IR 05000237/2019005

From kanterella
Jump to navigation Jump to search
Updated Inspection Plan for Dresden Nuclear Power Station, Units 2 and 3 (Report 05000237/2019005 and 05000249/2019005)
ML19240A336
Person / Time
Site: Dresden  Constellation icon.png
Issue date: 08/28/2019
From: Kenneth Riemer
NRC/RGN-III/DRP/B1
To: Bryan Hanson
Exelon Generation Co, Exelon Nuclear
References
IR 2019005
Download: ML19240A336 (7)


Text

ust 28, 2019

SUBJECT:

UPDATED INSPECTION PLAN FOR DRESDEN NUCLEAR POWER STATION, UNITS 2 AND 3 (REPORT 05000237/2019005 AND 05000249/2019005)

Dear Mr. Hanson:

The enclosed inspection plan lists the inspections scheduled through June 30, 2021, for the Dresden Nuclear Power Station, Units 2 and 3. The NRC provides the inspection plan to allow for the resolution of any scheduling conflicts and personnel availability issues. Routine inspections performed by resident inspectors are not included in the inspection plan. You should be aware that the agency is pursuing potential changes to the ROP, including changes to engineering inspections (SECY-18-0113, Recommendations for Modifying the Reactor Oversight Process Engineering Inspections), and other changes to the baseline inspection program described in SECY-19-0067, Recommendations for Enhancing the Reactor Oversight Process. Should these changes to the ROP be implemented, the engineering and other region-based inspections are subject to change in scope, as well as schedule, beginning in January 2020. The inspections listed during the last twelve months of the inspection plan are tentative and may be revised. The NRC will contact you as soon as possible to discuss changes to the inspection plan should circumstances warrant any changes. This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with 10 CFR 2.390, Public Inspections, Exemptions, Requests for Withholding.

Please contact me at 630-829-9628 with any questions you have regarding this letter.

Sincerely,

/RA/

Kenneth R. Riemer, Chief Branch 1 Division of Reactor Projects Docket Nos. 50-237; 50-249 and 72-037 License Nos. DPR-19 and DPR-25 Enclosure:

Inspection Plan cc: Distribution via LISTSERV