==SUBJECT:==
UPDATED INSPECTION PLAN FOR DRESDEN NUCLEAR POWER STATION, UNITS 2 AND 3 (REPORT 05000237/2020005 AND 05000249/2020005)
 
==Dear Mr. Hanson:==
The enclosed inspection plan lists the inspections scheduled through June 30, 2022, for Dresden Nuclear Power Station. The NRC provides the inspection plan to allow for the resolution of any scheduling conflicts and personnel availability issues. Routine inspections performed by resident inspectors are not included in the inspection plan. You should be aware that the agency is pursuing potential changes to the Reactor Oversight Process (ROP),
including changes to engineering inspections (SECY-18-0113, Recommendations for Modifying the Reactor Oversight Process Engineering Inspections), and other changes to the baseline inspection program described in SECY-19-0067, Recommendations for Enhancing the Reactor Oversight Process. Should these changes to the ROP be implemented, the engineering and other region-based inspections are subject to change in scope, as well as schedule. The inspections listed during the last twelve months of the inspection plan are tentative and may be revised. The NRC will contact you as soon as possible to discuss changes to the inspection plan should circumstances warrant any changes.
 
In response to the COVID-19 public health emergency (PHE), the NRC is adjusting inspection plans and schedules in order to safeguard the health and safety of both NRC and licensee staff while still effectively implementing the ROP. Each planned inspection is being carefully reviewed in order to determine if any portions of the inspection can be performed remotely, determine how best to perform on-site portions to minimize personnel health risks, and adjust inspection schedules if needed. This is done in accordance with guidance contained in the May 28, 2020 memo, Inspection Guidance During Transition From COVID-19 Mandatory Telework (ML20141L766). For inspections requiring extensive coordination with offsite organizations, such as evaluated emergency preparedness exercises, NRC guidance and frequently asked questions for security and emergency preparedness can be found here:
https://www.nrc.gov/about-nrc/covid-19/security-ep/. Similarly, the NRC has developed guidance if force-on-force inspections cannot be completed as scheduled due to an emergency, such as the COVID-19 PHE. These changes help ensure the health and safety of both NRC and licensee staff while maintaining the NRCs important safety and security mission during the COVID-19 PHE. The attached inspection plan is accurate on the date of issuance but remains subject to change based on approval of potential exemption requests or other changes needed due to changing conditions in the COVID-19 PHE. NRC staff will contact your appropriate regulatory affairs staff in order to coordinate inspection planning and scheduling. In addition to the full-implementation cyber inspection scheduled to be completed at your site, the NRC will also be performing baseline inspections of licensee cyber security programs. The specific schedule and procedure to be used for these baseline inspections are being developed by the NRC staff. The anticipated inspection dates are presented in the attached; however, the staff will confirm the schedule for these inspections with each utility separately.
 
In accordance with Title 10 of the Code of Federal Regulations (10 CFR) 2.390 of the NRCs Rules of Practice, a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
 
Please contact me at 630-829-9628 with any questions you have regarding this letter.
 
Sincerely,
/RA/
Kenneth R. Riemer, Chief Branch 1 Division of Reactor Projects Docket Nos. 05000237 and 05000249 License Nos. DPR-19 and DPR-25 Enclosure(s):
Inspection Plan cc: Distribution via LISTSERV Letter to Bryan from Kenneth Riemer dated September 1, 2020.
 
SUBJECT: UPDATED INSPECTION PLAN FOR DRESDEN NUCLEAR POWER STATION, UNITS 2 AND 3 (REPORT 05000237/2020005 AND 05000249/2020005)
DISTRIBUTION:
Jessie Quichocho Elise Burket RidsNrrDorlLpl3 RidsNrrPMDresden Resource RidsNrrDroIrib Resource John Giessner Kenneth OBrien Jamnes Cameron Allan Barker DRPIII DRSIII ROPassessment.Resource@nrc.gov ADAMS Accession Number: ML20244A313 Publicly Available Non-Publicly Available Sensitive Non-Sensitive OFFICE RIII  RIII NAME CPhillips:wc via KRiemer via email email DATE 8/20/2020 8/24/2020 OFFICIAL RECORD COPY
 
IP 22 Inspection Activity Plan Report 07200037 - Dresden (ISFSI)
07/01/2020 - 06/30/2022 Unit  Start  End  Activity CAC  Title  Staff Count ISFSI Pad Construction          2 1 03/15/2021 03/17/2021 IP 60853 000999 On-Site Fabrication Of Components And Construction On An ISFSI 1 04/05/2021 04/07/2021 IP 60853 000999 On-Site Fabrication Of Components And Construction On An ISFSI 1 05/03/2021 05/05/2021 IP 60853 000999 On-Site Fabrication Of Components And Construction On An ISFSI This report does not include INPO and OUTAGE activities.      Page 1 of 5 This report shows only on-site and announced inspection procedures.
 
8/31/2020 1:21:13 PM
 
IP 22 Inspection Activity Plan Report Dresden 07/01/2020 - 06/30/2022 Unit  Start  End  Activity CAC  Title  Staff Count Final Determination for Dresden Ultimate Heat Sink Apparent Violation      2 2, 3 07/01/2020 08/28/2020 IP 71111.07T 000700 Heat Sink Performance SECURITY BASELINE INSPECTION        2 2, 3 08/17/2020 08/21/2020 IP 71130.04 000736 Equipment Performance, Testing, and Maintenance 2, 3 08/17/2020 08/21/2020 IP 71151 001338 Performance Indicator Verification 2, 3 09/01/2020 12/31/2020 IP 71130.09 001656 Security Plan Changes Radiation Protection Baseline Inspection        1 2, 3 08/31/2020 09/04/2020 IP 71124.05 000729 Radiation Monitoring Instrumentation Inservice Inspection for Dresden Unit 3        1 3 10/26/2020 11/06/2020 IP 71111.08G 000701 Inservice Inspection Activities (BWR)
Security Baseline Inspection        2 2, 3 10/26/2020 10/30/2020 IP 71130.02 000734 Access Control 2, 3 10/26/2020 10/30/2020 IP 71130.05 000737 Protective Strategy Evaluation Radiation Protection Baseline Inspection        1 2, 3 11/02/2020 11/06/2020 IP 71124.01 000725 Radiological Hazard Assessment and Exposure Controls Design Bases Assurance Inspection (Team)        6 2, 3 01/11/2021 01/31/2021 IP 71111.21M 000713 Design Bases Assurance Inspection (Teams)
Corporate Security Baseline Inspection        3 2, 3 01/12/2021 01/14/2021 IP 71130.01 000733 Access Authorization Security Baseline Inspection        1 2, 3 01/25/2021 01/29/2021 IP 71130.14 000743 Review of Power Reactor Target Sets This report does not include INPO and OUTAGE activities.      Page 2 of 5 This report shows only on-site and announced inspection procedures.
 
8/31/2020 1:21:13 PM
 
IP 22 Inspection Activity Plan Report Dresden 07/01/2020 - 06/30/2022 Unit  Start  End  Activity CAC  Title  Staff Count Security Baseline Inspection          1 2, 3 02/01/2021 02/05/2021 IP 71130.01 000733 Access Authorization 2, 3 02/01/2021 02/05/2021 IP 71130.02 000734 Access Control 2, 3 02/01/2021 02/05/2021 IP 71151 001338 Performance Indicator Verification 2, 3 03/15/2021 03/19/2021 IP 71130.07 000739 Security Training Cyber Security Inspection          4 2, 3 03/08/2021 03/26/2021 IP 71130.10P 000741 Cyber Security Dresden April 2021 Initial License Exam        3 2 03/14/2021 03/19/2021 OV  000956 VALIDATION OF INITIAL LICENSE EXAMINATION (OV)
2 04/18/2021 04/24/2021 EXAD 000500 LICENSE EXAM ADMINISTRATION (EXAD)
2 05/01/2021 05/01/2021 EXAD 000500 LICENSE EXAM ADMINISTRATION (EXAD)
Dresden 2021 Biennial Licensed Operator Requalification Program Inspection      2 2, 3 05/09/2021 05/15/2021 IP 71111.11B 000704 Licensed Operator Requalification Program and Licensed Operator Performance Radiation Protection Baseline Inspection        1 2, 3 05/10/2021 05/14/2021 IP 71124.06 000730 Radioactive Gaseous and Liquid Effluent Treatment ISFSI Cask Loading Inspection 2Q2021        2 2, 3 06/07/2021 06/11/2021 IP 60855.1 000590 Operation of an Independent Spent Fuel Storage Installation at Operating Plants Radiation Protection Baseline Inspection        1 2, 3 06/07/2021 06/11/2021 IP 71124.08 000732 Radioactive Solid Waste Processing & Radioactive Material Handling, Storage, &
Transportation This report does not include INPO and OUTAGE activities.      Page 3 of 5 This report shows only on-site and announced inspection procedures.
 
8/31/2020 1:21:13 PM
 
IP 22 Inspection Activity Plan Report Dresden 07/01/2020 - 06/30/2022 Unit  Start  End  Activity CAC  Title  Staff Count Fire Protection          3 2, 3 07/12/2021 07/30/2021 IP 71111.21N.05 001646 Fire Protection Team Inspection (FPTI)
Radiation Protection Baseline Inspection        1 2, 3 07/19/2021 07/23/2021 IP 71124.07 000731 Radiological Environmental Monitoring Program Emergency Preparedness Exercise Inspection / Performance Indicator Verification      4 2, 3 07/19/2021 07/23/2021 IP 71114.07 000722 Exercise Evaluation - Hostile Action (HA) Event 2, 3 07/19/2021 07/23/2021 IP 71151 001397 Performance Indicator Verification Security Baseline Inspection        1 2, 3 10/01/2021 12/31/2021 IP 71130.09 001656 Security Plan Changes Inservice Inspection Dresden Unit 2        1 2 10/25/2021 11/22/2021 IP 71111.08G 000701 Inservice Inspection Activities (BWR)
Radiation Protection Baseline Inspection        1 2, 3 11/01/2021 11/05/2021 IP 71124.01 000725 Radiological Hazard Assessment and Exposure Controls 2, 3 11/01/2021 11/05/2021 IP 71124.02 000726 Occupational ALARA Planning and Controls Biennial Problem Identificationa and Resolution Inspection      4 2, 3 01/24/2022 02/11/2022 IP 71152B 000747 Problem Identification and Resolution Radiation Protection Baseline Inspection        1 2, 3 02/07/2022 02/11/2022 IP 71124.03 000727 In-Plant Airborne Radioactivity Control and Mitigation 2, 3 02/07/2022 02/11/2022 IP 71124.04 000728 Occupational Dose Assessment This report does not include INPO and OUTAGE activities.      Page 4 of 5 This report shows only on-site and announced inspection procedures.
 
8/31/2020 1:21:13 PM
 
IP 22 Inspection Activity Plan Report Dresden 07/01/2020 - 06/30/2022 Unit  Start  End  Activity CAC  Title  Staff Count Emergency Preparedness Baseline Inspection / Performance Indicator Verification      1 2, 3 02/14/2022 02/18/2022 IP 71114.02 000717 Alert and Notification System Testing 2, 3 02/14/2022 02/18/2022 IP 71114.03 000718 Emergency Response Organization Staffing and Augmentation System 2, 3 02/14/2022 02/18/2022 IP 71114.05 000720 Maintenance of Emergency Preparedness 2, 3 02/14/2022 02/18/2022 IP 71151 001397 Performance Indicator Verification Emergency Preparedness Baseline Inspection / Performance Indicator Verification      1 2, 3 03/14/2022 03/18/2022 IP 71114.02 000717 Alert and Notification System Testing 2, 3 03/14/2022 03/18/2022 IP 71114.03 000718 Emergency Response Organization Staffing and Augmentation System 2, 3 03/14/2022 03/18/2022 IP 71114.05 000720 Maintenance of Emergency Preparedness 2, 3 03/14/2022 03/18/2022 IP 71151 001397 Performance Indicator Verification Dresden April 2022 Initial License Exam        3 2, 3 03/27/2022 04/02/2022 OV  000956 VALIDATION OF INITIAL LICENSE EXAMINATION (OV)
2, 3 04/24/2022 04/30/2022 EXAD 000500 LICENSE EXAM ADMINISTRATION (EXAD)
Secuirty Baseline Inspection          1 2, 3 04/04/2022 04/08/2022 IP 71130.02 000734 Access Control 2, 3 04/04/2022 04/08/2022 IP 71151 001338 Performance Indicator Verification 2, 3 05/02/2022 05/06/2022 IP 71130.04 000736 Equipment Performance, Testing, and Maintenance Radiation Protection Baseline Inspection        1 2, 3 05/02/2022 05/06/2022 IP 71124.05 000729 Radiation Monitoring Instrumentation Dresden 2022 Biennial Licensed Operator Requalification Program Inspection      2 2, 3 05/29/2022 06/04/2022 IP 71111.11B 000704 Licensed Operator Requalification Program and Licensed Operator Performance This report does not include INPO and OUTAGE activities.      Page 5 of 5 This report shows only on-site and announced inspection procedures.
 
8/31/2020 1:21:13 PM
}}
}}

Revision as of 22:09, 24 September 2020

Updated Inspection Plan for Dresden Nuclear Power Station, Units 2 and 3 (Report 05000237/2020005 and 05000249/2020005)
ML20244A313
Person / Time
Site: Dresden  Constellation icon.png
Issue date: 09/01/2020
From: Kenneth Riemer