Line 3: |
Line 3: |
| | issue date = 07/19/2007 | | | issue date = 07/19/2007 |
| | title = 06/29/2007 Summary of Category 1 Working-Level Meeting with PPL to Discuss Steam Dryer Analysis, Licensing, Design Approach, and Power Ascension Test Plans | | | title = 06/29/2007 Summary of Category 1 Working-Level Meeting with PPL to Discuss Steam Dryer Analysis, Licensing, Design Approach, and Power Ascension Test Plans |
| | author name = Guzman R V | | | author name = Guzman R |
| | author affiliation = NRC/NRR/ADRO/DORL/LPLI-1 | | | author affiliation = NRC/NRR/ADRO/DORL/LPLI-1 |
| | addressee name = | | | addressee name = |
Line 9: |
Line 9: |
| | docket = 05000387, 05000388 | | | docket = 05000387, 05000388 |
| | license number = NPF-014, NPF-022 | | | license number = NPF-014, NPF-022 |
| | contact person = Guzman R V, NRR/DORL, 415-1030 | | | contact person = Guzman R, NRR/DORL, 415-1030 |
| | document type = Meeting Summary | | | document type = Meeting Summary |
| | page count = 7 | | | page count = 7 |
|
---|
Category:Meeting Summary
MONTHYEARML24155A1992024-06-0303 June 2024 Annual Assessment Meeting for Pa/Md/Ny/Nj Nuclear Power Plants - NRC Meeting Summary ML23228A1952023-08-21021 August 2023 Summary of August 10, 2023, Public Observation Meeting Re. Proposed Alternative ML23179A0012023-06-28028 June 2023 6/7/2023 - Annual Assessment Meeting for Pa/Md/Ny/Nj Nuclear Power Plants - Meeting Summary ML22187A1462022-07-0606 July 2022 Joint Annual Assessment Meeting for Pa/Md/Nj/Ny Nuclear Power Plants - Meeting Summary ML21035A1842021-02-11011 February 2021 Summary of the January 26, 2021, Meeting with Susquehanna Nuclear Regarding a Future License Amendment Request Related to Adopting Technical Specifications Task Force Traveler TSTF-505, Revision 2 ML20065F5522020-03-19019 March 2020 Summary of February 27, 2020, Meeting with Talen Energy Regarding Future License Amendment Request Related to Creating New Condition for Inoperable Manual Synchronization Circuit at Susquehanna Steam Electric Station, Units 1 and 2 ML19308A1082019-11-18018 November 2019 Summary of Meeting with Talen Energy Regarding a Future License Amendment Request Related to Revising the Dose Consequence Analysis for a Loss-Of-Coolant Accident at Susquehanna Steam Electric Station, Units 1 and 2 ML19259A2222019-10-16016 October 2019 Summary of September 16, 2019, Closed Meeting with Susquehanna Nuclear, LLC Regarding the Transition to Allow the Use of Atrium 11 Fuel for the Susquehanna Steam Electric Station, Units 1 and 2 ML19176A0502019-07-16016 July 2019 Summary of June 18, 2019, Meeting with Talen Energy Regarding Submittal of a Potential License Amendment Request Related to Changes to the Emergency Response Organization Staffing and Augmentation ML19191A1882019-07-0909 July 2019 Joint Annual Assessment Meeting (Webinar) for Pennsylvania Power Plants - Meeting Summary ML19134A0292019-05-21021 May 2019 Summary of Pre-Submittal Meeting with Susquehanna Nuclear, LLC to Discuss a Potential License Amendment Request Use of Atrium 11 Fuel ML18311A2622018-11-26026 November 2018 Summary of Pre-Submittal Meeting with Susquehanna Nuclear, LLC to Discuss a Potential License Amendment Request Emergency Service Water Piping Replacement for Susquehanna Steam Electric Station, Units 1 and 2 ML18156A2632018-06-15015 June 2018 May 15, 2018, Summary of Closed Pre-Submittal Meeting with Susquehanna Nuclear, LLC to Discuss a Potential License Amendment Request the Use of Atrium 11 Fuel for Susquehanna Steam Electric Station, Units 1 and 2 ML18141A2032018-05-22022 May 2018 2018 Susquehanna Annual Assessment Meeting Summary and Attendance List ML17250A3902017-09-14014 September 2017 Susquehanna Station, Units 1 and 2 - Summary of August 10, 2017, Pre-Submittal Teleconference with Susquehanna Nuclear, LLC to Discuss a Potential License Amendment Request Re: Technical Specifications Task Force Traveler-542 (CAC Nos. MG0059 and MG0060) ML17153A1012017-06-0202 June 2017 May 4, 2017, Summary of Annual Assessment Meeting for Susquehanna Steam Electric Station Held ML16131A1942016-05-10010 May 2016 April 27, 2016, Summary of Public Meeting on Susquehanna Steam Electric Station ML15295A2022015-10-29029 October 2015 Summary of Meeting with Susquehanna Nuclear, LLC on the TSTF-425 License Amendment Request for Susquehanna Steam Electric Station, Units 1 and 2 ML15278A4922015-10-0909 October 2015 Summary of Meeting with Susquehanna Nuclear, LLC on the Emergency Action Level Scheme Change Submittal for a License Amendment for Susquehanna Steam Electric Station, Units 1 and 2 ML15174A0262015-06-23023 June 2015 Annual Assessment Meeting Summary 2014 ML14247A6082014-09-0404 September 2014 2014 Susquehanna Regulatory Performance Meeting - Summary of Public Meeting ML14191A6992014-07-31031 July 2014 July 2, 2014 Summary of Meeting with PPL Susquehanna, LLC, Pre-Submittal Meeting Regarding Future Submittal for a License Transfer Amendment for Susquehanna Steam Electric Station, Units 1 and 2 ML14133A0592014-07-0101 July 2014 Summary of Closed Meeting Between Representatives of the Army Corps of Engineers, Nuclear Regulatory Commission, Federal Energy Regulatory Commission, Exelon Generation Co, LLC, and PPL Susquehanna, LLC, to Discuss Dam Failure Analysis.. ML14104B1302014-04-14014 April 2014 Summary of Public Meeting on April 9, 2014 ML13121A0812013-05-0101 May 2013 Summary of Public Meeting, Susquehanna Steam Electric Station ML13107B1372013-04-17017 April 2013 Annual Assessment Meeting Sign in Sheets for April 10, 2013 Public Meeting ML12297A2252012-10-23023 October 2012 Summary of Substantive Cross-Cutting Issues Progress Meeting with PPL Susquehanna, LLC, and Acknowledgement of Readiness for NRC 95002 Supplemental Follow-Up Inspection ML12093A3152012-04-0202 April 2012 Summary of March 21, 2012 Susquehanna 95002 Supplemental Inspection Public Exit and Regulatory Performance Meeting ML12093A1472012-04-0202 April 2012 Annual Assessment Meeting Summary ML1015304112010-06-0707 June 2010 Summary of Conference Call with Boiling Water Reactor Vessel and Internals Project Regarding Recent Operating Experience Associated with Replacement Steam Dryer ML0919101962009-07-16016 July 2009 Summary of Telephone Conference Call Held on June 25, 2009, Between the U.S. NRC and PPL Susquehanna, LLC, Comments on the Safety Evaluation Report with Open Items Related to the License Renewal of Susquehanna Steam Electric Station, Units ML0919402172009-07-13013 July 2009 SCWE Public Mtg Sign-in Sheets, for July 6, 2009 ML0919404402009-07-13013 July 2009 Meeting Summary, Public Meeting with PPL Susquehanna, LLC Re SCWE at Site ML0914800822009-06-0101 June 2009 Summary of Telephone Conference Call Held on May 21, 2009, Between the U.S. NRC and PPL Susquehanna, LLC, Concerning the Responses to RAIs Pertaining to the Susquehanna Steam Electric Station, Units 1 and 2, License Renewal Application ML0915204952009-06-0101 June 2009 Summary of Annual Assessment Meeting with PPL Susquehanna, LLC to Discuss the Nrc'S Assessment of the Safety Performance of the Susquehanna Steam Electric Station Units 1 and 2 for the Calendar Year 2008 ML0912502542009-05-0707 May 2009 Summary of Tele Conf Call Held on April 14th, 2009, Between the USNRC and PPL Susquehanna, LLC, Concerning Draft Requests for Additional Information Pertaining to the SSES, Units 1 and 2, License Renewal Application ML0900803792009-01-30030 January 2009 Summary of Telephone Conference Call Held on 12/18/08, Between the U.S. NRC and PPL Susquehanna, LLC, Concerning TLAA RAI ML0833101132008-12-0303 December 2008 Meeting Summary, Telephone Conference Call Between U.S. NRC and PPL Susquehanna, LLC, Concerning the Draft Request for Additional Information Pertaining to the Susquehanna Steam Electric Station Units 1 & 2, LRA ML0832307862008-11-19019 November 2008 11/13/2008-Summary of Telephone Conference Call Between NRC and PPL, Concerning the Responses to RAIs Pertaining to the Susquehanna Steam Electric Station, Units 1 and 2, License Renewal Application ML0832209472008-11-19019 November 2008 Summary of Telephone Conference Call Held on October 10, 2008, Between the U.S. Nuclear Regulatory Commission and PPL Susquehanna, Llc., Concerning the Responses to Requests for Additional Information Pertaining to the Susquehanna Steam... ML0830305912008-11-0303 November 2008 Summary of Telephone Conference Call Held on Sept 24, 2008, Between the U.S. NRC and PPL Susquehanna, Llc., Concerning Draft Requests for Additional Information Pertaining to the SSES, Units 1 and 2, License Renewal Application ML0828901522008-10-21021 October 2008 Summary of Telephone Conference Call Held on October 8, 2008, Between the USNRC and PPL Susquehanna, Llc. Concerning Draft Requests for Additional Information Pertaining to the, License Renewal Application ML0828004392008-10-17017 October 2008 09/15/2008-Summary of Telephone Conference Call Between Us NRC and PPL Susquehanna, LLC, Concerning Draft Request for Additional Information Pertaining to the Susquehanna Steam Electric Station, Units 1 & 2, License Renewal Application ML0828205772008-10-17017 October 2008 09/18/2008 Meeting Summary, Meeting Between the NRC and PPL Susquehanna, Llc., Concerning Requests for Additional Information Responses Pertaining to the Susquehanna Steam Electric Station, Units 1 and 2, License Renewal Application ML0822603532008-10-0101 October 2008 06/25/2008 Meeting Summary, Telephone Conference Call Between the NRC and PPL Susquehanna, LLC, Concerning Draft Request for Additional Information Pertaining to the Susquehanna, Units 1 and 2, License Renewal Application ML0814200522008-05-30030 May 2008 05/19/2008 Summary of Telephone Conference Call Held Between the NRC and PPL Susquehanna, LLC, Concerning Draft Request for Additional Information Pertaining to the Susquehanna, Units 1 and 2, License Renewal Application ML0811307322008-04-22022 April 2008 Summary of Annual Assessment Meeting with PPL Corporation and Susquehanna Nrc'S Assessment of the Safety Performance of the Susquehanna Steam Electric Station (Susquehanna) for Calendar Year 2007 ML0734804472008-04-0404 April 2008 05/14/2007 to 05/17/2007 - Summary of Meeting with PPL Susquehanna, LLC, Environmental Site Audit Related to the Review of the License Renewal Application ML0808501552008-03-26026 March 2008 Units 1 & 2 - Summary of March 18, 2008, Meeting with PPL Susquehanna, on Submission Details for Susquehanna Units and 2, Pose-Extended Power Uprate (EPU) Power Ascension (Tac No. MD8079) ML0801405152008-02-11011 February 2008 Summary of Telephone Conference Call Held on December 28, 2007, Between the U.S. Nuclear Regulatory Commission and PPL Susquehanna, LLC, Concerning Requests for Additional Information Pertaining to the Susquehanna Steam Electric Station, Un 2024-06-03
[Table view] |
Text
July 19, 2007LICENSEE:PPL Susquehanna, LLC (PPL)FACILITY:Susquehanna Steam Electric Station, Units 1 and 2 (SSES 1 and 2)
SUBJECT:
SUMMARY
OF JUNE 29, 2007, CATEGORY 1 WORKING-LEVELMEETING WITH PPL TO DISCUSS STEAM DRYER ANALYSIS, LICENSING, DESIGN APPROACH, AND POWER ASCENSION TEST
PLANSOn June 29, 2007, a public meeting was held between the U.S. Nuclear RegulatoryCommission (NRC), and representatives of PPL and its vendor, General Electric-Hitachi, at NRC Headquarters, One White Flint North, 11555 Rockville Pike, Rockville, Maryland. The purpose of the meeting was to discuss PPL's steam dryer finite element analysis, licensing, design approach, and power ascension test plans. Certain portions of the meeting were closed to the public as some of the presentation material and discussion were determined to be proprietary in nature.PPL provided an overview of the SSES 1 and 2 replacement steam dryer licensing, design,instrumentation, and test plans for the proposed constant pressure power uprate (CPPU).
PPL's conclusion is summarized as follows:(1) the steam dryer licensing basis is conservative and meets the American Society of Mechanical Engineers (ASME) fatigue limit of 13,600 pounds per square inch; (2) the fabricated replacement steam dryer will have reduced stress intensities and increased margins to the ASME fatigue limit;(3) the revised finite element model provides results less than the ASME limit; (4) the replacement steam dryer is designed and fabricated in accordance with Title 10 of the Code of Federal Regulations, Part 50, Appendix B using improved design and fabrication techniques;(5) the Unit 1 steam dryer will be instrumented for 107% current licensed thermal power (CLTP), will demonstrate structural adequacy of the new steam dryer design, and will validate dryer analysis tools;(6) the power ascension test program will be slow and deliberate, consists of an acceptancecriteria based on the 13,600 fatigue limit, will confirm no acoustic resonances at 114%
CLTP, will allow validation of analysis and dryer design prior to full CPPU operation, and will confirm acceptability of the dryer up to full CPPU conditions.
PPL Susquehanna, LLC- 2 -PPL also discussed its corrective actions related to a modeling input error in the finite elementanalysis, as well as its approach in responding to NRC staff's request for supplemental information (Agency Documents Access and Management System (ADAMS) Accession No.
ML071920490).
There were no members of the public in attendance, and no public meeting feedback forms were received. Enclosure 1 is a list of meeting attendees and Enclosure 2 is a non-proprietary copy of the licensee's slides presented at the meeting. A proprietary copy of the licensee's presentation slides can be found in ADAMS (Accession No. ML071980285). Please direct any inquiries to me at 301-415-1030, or rvg@nrc.gov./RA/Richard V. Guzman, Senior Project ManagerPlant Licensing Branch I-1 Division of Operating Reactor Licensing Office of Nuclear Reactor RegulationDocket Nos. 50-387 and 50-388
Enclosures:
- 1. List of Attendees
- 2. Licensee's Handouts/Slides (Non-Proprietary)cc w/encls: See next page
ML071970172OFFICELPLI-1/PMLPLI-1/LALPLI-1/BCNAMERGuzmanSLittleMKowalDATE7/18/077/18/077/19/07 LIST OF ATTENDEESNUCLEAR REGULATORY COMMISSION (NRC)NUCLEAR REACTOR REGULATION (NRR) CATEGORY 1 MEETINGWITH PPL SUSQUEHANNA, LLC (PPL)REPLACEMENT STEAM DRYER ANALYSIS, DESIGN, AND TESTING PLANSFOR THE PROPOSED EXTENDED POWER UPRATE APPLICATIONSUSQUEHANNA STEAM ELECTRIC STATION, UNITS 1 AND 2JUNE 27, 2007NAME ORGANIZATION1. Richard GuzmanNRC/NRR/Plant Licensing Branch I-12. Kamal ManolyNRC/NRR/Mechanical and Civil Engineering Branch
- 3. John WuNRC/NRR/Mechanical and Civil Engineering Branch
- 4. Chakrapani BasavarajuNRC/NRR/Mechanical and Civil Engineering Branch
- 5. William JessupNRC/NRR/Mechanical and Civil Engineering Branch
- 6. Tom ScarbroughNRC/NRR/Component Performance and Testing Branch
- 7. Tom AlexionNRC/NRR/Generic Communication and Power Uprate
- 8. Rick PagodinPPL
- 9. Micheal CrowthersPPL
- 10. Michael GorskiPPL
- 11. John BartosPPL
- 12. John KraisPPL
- 13. Kevin BrowningPPL
- 14. Craig NicholsGeneral Electric - Hitachi
- 15. Mike BridgesGeneral Electric - Hitachi
- 16. Jim KlapprothGeneral Electric - Hitachi
- 17. Larry KingGeneral Electric - Hitachi
- 18. Rico BettiGeneral Electric - Hitachi
- 19. Dan PapponeGeneral Electric - Hitachi
- 20. Joseph FerranteNuclear Management Company - Monticello
- 21. Shelly KuglerPublic Service Enterprise Group Nuclear - Hope Creek
- 22. Jamie Mallon Public Service Enterprise Group Nuclear - Hope Creek
- 23. Gary PavisConstellation Energy Group - Nine Mile Point
- 24. Steve Hambric NRC Contractor
- 25. Vic ShahNRC Contractor
- 26. Samir ZiadaNRC ContractorEnclosure 1 MEETING SLIDES (Non-proprietary version)Enclosure 2 Susquehanna Steam Electric Station, Units 1 and 2 cc:
Britt T. McKinneySr. Vice President and Chief Nuclear Officer PPL Susquehanna, LLC 769 Salem Blvd., NUCSB3 Berwick, PA 18603-0467Cornelius J. GannonVice President - Nuclear Operations PPL Susquehanna, LLC 769 Salem Blvd., NUCSB3 Berwick, PA 18603-0467Robert M. PaleyGeneral Manager - Plant Support PPL Susquehanna, LLC 769 Salem Blvd., NUCSB2 Berwick, PA 18603-0467Rocco R. SgarroManager - Nuclear Regulatory Affairs PPL Susquehanna, LLC Two North Ninth Street, GENPL4 Allentown, PA 18101-1179Supervisor -Nuclear Regulatory Affairs PPL Susquehanna, LLC 769 Salem Blvd., NUCSA4 Berwick, PA 18603-0467Michael H. CrowthersSupervising Engineer Nuclear Regulatory Affairs PPL Susquehanna, LLC Two North Ninth Street, GENPL4 Allentown, PA 18101-1179Ronald E. SmithGeneral Manager - Site Preparedness and Services PPL Susquehanna, LLC 769 Salem Blvd., NUCSA4 Berwick, PA 18603-0467Manager - Quality AssurancePPL Susquehanna, LLC 769 Salem Blvd., NUCSB2 Berwick, PA 18603-0467Luis A. RamosCommunity Relations Manager, Susquehanna PPL Susquehanna, LLC 634 Salem Blvd., SSO Berwick, PA 18603-0467Bryan A. Snapp, EsqAssoc. General Counsel PPL Services Corporation Two North Ninth Street, GENTW3 Allentown, PA 18101-1179Supervisor - Document Control ServicesPPL Susquehanna, LLC Two North Ninth Street, GENPL4 Allentown, PA 18101-1179Richard W. OsborneAllegheny Electric Cooperative, Inc.
212 Locust Street P.O. Box 1266 Harrisburg, PA 17108-1266Director, Bureau of Radiation ProtectionPennsylvania Department of Environmental Protection Rachel Carson State Office Building P.O. Box 8469 Harrisburg, PA 17105-8469Senior Resident InspectorU.S. Nuclear Regulatory Commission P.O. Box 35, NUCSA4Berwick, PA 18603-0035Regional Administrator, Region 1U.S. Nuclear Regulatory Commission
475 Allendale Road King of Prussia, PA 19406Board of SupervisorsSalem Township P.O. Box 405 Berwick, PA 18603-0035Dr. Judith JohnsrudNational Energy Committee Sierra Club 443 Orlando Avenue State College, PA 16803