ML18108A015: Difference between revisions

From kanterella
Jump to navigation Jump to search
(Created page by program invented by StriderTol)
(Created page by program invented by StriderTol)
Line 2: Line 2:
| number = ML18108A015
| number = ML18108A015
| issue date = 05/01/2018
| issue date = 05/01/2018
| title = Point Beach Nuclear Plant, Units 1 and 2 - NextEra Approach to Resolution of Tornado Missile Protection May 1, 2018
| title = NextEra Approach to Resolution of Tornado Missile Protection May 1, 2018
| author name =  
| author name =  
| author affiliation = NextEra Energy Point Beach, LLC
| author affiliation = NextEra Energy Point Beach, LLC

Revision as of 06:02, 31 January 2019

NextEra Approach to Resolution of Tornado Missile Protection May 1, 2018
ML18108A015
Person / Time
Site: Point Beach  NextEra Energy icon.png
Issue date: 05/01/2018
From:
Point Beach
To:
Division of Operating Reactor Licensing
Chawla M L, NRR/DORL/LPLIII, 415-8371
References
Download: ML18108A015 (8)


Text

NextEra Approach to Resolution of Tornado Missile Protection Point Beach Nuclear Plant Units 1 & 2 May 1, 2018 2 AGENDA*Introductions

  • Current Status
  • Compensatory Measures
  • Resolution Strategy
  • Conclusion 3 INTRODUCTIONS
  • NRC*NextEra Point Beach Team-Steve Catron, Fleet Licensing Manager-Anil Julka, Reliability & Risk Manager

-Eric Schultz, PB Licensing Manager

-Lori Christensen, PB Licensing Project Manager

  • 3 4CURRENT STATUS
  • Background
  • Initial Nonconformance Declaration (U1 & U2)-Turbine Driven Auxiliary Feedwater Pumps (TDAFPs) for unprotected steam supply piping
  • Comprehensive Compensatory Measures-Procedurally controlled measures-FLEX equipment sharing
  • Other Discernable Changes from Original Station Design-FLEX implementation-Station modifications (design basis and beyond design basis)
  • 5Compensatory measures in place; original station design improved over time and enhanced ability to mitigate a tornado missile event 6 RESOLUTION STRATEGY
  • The resolution strategy is to validate that Tornado Missile is not a significant hazard for the site-LAR submittal and approval will clear nonconformances
  • Options Considered for LAR Development-TMRE (Point Beach was a pilot plant)-Site-specific High Winds PRA (RG 1.200, Rev. 2)
  • 6License Amendment Request will screen out tornado missile as a significant hazard for the site 7 RESOLUTION STRATEGY
  • Site-specific High Winds PRA-Industry leader-Developed in 2013Updated to reflect as-built/as-operated plant
  • License Amendment Request submittal based on Site-Specific High Winds PRA-Site PRA concludes Tornado Missile is below the regulatory threshold in the Standard Review Plan and screens out as a significant hazard
  • Plan to submit LAR in second half of 2018
  • 8License Amendment Request will screen out tornado missile as a significant hazard for the site