UNITED STATES NUCLEAR REGULATORY COMMISSION REGION IV 1600 E. LAMAR BLVD.
ARLINGTON, TX 76011-4511 August 6, 2015 MEMORANDUM TO: Arkansas Nuclear One Communication Team Members FROM:
Troy W. Pruett /RA/
Executive Oversight Manager ANO 95003 Team
SUBJECT:
ARKANSAS NUCLEAR ONE INSPECTION PROCEDURE 95003 COMMUNICATION TEAM CHARTER The enclosed team charter establishes the purpose, objectives, and composition of the Arkansas Nuclear One (ANO) Inspection Procedure 95003 Communication Team. This team has been established to ensure that the agencys actions to address the root cause and corrective actions are clearly communicated and documented. This charter also defines the expected outcomes of the oversight process and the team membership. Questions involving the charter should be directed to Neil OKeefe at 817-200-1574 or Neil.OKeefe@nrc.gov.
Enclosure:
Arkansas Nuclear One Inspection Procedure 95003 Communication Team Charter
SUNSI Review By:
ADAMS Yes No Publicly Available Non-Publicly Available Non-Sensitive Sensitive OFFICE RIV/SPE RIV/BC RIV/D NAME NTaylor NOKeefe TPruett SIGNATURE
/RA/
/RA/
/RA/
DATE 7/8/15 8/6/15 8/6/15
Enclosure ARKANSAS NUCLEAR ONE INSPECTION PROCEDURE 95003 COMMUNICATION TEAM CHARTER Purpose
- 1. The Communication Team exists to coordinate important senior management briefings and interface with other Commission officer and external stakeholders as necessary during the conduct of the inspection. Additionally, the team is responsible for coordinating the acquisition of additional resources as necessary to support the overall effort.
Objectives The Teams duties and planned accomplishments include the following:
- 1. Create and maintain a public website to ensure effective communication with internal and external stakeholders.
- 2. Provide periodic briefings to the keep Communication Team members up to date on the status of licensee improvement activities and NRC inspection outcomes.
- 3. Seek input on appropriate communications and coordination actions.
- 4. Identify and develop topics for public meetings and Commission briefings.
- 5. Provide input for the lessons learned activities defined in Inspection Procedure 95003.
Team Membership Troy Pruett, Director, Division of Reactor Projects and Executive Oversight Manager Allen Howe, Deputy Director, Division of Inspection and Regional Support, NRR Neil OKeefe, Chief, Branch E, Division of Reactor Projects, Region IV and Team Leader for 95003 Sunil Weerakkody, Chief, DRA Operations and Human Factors Branch Nick Taylor, Senior Project Engineer, Branch E, Region IV and Assistant Team Leader for 95003 Brian Tindell, Senior Resident Inspector, Arkansas Nuclear One Mike Markley, Chief, Plant Licensing Branch IV-1, NRR/DORL Andrea George, Project Manager, ANO, NRR/DORL Victor Dricks, Senior Public Affairs Officer, Region IV
Bill Maier, Regional State Liaison Officer, Region IV The Chief, Branch E, Region IV is responsible for documenting and distributing the team meeting agendas and minutes.