-06-0808 June 2021 Meeting Summary for Ticap Workshop 3 ML21140A3892021-05-24024 May 2021 Riv Column 1 EOC 2020 Public Meeting Summary ML21132A2952021-05-14014 May 2021 Summary of Public Meeting to Discuss Technology Inclusive Content of Application Project ML20337A1572020-12-0808 December 2020 Summary of Teleconference Meeting with Entergy Operations, Inc. to Discuss the Forthcoming Supplemental Response Concerning Generic Letter 2004-02 for Arkansas Nuclear One, Units 1 and 2 ML20149K5412020-11-23023 November 2020 Memo to File: Environmental Assessment and Finding of No Significant Impact and NRC Financial Analysis for Entergy Operations, Inc. Decommissioning Funding Plan Submitted in Accordance with 10 CFR 72.30(b) and (C) for Arkansas Nuclear One I ML20150A4212020-11-23023 November 2020 Memo to File: Environmental Assessment and Finding of No Significant Impact and NRC Financial Analysis for Entergy Nuclear Company, LLC Decommissioning Funding Plan Submitted in Accordance with 10 CFR 72.30(b) and (C) for Grand Gulf ISFSI ML19204A2972019-07-31031 July 2019 Memo to Management Review Board Arkansas Follow-up FY2019 Proposed Final Report ML18173A0082018-06-20020 June 2018 Cancelling Numerous Inspection Report Numbers ML17153A0012017-06-0606 June 2017 Staff Observations of Testing for Generic Safety Issue 191 During a May 10 to May 11, 2017, Trip to the Alden Test Facility for Control Components Inc. Strainer Tests ML16145A3392016-05-24024 May 2016 NRC Supplemental Inspection Procedure 95003 (Report - 05000313/2016007, and 05000368/2016007) List of Documents Reviewed ML16088A2042016-03-28028 March 2016 Memo T Bowers from s Ruffin, Technical Assistance Requests - Review 2015 Tri-Annual Decommissioning Funding Plans for Multiple Independent Spent Fuel Storage Installations W/ Encl 2 (Template) ML16088A2052016-03-28028 March 2016 Enclosure 1 - (72.30 DFP Reviews to Be Completed 2015) - Memo T Bowers from s Ruffin, Technial Assistance Requests - Review 2015 Tri-Annual Decommissioning Funding Plans for Multiple Independent Spent Fuel Storage Installations ML16076A2212016-03-16016 March 2016 NRC Supplemental Inspection Procedure 95003 (Report 05000313/2016007, 05000368/2016007) Request for Information ML16061A3622016-03-0101 March 2016 OEDO-15-00641 DPO-2015-001 on the Significance Determination Process Evaluation for a Finding at Arkansas Nuclear One Involving the March 2013, Unit 1 Stator Drop Event, Redacted-Public ML15292A2412015-10-21021 October 2015 October 28, 2015, Notice of Forthcoming Closed Meeting to Discuss Dam Failure Analysis for Arkansas Nuclear One, Units 1 and 2 ML15218A6042015-08-0606 August 2015 Inspection Procedure 95003 Communication Team Charter ML15089A1642015-04-27027 April 2015 Summary of February 25, 2015, Partially Closed Meeting with Industry Stakeholders Regarding the Babcock and Wilcox Loss of Coolant Accident Evaluation Model Analysis ML14356A1722014-12-22022 December 2014 Summary of Site Audit to Support the Review of a License Amendment Request for Arkansas Nuclear One, Unit 2 to Transition to the National Fire Protection Association (NFPA) Standard 805 Fire Protection Licensing Basis ML14351A2602014-12-19019 December 2014 Memo C K Bladey Re Notice of Issuance of Exemption from Holtec Intl CoC No. 1014 Fuel Specification and Loading Conditions at Arkansas Nuclear One ISFSI ML14356A5612014-12-17017 December 2014 Third-Party Assessment of Safety Culture ML14345B0652014-12-11011 December 2014 Memo C Bladey Re Federal Register Notice of Issuance of Environmental Assessment and Finding of No Significant Impact ANO Units 1 & 2 ISFSI 72-12 and 72-1014 ML14213A4272014-09-12012 September 2014 Summary of July 16, 2014, Closed Meeting Between Representatives of the U.S. Army Corps of Engineers Nuclear Regulatory Commission, and Entergy Operations Inc. to Discuss Flooding Analysis Associated with Arkansas Nuclear One, Units 1 and 2 ML14184B2432014-07-10010 July 2014 Notice of Forthcoming Closed Meeting to Discuss Dam Failure Analysis for Arkansas Nuclear One, Units 1 and 2 ML14163A0502014-06-13013 June 2014 Summary of Conference Call with Arkansas Nuclear One, Unit 2, Regarding the Spring Steam Generator Inspections ML13269A2082013-12-12012 December 2013 Cover Memo from B. Caldwell to M. Markley RAI for Arkansas Nuclear One (ANO) Revision 15 Security Plan Review ML13255A4872013-09-10010 September 2013 Request for Additional Information to Entergy Operations, Arkansas Nuclear One-Units 1 and 2, Regarding NTTF Recommendation 9.3 Phase 1 Staffing Assessment Submittal ML12324A4222012-11-14014 November 2012 Meeting Notice with Entergy Operations, Inc. to Discuss the Status of the Revised Application for Arkansas Nuclear One, Unit 2 to Transition to National Fire Protection Association (NFPA) Standard 805 ML12319A1222012-11-14014 November 2012 Notice of Forthcoming Meeting with Entergy Operations, Inc. to Discuss Resubmittal of License Amendment Request to Adopt National Fire Protection Association (NFPA) Standard 805 at Arkansas Nuclear One, Unit 2 ML12271A2482012-09-27027 September 2012 10/9/2012 Notice of Forthcoming Meeting with Entergy Operations, Inc. to Discuss Resubmittal of License Amendment Request to Adopt National Fire Protection Association (NFPA) Standard 805 at Arkansas Nuclear One, Unit 2 ML12166A1002012-06-18018 June 2012 Forthcoming Meeting on 6/29/12 with Entergy Operations, Inc. to Discuss License Amendment Request to Adopt National Fire Protection Association (NFPA) Standard 805 at Arkansas Nuclear One, Unit 2 ML1214600172012-05-30030 May 2012 June 12-13, 2012, Notice of Meeting at the Plant Site in Russellville, AR to Discuss Entergy Operations, Inc.'S License Amendment Request to Adopt National Fire Protection Association (NFPA) Standard 805 at Arkansas Nuclear One, Unit 2 ML1134801002011-12-19019 December 2011 Notice of Forthcoming Meeting with Exelon Generation Company, LLC, and Entergy Operations, Inc., to Discuss Steam Generator Inspection Results at Three Mile Island, Unit 1, and Arkansas Nuclear One, Unit 1 ML1116101632011-09-0707 September 2011 Review of Amendment 22 of Safety Analysis Report - Period from 10/6/2008 Through 3/18/2010 ML1123506752011-08-31031 August 2011 Notice of Meeting with Entergy Operations, Inc. to Discuss a Proposed License Amendment Request for Arkansas Nuclear One, Unit 2, for Its Revised Fuel Handling Accident (Fha) Analysis and Several Technical Specification Task Force Travel ML1115704052011-06-0606 June 2011 Notice of Meeting with Entergy Operations, Inc., to Discuss Implementation of Quality Oversight and Verification Programs at Entergy Sites Including Actions Being Taken to Enhance Effectiveness ML11116A0332011-04-29029 April 2011 Monthly Operating Reports for the 1st Quarter of 2011 ML1111009242011-04-29029 April 2011 Summary of 3/15/11 (P.M. Session) Meeting with Entergy Operations, Inc. to Discuss Arkansas Nuclear One, Unit 1 Planned License Amendment Request for Technical Specification Change Service Water System Related Support Features ML1109506462011-04-11011 April 2011 Verbal Authorization of Request for Alternative ANO1-R&R-015, Request for Use of Non-ASME Code Repair to Service Water Piping in Accordance with Generic Letter 90-05, Fourth 10-Year Interval ML1108804522011-03-30030 March 2011 Notice of Forthcoming Meeting with Entergy Operations, Inc., to Discuss Proposed License Amendment Request to Adopt NFPA 805 for Arkansas Nuclear One, Units 1 and 2 ML1107504052011-03-21021 March 2011 Notice of Meeting with Entergy Operations, Inc., to Discuss Fleetwide Submittal for Proposed Technical Specification and Quality Assurance Program Manual Changes Related to Unit Staff Qualification Requirements ML1106200032011-03-0303 March 2011 3/15/11 Notice of Forthcoming Meeting with Entergy Operations, Inc. to Discuss Arkansas Nuclear One, Unit 1 Planned License Amendment Request for Technical Specification Change Service Water System Related Support Features 2024-05-08
[Table view] Category:Operating Procedures
MONTHYEARML15218A6042015-08-0606 August 2015 Inspection Procedure 95003 Communication Team Charter ML0504505952004-05-27027 May 2004 E-mail Discharge Test ML0412000722003-12-0909 December 2003 Procedure 2403.24, Perform 2D11 Station Battery Quarter. ML0412000572003-10-0202 October 2003 to 2D12-1989, 2D12 Performance Test. ML0412000552003-10-0202 October 2003 Procedure/Work Plan No. 2403.001, Change 009-00-0, Unit II 2D11 Performance Electrical Maintenance. ML0319707352003-07-0909 July 2003 Change No 018-03-0 to OP-1903.062, Communications System Operating Procedure. ML0236101542002-12-18018 December 2002 Document Update Notification, Change No. 018-02-0 for Document OP-1903.062, Titled, Communications System Operating Procedure. ML0412000532002-04-22022 April 2002 Proc/Work Plan No. 2403.001, Change 008-03-0 Unit II 2D11 Performance Test Electrical Maintenance. ML0209200842002-03-20020 March 2002 Communications System Operating Procedure ML0205904052002-02-21021 February 2002 OP-1903.033, Revision No. 018-01-0, Change No. PC-01, Protective Action Guidelines for Rescue/Repair & Damage Control Teams. ML0201105002001-10-23023 October 2001 07-00-00, Change AP-07 to OP-1903.035, Administration of Potassium Iodide. ML0037278552000-06-23023 June 2000 Revision No. 006-04-0, Change No. PC-04 for OP-1903.035, Administration of Potassium Iodide. 2015-08-06
[Table view] |
Text
UNITED STATES NUCLEAR REGULATORY COMMISSION REGION IV 1600 E. LAMAR BLVD. ARLINGTON, TX 76011-4511 August 6, 2015 MEMORANDUM TO: Arkansas Nuc lear One Communication Team Members FROM: Troy W. Pruett
/RA/ Executive Oversight Manager ANO 95003 Team
SUBJECT:
ARKANSAS NUCLEAR ONE INSPECTION PROCEDURE 95003 COMMUNICATION TEAM CHARTER The enclosed team charter establishes the purpose, objectives, and composition of the Arkansas Nuclear One (ANO) Inspection Procedure 95003 Communication Team. This team has been established to ensure that the agency's actions to address the root cause and corrective actions are clearly communicated and documented. This charter also defines the expected outcomes of the oversight process and the team membership. Questions involving the charter should be directed to Neil OKeefe at 817-200-1574 or Neil.OKeefe@nrc.gov
.
Enclosure:
Arkansas Nuclear One Inspection Procedure 95003 Communication Team Charter
SUNSI Review By: ADAMS Yes No Publicly Available Non-Publicly Available Non-Sensitive Sensitive OFFICE RIV/SPE RIV/BC RIV/D NAME NTaylor NOKeefe TPruett SIGNATURE /RA/ /RA/ /RA/ DATE 7/8/15 8/6/15 8/6/15 Enclosure ARKANSAS NUCLEAR ONE INSPECTION PROCEDURE 95003 COMMUNICATION TEAM CHARTER Purpose 1. The Communication Team exists to coordi nate important senior management briefings and interface with other Commission officer and external stakeholders as necessary during the conduct of the inspection. Additionally, the team is responsible for coordinating the acquisition of additional resources as necessary to support the overall effort.
Objectives
The Team's duties and planned accomplishments include the following:
- 1. Create and maintain a public website to ensure effective communication with internal and external stakeholders.
- 2. Provide periodic briefings to the keep Communication Team members up to date on the status of licensee improvement activities and NRC inspection outcomes.
- 3. Seek input on appropriate communications and coordination actions.
- 4. Identify and develop topics for public meetings and Commission briefings.
- 5. Provide input for the lessons learned activities defined in Inspection Procedure 95003.
Team Membership
- Troy Pruett, Director, Division of Reacto r Projects and Executive Oversight Manager
- Allen Howe, Deputy Director, Division of Inspection and Regional Support, NRR
- Neil OKeefe, Chief, Branch E, Division of Reactor Projects, Region IV and Team Leader for 95003
- Nick Taylor, Senior Project Engineer, Branch E, Region IV and Assistant Team Leader for 95003
- Mike Markley, Chief, Plant Licensing Branch IV-1, NRR/DORL
- Bill Maier, Regional State Liaison Officer, Region IV The Chief, Branch E, Region IV is responsible for documenting and distributing the team meeting agendas and minutes.