LR-N16-0161, Flood Hazards Mitigating Strategies Assessment (MSA) Report Submittal: Difference between revisions

From kanterella
Jump to navigation Jump to search
(Created page by program invented by StriderTol)
(Created page by program invented by StriderTol)
 
Line 82: Line 82:
There are no regulatory commitments contained in this letter. If you have any questions or require additional information, please do not hesitate to contact Mr. Brian J. Thomas at 856-339-2022.
There are no regulatory commitments contained in this letter. If you have any questions or require additional information, please do not hesitate to contact Mr. Brian J. Thomas at 856-339-2022.
I declare under penalty of perjury that the foregoing is true and correct.
I declare under penalty of perjury that the foregoing is true and correct.
Executed on      f l. I ~ 6 II'
Executed on      f l. I ~ 6 II' (Date)
              -----------------------
(Date)
Sincerely, Charles V. McFeaters Site Vice President Salem Generating Station : SGS FLEX DB and MSFHI- Flood Parameter Comparison Tables cc:    Mr. Daniel Dorman, Administrator, Region I, NRC Mr. Patrick Finney, NRC Senior Resident Inspector, Salem Ms. Carleen J. Parker, Project Manager, NRC/NRRlDORL Mr. John Boska, Senior Project Manager, NRC/NRRlJLD Mr. Patrick Mulligan, Chief, NJBNE Mr. Thomas Cachaza, Salem Commitment Tracking Coordinator Mr. Lee Marabella, PSEG Corporate Commitment Coordinator
Sincerely, Charles V. McFeaters Site Vice President Salem Generating Station : SGS FLEX DB and MSFHI- Flood Parameter Comparison Tables cc:    Mr. Daniel Dorman, Administrator, Region I, NRC Mr. Patrick Finney, NRC Senior Resident Inspector, Salem Ms. Carleen J. Parker, Project Manager, NRC/NRRlDORL Mr. John Boska, Senior Project Manager, NRC/NRRlJLD Mr. Patrick Mulligan, Chief, NJBNE Mr. Thomas Cachaza, Salem Commitment Tracking Coordinator Mr. Lee Marabella, PSEG Corporate Commitment Coordinator



Latest revision as of 22:08, 4 February 2020

Flood Hazards Mitigating Strategies Assessment (MSA) Report Submittal
ML16365A151
Person / Time
Site: Salem  PSEG icon.png
Issue date: 12/30/2016
From: Mcfeaters C
Public Service Enterprise Group
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
CAC MF3790, CAC MF3791, LR-N16-0161
Download: ML16365A151 (8)


Text

PSEG Nuclear LLC P.O. Box 236, Hancocks Bridge, NJ 08038-0236 10 CFR 50.4 LR-N16-0161 DEC 3 0 ?016 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555 Salem Generating Station, Units 1 and 2 Renewed Facility Operating License Nos. DPR-70 and DPR-75 NRC Docket Nos. 50-272 and 50-311

Subject:

Salem Generating Station's Flood Hazards Mitigating Strategies Assessment (MSA)

Report Submittal

References:

1. NRC Letter, "Request for Information Pursuant to Title 10 of the Code of Federal Regulations 50.54(f) Regarding Recommendations 2.1, 2.3, and 9.3, of the Near-Term Task Force Review of Insights from the Fukushima Dai-ichi Accident," dated March 12, 2012.
2. PSEG Letter LR-N14-0042, "PSEG Nuclear LLC's Response to Request for Information Regarding Flooding Aspects of Recommendation 2.1 of the Near-Term Task Force Review of Insights from the Fukushima Dai-ichi Accident- Salem Generating Station Flood Hazard Reevaluation," dated March 11,2014.
3. PSEG Letter LR-N14-0170, "PSEG Nuclear LLC's 30-day Response to Request for Additional Information Regarding Flooding Aspects of Recommendation 2.1 of the Near-Term Task Force Review of Insights from Fukushima Dai-Ichi Accident," dated July 28, 2014.
4. NRC Letter, "Nuclear Regulatory Commission Report for the Audit of PSEG Nuclear LLC's Flood Hazard Reevaluation Report Submittals Relating to the Near-Term Task Force Recommendation 2.1 - Flooding for Salem Nuclear Generating Station, Units 1 and 2 (CAC NOS. MF3790 and MF3791 )," dated January 8, 2016.
5. NRC Memorandum to COMSECY-14-0037, "Staff Requirements - COMSECY-14-0037

- Integration of Mitigating Strategies for Beyond-Design-Basis External Events and the Reevaluation of Flooding Hazards," dated March 30, 2015.

Page 2 10 CFR SO.4 LR-N16-0161

6. Nuclear Energy Institute (NEI), Report NEI 12-06, Revision 2, "Diverse and Flexible Coping Strategies (FLEX) Implementation Guide," dated December 201S.
7. NRC Interim Staff Guidance JLD-ISG-2012-01, Revision 1, "Compliance with Order EA-12-049, Order Modifying Licenses with Regard to Requirements for Mitigating Strategies for Beyond-Design-Basis External Events," dated January 22, 2016.
8. NRC Letter, "Salem Nuclear Generating Station, Units 1 and 2 Interim Staff Response to Reevaluated Flood Hazards Submitted in Response to 10 CFR SO.S4(f) Information Request - Flood-Causing Mechanism Reevaluation (TAC NOS. MF3790 and MF3791 ),"

dated September 10, 201S.

9. NRC Letter, "Supplemental Information Related to Request for Information Pursuant to Title 10 of the Code of Federal Regulations SO.S4(f) Regarding Flooding Hazard Reevaluations for Recommendation 2.1 of the Near-Term Task Force Review of Insights from the Fukushima Dai-ichi Accident," dated March 1, 2013.
10. PSEG Letter LR-N14-0207, "PSEG Nuclear LLC's 90-day Response to Request for Additional Information Regarding Flooding Aspects of Recommendation 2.1 of the Near-Term Task Force Review of Insights from the Fukushima Dai-ichi Accident," dated September 23, 2014.
11. PSEG Letter LR-N1S-01 01, "Salem Generating Station's Response to Request for Additional Information Regarding Flooding Aspects of Recommendation 2.1 of the Near-Term Task Force Review of Insights from the Fukushima Dai-ichi Accident," dated May 7, 201S.
12. NRC Letter, "Salem Nuclear Generating Station, Units 1 and 2 - Staff Assessment of Response to 10 CFR 50.S4(f) Information Request - Flood-Causing Mechanism Reevaluation (CAC NOS. MF3790 AND MF3791 )," dated October 7, 2016.
13. PSEG Letter LR-N12-0370, "Salem Generating Station Response to Recommendation 2.3: Flooding Walkdown of the Near-Term Task Force Review of Insights from the Fukushima Dai-ichi Accident," dated November 26,2012.

The purpose of this letter is to provide the Salem Generating Station (SGS) mitigating strategies assessment (MSA) for reevaluated external flood hazards.

On March 12, 2012, the NRC issued Reference 1 to request information associated with Near-Term Task Force (NTTF) Recommendation 2.1 for Flooding. One of the Required Responses in Reference 1 directed licensees to submit a Flood Hazard Reevaluation Report (FHRR). For SGS. PSEG submitted the FHRR on March 11, 2014 (Reference 2). The reevaluated flood hazard was further developed in response to requests for additional information and a regulatory audit (References 3, 4, 10 and 11). Per Reference 9, the NRC considers the reevaluated flood hazard to be "beyond the current designllicensing basis of operating plants."

Concurrent with the flood hazard reevaluation, SGS developed and implemented mitigating strategies in accordance with NRC Order EA-12-049, "Requirements for Mitigation Strategies for Beyond-Design-Basis External Events." In Reference S, the Commission affirmed that licensees need to assess their mitigating strategies for beyond-design-basis (BDB) external

Page 3 10 CFR 50.4 LR-N16-0161 events, including the reevaluated flood hazards. Guidance for performing mitigating strategies assessments (MSAs) is contained in Appendix G of Reference 6, endorsed by the NRC (with conditions) in Reference 7. For the purpose of the MSAs, the NRC has termed the reevaluated flood hazard, summarized in Reference 8, as the "Mitigating Strategies Flood Hazard Information" (MSFHI). Reference 6, Appendix G, describes the MSA for flooding as containing the following elements:

  • Section G.2 - Characterization of the MSFHI
  • Section G.3 - Comparison of the MSFHI and FLEX DB Flood
  • Section G.4.1 - Assessment of Current FLEX Strategies (if necessary)
  • Section G.4.2 - Assessment for Modifying FLEX Strategies (if necessary)
  • Section G.4.3 - Assessment of Alternative Mitigating Strategies (if necessary)
  • Section G.4.4 - Assessment of Targeted Hazard Mitigating Strategies (if necessary)

The following provides the MSA results for the Salem Generating Station.

Reference 6. Section G.2 - Characterization of the MSFH I Characterization of the Mitigating Strategies Flood Hazard Information (MSFHI) is summarized in Reference 8, the NRC's interim response to the flood hazard reevaluation submittal (Reference 2) and related correspondence (References 3, 4, 10 and 11). A more detailed description of the MSFHI, along with the basis for inputs, assumptions, methodologies, and models, is provided in the following references:

  • Local Intense Precipitation (LIP): See Section 2.1 of Reference 2, Enclosure 1.
  • Flooding in Streams and Rivers: See Section 2.2 of Reference 2, Enclosure 1.
  • Dam Breaches and Failures: See Section 2.3 of Reference 2, Enclosure 1.
  • Storm Surge: See Section 2.4 of Reference 2, Enclosure 1.
  • Seiche: See Section 2.5 of Reference 2, Enclosure 1.
  • Tsunami: See Section 2.6 of Reference 2, Enclosure 1.
  • Ice-Induced Flooding: See Section 2.7 of Reference 2, Enclosure 1.
  • Channel Migration or Diversion: See Section 2.8 of Reference 2, Enclosure 1.
  • Combined Effects (including wind-waves and runup effects): See Section 2.9 of Reference 2, Enclosure 1.
  • Other Associated Effects (Le., hydrodynamic loading, including debris; effects caused by sediment deposition and erosion; concurrent site conditions; and groundwater ingress): See Sections 2.10 and 3.10 of Reference 2, Enclosure 1.
  • Flood Event Duration Parameters (Le. warning time, period of site preparation, period of inundation, and period of recession): See Section 2.10.6 of Reference 2, Enclosure 1.

As discussed in Reference 2, the flood hazard reevaluation showed that the Flooding in Streams and Rivers (including combined effects provided in NUREG/CR-7046, "Design-Basis Flood Estimation for Site Characterization at Nuclear Power Plants in the United States of America," Appendix H, H.1), Dam Breaches and Failures (including combined effects provided in NUREG/CR-7046, Appendix H, H.2), Seiche, Tsunami (including combined effects provided in NUREG/CR-7046, Appendix H, H.5), Ice-Induced Flooding, and Channel Migration or Diversion flood-causing mechanisms were either determined to be implausible or completely bounded by other mechanisms. Storm Surge (including combined effects provided in NUREG/CR-7046, Appendix H, H.3) is the primary flood-causing mechanism at Salem

Page 4 10 CFR 50.4 LR-N16-0161 Generating Station; however, the reevaluated flood hazard water surface elevation level (WSEL) remains bounded by the current design basis. LIP is the only flood hazard at SGS for which the reevaluated maximum water surface elevation (WSEL) exceeds its current design basis (COB) WSEL. Parameters for this flood-causing mechanism, including associated effects and flood event duration parameters, are described in detail in Reference 2 and summarized in to this letter.

In Reference 8, the NRC concluded that the "reevaluated flood hazards information, as summarilzed in Attachment 1, is suitable for the assessment of mitigating strategies developed in response to Order EA-12-049 for Salem." Table 2 of Reference 8 describes the reevaluated flood hazards that exceed the current design-basis for use in the MSA (i.e., LIP with associated effects and flood duration parameters).

As discussed in Reference 2, the reevaluated LIP event could produce flood levels that are above the watertight door thresholds, but significantly below the plants' flood-protected elevation of 115 ft. Public Service Datum (PSD); e.g., the maximum LIP flood level at critical door locations is 102 ft. PSD. Protection of safety related SSCs can be ensured by implementing operating procedure SC.OP-AB.ZZ-0001, "Adverse Environmental Conditions," which instructs operators to close all watertight doors. Following submittal of Reference 2, PSEG revised SC.OP-AB.ZZ-0001 to include actions to close watertight doors if the National Weather Service Probabilistic Quantitative Precipitation Forecast (PQPF) predicts Local Intense Precipitation (LI P) to exceed 6 inches over the next 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br />.

The process for closure of the March 12, 2012 Request for Information, Recommendation 2.1 :

Flooding has evolved with NRC and the industry reaching a common ground with the development of the MSA process, and subsequently with the issuance of NEI 16-05, "External Flooding Assessment Guidelines," as endorsed in Interim Staff Guidance JLD-ISG-2016-01, "Guidance for Activities Related to Near-Term Task Force Recommendation 2.1, Flooding Hazard Reevaluation; Focused Evaluation and Integrated Assessment." One area in the MSA process that is not clearly discussed pertains to flood mechanisms which exceed the current licensing basis for that mechanism and therefore are included in the MSFHI, but still have significant available physical margin (APM) to the plant's design basis flood protection level. In the case of SGS, the plant's design basis flood protection features are established to mitigate the effects of a hurricane storm surge event, with the flood protection elevation at approximately 115ft. PSD.

A LIP event alone cannot produce a water surface elevation across the site to challenge SGS's flood protection elevation. Only events where Delaware River water is pushed onto the site from a storm surge could challenge SGS's installed flood protection features' design elevation.

Due to the APM during a LIP event, an extended loss of AC power and loss of ultimate heat sink are not credible outcomes of a BDB LIP event. Therefore, SGS does not consider LIP an event that can challenge key safety functions, and only considers LIP flooding elevations and associated effects in the protection of FLEX connections and equipment during storage.

Reference 6, Section G.3 - Basis for Mitigating Strategies Assessment (FLEX Design Basis Comparison)

At Salem Generating Station, the FLEX design basis (FLEX DB) flood is primarily based on the plant's current design basis (COB) flood, but also incorporated aspects of the reevaluated flood hazard (i.e. MSFHI), including LIP, Flooding in Streams and Rivers, Dam Breaches and Failures, and Tsunami. The FLEX DB flood and associated mitigating strategies are bounded by

Page 5 10 CFR 50.4 LR-N16-0161 the Storm Surge event. LIP is the only flood hazard at SGS for which the reevaluated WSEL exceeds its COB WSEL; therefore, a comparison of the COB, FLEX DB, and MSFHI for LIP is provided in Attachment 1.

Comparison of the FLEX DB and reevaluated flood hazards (Le. MSFHI) shows that the FLEX DB flood bounds the MSFHI for all applicable flood-causing mechanisms, including associated effects and flood event duration parameters. Therefore, SGS considers the requirement to address the reevaluated flooding hazards within its BOB mitigating strategies as being satisfied with no further action required.

There are no regulatory commitments contained in this letter. If you have any questions or require additional information, please do not hesitate to contact Mr. Brian J. Thomas at 856-339-2022.

I declare under penalty of perjury that the foregoing is true and correct.

Executed on f l. I ~ 6 II' (Date)

Sincerely, Charles V. McFeaters Site Vice President Salem Generating Station : SGS FLEX DB and MSFHI- Flood Parameter Comparison Tables cc: Mr. Daniel Dorman, Administrator, Region I, NRC Mr. Patrick Finney, NRC Senior Resident Inspector, Salem Ms. Carleen J. Parker, Project Manager, NRC/NRRlDORL Mr. John Boska, Senior Project Manager, NRC/NRRlJLD Mr. Patrick Mulligan, Chief, NJBNE Mr. Thomas Cachaza, Salem Commitment Tracking Coordinator Mr. Lee Marabella, PSEG Corporate Commitment Coordinator

LR-N16-0161 ATTACHMENT 1 SGS FLEX DB AND MSFHI - FLOOD PARAMETER COMPARISON TABLES

LR-N16-0161 Table 1 - Local Intense Precipitation Flood Parameter Comparison Flood Scenario Parameter Plant's FLEX MSFHI Bounded Current Design (B) or Design Basis Not Basis Bounded (NB)

1. Max Stillwater Elevation (ft. NAVD88) Nil 12.2 12.2 B N/A N/A N/A N/A V)

'00 2. Max Wave Run-up Elevation (ft. NAVD88)

~~

(i5W 3. Max Hydrodynamic (lb/ft)/Debris Loading (Ib) Nil See note See note B

>'0 Q) Q)

--l ...... 4. Effects of Sediment Deposition/Erosion Nil See note See note B

'0 .~

o ()

o 0

5. Other associated effects (identify each effect) N/A N/A N/A N/A

_V)

LL~ 6. Concurrent Site Conditions Nil See note See note B

7. Effects on Groundwater Nil See note See note N/A c 8. Warning Time (hours) Nil See note See note N/A

-g~g 9 . Period of Site Preparation (hours) Nil See note See note N/A

.2>~

LLwB 10. Period of Inundation (hours) Nil 1 1 B

11. Period of Recession (hours) Nil <11 <11 B
12. Plant Mode of Operations Any Any Any B Other
13. Other Factors N/A N/A N/A N/A

=

N/A Not Applicable =

Nil Not Included NOTES CORRESPONDING TO TABLE 1 LINE ITEMS:

1. Elevation varies around the site; this elevation represents the maximum flood elevation at critical door locations. The LIP maximum stillwater elevation is also considered in siting the Outdoor FLEX Storage Areas, and protection of FLEX equipment and connections in the Salem Unit 2 Canyon Area.

=

NAVD88 North American Vertical Datum of 1988. 12.2 ft. NAVD88 is equivalent to 102.0 ft PSD.

2. Consideration of wind-wave action for the LIP event is not explicitly required by NUREG/CR-7046 and is judged to be a negligible because of limited fetch lengths and water depths.
3. The hydrodynamic and hydrostatic loads during a LIP are negligible compared to the design basis loads on SSC due to the Storm Surge event. The debris load for the LIP event is assumed to be negligible due to low flow velocity and water depths. The water depths around the buildings due to LIP are relatively shallow. Also, tie-downs for FLEX equipment at Outdoor FLEX Storage Areas consider the effects of water-induced drag loads.
4. The flow velocities due to the LIP event are determined to be below the suggested velocities (FHRR Reference 2.1-4) for the ground cover type (asphalt, concrete and gravel) at the plant area. Therefore, significant erosion is not expected for the LIP flood. Similarly, the relatively low velocities and flow depths are not expected to have the power to transport sediment and cause significant deposition during the LIP flood. Refer to FHRR Section 2.1.4.2 for further discussion.
5. N/A
6. High winds could be generated concurrent to a LIP event. However, manual actions are not required to protect the plant during LIP flooding so this concurrent condition is not applicable. Closure of watertight doors around the plant takes place prior to the onset of the LIP event.
7. Below grade structures at SGS are designed to mitigate the effects of the continuous presence of groundwater through the use of waterproofing and waterstops. Refer to FHRR Sections 2.10.5 and 3.10.5 for further discussion.
8. The reevaluated LIP event could produce flood levels that are above watertight door thresholds, but significantly below the plants flood protected elevation described in FHRR Section 1.5. Plant safety can be ensured by implementing operating procedure SC.OP-AB.ZZ-0001 , which instructs operators to close all watertight doors. PSEG updated SC.OP-AB.ZZ-0001 to include guidance on accessing the National Weather Service's Probabilistic Quantitative Precipitation Forecast (NWS PQPF). If the NWS PQPF predicts greater than 6 inches of rainfall in the next 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br />, operators are instructed to close the watertight doors.

1 of 2

LR-N16-0161

9. SSG's important to safety are currently protected by means of permanent/passive measures and permanent active features, i.e., watertight doors. Watertight door closure can be performed well within the warning time provided by the 24-hour PQPF trigger discussed above in Note 8, as shown by SGS operating experience (e.g., the flooding walkdown report in Reference 13 documents actual closure can be performed within the required period of time following exceedance of a high river water level trigger). Therefore, the period of site preparation can be performed given the warning time discussed above.
10. SSG's important to safety are currently protected by means of permanent measures. The LIP event is assumed to occur over a one hour period, then enter into a period of recession across the site.
11. Following a one hour LIP event, waters recede from critical door locations in approximately seven hours (See FHRR Table 2.1-3). FHRR Figure 2.1-9 shows the flood depths at 11 hours1.273148e-4 days <br />0.00306 hours <br />1.818783e-5 weeks <br />4.1855e-6 months <br /> after the one hour LIP event concludes. Minor standing water is around the site, but Outdoor FLEX Storage Areas are accessible and critical FLEX deployment routes are passable. SSG's important to safety are currently protected by means of permanent measures.
12. Protection against the LIP flood causing mechanism can be implemented in any operational mode.
13. N/A 2of2