U1: CY2018 Master Inspection Plan
ML17354B035
Person / Time
Site: Dresden Constellation icon.png
Issue date: 12/20/2017
From: Rhex Edwards
NRC/RGN-III/DNMS/MCID
To: Walker D
Exelon Corp
References
Download: ML17354B035 (1)


Text

Edwards, Rhex From: Edwards, Rhex Sent: Wednesday, December 20, 2017 12:11 PM To: Dean.Walker@exeloncorp.com

Subject:

Dresden Ul: CY2018 Master Inspection Plan

Dear Mr. Walker,

In accordance with Inspection Manual Chapter (IMC) 2561, "Decommissioning Power Reactor Inspection Program," the NRC Region Ill staff developed a Master Inspection Plan (MIP) for the Dresden Nuclear Power Station, Unit 1, for calendar year 2018. The inspection plan is based on your current performance and your planned decommissioning activities for the site in January through December 2018. Below is a list of the periodic inspection procedures we expect to use during our inspections. The procedures used during each inspection will depend on the specific activities being conducted at the site. Additional discretionary inspection procedures may be used if decommissioning activities warrant. We will gladly discuss any questions you may have regarding this MIP. If you have questions, please contact me at (630) 829-9722. If you have questions related to security inspections, please contact the Plant Support Branch Chief at 630-829-9500.

Sincerely, Rhex Edwards Inspection Procedure (IP) Start Date End Date IP 37801: Safety Reviews, 06/01/2018 08/01/2018 Design Changes, and Modifications IP 71801: Performance and 06/01/2018 08/01/2018 Status Review IP 83750: Occupational 06/01/2018 08/01/2018 Radiation Exposure IP 84750: Radioactive Waste 06/01/2018 08/01/2018 Treatment, Effluent and Environmental Monitoring IP 86750: Waste Management 06/01/2018 08/01/2018 and Transportation Rhex Edwards Senior Health Physicist USNRC Region Ill DNMS MCID 630-829-9722 1