5/7/2013 - Summary of Annual Assessment Meeting - Three Mile Island
ML13141A637
Person / Time
Site: Three Mile Island Constellation icon.png
Issue date: 05/21/2013
From: Hunegs G
NRC/RGN-I/DRP/PB6
To:
Exelon Generation Co
HUNEGS, GK
References
Download: ML13141A637 (2)


Text

UNITED STATES NUCLEAR REGULATORY COMMISSION REGION I 2100 RENAISSANCE BOULEVARD, SUITE 100 KING OF PRUSSIA, PENNSYLVANIA 19406-2713 May 21, 2013 MEETING

SUMMARY

LICENSEE: Exelon Generation Company, LLC FACILITY: Three Mile Island Nuclear Station, Unit 1

SUBJECT:

SUMMARY

OF PUBLIC MEETING On May 7, 2013, at 5:30 pm to 7:00 pm, the U. S. Nuclear Regulatory Commission (NRC) conducted a public open-house at the Londonderry Township Municipal Building in Middletown, PA. The NRC conducted the open-house to discuss its assessment of the safety performance at Three Mile Island, Unit 1, for 2012.

A notice of the open-house was issued on March 25, 2013 and was posted on the NRCs external (public) Web page. The meeting notice can be found in the NRCs Agencywide Documents Access and Management System (ADAMS) with Accession No. ML13084A302.

ADAMS is accessible from the NRC Web page at: http://www.nrc.gov/reading-rm/adams.html.

The NRC presented poster boards and was available to discuss its assessment of the safety performance of Three Mile Island for the period of January 1 through December 31, 2012, as documented in our letter dated March 4, 2013 (ADAMS Accession No. ML13057A300). The NRC poster boards presented included background on the Reactor Oversight Process (ROP).

Additional information relative to the NRC's Annual Assessment Process and the safety performance of Three Mile Island, Unit 1 can be found on the NRC's web site at:

www.nrc.gov/NRR/OVERSIGHT/ASSESS/index.html.

Members of the public, local officials, state officials, and members of the media attended the open-house and were offered the opportunity to question the NRC regarding Three Mile Islands performance and the role of the agency in ensuring safe plant operations.

/RA/

Gordon K. Hunegs, Chief Projects Branch 6 Division of Reactor Projects

ML13057A300.

The NRC poster boards presented included background on the Reactor Oversight Process (ROP). Additional information relative to the NRC's Annual Assessment Process and the safety performance of Three Mile Island, Unit 1 can be found on the NRC's web site at:

www.nrc.gov/NRR/OVERSIGHT/ASSESS/index.html.

Members of the public, local officials, state officials, and members of the media attended the open-house and were offered the opportunity to question the NRC regarding Three Mile Islands performance and the role of the agency in ensuring safe plant operations.

/RA/

Gordon K. Hunegs, Chief Projects Branch 6 Division of Reactor Projects Distribution: (via email) D.Werkheiser, DRP G. Hunegs, DRP J.Heinly, DRP B.Bickett, DRP RidsNRRPMThreeMileIslandResource A.Dugandzic, DRP DOC NAME: G:\DRP\BRANCH6\ROP Assessment Folders\ROP 13\End-of-Cycle\TMI\TMI Annual Assessment Meeting Summary 2013.docx ADAMS Accession No.: ML13141A637 SUNSI Review Non-Sensitive Publicly Available Sensitive Non-Publicly Available OFFICE RI/DRP RI/DRP NAME BBickett/BB GHunegs/GH DATE 05/21 /12 05/21/12