| | number = ML100620980 | | | number = ML100620980 |
| | issue date = 03/03/2010 | | | issue date = 03/03/2010 |
| | title = Robinson Report 22 - 2010001 Inspection/Activity Plan | | | title = Report 22 - 2010001 Inspection/Activity Plan |
| | author name = | | | author name = |
| | author affiliation = NRC/RGN-II/DRP | | | author affiliation = NRC/RGN-II/DRP |
Revision as of 18:13, 16 April 2019
|
---|
Category:Inspection Plan
MONTHYEARML23342A0902023-12-0808 December 2023 Notification of Inspection and Request for Information for NRC Problem Identification and Resolution Inspection ML23235A0552023-08-23023 August 2023 Notification of an Fire Protection Team Inspection (FPTI) (NRC Inspection Report 05000261/2023010) and Request for Information (RFI) IR 05000261/20230052023-08-21021 August 2023 Updated Inspection Plan for H.B. Robinson Steam Electric Plant (Report 05000261/2023005) ML23131A4192023-05-10010 May 2023 003 Radiation Safety Baseline Inspection Information Request IR 05000261/20220062023-03-0101 March 2023 Annual Assessment Letter for H.B. Robinson Steam Electric Plant, Unit 2 (Report 05000261/2022006) IR 05000261/20220052022-08-26026 August 2022 Updated Inspection Plan for the H.B Robinson Steam Electric Plant - Report 05000261/2022005-Final ML22098A2262022-04-11011 April 2022 Notification of Inspection and Request for Information for NRC Problem Identification and Resolution Inspection IR 05000261/20210062022-03-0202 March 2022 Annual Assessment Letter for H.B. Robinson Steam Electric Plant Unit 2 (Report No. 05000261/2021006) ML22018A0292022-01-18018 January 2022 Region 2 RFI - 2022 Program Inspections ML21295A2992021-10-22022 October 2021 Document Request for Robinson Nuclear Plant - Radiation Protection Inspection - Inspection Report 2021004 IR 05000261/20200062021-03-0303 March 2021 Annual Assessment Letter for H.B. Robinson Steam Electric Plant Unit 2 Report 05000261/2020006 ML20191A2192020-07-0909 July 2020 Notification of Conduct of a Fire Protection Team Baseline Inspection U.S. Nuclear Regulatory Commission Inspection Report No. 05000261/2020012 ML19347D1072019-12-13013 December 2019 Plan - Notification of Inspection and Request for Information for NRC Problem Identification and Resolution Inspection IR 05000261/20190052019-08-28028 August 2019 Updated Inspection Plan for H.B. Robinson Steam Electric Plant, Unit 2 - (Report 05000261/2019005) ML19232A4172019-08-20020 August 2019 Radiation Safety Baseline Inspection RFI 2019-004 IR 05000261/20180062019-03-0404 March 2019 Annual Assessment Letter for H. B. Robinson Steam Electric Plant, Unit 2 - Report 05000261/2018006, Report 05000261/2018402, Report 05000261/2018501 IR 05000261/20180052018-08-23023 August 2018 Updated Inspection Plan for H.B. Robinson Steam Electric Plant Unit 2 (Inspection Report 05000261/2018005) ML18215A1352018-08-0303 August 2018 U2 Baseline In-Service Inspection 2018003 Public ML18172A1142018-06-20020 June 2018 Radiation Safety Baseline Inspection Emailed Initial Information Request 2018003 ML18115A0512018-04-25025 April 2018 RP Inspect Info & Doc Request IR 05000261/20170062018-02-28028 February 2018 Annual Assessment Letter for H.B. Robinson Steam Electric Plant Unit 2 - Report 05000261/2017006, Report 05000261/2017402, Report 05000261/2017501 IR 05000261/20170052017-08-28028 August 2017 Updated Inspection Plan for H. B. Robinson Steam Electric Plant - NRC Inspection Report 05000261/2017005 IR 05000261/20160062017-03-0101 March 2017 Annual Assessment Letter for H. B. Robinson Steam Electric Plant - NRC Inspection Report 05000261/2016006 ML17021A0042017-01-20020 January 2017 Notification of Inspection and Request for Information IR 05000261/20160052016-08-31031 August 2016 Mid-Cycle Assessment Letter for H.B Robinson Steam Electric Plant - NRC Inspection Report 05000261/2016005 ML16092A2002016-03-29029 March 2016 Notification of H.B. Robinson Steam Electric Plant - Component Design Bases Inspection - U.S. Nuclear Regulatory Commission Inspection Report 05000261/2016008 IR 05000261/20150062016-03-0202 March 2016 Annual Assessment Letter for H.B. Robinson Steam Electric Plant - NRC Inspection Report 05000261/2015006 IR 05000261/20150052015-09-0101 September 2015 Mid-Cycle Assessment Letter for H.B. Robinson Steam Electric Plant - NRC Inspection Report 05000261/2015005 IR 05000261/20140012015-03-0404 March 2015 Annual Assessment Letter for H.B. Robinson Steam Electric Plant NRC Inspection Report 05000261/2014001 ML14245A1732014-09-0202 September 2014 Mid-Cycle Ltr 2014 ML14063A1832014-03-0404 March 2014 2013 Annual Assessment Letter for H.B. Robinson Steam Electric Plant ML13246A0682013-09-0303 September 2013 Mid Cycle Assessment Letter ML13224A3172013-08-12012 August 2013 Notification of Inspection and Request for Information ML13085A1272013-03-26026 March 2013 Notification of Inspection and Request for Information IR 05000261/20120012013-03-0404 March 2013 Annual Assessment Letter for H.B. Robinson Steam Electric Plant (NRC Inspection Report 05000261/2012001) ML12248A1642012-09-0404 September 2012 Mid Cycle Assessment Letter Robinson 2012 ML12209A3772012-07-27027 July 2012 IR 05000261-12-008, on 01/01/2012, H.B. Robinson Steam Electric Plant-Notification of Conduct of a Triennial Fire Protection Baseline Inspection ML1206504242012-03-0505 March 2012 End of Cycle Assessment Report 22 IR 05000261/20110012011-03-0404 March 2011 Annual Assessment Letter (Report 05000261/2011001) ML1024405952010-09-0101 September 2010 Report 22 - 2010 Mid Cycle Inspection/Activity Plan ML1006209802010-03-0303 March 2010 Report 22 - 2010001 Inspection/Activity Plan ML0924405542009-09-0101 September 2009 Inspection/Activity Plan, Report 22, 09/01/2009 - 12/31/2010 RNP-RA/09-0067, Nickel-Alloy Nozzles and Penetrations Program Inspection Plan2009-07-29029 July 2009 Nickel-Alloy Nozzles and Penetrations Program Inspection Plan ML0824610022008-09-0202 September 2008 Inspection / Activity Plan, 09/01/2008 - 12/31/2009, Report 22 IR 05000261/20080012008-03-0303 March 2008 Annual Assessment Letter (IR 05000261-08-001) ML0724306772007-08-31031 August 2007 Mid-Cycle 2007 Report ML0724702262007-08-31031 August 2007 Mid-Cycle Performance Review and Inspection Plan - H.B. Robinson Steam Electric Plant Unit 2 ML0706001892007-03-0101 March 2007 Inspection / Activity Plan 03/01/2007 - 09/30/2008 - Report 22 ML0624304422006-08-31031 August 2006 Mid-Cycle Performance Review and Inspection Plan, 09/01/06 - 03/31/08 ML0606103992006-03-0202 March 2006 Inspection/Activity Plan for 03/01/2006 - 09/30/2007 2023-08-23
[Table view] |
Text
Inspection / Activity Plan Page 1 of 2 03/03/2010 07:02:24 Report 22 03/01/2010
-06/30/2011 Unit Number Planned Dates Start End Inspection Activity Title No. of Staff on Site Robinson TFPI 805-TRIENNIAL FIRE PROTECTION 7
PSB1-RP-RP OCCUPATIONAL BASELINE WEEK1 2
EB3ISI-UNIT 2 INSERVICE INSPECTION 1
EB3TI172-EB3 RCS DM BUTT WELDS 1
EB3SGISI-EB3 SG INSERVICE INSPECTION 1
PSB1-RP-RP OCCUPATIONAL BASELINE WEEK 2 3
PSB1EP-EMERGENCY PREPAREDNESS INSPECTION 1
PSB1-RP-RP GROUND WATER PROTECTION 1
PI&R-PROBLEM IDENTIFICATION AND RESOLUTION 7
EB1-COMPONENT DESIGN BASES INSPECTION 6
Inspection / Activity Plan Page 2 of 2 03/03/2010 07:02:24 Report 22 03/01/2010
-06/30/2011 Unit Number Planned Dates Start End Inspection Activity Title No. of Staff on Site Robinson EB1-COMPONENT DESIGN BASES INSPECTION 6
PSB1-RP-RP PUBLIC RADIAITON SAFETY INSP 3
INSP-MODS/50.59 INSP 2
OL EXAM-INITIAL EXAM PREP 3
OL EXAM-INITIAL EXAM - WEEK 1 3
OL EXAM-INITIAL EXAM - WEEK 2 3
PSB1EP-EMERGENCY PREPAREDNESS EXERCISE 4