Memo Annual Assessment Meeting Summary for Three Mile Island
ML101530120
Person / Time
Site: Crane Constellation icon.png
Issue date: 05/27/2010
From: Ronald Bellamy
NRC/RGN-I/DRP/PB6
To:
Exelon Generation Co
BELLAMY rr
References
Download: ML101530120 (3)


Text

UNITED STATES NUCLEAR REGULATORY COMMISSION REGION I 475 ALLENDALE ROAD KING OF PRUSSIA, PENNSYLVANIA 19406-1415 May 27,2010 LICENSEE:

EXELON GENERATION COMPANY, LLC FACILITY:

THREE MILE ISLAND POWER STATION, UNIT 1

SUBJECT:

ANNUAL ASSESSMENT MEETING

SUMMARY

On April 13, 2010, at 6:00 p.m.. the Nuclear Regulatory Commission (NRC) staff met with interested members of the public and Exelon at the Londonderry Town Hall, Middletown, PA to review and discuss the NRC's Annual Assessment of the performance of the Three Mile Island Power Station, Unit 1. The NRC assessment of the safety performance at Three Mile Island Unit 1 was for the period from January 1 through December 31,2009. The staff used posters, handouts, and an electronic slide show to discuss performance and respond to questions. In addition to NRC staff, several licensee staff members, two reporters, and several state and local officials attended the meeting.

The NRC's assessment letter can be found in ADAMS with Accession Number ML100621304.

The annual assessment meeting notice, with the attached meeting agenda, can be found in ADAMS with Accession Numbers ML100810315. ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html.

Sincerely, IRA!

Ronald R. Bellamy, Ph.D., Chief Projects Branch 6 Division of Reactor Projects Attachments:

See List of Attendees

April 13,2010 - Three Mile Island Annual Assessment Meeting with Exelon Attendees NRC:

Ronald Bellamy, Branch Chief, Region I Division of Reactor Projects David Kern, TMI Senior Resident Inspector Javier Brand, TMI Resident Inspector Peter Bamford, TMI Project Manager Diane Screnci, Region I Public Affairs Exelon:

William Noll, Site Vice President Dave Atherholt, Manager, Regulatory Assurance Bill Carsky, TMI Operations Director Ralph Desantis, Manager, Communications John Karkoska, Security Manager Local Officials: Steve Letavic, Londonderry Town Manager Anna Dale, Londonderry Town Supervisor Daryl LeHew, Londonderry Town Supervisor State Officials: David Allard, Director, PA Dept of Environmental Protection Dennis Dyckman, Nuclear Safety Specialist, PA Bureau of Radiation Protection Henry Tamanini, Planning Supervisor, PA Emergency Mgmt Agency

LICENSEE:

EXELON GENERATION COMPANY, LLC FACILITY:

THREE MILE ISLAND POWER STATION, UNIT 1

SUBJECT:

ANNUAL ASSESSMENT MEETING

SUMMARY

On April 13, 2010, at 6:00 p.m., the Nuclear Regulatory Commission (NRC) staff met with interested members of the public and Exelon at the Londonderry Town Hall, Middletown, PA to review and discuss the NRC's Annual Assessment of the performance of the Three Mile Island Power Station Unit 1. The NRC assessment of the safety performance at Three Mile Island Unit 1 was for the period from January 1 through December 31,2009. The staff used posters, handouts, and an electronic slide show to discuss performance and respond to questions. In addition to NRC staff, several licensee staff members, two reporters, and several state and local officials attended the meeting.

The NRC's assessment letter can be found in ADAMS with Accession Number ML100621304.

The annual assessment meeting notice, with the attached meeting agenda, can be found in ADAMS with Accession Numbers ML100810315. ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html.

Sincerely, IRAJ Ronald R. Bellamy, Ph.D., Chief Projects Branch 6 Division of Reactor Projects Distribution:

D. Kern, DRP, SRI S. Collins, RA J. Brand, DRP, RI M. Dapas. ORA C. LaRegina, DRP, Resident OA D. Lew, DRP L. Trocine, RI OEDO J. Clifford, DRP H. Chernoff, NRR R. Bellamy, DRP P. Bamford, NRR G. Barber, DRP E. Miller, NRR C. Newport, DRP SUNSI REVIEW COMPLETE:

RRB (Reviewer's Initials)

ML101530120 After declaring this document An Official Agency Record it will be released to the Public.

Doc Name: G:\\DRP\\BRANCH6\\ROP ASSESSMENT FOLDERS\\ROP 10\\TMI\\END-OF-CYCLE\\TMI 2010 AA MEETING

SUMMARY

(2).DOC To receive acopy of this document, indicate in the box: "C" =Copy without attachment/enclosure "E" =Copy with attachment/enclosure "N" =No copy RIIDRP OFFICE RI/DRP NAME DKernl SB for DK SBarber/ SB DATE 05/27/10 05/27/10 OFFICIAL RECORD COpy