IR 05000237/2018005
| ML18240A323 | |
| Person / Time | |
|---|---|
| Site: | Dresden |
| Issue date: | 08/28/2018 |
| From: | Jamnes Cameron Reactor Projects Region 3 Branch 4 |
| To: | Bryan Hanson Exelon Generation Co, Exelon Nuclear |
| References | |
| IR 2018005 | |
| Download: ML18240A323 (4) | |
Text
August 28, 2018
SUBJECT:
UPDATED INSPECTION PLAN FOR DRESDEN NUCLEAR POWER STATION, UNITS 2 AND 3 (REPORT 05000237/2018005 AND 05000249/2018005)
Dear Mr. Hanson:
The enclosed inspection plan lists the inspections scheduled through June 30, 2020, for Dresden Nuclear Power Station, Units 2 and 3. The NRC provides the inspection plan to allow for the resolution of any scheduling conflicts and personnel availability issues. Routine inspections performed by resident inspectors are not included in the inspection plan. The inspections listed during the last twelve months of the inspection plan are tentative and may be revised. The NRC will contact you as soon as possible to discuss changes to the inspection plan should circumstances warrant any changes.
This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with 10 CFR 2.390, Public Inspections, Exemptions, Requests for Withholding.
Please contact me at 630-829-9833 with any questions you have regarding this letter.
Sincerely,
/RA/
Jamnes Cameron, Chief Branch 4 Division of Reactor Projects
Docket Nos. 50-237; 50-249 License Nos. DPR-19; DPR-25
Enclosure:
Inspection Plan
cc: Distribution via LISTSERV
Letter to Bryan