NRC Supplemental Inspection Procedure 95003 (Report - 05000313/2016007, and 05000368/2016007) List of Documents Reviewed
ML16145A339
Person / Time
Site: Arkansas Nuclear  Entergy icon.png
Issue date: 05/24/2016
From: John Dixon
NRC/RGN-IV/DRP/RPB-E
To:
John Dixon
References
IR 2016007
Download: ML16145A339 (31)


See also: IR 05000313/2016007

Text

x SUNSI Review

By: JLDixon

ADAMS

x Yes No

x Publicly Available

Non-Publicly Available

x Non-Sensitive

Sensitive

OFFICE

RIV/DRP

RIV/DRP

NAME

JDIXON

NOKEEFE

SIGNATURE

/RA/

/RA/

DATE

5/13/16

5/13/16

- 1 -

Enclosure

DOCUMENTS REVIEWED

AREA ACTION PLANS

Title

ROOT CAUSE EVALUATIONS (RCE)

Number

Title

Revision/Date

CR-ANO-C-2013-0888

Unit-1 Main Turbine Generator Stator

0

CR-ANO-C-2014-2318

NOV Stator Lift Assembly Collapse, EN-MA-

119 Non-Compliance

1-4

CR-ANO-C-2015-1240

Corrective Action Program Implementation

0-1

CR-ANO-C-2015-2829

Leadership Fundamentals

0-1

CR-ANO-C-2015-2831

Organizational Capacity

0-1

CR-ANO-C-2015-2833

Design and Licensing Basis

0-1

CR-ANO-C-2015-2834

Preventative Maintenance

0-1

CR-ANO-C-2015-2836

Corporate and Independent Oversight

0-1

CR-ANO-C-2015-2838

Vendor Oversight

0

CR-ANO-C-2015-4647

Procedure Use and Adherence

0

CR-ANO-2-2013-2242

Unit Auxiliary Transformer 2X-02 Bus Faults

and 2X-02 Explosion/Fire

0

CR-ANO-C-2013-1304

Degraded Flood Barrier

0

CR-ANO-2-2014-0707

ANO-2 Trip from 100% Power While Aligned to

Offsite Power (Startup 3 Transformer-2X-03)

0

Corporate Oversight

Corrective Action Program

Decision Making and Risk Management

Design and Licensing Basis

Flood Protection Program

Leadership Fundamentals

Lift Rig and Vendor Oversight

Nuclear Fundamentals

Nuclear Safety Culture

Organizational Capacity

Plant Health

Preventative Maintenance

Procedure and Work Instruction Quality

Training

- 2 -

Enclosure

ROOT CAUSE EVALUATIONS (RCE)

Number

Title

Revision/Date

CR-ANO-2-2015-0362

Unplanned Reactor Scrams

0

CR-ANO-C-2014-1142

Flood Protection Issues

0-3

CR-ANO-C-2015-2832

Decision Making and Risk Management

0-1

CR-ANO-C-2015-4626

Training to Improve Organization Performance

0

RECOVERY PROCEDURES (RC)

Number

Title

Revision/Date

EN-LI-123-B2, IACPD

ANO Allocation of Resources Assessment

0

EN-LI-123-A6

Recovery Project Review Boards

0

EN-LI-123-B5

Nuclear Safety Culture Assessment

0

EN-LI-123-B4

Assessment of Performance in the Reactor

Safety Strategic Performance Area (IP 95003)

0

EN-LI-123-B3

Historical Data Review

0

EN-DC-115-ANO-RC

Entergy Nuclear Management Manual -

Engineering Change Process

0

EN-LI-123-A2

Recovery Team Assessments

0

EN-LI-123-A1

Recovery Project Administrative Controls

0

EN-LI-118-ANO-RC

Root Cause Evaluation Process

2

EN-LI-123-12-ANO-RC

Comprehensive Recovery Plan and

Performance Metrics

0-1

EN-LI-123-B7

Collective Evaluation and Action Plan

Development

0

EN-LI-123-B8

Comprehensive Recovery Plan and

Performance Metrics

0

EN-LI-123-04-ANO-RC

Recovery Project Administrative Controls

0

EN-LI-123-05-ANO-RC

Recovery Team Assessments

0

KAR - Configuration Control Assessment

0

KAR - Design Assessment

3

- 3 -

Enclosure

RECOVERY PROCEDURES (RC)

Number

Title

Revision/Date

EN-FAP-PM-003

Project Implementation - Segment 1 and 2

3

EN-LI-123-B4-FA-001,

KAR

Air Operated Valve (AOV) Program Focused

Assessment

December 1,

2015

EN-LI-123-B2-FA-002,

IACPD

ANO PM Technical Basis and Program

Assessment

0

EN-QV-136-ANO-RC

Nuclear Safety Culture Monitoring

0

EN-LI-123-07-ANO-RC

Identification, Assessment and Correction of

Performance Deficiencies (IACDP) Review

EN-LI-123-11-ANO-RC

Collective Evaluation and Action Plan

Development

EN-LI-123-09-ANO-RC

Assessment of Performance in the Reactor

Safety Strategic Performance Area (IP 95003)

EN-LI-123-10-ANO-RC

Nuclear Safety Culture Assessment

EN-LI-123-08-ANO-RC

Historical Data Review

0

EN-LI-102-ANO-RC

Corrective Action Program

0-2

PROCEDURES

Number

Title

Revision/Date

EN-HU-105

Human Performance - Managed Defenses

15

EN-LI-118-ANO

Root Cause Analysis Process

7

EN-LI-104

Self-Assessment and Benchmark Process

11

EN-FAP-LI-003

Corrective Action Review Board (CARB)

Process

17

EN-FAP-PM-004

Project Implementation - Segment 3 and 4

3

EN-FAP-OM-020

Comprehensive Recovery Plans

1

EN-HU-106

Procedure and Work Instruction Use and

Adherence

3

EN-OM-123

Fatigue Management Program

12

EN-OU-108

Shutdown Safety Management Program

(SSMP)

8

EN-QV-125

Major Project Oversight

6

EN-WM-104

On Line Risk Assessment

12

EN-FAP-LI-002

Project Review Boards

0

- 4 -

Enclosure

PROCEDURES

Number

Title

Revision/Date

EN-FAP-LI-005

Recovery Project Admin Controls

0

EN-FAP-LI-004

Corrective Action Program Performance

Indicators

3

EN-FAP-OM-016

Performance Management Processes and

Practices

6

EN-FAP-OM-005

Nuclear Performance Indicator Program

2-3

EN-FAP-LI-001

Condition Review Group (CRG)

5

EN-LI-102

Corrective Action Program

24

EN-LI-121

Trending and Performance Review Process

18

EN-LI-121-01

Trend Codes

7

EN-LI-121-02

Trend Analysis

1

EN-DC-336

Plant Health Committee

8

EN-OP-111

Operational Decision Making Issue (ODMI)

Process

11-12

EN-FAP-PM-001

Asset Management Plan Development, Tracking

and Control

2

EN-DC-143

Engineering Health Reports

18

EN-DC-143-01

System and Component Health Report

Supplemental Guidance

12

EN-FAP-MP-008

Processing Obsolete Items Identified During the

Procurement Process

1

EN-OE-100

Operating Experience Program

24

EN-OE-100-01

IER Level 1 and Level 2 Evaluations and

Effectiveness Reviews

1

EN-OE-100-02

Operating Experience Evaluations

1

EN-OP-105

Conduct of Operations

16

EN-OP-115

Conduct of Operations

16

EN-RP-502

Inspection and Maintenance of Respiratory

Protection Equipment

9

EN-WM-105

Planning

16

EN-TQ-201-04

SAT - Implementation Phase

6

EN-TQ-212

Conduct of Training and Qualification

14

EN-EC-101

Differing Professional Opinion Resolution

Process

0

EN-AD-101

Procedure Process

26

- 5 -

Enclosure

PROCEDURES

Number

Title

Revision/Date

EN-LI-123-2

Safety Culture Review

4

EN-QV-134

Employee Survey Response Protocol

2

EN-QV-136

Nuclear Safety Culture Monitoring

4-6

EN-PL-190

Maintaining a Strong Safety Culture

0-4

EN-PL-187

Safety Conscious Work Environment (SCWE)

Policy

0-2

FQC-PI-ACE

Apparent Cause Evaluator

0

FQC-PI-RCE

Root Cause Evaluator

0

EN-PL-155

Entergy Nuclear Change Management

9

EN-TQ-130

Project Management Training Program

0

1015.004A,

COPD-020

ANO Operations Concerns Program

9

1403.151

Unit 1 Relay Calibration for DG1 and DG2

Generator

9

EN-WM-100

Work Request (WR) Generation, Screening and

Classification

12

FFAM-PM-001

Project Management Job Familiarization Guide

0

EN-FAP-OM-011

Corporate Oversight Model

12

EN-OP-104

Operability Determination Process

10

EN-OP-115-03

Shift Turnover and Relief

2

1903.010

Emergency Action Level Classification

52

EN-FAP-OM-002

Management Review Meetings

4

EN-FAP-OP-006

Operator Aggregate Impact Index Performance

Indicator

2

EN-OP-115-01

Operator Rounds

0

EN-OP-122

Operational Decision-Making Issue Precursor

Process

0

EN-TQ-104

Engineering Support Personnel Training

Program

19

5000.025

ANO Coatings Assessment Program

1

1005.002

Control of Heavy Loads

28

- 6 -

Enclosure

PROCEDURES

Number

Title

Revision/Date

1015.047

Condition Reporting Immediate Reportability

Determination

6

1015.036

Containment Building Closeout

44

1015.001

Conduct of Operations

110

1015.003A

Unit 1 Operations Logs

92

1104.027

Battery and Switchgear Emergency Cooling

System

48

1104.020

Clean Waste System Operation

59

1202.011

HPI Cooldown

7

1203.001

ICS Abnormal Operation

13

1203.023

Small Steam Generator Tube Leaks

22

1203.024

Loss of Instrument Air

1203.045

Rapid Plant Shutdown

17

1203.012N

Annunciator K16 Corrective Action

47

1405.016

Unit 1 Penetration Fire Barrier Visual Inspection

20

1412.001

Preventative Maintenance of Limitorque

SB/SMB Motor Operators

48

1304.037

Unit 1 Reactor Protection System Channel A

Test

70

1304.063

Unit 1 P-7A Speed Control Calibration

26

1403.179

Molded Case Circuit Breaker Testing

28

2106.006

Emergency Feedwater System Operations

90

2202.004

Steam Generator Tube Rupture

14

2202.005

Excess Steam Demand

15

2203.21

Loss of Instrument Air

17

2203.038

Primary to Secondary Leakage

15

2203.053

Rapid Power Reduction

3

COPD-013

Operations Maintenance Interface Standards

and Expectations

52

EN-OP-102

Protective and Caution Tagging

18

EN-OP-102-01

Protective and Caution Tagging Forms and

Checklist

10

- 7 -

Enclosure

PROCEDURES

Number

Title

Revision/Date

EN-HU-102

Human Performance Traps & Tools

14

COPD-024

Risk Assessment Guidelines

58

EN-DC-151

PRA Maintenance and Update

5

EN-FAP-OM-021

Critical Decision Procedure

1

EN-FAP-WM-002

Critical Evolutions

3

EN-MA-119

Material Handling Program

24

EN-MA-119-01

Control, Storage, and Inspection of Lifting

Equipment

7

EN-DC-319

Boric Acid Control Program (BACCP)

11

EN-DC-344

Large Motor Program

4

EN-MA-123

Identification and Trending of Rework

8

EN-TQ-119

Maintenance Training Program

9

EN-TQ-119-02

Mechanical Maintenance Training Program

1

EN-TQ-119-03

Electrical Maintenance Training Program

2

EN-DC-148

Vendor Manuals and the Vendor Re-Contact

Process

5

EN-MA-101

Conduct of Maintenance

18

EN-WM-101

On-line Work Management Process

12

EN-WM-102

Work Implementation and Closeout

9

EN-FAP-WM-011

Work Planning Standard

4

EN-FAP-WM-012

Work Management Process Indicators

3

EN-DC-324

Preventive Maintenance Program

15

EN-DC-153

Preventive Maintenance Component

Classification

12

EN-DC-310

Predictive Maintenance Program

7

EN-EP-305

Emergency Planning 10 CFR 50.54(q) Review

Program

1-3

EN-EP-306

Drills and Exercises

7

- 8 -

Enclosure

PROCEDURES

Number

Title

Revision/Date

EN-EP-308

Emergency Planning Critiques

3

EN-TQ-110

Emergency Response Organization Training

12

EN-TQ-110-01

Fleet E-Plan Training Course Summary

3

EP-002

EP Desk Guide: Early Warning System

12

EP-003

EP Desk Guide: OSC Emergency Response

Facility Walkthrough

19

EP-006

EP Desk Guide: Drill/Exercise Manual

Addendum

11-12

EP-017

EP Desk Guide: AEOF Emergency Response

Facility Walkthrough

13

EP-008

EP Desk Guide: EOF Emergency Response

Facility Walkthrough

34

1203.0121

Annunciator K10 Corrective Action

54

1903.003

Assignment of Personnel to the Emergency

Response Organization (ERO)

21

1903.004

Administration and Maintenance of the

Emergency Plan and Implementing Procedures

31

1903.10

Emergency Action Level Classification

51-52

1903.11

Emergency Response / Notifications

48 & 50

1903.062

Communications System Operating Procedure

28

1903.069

Equipment Important to Emergency

Preparedness

3

2203.012K

Annunciator 2K11 Corrective Action

45

EN-DC-329

Engineering Programs Control and Oversight

6

EN-DC-105

Entergy Nuclear Management Manual -

Configuration Management

4

EN-DC-112

Entergy Nuclear Management Manual -

Engineering Change Request Process

8

EN-DC-126

Entergy Nuclear Management Manual -

Engineering Calculation Process

5

EN-DC-132

Entergy Nuclear Management Manual - Control

of Engineering Documents

7

EN-DC-134

Entergy Nuclear Management Manual - Design

Verification

6

EN-EC-100-01

Employee Concern Coordinator Training

Program

1

- 9 -

Enclosure

PROCEDURES

Number

Title

Revision/Date

EN-EC-100

Guidelines for Implementation of the Employee

Concerns

9

2104.037

Alternate AC Diesel Generator Operations

31

1403.152

Unit 1 A4 Bus Undervoltage Relay Calibration

10

FCBT-GET-PATSS

Entergy Fleet Plant Access Training

22

EN-HR-138

Executive Review Board Process for Employees

5

EN-HR-138-01

Executive Review Board for Supplemental

Personnel

1

EN-DC-195

Margin Management

8

EN-MA-130

NMM FIN Team Process

3

EN-OM-126

Management and Oversight of Supplemental

Personnel

11

EN-OM-126-02

Qualification of Responsible Oversight for

Supplemental Personnel

2

EN-OM-126-03

Qualification of Supplemental Supervisors

2

EN-OM-OU-103

Long Range Outage Planning

3

EN-FAP-OU-100

Refueling Outage Preparation and Milestones

7

EN-FAP-OU-104

Refueling Outage Scope Identification and

Control

4

SEP-WTI-ANO-001

Wall Thinning Inspection (WTI)

1

SEP-ISI-ANO1-101

ASME Section XI, Division 1 ANO 1 Inservice

Inspection Program

1

SEP-ISI-ANO2-105

ASME Section XI, Division 1 ANO 2 Inservice

Inspection Program

1

EN-DC-167

Classification of Structures, Systems, and

Components

8

EN-DC-184

NRC Generic Letter 89-13 Service Water

Program

3

EN-DC-340

Microbiologically Influenced Corrosion (MIC)

Monitoring Program

3

EN-DC-348

Non-EQ Insulated Cables and Connections

Inspection

5

1412.054

Unit 1 AC Motor Control Centers

32

EN-FAP-LR-007

Evaluation of Aging Management Programs

6

- 10 -

Enclosure

PROCEDURES

Number

Title

Revision/Date

EN-FAP-LR-020

License Renewal Implementation

2

SEP-RR-ANO-C-001

ASME Repair Replacement Program

2

1203.012H

Annunciator K09 Corrective Action

46

1032.036

Service Water Piping Leak Evaluation and

Monitoring

4

1402.009

P-7 A&B Emergency Feedwater Pump

Maintenance

12

2104.039

HPSI System Operation

45

2311.002

Service Water System Flow Test

21

2305.020

SW to EFW Flush and MOV DP Tests

10

PQR-107

1

6030.110

Termination, Splicing and Soldering of Cable

and Wire

004-050-0

EN-DC-222

Facility Ratings per NERC Reliability Standard

FAC-008

0

EN-DC-349

Metal Enclosed Bus Inspection Procedure

3

EN-DC-346

Cable Reliability Program

6

1203.25

Natural Emergencies

56

2203.008

Natural Emergencies

38

6030.101

Installation of Penetration Seals

12

2412.074

Unit 2 AC Motor Control Centers

21

ENGINEERING

REPORTS

Number

Title

Revision/Date

OAR 1431

Inservice Inspection Summary Report for Twenty-

Fifth Refueling Outage (1R25)

May 21, 2015

OAR 1422

Inservice Inspection Summary Report for the

Twenty-Fourth Refueling Outage (1R24), ANO -

Unit 1

October 8, 2013

OAR 2421

Inservice Inspection Summary Report for the

Twenty-Third Refueling Outage (2R23)- ANO Unit 2

August 18, 2014

- 11 -

Enclosure

ENGINEERING REPORTS

Number

Title

Revision/Date

OAR 2412

Inservice Inspection Summary Report for the

Twenty-Second Refueling Outage (2R22) ANO -

Unit2

December 3,

2012

2-BOP-UT-15-048

Service Water Supply Header #2-MIC 2.B.2.13

September 1,

2015

A-EP-2005-001

ANO Microbiological Influenced Corrosion (MIC)

Program

1

NF001099

NALCO Analysis - Unit 1 Service Supply To

Reactor Building Coolers VCC-2A/2B (A EFW

Pump Room)

November 7,

2011

NF001100

NALCO Analysis - Unit 1 Intake (P-4A Discharge At

Upstream Weld of CV-3646)

November 1,

2011

ANO2 2P32C

RCP Discharge - DMW

September 11,

2009

ANO2 2P32D

RCP Discharge - DMW

September 10,

2009

ANO2 2SI-15B

Safety Injection Nozzle - DMW

September 12,

2009

Design Report Update: Upgraded Public Alert and

Notification System (ANS) Arkansas Nuclear One

(ANO)

May 2009

Arkansas Nuclear One On-Shift Staffing Analysis

Final Report

December 13,

2012

1903.062C

Emergency Response Staffing Drill Report -

Quarterly Call-In Drill

June 27, 2011

1903.062C

Emergency Response Staffing Drill Report -

Quarterly Call-In Drill

June 22, 2012

1903.062C

Emergency Response Staffing Drill Report - Off

Hours Mobilization Drill

November 27,

2012

1903.062C

Emergency Response Staffing Drill Report -

Quarterly Call-In Drill

August 23,

2014

1903.062C

Emergency Response Staffing Drill Report - Off

Hours Mobilization Drill

September 10,

2015

EP-2011-0023

Arkansas Nuclear One ANS Design Report Update

Corrections

June 14,

2011

- 12 -

Enclosure

WORK ORDERS (WO)

52577704

52608471

52370372

52367410

00347269

52331320

52531334

52508905

52571931

00389851

00241168

0369570

00412506

0353954 03

00353954 09

00353954 17

00353954 19

00253954 30

00353954 45

00354318 01

00346560 30

00354320 01

00414355 04

52273592 01

52517147 01

52516176 01

00128151 01

00128143 01

52366905 01

51670375 01

0021546501

5240333301

5259301401

52544655 01

5227083301

0035994401

5248507101

00369706

00393937

435863

0036449901

5253132301

0028543101

00122821

00122823

ENGINEERING REPORTS

Number

Title

Revision/Date

EP-2015-024

December 9, 2015 Full Scale Drill

January 8,

2016

NQ-2007-007

QA Surveillance Report QS-2007-ANO-001

April 17, 2007

NQ-2010-008

Quality Assurance Surveillance Report QS-2010-

ANO-003

April 27, 2009

NQ-2011-010

Quality Assurance Audit Report QA-07-2011-ANO-1

June 28, 2011

1903.062C

Emergency Response Staffing Drill Report -

Quarterly Call-In Drill

February 27,

2014

1903.062C

Emergency Response Staffing Drill Report -

Quarterly Call-In Drill

March 15, 2013

NQ-2015-028

Quality Assurance Audit Report QA-07-2015-ANO-

01, Emergency Plan

June 10, 2015

TRAINING LESSON PLANS

Number

Title

Revision/Date

ASLPSTASRO

1603

Operability Determination Functionality Assessment

Fundamentals

January 26,

2016

ASLPOPSTAG

1603

Tagging OE

January 26,

2016

ASWKBEAL16

03

EAL Workbook

January 25,

2016

A1LPNLORRX

T1603

Reactor Theory

January 21,

2016

- 13 -

Enclosure

WORK ORDERS (WO)

5151546901

5257036701

5244879101

0036958301

0039057501

0015558801

5235599001

5260741801

435862

52608471

5220054901

5257584001

5254548301

5226553301

5260741801

0015558801

5235599001

ENGINEERING REQUESTS (ER)

002409E201

974487E201

ER-ANO-2005-

0149-005

ER-ANO-2003-

0258-000

ER-ANO-2005-

0149-004

ER-963419E201

ER-991392-E301 ER-ANO-2001-

1205-001

ENGINEERING CHANGE (EC)

002409E201

974487E201

EC-34948

EC-46318

EC-51913

EC-51777

EC-51778

EC-48771

EC-45635

EC-5568

EC-46389

EC-52545

EC-53949

EC-62927

EC-49725

EC-15295

DESIGN CHANGE PACKAGE (DCP)

Number

Title

Revision/Date

EQUIVALENT CHANGE (EC)

Number

Title

Revision/Date

92-2021

ANO Offsite Power Regulation for Start-Up #3 and

Start-Up #2

September 29,

1994

93-1003

ANO Offsite Power Regulation for Start-Up #1

September 1,

1993

EC-52493

Provide justification and documentation to mitigate

the risk of water induced electrical faults associated

with the Startup Transformer #2 switchgear 2A-111,

2A-211, 2H-13, 2H-23 and associated non-

segregated buses and also associated with Startup

Transformer #3 switchgear 2A-113, 2A-213, 2H-15,

2H-25 and associated non-segregated buses.

July 13, 2015

EC-45220

Evaluate minor changes associated with the repair

and reinstallation of the power cables

- 14 -

Enclosure

ACTION REQUESTS (ARs)

228139

229523

229036

228140

CONDITION REPORTS (CRs) FROM NRC QUESTIONING

CR-ANO-1-2016-00339

CR-ANO-1-2016-00472

CR-ANO-1-2016-00511

CR-ANO-1-2016-00340

CR-ANO-1-2016-00473

CR-ANO-1-2016-00517

CR-ANO-1-2016-00341

CR-ANO-1-2016-00474

CR-ANO-1-2016-00733

CR-ANO-1-2016-00342

CR-ANO-1-2016-00481

CR-ANO-1-2016-00739

CR-ANO-1-2016-00343

CR-ANO-1-2016-00484

CR-ANO-1-2016-00767

CR-ANO-1-2016-00347

CR-ANO-1-2016-00486

CR-ANO-1-2016-00768

CR-ANO-1-2016-00348

CR-ANO-1-2016-00487

CR-ANO-1-2016-00769

CR-ANO-1-2016-00350

CR-ANO-1-2016-00488

CR-ANO-1-2016-00689

CR-ANO-1-2016-00352

CR-ANO-1-2016-00490

CR-ANO-1-2016-00824

CR-ANO-1-2016-00353

CR-ANO-1-2016-00491

CR-ANO-1-2016-00834

CR-ANO-1-2016-00354

CR-ANO-1-2016-00492

CR-ANO-1-2016-00836

CR-ANO-1-2016-00356

CR-ANO-1-2016-00493

CR-ANO-1-2016-00839

CR-ANO-1-2016-00357

CR-ANO-1-2016-00494

CR-ANO-C-2016-00428

CR-ANO-1-2016-00372

CR-ANO-1-2016-00439

CR-ANO-2-2016-00343

CR-ANO-1-2016-00374

CR-ANO-1-2016-00445

CR-ANO-2-2016-00346

CR-ANO-1-2016-00375

CR-ANO-1-2016-00641

CR-ANO-2-2016-00347

CR-ANO-1-2016-00545

CR-ANO-1-2016-00592

CR-ANO-2-2016-00417

CR-ANO-1-2016-00549

CR-ANO-1-2016-00606

CR-ANO-2-2016-00421

COMPLETED SURVEILLANCE, MAINTENANCE AND MODIFICATION TESTING

Number

Title

Revision/Date

5220.009, Unit-2

5220.009, Unit-2, Containment Building & Exterior

Structural Inspection

September 20,

2015

2-ISI-VT-15-147

2-ISI-VT-15-147, Visual Examination of IWE

Surfaces (General), Summary A2.E1.11.WS-028

October 20,

2015

2-ISI-VT-15-148

2-ISI-VT-15-148, Visual Examination of IWE

Surfaces (General), Summary A2.E1.11.WS-029

October 20,

2015

2-ISI-VT-15-149

2-ISI-VT-15-149, Visual Examination of IWE

Surfaces (General), Summary A2.E1.11.WS-030

October 10,

2015

2-ISI-VT-15-159

2-ISI-VT-15-159, Visual Examination of IWE

Surfaces (General), Summary A2.E1.30, Moisture

Barrier

October 29,

2015

2-ISI-VT-15-162

2-ISI-VT-15-162, Visual Examination of IWE

Surfaces (General), Summary A2.E1.30, Moisture

Barrier

November 3,

2015

1405.016, U-1

OP-1405.016, U-1, Penetration Fire Barrier Visual

Inspections

20

2405.016, U-2

OP-2405.016, U-2, Penetration Fire Barrier Visual

20

- 15 -

Enclosure

CONDITION REPORTS (CRs) FROM NRC QUESTIONING

CR-ANO-1-2016-00550

CR-ANO-1-2016-00333

CR-ANO-2-2016-00921

CR-ANO-1-2016-00551

CR-ANO-1-2016-00334

CR-ANO-2-2016-00391

CR-ANO-1-2016-00552

CR-ANO-1-2016-00335

CR-ANO-2-2016-00396

CR-ANO-2-2016-00508

CR-ANO-1-2016-00336

CR-ANO-2-2016-00397

CR-ANO-2-2016-00490

CR-ANO-1-2016-00337

CR-ANO-2-2016-00398

CR-ANO-2-2016-00510

CR-ANO-1-2016-00338

CR-ANO-2-2016-00399

CR-ANO-2-2016-00533

CR-ANO-2-2016-00670

CR-ANO-2-2016-00401

CR-ANO-2-2016-00632

CR-ANO-2-2016-00672

CR-ANO-2-2016-00403

CR-ANO-2-2016-00431

CR-ANO-2-2016-00674

CR-ANO-2-2016-00508

CR-ANO-2-2016-00445

CR-ANO-2-2016-00676

CR-ANO-1-2016-00098

CR-ANO-2-2016-00404

CR-ANO-2-2016-00677

CR-ANO-C-2016-00418

CR-ANO-2-2016-00405

CR-ANO-2-2016-00287

CR-ANO-C-2016-00435

CR-ANO-2-2016-00406

CR-ANO-2-2016-00372

CR-ANO-C-2016-00434

CR-ANO-2-2016-00407

CR-ANO-2-2016-00375

CR-ANO-1-2016-01075

CR-ANO-2-2016-00408

CR-ANO-C-2016-00446

CR-ANO-1-2016-01087

CR-ANO-2-2016-00410

CR-ANO-C-2016-00456

CR-ANO-C-2016-00524

CR-ANO-2-2016-00412

CR-ANO-C-2016-00457

CR-ANO-2-2016-00443

CR-ANO-2-2016-00413

CR-ANO-C-2016-00463

CR-ANO-2-2016-00454

CR-ANO-C-2016-00178

CR-ANO-C-2016-00471

CR-ANO-2-2016-00722

CR-ANO-C-2016-00074

CR-ANO-C-2016-00476

CR-ANO-2-2016-00730

CR-ANO-C-2016-0399

CR-ANO-C-2016-00478

CR-ANO-2-2016-00648

CR-ANO-C-2016-0422

CR-ANO-C-2016-00479

CR-ANO-2-2016-00264

CR-ANO-C-2016-0425

CR-ANO-C-2016-00480

CR-ANO-2-2016-00283

CR-ANO-C-2016-0462

CR-ANO-C-2016-00482

CR-ANO-C-2016-00419

CR-ANO-C-2016-0510

CR-ANO-C-2016-01264

CR-ANO-C-2016-00563

CR-ANO-C-2016-00230

CR-ANO-C-2016-00582

CR-ANO-C-2016-00582

CR-ANO-C-2016-00323

CR-ANO-1-2016-00209

CR-ANO-1-2016-00236

CR-ANO-C-2016-00400

CR-ANO-C-2016-00558

CR-ANO-1-2016-00606

CR-ANO-C-2016-00463

CR-ANO-C-2016-00782

CR-ANO-1-2016-00402

CR-ANO-C-2016-00571

CR-ANO-C-2016-01224

CR-ANO-1-2016-00396

CR-ANO-C-2016-01224

CR-ANO-C-2016-01264

CR-ANO-2-2016-00677

CR-ANO-C-2016-01264

CR-ANO-C-2016-00651

CR-ANO-2-2016-00670

CR-ANO-C-2016-00678

CR-ANO-2-2016-00361

CR-ANO-2-2016-00421

CR-ANO-C-2016-00614

CR-ANO-C-2016-00679

CR-ANO-C-2016-00587

CR-ANO-C-2016-01348

CR-ANO-1-2016-01102

CR-ANO-1-2016-00488

CR-ANO-C-2016-01389

CR-ANO-2-2016-01319

CR-ANO-2-2016-00789

CR-ANO-2-2016-00946

CR-ANO-C-2016-01528

CR-ANO-C-2016-00377

CR-ANO-C-2016-00895

CR-ANO-C-2016-01529

CR-ANO-1-2016-00769

CR-ANO-1-2016-00401

CR-ANO-1-2016-00787

CR-ANO-1-2016-00778

CR-ANO-1-2016-00438

CR-ANO-2-2016-00343

CR-ANO-1-2016-00149

CR-ANO-1-2016-00397

CR-ANO-C-2016-00588

CR-ANO-C-2016-00255

CR-ANO-1-2016-00056

CR-ANO-2-2016-00764

CR-ANO-1-2016-00320

CR-ANO-C-2016-0462

CR-ANO-C-2016-00803

CR-ANO-C-2016-00328

CR-ANO-C-2016-00331

CR-ANO-C-2016-00816

CR-ANO-1-2016-00334

- 16 -

Enclosure

CONDITION REPORTS (CRs) FROM NRC QUESTIONING

CR-ANO-1-2016-00490

CR-ANO-C-2016-00838

CR-ANO-1-2016-00240

CR-ANO-C-2016-0399

CR-ANO-C-2016-00884

CR-ANO-1-2016-00279

CR-ANO-C-2016-0422

CR-ANO-C-2016-00895

CR-ANO-C-2016-01131

CR-ANO-2-2016-00375

CR-ANO-C-2016-00905

CR-ANO-C-2016-01155

CR-ANO-C-2016-00194

CR-ANO-1-2016-00352

CR-ANO-1-2016-00237

CONDITION REPORTS (CRs)

CR-ANO-C-2015-2221

CR-ANO-C-2015-2286

CR-ANO-C-2015-2451

CR-ANO-C-2015-2323

CR-ANO-C-2015-1864

CR-ANO-C-2015-2282

CR-ANO-1-2015-2346

CR-ANO-C-2015-2467

CR-ANO-C-2015-2244

CR-ANO-C-2015-2241

CR-ANO-C-2015-2775

CR-ANO-C-2015-1746

CR-ANO-2-2015-1746

CR-ANO-C-2015-2328

CR-ANO-C-2015-2328

CR-ANO-C-2015-2406

CR-ANO-C-2015-2379

CR-ANO-C-2015-2368

CR-ANO-C-2015-2318

CR-ANO-C-2015-2523

CR-ANO-C-2015-1245

CR-ANO-C-2015-2500

CR-ANO-1-2015-2643

CR-ANO-C-2014-2488

CR-ANO-1-2014-00759

CR-ANO-2-2015-01671

CR-ANO-C-2011-02942

CR-ANO-1-2015-02230

CR-ANO-2-2015-05263

CR-ANO-C-2014-00259

CR-ANO-1-2015-02618

CR-ANO-2-2015-02879

CR-ANO-C-2015-01240

CR-ANO-1-2015-02619

CR-ANO-C-2015-02831

CR-ANO-C-2015-02145

CR-ANO-1-2015-02620

CR-ANO-2-2015-01826

CR-ANO-C-2015-02241

CR-ANO-1-2015-02621

CR-ANO-C-2015-01032

CR-ANO-C-2015-02244

CR-ANO-1-2015-02628

CR-ANO-2-2015-00797

CR-ANO-C-2015-02245

CR-ANO-1-2015-02630

CR-ANO-2-2014-02970

CR-ANO-C-2015-02249

CR-ANO-1-2015-02633

CR-ANO-C-2014-02814

CR-ANO-C-2015-02829

CR-ANO-1-2015-02634

CR-ANO-1-2014-01628

CR-ANO-C-2015-02832

CR-ANO-1-2015-02670

CR-ANO-2-2013-01961

CR-ANO-C-2015-02834

CR-ANO-1-2015-04178

CR-ANO-2-2013-01913

CR-ANO-C-2015-03030

CR-ANO-2-2013-02502

CR-ANO-1-2009-01045

CR-ANO-C-2015-03567

CR-ANO-2-2015-02879

CR-ANO-1-2008-02560

CR-ANO-C-2015-04389

CR-ANO-1-2015-00882

CR-ANO-1-2005-01140

CR-ANO-C-2015-02831

CR-ANO-C-2015-03029

CR-ANO-1-2015-03272

CR-ANO-C-2013-02916

CR-ANO-C-2006-00665

CR-ANO-C-2010-00977

CR-ANO-C-2010-02502

CR-ANO-C-2012-00098

CR-ANO-C-2012-00358

CR-ANO-C-2013-00666

CR-ANO-C-2013-00781

CR-ANO-2-2015-04328

CR-ANO-C-2014-02478

CR-ANO-C-2015-03618

CR-ANO-C-2015-04767

CR-ANO-C-2014-02596

CR-ANO-C-2014-02597

CR-ANO-C-2015-02834

CR-ANO-C-2015-02388

CR-ANO-C-2015-04198

CR-ANO-1-2004-00668

CR-ANO-C-2015-02982

CR-ANO-C-2015-04521

CR-ANO-C-2015-03663

CR-ANO-C-2015-00712

CR-ANO-C-2015-04766

CR-ANO-C-2015-04884

CR-ANO-C-2015-04768

CR-ANO-C-2015-04769

CR-ANO-C-2015-04865

CR-ANO-C-2015-04879

CR-ANO-C-2015-04406

CR-ANO-C-2015-04893

CR-ANO-C-2015-04881

CR-ANO-C-2015-04950

CR-ANO-C-2015-01493

CR-ANO-C-2015-02385

- 17 -

Enclosure

CONDITION REPORTS (CRs)

CR-ANO-C-2015-04769

CR-ANO-C-2015-03033

CR-ANO-C-2015-04770

CR-ANO-C-2015-04659

CR-ANO-C-2015-02413

CR-ANO-C-2015-01239

CR-ANO-C-2013-02823

CR-ANO-C-2013-02973

CR-ANO-C-2014-03276

CR-ANO-C-2015-02336

CR-ANO-C-2015-02406

CR-ANO-C-2015-01342

CR-ANO-2-2013-02242

CR-ANO-C-2011-01540

CR-ANO-1-2015-02735

CR-ANO-1-2015-02230

CR-ANO-C-2015-02412

CR-ANO-1-2015-01940

CR-ANO-C-2004-02078

CR-ANO-C-2015-02365

CR-ANO-2-2015-02253

CR-ANO-2-2013-01621

CR-ANO-C-2015-01962

CR-ANO-1-2015-00795

CR-ANO-2-2013-01620

CR-ANO-C-2015-01577

CR-ANO-1-2013-01054

CR-ANO-2-2013-01616

CR-ANO-2-2014-00707

CR-ANO-2-2015-04711

CR-ANO-C-2010-01551

CR-ANO-2-2015-00550

CR ANO-C-2015-03031

CR-ANO-C-2003-00905

CR-ANO-2-2013-00565

CR ANO-C-2015-02830

CR-ANO-1-2003-00958

CR ANO-C-2013-02838

CR ANO-C-2015-04677

CR-ANO-2-2003-01417

CR-ANO-1-2015-02857

CR-ANO-1-2015-02353

CR-ANO-2-2003-01544

CR-ANO-2-2015-03105

CR-ANO-1-2015-02631

CR-ANO-1-2005-00578

CR-ANO-1-2007-01622

CR-ANO-1-2015-02306

CR-ANO-2-2015-05156

CR-ANO-C-2015-01711

CR-ANO-1-2013-02185

CR-ANO-1-2010-01457

CR-ANO-2-2014-00232

CR-ANO-1-2013-02846

CR-ANO-2-2011-00386

CR-ANO-C-2014-00259

CR-ANO-2-2015-04749

CR-ANO 2-2011-01098

CR-ANO-2-2014-00264

CR-ANO-1-2015-01028

CR-ANO 1-2011-01680

CR-ANO-1-2015-00193

CR-ANO-1-2015-02346

CR-ANO 1-2013-00510

CR-ANO-1-2015-00200

CR-ANO-2-2015-01634

CR-ANO 2-2013-00892

CR-ANO-1-2015-00498

CR-ANO-2-2015-02221

CR-ANO C-2013-01097

CR-ANO-1-2015-00762

CR-ANO-2-2015-03011

CR-ANO C-2013-01156

CR-ANO-1-2015-00861

CR-ANOC-2015-01284

CR-ANO C-2013-01304

CR-ANO-1-2015-00881

CR-ANO-C-2015-01493

CR-ANO 2-2013-01822

CR-ANO-C-2013-02916

CR-ANO-2-2015-05013

CR-ANO-C-2014-00202

CR-ANO-C-2015-03229

CR-ANO-C-2015-03033

CR-ANO-C-2014-00210

CR-ANO-2-2015-04187

CR-ANO-C-2015-03942

CR-ANO-C-2015-2379

CR-ANO-C-2014-2488

CR-ANO-C-2015-02838

CR-ANO-C-2015-2368

CR-ANO-2-2015-04348

CR-ANO-C-2015-05072

CR-ANO-C-2015-2436

CR-ANO-2-2015-04386

CR-ANO-C-2015-2175

CR-ANO-C-2015-1864

CR-ANO-1-2015-00902

CR-ANO-C-2014-01925

CR-ANO-1-2015-02643

CR-ANO-1-2015-01112

CR-ANO-1-2015-00627

CR-ANO-C-2015-02285

CR-ANO-2-2014-00648

CR-ANO-1-2015-05010

CR-ANO-C-2015-2328

CR-ANO-2-2014-03475

CR-ANO-1-2015-02618

CR-ANO-1-2015-02456

CR-ANO-2-2015-00581

CR-ANO-C-2015-02287

CR-ANO-1-2015-02630

CR-ANO-2-2015-02210

CR-ANO-C-2015-02284

CR-ANO-1-2015-02620

CR-ANO-2-2015-01364

CR-ANO-1-2015-2643

CR-ANO-C-2015-01879

CR-ANO-C-2015-02833

CR-ANO-C-2015-02368

CR-ANO-2-2015-05036

CR-ANO-C-2015-04461

CR-ANO-C-2015-00627

CR-ANO-C-2015-02296

CR-ANO-C-2015-02367

CR-ANO-C-2015-02369

CR-ANO-1-2015-00408

CR-ANO-C-2015-03034

CR-ANO-C-2015-02222

CR-ANO-C-2015-02834

CR-ANO-C-2015-03788

CR-ANO-1-2015-00513

- 18 -

Enclosure

CONDITION REPORTS (CRs)

CR-ANO-C-2015-04965

CR-ANO-C-2015-05010

CR-ANO-C-2015-04804

CR-ANO-C-2015-02460

CR-HQN-2014-00291

CR-ANO-1-2015-00386

CR-HQN-2016-00105

CR-HQN-2016-00207

CR-ANO-1-2015-03766

CR-HQN-2016-00207

CR-HQN-2015-868

CR-HQN-2014-00570

CR-HQN-2015-00566

CR-HQN-2014-0291

CR-HQN-2013-00278

CR-HQN-2014-00667

CR-IP3-2015-03795

CR-RBS-2013-03328

MISCELLANEOUS DOCUMENTS

Title

Revision/Date

ANO Unit 1, At-Power Probabilistic Risk Analysis Model

4

ANO Unit 2, At-Power Probabilistic Risk Analysis Model

4

ANO Unit 2 Service Water Performance Monitoring Plan and Trending

Data

ANO Unit 1 Emergency Feedwater System

8

Arkansas Nuclear One Integrated Resource Allocation Project Plan

November 11,

2015

Arkansas Nuclear One Collective Evaluation Report, Part 1

0

ANO 5-Year Staffing Summary 2016-2021

February 1, 2016

ANO Unit 2 Condensate, Heater Drain System Health Report, 4th Quarter

2014

ANO Unit 2 Condensate, Heater Drain System Health Report, 4th Quarter

2015

ANO Emergency Plan

0, 36, 37, 38, 39,

& 40

ANO Unit 1 Operations 5 year Staffing Summary Target Year 2016,

February 1, 2016

ANO 1R25 Outage Commitment List

ANO 2R24 Outage Commitment List

ANO 2015 Equipment Reliability Online Commitment List

ANO 2016 Equipment Reliability Online Commitment List (Draft)

ANO 2016 Backlog Reduction Project Plan

ANO Current O&M Projects (2016-2020)

January 25,

2016

ANO Long Range Outage Plan Summary - Next 5 Outages

ANO MPRC Capital Spreadsheet (2016-2020)

February 3, 2016

ANO-1 AC Distribution Health Report 3Q15

ANO-1 DC Distribution Health Report 3Q15

- 19 -

Enclosure

MISCELLANEOUS DOCUMENTS

Title

Revision/Date

ANO-1 Reactor Protection System Health Report 3Q15

ANO-1 Emergency Feedwater System Health Report 3Q15

ANO-1 Service Water Health Report 3Q15

ANO-1 AC Distribution Performance Monitoring Plan and Trending Data,

4Q15

ANO-1 DC Distribution Performance Monitoring Plan and Trending Data,

4Q15

ANO-1 Reactor Protection System Performance Monitoring Plan and

Trending Data, 4Q15

ANO-1 Emergency Feedwater Performance Monitoring Plan and Trending

Data, 4Q15

ANO-1 Service Water Performance Monitoring Plan and Trending Data,

4Q15

ANO-2 AC Distribution Health Report 3Q15

ANO-2 DC Distribution Health Report 3Q15

ANO-2 Reactor Protection System Health Report 3Q15

ANO-2 Emergency Feedwater System Health Report 3Q15

ANO-2 Service Water Health Report 3Q15

ANO-2 AC Distribution Performance Monitoring Plan and Trending Data,

4Q15

ANO-2 DC Distribution Performance Monitoring Plan and Trending Data,

4Q15

ANO-2 Reactor Protection System Performance Monitoring Plan and

Trending Data, 4Q15

ANO-2 Emergency Feedwater Performance Monitoring Plan and Trending

Data, 4Q15

ANO-2 Service Water Performance Monitoring Plan and Trending Data,

4Q15

ANO Communication Handbook

December 10,

2014

ANO Predictive Maintenance Component Watchlist

Apparent Cause Evaluation CR-ANO-C-2014-1012, Collective Evaluation

of 7 Risk-Significant Issues in 2013

April 15, 2014

Apparent Cause Evaluation CR-ANO-C-2015-4626, Training to Improve

Effectiveness

January 26,

2016

ASLP-MMCT-PRSVL, Pressure Relief Valves

0

- 20 -

Enclosure

MISCELLANEOUS DOCUMENTS

Title

Revision/Date

A2SPGLOR160101, EOL Rapid Shutdown Simulator Lesson

July 27, 2015

ASLP-GM-PMOWN, Maintenance PM Program Owner Training Module

0

ASVEN-SUPV-SAFCON; PowerPoint Presentation: Management Actions

to Detect and Prevent Retaliation and Minimize Chilling Effect

January 2016

ANO People Health Committee Organizational Metrics and Risk

Assessment for Nuclear Engineering

November 1,

2015

ANO People Health Committee Meeting Minutes

February 22,

2016

ANO Organizational Capacity Assessment Policy Guide

7

ANO Organizational Engagement (OR) Survey Analysis

August 25, 2015

ANO Organizational Engagement (OR) Survey Analysis

January 6, 2016

ANO People Heath Committee Meeting Minutes

February 22,

2016

CARB Meeting Minutes

February 24,

2016

CRG Meeting Minutes

January 11,

2016

CRG Meeting Minutes

January 12,

2016

CRG Meeting Minutes

January 26,

2016

CRG Meeting Minutes

January 28,

2016

Comparative Gap Analysis of the ANO Vendor Oversight Fundamental

Problem to CR-ANO-C-2014-02318 Stator Lift Assembly Collapse

0

Corporate vs. ANO Reconciliation of EN-PL-100 Implementation Topics

and Question Meeting Summary

February 16-17,

2016

Conger-Elsea Arkansas Nuclear One (ANO) Station 95003 Inspection

Readiness Assessment Report

December 4,

2015

Emergency Response Organization Staff Assignments

January 14,

2015

Emergency Response Organization Staff Assignments

February 4, 2016

Engineering Programs Snapshot Assessment - Entergy EN-DC-174-

Engineering Program Section-ASME Code Section XI ISI Program

December 17,

2015

Engineering Programs Snapshot Assessment - Entergy EN-DC-174-

Engineering Program Section XI Repair and Replacement (RR)

December 14,

2015

Containment Repair and Replacement Program

- 21 -

Enclosure

MISCELLANEOUS DOCUMENTS

Title

Revision/Date

Engineering Programs Snapshot Assessment - Arkansas Nuclear One,

Welding Program

December 11,

2015

Engineering Programs Snapshot Assessment - Arkansas Nuclear One

Microbiologically Induced Corrosion Monitoring Program

December 9,

2015

Engineering Programs Snapshot Assessment - Arkansas Nuclear One

Generic Letter (GL) 89-13 Service Water Program

December 15,

2015

ESEM-SUPC-SCWE; Safety Conscious Work Environment

0

ERWG Management of Preventative Maintenance on Non-Critical

Components

0

FCBT-ADM-SCWE; Safety Conscious Work Environment

2

Force 431, Revision 3, Change in Technical Specifications End States

(BAW-2441, Arkansas Nuclear One, Unit 1

March 26, 2013

FORM OPS-A26, Control of Room Checklist - RCS 200F

January 28,

2016

FORM OPS-B28, Control of Room Task Checklist and Miscellaneous Log

January 28,

2016

Historical Data Review Performance Area Report

0

Integrated Nuclear Safety Culture Assessment (INSCAR)

December 2015

IER L2 15-29 Weakness in Reactivity Control

Indus Asset Suite (IAS Work Control Software Suite)

Industry Guideline 2013-001, Equipment Reliability Working Group,

Management of Preventive Maintenance on Non-Critical Components

0

Letter 2CAN031303, License Amendment Request, Adoption of

Technical Specification Task Force 422, Revision 2, Change in Technical

Specifications End States (CE NPSD-1186), Arkansas Nuclear One,

Unit 2

March 26, 2013

Letter 1CAN031306, License Amendment Request, Adoption of

Technical Specification Task Force 431, Revision 3, Change in Technical

Specifications End States (BAW-2441, Arkansas Nuclear One, Unit 1

March 26, 2013

Letter 1CAN031306, License Amendment Request, Adoption of

Technical Specification Task Force 431, Revision 3, Change in Technical

Specifications End States (BAW-2441, Arkansas Nuclear One, Unit 1

March 26, 2013

Letter 1CAN121302, License Amendment Request, Technical

Specification Change to Extend the Type A Test Frequency to 15 Years,

Arkansas Nuclear One, Unit 1

December 20,

2013

List of Self-Assessments and Benchmarks

2016

- 22 -

Enclosure

MISCELLANEOUS DOCUMENTS

Title

Revision/Date

Letter of Agreement between Entergy Operations, Inc. and Arkansas

Department of Health

January 16,

2015

Leadership Team Discussion Conceptual Design

LT - Apparent Cause Evaluation Report - Undocumented Control

Circuitry Jumpers Found on SU3 VR

September 19,

2013

Mechanical Superintendent Bench Strength Planning Report

January 29,

2016

Model Change Requests List for ANO, Unit 1, Probabilistic Risk Analysis

Model

January 28,

2016

Model Change Requests List for ANO, Unit 2, Probabilistic Risk Analysis

Model

January 28,

2016

Management Program for License Renewal Implementation

0

NSC Observation Data Analysis for the Week

January 29,

2016

NRC Bulletin 2003-01, Potential Impact of Debris Blockage on Emergency

Sump Recirculation at PWRs

Nuclear Safety Culture Assessment, November 2014 Final Results

Report, Synergy Consulting Services

March 1, 2015

Operations Shift Schedule

CY 2016

Operational Decision Making Issue; R1 Reactor Vessel Flange Inner

O-ring Leakage

January 5, 2016

ODMI: Increasing Void Size Downstream of CV-1400 per PI-1400

Blowdowns

December 8,

2014

ODMI Precursor for CR-ANO-1-2015-4273

January 30,

2016

Operational Excellence, Arkansas Nuclear One Recovery Plan (from the

Operations Website)

Plant Health Problem Area

Plant Health Committee Meeting Package

February 2,

2016

Plant Health Working Group Meeting Package

February 1,

2016

Plant Health Project Plan

1

Plant Health Committee Meeting Package

January 26,

2016

PM Basis Template - EN - Switchgear - Medium Voltage - 1kV to 7kV

September 25,

2008

Project Plant to Implement Standards Team During Refuel Outage 2R24

- 23 -

Enclosure

Miscellaneous Documents

Title

Revision/Date

Post-Event Simulator Testing: ANO-2 ASI Trip During 1-Hour Shutdown

April 27, 2014

Preventive Maintenance Optimization Software (PMOS PM Database)

Post-Outage Reports for refueling outages 1R20 through 1R25 and 2R19

through 2R24

Production Performance Review Meeting Report

January 29,

2016

Predictive Maintenance Watch List

Performance Review Meeting Report ANO / Radiation Protection

January 2016

Performance Review Meeting Report ANO / Security

January 2016

PowerPoint Presentation, Fleet Performance Evaluation RCE & Update

Repair Replacement Plan 2E-35A

September 30,

2015

Repair Replacement Plan 2E-35B

September 30,

2015

Repair Replacement Plan 2SW-25B

October 26,

2014

Radiation Protection Performance Review Meeting

January 2016

Recovery Team Phase 2 Indoctrination Briefing

SARB Observation Sheet

February 2, 2016

SARB Meeting Agenda

February 2, 2016

Selected Condition Review Group (CRG) Meetings

January 27, 2016 /

February 1, 2016 /

February 2, 2016

Standing Order: Condition Reports Bypassing the Control Room with

Potential Operability Impact

January 27,

2016

Sump Recirculation at PWRs

SU3 Non-Segregated Bus - Insulation Test Data

October 10,

2015

Safety Culture Leadership Team Minutes

January 2014 -

January 2016

System Health Report - Switchyard

Q3 - 2015

Task to Training Matrix, ANO Mechanical Maintenance

January 15,

2016

Task to Training Matrix, ANO Instrument and Controls Maintenance

February 22,

2016

- 24 -

Enclosure

Miscellaneous Documents

Title

Revision/Date

Technical Manual 01-1236437-00; Instructions Manual Unit 1 Reactor

Vessel

5

TDI075 0260, Instruction Manual for Ingersoll-Rand High Pressure Safety

Injection Pumps

TRM 3.7.12, Unit 1, Fire Barriers

TRM 3.7.5, Unit 2, Fire Barriers

Third Party Nuclear Safety Culture Performance Assessment (TPSCPA)

May 1, 2015

T+1 Meeting Week Critique for January 25, 2016

February 4, 2016

T+1 Meeting Week Critique for February 1, 2016

February 12,

2016

T+1 Meeting Week Critique for February 8, 2016

February 19,

2016

T+1 Meeting Week Critique for January 18, 2016

January 28,

2016

Unit 2 Operations Manning & Active List

Q1 - 2016

Unit 1 Shift Relief Sheet (living document reviewed daily from 1/25/2016

through 2/5/2016)

Unit 1 and Unit 2 Crane Deficiency Lists

January 25,

2016

Unit 1 Shift Relief Sheet (computer generated living document)

Unit 2 Shift Relief Sheet (computer generated living document)

Unit 1 Operations Manning & Active List

Q1 - 2016

Unmitigated SPV PMs from 2015 Project Excel Spreadsheet

V-1007-00, Unit 1, High Pressure Injection MOV Data

2

Welding Material Requisition No. 05368

December 1,

2014

2015 Senior Leader Face to Face Meeting Matrix (Excel spreadsheet)

2016 Corporate Oversight Plan ANO 95-003 Recovery, Interoffice Memo,

Interim Paired Observation Guideline,

0

2R25 Master Activities List for HPSI, LPSI, SDC, EFW, Spray, and SI

January 20,

2016

2X-03 4160V Hi-POT Test

October 10,

2015

2X-03 6900V HI-POT Test

October 10,

2015

- 25 -

Enclosure

MISCELLANEOUS DOCUMENTS

Number

Title

Revision/Date

ULD-1-SYS-12

ANO Unit 1 Emergency Feedwater System

8

ULD-1-TOP-20

ANO-1 Reactor Building Sump Qualification Basis

SCEW A013, CV-

1000, AZ-1000

System Component Evaluation Worksheet

10

EQDRS A013

EQ Data Record Summary Sheet

5

WT-WTANO-2013-

325

EQRA V33-003

Environmental Qualification Report Assessment

6

ULD-1-TOP-20

ANO-1 Reactor Building Sump Qualification Basis

Att. 9.2,

EN-EP-305

10 CFR 50.54(q) Evaluation - ANO E-Plan Revision

36

December 5,

2012

Att. 9.2,

EN-EP-305

10 CFR 50.54(q) Evaluation - ANO E-Plan Revision

37

February 13,

2013

Att. 9.2,

EN-EP-305

10 CFR 50.54(q) Evaluation - ANO E-Plan Revision

37 (Addendum)

January 20,

2016

Att. 9.2,

EN-EP-305

10 CFR 50.54(q) Evaluation - ANO E-Plan Revision

38

December 17,

2013

Att. 9.2,

EN-EP-305

10 CFR 50.54(q) Evaluation - ANO E-Plan Revision

38 (Addendum)

January 20,

2016

Att. 9.2,

EN-EP-305

10 CFR 50.54(q) Evaluation - ANO E-Plan Revision

39

October 23,

2014

Att. 9.2,

EN-EP-305

10 CFR 50.54(q) Evaluation - ANO E-Plan Revision

39 (Addendum)

January 20,

2016

Att. 9.2,

EN-EP-305

10 CFR 50.54(q) Evaluation - ANO E-Plan Revision

40

December 15,

2015

8.Q.3-8.1

Limitorque Type HBC, SB/SMB-0 and Type SMB-00

Valve Operator Maintenance

17

ASLP-EP-A0060

Training Material: Duty Emergency Planner

8

ASGATT-EM-

DECISION

MAKING

Training - Non-Conservative Decision Making,

Operating Experience Responses and Assumptions,

Lifted Leads, and PMTs

CEO-99/00089

Switchyard and Transmission Interface Agreements

January 20,

2016

EC-61177

Qualification of the Unit 1 Circulating Water Lifting

Tool

7

EC-26194

Intake Structure Spreader Lifting Beam Re-Rate

0

EC12402

Determination of Limiting ANO-2 Condensate Pump

Pressure to Avoid

Exceeding Allowable Flow

1

WPS-SS-8/8-B

- 26 -

Enclosure

MISCELLANEOUS DOCUMENTS

Number

Title

Revision/Date

EC 61455, 2R24

Evaluate Leak from 2SI-13D for Boric Acid

February 13,

2013

ENS-PL-158

Switchyard and Transmission Interface

Requirements

FFAM-CAA-DPIC

Department Performance Improvement Coordinator

(DPIC) Job Familiarization Guide

7

FFAM-OE-

OECOORD

OE Coordinator / ICES Coordinator Job

Familiarization Guide

0

FFAM-PI-CARB

CARB Member Job Familiarization Guide

0

FFAM-PI-RMCAP

Corrective Action Program Responsible Manager

0

FLP-CAA-

TRENDANALYSIS Trend Analysis Training

1

HDR-95003-001

ANO-Historical Data Review - HDR Performance

Area Report

0

HDR-95003-002

ANO-Historical Data Review - HDR Assessment

Area Report

0

ANO EN-LI-123-

BA-FA-001

Focused Assessment Performance Area Report,

Problem Identification and Resolution

May 11, 2015

OE-NOE-2013-

000482

December 5,

2012

OE-NOE-2015-

000123

January 20,

2016

OE-NOE-2015-

00199

December 17,

2013

SIDP-1029

Inadequate Interrupting Capability of Switchyard

22kV Breakers

February 10,

20015

SIDP-7479

B0125 - Replace Bushings and Develop PSR for

Breaker Replacement

June 3, 2015

SIPD-7388

Re-Design and Replace U2 SU2 and SU3 Non-Seg

Bus

September 1,

2015

SIPD-7776

B0126 - 22kV Breaker Replacement in 2R26 (Fall

2018)

January 28,

2016

TDI075 0390

Electronic Only Installation Operation and

Maintenance Manual for Unit II

Condensate Pumps

0

ULD-2-SYS-16

Upper Level Document, ANO Unit 2, 4.16 kV System

October 23,

2014

0CNA129208

Conceptual Design for Station Blackout (SBO)

Modification - ANO, Unites 1 and 2 (TAC NOS.

M84338 and 84339)

0CAN021401

Response to Request for Additional Information

(RAI) Regarding Response to Bulletin 2012001,

Design Vulnerability in Electric Power System ANO -

Units 1 and 2 Docket Nos. 50-313 and 50-368

License Nos. DPR-51 and NPF-6

- 27 -

Enclosure

LEARNING ORGANIZATION

Number

Title

Revision/Date

MISCELLANEOUS DOCUMENTS

Number

Title

Revision/Date

0CAN119507

Notification of Completion of Station Blackout Diesel

Testing Commitments

0CAN089203

Conceptual Design for Station Blackout Modification

(TAC Nos. M68508 and M68509)

1007914

EPRI Report, Lifting, Rigging, and Small Hoist Usage

Guide

0

0CNA119310

Station Blackout (SBO) Commitment For A One-

Time Confirmatory Load Test, ANO, Units 1 and 2

(Tac Nos. M85956 and M85957)

1378-1 (Obsolete)

GE Technical Information Letter (Proprietary) -

Improving Reliability of Medium Voltage Generator

Auxiliary Equipment

December 12,

2002

1701 (Obsolete)

GE Technical Information Letter (Proprietary) -

Improving Reliability of Medium Voltage Generator

Auxiliary Equipment

December 12,

2002

1701-R1

GE Technical Information Letter (Proprietary) -

Improving the Reliability of Medium and High Voltage

Auxiliary Equipment

March 2, 2015

LO-ALO-2011-049

ANO Preventative Maintenance Program Focused

Self-Assessment

February 3,

2012

LO-ALO-2014-001

LO-ALO-2014-066

Snapshot Assessment Focusing Specifically on

Reactivity Management

LO-ALO-2014-094

Maintenance Services Supplemental Worker

Oversight

December 9,

2015

LO-ALO-2015-001

LO-ALO-2015-043

Pre-NRC Fire Protection Triennial Self-Assessment

Plan

LO-ALO-2015-059

LO-ALO-2015-071

Entergy Nuclear Vendor Manuals and the Re-Contact

Process

January 11,

2016

LO-ALO-2015-072

Entergy Nuclear Acceptance of Vendor Documents

January 10,

2016

LO-ALO-2015-107

10 CFR Part 37 Materials Security Review

January 8,

2016

LO-ALO-2014-072

Outage Readiness and OCC Effectiveness Snapshot

Self-Assessment

January 10,

2016

- 28 -

Enclosure

DRAWINGS

Title

Revision/Date

LEARNING ORGANIZATION

Number

Title

Revision/Date

LO-ALO-2015-073

Preventive Maintenance Component Classification

Assessment

December 16,

2015

LO-ALO-2015-079

Single Point Vulnerability Process-Assessment

January 5,

2016

LO-ALO-2015-081

Margin Management Self-Assessment

January 5,

2016

LO-ALO-2015-084

Entergy Predictive Maintenance Program

Assessment

January 7,

2016

LO-ALO-2015-090

Entergy ANO Protective System Maintenance

Monitoring Program Assessment

December 15,

2015

LO-ALO-2015-115

Performance Analysis and Training Needs Analysis

Snapshot Self-Assessment

LO-ALO-2015-117

Ops Training Comprehensive Assessment Plan

LO-ALO-2015-093

Motor Operated Valve Program Snapshot

Assessment

November 18,

2015

LO-ALO-2015-098 Entergy Large Motor Program Assessment

January 8,

2016

M-230 Sheet 1; Piping & Instrument Diagram - Reactor Coolant System

120

RC-201 Sheet 1; Small Pipe Isometric - Reactor Vessel R-1 Flange Gasket

Leak-off Drain

6

RC-202 Sheet 1: Small Pipe Isometric - Reactor Vessel Flange Gasket

Leak-off (Pressure Test Connection)

8

LW-263 Sheet 1; P-32A/B/C/D (seal) Overflow and Leakage Drains

to RB Sump

4

M1B-223 Sheet 1; Upper (RV) Shell Assembly

1

M1B-400 Sheet 1; Specification Drawing for Replacement RVCH ANO-1

0

M1B-408 Sheet 1; ANO-1 Replacement RVCH - Final Machining of Sealing

Surface, Gasket Grooves and Flange External Diameter

0

M1B-425 Sheet 1; ANO-1 Replacement RVCH - Final Machining of Stud

Holes and o-ring Clip Location Grooves

0

M-213 Sheet 2; Piping & Instrument Diagram - Laundry Waste and

Containment & Aux Building Sump Drainage

31

6600-M-2084 Piping Class Sheet

10

C-149 Reactor Building Reinforced Concrete Ground Floor EL. 3570

8

C-151 Reactor Building Reinforced Concrete Plans EL. 362-0 to 376-6

2

- 29 -

Enclosure

DRAWINGS

Title

Revision/Date

C-152 Reactor Building Reinforced Concrete Operating Floor EL. 401-6

7

C-155 Reactor Building Reinforced Concrete Wall Sections & Details -

Sheet 2

8

C-161 Reactor Building Reinforced Concrete Plan EL. 396-6 To EL.

406-6

4

C-174 Reactor Building Structural Steel Plan EL. 357-0

13

C-175 Reactor Building Structural Steel Plan EL. 373-6 and 376-6

11

C-176 Reactor Building Structural Steel Plan EL. 401-6

10

C-177 Reactor Building Structural Steel Plan at EL. 424-6

27

C-179 Reactor Building Structural Steel Miscellaneous Platforms

7

C-109 Reactor Building Liner Plate Typical Details

12

C-202, Unit 1, Auxiliary Building Plan Elevation 335-0

14

C-2113, Reactor Building Liner Plate Typical Wall Details

13

C-2148 Reactor Building Concrete Outline Plans at EL. 336-6, EL. 357-0

& EL.376-6

11

C-2151 Reactor Building Reinforced Concrete Plan EL. 357-0

6

C-2152 Reactor Building Reinforced Concrete Plan EL. 376-6

8

ANO-M-592, Containment Sump Strainer Specification

3

C-2167, Reactor Building Reinforced Concrete Miscellaneous Sections &

Details, Sheet 1

8

C-2202, Auxiliary Building Plan Elevation 335-0

15

C-2612, Containment Building IWE Boundaries, Sheet 10

5

C-2612 Containment Building IWE Boundary Drawing, Sheet 19

0

C-2612 Containment Building IWE Boundary, Sheet 24

0

FB-160-1, Fire Barrier Penetration Computer Room, Sheet 1

1

FB-160-1, Fire Barrier Penetration Computer Room, Sheet 2

2

FB-2109, Fire Penetration MCC Room, Sheet 1

1

M-120, Plumbing and Draining Containment Building Area 25, Plan

Elevation 336-6-337-0, Sheet 3

N

M-213, Unit-1, Piping & Instrument Diagram-Laundry Waste and

Containment & Aux. Building Sump Drainage, Sheet 2

31

- 30 -

Enclosure

CALCULATIONS

Title

Revision/Date

DRAWINGS

Title

Revision/Date

M-232, Unit-1, Piping & Instrument Diagram-Decay Heat Removal System,

Sheet 1

106

M-592-1, Unit-1, RB Sump Strainer Final Design Strainer Layout

M-592-5, Unit-1, Sump Strainer Cartridge 400/10 Pockets, Sheet 1

00

M-2206, Unit 2, Piping & Instrument Diagram-Steam Generator Secondary

System, Sheet 1

152

M-2213, Unit 2, Piping & Instrument Diagram-Liquid Radioactive Waste

System Reactor Building All Elevations, Sheet 8

11

M-2230, Unit 2, Piping & Instrument Diagram-Reactor Coolant System,

Sheet 2

44

M-592, Containment Sump Strainer Specification

3

CALC-ANO1-ME-11000027, Review of the Wall Thinning Inspection Aging

CALC 89-E-0137-01; Service Water Flow to the Emergency Feedwater

System

3

CALC-1.1.1 RB Seismic Analysis for Containment BLDG and Internals

0

CALC-46 Reactor Bldg. Internals

0

CALC-ANO-SE-15-00001 - Single Point Vulnerabilities Project

0

CALC-47 Reactor Bldg. Internals

0

CALC-95-R-0024-01, Basic Requirement for the Component Data Base on

Station Doors and Hatches

12

CALC-07-E-0019-01, Accountability of Unit 1 RB Sump Strainers Sacrificial

Surface Area

2

CALC-ANO2-FP-09-00035, Fire Protection Engineering Evaluation for

Penetration Seals in Fire Area GG

2

CALC-05-E-0005-01, Allowable Liner Plate Thickness

0

CALC-ANOC-CS-14-00005, PCI Promatec Product 12 Flood Sealant

0

CALC-ANO1-ME-11000027, Review of the Wall Thinning Inspection Aging

CALC-89-E-0137-01; Service Water Flow to the Emergency Feedwater

System

3

CALC-1.1.1 RB Seismic Analysis for Containment BLDG and Internals

0

CALC-46 and CALC-47 Reactor Bldg. Internals

0