ML092670503: Difference between revisions

From kanterella
Jump to navigation Jump to search
(Created page by program invented by StriderTol)
(StriderTol Bot change)
 
Line 25: Line 25:
==SUMMARY==
==SUMMARY==
OF SEPTEMBER 23, 2009, MEETING WITH EXELON TO DISCUSS GENERIC LETTER 2004-02 SUPPLEMENTAL RESPONSE REQUEST FOR ADDITIONAL INFORMATION (TAC NO. MC4724)
OF SEPTEMBER 23, 2009, MEETING WITH EXELON TO DISCUSS GENERIC LETTER 2004-02 SUPPLEMENTAL RESPONSE REQUEST FOR ADDITIONAL INFORMATION (TAC NO. MC4724)
On September 23, 2009, a Category 1 public meeting was held by teleconference between the U.S. Nuclear Regulatory Commission (NRC) and representatives of Exelon Generation Company, LLC (Exelon, the licensee). The purpose of the meeting was to discuss remaining issues identified during NRC staff review of the Three Mile Island, Unit 1 (TMI-1) Generic Letter (GL) 2004-02 supplemental response. A listing of the issues of concern can be found in NRC letter dated July 23,2009, available at Agencywide Documents Access and Management System (ADAMS) Accession No. ML091890848. The meeting was a follow-up to a teleconference held on August 11, 2009, (meeting summary available at ADAMS Accession No.
On September 23, 2009, a Category 1 public meeting was held by teleconference between the U.S. Nuclear Regulatory Commission (NRC) and representatives of Exelon Generation Company, LLC (Exelon, the licensee). The purpose of the meeting was to discuss remaining issues identified during NRC staff review of the Three Mile Island, Unit 1 (TMI-1) Generic Letter (GL) 2004-02 supplemental response. A listing of the issues of concern can be found in NRC letter dated July 23,2009, available at Agencywide Documents Access and Management System (ADAMS) Accession No. ML091890848. The meeting was a follow-up to a teleconference held on August 11, 2009, (meeting summary available at ADAMS Accession No. ML092250551) and was intended to give Exelon the opportunity to explain their proposed approach for responding to the NRC staff's concerns. The meeting was also intended to give the NRC staff the opportunity to provide feedback regarding the licensee's proposed approach and to provide a mechanism for the NRC and Exelon to come to a mutual agreement on the remaining steps toward resolution of the outstanding GL 2004-02 issues for TMI-1.
ML092250551) and was intended to give Exelon the opportunity to explain their proposed approach for responding to the NRC staff's concerns. The meeting was also intended to give the NRC staff the opportunity to provide feedback regarding the licensee's proposed approach and to provide a mechanism for the NRC and Exelon to come to a mutual agreement on the remaining steps toward resolution of the outstanding GL 2004-02 issues for TMI-1.
Four of the draft responses to the TMI-1 specific issues, contained in the NRC request for additional information (RAI), letter dated July 23, 2009, were discussed in detail. These are the issues relating to RAI numbers 7, 11 and 13, as well as the general question regarding sump de-aeration potential. The draft responses discussed can be found at ADAMS Accession No. ML092650407. After discussion of the draft responses, it was determined that the only item requiring further discussion was the sump de-aeration question. A further follow-up public meeting teleconference will be scheduled to discuss this issue.
Four of the draft responses to the TMI-1 specific issues, contained in the NRC request for additional information (RAI), letter dated July 23, 2009, were discussed in detail. These are the issues relating to RAI numbers 7, 11 and 13, as well as the general question regarding sump de-aeration potential. The draft responses discussed can be found at ADAMS Accession No.
ML092650407. After discussion of the draft responses, it was determined that the only item requiring further discussion was the sump de-aeration question. A further follow-up public meeting teleconference will be scheduled to discuss this issue.
No proprietary information was discussed at the meeting. One member of the public was in attendance. No comments were presented to the NRC staff during the public portion of the meeting. A list of attendees is provided in the enclosure.
No proprietary information was discussed at the meeting. One member of the public was in attendance. No comments were presented to the NRC staff during the public portion of the meeting. A list of attendees is provided in the enclosure.



Latest revision as of 09:28, 12 March 2020

Summary of Meeting with Exelon to Discuss Generic Letter 2004-02 Supplemental Response Request for Additional Information
ML092670503
Person / Time
Site: Three Mile Island Constellation icon.png
Issue date: 09/30/2009
From: Peter Bamford
Plant Licensing Branch 1
To:
Exelon Generation Co
Bamford, Peter J., NRR/DORL 415-2833
References
GL-04-002, TAC MC4724
Download: ML092670503 (4)


Text

UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 September 30, 2009 LICENSEE: Exelon Generation Company, LLC (Exelon)

FACILITY: Three Mile Island Nuclear Station, Unit 1

SUBJECT:

SUMMARY

OF SEPTEMBER 23, 2009, MEETING WITH EXELON TO DISCUSS GENERIC LETTER 2004-02 SUPPLEMENTAL RESPONSE REQUEST FOR ADDITIONAL INFORMATION (TAC NO. MC4724)

On September 23, 2009, a Category 1 public meeting was held by teleconference between the U.S. Nuclear Regulatory Commission (NRC) and representatives of Exelon Generation Company, LLC (Exelon, the licensee). The purpose of the meeting was to discuss remaining issues identified during NRC staff review of the Three Mile Island, Unit 1 (TMI-1) Generic Letter (GL) 2004-02 supplemental response. A listing of the issues of concern can be found in NRC letter dated July 23,2009, available at Agencywide Documents Access and Management System (ADAMS) Accession No. ML091890848. The meeting was a follow-up to a teleconference held on August 11, 2009, (meeting summary available at ADAMS Accession No. ML092250551) and was intended to give Exelon the opportunity to explain their proposed approach for responding to the NRC staff's concerns. The meeting was also intended to give the NRC staff the opportunity to provide feedback regarding the licensee's proposed approach and to provide a mechanism for the NRC and Exelon to come to a mutual agreement on the remaining steps toward resolution of the outstanding GL 2004-02 issues for TMI-1.

Four of the draft responses to the TMI-1 specific issues, contained in the NRC request for additional information (RAI), letter dated July 23, 2009, were discussed in detail. These are the issues relating to RAI numbers 7, 11 and 13, as well as the general question regarding sump de-aeration potential. The draft responses discussed can be found at ADAMS Accession No. ML092650407. After discussion of the draft responses, it was determined that the only item requiring further discussion was the sump de-aeration question. A further follow-up public meeting teleconference will be scheduled to discuss this issue.

No proprietary information was discussed at the meeting. One member of the public was in attendance. No comments were presented to the NRC staff during the public portion of the meeting. A list of attendees is provided in the enclosure.

-2 Please direct any inquiries to me at 301-415-2833 or peter.bamford@nrc.gov.

rJ1;r;;~,,",vT Peter Bamford

,,, L.'-(.. ~

Plant Licensing Branch 1-2 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-289

Enclosure:

List of Attendees cc w/encls: Distribution via ListServ

LIST OF ATTENDEES SEPTEMBER 23,2009, MEETING WITH EXELON GENERATION COMPANY, LLC THREE MILE ISLAND, UNIT 1 GENERIC LETTER 2004-02 SUPPLEMENTAL RESPONSE EXELON Todd Wickel Rich Sievers Wendi Croft Brian Davenport Keith Boring ALiON Rob Choromokos Stewart Bailey Stephen Smith John Lehning Peter Bamford PUBLIC Russ Lytton, Duke Power Enclosure

-2 Please direct any inquiries to me at 301-415-2833 or peter. bamford@nrc.gov.

/raj Peter Bamford Plant Licensing Branch 1-2 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-289

Enclosure:

List of Attendees cc w/encls: Distribution via ListServ DISTRIBUTION:

PUBLIC RidsNrrPMThreeMilelsland Resource SSmith, NRR Branch Reading RidsNrrLAABaxter Resource SBailey, NRR RidsAcrsAcnw_MailCTR Resource RidsRgnlMailCenter Resource JLehning, NRR RidsNrrDorlLpll-2 Resource CTucci, NRR LTrocine, EDO Region 1 RidsOgcRp Resource ADAMS Accession Nos.: Package ML092650416; Meeting NoticeML092250580; Meeting Handout ML092650407; Meeting Summary ML092670503 OFFICE DORULPLI-2/PM DORULPLI-2/LA NRRISSIB/BC DORULPLI-2/BC NAME PBamford ABaxter SBailey HChernoff DATE 9/24/09 9/28/09 9/29/09 9/30109 OFFICIAL RECORD COpy