ML071030397: Difference between revisions

From kanterella
Jump to navigation Jump to search
(Created page by program invented by StriderTol)
(StriderTol Bot change)
 
(One intermediate revision by the same user not shown)
Line 15: Line 15:


=Text=
=Text=
{{#Wiki_filter:April 13, 2007  
{{#Wiki_filter:April 13, 2007 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, D.C. 20555 Gentlemen:
In the Matter of                )        Docket No. 50-259 Tennessee Valley Authority      )
BROWNS FERRY NUCLEAR PLANT (BFN) - STATUS OF UNIT 1 RESTART ISSUES, REVISION 12 This letter updates the status of the Unit 1 Bulletins, Generic Letters, Nuclear Performance Plan Special Programs, and TMI Action Items identified in TVA's regulatory framework letters to NRC (References 1 and 2). As documented in the NRCs approval of TVAs regulatory framework (References 3 and 4), the staff requested and TVA agreed to provide formal notification of the completion of each generic communication within 90 days of its internal commitment completion. This letter is part of the process that is being used to satisfy this request. Additional items from the NRCs Browns Ferry Unit 1 Recovery Issues List (Reference 5) have also been included. to this letter provides background information regarding the regulatory framework for the restart of Unit 1, lists the individual issues cited in the framework letters and the NRCs Recovery Issues List, describes TVAs commitment or outstanding action for each issue, references key correspondence, discusses the background of the issue, and describes the completion or status of each issue, as appropriate. A summary of the issues that will be completed after restart for Unit 1 is provided as Enclosure 2.


U.S. Nuclear Regulatory Commission  
U.S. Nuclear Regulatory Commission Page 2 April 13, 2007 TVA intends to periodically update this submittal until the Unit 1 commitments related to restart or power operation are completed (TVA committed actions are completed). The first status of these generic communications was provided in Reference 6. The updates will provide the formal notification of the completion of each Unit 1 Bulletin, Generic Letter, Nuclear Performance Plan Special Program, and TMI Action Item required for restart. Changes to the completion status and newly added issues are bolded in the table of contents.
Changes to the completion status are also bolded in the text which describes each item. Other changes are noted by revision bars on the right hand side of the page.
There are no new positions or commitments contained in this letter. If you have any questions, please contact me at (205) 729-2636.
Sincerely, Original signed by:
William D. Crouch Manager of Licensing and Industry Affairs


ATTN:  Document Control Desk
==References:==
 
: 1. TVA letter, T. E. Abney to NRC, dated December 13, 2002, Browns Ferry Nuclear Plant (BFN) - Unit 1 - Regulatory Framework for the Restart of Unit 1
Washington, D.C. 20555
: 2. TVA letter, T. E. Abney to NRC, dated February 28, 2003, Browns Ferry Nuclear Plant (BFN) - Unit 1 - Regulatory Framework for the Restart of Unit 1
 
: 3. NRC memorandum from K. N. Jabbour, dated May 13, 2003, Summary of April 24, 2003, Meeting Regarding the Regulatory Framework for Browns Ferry Unit 1 Restart Project (TAC No. MB7679)
Gentlemen:
: 4. NRC letter, K. N. Jabbour to J. A. Scalice, dated August 14, 2003, Regulatory Framework for the Restart of Browns Ferry Nuclear Plan, Unit 1 (TAC MB7679)
 
In the Matter of                ) Docket No. 50-259 Tennessee Valley Authority      ) 
 
BROWNS FERRY NUCLEAR PLANT (BFN) - STATUS OF UNIT 1 RESTART ISSUES, REVISION 12 This letter updates the status of the Unit 1 Bulletins, Generic Letters, Nuclear Performance Plan Special Programs, and TMI Action Items identified in TVA's regulatory framework
 
letters to NRC (References 1 and 2). As documented in the
 
NRC's approval of TVA's regulatory framework (References 3
 
and 4), the staff requested and TVA agreed to provide formal
 
notification of the completion of each generic communication
 
within 90 days of its internal commitment completion. This
 
letter is part of the process that is being used to satisfy
 
this request. Additional items from the NRC's Browns Ferry
 
Unit 1 Recovery Issues List (Reference 5) have also been
 
included.
 
to this letter provides background information
 
regarding the regulatory framework for the restart of Unit 1, lists the individual issues cited in the framework letters and
 
the NRC's Recovery Issues List, describes TVA's commitment or
 
outstanding action for each issue, references key
 
correspondence, discusses the background of the issue, and
 
describes the completion or status of each issue, as
 
appropriate. A summary of the issues that will be completed
 
after restart for Unit 1 is provided as Enclosure 2.
 
U.S. Nuclear Regulatory Commission Page 2 April 13, 2007
 
TVA intends to periodically update this submittal until the
 
Unit 1 commitments related to restart or power operation are
 
completed (TVA committed actions are completed). The first
 
status of these generic communications was provided in
 
Reference 6. The updates will provide the formal notification
 
of the completion of each Unit 1 Bulletin, Generic Letter, Nuclear Performance Plan Special Program, and TMI Action Item
 
required for restart. Changes to the completion status and
 
newly added issues are bolded in the table of contents. 
 
Changes to the completion status are also bolded in the text
 
which describes each item. Other changes are noted by
 
revision bars on the right hand side of the page.
 
There are no new positions or commitments contained in this
 
letter. If you have any questions, please contact me at
 
(205) 729-2636.
 
Sincerely,
 
Original signed by:  
 
William D. Crouch
 
Manager of Licensing
 
and Industry Affairs
 
References
: 1. TVA letter, T. E. Abney to NRC, dated December 13, 2002, Browns Ferry Nuclear Plant (BFN) - Unit 1 - Regulatory  
 
Framework for the Restart of Unit 1 2. TVA letter, T. E. Abney to NRC, dated February 28, 2003, Browns Ferry Nuclear Plant (BFN) - Unit 1 - Regulatory  
 
Framework for the Restart of Unit 1 3. NRC memorandum from K. N. Jabbour, dated May 13, 2003, Summary of April 24, 2003, Meeting Regarding the  
 
Regulatory Framework for Browns Ferry Unit 1 Restart  
 
Project (TAC No. MB7679) 4. NRC letter, K. N. Jabbour to J. A. Scalice, dated August 14, 2003, Regulatory Framework for the Restart of  
 
Browns Ferry Nuclear Plan, Unit 1 (TAC MB7679)


U.S. Nuclear Regulatory Commission Page 3 April 13, 2007
U.S. Nuclear Regulatory Commission Page 3 April 13, 2007
: 5. NRC letter, J. W. Shea to K. W. Singer, dated January 6, 2006, Meeting Summaries: 1.) Category 1 Public  
: 5. NRC letter, J. W. Shea to K. W. Singer, dated January 6, 2006, Meeting Summaries: 1.) Category 1 Public Meeting with Tennessee Valley Authority (TVA) RE. Browns Ferry Unit 1 Recovery Status; 2.) Meeting of the NRC Restart Panel for the Browns Ferry Unit 1 Recovery -
 
Docket No. 50-259
Meeting with Tennessee Valley Authority (TVA) RE. Browns  
: 6. TVA letter, T. E. Abney to NRC, dated November 19, 2004, Browns Ferry Nuclear Plant (BFN) - Status of Unit 1 Restart Issues Enclosures cc (Enclosures):
 
Ferry Unit 1 Recovery Status; 2.) Meeting of the NRC  
 
Restart Panel for the Browns Ferry Unit 1 Recovery -  
 
Docket No. 50-259 6. TVA letter, T. E. Abney to NRC, dated November 19, 2004, Browns Ferry Nuclear Plant (BFN) - Status of Unit 1  
 
Restart Issues  
 
Enclosures  
 
cc (Enclosures):
(Via NRC Electronic Distribution)
(Via NRC Electronic Distribution)
U.S. Nuclear Regulatory Commission
U.S. Nuclear Regulatory Commission Region II Sam Nunn Atlanta Federal Center 61 Forsyth Street, SW, Suite 23T85 Atlanta, Georgia 30303-3415 Mr. Malcolm T. Widmann, Branch Chief U.S. Nuclear Regulatory Commission Region II Sam Nunn Atlanta Federal Center 61 Forsyth Street, SW, Suite 23T85 Atlanta, Georgia 30303-8931 NRC Senior Resident Inspector Browns Ferry Nuclear Plant 10833 Shaw Road Athens, AL 35611-6970 Ms. Margaret Chernoff, Senior Project Manager U.S. Nuclear Regulatory Commission (MS 08G9)
 
One White Flint, North 11555 Rockville Pike Rockville, Maryland 20852-2739 Ms. Eva A. Brown, Project Manager U.S. Nuclear Regulatory Commission (MS 08G9)
Region II  
One White Flint, North 11555 Rockville Pike Rockville, Maryland 20852-2739
 
Sam Nunn Atlanta Federal Center  
 
61 Forsyth Street, SW, Suite 23T85  
 
Atlanta, Georgia 30303-3415  
 
Mr. Malcolm T. Widmann, Branch Chief
 
U.S. Nuclear Regulatory Commission  
 
Region II  
 
Sam Nunn Atlanta Federal Center  
 
61 Forsyth Street, SW, Suite 23T85  
 
Atlanta, Georgia 30303-8931  
 
NRC Senior Resident Inspector  
 
Browns Ferry Nuclear Plant  
 
10833 Shaw Road  
 
Athens, AL 35611-6970  
 
Ms. Margaret Chernoff, Senior Project Manager  
 
U.S. Nuclear Regulatory Commission (MS 08G9)  
 
One White Flint, North  
 
11555 Rockville Pike  
 
Rockville, Maryland 20852-2739  
 
Ms. Eva A. Brown, Project Manager  
 
U.S. Nuclear Regulatory Commission (MS 08G9)  
 
One White Flint, North  
 
11555 Rockville Pike  
 
Rockville, Maryland 20852-2739 U.S. Nuclear Regulatory Commission Page 4 April 13, 2007
 
JEM:TLE:BAB
 
Enclosures
 
cc (Enclosures):
M. Bajestani, NAB 1A-BFN
 
A. S. Bhatnagar, LP 6A-C
 
R. H. Bryan, Jr., LP 4J-C
 
R. G. Jones, POB 2C-BFN
 
R. F. Marks, PAB 1A-BFN
 
B. J. O'Grady, PAB 1E-BFN
 
P. D. Swafford, LP 6A-C
 
J. Valente, NAB 1E-BFN
 
E. J. Vigluicci, WT 6A-K
 
B. A. Wetzel, BR 4X-C
 
NSRB Support, LP 5M-C
 
EDMS WT CA-K S:lic/submit/subs/Status of Unit 1 Restart Issues - R12.doc
 
Open:      TVA committed actions are not complete.
Closed:    Item has been closed by NRC document.
Complete:  TVA committed actions are completed.
C-C:      Issue is "Closed" and "Complete."
E1-i INDEX TO ENCLOSURE 1 TENNESSEE VALLEY AUTHORITY BROWNS FERRY NUCLEAR PLANT (BFN)
STATUS OF UNIT 1 ISSUES
 
TABLE OF COMMENTS TOPIC  PAGE STATUS FOR RESTART Background  E1-1  -
Bulletin 79-02, Pipe Support Base Plate Designs Using Concrete Expansion Anchor Bolts E1-4  C-C Bulletin 79-12, Short Period Scrams at BWR Facilities E1-5  C-C Bulletin 79-14, Seismic Analysis for As-Built Safety-Related Piping Systems E1-6  C-C Bulletin 80-06, Engineered Safety Feature (ESF)
Reset Controls E1-7  C-C Bulletin 84-02, Failures of General Electric Type HFA Relays in Use in Class 1E Safety
 
Systems  E1-8  Closed Bulletin 86-02, Static "O" Ring Differential Pressure Switches E1-9  C-C Bulletin 88-03, Inadequate Latch Engagement in HFA Type Relays Manufactured by General
 
Electric (GE) Company E1-11  Closed Bulletin 88-04, Potential Safety-Related Pump Loss  E1-12  C-C Bulletin 88-07, Power Oscillations in Boiling Water Reactors, and Supplement 1 E1-14  C-C Bulletin 88-10, Nonconforming Molded-Case Circuit Breakers E1-15  C-C Open:      TVA committed actions are not complete.
Closed:    Item has been closed by NRC document.
Complete:  TVA committed actions are completed.
C-C:      Issue is "Closed" and "Complete."
E1-ii TOPIC  PAGE STATUS FOR RESTART Bulletin 90-01, Loss of Fill Oil in Transmitters Manufactured by Rosemount E1-16  C-C Bulletin 93-02, Debris Plugging of Emergency Core Cooling Suction Strainers, and
 
Supplement 1 E1-18  C-C Bulletin 93-03, Resolution of Issues Related To Reactor Vessel Water Level Instrumentation in
 
BWRs  E1-20  C-C Bulletin 95-02, Unexpected Clogging of a Residual Heat Removal (RHR) Pump Strainer
 
While Operating in Suppression Pool Cooling
 
Mode  E1-21  C-C Bulletin 96-03, Potential Plugging of Emergency Core Cooling Suction Strainers by Debris in


Boiling-Water Reactors E1-22  C-C Cable Ampacity  E1-23  Complete Cable Installation Issue Number 1, Brand Rex Cable Issues E1-24  Open Cable Installation Issue Number 2, Cable Separations Issues E1-25  Complete Cable Installation Issue Number 3, Low Voltage Vertical Cable Supports E1-28  Open Cable Installation Issue Number 4, Medium Voltage Cable Bend Radius E1-29  Open Cable Installation Issue Number 5, Missing Conduit Bushings E1-31  Open Cable Installation Issue Number 6, Sidewall Pressure, Cable Pullbys, Cable Jamming, Pulling Around 90 Degree Condulets and Thru
U.S. Nuclear Regulatory Commission Page 4 April 13, 2007 JEM:TLE:BAB Enclosures cc (Enclosures):
M. Bajestani, NAB 1A-BFN A. S. Bhatnagar, LP 6A-C R. H. Bryan, Jr., LP 4J-C R. G. Jones, POB 2C-BFN R. F. Marks, PAB 1A-BFN B. J. OGrady, PAB 1E-BFN P. D. Swafford, LP 6A-C J. Valente, NAB 1E-BFN E. J. Vigluicci, WT 6A-K B. A. Wetzel, BR 4X-C NSRB Support, LP 5M-C EDMS WT CA-K S:lic/submit/subs/Status of Unit 1 Restart Issues - R12.doc


Mid-Run Flex Conduit Issues E1-32 Open Open:      TVA committed actions are not complete.
INDEX TO ENCLOSURE 1 TENNESSEE VALLEY AUTHORITY BROWNS FERRY NUCLEAR PLANT (BFN)
STATUS OF UNIT 1 ISSUES TABLE OF COMMENTS STATUS FOR TOPIC                          PAGE RESTART Background                                          E1-1      -
Bulletin 79-02, Pipe Support Base Plate Designs Using Concrete Expansion Anchor Bolts              E1-4    C-C Bulletin 79-12, Short Period Scrams at BWR Facilities                                        E1-5    C-C Bulletin 79-14, Seismic Analysis for As-Built Safety-Related Piping Systems                      E1-6    C-C Bulletin 80-06, Engineered Safety Feature (ESF)
Reset Controls                                    E1-7    C-C Bulletin 84-02, Failures of General Electric Type HFA Relays in Use in Class 1E Safety Systems                                            E1-8 Closed Bulletin 86-02, Static "O" Ring Differential Pressure Switches                                  E1-9    C-C Bulletin 88-03, Inadequate Latch Engagement in HFA Type Relays Manufactured by General Electric (GE) Company                              E1-11 Closed Bulletin 88-04, Potential Safety-Related Pump Loss                                              E1-12  C-C Bulletin 88-07, Power Oscillations in Boiling Water Reactors, and Supplement 1                  E1-14  C-C Bulletin 88-10, Nonconforming Molded-Case Circuit Breakers                                  E1-15  C-C Open:      TVA committed actions are not complete.
Closed:    Item has been closed by NRC document.
Closed:    Item has been closed by NRC document.
Complete:  TVA committed actions are completed.
Complete:  TVA committed actions are completed.
C-C:      Issue is "Closed" and "Complete."
C-C:      Issue is Closed and Complete.
E1-iii TOPIC  PAGE STATUS FOR RESTART Cable Installation Issue Number 7, Use of Condulets as Pull Points E1-33  Open Cable Installation Issue Number 8, Medium Voltage Vertical Cable Supports E1-34  Open Cable Splices  E1-35  Complete Cable Tray Supports  E1-36  C-C Component and Piece Part Qualification  E1-38  Complete Conduit Supports  E1-39  C-C Configuration Management/Design Baseline  E1-41  C-C Containment Coatings  E1-42  Complete Control Rod Drive (CRD) Insert and Withdrawal Piping  E1-43  C-C Design Calculation Review  E1-44  C-C Environmental Qualification  E1-45  Open Fire Protection / 10 CFR 50, Appendix R  E1-46  Open Flexible Conduits  E1-48  Complete Fuses  E1-50  Complete Generic Letter 82-33, Instrumentation to Follow the Course of an Accident - Regulatory Guide
E1-i


1.97 E1-51  C-C Generic Letter 83-08, Modification of Vacuum Breakers on Mark 1 Containments E1-54  C-C Generic Letter 83-28, Salem ATWS, Item 1.2, Post Trip Review (Data and Information
STATUS FOR TOPIC                        PAGE RESTART Bulletin 90-01, Loss of Fill Oil in Transmitters Manufactured by Rosemount          E1-16    C-C Bulletin 93-02, Debris Plugging of Emergency Core Cooling Suction Strainers, and Supplement 1                                   E1-18    C-C Bulletin 93-03, Resolution of Issues Related To Reactor Vessel Water Level Instrumentation in BWRs                                            E1-20    C-C Bulletin 95-02, Unexpected Clogging of a Residual Heat Removal (RHR) Pump Strainer While Operating in Suppression Pool Cooling Mode                                            E1-21    C-C Bulletin 96-03, Potential Plugging of Emergency Core Cooling Suction Strainers by Debris in Boiling-Water Reactors                          E1-22    C-C Cable Ampacity                                    E1-23 Complete Cable Installation Issue Number 1, Brand Rex Cable Issues                                    E1-24    Open Cable Installation Issue Number 2, Cable Separations Issues                              E1-25 Complete Cable Installation Issue Number 3, Low Voltage Vertical Cable Supports                        E1-28    Open Cable Installation Issue Number 4, Medium Voltage Cable Bend Radius                      E1-29    Open Cable Installation Issue Number 5, Missing Conduit Bushings                                E1-31    Open Cable Installation Issue Number 6, Sidewall Pressure, Cable Pullbys, Cable Jamming, Pulling Around 90 Degree Condulets and Thru Mid-Run Flex Conduit Issues                    E1-32    Open Open:     TVA committed actions are not complete.
 
Closed:   Item has been closed by NRC document.
Capability)
Complete: TVA committed actions are completed.
E1-55  Closed Open:     TVA committed actions are not complete.
C-C:     Issue is Closed and Complete.
Closed:   Item has been closed by NRC document.
E1-ii
Complete: TVA committed actions are completed.
C-C:       Issue is "Closed" and "Complete."
E1-iv TOPIC  PAGE STATUS FOR RESTART Generic Letter 83-28, Salem ATWS, Item 4.5.2, Periodic On-Line Testing E1-56  Closed Generic Letter 83-28, Salem ATWS, Item 4.5.3, Intervals for On-Line Testing E1-57  Closed Generic Letter 87-02, Verification of Seismic Adequacy of Mechanical and Electrical


Equipment In Operating Reactors, Unresolved
STATUS FOR TOPIC                        PAGE  RESTART Cable Installation Issue Number 7, Use of Condulets as Pull Points                        E1-33    Open Cable Installation Issue Number 8, Medium Voltage Vertical Cable Supports                E1-34    Open Cable Splices                                    E1-35 Complete Cable Tray Supports                              E1-36    C-C Component and Piece Part Qualification            E1-38 Complete Conduit Supports                                  E1-39    C-C Configuration Management/Design Baseline          E1-41    C-C Containment Coatings                              E1-42 Complete Control Rod Drive (CRD) Insert and Withdrawal Piping                                          E1-43    C-C Design Calculation Review                        E1-44    C-C Environmental Qualification                      E1-45    Open Fire Protection / 10 CFR 50, Appendix R          E1-46    Open Flexible Conduits                                E1-48 Complete Fuses                                            E1-50 Complete Generic Letter 82-33, Instrumentation to Follow the Course of an Accident - Regulatory Guide 1.97                                            E1-51    C-C Generic Letter 83-08, Modification of Vacuum Breakers on Mark 1 Containments                E1-54    C-C Generic Letter 83-28, Salem ATWS, Item 1.2, Post Trip Review (Data and Information Capability)                                    E1-55  Closed Open:    TVA committed actions are not complete.
Closed:  Item has been closed by NRC document.
Complete: TVA committed actions are completed.
C-C:      Issue is Closed and Complete.
E1-iii


Safety Issue (USI) A-46 E1-58 Complete Generic Letter 88-01, NRC Position on IGSCC in BWR Austenitic Stainless Steel Piping E1-60 C-C Generic Letter 88-11, Radiation Embrittlement of Reactor Vessel Materials and Its Impact on  
STATUS FOR TOPIC                        PAGE  RESTART Generic Letter 83-28, Salem ATWS, Item 4.5.2, Periodic On-Line Testing                        E1-56  Closed Generic Letter 83-28, Salem ATWS, Item 4.5.3, Intervals for On-Line Testing                  E1-57  Closed Generic Letter 87-02, Verification of Seismic Adequacy of Mechanical and Electrical Equipment In Operating Reactors, Unresolved Safety Issue (USI) A-46                         E1-58 Complete Generic Letter 88-01, NRC Position on IGSCC in BWR Austenitic Stainless Steel Piping           E1-60   C-C Generic Letter 88-11, Radiation Embrittlement of Reactor Vessel Materials and Its Impact on Plant Operations                                E1-61    C-C Generic Letter 88-14, Instrument Air Supply System Problems Affecting Safety-Related Equipment                                      E1-63  Closed Generic Letter 88-20, Individual Plant Examination for Severe Accident Vulnerabilities                                E1-64 Complete Generic Letter 88-20, Supplement 4, Individual Plant Examination of External Events (IPEEE) for Severe Accident Vulnerabilities            E1-66 Complete Generic Letter 89-06, Task Action Plan Item I.D.2 - Safety Parameter Display System        E1-68  Closed Generic Letter 89-08, Erosion/Corrosion-Induced Pipe Wall Thinning                              E1-70  Closed Generic Letter 89-10, Safety-Related Motor-Operated Valve Testing and Surveillance  E1-71  Closed Generic Letter 89-13, Service Water System Problems Affecting Safety-Related Equipment    E1-73    C-C Open:    TVA committed actions are not complete.
Closed:  Item has been closed by NRC document.
Complete: TVA committed actions are completed.
C-C:      Issue is Closed and Complete.
E1-iv


Plant Operations E1-61  C-C Generic Letter 88-14, Instrument Air Supply System Problems Affecting Safety-Related  
STATUS FOR TOPIC                        PAGE RESTART Generic Letter 89-16, Installation of a Hardened Wetwell Vent                          E1-74  C-C Generic Letter 92-01, Reactor Vessel Structural Integrity, Revision 1, and Revision 1 Supplement 1                                    E1-75  C-C Generic Letter 92-04, Resolution of the Issues Related to Reactor Vessel Water Level Instrumentation in BWRs                        E1-78  C-C Generic Letter 94-02, Long-Term Solutions and Upgrade of Interim Operating Recommendations for Thermal-Hydraulic Instabilities in Boiling Water Reactors                          E1-79 Closed Generic Letter 94-03, Intergranular Stress Corrosion Cracking of Core Shrouds in Boiling Water Reactors                                  E1-80  C-C Generic Letter 95-07, Pressure Locking and Thermal Binding of Safety-Related and Power-Operated Gate Valves                      E1-81  C-C Generic Letter 96-01, Testing of Safety-Related Logic Circuits                  E1-83 Closed Generic Letter 96-05, Periodic Verification of Design-Basis Capability of Motor-Operated Valves                                          E1-84  C-C Generic Letter 96-06, Assurance of Equipment Operability and Containment Integrity During Design-Basis Accident Conditions                E1-85  C-C Generic Letter 97-04, Assurance of Sufficient Net Positive Suction Head for Emergency Core Cooling and Containment Heat Removal Pumps      E1-87  C-C Generic Letter 98-01, Year 2000 Readiness of Computer Systems at Nuclear Power Plants        E1-89  C-C Open:    TVA committed actions are not complete.
Closed:  Item has been closed by NRC document.
Complete: TVA committed actions are completed.
C-C:      Issue is Closed and Complete.
E1-v


Equipment E1-63 Closed Generic Letter 88-20, Individual Plant Examination for Severe Accident
STATUS FOR TOPIC                        PAGE  RESTART Generic Letter 98-04, Potential for Degradation of the Emergency Core Cooling System and the Containment Spray System After a Loss-of-Coolant Accident Because of Construction and Protective Coating Deficiencies and Foreign Material in Containment                        E1-90      C-C Generic Letter 2003-01, Control Room Habitability                                    E1-92 Complete Generic Safety Issue 75 / Multi-Plant Action B085, Generic Letter 83-28, Item 1.2, Post-Trip Review - Data and Information Capability                                      E1-94  Closed HVAC Duct Supports                                E1-95      C-C Instrument Sensing Lines                          E1-96  Complete Instrument Tubing                                E1-97  Complete Intergranular Stress Corrosion Cracking (IGSCC)  E1-98    C-C Large Bore Piping Supports                        E1-99      C-C License Renewal - Appendix F Commitments          E1-100    Open License Renewal - Non-Appendix F Commitments      E1-103    Open Long Term Torus Integrity Program                E1-104 Complete Lower Drywell Platforms and Miscellaneous Steel  E1-106    C-C Moderate Energy Line Break (MELB)                E1-108    C-C NUREG-0737 (TMI Action Plan), Action Item I.D.1, Control Room Design Review              E1-109  Closed NUREG-0737 (TMI Action Plan), Action Item I.D.2, Safety Parameter Display Console        E1-111  Closed Open:    TVA committed actions are not complete.
Closed:  Item has been closed by NRC document.
Complete: TVA committed actions are completed.
C-C:      Issue is Closed and Complete.
E1-vi


Vulnerabilities E1-64 Complete Generic Letter 88-20, Supplement 4, Individual Plant Examination of External Events (IPEEE)  
STATUS FOR TOPIC                        PAGE  RESTART NUREG-0737 (TMI Action Plan), Action Item II.B.3, Post-Accident Sampling System          E1-112    C-C NUREG-0737 (TMI Action Plan), Action Item II.E.4.2.1-4, Containment Isolation Dependability - Implement Diverse Isolation    E1-114    Open NUREG-0737 (TMI Action Plan), Action Item II.F.1.2.C, Accident - Monitoring -
Containment High Range Radiation                E1-115 Closed NUREG-0737 (TMI Action Plan), Action Item II.F.1.2.D, Accident - Monitoring -
Containment Pressure                            E1-116    C-C NUREG-0737 (TMI Action Plan), Action Item II.F.1.2.E, Accident - Monitoring -
Containment Water Level                        E1-117    C-C NUREG-0737 (TMI Action Plan), Action Item II.F.2.4 (Generic Letter 84-23),
Instrumentation for Detection of Inadequate Core Cooling                                    E1-118    C-C NUREG-0737 (TMI Action Plan), Action Item II.K.3.13, HPCI/RCIC Initiation Levels          E1-120    C-C NUREG-0737 (TMI Action Plan), Action Item II.K.3.18, ADS Actuation Modifications          E1-122  Closed NUREG-0737 (TMI Action Plan), Action Item II.K.3.27, Common Reference Level for Vessel Level Instrumentation                          E1-123    C-C NUREG-0737 (TMI Action Plan), Action Item II.K.3.28, Qualification of ADS Accumulators    E1-124    C-C Platform Thermal Growth                          E1-126    C-C Q-List                                            E1-127 Complete Restart Test Program                              E1-128    Open Open:    TVA committed actions are not complete.
Closed:  Item has been closed by NRC document.
Complete: TVA committed actions are completed.
C-C:      Issue is Closed and Complete.
E1-vii


for Severe Accident Vulnerabilities E1-66  Complete Generic Letter 89-06, Task Action Plan Item I.D.2 - Safety Parameter Display System E1-68  Closed Generic Letter 89-08, Erosion/Corrosion-Induced Pipe Wall Thinning E1-70  Closed Generic Letter 89-10, Safety-Related Motor-Operated Valve Testing and Surveillance E1-71  Closed Generic Letter 89-13, Service Water System Problems Affecting Safety-Related Equipment E1-73  C-C Open:     TVA committed actions are not complete.
STATUS FOR TOPIC                        PAGE  RESTART Seismic Class II Over I / Spatial Systems Interactions and Water Spray                    E1-129 Complete Small Bore Piping                                E1-130 Complete Thermal Overloads                                E1-131    C-C Unresolved Safety Issue A-7, Mark I Long-Term Program                                        E1-133    C-C Unresolved Safety Issue A-9, Anticipated Transients Without Scram                        E1-133    C-C Unresolved Safety Issue A-24, Qualification of Class 1E Safety Related Equipment              E1-135    C-C Unresolved Safety Issue A-26, Reactor Vessel Pressure Transient Protection                  E1-136    C-C Unresolved Safety Issue A-44, Station Blackout    E1-137 Complete Unresolved Safety Issue A-46, Seismic Qualification of Equipment in Operating Plants                                          E1-138 Complete Open:     TVA committed actions are not complete.
Closed:   Item has been closed by NRC document.
Closed:   Item has been closed by NRC document.
Complete: TVA committed actions are completed.
Complete: TVA committed actions are completed.
C-C:       Issue is "Closed" and "Complete."
C-C:     Issue is Closed and Complete.
E1-v TOPIC  PAGE STATUS FOR RESTART Generic Letter 89-16, Installation of a Hardened Wetwell Vent E1-74  C-C Generic Letter 92-01, Reactor Vessel Structural Integrity, Revision 1, and Revision 1
E1-viii


Supplement 1 E1-75  C-C Generic Letter 92-04, Resolution of the Issues Related to Reactor Vessel Water Level
ENCLOSURE 1 TENNESSEE VALLEY AUTHORITY BROWNS FERRY NUCLEAR PLANT (BFN)
STATUS OF UNIT 1 ISSUES BACKGROUND The Browns Ferry Nuclear Plant (BFN) consists of three units.
Units 1 and 3 were voluntarily shut down by the Tennessee Valley Authority (TVA) in March 1985 because of questions about the primary containment isolation leak rate testing for Unit 1 and reactor water level instrumentation for Unit 3. Unit 2 was in a refueling outage at the time. Additional questions and concerns were subsequently raised about the overall adequacy of TVA's nuclear program, and Browns Ferry remained shut down until adequate corrective actions were defined to address the root causes of TVA's nuclear program problems.
On September 17, 1985, NRC requested, pursuant to 10 CFR 50.54(f), that TVA submit information about its plans for correcting Browns Ferrys problems and for correcting problems in the overall management of its nuclear program. NRC also requested that this information be submitted before TVA restarted Browns Ferry. In response to this request, TVA prepared a Corporate Nuclear Performance Plan (CNPP) Volume 1 which identified the root causes of the problems in the management of TVA's nuclear program and described TVA's plans for correcting those problems.
Additionally, TVA prepared a Browns Ferry Nuclear Performance Plan (BFNPP) Volume 3 which identified the root causes of problems specifically related to Browns Ferry, defined plans for correcting those problems, and responded to the NRC's request for Browns Ferry specific information. Taken together, these two plans provided a complete account of the actions which TVA undertook to improve its nuclear program for Browns Ferry.
The regulatory framework for the restart of Unit 2 after its extended outage was unusual. TVA's submittal of the Browns Ferry Nuclear Performance Plan and NRC's review and issuance of Safety Evaluation Reports for each individual program was atypical.
While this level of NRC involvement did result in added confidence for the approval of Unit 2 restart, it required significant TVA and NRC resources for the approval of individual programs and criteria. In most cases, TVA began the implementation of these programs "at risk, which meant prior to NRC approval. Significant redesign and additional modifications were required whenever the criteria was changed during the approval process. NRC evaluation of the BFNPP special programs was documented by the issuance of issue specific Safety April 13, 2007                  E1-1


Instrumentation in BWRs E1-78  C-C Generic Letter 94-02, Long-Term Solutions and Upgrade of Interim Operating Recommendations
Evaluation Reports (SERs) or in NUREG-1232, Volume 3, Safety Evaluation Report on the Browns Ferry Nuclear Performance Plan, and its supplements. Following implementation of these recovery programs, Unit 2 returned to service on May 24, 1991, and was removed from the Problem Plant List in June 1992.
TVAs proposed regulatory framework for the restart of Units 1 and 3 (Reference 1) was more consistent with normal industry practice. The proposed programs were established to provide a high degree of confidence that the facility and personnel were ready to restart and operate Units 1 and 3 in a safe and reliable manner, and promote the efficient utilization of TVA and NRC resources. TVA's plans for the restart of Units 1 and 3 were based on the regulatory requirements, corrective action programs, commitments, Technical Specifications improvements, and internally identified deficiencies and concerns that were resolved prior to the restart of Unit 2. NRC approval of the framework for the restart of Units 1 and 3 was documented in Reference 2. Changes to the implementation of BFNPP special programs on Unit 3 was documented by the issuance of issue specific SERs. The NRC Staffs request that the Commission authorize the Region II Administrator to allow restart of Unit 3 was forwarded by SECY 95-264. Following restart plan completion and NRC restart approval, Unit 3 restarted on November 19, 1995.
Units 1 and 3 were removed from the Watch List in June 1996.
Since restart of Unit 3, there were changes in regulations, TVAs processes, and NRCs processes which warranted revision to the regulatory framework for restart of Unit 1. TVAs successful restart and operation of Units 2 and 3 and the proposed revision to the Unit 1 restart program (References 3 and 4) will establish a high degree of confidence that the facility and personnel are ready to restart and operate Unit 1 in a safe and reliable manner, and promote the efficient utilization of TVA and NRC resources. TVAs plans for the restart of Unit 1 continue to be based on the regulatory requirements, corrective action special programs, commitments, Technical Specifications improvements, and internally identified deficiencies and concerns that were resolved prior to restart of Units 2 and 3. TVA proposed that, at its discretion, it could modify the implementation precedent for BFNPP Special Programs to incorporate efficiencies or experience gained from use of those precedents in restarting Unit 3 or from changes in TVA internal processes.
As documented in the NRCs approval of TVAs proposed regulatory framework (References 5 and 6), the staff requested and TVA agreed to provide formal notification of the completion of each generic communication within 90 days of its internal commitment completion. This letter provides the process that will be used to satisfy this request. Additional items for restart were also identified in the NRCs Browns Ferry Unit 1 Recovery Issues List (Reference 7).
April 13, 2007                  E1-2


for Thermal-Hydraulic Instabilities in
This enclosure lists the individual issues cited in the framework letters and the NRCs Recovery Issues List, describes TVAs commitment or outstanding action for each issue, references key correspondence, discusses the background of the issue, and describes the completion or status of each issue, as appropriate.
A summary of the issues that will be completed after restart for Unit 1 is provided as Enclosure 2.
TVA intends to update this submittal until the Unit 1 commitments related to restart or power operation are completed (TVA committed actions are completed). Changes to the completion status and newly added issues are bolded in the table of contents. Changes to the completion status are also bolded in the text which describes each item. In addition, the bottom of each page will contain a stamp that will show the submittal date.
Other changes are noted by revision bars on the right hand side of the page. These updates will provide the formal notification of the completion of each Unit 1 Bulletin, Generic Letter, Nuclear Performance Plan Special Program, and TMI Action Item required for restart and listed in the regulatory framework letters.
REFERENCES
: 1. TVA letter to NRC, dated July 10, 1991, Regulatory Framework for the Restart of Units 1 and 3
: 2. NRC letter to TVA, dated April 1, 1992, Return to Service of Browns Ferry, Units 1 and 3
: 3. TVA letter to NRC, dated December 13, 2002, Regulatory Framework for the Restart of Unit 1
: 4. TVA letter to NRC, dated February 28, 2003, Regulatory Framework for the Restart of Unit 1
: 5. NRC memorandum from K. N. Jabbour, dated May 13, 2003, Summary of April 24, 2003, Meeting Regarding the Regulatory Framework for Browns Ferry Unit 1 Restart Project (TAC No.
MB7679)
: 6. NRC letter to TVA, dated August 14, 2003, Regulatory Framework for the Restart of Browns Ferry Nuclear Plant, Unit 1
: 7. NRC letter, J. W. Shea to K. W. Singer, dated January 6, 2006, Meeting Summaries: 1.) Category 1 Public Meeting with Tennessee Valley Authority (TVA) RE. Browns Ferry Unit 1 Recovery Status; 2.) Meeting of the NRC Restart Panel for the Browns Ferry Unit 1 Recovery - Docket No. 50-259 April 13, 2007                  E1-3


Boiling Water Reactors E1-79  Closed Generic Letter 94-03, Intergranular Stress Corrosion Cracking of Core Shrouds in Boiling
Bulletin 79-02, Pipe Support Base Plate Designs Using Concrete Expansion Anchor Bolts Commitment:   TVA will complete Bulletin 79-02.
 
Discussion:   TVA initiated programs in 1979 to comply with Bulletins 79-02 and 79-14 regarding the adequacy of piping system supports and anchor bolts. BFNs programs involved the reanalysis of pipe stress problems using the as-built configuration and amplified response spectra for Seismic Class I structures and the evaluation of the acceptability of the associated pipe supports. The scope of the program included Unit 1 safety-related large bore (greater than 22 inches in diameter) piping and computer analyzed small bore piping that was not included in the Small Bore Piping Program.
Water Reactors E1-80  C-C Generic Letter 95-07, Pressure Locking and Thermal Binding of Safety-Related and
Pipe stress analysis and pipe support evaluations are based on walkdown inspection data for the safety-related piping systems. The walkdown inspections were instituted to determine the actual field configuration of the Class I piping systems and supports. NRC approval of TVA's program for the resolution of Bulletins 79-02 and 79-14 is documented in Reference 1.
 
Status:       C-C Piping stress analysis and pipe support calculations were prepared for Class I piping.
Power-Operated Gate Valves E1-81  C-C Generic Letter 96-01, Testing of Safety-Related Logic Circuits E1-83  Closed Generic Letter 96-05, Periodic Verification of Design-Basis Capability of Motor-Operated
Where required, design modifications were implemented.
 
NRC closed this item in Inspection Report 2006-009 (Reference 2).
Valves  E1-84  C-C Generic Letter 96-06, Assurance of Equipment Operability and Containment Integrity During
 
Design-Basis Accident Conditions E1-85  C-C Generic Letter 97-04, Assurance of Sufficient Net Positive Suction Head for Emergency Core
 
Cooling and Containment Heat Removal Pumps E1-87  C-C Generic Letter 98-01, Year 2000 Readiness of Computer Systems at Nuclear Power Plants E1-89  C-C Open:      TVA committed actions are not complete.
Closed:    Item has been closed by NRC document.
Complete:  TVA committed actions are completed.
C-C:      Issue is "Closed" and "Complete."
E1-vi TOPIC  PAGE STATUS FOR RESTART Generic Letter 98-04, Potential for Degradation of the Emergency Core Cooling System and the
 
Containment Spray System After a Loss-of-
 
Coolant Accident Because of Construction and
 
Protective Coating Deficiencies and Foreign
 
Material in Containment E1-90  C-C Generic Letter 2003-01, Control Room Habitability E1-92  Complete Generic Safety Issue 75 / Multi-Plant Action B085, Generic Letter 83-28, Item 1.2, 
 
Post-Trip Review - Data and Information
 
Capability E1-94  Closed HVAC Duct Supports  E1-95  C-C Instrument Sensing Lines  E1-96  Complete Instrument Tubing  E1-97  Complete Intergranular Stress Corrosion Cracking (IGSCC)  E1-98  C-C Large Bore Piping Supports  E1-99  C-C License Renewal - Appendix F Commitments  E1-100  Open License Renewal - Non-Appendix F Commitments  E1-103  Open Long Term Torus Integrity Program  E1-104  Complete Lower Drywell Platforms and Miscellaneous Steel  E1-106  C-C Moderate Energy Line Break (MELB)  E1-108  C-C NUREG-0737 (TMI Action Plan), Action Item I.D.1, Control Room Design Review E1-109  Closed NUREG-0737 (TMI Action Plan), Action Item I.D.2, Safety Parameter Display Console E1-111  Closed Open:      TVA committed actions are not complete.
Closed:    Item has been closed by NRC document.
Complete:  TVA committed actions are completed.
C-C:      Issue is "Closed" and "Complete."
E1-vii TOPIC  PAGE STATUS FOR RESTART NUREG-0737 (TMI Action Plan), Action Item II.B.3, Post-Accident Sampling System E1-112  C-C NUREG-0737 (TMI Action Plan), Action Item II.E.4.2.1-4, Containment Isolation
 
Dependability - Implement Diverse Isolation E1-114  Open NUREG-0737 (TMI Action Plan), Action Item II.F.1.2.C, Accident - Monitoring -
 
Containment High Range Radiation E1-115  Closed NUREG-0737 (TMI Action Plan), Action Item II.F.1.2.D, Accident - Monitoring -
 
Containment Pressure E1-116  C-C NUREG-0737 (TMI Action Plan), Action Item II.F.1.2.E, Accident - Monitoring -
 
Containment Water Level E1-117  C-C NUREG-0737 (TMI Action Plan), Action Item II.F.2.4 (Generic Letter 84-23),
Instrumentation for Detection of Inadequate
 
Core Cooling E1-118  C-C NUREG-0737 (TMI Action Plan), Action Item II.K.3.13, HPCI/RCIC Initiation Levels E1-120  C-C NUREG-0737 (TMI Action Plan), Action Item II.K.3.18, ADS Actuation Modifications E1-122  Closed NUREG-0737 (TMI Action Plan), Action Item II.K.3.27, Common Reference Level for Vessel
 
Level Instrumentation E1-123  C-C NUREG-0737 (TMI Action Plan), Action Item II.K.3.28, Qualification of ADS Accumulators E1-124  C-C Platform Thermal Growth E1-126  C-C Q-List  E1-127  Complete Restart Test Program  E1-128  Open Open:      TVA committed actions are not complete.
Closed:    Item has been closed by NRC document.
Complete:  TVA committed actions are completed.
C-C:      Issue is "Closed" and "Complete."
E1-viii TOPIC  PAGE STATUS FOR RESTART Seismic Class II Over I / Spatial Systems Interactions and Water Spray E1-129  Complete Small Bore Piping  E1-130  Complete Thermal Overloads  E1-131  C-C Unresolved Safety Issue A-7, Mark I Long-Term Program  E1-133  C-C Unresolved Safety Issue A-9, Anticipated Transients Without Scram E1-133  C-C Unresolved Safety Issue A-24, Qualification of Class 1E Safety Related Equipment E1-135  C-C Unresolved Safety Issue A-26, Reactor Vessel Pressure Transient Protection E1-136  C-C Unresolved Safety Issue A-44, Station Blackout E1-137  Complete Unresolved Safety Issue A-46, Seismic Qualification of Equipment in Operating
 
Plants  E1-138  Complete April 13, 2007 E1-1 ENCLOSURE 1 TENNESSEE VALLEY AUTHORITY BROWNS FERRY NUCLEAR PLANT (BFN)
STATUS OF UNIT 1 ISSUES BACKGROUND T he Browns Ferry Nuclear Plant (BFN) consists of three units.
Units 1 and 3 were voluntarily shut down by the Tennessee Valley
 
Authority (TVA) in March 1985 because of questions about the
 
primary containment isolation leak rate testing for Unit 1 and
 
reactor water level instrumentation for Unit 3. Unit 2 was in a
 
refueling outage at the time. Additional questions and concerns
 
were subsequently raised about the overall adequacy of TVA's
 
nuclear program, and Browns Ferry remained shut down until
 
adequate corrective actions were defined to address the root
 
causes of TVA's nuclear program problems.
 
On September 17, 1985, NRC requested, pursuant to 10 CFR
 
50.54(f), that TVA submit information about its plans for
 
correcting Browns Ferry's problems and for correcting problems in
 
the overall management of its nuclear program. NRC also
 
requested that this information be submitted before TVA restarted
 
Browns Ferry. In response to this request, TVA prepared a
 
Corporate Nuclear Performance Plan (CNPP) Volume 1 which
 
identified the root causes of the problems in the management of
 
TVA's nuclear program and described TVA's plans for correcting
 
those problems.
 
Additionally, TVA prepared a Browns Ferry Nuclear Performance
 
Plan (BFNPP) Volume 3 which identified the root causes of
 
problems specifically related to Browns Ferry, defined plans for
 
correcting those problems, and responded to the NRC's request for
 
Browns Ferry specific information. Taken together, these
 
two plans provided a complete account of the actions which TVA
 
undertook to improve its nuclear program for Browns Ferry.
 
The regulatory framework for the restart of Unit 2 after its
 
extended outage was unusual. TVA's submittal of the Browns Ferry
 
Nuclear Performance Plan and NRC's review and issuance of Safety
 
Evaluation Reports for each individual program was atypical. 
 
While this level of NRC involvement did result in added
 
confidence for the approval of Unit 2 restart, it required
 
significant TVA and NRC resources for the approval of individual
 
programs and criteria. In most cases, TVA began the
 
implementation of these programs "at risk," which meant prior to
 
NRC approval. Significant redesign and additional modifications
 
were required whenever the criteria was changed during the
 
approval process. NRC evaluation of the BFNPP special programs
 
was documented by the issuance of issue specific Safety April 13, 2007 E1-2 Evaluation Reports (SERs) or in NUREG-1232, Volume 3, Safety Evaluation Report on the Browns Ferry Nuclear Performance Plan, and its supplements. Following implementation of these recovery
 
programs, Unit 2 returned to service on May 24, 1991, and was
 
removed from the Problem Plant List in June 1992.
 
TVA's proposed regulatory framework for the restart of Units 
 
1 and 3 (Reference 1) was more consistent with normal industry
 
practice. The proposed programs were established to provide a
 
high degree of confidence that the facility and personnel were
 
ready to restart and operate Units 1 and 3 in a safe and reliable
 
manner, and promote the efficient utilization of TVA and NRC
 
resources. TVA's plans for the restart of Units 1 and 3 were
 
based on the regulatory requirements, corrective action programs, commitments, Technical Specifications improvements, and
 
internally identified deficiencies and concerns that were
 
resolved prior to the restart of Unit 2. NRC approval of the
 
framework for the restart of Units 1 and 3 was documented in
 
Reference 2. Changes to the implementation of BFNPP special
 
programs on Unit 3 was documented by the issuance of issue
 
specific SERs. The NRC Staff's request that the Commission
 
authorize the Region II Administrator to allow restart of Unit 3
 
was forwarded by SECY 95-264. Following restart plan completion
 
and NRC restart approval, Unit 3 restarted on November 19, 1995.
 
Units 1 and 3 were removed from the Watch List in June 1996.
 
Since restart of Unit 3, there were changes in regulations, TVA's
 
processes, and NRC's processes which warranted revision to the
 
regulatory framework for restart of Unit 1. TVA's successful
 
restart and operation of Units 2 and 3 and the proposed revision
 
to the Unit 1 restart program (References 3 and 4) will establish
 
a high degree of confidence that the facility and personnel are
 
ready to restart and operate Unit 1 in a safe and reliable
 
manner, and promote the efficient utilization of TVA and NRC
 
resources. TVA's plans for the restart of Unit 1 continue to be
 
based on the regulatory requirements, corrective action special
 
programs, commitments, Technical Specifications improvements, and
 
internally identified deficiencies and concerns that were
 
resolved prior to restart of Units 2 and 3. TVA proposed that, at its discretion, it could modify the implementation precedent
 
for BFNPP Special Programs to incorporate efficiencies or
 
experience gained from use of those precedents in restarting
 
Unit 3 or from changes in TVA internal processes.
 
As documented in the NRC's approval of TVA's proposed regulatory
 
framework (References 5 and 6), the staff requested and TVA
 
agreed to provide formal notification of the completion of each
 
generic communication within 90 days of its internal commitment
 
completion. This letter provides the process that will be used
 
to satisfy this request. Additional items for restart were also
 
identified in the NRC's Browns Ferry Unit 1 Recovery Issues List (Reference 7).
April 13, 2007 E1-3 This enclosure lists the individual issues cited in the framework letters and the NRC's Recovery Issues List, describes TVA's
 
commitment or outstanding action for each issue, references key
 
correspondence, discusses the background of the issue, and
 
describes the completion or status of each issue, as appropriate.
 
A summary of the issues that will be completed after restart for
 
Unit 1 is provided as Enclosure 2.
 
TVA intends to update this submittal until the Unit 1 commitments
 
related to restart or power operation are completed (TVA
 
committed actions are completed). Changes to the completion
 
status and newly added issues are bolded in the table of
 
contents. Changes to the completion status are also bolded in
 
the text which describes each item. In addition, the bottom of
 
each page will contain a stamp that will show the submittal date.
 
Other changes are noted by revision bars on the right hand side
 
of the page. These updates will provide the formal notification
 
of the completion of each Unit 1 Bulletin, Generic Letter, Nuclear Performance Plan Special Program, and TMI Action Item
 
required for restart and listed in the regulatory framework
 
letters. REFERENCES
: 1. TVA letter to NRC, dated July 10, 1991, Regulatory Framework for the Restart of Units 1 and 3 2. NRC letter to TVA, dated April 1, 1992, Return to Service of Browns Ferry, Units 1 and 3 3. TVA letter to NRC, dated December 13, 2002, Regulatory Framework for the Restart of Unit 1 4. TVA letter to NRC, dated February 28, 2003, Regulatory Framework for the Restart of Unit 1 5. NRC memorandum from K. N. Jabbour, dated May 13, 2003, Summary of April 24, 2003, Meeting Regarding the Regulatory
 
Framework for Browns Ferry Unit 1 Restart Project (TAC No.
 
MB7679) 6. NRC letter to TVA, dated August 14, 2003, Regulatory Framework for the Restart of Browns Ferry Nuclear Plant, Unit
 
1 7. NRC letter, J. W. Shea to K. W. Singer, dated January 6, 2006, Meeting Summaries: 1.) Category 1 Public Meeting with Tennessee Valley Authority (TVA) RE. Browns
 
Ferry Unit 1 Recovery Status; 2.) Meeting of the NRC Restart
 
Panel for the Browns Ferry Unit 1 Recovery - Docket No. 50-
 
259 April 13, 2007 E1-4 Bulletin 79-02, Pipe Support Base Plate Designs Using Concrete Expansion Anchor Bolts  
 
Commitment: TVA will complete Bulletin 79-02.  
 
Discussion: TVA initiated programs in 1979 to comply with Bulletins 79-02 and 79-14 regarding the adequacy of  
 
piping system supports and anchor bolts. BFN's
 
programs involved the reanalysis of pipe stress  
 
problems using the as-built configuration and  
 
amplified response spectra for Seismic Class I  
 
structures and the evaluation of the acceptability  
 
of the associated pipe supports. The scope of the  
 
program included Unit 1 safety-related large bore (greater than 2 2 inches in diameter) piping and computer analyzed small bore piping that was not  
 
included in the Small Bore Piping Program.  
 
Pipe stress analysis and pipe support evaluations  
 
are based on walkdown inspection data for the  
 
safety-related piping systems. The walkdown  
 
inspections were instituted to determine the actual  
 
field configuration of the Class I piping systems  
 
and supports. NRC approval of TVA's program for  
 
the resolution of Bulletins 79-02 and 79-14 is  
 
documented in Reference 1.  
 
Status: C-C  
 
Piping stress analysis and pipe support  
 
calculations were prepared for Class I piping.
 
Where required, design modifications were  
 
implemented.  
 
NRC closed this item in Inspection Report 2006-009 (Reference 2).  


==References:==
==References:==
1.
: 1. NRC letter to TVA, dated January 23, 1991, NUREG-1232, Volume 3, Supplement 2 -
NRC letter to TVA, dated January 23, 1991, NUREG-1232, Volume 3, Supplement 2 -
 
Browns Ferry, Unit 2, Section 2.2.3.1 (Page 2-8)
Browns Ferry, Unit 2, Section 2.2.3.1 (Page 2-8)
: 2. NRC letter to TVA, dated March 5, 2007, Browns Ferry Nuclear Plant Unit 1 Recovery - NRC  
: 2. NRC letter to TVA, dated March 5, 2007, Browns Ferry Nuclear Plant Unit 1 Recovery - NRC Integrated Inspection Report 05000259/2006009 April 13, 2007                   E1-4
 
Integrated Inspection Report 05000259/2006009  
 
April 13, 2007 E1-5 Bulletin 79-12, Short Period Scrams at BWR Facilities
 
Commitment: TVA will complete Bulletin 79-12.


Discussion: In response to Bulletin 79-12, TVA committed to perform unit and cycle specific analyses of control  
Bulletin 79-12, Short Period Scrams at BWR Facilities Commitment:    TVA will complete Bulletin 79-12.
 
Discussion:   In response to Bulletin 79-12, TVA committed to perform unit and cycle specific analyses of control rod withdrawal sequences in order to ensure that rod notch worths were acceptable (References 1 and 2). In Reference 3, TVA notified NRC that it was implementing the generic Banked Position Withdrawal Sequence and Reduced Notch Worth Procedure. The resulting withdrawal sequences ensure that the notch worths are sufficiently small so as to minimize the possibility of a fast period scram. Therefore, cycle specific analyses of control rod withdrawal sequences were no longer required.
rod withdrawal sequences in order to ensure that  
Status:       C-C The Banked Position Withdrawal Sequence and Reduced Notch Worth Procedures have been incorporated into plant procedures.
 
NRC closed this item in Inspection Report 2006-007 (Reference 4).
rod notch worths were acceptable (References 1  
 
and 2). In Reference 3, TVA notified NRC that it  
 
was implementing the generic Banked Position  
 
Withdrawal Sequence and Reduced Notch Worth  
 
Procedure. The resulting withdrawal sequences  
 
ensure that the notch worths are sufficiently small  
 
so as to minimize the possibility of a fast period  
 
scram. Therefore, cycle specific analyses of  
 
control rod withdrawal sequences were no longer  
 
required.  
 
Status: C-C  
 
The Banked Position Withdrawal Sequence and Reduced  
 
Notch Worth Procedures have been incorporated into  
 
plant procedures.  
 
NRC closed this item in Inspection Report 2006-007 (Reference 4).  


==References:==
==References:==
1.
: 1. TVA letter to NRC, dated July 30, 1979, Office of Inspection and Enforcement Bulletin 79                   RII:JPO 50-259, -260, -296 - Browns Ferry Nuclear Plant Units 1, 2, and 3
TVA letter to NRC, dated July 30, 1979, Office of Inspection and Enforcement Bulletin 79  
: 2. TVA letter to NRC, dated August 19, 1981, Office of Inspection and Enforcement Bulletin 79                   RII:JPO 50-259, -260, -296 - Browns Ferry Nuclear Plant
 
: 3. TVA letter to NRC, dated January 4, 1990, Office of Inspection and Enforcement Bulletin 79                   Commitment Revisions Regarding Fast Period Scrams
RII:JPO 50-259, -260, -296 - Browns Ferry  
: 4. NRC letter to TVA, dated August 10, 2006, Browns Ferry Nuclear Plant Unit 1 Recovery - NRC Integrated Inspection Report 05000259/2006007 April 13, 2007                   E1-5
 
Nuclear Plant Units 1, 2, and 3
: 2. TVA letter to NRC, dated August 19, 1981, Office of Inspection and Enforcement Bulletin 79  
 
RII:JPO 50-259, -260, -296 - Browns Ferry  
 
Nuclear Plant
: 3. TVA letter to NRC, dated January 4, 1990, Office of Inspection and Enforcement Bulletin 79  
 
Commitment Revisions Regarding Fast Period  
 
Scrams 4. NRC letter to TVA, dated August 10, 2006, Browns Ferry Nuclear Plant Unit 1 Recovery - NRC  
 
Integrated Inspection Report 05000259/2006007  
 
April 13, 2007 E1-6 Bulletin 79-14, Seismic Analysis for As-Built Safety-Related Piping Systems
 
Commitment: TVA will complete Bulletin 79-14.
 
Discussion: TVA initiated programs in 1979 to comply with Bulletins 79-02 and 79-14 regarding the adequacy of
 
piping system supports and anchor bolts. BFN's
 
programs involved the reanalysis of pipe stress


problems using the as-built configuration and  
Bulletin 79-14, Seismic Analysis for As-Built Safety-Related Piping Systems Commitment:    TVA will complete Bulletin 79-14.
 
Discussion:    TVA initiated programs in 1979 to comply with Bulletins 79-02 and 79-14 regarding the adequacy of piping system supports and anchor bolts. BFNs programs involved the reanalysis of pipe stress problems using the as-built configuration and amplified response spectra for Seismic Class I structures and the evaluation of the acceptability of the associated pipe supports. The scope of the program included Unit 1 safety-related large bore (greater than 22 inches in diameter) piping and computer analyzed small bore piping that was not included in the Small Bore Piping Program.
amplified response spectra for Seismic Class I  
Pipe stress analysis and pipe support evaluations were based on walkdown inspection data for the safety-related piping systems. The walkdown inspections were instituted to determine the actual field configuration of the Class I piping systems and supports. NRC approval of TVA's program for the resolution of Bulletins 79-02 and 79-14 is documented in Reference 1.
 
Status:       C-C Piping stress analysis and pipe support calculations were prepared for Class I piping.
structures and the evaluation of the acceptability  
Where required, design modifications were implemented.
 
NRC closed this item in Inspection Report 2006-009 (Reference 2).
of the associated pipe supports. The scope of the  
 
program included Unit 1 safety-related large bore (greater than 2 2 inches in diameter) piping and computer analyzed small bore piping that was not  
 
included in the Small Bore Piping Program.  
 
Pipe stress analysis and pipe support evaluations  
 
were based on walkdown inspection data for the  
 
safety-related piping systems. The walkdown  
 
inspections were instituted to determine the actual  
 
field configuration of the Class I piping systems  
 
and supports. NRC approval of TVA's program for  
 
the resolution of Bulletins 79-02 and 79-14 is  
 
documented in Reference 1.  
 
Status: C-C  
 
Piping stress analysis and pipe support  
 
calculations were prepared for Class I piping.
 
Where required, design modifications were  
 
implemented.  
 
NRC closed this item in Inspection Report 2006-009 (Reference 2).  


==References:==
==References:==
1.
: 1. NRC letter to TVA, dated January 23, 1991, NUREG-1232, Volume 3, Supplement 2 -
NRC letter to TVA, dated January 23, 1991, NUREG-1232, Volume 3, Supplement 2 -
 
Browns Ferry, Unit 2, Section 2.2.3.1 (Page 2-8)
Browns Ferry, Unit 2, Section 2.2.3.1 (Page 2-8)
: 2. NRC letter to TVA, dated March 5, 2007, Browns Ferry Nuclear Plant Unit 1 Recovery - NRC  
: 2. NRC letter to TVA, dated March 5, 2007, Browns Ferry Nuclear Plant Unit 1 Recovery - NRC Integrated Inspection Report 05000259/2006009 April 13, 2007                   E1-6
 
Integrated Inspection Report 05000259/2006009  
 
April 13, 2007 E1-7 Bulletin 80-06, Engineered Safety Feature (ESF) Reset Controls
 
Commitment: TVA will complete Bulletin 80-06.
 
Discussion: In Reference 1, TVA stated that the need for modification to the Traversing Incore Probe (TIP)
 
system was identified as a result of the reviews
 
performed for Bulletin 80-06. In Reference 2, TVA
 
committed to perform the modification to the TIP
 
system prior to restart.


Status: C-C  
Bulletin 80-06, Engineered Safety Feature (ESF) Reset Controls Commitment:    TVA will complete Bulletin 80-06.
 
Discussion:    In Reference 1, TVA stated that the need for modification to the Traversing Incore Probe (TIP) system was identified as a result of the reviews performed for Bulletin 80-06. In Reference 2, TVA committed to perform the modification to the TIP system prior to restart.
TVA modified TIP circuitry for ESF reset.  
Status:       C-C TVA modified TIP circuitry for ESF reset.
 
NRC closed this item in Inspection Report 2006-008 (Reference 3).
NRC closed this item in Inspection Report 2006-008 (Reference 3).  


==References:==
==References:==
1.
: 1. TVA letter to NRC, dated December 4, 1981, in Regards to Bulletin 80-06
TVA letter to NRC, dated December 4, 1981, in Regards to Bulletin 80-06
: 2. TVA letter to NRC, dated April 28, 1988, IE Bulletin No. 80 Engineered Safety Feature (ESF) Reset Control
: 2. TVA letter to NRC, dated April 28, 1988, IE Bulletin No. 80 Engineered Safety  
: 3. NRC letter to TVA, dated November 9, 2006, Browns Ferry Nuclear Plant Unit 1 Recovery - NRC Integrated Inspection Report 05000259/2006008 April 13, 2007                   E1-7
 
Feature (ESF) Reset Control
: 3. NRC letter to TVA, dated November 9, 2006, Browns Ferry Nuclear Plant Unit 1 Recovery - NRC  
 
Integrated Inspection Report 05000259/2006008  
 
April 13, 2007 E1-8 Bulletin 84-02, Failures of General Electric Type HFA Relays in Use in Class 1E Safety Systems


Commitment: TVA will replace relay coil spools in HFA relays in the reactor protection system (RPS) and other  
Bulletin 84-02, Failures of General Electric Type HFA Relays in Use in Class 1E Safety Systems Commitment:   TVA will replace relay coil spools in HFA relays in the reactor protection system (RPS) and other safety systems.
 
Discussion:   TVA responded to Bulletin 84-02 by Reference 1.
safety systems.  
Status:       Closed NRC closed this item in Inspection Report 2004-009 (Reference 2).
 
Discussion: TVA responded to Bulletin 84-02 by Reference 1.  
 
Status: Closed  
 
NRC closed this item in Inspection Report 2004-009 (Reference 2).  


==References:==
==References:==
1.
: 1. TVA letter to NRC, dated July 10, 1984, Inspection and Enforcement Bulletin 84                   Failures of General Electric Type HFA Relays in Use in Class 1E Safety Systems - Browns Ferry, Sequoyah, Watts Bar, and Bellefonte Nuclear Plants
TVA letter to NRC, dated July 10, 1984, Inspection and Enforcement Bulletin 84  
: 2. NRC letter to TVA, dated February 11, 2005, Browns Ferry Nuclear Plant Unit 1 Recovery - NRC Integrated Inspection Report 05000259/2004009 April 13, 2007                  E1-8


Failures of General Electric Type HFA Relays in
Bulletin 86-02, Static "O" Ring Differential Pressure Switches Commitment:   TVA will complete Bulletin 86-02.
 
Discussion:   TVA responded to Bulletin 86-02 by Reference 1.
Use in Class 1E Safety Systems - Browns Ferry, Sequoyah, Watts Bar, and Bellefonte Nuclear
Two Static "O" Ring (SOR) differential pressure switches were installed (or planned for installation) in the Residual Heat Removal (RHR) system minimum flow recirculation lines. TVA committed to:
 
Plants 2. NRC letter to TVA, dated February 11, 2005, Browns Ferry Nuclear Plant Unit 1 Recovery - NRC
 
Integrated Inspection Report 05000259/2004009
 
April 13, 2007 E1-9 Bulletin 86-02, Static "O" Ring Differential Pressure Switches  
 
Commitment: TVA will complete Bulletin 86-02.  
 
Discussion: TVA responded to Bulletin 86-02 by Reference 1.
Two Static "O" Ring (SOR) differential pressure  
 
switches were installed (or planned for  
 
installation) in the Residual Heat Removal (RHR)  
 
system minimum flow recirculation lines. TVA  
 
committed to:
: 1. Revise the RHR pump flow rate test to include steps to verify minimum flow switch operability;
: 1. Revise the RHR pump flow rate test to include steps to verify minimum flow switch operability;
: 2. Perform maintenance instructions semiannually until two consecutive tests were attained; and
: 2. Perform maintenance instructions semiannually until two consecutive tests were attained; and
: 3. Evaluate the SOR test report and adjust setpoints, as required.  
: 3. Evaluate the SOR test report and adjust setpoints, as required.
 
Status:       C-C TVA installed two Static "O" Ring differential pressure switches in the Unit 1 RHR system and the RHR Pump Surveillance Instructions were revised to include steps to verify proper switch operation.
Status: C-C  
TVA installed two Static "O" Ring differential pressure switches in the Unit 1 Core Spray system and the Core Spray Pump Surveillance Instructions were revised to include steps to verify proper switch operation.
 
The commitment to perform the maintenance instruction semiannually has been evaluated in accordance with the commitment management process and deleted. NRC was notified of the commitment deletion by Reference 2.
TVA installed two Static "O" Ring differential  
The SOR test report has been evaluated; the accuracy values used for these switches are bounded by the data used in the SOR test report.
 
NRC closed this item in Inspection Report 2005-06 (Reference 3).
pressure switches in the Unit 1 RHR system and the  
 
RHR Pump Surveillance Instructions were revised to  
 
include steps to verify proper switch operation.  
 
TVA installed two Static "O" Ring differential  
 
pressure switches in the Unit 1 Core Spray system  
 
and the Core Spray Pump Surveillance Instructions  
 
were revised to include steps to verify proper  
 
switch operation.  
 
The commitment to perform the maintenance  
 
instruction semiannually has been evaluated in  
 
accordance with the commitment management process  
 
and deleted. NRC was notified of the commitment  
 
deletion by Reference 2.  
 
The SOR test report has been evaluated; the  
 
accuracy values used for these switches are bounded  
 
by the data used in the SOR test report.  
 
NRC closed this item in Inspection Report 2005-06 (Reference 3).  


==References:==
==References:==
1.
: 1. TVA letter to NRC, dated July 20, 1987, NRC Office of Inspection and Enforcement (IE)
TVA letter to NRC, dated July 20, 1987, NRC Office of Inspection and Enforcement (IE)  
Bulletin 86 Static "O" Ring (SOR)
Differential Pressure Switches April 13, 2007                    E1-9
: 2. TVA letter to NRC, dated August 17, 1995, BFN Revision to Commitments to Perform Testing of Static-O-Ring Differential Pressure Switches and Voltage Verification Testing of Reactor Protective System Equipment
: 3. NRC letter to TVA, dated May 16, 2005, Browns Ferry Nuclear Plant Unit 1 Recovery - NRC Integrated Inspection Report 05000259/2005006 April 13, 2007                  E1-10


Bulletin 86 Static "O" Ring (SOR)
Bulletin 88-03, Inadequate Latch Engagement in HFA Type Relays Manufactured by General Electric (GE) Company Commitment:   TVA will complete Bulletin 88-03.
 
Discussion:   TVA originally responded to Bulletin 88-03 in Reference 1. TVA stated the BFN inspections and the repair or replacement of the relays which fail the inspection criteria are scheduled to be completed before restart of each unit. In Reference 2, NRC closed Bulletin 88-03. However, TVA was still required to notify the NRC of inspection results for Unit 1.
Differential Pressure Switches April 13, 2007 E1-10
Status:       Closed NRC closed this item in Inspection Report 2004-009 (Reference 3).
: 2. TVA letter to NRC, dated August 17, 1995, BFN Revision to Commitments to Perform Testing of
 
Static-O-Ring Differential Pressure Switches and
 
Voltage Verification Testing of Reactor
 
Protective System Equipment
: 3. NRC letter to TVA, dated May 16, 2005, Browns Ferry Nuclear Plant Unit 1 Recovery - NRC
 
Integrated Inspection Report 05000259/2005006
 
April 13, 2007 E1-11 Bulletin 88-03, Inadequate Latch Engagement in HFA Type Relays Manufactured by General Electric (GE) Company  
 
Commitment: TVA will complete Bulletin 88-03.  
 
Discussion: TVA originally responded to Bulletin 88-03 in Reference 1. TVA stated the BFN inspections and  
 
the repair or replacement of the relays which fail  
 
the inspection criteria are scheduled to be  
 
completed before restart of each unit. In  
 
Reference 2, NRC closed Bulletin 88-03. However, TVA was still required to notify the NRC of  
 
inspection results for Unit 1.  
 
Status: Closed  
 
NRC closed this item in Inspection Report 2004-009 (Reference 3).  


==References:==
==References:==
1.
: 1. TVA letter to NRC, dated July 6, 1988, Nuclear Regulatory Commission (NRC) Bulletin 88-03, Inadequate Latch Engagement in HFA-Type Latching Relays Manufactured by General Electric (GE)
TVA letter to NRC, dated July 6, 1988, Nuclear Regulatory Commission (NRC) Bulletin 88-03, Inadequate Latch Engagement in HFA-Type Latching  
Company
 
: 2. NRC letter to TVA, dated August 2, 1990, Closure of NRC Bulletin 88-03 for the Browns Ferry Nuclear Plant (TAC Nos. 73852, 73853, and 73854)
Relays Manufactured by General Electric (GE)  
: 3. NRC letter to TVA, dated February 11, 2005, Browns Ferry Nuclear Plant Unit 1 Recovery - NRC Integrated Inspection Report 05000259/2004009 April 13, 2007                   E1-11
 
Company 2. NRC letter to TVA, dated August 2, 1990, Closure of NRC Bulletin 88-03 for the Browns Ferry  
 
Nuclear Plant (TAC Nos. 73852, 73853, and 73854)
: 3. NRC letter to TVA, dated February 11, 2005, Browns Ferry Nuclear Plant Unit 1 Recovery - NRC  
 
Integrated Inspection Report 05000259/2004009 April 13, 2007 E1-12 Bulletin 88-04, Potential Safety-Related Pump Loss
 
Commitment: TVA will complete Bulletin 88-04.
 
Discussion: NRC Bulletin 88-04 requested licensees to investigate and correct, as applicable, two
 
miniflow design concerns for safety-related system
 
pumps. The first concern involved the potential
 
for dead-heading one or more pumps. The second
 
concern was whether or not the installed miniflow
 
capacity was adequate.


Bulletin 88-04, Potential Safety-Related Pump Loss Commitment:    TVA will complete Bulletin 88-04.
Discussion:    NRC Bulletin 88-04 requested licensees to investigate and correct, as applicable, two miniflow design concerns for safety-related system pumps. The first concern involved the potential for dead-heading one or more pumps. The second concern was whether or not the installed miniflow capacity was adequate.
TVA responded to the Bulletin (Reference 1),
TVA responded to the Bulletin (Reference 1),
endorsing the BWR Owners Group response and  
endorsing the BWR Owners Group response and providing BFN specific information. NRC requested additional information in Reference 2, which was provided by TVA in Reference 3. Reference 4 documents NRR closure of this issue for Unit 1.
 
NRC addressed this issue for Unit 1 in Inspection Report 95-31 (Reference 5). TVA notified NRC that its actions were complete in Reference 6.
providing BFN specific information. NRC requested  
Status:       C-C NRC closed this item in Inspection Report 2004-009 (Reference 7).
 
additional information in Reference 2, which was  
 
provided by TVA in Reference 3. Reference 4  
 
documents NRR closure of this issue for Unit 1.
 
NRC addressed this issue for Unit 1 in Inspection  
 
Report 95-31 (Reference 5). TVA notified NRC that  
 
its actions were complete in Reference 6.  
 
Status: C-C  
 
NRC closed this item in Inspection Report 2004-009 (Reference 7).  


==References:==
==References:==
1.
: 1. Letter from TVA to NRC dated September 30, 1988, Browns Ferry (BFN), Watts Bar (WBN), and Bellefonte (BLN) Nuclear Plants - NRC Bulletin (NRCB) 88-04, Potential Safety-Related Pump Loss
Letter from TVA to NRC dated September 30, 1988, Browns Ferry (BFN), Watts Bar (WBN), and  
: 2. Letter from NRC to TVA dated March 1, 1989, Response to NRC Bulletin 88 Browns Ferry Nuclear Plant, Units 1, 2, and 3
 
: 3. Letter from TVA to NRC dated April 05, 1989, Browns Ferry Nuclear Plant (BFN) Units 1 and 3 -
Bellefonte (BLN) Nuclear Plants - NRC Bulletin (NRCB) 88-04, Potential Safety-Related Pump Loss
Additional Response to NRC Bulletin 88-04 (NRCB 88-04) - Potential Safety-Related Pump Loss
: 2. Letter from NRC to TVA dated March 1, 1989, Response to NRC Bulletin 88 Browns Ferry  
: 4. Letter from NRC to TVA, dated May 8, 1989, Response to NRC Bulletin 88 Browns Ferry Nuclear Plant, Units 1 and 3
 
: 5. NRC letter to TVA, dated June 28, 1995, NRC Inspection Report 95-31 [Section 7.b., page 18]
Nuclear Plant, Units 1, 2, and 3
April 13, 2007                   E1-12
: 3. Letter from TVA to NRC dated April 05, 1989, Browns Ferry Nuclear Plant (BFN) Units 1 and 3 -  
: 6. TVA letter to NRC, dated May 7, 2004, Browns Ferry Nuclear Plant (BFN) Unit 1 - Completion of NRC Bulletin 88-04, Potential Safety-Related Pump Loss
 
: 7. NRC letter to TVA, dated February 11, 2005, Browns Ferry Nuclear Plant Unit 1 Recovery - NRC Integrated Inspection Report 05000259/2004009 April 13, 2007                   E1-13
Additional Response to NRC Bulletin 88-04 (NRCB 88-04) - Potential Safety-Related Pump  
 
Loss 4. Letter from NRC to TVA, dated May 8, 1989, Response to NRC Bulletin 88 Browns Ferry  
 
Nuclear Plant, Units 1 and 3
: 5. NRC letter to TVA, dated June 28, 1995, NRC Inspection Report 95-31 [Section 7.b., page 18]  
 
April 13, 2007 E1-13
: 6. TVA letter to NRC, dated May 7, 2004, Browns Ferry Nuclear Plant (BFN) Unit 1 - Completion of  
 
NRC Bulletin 88-04, Potential Safety-Related  
 
Pump Loss
: 7. NRC letter to TVA, dated February 11, 2005, Browns Ferry Nuclear Plant Unit 1 Recovery - NRC  
 
Integrated Inspection Report 05000259/2004009 April 13, 2007 E1-14 Bulletin 88-07, Power Oscillations in Boiling Water Reactors, and Supplement 1
 
Commitment: TVA will complete Bulletin 88-07.
 
Discussion: TVA responded to Bulletin 88-07 by Reference 1 and confirmed that the actions required by the Bulletin
 
were implemented. TVA responded to Supplement 1 to
 
Bulletin 88-07 by Reference 2 and confirmed its
 
plans to implement the General Electric interim
 
stability recommendations. The proposed Technical


Specification changes to implement the reactor core  
Bulletin 88-07, Power Oscillations in Boiling Water Reactors, and Supplement 1 Commitment:    TVA will complete Bulletin 88-07.
 
Discussion:    TVA responded to Bulletin 88-07 by Reference 1 and confirmed that the actions required by the Bulletin were implemented. TVA responded to Supplement 1 to Bulletin 88-07 by Reference 2 and confirmed its plans to implement the General Electric interim stability recommendations. The proposed Technical Specification changes to implement the reactor core thermal-hydraulic stability recommendations contained in Supplement 1 to Bulletin 88-07 were provided by Reference 3 and approved in Reference 4.
thermal-hydraulic stability recommendations  
Status:       C-C Refer to the topic entitled Generic Letter 94               Long-Term Solutions and Upgrade of Interim Operating Recommendations for Thermal-Hydraulic Instabilities in Boiling Water Reactors for additional actions TVA has taken to address this issue.
 
NRC closed this item in Inspection Report 2006-007 (Reference 5).
contained in Supplement 1 to Bulletin 88-07 were  
 
provided by Reference 3 and approved in  
 
Reference 4.  
 
Status: C-C  
 
Refer to the topic entitled Generic Letter 94  
 
Long-Term Solutions and Upgrade of Interim  
 
Operating Recommendations for Thermal-Hydraulic  
 
Instabilities in Boiling Water Reactors for  
 
additional actions TVA has taken to address this  
 
issue.  
 
NRC closed this item in Inspection Report 2006-007 (Reference 5).  


==References:==
==References:==
1.
: 1. TVA letter to NRC, dated November 4, 1988, NRC Bulletin 88-07: Power Oscillations in Boiling Water Reactors
TVA letter to NRC, dated November 4, 1988, NRC Bulletin 88-07: Power Oscillations in Boiling  
: 2. TVA letter to NRC, dated March 6, 1989, NRC Bulletin 88-07, Supplement 1 - Power Oscillations in Boiling Water Reactors (BWRs)
: 3. TVA letter to NRC, dated January 14, 1992, TVA BFN Technical Specification (TS) No. 300 Reactor Core Thermal-Hydraulic Stability
: 4. NRC letter to TVA, dated May 31, 1994, Issuance of Technical Specification Amendments for the Browns Ferry Nuclear Plant Units 1 and 3 (TS 300)
: 5. NRC letter to TVA, dated August 10, 2006, Browns Ferry Nuclear Plant Unit 1 Recovery - NRC Integrated Inspection Report 05000259/2006007 April 13, 2007                    E1-14


Water Reactors
Bulletin 88-10, Nonconforming Molded-Case Circuit Breakers Commitment:   TVA will complete Bulletin 88-10.
: 2. TVA letter to NRC, dated March 6, 1989, NRC Bulletin 88-07, Supplement 1 - Power
Discussion:   TVA provided a revised response to Bulletin 88-10 in Reference 1. TVA stated that it had completed its Bulletin 88-10 effort for Units 1, 2 and 3.
 
TVA had removed the Class 1E Molded Case Circuit Breakers (MCCBs) without adequate traceability from installed service and the warehouse. NRC closed this Bulletin for Unit 1 in Reference 2.
Oscillations in Boiling Water Reactors (BWRs)
Status:       C-C For Unit 1, TVA has removed the Class 1E MCCBs which did not have adequate traceability from both installed service and the warehouse.
: 3. TVA letter to NRC, dated January 14, 1992, TVA BFN Technical Specification (TS) No. 300 Reactor
NRC closed this item in Inspection Report 2005-009 (Reference 3).
 
Core Thermal-Hydraulic Stability
: 4. NRC letter to TVA, dated May 31, 1994, Issuance of Technical Specification Amendments for the
 
Browns Ferry Nuclear Plant Units 1 and 3 (TS 300) 5. NRC letter to TVA, dated August 10, 2006, Browns Ferry Nuclear Plant Unit 1 Recovery - NRC
 
Integrated Inspection Report 05000259/2006007
 
April 13, 2007 E1-15 Bulletin 88-10, Nonconforming Molded-Case Circuit Breakers  
 
Commitment: TVA will complete Bulletin 88-10.  
 
Discussion: TVA provided a revised response to Bulletin 88-10 in Reference 1. TVA stated that it had completed  
 
its Bulletin 88-10 effort for Units 1, 2 and 3.
 
TVA had removed the Class 1E Molded Case Circuit  
 
Breakers (MCCBs) without adequate traceability from  
 
installed service and the warehouse. NRC closed  
 
this Bulletin for Unit 1 in Reference 2.  
 
Status: C-C  
 
For Unit 1, TVA has removed the Class 1E MCCBs  
 
which did not have adequate traceability from both  
 
installed service and the warehouse.  
 
NRC closed this item in Inspection Report 2005-009 (Reference 3).  


==References:==
==References:==
1.
: 1. TVA letter to NRC, dated November 29, 1990, Browns Ferry Nuclear Plant (BFN) - Revised Response and Notification of Implementation of NRC Bulletin 88-10 Nonconforming Molded Case Circuit Breakers (MCCBs)
TVA letter to NRC, dated November 29, 1990, Browns Ferry Nuclear Plant (BFN) - Revised  
: 2. NRC letter to TVA, dated March 10, 1992, NRC Inspection Report Nos. 50-259/92-03, 50-260/92-03, and 50-296/92-03)
 
: 3. NRC letter to TVA, dated February 13, 2006, Browns Ferry Nuclear Plant Unit 1 Recovery - NRC Integrated Inspection Report 05000259/2005009 April 13, 2007                   E1-15
Response and Notification of Implementation of  
 
NRC Bulletin 88-10 Nonconforming Molded Case  
 
Circuit Breakers (MCCBs)
: 2. NRC letter to TVA, dated March 10, 1992, NRC Inspection Report Nos. 50-259/92-03,
 
50-260/92-03, and 50-296/92-03)
: 3. NRC letter to TVA, dated February 13, 2006, Browns Ferry Nuclear Plant Unit 1 Recovery - NRC  
 
Integrated Inspection Report 05000259/2005009 April 13, 2007 E1-16 Bulletin 90-01, Loss of Fill Oil in Transmitters Manufactured by Rosemount 
 
Commitment: TVA will complete Bulletin 90-01.
 
Discussion: TVA originally responded to Bulletin 90-01 in Reference 1. TVA responded to Supplement 1 to
 
Bulletin 90-01 in Reference 2. The commitments
 
made in Reference 2 superseded the commitments made
 
in Reference 1. In Reference 2, TVA stated that it
 
would formally notify the NRC of the proposed
 
resolution of the Rosemount transmitter issue for
 
Unit 1 prior to Unit 1 startup. NRC's Safety
 
Evaluation (Reference 3) applied to all three units
 
but stated additional information would be required
 
on Unit 1.
 
In Reference 4, TVA notified NRC of its plan to
 
replace the BFN Unit 1 Rosemount transmitters that
 
meet the criteria specified in NRC Bulletin 90-01, Supplement 1 with new or refurbished transmitters
 
prior to Unit 1 restart. NRC found TVA's response


acceptable in Reference 5.  
Bulletin 90-01, Loss of Fill Oil in Transmitters Manufactured by Rosemount Commitment:    TVA will complete Bulletin 90-01.
 
Discussion:    TVA originally responded to Bulletin 90-01 in Reference 1. TVA responded to Supplement 1 to Bulletin 90-01 in Reference 2. The commitments made in Reference 2 superseded the commitments made in Reference 1. In Reference 2, TVA stated that it would formally notify the NRC of the proposed resolution of the Rosemount transmitter issue for Unit 1 prior to Unit 1 startup. NRCs Safety Evaluation (Reference 3) applied to all three units but stated additional information would be required on Unit 1.
Status: C-C TVA has replaced the BFN Unit 1 Rosemount  
In Reference 4, TVA notified NRC of its plan to replace the BFN Unit 1 Rosemount transmitters that meet the criteria specified in NRC Bulletin 90-01, Supplement 1 with new or refurbished transmitters prior to Unit 1 restart. NRC found TVAs response acceptable in Reference 5.
 
Status:       C-C TVA has replaced the BFN Unit 1 Rosemount transmitters that meet the criteria specified in NRC Bulletin 90-01, Supplement 1 with new or refurbished transmitters.
transmitters that meet the criteria specified in  
NRC closed this item in Inspection Report 2005-009 (Reference 6).
 
April 13, 2007                   E1-16
NRC Bulletin 90-01, Supplement 1 with new or  
 
refurbished transmitters.  
 
NRC closed this item in Inspection Report 2005-009 (Reference 6).  
 
April 13, 2007 E1-17


==References:==
==References:==
1.
: 1. TVA letter to NRC, dated July 18, 1990, Response to NRC Bulletin No. 90-01: Loss of Fill-Oil in Transmitters Manufactured by Rosemount
TVA letter to NRC, dated July 18, 1990, Response to NRC Bulletin No. 90-01: Loss of Fill-Oil in  
: 2. TVA letter to NRC, dated March 5, 1993, Response to NRC Bulletin No. 90-01, Supplement 1 - Loss of Fill Oil in Transmitters Manufactured by Rosemount
 
: 3. NRC letter to TVA, dated April 4, 1995, NRC Bulletin 90-01, Supplement 1, Loss of Fill-Oil in Transmitters Manufactured by Rosemount -
Transmitters Manufactured by Rosemount
: 2. TVA letter to NRC, dated March 5, 1993, Response to NRC Bulletin No. 90-01, Supplement 1 - Loss  
 
of Fill Oil in Transmitters Manufactured by  
 
Rosemount
: 3. NRC letter to TVA, dated April 4, 1995, NRC Bulletin 90-01, Supplement 1, Loss of Fill-Oil  
 
in Transmitters Manufactured by Rosemount -  
 
Browns Ferry Nuclear Plant Units 1, 2, and 3 (TAC Nos. M85361, M85362, and M85363)
Browns Ferry Nuclear Plant Units 1, 2, and 3 (TAC Nos. M85361, M85362, and M85363)
: 4. TVA letter to NRC, dated June 7, 2004, Browns Ferry Nuclear Plant (BFN) - Unit 1 - Response to  
: 4. TVA letter to NRC, dated June 7, 2004, Browns Ferry Nuclear Plant (BFN) - Unit 1 - Response to NRC Bulletin no. 90-01, Supplement 1 - Loss of Fill Oil in Transmitters Manufactured by Rosemount
 
: 5. NRC letter to TVA, dated February 7, 2005, Browns Ferry Nuclear Plant, Unit 1 - Closeout of Bulletin 90-01, Supplement 1, Loss of Fill-Oil in Transmitters Manufactured by Rosemount (TAC No. MC3381)
NRC Bulletin no. 90-01, Supplement 1 - Loss of  
: 6. NRC letter to TVA, dated February 13, 2006, Browns Ferry Nuclear Plant Unit 1 Recovery - NRC Integrated Inspection Report 05000259/2005009 April 13, 2007                  E1-17
 
Fill Oil in Transmitters Manufactured by  


Rosemount
Bulletin 93-02, Debris Plugging of Emergency Core Cooling Suction Strainers, and Supplement 1 Commitment:   TVA will complete Bulletin 93-02 and Supplement 1 prior to restart.
: 5. NRC letter to TVA, dated February 7, 2005, Browns Ferry Nuclear Plant, Unit 1 - Closeout of
Discussion:   TVA responded to Bulletin 93-02 in Reference 1 and committed to:
 
Bulletin 90-01, Supplement 1, Loss of Fill-Oil
 
in Transmitters Manufactured by Rosemount (TAC No. MC3381)
: 6. NRC letter to TVA, dated February 13, 2006, Browns Ferry Nuclear Plant Unit 1 Recovery - NRC
 
Integrated Inspection Report 05000259/2005009
 
April 13, 2007 E1-18 Bulletin 93-02, Debris Plugging of Emergency Core Cooling Suction Strainers, and Supplement 1  
 
Commitment: TVA will complete Bulletin 93-02 and Supplement 1 prior to restart.  
 
Discussion: TVA responded to Bulletin 93-02 in Reference 1 and committed to:
: 1. Evaluate Unit 1 for permanent fibrous material.
: 1. Evaluate Unit 1 for permanent fibrous material.
: 2. Inspect Unit 1 and remove temporary fibrous material.
: 2. Inspect Unit 1 and remove temporary fibrous material.
: 3. Confirm completion of the above listed activities before startup.  
: 3. Confirm completion of the above listed activities before startup.
 
In TVA's response to Supplement 1 of Bulletin 93-02 (Reference 2), TVA committed to augment the operator's required reading program, conduct classroom and/or simulator training, revise appendices in BFNs Emergency Operating Instructions (EOIs) to include caution statements and actions for monitoring net positive suction head, and change the applicable design control procedure to require evaluation of fibrous material being introduced into the drywell.
In TVA's response to Supplement 1 of Bulletin 93-02 (Reference 2), TVA committed to augment the  
In Reference 3, NRC stated that TVA's response to Supplement 1 adequately addressed the actions TVA would take to assure continued Emergency Core Cooling System (ECCS) suction capability. TVA notified NRC of the completion of the commitments made in response to Supplement 1 of Bulletin 93-02 for all three units in Reference 4.
 
TVA updated its response to the Bulletin for Unit 1 in Reference 5.
operator's required reading program, conduct  
Status:       C-C TVA has evaluated the drywell for permanent fibrous material. The results were similar to Units 2 and 3. Limited amounts of fibrous material are permanently installed in several containment penetrations. Also, in accordance with the Units 2 and 3s precedent, TVA has revised its Unit 1 General Operating Instruction on Drywell Closeout to ensure temporary fibrous air filters or other temporary sources of fibrous material are removed.
 
April 13, 2007                    E1-18
classroom and/or simulator training, revise  
 
appendices in BFN's Emergency Operating  
 
Instructions (EOIs) to include caution statements  
 
and actions for monitoring net positive suction  
 
head, and change the applicable design control  
 
procedure to require evaluation of fibrous material  
 
being introduced into the drywell.  
 
In Reference 3, NRC stated that TVA's response to  
 
Supplement 1 adequately addressed the actions TVA  
 
would take to assure continued Emergency Core  
 
Cooling System (ECCS) suction capability. TVA  
 
notified NRC of the completion of the commitments  
 
made in response to Supplement 1 of Bulletin 93-02  
 
for all three units in Reference 4.  
 
TVA updated its response to the Bulletin for Unit 1  
 
in Reference 5.  
 
Status: C-C  
 
TVA has evaluated the drywell for permanent fibrous  
 
material. The results were similar to Units
 
2 and 3. Limited amounts of fibrous material are  


permanently installed in several containment
Inspection Report 2006-006 (Reference 6) stated However, final closure of this item will be deferred until NRR completes their review in this area and any SERs, if required, are issued.
 
In a letter dated July 26, 2006 (Reference 7), NRR issued an SER concluding BFN has satisfied this Bulletin.
penetrations. Also, in accordance with the Units 2
NRC closed this item in Inspection Report 2006-008 (Reference 8).
 
and 3's precedent, TVA has revised its Unit 1
 
General Operating Instruction on Drywell Closeout
 
to ensure temporary fibrous air filters or other
 
temporary sources of fibrous material are removed.
 
April 13, 2007 E1-19 Inspection Report 2006-006 (Reference 6) stated "-
However, final closure of this item will be  
 
deferred until NRR completes their review in this  
 
area and any SERs, if required, are issued."
 
In a letter dated July 26, 2006 (Reference 7), NRR  
 
issued an SER concluding BFN has satisfied this  
 
Bulletin.  
 
NRC closed this item in Inspection Report 2006-008 (Reference 8).  


==References:==
==References:==
1.
: 1. TVA letter to NRC, dated May 23, 1993, NRC Bulletin No. 93-02, Debris Plugging of Emergency Core Cooling Suction Strainers
TVA letter to NRC, dated May 23, 1993, NRC Bulletin No. 93-02, Debris Plugging of Emergency  
: 2. TVA letter to NRC, dated April 18, 1994, NRC Bulletin 93-02, Supplement 1 - Debris Plugging of Emergency Core Cooling System (ECCS) Suction Strainers
 
: 3. NRC letter to TVA, dated July 19, 1994, Response to NRC Bulletin 93 Supplement 1, Debris Plugging of Emergency Core Cooling Suction Strainers
Core Cooling Suction Strainers
: 4. TVA letter to NRC, dated July 29, 1994, NRC Bulletin 93-02, Supplement 1 - Debris Plugging of Emergency Core Cooling System (ECCS) Suction Strainers - Commitment Completion
: 2. TVA letter to NRC, dated April 18, 1994, NRC Bulletin 93-02, Supplement 1 - Debris Plugging  
: 5. TVA letter to NRC, dated May 6, 2004, Browns Ferry Nuclear Plant (BFN) Unit 1 - Update to TVA Response to NRC Bulletin No. 93-02, Debris Plugging of Emergency Core Cooling Suction Strainers
 
: 6. NRC letter to TVA, dated May 15, 2006, Browns Ferry Nuclear Plant Unit 1 Recovery - NRC Integrated Inspection Report 05000259/2006006
of Emergency Core Cooling System (ECCS) Suction  
: 7. NRC Letter To TVA, dated July 26, 2006, Browns Ferry Nuclear Plant, Unit 1 - Review Of Licensee Response To NRC Bulletin 93-02, Debris Plugging of Emergency Core Cooling Suction Strainers (TAC No. Mc3393)
 
: 8. NRC letter to TVA, dated November 9, 2006, Browns Ferry Nuclear Plant Unit 1 Recovery - NRC Integrated Inspection Report 05000259/2006008 April 13, 2007                  E1-19
Strainers
: 3. NRC letter to TVA, dated July 19, 1994, Response to NRC Bulletin 93 Supplement 1, Debris  
 
Plugging of Emergency Core Cooling Suction  
 
Strainers
: 4. TVA letter to NRC, dated July 29, 1994, NRC Bulletin 93-02, Supplement 1 - Debris Plugging  
 
of Emergency Core Cooling System (ECCS) Suction  
 
Strainers - Commitment Completion
: 5. TVA letter to NRC, dated May 6, 2004, Browns Ferry Nuclear Plant (BFN) Unit 1 - Update to TVA  
 
Response to NRC Bulletin No. 93-02, Debris  
 
Plugging of Emergency Core Cooling Suction  


Strainers
Bulletin 93-03, Resolution of Issues Related to Reactor Vessel Water Level Instrumentation in BWRs Commitment:   TVA intends to complete a modification which will prevent the buildup of non-condensibles in water level reference legs by injecting CRD system charging water into the reference legs.
: 6. NRC letter to TVA, dated May 15, 2006, Browns Ferry Nuclear Plant Unit 1 Recovery - NRC
Discussion:   TVA's response to Bulletin 93-03 was provided by Reference 1. TVA committed to perform modifications on Unit 1 prior to restart. NRC accepted TVAs response to the Bulletin in Reference 2. A detailed description of the modification installed on Unit 2 was provided in Reference 3.
 
Status:       C-C TVA completed the described modification.
Integrated Inspection Report 05000259/2006006
NRC closed this item in Inspection Report 2006-009 (Reference 4).
: 7. NRC Letter To TVA, dated July 26, 2006, Browns Ferry Nuclear Plant, Unit 1 - Review Of Licensee
 
Response To NRC Bulletin 93-02, "Debris Plugging
 
of Emergency Core Cooling Suction Strainers" (TAC No. Mc3393)
: 8. NRC letter to TVA, dated November 9, 2006, Browns Ferry Nuclear Plant Unit 1 Recovery - NRC
 
Integrated Inspection Report 05000259/2006008
 
April 13, 2007 E1-20 Bulletin 93-03, Resolution of Issues Related to Reactor Vessel Water Level Instrumentation in BWRs  
 
Commitment: TVA intends to complete a modification which will prevent the buildup of non-condensibles in water  
 
level reference legs by injecting CRD system  
 
charging water into the reference legs.  
 
Discussion: TVA's response to Bulletin 93-03 was provided by Reference 1. TVA committed to perform  
 
modifications on Unit 1 prior to restart. NRC  
 
accepted TVA's response to the Bulletin in  
 
Reference 2. A detailed description of the  
 
modification installed on Unit 2 was provided in  
 
Reference 3.  
 
Status: C-C  
 
TVA completed the described modification.  
 
NRC closed this item in Inspection Report 2006-009 (Reference 4).  


==References:==
==References:==
1.
: 1. TVA letter to NRC, dated July 30, 1993, Response to NRC Bulletin (NRCB) 93-03, Resolution of Issues Related to Reactor Vessel Water Level Instrumentation in Boiling Water Reactors
TVA letter to NRC, dated July 30, 1993, Response to NRC Bulletin (NRCB) 93-03, Resolution of  
: 2. NRC letter to TVA, dated April 20, 1994, Browns Ferry Nuclear Plant Units 1, 2, and 3 - Response To NRC Bulletin 93-03, "Resolution of Issues Related to Reactor Vessel Water Level Instrumentation in BWRs," (TAC Nos. M86882, M86883, and M86884)
 
: 3. TVA letter to NRC, dated December 14, 1994, Hardware Modification Completion and Description in Response to Bulletin 93-03, Resolution of Issues Related to Reactor Vessel Water Level Instrumentation in Boiling Water Reactors
Issues Related to Reactor Vessel Water Level  
: 4. NRC letter to TVA, dated March 5, 2007, Browns Ferry Nuclear Plant Unit 1 Recovery - NRC Integrated Inspection Report 05000259/2006009 April 13, 2007                    E1-20
 
Instrumentation in Boiling Water Reactors
: 2. NRC letter to TVA, dated April 20, 1994, Browns Ferry Nuclear Plant Units 1, 2, and 3 - Response  
 
To NRC Bulletin 93-03, "Resolution of Issues  


Related to Reactor Vessel Water Level
Bulletin 95-02, Unexpected Clogging of a Residual Heat Removal (RHR) Pump Strainer While Operating in Suppression Pool Cooling Mode Commitment:   Appropriate actions will be taken prior to Unit 1 restart.
 
Discussion:   TVA's response to Bulletin 95-02 was provided in Reference 1. For Units 2 and 3, TVA committed to clean the suppression pool and perform confirmatory inspection and test prior to restart. TVA also committed to perform a visual inspection of the Emergency Core Cooling System pump suction strainers during each refueling outage and a program for suppression pool cleaning will be developed prior to restart. TVA stated that the programs established to ensure Emergency Core Cooling System pump operability on Units 2 and 3 would apply to Unit 1 when it was returned to service. NRC found TVAs response acceptable in Reference 2.
Instrumentation in BWRs," (TAC Nos. M86882, M86883, and M86884)
Status:       C-C The Unit 1 suppression pool was drained, cleaned, inspected and recoated as necessary. Program to ensure suppression pool cleanliness and control of foreign material has been implemented.
: 3. TVA letter to NRC, dated December 14, 1994, Hardware Modification Completion and Description
NRC closed this item in Inspection Report 2006-006 (Reference 3).
 
in Response to Bulletin 93-03, Resolution of
 
Issues Related to Reactor Vessel Water Level
 
Instrumentation in Boiling Water Reactors
: 4. NRC letter to TVA, dated March 5, 2007, Browns Ferry Nuclear Plant Unit 1 Recovery - NRC
 
Integrated Inspection Report 05000259/2006009
 
April 13, 2007 E1-21 Bulletin 95-02, Unexpected Clogging of a Residual Heat Removal (RHR) Pump Strainer While Operating in  
 
Suppression Pool Cooling Mode  
 
Commitment: Appropriate actions will be taken prior to Unit 1 restart.
Discussion: TVA's response to Bulletin 95-02 was provided in Reference 1. For Units 2 and 3, TVA committed to  
 
clean the suppression pool and perform confirmatory  
 
inspection and test prior to restart. TVA also  
 
committed to perform a visual inspection of the  
 
Emergency Core Cooling System pump suction  
 
strainers during each refueling outage and a  
 
program for suppression pool cleaning will be  
 
developed prior to restart. TVA stated that the  
 
programs established to ensure Emergency Core  
 
Cooling System pump operability on Units 2 and 3  
 
would apply to Unit 1 when it was returned to  
 
service. NRC found TVA's response acceptable in  
 
Reference 2.  
 
Status: C-C  
 
The Unit 1 suppression pool was drained, cleaned, inspected and recoated as necessary. Program to  
 
ensure suppression pool cleanliness and control of  
 
foreign material has been implemented.  
 
NRC closed this item in Inspection Report 2006-006 (Reference 3).  


==References:==
==References:==
1.
: 1. TVA letter to NRC, dated November 15, 1995, Browns Ferry Nuclear Plant (BFN) - NRC Bulletin 95-02, Unexpected Clogging of a Residual Heat Removal (RHR) Pump Strainer While Operating In Suppression Pool Cooling Mode
TVA letter to NRC, dated November 15, 1995, Browns Ferry Nuclear Plant (BFN) - NRC Bulletin  
: 2. NRC letter to TVA, dated March 14, 1996, Browns Ferry Nuclear Plant Units 1, 2, and 3 - Response to Bulletin 95-02 (TAC Nos. M93876, M93877, and M93878)
 
: 3. NRC letter to TVA, dated May 15, 2006, Browns Ferry Nuclear Plant Unit 1 Recovery - NRC Integrated Inspection Report 05000259/2006006 April 13, 2007                   E1-21
95-02, Unexpected Clogging of a Residual Heat  
 
Removal (RHR) Pump Strainer While Operating In  
 
Suppression Pool Cooling Mode
: 2. NRC letter to TVA, dated March 14, 1996, Browns Ferry Nuclear Plant Units 1, 2, and 3 - Response  
 
to Bulletin 95-02 (TAC Nos. M93876, M93877, and  
 
M93878) 3. NRC letter to TVA, dated May 15, 2006, Browns Ferry Nuclear Plant Unit 1 Recovery - NRC  
 
Integrated Inspection Report 05000259/2006006  
 
April 13, 2007 E1-22 Bulletin 96-03, Potential Plugging of Emergency Core Cooling Suction Strainers By Debris In Boiling-Water
 
Reactors Commitment: Appropriate modifications to address Bulletin 96-03 will be implemented on Unit 1 prior to its restart.


Discussion: TVA originally responded to the Bulletin in Reference 1 and committed to describing planned  
Bulletin 96-03, Potential Plugging of Emergency Core Cooling Suction Strainers By Debris In Boiling-Water Reactors Commitment:    Appropriate modifications to address Bulletin 96-03 will be implemented on Unit 1 prior to its restart.
 
Discussion:   TVA originally responded to the Bulletin in Reference 1 and committed to describing planned actions and schedules to be utilized to resolve the Bulletin within 90 days following the approval of the Utility Resolution Guidelines. TVA described its plans for resolution of the Bulletin in Reference 2 and committed to resolve the Bulletin prior to restart for Unit 1.
actions and schedules to be utilized to resolve the  
Status:       C-C TVA has installed new, high capacity passive strainers on Unit 1, which are of the same design as on Units 2 and 3.
 
NRC closed this item in Inspection Report 2006-009 (Reference 3).
Bulletin within 90 days following the approval of  
 
the Utility Resolution Guidelines. TVA described  
 
its plans for resolution of the Bulletin in  
 
Reference 2 and committed to resolve the Bulletin  
 
prior to restart for Unit 1.  
 
Status: C-C  
 
TVA has installed new, high capacity passive  
 
strainers on Unit 1, which are of the same design  
 
as on Units 2 and 3.  
 
NRC closed this item in Inspection Report 2006-009 (Reference 3).  


==References:==
==References:==
1.
: 1. TVA letter to NRC, dated November 4, 1996, Browns Ferry Nuclear Plant (BFN) - NRC Bulletin No. 96-03, Potential Plugging of Emergency Core Cooling Suction Strainers by Debris in Boiling-Water Reactors (TAC Nos. M96135, M96136, M96137)
TVA letter to NRC, dated November 4, 1996, Browns Ferry Nuclear Plant (BFN) - NRC Bulletin  
: 2. TVA letter to NRC, dated July 25, 1997, Browns Ferry Nuclear Plant (BFN) - NRC Bulletin No.
96-03, Potential Plugging of Emergency Core Cooling Suction (ECCS) Strainers by Debris in Boiling Water Reactors (TAC Nos. M96135, M96136, M96137)
: 3. NRC letter to TVA, dated March 5, 2007, Browns Ferry Nuclear Plant Unit 1 Recovery - NRC Integrated Inspection Report 05000259/2006009 April 13, 2007                    E1-22


No. 96-03, Potential Plugging of Emergency Core
Cable Ampacity Commitment:   The cable ampacity issue will be resolved in accordance with the Unit 2 precedent.
 
Discussion:   TVA developed a new electrical design standard to address ampacities for cables in conduits, cable trays, and duct banks, as well as derating factors for cable coatings, fire wraps, cable tray covers, and cable tray bottoms. Approval of this program is contained in NUREG-1232 (Reference 1).
Cooling Suction Strainers by Debris in 
Status:       Complete TVA has resolved the cable ampacity issue.
 
Boiling-Water Reactors (TAC Nos. M96135, M96136, M96137) 2. TVA letter to NRC, dated July 25, 1997, Browns Ferry Nuclear Plant (BFN) - NRC Bulletin No. 
 
96-03, Potential Plugging of Emergency Core
 
Cooling Suction (ECCS) Strainers by Debris in
 
Boiling Water Reactors (TAC Nos. M96135, M96136, M96137) 3. NRC letter to TVA, dated March 5, 2007, Browns Ferry Nuclear Plant Unit 1 Recovery - NRC
 
Integrated Inspection Report 05000259/2006009
 
April 13, 2007 E1-23 Cable Ampacity Commitment: The cable ampacity issue will be resolved in accordance with the Unit 2 precedent.  
 
Discussion: TVA developed a new electrical design standard to address ampacities for cables in conduits, cable  
 
trays, and duct banks, as well as derating factors  
 
for cable coatings, fire wraps, cable tray covers, and cable tray bottoms. Approval of this program  
 
is contained in NUREG-1232 (Reference 1).  
 
Status: Complete  
 
TVA has resolved the cable ampacity issue.  


==References:==
==References:==
1.
: 1. NRC letter to TVA, dated January 23, 1991, NUREG-1232, Volume 3, Supplement 2 -
NRC letter to TVA, dated January 23, 1991, NUREG-1232, Volume 3, Supplement 2 -
Browns Ferry Unit 2 [Section 3.11.3, Page 3-9]
April 13, 2007                  E1-23


Browns Ferry Unit 2 [Section 3.11.3, Page 3-9]
Cable Installation Issue Number 1, Brand Rex Cable Issues Commitment:   To resolve the Brand Rex cable issue, corrective actions will be implemented prior to the restart of Unit 1 in accordance with the Unit 2 precedent.
 
Discussion:   The action plan to disposition concerns related to cable installation issues, including Brand Rex, was provided in Reference 1. The Safety Evaluation on this program was provided by Reference 2. In summary, the Staff found implementing the corrective actions for the Brand Rex cable issue in accordance with the Unit 2 precedent to be acceptable pending the results of additional qualification testing being performed by TVA.
April 13, 2007 E1-24 Cable Installation Issue Number 1, Brand Rex Cable Issues Commitment: To resolve the Brand Rex cable issue, corrective actions will be implemented prior to the restart of  
TVA has identified contract number 80K6-825419 as the source of the Brand Rex cables issue for BFN.
 
Additional testing demonstrated the ability of the cables to perform their intended safety function for a qualified life of 40 years. TVA has removed all non-installed Brand Rex cable furnished on contract 80K6-825419. Administrative controls are in place to prevent future applications of this cable type and manufacturer from being installed at BFN.
Unit 1 in accordance with the Unit 2 precedent.  
Status:       Open
 
Discussion: The action plan to disposition concerns related to cable installation issues, including Brand Rex, was  
 
provided in Reference 1. The Safety Evaluation on  
 
this program was provided by Reference 2. In  
 
summary, the Staff found implementing the  
 
corrective actions for the Brand Rex cable issue in  
 
accordance with the Unit 2 precedent to be  
 
acceptable pending the results of additional  
 
qualification testing being performed by TVA.  
 
TVA has identified contract number 80K6-825419 as  
 
the source of the Brand Rex cables issue for BFN.
 
Additional testing demonstrated the ability of the  
 
cables to perform their intended safety function  
 
for a qualified life of 40 years. TVA has removed  
 
all non-installed Brand Rex cable furnished on  
 
contract 80K6-825419. Administrative controls are  
 
in place to prevent future applications of this  
 
cable type and manufacturer from being installed at  
 
BFN.
Status: Open  


==References:==
==References:==
1.
: 1. TVA letter to NRC, dated May 10, 1991, Action Plan to Disposition Concerns Related to Units 1 and 3 Cable Installation Issues Including Cable Separations
TVA letter to NRC, dated May 10, 1991, Action Plan to Disposition Concerns Related to Units 1  
: 2. NRC letter to TVA, dated April 8, 1992, Safety Evaluation of TVA Plans to Resolve Electrical Cable Installation and Separation Issues April 13, 2007                   E1-24
 
and 3 Cable Installation Issues Including Cable  
 
Separations
: 2. NRC letter to TVA, dated April 8, 1992, Safety Evaluation of TVA Plans to Resolve Electrical  
 
Cable Installation and Separation Issues  
 
April 13, 2007 E1-25 Cable Installation Issue Number 2, Cable Separations Issues
 
Commitment: TVA committed to the following:
: 1. Prior to fuel load of Unit 1, TVA will implement all corrective actions in accordance


with the Unit 2 criteria and implementation  
Cable Installation Issue Number 2, Cable Separations Issues Commitment:    TVA committed to the following:
 
: 1. Prior to fuel load of Unit 1, TVA will implement all corrective actions in accordance with the Unit 2 criteria and implementation precedent for the following cable separations issues:
precedent for the following cable separations  
 
issues:
* V4 and V5 cables which originate from safety-related power supplies,
* V4 and V5 cables which originate from safety-related power supplies,
* Nondivisional V4 and V5 cables which originate from nonsafety-related power  
* Nondivisional V4 and V5 cables which originate from nonsafety-related power supplies,
 
* V3 cables which originate from safety-related and from nonsafety-related power supplies,
supplies,
* Nondivisional V1 and V2 cables which originate from both safety-related and nonsafety-related power supplies,
* V3 cables which originate from safety-related and from nonsafety-related  
 
power supplies,
* Nondivisional V1 and V2 cables which originate from both safety-related and  
 
nonsafety-related power supplies,
* Divisional and nondivisional cables designated with an IE and IES suffix, and
* Divisional and nondivisional cables designated with an IE and IES suffix, and
* Divisional V1 and V2 cables. 2. As documented in References 1 through 6, Unit 2 validated the use of the cable schedule  
* Divisional V1 and V2 cables.
 
: 2. As documented in References 1 through 6, Unit 2 validated the use of the cable schedule drawings (45C800 series) in determining the installed configuration of cables in the plant.
drawings (45C800 series) in determining the  
Unit 1 cables were included in the population of cables that were used in the validation process during the Unit 2 restart effort. As documented in Reference 7, the Unit 1 cables have always been routed manually. The Unit 1 circuit schedule was not an electronic database. Therefore, TVA will use the 45C800 series drawings as the document of record in the determination of acceptable routing for Unit 1.
 
April 13, 2007                   E1-25
installed configuration of cables in the plant.  
: 3. The Unit 1 Master Equipment List (MEL) will establish the list of equipment and device IDs for safety-related and quality-related systems.
 
For nondivisional V1, V2, V3, V4 and V5 cables identified in the MEL as safety-related for Unit 1, cable separation issues will be resolved by analyzing design drawings to identify cables required to support the safety-related and quality-related devices.
Unit 1 cables were included in the population  
The resulting list will be compared against the 45C800 drawings to determine if cables are correctly identified as divisional. If it is determined that a change in divisional status is required, the respective cables will be evaluated against separations criteria.
 
Corrective actions will be completed prior to fuel load.
of cables that were used in the validation  
: 4. For cables contained in divisional and nondivisional cable trays that physically connect on Unit 1, corrective actions will be implemented prior to Unit 1 fuel load.
 
Discussion:   TVA had identified instances where the electrical separation requirements had not been met at BFN.
process during the Unit 2 restart effort. As  
The Units 1 and 3 specific action plan to disposition concerns related to cable installation issues, including cable separation, was provided in Reference 1. The Safety Evaluation on this program was provided by Reference 2. Additional information was requested regarding the corrective actions to be implemented for discrepancies associated with the two cables contained in divisional and nondivisional cable trays that physically connect. This additional information was provided by TVA in Reference 3. The NRC Staff accepted this information in Reference 4.
 
Status:       Complete Evaluations have been completed and noted discrepancies have been completed.
documented in Reference 7, the Unit 1 cables  
April 13, 2007                   E1-26
 
have always been routed manually. The Unit 1  
 
circuit schedule was not an electronic  
 
database. Therefore, TVA will use the 45C800  
 
series drawings as the document of record in  
 
the determination of acceptable routing for  
 
Unit 1.
April 13, 2007 E1-26
: 3. The Unit 1 Master Equipment List (MEL) will establish the list of equipment and device IDs  
 
for safety-related and quality-related systems.  
 
For nondivisional V1, V2, V3, V4 and V5 cables  
 
identified in the MEL as safety-related for  
 
Unit 1, cable separation issues will be  
 
resolved by analyzing design drawings to  
 
identify cables required to support the
 
safety-related and quality-related devices.
 
The resulting list will be compared against the  
 
45C800 drawings to determine if cables are  
 
correctly identified as divisional. If it is  
 
determined that a change in divisional status  
 
is required, the respective cables will be  
 
evaluated against separations criteria.
 
Corrective actions will be completed prior to  
 
fuel load.
: 4. For cables contained in divisional and nondivisional cable trays that physically  
 
connect on Unit 1, corrective actions will be  
 
implemented prior to Unit 1 fuel load.  
 
Discussion: TVA had identified instances where the electrical separation requirements had not been met at BFN.
 
The Units 1 and 3 specific action plan to  
 
disposition concerns related to cable installation  
 
issues, including cable separation, was provided  
 
in Reference 1. The Safety Evaluation on this  
 
program was provided by Reference 2. Additional  
 
information was requested regarding the corrective  
 
actions to be implemented for discrepancies  
 
associated with the two cables contained in  
 
divisional and nondivisional cable trays that  
 
physically connect. This additional information  
 
was provided by TVA in Reference 3. The NRC Staff  
 
accepted this information in Reference 4.  
 
Status: Complete  
 
Evaluations have been completed and noted  
 
discrepancies have been completed.  
 
April 13, 2007 E1-27


==References:==
==References:==
1.
: 1. TVA letter to NRC, dated January 6, 1989, Browns Ferry Nuclear Plant (BFN) - Electrical Cable Separation
TVA letter to NRC, dated January 6, 1989, Browns Ferry Nuclear Plant (BFN) - Electrical  
: 2. TVA letter to NRC, dated June 9, 1989, Browns Ferry Nuclear Plant (BFN) - Electrical Cable Separation
 
: 3. TVA letter to NRC, dated October 23, 1989, Browns Ferry Nuclear Plant (BFN) - Electrical Cable Separation
Cable Separation
: 4. TVA letter to NRC, dated December 14, 1989, Browns Ferry Nuclear Plant (BFN) - Electrical Cable Separation
: 2. TVA letter to NRC, dated June 9, 1989, Browns Ferry Nuclear Plant (BFN) - Electrical Cable  
 
Separation
: 3. TVA letter to NRC, dated October 23, 1989, Browns Ferry Nuclear Plant (BFN) - Electrical  
 
Cable Separation
: 4. TVA letter to NRC, dated December 14, 1989, Browns Ferry Nuclear Plant (BFN) - Electrical  
 
Cable Separation
: 5. NRC letter to TVA, dated February 23, 1990, NRC Inspection Report No. 50-260/89-59
: 5. NRC letter to TVA, dated February 23, 1990, NRC Inspection Report No. 50-260/89-59
: 6. NRC letter to TVA, dated August 10, 1990, NRC Inspection Report No. 50-260/90-13
: 6. NRC letter to TVA, dated August 10, 1990, NRC Inspection Report No. 50-260/90-13
: 7. TVA letter to NRC, dated December 29, 1992, Response to Request for Additional Information  
: 7. TVA letter to NRC, dated December 29, 1992, Response to Request for Additional Information on Electrical Cables in Divisional and Nondivisional Trays Which Are Physically Connected April 13, 2007                   E1-27
 
on Electrical Cables in Divisional and  
 
Nondivisional Trays Which Are Physically  
 
Connected  
 
April 13, 2007 E1-28 Cable Installation Issue Number 3, Low Voltage Vertical Cable Supports Commitment: TVA will resolve the low voltage vertical cable supports issue in accordance with the Unit 2
 
precedent.
 
Discussion: The action plan to disposition concerns related to cable installation issues, including vertical cable
 
supports, was provided in Reference 1. The Safety


Evaluation on this program was provided by  
Cable Installation Issue Number 3, Low Voltage Vertical Cable Supports Commitment:    TVA will resolve the low voltage vertical cable supports issue in accordance with the Unit 2 precedent.
 
Discussion:    The action plan to disposition concerns related to cable installation issues, including vertical cable supports, was provided in Reference 1. The Safety Evaluation on this program was provided by Reference 2. In summary, since no Unit 2 cables with acceptable sidewall bearing pressure failed Hi-Pot testing, the walkdown and evaluation of Unit 1 safety-related low voltage power, control and instrumentation cable is adequate to satisfactorily resolve the vertical support issue.
Reference 2. In summary, since no Unit 2 cables  
Status:       Open
 
with acceptable sidewall bearing pressure failed  
 
Hi-Pot testing, the walkdown and evaluation of  
 
Unit 1 safety-related low voltage power, control  
 
and instrumentation cable is adequate to  
 
satisfactorily resolve the vertical support issue.  
 
Status: Open  


==References:==
==References:==
1.
: 1. TVA letter to NRC, dated May 10, 1991, Action Plan to Disposition Concerns Related to Units 1 and 3 Cable Installation Issues Including Cable Separations
TVA letter to NRC, dated May 10, 1991, Action Plan to Disposition Concerns Related to Units 1  
: 2. NRC letter to TVA, dated April 8, 1992, Safety Evaluation of TVA Plans to Resolve Electrical Cable Installation and Separation Issues April 13, 2007                  E1-28


and 3 Cable Installation Issues Including Cable
Cable Installation Issue Number 4, Medium Voltage Cable Bend Radius Commitment:   Safety-related medium voltage cables will be identified, walked down and evaluated against the bend radius criteria used for Unit 2 (General Construction Specification G-38). The following corrective actions will be completed:
 
A. Group 1 cables with bend radius of less than 6 times the cable outside diameter (OD) will be replaced.
Separations
B. Group 2 cables with bend radius from 6 times the cable OD to less than 8 times the cable OD will be tested prior to restart and during subsequent outages to facilitate a trend analysis.
: 2. NRC letter to TVA, dated April 8, 1992, Safety Evaluation of TVA Plans to Resolve Electrical
C. Group 3 cables, with bend radius 8 times or greater than the cable OD will be allowed to remain in service and be subjected to only normal maintenance testing.
 
Discussion:   The action plan to disposition concerns related to cable installation issues, including medium voltage cable bend radius, was provided in Reference 1.
Cable Installation and Separation Issues
The Safety Evaluation of this program was provided by Reference 2. In summary, since safety-related medium voltage cables are to be identified, walked down and evaluated against the bend radius acceptance criteria contained in Construction Specification G-38 and dispositioned in accordance with the same criteria used for Unit 2, the proposed corrective actions are adequate.
 
In Reference 3, TVA proposed a new program and corrective actions for medium cable bend radius issues. Results of reinspections were presented to NRC and Hi-Pot testing was replaced with Load Cycle and Corona Testing. Additional information regarding the revised program was requested in Reference 4, which was provided by TVA in Reference 5. NRC issuance of a Safety Evaluation for this program and a request for additional information was contained in Reference 6. TVA replied in Reference 7, and the Supplemental Safety Evaluation Report was provided in Reference 8.
April 13, 2007 E1-29 Cable Installation Issue Number 4, Medium Voltage Cable Bend Radius Commitment: Safety-related medium voltage cables will be identified, walked down and evaluated against the  
Status:       Open April 13, 2007                   E1-29
 
bend radius criteria used for Unit 2 (General  
 
Construction Specification G-38). The following  
 
corrective actions will be completed:
A. Group 1 cables with bend radius of less than 6 times the cable outside diameter (OD) will be  
 
replaced.
B. Group 2 cables with bend radius from 6 times the cable OD to less than 8 times the cable OD will  
 
be tested prior to restart and during subsequent  
 
outages to facilitate a trend analysis.
C. Group 3 cables, with bend radius 8 times or greater than the cable OD will be allowed to  
 
remain in service and be subjected to only  
 
normal maintenance testing.  
 
Discussion: The action plan to disposition concerns related to cable installation issues, including medium voltage  
 
cable bend radius, was provided in Reference 1.
 
The Safety Evaluation of this program was provided  
 
by Reference 2. In summary, since safety-related  
 
medium voltage cables are to be identified, walked  
 
down and evaluated against the bend radius  
 
acceptance criteria contained in Construction  
 
Specification G-38 and dispositioned in accordance  
 
with the same criteria used for Unit 2, the  
 
proposed corrective actions are adequate.  
 
In Reference 3, TVA proposed a new program and  
 
corrective actions for medium cable bend radius  
 
issues. Results of reinspections were presented to  
 
NRC and Hi-Pot testing was replaced with Load Cycle  
 
and Corona Testing. Additional information  
 
regarding the revised program was requested in  
 
Reference 4, which was provided by TVA in  
 
Reference 5. NRC issuance of a Safety Evaluation  
 
for this program and a request for additional  
 
information was contained in Reference 6. TVA  
 
replied in Reference 7, and the Supplemental Safety  
 
Evaluation Report was provided in Reference 8.
Status: Open  
 
April 13, 2007 E1-30


==References:==
==References:==
1.
: 1. TVA letter to NRC, dated May 10, 1991, Action Plan to Disposition Concerns Related to Units 1 and 3 Cable Installation Issues Including Cable Separations
TVA letter to NRC, dated May 10, 1991, Action Plan to Disposition Concerns Related to Units 1  
: 2. NRC letter to TVA, dated April 8, 1992, Safety Evaluation of TVA Plans to Resolve Electrical Cable Installation and Separation Issues
 
and 3 Cable Installation Issues Including Cable  
 
Separations
: 2. NRC letter to TVA, dated April 8, 1992, Safety Evaluation of TVA Plans to Resolve Electrical  
 
Cable Installation and Separation Issues
: 3. TVA letter to NRC, dated March 17, 1993, Medium Voltage Cable Bend Radius Issues
: 3. TVA letter to NRC, dated March 17, 1993, Medium Voltage Cable Bend Radius Issues
: 4. NRC letter to TVA, dated August 23, 1993, Request for Additional Information Regarding  
: 4. NRC letter to TVA, dated August 23, 1993, Request for Additional Information Regarding Medium Voltage Cable Bend Radius
 
: 5. TVA letter to NRC, dated January 10, 1994, Response to Request for Additional Information Regarding Medium Voltage Cable Bend Radius
Medium Voltage Cable Bend Radius
: 6. NRC letter to TVA, dated July 1, 1994, Safety Evaluation and Request for Additional Information Regarding Medium Voltage Cable Bend Radius Issues
: 5. TVA letter to NRC, dated January 10, 1994, Response to Request for Additional Information  
: 7. TVA letter to NRC, dated September 15, 1994, Reply to NRC Request for Additional Information (RAI) Regarding Medium Voltage Cable Bend Radius Issues
 
: 8. NRC letter to TVA, dated January 9, 1995, Supplemental Safety Evaluation for Medium Voltage Cable Bend Radius April 13, 2007                   E1-30
Regarding Medium Voltage Cable Bend Radius
: 6. NRC letter to TVA, dated July 1, 1994, Safety Evaluation and Request for Additional  
 
Information Regarding Medium Voltage Cable Bend  
 
Radius Issues
: 7. TVA letter to NRC, dated September 15, 1994, Reply to NRC Request for Additional Information (RAI) Regarding Medium Voltage Cable Bend Radius  
 
Issues 8. NRC letter to TVA, dated January 9, 1995, Supplemental Safety Evaluation for Medium  
 
Voltage Cable Bend Radius  
 
April 13, 2007 E1-31 Cable Installation Issue Number 5, Missing Conduit Bushings
 
Commitment: Type PN cables in 10 CFR 50.49 circuits will be replaced under the Environmental Qualification
 
program.
Discussion: The action plan to disposition concerns related to cable installation issues, including missing
 
conduit bushings, was provided in Reference 1. The
 
Safety Evaluation on this program was provided by
 
Reference 2. In summary, the only cables found
 
damaged on Unit 2 as a result of pulling the cables
 
over a conduit end with a missing bushing were the
 
Type PN. Replacing this type of cable in Unit 1
 
10 CFR 50.49 circuits was considered adequate to
 
resolve this issue.


Status: Open  
Cable Installation Issue Number 5, Missing Conduit Bushings Commitment:    Type PN cables in 10 CFR 50.49 circuits will be replaced under the Environmental Qualification program.
Discussion:    The action plan to disposition concerns related to cable installation issues, including missing conduit bushings, was provided in Reference 1. The Safety Evaluation on this program was provided by Reference 2. In summary, the only cables found damaged on Unit 2 as a result of pulling the cables over a conduit end with a missing bushing were the Type PN. Replacing this type of cable in Unit 1 10 CFR 50.49 circuits was considered adequate to resolve this issue.
Status:       Open


==References:==
==References:==
1.
: 1. TVA letter to NRC, dated May 10, 1991, Action Plan to Disposition Concerns Related to Units 1 and 3 Cable Installation Issues Including Cable Separations
TVA letter to NRC, dated May 10, 1991, Action Plan to Disposition Concerns Related to Units 1  
: 2. NRC letter to TVA, dated April 8, 1992, Safety Evaluation of TVA Plans to Resolve Electrical Cable Installation and Separation Issues April 13, 2007                   E1-31
 
and 3 Cable Installation Issues Including Cable  
 
Separations
: 2. NRC letter to TVA, dated April 8, 1992, Safety Evaluation of TVA Plans to Resolve Electrical  
 
Cable Installation and Separation Issues  
 
April 13, 2007 E1-32 Cable Installation Issue Number 6, Sidewall Pressure, Cable Pullbys, Cable Jamming, Pulling Around 90 Degree
 
Condulets and Thru Mid-Run
 
Flex Conduit Issues
 
Commitment: The cables identified in the Master Equipment List (MEL) as safety-related cables for Unit 1, which are not replaced by other programs, will be
 
reviewed to determine the configuration of their
 
associated raceway. If the design of the raceway
 
meets the criteria for sidewall pressure, jamming, pullbys, mid-run flex or pulling around 90 degree
 
condulet concerns, a walkdown will be performed to
 
confirm the installed configuration. Confirmatory
 
walkdowns will be completed prior to Unit 1
 
restart.
Discussion: The action plan to disposition concerns related to cable installation issues, including sidewall
 
pressure, cable pullbys, cable jamming, pulling
 
around 90 degree condulets and thru mid-run flex
 
conduit issues, was provided in Reference 1. 
 
Information regarding cable walkdowns and cable
 
routing system database validation was provided in
 
Reference 2.
 
A Safety Evaluation on cable installation and
 
separation and request for additional information


on divisional/nondivisional separation  
Cable Installation Issue Number 6, Sidewall Pressure, Cable Pullbys, Cable Jamming, Pulling Around 90 Degree Condulets and Thru Mid-Run Flex Conduit Issues Commitment:    The cables identified in the Master Equipment List (MEL) as safety-related cables for Unit 1, which are not replaced by other programs, will be reviewed to determine the configuration of their associated raceway. If the design of the raceway meets the criteria for sidewall pressure, jamming, pullbys, mid-run flex or pulling around 90 degree condulet concerns, a walkdown will be performed to confirm the installed configuration. Confirmatory walkdowns will be completed prior to Unit 1 restart.
 
Discussion:    The action plan to disposition concerns related to cable installation issues, including sidewall pressure, cable pullbys, cable jamming, pulling around 90 degree condulets and thru mid-run flex conduit issues, was provided in Reference 1.
discrepancies was provided in Reference 3. In  
Information regarding cable walkdowns and cable routing system database validation was provided in Reference 2.
 
A Safety Evaluation on cable installation and separation and request for additional information on divisional/nondivisional separation discrepancies was provided in Reference 3. In summary, cable damage was not identified on Unit 2 during the resolution of the sidewall pressure, cable pullbys, cable jamming and pulling around 90-degree condulets and through mid-run flex conduits issues.
summary, cable damage was not identified on Unit 2  
Status:       Open
 
during the resolution of the sidewall pressure, cable pullbys, cable jamming and pulling around
 
90-degree condulets and through mid-run flex  
 
conduits issues.  
 
Status: Open  


==References:==
==References:==
1.
: 1. TVA letter to NRC, dated May 10, 1991, Action Plan to Disposition Concerns Related to Units 1 and 3 Cable Installation Issues Including Cable Separations
TVA letter to NRC, dated May 10, 1991, Action Plan to Disposition Concerns Related to Units 1  
: 2. TVA letter to NRC, dated March 6, 1992, Additional Information on TVA's Action Plan for Units 1 and 3 Cable Installation Issues Including Cable Separations
: 3. NRC letter to TVA, dated April 8, 1992, Safety Evaluation of TVA Plans to Resolve Electrical Cable Installation and Separation Issues April 13, 2007                  E1-32


and 3 Cable Installation Issues Including Cable
Cable Installation Issue Number 7, Use of Condulets as Pull Points Commitment:   The 600V safety-related cables that are susceptible to damage from the use of condulets as pull points will be resolved in accordance with the Unit 2 precedent.
 
Discussion:   The action plan to disposition concerns related to cable installation issues, including the use of condulets as pull points, was provided in Reference 1. The Safety Evaluation on this program was provided by Reference 2. In summary, TVA's evaluation of this issue for Unit 2 determined that the type of conduit configurations susceptible to this problem was limited to several cases of large 600 volt cables in three inch conduits. Therefore, TVA will review the Unit 1 600 volts cables installed in conduit in accordance with the Unit 2 program guidelines / The required corrective actions will be completed prior to fuel load.
Separations
Status:       Open
: 2. TVA letter to NRC, dated March 6, 1992, Additional Information on TVA's Action Plan for
 
Units 1 and 3 Cable Installation Issues
 
Including Cable Separations
: 3. NRC letter to TVA, dated April 8, 1992, Safety Evaluation of TVA Plans to Resolve Electrical
 
Cable Installation and Separation Issues
 
April 13, 2007 E1-33 Cable Installation Issue Number 7, Use of Condulets as Pull Points Commitment: The 600V safety-related cables that are susceptible to damage from the use of condulets as pull points  
 
will be resolved in accordance with the Unit 2  
 
precedent.  
 
Discussion: The action plan to disposition concerns related to cable installation issues, including the use of  
 
condulets as pull points, was provided in  
 
Reference 1. The Safety Evaluation on this program  
 
was provided by Reference 2. In summary, TVA's  
 
evaluation of this issue for Unit 2 determined that  
 
the type of conduit configurations susceptible to  
 
this problem was limited to several cases of large  
 
600 volt cables in three inch conduits. Therefore, TVA will review the Unit 1 600 volts cables  
 
installed in conduit in accordance with the Unit 2  
 
program guidelines / The required corrective  
 
actions will be completed prior to fuel load.  
 
Status: Open  


==References:==
==References:==
1.
: 1. TVA letter to NRC, dated May 10, 1991, Action Plan to Disposition Concerns Related to Units 1 and 3 Cable Installation Issues Including Cable Separations
TVA letter to NRC, dated May 10, 1991, Action Plan to Disposition Concerns Related to Units 1  
: 2. NRC letter to TVA, dated April 8, 1992, Safety Evaluation of TVA Plans to Resolve Electrical Cable Installation and Separation Issues April 13, 2007                  E1-33


and 3 Cable Installation Issues Including Cable
Cable Installation Issue Number 8, Medium Voltage Vertical Cable Supports Commitment:   The medium voltage vertical cable supports issue will be resolved by evaluating cables not meeting the vertical cable support criteria for static sidewall bearing pressure (SSBP). Cables with unacceptable SSBP will be Hi-Pot tested. Cables passing the Hi-Pot test will be supported in accordance with G-38. Cables failing the Hi-Pot test will be replaced.
 
Discussion:   The action plan to disposition concerns related to cable installation issues, including medium voltage vertical cable supports, was provided in Reference 1. The Safety Evaluation on this program was provided by Reference 2. In summary, since no Unit 2 cables with acceptable sidewall bearing pressure failed Hi-Pot testing, the walkdowns and evaluation of Class 1E medium voltage cables is adequate to satisfactorily resolve the vertical support issue.
Separations
Status:       Open
: 2. NRC letter to TVA, dated April 8, 1992, Safety Evaluation of TVA Plans to Resolve Electrical
 
Cable Installation and Separation Issues
 
April 13, 2007 E1-34 Cable Installation Issue Number 8, Medium Voltage Vertical Cable Supports Commitment: The medium voltage vertical cable supports issue will be resolved by evaluating cables not meeting  
 
the vertical cable support criteria for static  
 
sidewall bearing pressure (SSBP). Cables with  
 
unacceptable SSBP will be Hi-Pot tested. Cables  
 
passing the Hi-Pot test will be supported in  
 
accordance with G-38. Cables failing the
 
Hi-Pot test will be replaced.  
 
Discussion: The action plan to disposition concerns related to cable installation issues, including medium voltage  
 
vertical cable supports, was provided in  
 
Reference 1. The Safety Evaluation on this program  
 
was provided by Reference 2. In summary, since no  
 
Unit 2 cables with acceptable sidewall bearing  
 
pressure failed Hi-Pot testing, the walkdowns and  
 
evaluation of Class 1E medium voltage cables is  
 
adequate to satisfactorily resolve the vertical  
 
support issue.  
 
Status: Open  


==References:==
==References:==
1.
: 1. TVA letter to NRC, dated May 10, 1991, Action Plan to Disposition Concerns Related to Units 1 and 3 Cable Installation Issues Including Cable Separations
TVA letter to NRC, dated May 10, 1991, Action Plan to Disposition Concerns Related to Units 1  
: 2. NRC letter to TVA, dated April 8, 1992, Safety Evaluation of TVA Plans to Resolve Electrical Cable Installation and Separation Issues April 13, 2007                   E1-34
 
and 3 Cable Installation Issues Including Cable  
 
Separations
: 2. NRC letter to TVA, dated April 8, 1992, Safety Evaluation of TVA Plans to Resolve Electrical  
 
Cable Installation and Separation Issues  
 
April 13, 2007 E1-35 Cable Splices
 
Commitment: TVA will identify Class IE cable splices located in harsh environment and ensure they are qualified for
 
their intended service during a design basis
 
accident (DBA).
 
Discussion: TVA's program to resolve the splice issue was submitted in Reference 1. TVA performed a field
 
walkdown of safety-related conduits to identify and
 
document Class 1E cable splices which are required


to be environmentally qualified and to verify the  
Cable Splices Commitment:  TVA will identify Class IE cable splices located in harsh environment and ensure they are qualified for their intended service during a design basis accident (DBA).
 
Discussion:  TVAs program to resolve the splice issue was submitted in Reference 1. TVA performed a field walkdown of safety-related conduits to identify and document Class 1E cable splices which are required to be environmentally qualified and to verify the installed splice configuration. The field data was evaluated against construction specification requirements to determine which splices require rework. Actions were taken to either rework the splice or rework both the splice and raceway system to accommodate a qualified splice.
installed splice configuration. The field data was  
Status:       Complete
 
evaluated against construction specification  
 
requirements to determine which splices require  
 
rework. Actions were taken to either rework the  
 
splice or rework both the splice and raceway system  
 
to accommodate a qualified splice.  
 
Status: Complete  


==References:==
==References:==
1.
: 1. TVA letter to NRC, dated April 28, 1988, Browns Ferry Nuclear Plant (BFN) - Electrical Issues (NRC TAC No. 62260)
TVA letter to NRC, dated April 28, 1988, Browns Ferry Nuclear Plant (BFN) - Electrical Issues (NRC TAC No. 62260)  
April 13, 2007                  E1-35


April 13, 2007 E1-36 Cable Tray Supports  
Cable Tray Supports Commitment:   TVA intends to utilize the Seismic Qualification Utility Group (SQUG) Generic Implementation Procedure (GIP) for seismic qualification of cable trays.
 
Discussion:   The original action plan to disposition concerns related to Unit 1 cable tray supports was provided in Reference 1. However, due to the issuance of Supplement 1 to Generic Letter 87-02, Verification of Seismic Adequacy of Mechanical and Electrical Equipment in Operating Reactors, Unresolved Safety Issue (USI) A-46, BFN submitted a revised program in order to take advantage of the NRC approved process for resolving USI A-46 (Reference 2). NRC accepted the schedule for implementing the revised program for Unit 1 in Reference 3 and requested additional information regarding the revised methodology and criteria. This information was provided in Reference 4 and accepted by NRC in Reference 5.
Commitment: TVA intends to utilize the Seismic Qualification Utility Group (SQUG) Generic Implementation  
Status:       C-C The Unit 1 cable tray supports have been evaluated utilizing the GIP in accordance with USI A-46. A summary report was provided to NRC in Reference 6.
 
Necessary modifications and repairs have been completed.
Procedure (GIP) for seismic qualification of cable  
NRC closed this item in document dated March 9, 2007 (Reference 7).
 
trays.
Discussion: The original action plan to disposition concerns related to Unit 1 cable tray supports was provided  
 
in Reference 1. However, due to the issuance of  
 
Supplement 1 to Generic Letter 87-02, Verification  
 
of Seismic Adequacy of Mechanical and Electrical  
 
Equipment in Operating Reactors, Unresolved Safety  
 
Issue (USI) A-46, BFN submitted a revised program  
 
in order to take advantage of the NRC approved  
 
process for resolving USI A-46 (Reference 2). NRC  
 
accepted the schedule for implementing the revised  
 
program for Unit 1 in Reference 3 and requested  
 
additional information regarding the revised  
 
methodology and criteria. This information was  
 
provided in Reference 4 and accepted by NRC in  
 
Reference 5.  
 
Status: C-C  
 
The Unit 1 cable tray supports have been evaluated  
 
utilizing the GIP in accordance with USI A-46. A  
 
summary report was provided to NRC in Reference 6.  
 
Necessary modifications and repairs have been  
 
completed.  
 
NRC closed this item in document dated
 
March 9, 2007 (Reference 7).  


==References:==
==References:==
1.
: 1. TVA letter to NRC, dated March 27, 1991, Action Plan to Disposition Concerns Related to Units 1 and 3 Cable Tray Supports
TVA letter to NRC, dated March 27, 1991, Action Plan to Disposition Concerns Related to Units 1  
: 2. TVA letter to NRC, dated September 21, 1992, Supplement 1 to Generic Letter 87-02, Verification of Seismic Adequacy of Mechanical and Electrical Equipment in Operating Reactors, Unresolved Safety Issue (USI) A-46 and Supplement 4 to Generic Letter 88-20, Individual Plant Examination of External Events (IPEEE) for Severe Accident Vulnerabilities
: 3. NRC letter to TVA, dated November 19, 1992, Generic Letter 87-02, Supplement 1 Response -
Browns Ferry Nuclear Plant April 13, 2007                  E1-36
: 4. TVA letter to NRC, dated January 19, 1993, Generic Letter (GL) 87-02, Supplement 1, 120-Day Response, Request for Additional Information
: 5. NRC letter to TVA, dated March 19, 1993, Generic Letter 87-02, Supplement 1 Response - Browns Ferry Nuclear Plant
: 6. TVA letter to NRC, dated October 7, 2004, Browns Ferry Nuclear Plant (BFN) Unit 1 - Response to NRC Generic Letter (GL) 87-02, Supplement 1 that Transmits Supplemental Safety Evaluation Report No. 2 (SSER No. 2) on SQUG Generic Implementation Procedure, Revision 2, as corrected on February 14, 1992 (GIP-2)
: 7. NRC Meeting Summary dated March 9, 2007, Meeting Summary - Internal Meeting of the Browns Ferry Unit 1 Restart Panel - Docket No.
50-259 April 13, 2007                  E1-37


and 3 Cable Tray Supports
Component and Piece Part Qualification Commitment:   TVA will implement a component and piece part qualification program.
: 2. TVA letter to NRC, dated September 21, 1992, Supplement 1 to Generic Letter 87-02, Verification of Seismic Adequacy of Mechanical
Discussion:   In Reference 1, TVA provided a change in methodology in performing the component and piece part qualification for safety-related components in 10 CFR 50.49 applications. TVA proposed to use statistical sampling techniques to achieve a 95/95 confidence level of qualification adequacy as opposed to the 100% verification performed for Unit 2. Additional information was requested by the NRC Staff in Reference 2, which was provided by TVA in Reference 3. In Reference 4, NRC responded that this issue would be addressed by inspection rather than a revision to the Safety Evaluation.
 
Since this correspondence, TVA decided to perform a 100% verification as performed on Unit 2.
and Electrical Equipment in Operating Reactors, Unresolved Safety Issue (USI) A-46 and
Status:       Complete The Unit 1 component and piece part qualification program for safety-related components in 10 CFR 50.49 applications has been implemented.
 
Supplement 4 to Generic Letter 88-20, Individual
 
Plant Examination of External Events (IPEEE) for
 
Severe Accident Vulnerabilities
: 3. NRC letter to TVA, dated November 19, 1992, Generic Letter 87-02, Supplement 1 Response -
 
Browns Ferry Nuclear Plant April 13, 2007 E1-37
: 4. TVA letter to NRC, dated January 19, 1993, Generic Letter (GL) 87-02, Supplement 1, 120-Day
 
Response, Request for Additional Information
: 5. NRC letter to TVA, dated March 19, 1993, Generic Letter 87-02, Supplement 1 Response - Browns
 
Ferry Nuclear Plant
: 6. TVA letter to NRC, dated October 7, 2004, Browns Ferry Nuclear Plant (BFN) Unit 1 - Response to
 
NRC Generic Letter (GL) 87-02, Supplement 1 that
 
Transmits Supplemental Safety Evaluation Report
 
No. 2 (SSER No. 2) on SQUG Generic
 
Implementation Procedure, Revision 2, as
 
corrected on February 14, 1992 (GIP-2)
: 7. NRC Meeting Summary dated March 9, 2007, "Meeting Summary - Internal Meeting of the
 
Browns Ferry Unit 1 Restart Panel - Docket No.
 
50-259" April 13, 2007 E1-38 Component and Piece Part Qualification  
 
Commitment: TVA will implement a component and piece part qualification program.  
 
Discussion: In Reference 1, TVA provided a change in methodology in performing the component and piece  
 
part qualification for safety-related components in  
 
10 CFR 50.49 applications. TVA proposed to use  
 
statistical sampling techniques to achieve a 95/95  
 
confidence level of qualification adequacy as  
 
opposed to the 100% verification performed for
 
Unit 2. Additional information was requested by  
 
the NRC Staff in Reference 2, which was provided by  
 
TVA in Reference 3. In Reference 4, NRC responded  
 
that this issue would be addressed by inspection  
 
rather than a revision to the Safety Evaluation.  
 
Since this correspondence, TVA decided to perform  
 
a 100% verification as performed on Unit 2.  
 
Status: Complete  
 
The Unit 1 component and piece part qualification  
 
program for safety-related components in
 
10 CFR 50.49 applications has been implemented.  


==References:==
==References:==
1.
: 1. TVA letter to NRC, dated June 12, 1992, Request for Revision to Safety Evaluation Issued by NRC on January 10, 1990, Related to Component and Piece Part Qualification Plan
TVA letter to NRC, dated June 12, 1992, Request for Revision to Safety Evaluation Issued by NRC  
: 2. NRC letter to TVA, dated October 29, 1992, Request for Additional Information Regarding Browns Ferry Nuclear Plant Units 1 and 3 Component and Piece Parts Qualification Program
: 3. TVA letter to NRC, dated December 17, 1992, Request for Additional Information (RAI)
Regarding BFN Units 1 and 3 Component and Piece Parts Qualification Plan
: 4. NRC letter to TVA, dated December 7, 1993, Browns Ferry Nuclear Plant Units 1 and 3 Component and Piece Parts Qualification Program April 13, 2007                  E1-38


on January 10, 1990, Related to Component and
Conduit Supports Commitment:   TVA intends to utilize the Seismic Qualification Utility Group (SQUG) Generic Implementation Procedure (GIP) for seismic qualification of conduit supports.
 
Discussion:   The original action plan to disposition concerns related to Unit 1 conduits and conduit supports was provided in References 1 through 3 and approved in Reference 4. However, due to the issuance of Supplement 1 to Generic Letter 87-02, Verification of Seismic Adequacy of Mechanical and Electrical Equipment in Operating Reactors, Unresolved Safety Issue (USI) A-46, BFN submitted a revised program in order to take advantage of the NRC approved process for resolving USI A-46 (Reference 5). NRC requested additional information regarding the schedule for implementing the revised program in Reference 6.
Piece Part Qualification Plan
In Reference 7, TVA committed to implement the long-term qualification of conduits and conduit supports prior to Unit 1 restart. In Reference 8, NRC determined that it was acceptable for TVA to complete the portion of its USI A-46 program that pertain to conduits and conduit supports, prior to Unit 1 restart in lieu of its prior restart commitments.
: 2. NRC letter to TVA, dated October 29, 1992, Request for Additional Information Regarding
Status:       C-C The Unit 1 conduit supports have been evaluated utilizing the GIP in accordance with USI A-46.
 
A summary report was provided to NRC in Reference 9. Necessary modifications and repairs have been completed.
Browns Ferry Nuclear Plant Units 1 and 3
NRC closed this item in document dated March 9, 2007 (Reference 10).
 
Component and Piece Parts Qualification Program
: 3. TVA letter to NRC, dated December 17, 1992, Request for Additional Information (RAI)
 
Regarding BFN Units 1 and 3 Component and Piece
 
Parts Qualification Plan
: 4. NRC letter to TVA, dated December 7, 1993, Browns Ferry Nuclear Plant Units 1 and 3
 
Component and Piece Parts Qualification Program
 
April 13, 2007 E1-39 Conduit Supports  
 
Commitment: TVA intends to utilize the Seismic Qualification Utility Group (SQUG) Generic Implementation  
 
Procedure (GIP) for seismic qualification of  
 
conduit supports.  
 
Discussion: The original action plan to disposition concerns related to Unit 1 conduits and conduit supports was  
 
provided in References 1 through 3 and approved in  
 
Reference 4. However, due to the issuance of  
 
Supplement 1 to Generic Letter 87-02, Verification  
 
of Seismic Adequacy of Mechanical and Electrical  
 
Equipment in Operating Reactors, Unresolved Safety  
 
Issue (USI) A-46, BFN submitted a revised program  
 
in order to take advantage of the NRC approved  
 
process for resolving USI A-46 (Reference 5). NRC  
 
requested additional information regarding the  
 
schedule for implementing the revised program in  
 
Reference 6.  
 
In Reference 7, TVA committed to implement the  
 
long-term qualification of conduits and conduit  
 
supports prior to Unit 1 restart. In Reference 8, NRC determined that it was acceptable for TVA to  
 
complete the portion of its USI A-46 program that  
 
pertain to conduits and conduit supports, prior to  
 
Unit 1 restart in lieu of its prior restart  
 
commitments.  
 
Status: C-C  
 
The Unit 1 conduit supports have been evaluated  
 
utilizing the GIP in accordance with USI A-46.  
 
A summary report was provided to NRC in  
 
Reference 9. Necessary modifications and repairs  
 
have been completed.  
 
NRC closed this item in document dated
 
March 9, 2007 (Reference 10).  


==References:==
==References:==
1.
: 1. TVA letter to NRC, dated May 6, 1991, Program for Resolving Conduit and Conduit Supports Issue Prior to the Restart of Units 1 and 3
TVA letter to NRC, dated May 6, 1991, Program for Resolving Conduit and Conduit Supports Issue  
: 2. TVA letter to NRC, dated December 12, 1991, Small Bore Piping Program, Tubing, and Conduit Support Plans for Units 1 and 3 - Additional Information April 13, 2007                   E1-39
 
: 3. TVA letter to NRC, dated January 29, 1992, Action Plan to Disposition Concerns Related to Units 1 and 3 Conduit and Conduit Support -
Prior to the Restart of Units 1 and 3
: 2. TVA letter to NRC, dated December 12, 1991, Small Bore Piping Program, Tubing, and Conduit  
 
Support Plans for Units 1 and 3 - Additional  
 
Information April 13, 2007 E1-40
: 3. TVA letter to NRC, dated January 29, 1992, Action Plan to Disposition Concerns Related to  
 
Units 1 and 3 Conduit and Conduit Support -  
 
Additional Information
Additional Information
: 4. NRC letter to TVA, dated March 20, 1992, Safety Evaluation of Action Plan to Resolve Conduit and  
: 4. NRC letter to TVA, dated March 20, 1992, Safety Evaluation of Action Plan to Resolve Conduit and Conduit Supports Issues for the Browns Ferry Nuclear Plant Units 1 and 3
 
: 5. TVA letter to NRC, dated September 21, 1992, Supplement 1 to Generic Letter 87-02, Verification of Seismic Adequacy of Mechanical and Electrical Equipment in Operating Reactors, Unresolved Safety Issue (USI) A-46 and Supplement 4 to Generic Letter 88-20, Individual Plant Examination of External Events (IPEEE) for Severe Accident Vulnerabilities
Conduit Supports Issues for the Browns Ferry  
: 6. NRC letter to TVA, dated November 19, 1992, Generic Letter 87-02, Supplement 1 Response -
 
Nuclear Plant Units 1 and 3
: 5. TVA letter to NRC, dated September 21, 1992, Supplement 1 to Generic Letter 87-02, Verification of Seismic Adequacy of Mechanical  
 
and Electrical Equipment in Operating Reactors, Unresolved Safety Issue (USI) A-46 and  
 
Supplement 4 to Generic Letter 88-20, Individual  
 
Plant Examination of External Events (IPEEE) for  
 
Severe Accident Vulnerabilities
: 6. NRC letter to TVA, dated November 19, 1992, Generic Letter 87-02, Supplement 1 Response -  
 
Browns Ferry Nuclear Plant
Browns Ferry Nuclear Plant
: 7. TVA letter to NRC, dated January 19, 1993, Generic Letter (GL) 87-02, Supplement 1, 120-Day  
: 7. TVA letter to NRC, dated January 19, 1993, Generic Letter (GL) 87-02, Supplement 1, 120-Day Response, Request for Additional Information
 
: 8. NRC letter to TVA, dated March 19, 1993, Generic Letter 87-02, Supplement 1 Response - Browns Ferry Nuclear Plant
Response, Request for Additional Information
: 9. TVA letter to NRC, dated October 7, 2004, Browns Ferry Nuclear Plant (BFN) Unit 1 - Response to NRC Generic Letter (GL) 87-02, Supplement 1 that Transmits Supplemental Safety Evaluation Report No. 2 (SSER No. 2) on SQUG Generic Implementation Procedure, Revision 2, as corrected on February 14, 1992 (GIP-2)
: 8. NRC letter to TVA, dated March 19, 1993, Generic Letter 87-02, Supplement 1 Response - Browns  
: 10. NRC Meeting Summary dated March 9, 2007, Meeting Summary - Internal Meeting of the Browns Ferry Unit 1 Restart Panel - Docket No.
 
50-259 April 13, 2007                 E1-40
Ferry Nuclear Plant
: 9. TVA letter to NRC, dated October 7, 2004, Browns Ferry Nuclear Plant (BFN) Unit 1 - Response to  
 
NRC Generic Letter (GL) 87-02, Supplement 1 that  
 
Transmits Supplemental Safety Evaluation Report  
 
No. 2 (SSER No. 2) on SQUG Generic  
 
Implementation Procedure, Revision 2, as  
 
corrected on February 14, 1992 (GIP-2) 1 0. NRC Meeting Summary dated March 9, 2007, "Meeting Summary - Internal Meeting of the  
 
Browns Ferry Unit 1 Restart Panel - Docket No.  
 
50-259" April 13, 2007 E1-41 Configuration Management/Design Baseline
 
Commitment: The Unit 1 Design Baseline Verification Program (DBVP) will consolidate the two-phase (pre- and
 
post-restart) approach performed on Unit 2.
 
Discussion: The objective of the DBVP was to re-establish the design basis and evaluate the plant configuration
 
to ensure that it satisfies the design basis. The
 
DBVP, including a discussion of lessons learned
 
from the Unit 2 precedent, was provided in
 
Reference 1. In Reference 2, NRC determined that
 
this commitment was more comprehensive than that
 
accepted by the staff for Unit 2, and was therefore
 
acceptable.


Status: C-C  
Configuration Management/Design Baseline Commitment:  The Unit 1 Design Baseline Verification Program (DBVP) will consolidate the two-phase (pre- and post-restart) approach performed on Unit 2.
 
Discussion:  The objective of the DBVP was to re-establish the design basis and evaluate the plant configuration to ensure that it satisfies the design basis. The DBVP, including a discussion of lessons learned from the Unit 2 precedent, was provided in Reference 1. In Reference 2, NRC determined that this commitment was more comprehensive than that accepted by the staff for Unit 2, and was therefore acceptable.
Unit 1 satisfies its design basis, safety related  
Status:       C-C Unit 1 satisfies its design basis, safety related structures, systems, and components are supported by engineering analysis and documentation, and the plant configuration is in conformance with TVAs commitments.
 
NRC closed this item in document dated March 9, 2007 (Reference 3).
structures, systems, and components are supported  
 
by engineering analysis and documentation, and the  
 
plant configuration is in conformance with TVA's
 
commitments.  
 
NRC closed this item in document dated
 
March 9, 2007 (Reference 3).  


==References:==
==References:==
1.
: 1. TVA letter to NRC, dated June 13, 1991, Design Baseline Verification Program (DBVP)
TVA letter to NRC, dated June 13, 1991, Design Baseline Verification Program (DBVP)
: 2. NRC letter to TVA, dated November 21, 1991, Assessment of Browns Ferry Nuclear Plant, Units 1 and 3 Design Baseline Verification Program
: 2. NRC letter to TVA, dated November 21, 1991, Assessment of Browns Ferry Nuclear Plant, Units 1 and 3 Design Baseline Verification  
: 3. NRC Meeting Summary dated March 9, 2007, Meeting Summary - Internal Meeting of the Browns Ferry Unit 1 Restart Panel - Docket No.
50-259 April 13, 2007                  E1-41


Program 3. NRC Meeting Summary dated March 9, 2007, "Meeting Summary - Internal Meeting of the
Containment Coatings Commitment:   The containment coating program will be implemented in accordance with the Unit 2 precedent.
 
Discussion:   The containment coatings program was described in the Nuclear Performance Plan (Reference 1). TVA performed walkdown inspections of unqualified coating on components installed inside primary containment on Unit 2 to baseline the uncontrolled coating log. An analysis was performed to determine the maximum allowable quantity of coating debris which could be transported to the suction strainers without affecting the ability of the ECCS pumps to perform their post-Loss of Coolant Accident (LOCA) function. Corrective actions were taken to ensure that the amount of unqualified coating is maintained below the maximum allowable quantity. NRC approval of the program is documented in Reference 2.
Browns Ferry Unit 1 Restart Panel - Docket No.
Status:       Complete The containment coatings program was completed, and the Uncontrolled Coatings Log was issued.
 
50-259" April 13, 2007 E1-42 Containment Coatings  
 
Commitment: The containment coating program will be implemented in accordance with the Unit 2 precedent.  
 
Discussion: The containment coatings program was described in the Nuclear Performance Plan (Reference 1). TVA  
 
performed walkdown inspections of unqualified  
 
coating on components installed inside primary  
 
containment on Unit 2 to baseline the uncontrolled  
 
coating log. An analysis was performed to  
 
determine the maximum allowable quantity of coating  
 
debris which could be transported to the suction  
 
strainers without affecting the ability of the ECCS  
 
pumps to perform their post-Loss of Coolant  
 
Accident (LOCA) function. Corrective actions were  
 
taken to ensure that the amount of unqualified  
 
coating is maintained below the maximum allowable  
 
quantity. NRC approval of the program is  
 
documented in Reference 2.  
 
Status: Complete  
 
The containment coatings program was completed, and  
 
the Uncontrolled Coatings Log was issued.  


==References:==
==References:==
1.
: 1. TVA letter to NRC, dated October 24, 1988, Browns Ferry Nuclear Plant (BFN) - Nuclear Performance Plan, Revision 2
TVA letter to NRC, dated October 24, 1988, Browns Ferry Nuclear Plant (BFN) - Nuclear  
: 2. NRC letter to TVA, dated January 23, 1991, NUREG-1232, Volume 3, Supplement 2 - Browns Ferry, Unit 2, Section 3.7 (Page 3-7)
 
April 13, 2007                 E1-42
Performance Plan, Revision 2
: 2. NRC letter to TVA, dated January 23, 1991, NUREG-1232, Volume 3, Supplement 2 - Browns  
 
Ferry, Unit 2, Section 3.7 (Page 3-7)  
 
April 13, 2007 E1-43 Control Rod Drive (CRD) Insert and Withdrawal Piping
 
Commitment: The seismic qualification of the CRD insert and withdrawal piping will be implemented in accordance
 
with the Unit 2 precedent.
 
Discussion: TVA's program for the seismic qualification of the 185 CRD insert and withdrawal lines on Unit 2 was


provided in Reference 1 and approved by NRC in  
Control Rod Drive (CRD) Insert and Withdrawal Piping Commitment:  The seismic qualification of the CRD insert and withdrawal piping will be implemented in accordance with the Unit 2 precedent.
 
Discussion:  TVA's program for the seismic qualification of the 185 CRD insert and withdrawal lines on Unit 2 was provided in Reference 1 and approved by NRC in Reference 2.
Reference 2.  
Status:       C-C Based on reanalysis, pipe supports for CRD insert and withdrawal piping were replaced with new support frames.
 
NRC closed this item in document dated March 9, 2007 (Reference 3).
Status: C-C  
 
Based on reanalysis, pipe supports for CRD insert  
 
and withdrawal piping were replaced with new  
 
support frames.  
 
NRC closed this item in document dated
 
March 9, 2007 (Reference 3).  


==References:==
==References:==
1.
: 1. TVA letter to NRC, dated December 11, 1989, Revised Program Plan - Seismic Qualification of the Control Rod Drive Hydraulic (CRDH) Piping System
TVA letter to NRC, dated December 11, 1989, Revised Program Plan - Seismic Qualification of  
: 2. NRC letter to TVA, dated January 23, 1991, NUREG-1232, Volume 3, Supplement 2 -
 
the Control Rod Drive Hydraulic (CRDH) Piping  
 
System 2. NRC letter to TVA, dated January 23, 1991, NUREG-1232, Volume 3, Supplement 2 -
 
Browns Ferry, Unit 2, Section 2.2.3.2 (Page 2-9)
Browns Ferry, Unit 2, Section 2.2.3.2 (Page 2-9)
: 3. NRC Meeting Summary dated March 9, 2007, "Meeting Summary - Internal Meeting of the  
: 3. NRC Meeting Summary dated March 9, 2007, Meeting Summary - Internal Meeting of the Browns Ferry Unit 1 Restart Panel - Docket No.
50-259 April 13, 2007                  E1-43


Browns Ferry Unit 1 Restart Panel - Docket No.
Design Calculation Review Issue:       Complete a design calculation review.
 
Discussion:   The objective of the design calculation review was to:
50-259" April 13, 2007 E1-44 Design Calculation Review  
: a. Identify calculations considered to be essential;
 
: b. Ensure that essential calculations support the plant licensing commitments and design basis requirements;
Issue: Complete a design calculation review.  
: c. Ensure that essential calculations are technically adequate and consistent with the plant configuration; and
 
: d. Ensure that essential calculations supporting the Design Baseline and Verification Program (DBVP) are consistent with the plant functional configuration.
Discussion: The objective of the design calculation review was to: a. Identify calculations considered to be essential;
Status:       C-C The design calculation review was incorporated into the Configuration Management / Design Baseline Verification Program in Reference 1.
: b. Ensure that essential calculations support the plant licensing commitments and design basis  
NRC closed this item in document dated March 9, 2007 (Reference 2).
 
requirements;
: c. Ensure that essential calculations are technically adequate and consistent with the  
 
plant configuration; and
: d. Ensure that essential calculations supporting the Design Baseline and Verification Program (DBVP) are consistent with the plant functional  
 
configuration.  
 
Status: C-C  
 
The design calculation review was incorporated into  
 
the Configuration Management / Design Baseline  
 
Verification Program in Reference 1.  
 
NRC closed this item in document dated
 
March 9, 2007 (Reference 2).  


==References:==
==References:==
1.
: 1. TVA letter to NRC, dated June 13, 1991, Design Baseline Verification Program (DBVP)
TVA letter to NRC, dated June 13, 1991, Design Baseline Verification Program (DBVP)
: 2. NRC Meeting Summary dated March 9, 2007, Meeting Summary - Internal Meeting of the Browns Ferry Unit 1 Restart Panel - Docket No.
: 2. NRC Meeting Summary dated March 9, 2007, "Meeting Summary - Internal Meeting of the  
50-259 April 13, 2007                   E1-44
 
Browns Ferry Unit 1 Restart Panel - Docket No.  
 
50-259" April 13, 2007 E1-45 Environmental Qualification
 
Commitment: TVA will complete the qualification of Class IE safety-related equipment.
 
Discussion: The qualification of Class IE safety-related equipment will be accomplished when BFN certifies
 
compliance with 10 CFR 50.49, Environmental
 
qualification of electric equipment important to
 
safety for nuclear power plants.


Status: Open  
Environmental Qualification Commitment:  TVA will complete the qualification of Class IE safety-related equipment.
Discussion:  The qualification of Class IE safety-related equipment will be accomplished when BFN certifies compliance with 10 CFR 50.49, Environmental qualification of electric equipment important to safety for nuclear power plants.
Status:       Open


==References:==
==References:==
None  
None April 13, 2007                  E1-45


April 13, 2007 E1-46 Fire Protection / 10 CFR 50, Appendix R  
Fire Protection / 10 CFR 50, Appendix R Commitment:   TVA will comply with License Condition 2.C(13).
 
Discussion:   License Condition 2.C(13) states:
Commitment: TVA will comply with License Condition 2.C(13).  
Browns Ferry Nuclear Plant shall implement and maintain in effect all provisions of the approved Fire Protection Program as described in the Final Safety Analysis Report for BFN as approved in the SEs dated December 8, 1988, March 6, 1991, March 31, 1993, November 2, 1995 and Supplement dated November 3, 1989 subject to the following provision:
 
The licensee may make changes to the approved fire protection program without prior approval of the Commission only if those changes would not adversely affect the ability to achieve and maintain safe shutdown in the event of a fire.
Discussion: License Condition 2.C(13) states:  
NRC issued its Safety Evaluation Report (SER) for BFNs Safe Shutdown Analysis in Reference 1 and approved the associated License Amendment in Reference 2. The SER for the BFN Fire Protection Plan and Fire Hazards Analysis was provided in Reference 3. The NRC staff issued a License amendment for the 10 CFR 50, Appendix R Post-fire Safe Shutdown Program in Reference 4 and issued a supplemental Safety Evaluation in Reference 5.
"Browns Ferry Nuclear Plant shall implement  
As requested by the NRC in a letter to TVA dated September 21, 2006 (Reference 6), TVA will notify the NRC of each of the following items:
 
: 1. TVA, in its letter of April 24, 2006 (Reference 7), committed to identify the Appendix R, Paragraph III.G.2, noncompliances involving operator manual actions, to place them into TVAs corrective action program, and to implement compensatory measures. Therefore, TVA should complete the commitments made in its April 24, 2006, letter, as well as any other restart related commitments made previously to the NRC regarding post-fire operator manual actions.
and maintain in effect all provisions of the  
April 13, 2007                 E1-46
 
: 2. Safe Shutdown Instructions used to direct those actions needed to bring the unit to safe shutdown in the event of a fire will be completed by January 1, 2007.
approved Fire Protection Program as described  
: 3. Concerning the Unit 1 safe-shutdown analysis design assumptions.
 
Status:       Open
in the Final Safety Analysis Report for BFN  
 
as approved in the SEs dated December 8, 1988, March 6, 1991, March 31, 1993, November 2, 1995 and Supplement dated  
 
November 3, 1989 subject to the following  
 
provision:
The licensee may make changes to the  
 
approved fire protection program  
 
without prior approval of the  
 
Commission only if those changes would  
 
not adversely affect the ability to  
 
achieve and maintain safe shutdown in  
 
the event of a fire."
 
NRC issued its Safety Evaluation Report (SER) for  
 
BFN's Safe Shutdown Analysis in Reference 1 and  
 
approved the associated License Amendment in  
 
Reference 2. The SER for the BFN Fire Protection  
 
Plan and Fire Hazards Analysis was provided in  
 
Reference 3. The NRC staff issued a License  
 
amendment for the 10 CFR 50, Appendix R Post-fire  
 
Safe Shutdown Program in Reference 4 and issued a  
 
supplemental Safety Evaluation in Reference 5.  
--------------------------------
 
As requested by the NRC in a letter to TVA dated September 21, 2006 (Reference 6), TVA will notify  
 
the NRC of each of the following items:
: 1. TVA, in its letter of April 24, 2006 (Reference 7), committed to identify the  
 
Appendix R, Paragraph III.G.2, noncompliances  
 
involving operator manual actions, to place them  
 
into TVA's corrective action program, and to  
 
implement compensatory measures. Therefore, TVA  
 
should complete the commitments made in its  
 
April 24, 2006, letter, as well as any other  
 
restart related commitments made previously to  
 
the NRC regarding post-fire operator manual  
 
actions.
April 13, 2007 E1-47
: 2. Safe Shutdown Instructions used to direct those actions needed to bring the unit to safe  
 
shutdown in the event of a fire will be  
 
completed by January 1, 2007.
: 3. Concerning the Unit 1 safe-shutdown analysis design assumptions.  
 
Status: Open  


==References:==
==References:==
1.
: 1. NRC letter to TVA, dated December 8, 1988, Units 1, 2 and 3 - Appendix R Safe Shutdown System Analysis (TAC 60627, 60628, 60629)
NRC letter to TVA, dated December 8, 1988, Units 1, 2 and 3 - Appendix R Safe Shutdown  
 
System Analysis (TAC 60627, 60628, 60629)
: 2. NRC letter to TVA, dated March 6, 1991, Issuance of Amendment (TAC No. 72965) (TS 268)
: 2. NRC letter to TVA, dated March 6, 1991, Issuance of Amendment (TAC No. 72965) (TS 268)
: 3. NRC letter to TVA, dated March 31, 1993, Fire Protection Program - Browns Ferry Nuclear Plant  
: 3. NRC letter to TVA, dated March 31, 1993, Fire Protection Program - Browns Ferry Nuclear Plant Units 1, 2 and 3 (TAC Nos. M82687, M82688 and M82689)
 
: 4. NRC letter to TVA, dated November 2, 1995, Safety Evaluation of Post-Fire Safe Shutdown Capability and Issuance of Technical Specification Amendments for the Browns Ferry Nuclear Plant Units 1, 2, and 3 (TAC Nos.
Units 1, 2 and 3 (TAC Nos. M82687, M82688 and  
 
M82689) 4. NRC letter to TVA, dated November 2, 1995, Safety Evaluation of Post-Fire Safe Shutdown  
 
Capability and Issuance of Technical  
 
Specification Amendments for the Browns Ferry  
 
Nuclear Plant Units 1, 2, and 3 (TAC Nos.  
 
M85254, N87900, M87901, and M87902) (TS 337)
M85254, N87900, M87901, and M87902) (TS 337)
: 5. NRC letter to TVA, dated November 3, 1989, Supplemental Safety Evaluation on Post-Fire Safe  
: 5. NRC letter to TVA, dated November 3, 1989, Supplemental Safety Evaluation on Post-Fire Safe Shutdown Systems and Final Review of the National Fire Protection Association Code Deviations - Browns Ferry Nuclear Plant, Unit 2 (TAC Nos. 72908 and 00459)
 
: 6. NRC letter to TVA, dated September 21, 2006, Browns Ferry Nuclear Plant, Unit 1 - Status of Fire Protection Program (TAC No. MC8826)
Shutdown Systems and Final Review of the  
: 7. TVA letter to NRC dated April 24, 2006, Browns Ferry Nuclear Plant (BFN) - Units 1, 2 and 3 -
 
Fire Protection Program - Post-Fire Operator Manual Actions April 13, 2007                 E1-47
National Fire Protection Association Code  
 
Deviations - Browns Ferry Nuclear Plant, Unit 2 (TAC Nos. 72908 and 00459)
: 6. NRC letter to TVA, dated September 21, 2006, Browns Ferry Nuclear Plant, Unit 1 - Status of  
 
Fire Protection Program (TAC No. MC8826)
: 7. TVA letter to NRC dated April 24, 2006, Browns Ferry Nuclear Plant (BFN) - Units 1, 2 and 3 -  
 
Fire Protection Program - Post-Fire Operator  
 
Manual Actions  
 
April 13, 2007 E1-48 Flexible Conduits
 
Commitment: Actions necessary to disposition flexible conduit concerns for the 10 CFR 50.49 equipment will be
 
completed prior to restart. Flexible conduits
 
attached to safety-related electrical equipment not


covered by 10 CFR 50.49 and within the scope of USI  
Flexible Conduits Commitment:  Actions necessary to disposition flexible conduit concerns for the 10 CFR 50.49 equipment will be completed prior to restart. Flexible conduits attached to safety-related electrical equipment not covered by 10 CFR 50.49 and within the scope of USI A-46 will be evaluated for seismic adequacy using BFNs A-46 program.
 
Discussion:   The program and schedule for the resolution of flexible conduit issues for Unit 1 has been provided to the NRC as part of the resolution of Generic Letter 87-02. In Reference 1, TVA provided a schedule for flexible conduits associated with the resolution of USI A-46. NRC requested additional information regarding the schedule in Reference 2. In Reference 3, TVA provided the schedule for completing flexible conduit concerns in two phases. Flexible conduits attached to electrical equipment covered by 10 CFR 50.49 would be resolved prior to restart of Unit 1. Seismic qualification of flexible conduit other than those connected to electrical equipment covered by 10 CFR 50.49 (i.e., important to safety, but in a mild environment) and within the scope of USI A-46 would be included as part of the resolution of USI A-46.
A-46 will be evaluated for seismic adequacy using  
In Reference 4, NRC found this program acceptable; however, additional information was requested regarding two separate issues regarding flexible conduit. TVA provided the requested information in Reference 5. Additional information was provided by TVA in Reference 6. NRC subsequently provided a supplemental safety evaluation in Reference 7.
 
Status:       Complete Safety related flexible conduits were evaluated.
BFN's A-46 program.  
Breakages (conduit failures) from this evaluation were resolved.
 
Discussion: The program and schedule for the resolution of flexible conduit issues for Unit 1 has been  
 
provided to the NRC as part of the resolution of  
 
Generic Letter 87-02. In Reference 1, TVA provided  
 
a schedule for flexible conduits associated with  
 
the resolution of USI A-46. NRC requested  
 
additional information regarding the schedule in  
 
Reference 2. In Reference 3, TVA provided the  
 
schedule for completing flexible conduit concerns  
 
in two phases. Flexible conduits attached to  
 
electrical equipment covered by 10 CFR 50.49 would  
 
be resolved prior to restart of Unit 1. Seismic  
 
qualification of flexible conduit other than those  
 
connected to electrical equipment covered by 10 CFR  
 
50.49 (i.e., important to safety, but in a mild  
 
environment) and within the scope of USI A-46 would  
 
be included as part of the resolution of USI A-46.  
 
In Reference 4, NRC found this program acceptable;  
 
however, additional information was requested  
 
regarding two separate issues regarding flexible  
 
conduit. TVA provided the requested information in  
 
Reference 5. Additional information was provided  
 
by TVA in Reference 6. NRC subsequently provided a  
 
supplemental safety evaluation in Reference 7.  
 
Status: Complete  
 
Safety related flexible conduits were evaluated.
 
Breakages (conduit failures) from this evaluation  
 
were resolved.  


==References:==
==References:==
1.
: 1. TVA letter to NRC, dated September 21, 1992, Supplement 1 to Generic Letter 87-02, Verification of Seismic Adequacy of Mechanical and Electrical Equipment in Operating Reactors, Unresolved Safety Issue (USI) A-46 and Supplement 4 to Generic Letter 88-20, Individual Plant Examination of External Events (IPEEE) for Severe Accident Vulnerabilities.
TVA letter to NRC, dated September 21, 1992, Supplement 1 to Generic Letter 87-02, Verification of Seismic Adequacy of Mechanical  
April 13, 2007                 E1-48
 
: 2. NRC letter to TVA, dated November 19, 1992, Generic Letter 87-02, Supplement 1 Response -
and Electrical Equipment in Operating Reactors, Unresolved Safety Issue (USI) A-46 and  
 
Supplement 4 to Generic Letter 88-20, Individual  
 
Plant Examination of External Events (IPEEE) for  
 
Severe Accident Vulnerabilities.
April 13, 2007 E1-49
: 2. NRC letter to TVA, dated November 19, 1992, Generic Letter 87-02, Supplement 1 Response -  
 
Browns Ferry Nuclear Plant
Browns Ferry Nuclear Plant
: 3. TVA letter to NRC, dated January 19, 1993, Generic Letter (GL) 87-02, Supplement 1, 120-Day  
: 3. TVA letter to NRC, dated January 19, 1993, Generic Letter (GL) 87-02, Supplement 1, 120-Day Response, Request for Additional Information
 
: 4. NRC letter to TVA, dated March 19, 1993, Generic Letter 87-02, Supplement 1 Response - Browns Ferry Nuclear Plant
Response, Request for Additional Information
: 5. TVA letter to NRC, dated October 15, 1993, Generic Letter (GL) 87-02, Supplement 1, Verification of Seismic Adequacy of Mechanical and Electrical Equipment in Operating Reactors, Unresolved Safety Issue (USI) A Response to Request for Additional Information Regarding the Evaluation of the Seismic Adequacy of Flexible Conduit
: 4. NRC letter to TVA, dated March 19, 1993, Generic Letter 87-02, Supplement 1 Response - Browns  
: 6. TVA letter to NRC, dated September 28, 1995, Browns Ferry Nuclear Plant (BFN)- Units 1, 2, and 3 - Seismic Adequacy of Flexible Conduits
 
: 7. NRC letter to TVA, dated October 3, 1995, Supplemental Safety Evaluation of Flexible Conduit Seismic Design and Installation Criteria April 13, 2007                 E1-49
Ferry Nuclear Plant
: 5. TVA letter to NRC, dated October 15, 1993, Generic Letter (GL) 87-02, Supplement 1, Verification of Seismic Adequacy of Mechanical  
 
and Electrical Equipment in Operating Reactors, Unresolved Safety Issue (USI) A Response to  
 
Request for Additional Information Regarding the  
 
Evaluation of the Seismic Adequacy of Flexible  
 
Conduit 6. TVA letter to NRC, dated September 28, 1995, Browns Ferry Nuclear Plant (BFN)- Units 1, 2,
 
and 3 - Seismic Adequacy of Flexible Conduits
: 7. NRC letter to TVA, dated October 3, 1995, Supplemental Safety Evaluation of Flexible  
 
Conduit Seismic Design and Installation Criteria  
 
April 13, 2007 E1-50 Fuses Commitment: The fuse issue will be resolved in accordance with the Unit 2 precedent.
 
Discussion: NRC approval of TVA's fuse program is documented in NUREG-1232 (Reference 1). The completion plan for
 
the fuse program was provided by Reference 2. TVA
 
has removed the reference to amperage from drawings
 
and replaced them with the appropriate unique
 
identifier for Class 1E fuses. TVA has installed
 
permanent fuse labeling.


Status: Complete  
Fuses Commitment:  The fuse issue will be resolved in accordance with the Unit 2 precedent.
Discussion:  NRC approval of TVA's fuse program is documented in NUREG-1232 (Reference 1). The completion plan for the fuse program was provided by Reference 2. TVA has removed the reference to amperage from drawings and replaced them with the appropriate unique identifier for Class 1E fuses. TVA has installed permanent fuse labeling.
Status:       Complete


==References:==
==References:==
1.
: 1. NRC letter to TVA, dated January 23, 1991, NUREG-1232, Volume 3, Supplement 2 - Browns Ferry, Unit 2, Section 3.11.2 (Page 3-9)
NRC letter to TVA, dated January 23, 1991, NUREG-1232, Volume 3, Supplement 2 - Browns  
: 2. TVA letter to NRC, dated January 29, 1992, Completion Plan for the Fuse Program April 13, 2007                 E1-50
 
Ferry, Unit 2, Section 3.11.2 (Page 3-9)
: 2. TVA letter to NRC, dated January 29, 1992, Completion Plan for the Fuse Program  
 
April 13, 2007 E1-51 Generic Letter 82-33, Instrumentation to Follow the Course of an Accident - Regulatory Guide 1.97 Commitment: TVA will complete Generic Letter 82-33.
 
Discussion: Supplement 1 to NUREG-0737, which included the request to review Regulatory Guide 1.97, was sent
 
to TVA in Generic Letter 82-33 (Reference 1). TVA
 
originally responded to Generic Letter 82-33 in
 
Reference 2.
 
TVA was ordered to submit a report to NRC
 
describing how the requirements of Supplement 1 to
 
NUREG-0737 have been or will be met and an
 
implementation schedule (Reference 3).
 
NRC requested additional information and/or
 
justification in Reference 4. TVA responded to
 
this request in Reference 5. TVA provided updated
 
information regarding Reactor Coolant System
 
pressure indication in Reference 6. A Safety
 
Evaluation Report (SER) was issued by NRC in
 
Reference 7. As part of this SER, TVA was directed
 
to qualify the instrumentation that measures seven
 
variables in accordance with 10 CFR 50.49. TVA
 
either provided additional justification or
 
committed to upgrade the instrumentation discussed
 
in the SER in Reference 8. A revised SER was
 
issued as part of the NRC's February 8, 1990 letter (Reference 9). This revised SER also directed TVA
 
to install a qualified neutron monitoring system. 
 
In Reference 10, TVA requested further BFN specific
 
actions regarding the neutron flux monitoring
 
instrumentation be deferred pending the resolution
 
of the BWR Owners' Group appeal.
 
In Reference 11, TVA identified previously
 
submitted deviation to Regulatory Guide 1.97 for
 
which NRC review was still required, addressed
 
discrepancies between TVA letters and NRC SERs, and
 
identified new deviations for NRC review. 
 
Additional information regarding emergency damper
 
position indication was provided by TVA in
 
Reference 12. The deviations addressed above were
 
addressed in the NRC's May 10, 1991, SER (Reference 13). In addition, implementation of
 
qualified neutron flux monitoring capability was
 
deferred pending review of an appeal by the BWR
 
Owners Group.
April 13, 2007 E1-52 A revised SER regarding neutron flux monitoring instrumentation was issued in Reference 14. TVA's
 
review of BFN's neutron flux monitoring


instrumentation against the criteria referenced by  
Generic Letter 82-33, Instrumentation to Follow the Course of an Accident - Regulatory Guide 1.97 Commitment:  TVA will complete Generic Letter 82-33.
Discussion:  Supplement 1 to NUREG-0737, which included the request to review Regulatory Guide 1.97, was sent to TVA in Generic Letter 82-33 (Reference 1). TVA originally responded to Generic Letter 82-33 in Reference 2.
TVA was ordered to submit a report to NRC describing how the requirements of Supplement 1 to NUREG-0737 have been or will be met and an implementation schedule (Reference 3).
NRC requested additional information and/or justification in Reference 4. TVA responded to this request in Reference 5. TVA provided updated information regarding Reactor Coolant System pressure indication in Reference 6. A Safety Evaluation Report (SER) was issued by NRC in Reference 7. As part of this SER, TVA was directed to qualify the instrumentation that measures seven variables in accordance with 10 CFR 50.49. TVA either provided additional justification or committed to upgrade the instrumentation discussed in the SER in Reference 8. A revised SER was issued as part of the NRC's February 8, 1990 letter (Reference 9). This revised SER also directed TVA to install a qualified neutron monitoring system.
In Reference 10, TVA requested further BFN specific actions regarding the neutron flux monitoring instrumentation be deferred pending the resolution of the BWR Owners' Group appeal.
In Reference 11, TVA identified previously submitted deviation to Regulatory Guide 1.97 for which NRC review was still required, addressed discrepancies between TVA letters and NRC SERs, and identified new deviations for NRC review.
Additional information regarding emergency damper position indication was provided by TVA in Reference 12. The deviations addressed above were addressed in the NRC's May 10, 1991, SER (Reference 13). In addition, implementation of qualified neutron flux monitoring capability was deferred pending review of an appeal by the BWR Owners Group.
April 13, 2007                  E1-51


the SER was provided in References 15 and 16. As  
A revised SER regarding neutron flux monitoring instrumentation was issued in Reference 14. TVA's review of BFNs neutron flux monitoring instrumentation against the criteria referenced by the SER was provided in References 15 and 16. As part of Reference 16, TVA committed to evaluate the neutron monitoring system cables, electrical penetrations and connectors for conformance to the criteria reference by the SER. This evaluation has been completed. Consistent with the conclusions reached for Units 2 and 3, the Unit 1 neutron monitoring system cables, electrical penetrations, and electrical connectors are capable of operating throughout the one hour duration of the ATWS event.
 
NRC acceptance of the deviation requested by TVA was documented in the May 3, 1994 SER (Reference 17).
part of Reference 16, TVA committed to evaluate the  
Status:       C-C TVA has replaced the subject instrumentation with qualified devices.
 
NRC closed this item in Inspection Report 2005-07 (Reference 18).
neutron monitoring system cables, electrical  
 
penetrations and connectors for conformance to the  
 
criteria reference by the SER. This evaluation has  
 
been completed. Consistent with the conclusions  
 
reached for Units 2 and 3, the Unit 1 neutron  
 
monitoring system cables, electrical penetrations, and electrical connectors are capable of operating  
 
throughout the one hour duration of the ATWS event.  
 
NRC acceptance of the deviation requested by TVA  
 
was documented in the May 3, 1994 SER (Reference 17).  
 
Status: C-C TVA has replaced the subject instrumentation with  
 
qualified devices.  
 
NRC closed this item in Inspection Report 2005-07 (Reference 18).  


==References:==
==References:==
1.
: 1. NRC letter to All Licensees of Operating Reactors, Applicants for Operating Licenses, and Holders of Construction Permits, dated December 17, 1982, Supplement 1 to NUREG-0737 -
NRC letter to All Licensees of Operating Reactors, Applicants for Operating Licenses, and  
 
Holders of Construction Permits, dated  
 
December 17, 1982, Supplement 1 to NUREG-0737 -  
 
Requirements for Emergency Response Capability (Generic Letter 82-33)
Requirements for Emergency Response Capability (Generic Letter 82-33)
: 2. TVA letter to NRC, dated April 30, 1984, in regards to Generic Letter 82-33
: 2. TVA letter to NRC, dated April 30, 1984, in regards to Generic Letter 82-33
: 3. NRC letter to TVA, dated June 12, 1984, Issuance of Orders Confirming Licensee Commitments on  
: 3. NRC letter to TVA, dated June 12, 1984, Issuance of Orders Confirming Licensee Commitments on Emergency Response Capability
 
: 4. NRC letter to TVA, dated January 23, 1985, Emergency Response Capability - Conformance to R.G. 1.97, Rev. 2
Emergency Response Capability
: 4. NRC letter to TVA, dated January 23, 1985, Emergency Response Capability - Conformance to  
 
R.G. 1.97, Rev. 2
: 5. TVA letter to NRC, dated May 7, 1985, in regards to conformance with Regulatory Guide 1.97
: 5. TVA letter to NRC, dated May 7, 1985, in regards to conformance with Regulatory Guide 1.97
: 6. TVA letter to NRC, dated November 20, 1985, in regards to conformance with Regulatory  
: 6. TVA letter to NRC, dated November 20, 1985, in regards to conformance with Regulatory Guide 1.97
 
: 7. NRC letter to TVA, date June 23, 1988, Generic Letter 82-33, Request for Compliance with the Guidelines of Regulatory Guide (R.G.) 1.97 as Applied to Emergency Response Facilities April 13, 2007                   E1-52
Guide 1.97
: 8. TVA letter to NRC, dated August 23, 1988, Response to NRC's Safety Evaluation Report on Regulatory Guide 1.97 as Applied to Emergency Response Facilities Dated June 23, 1988
: 7. NRC letter to TVA, date June 23, 1988, Generic Letter 82-33, Request for Compliance with the  
: 9. NRC letter to TVA, dated February 8, 1990, Emergency Response Capability - Conformance to Regulatory Guide 1.97. Revision 3
 
: 10. TVA letter to NRC, dated September 14, 1990, Response to NRC's February 8, 1990 Safety Evaluation Report Regarding Conformance to Regulatory Guide 1.97, Revision 3 - Neutron Flux Monitoring Instrumentation
Guidelines of Regulatory Guide (R.G.) 1.97 as  
: 11. TVA letter to NRC, dated October 15, 1990, Response to NRC Supplemental Safety Evaluation Report (SER) on Regulatory Guide (RG) 1.97 Compliance dated February 8, 1990
 
: 12. TVA letter to NRC, dated December 21, 1990, Regulatory Guide (RG) 1.97 Emergency Ventilation Dampers Position Indication
Applied to Emergency Response Facilities April 13, 2007 E1-53
: 13. NRC letter to TVA, dated May 10, 1991, Safety Evaluation of Emergency Response Capability -
: 8. TVA letter to NRC, dated August 23, 1988, Response to NRC's Safety Evaluation Report on  
Conformance to Regulatory Guide 1.97, Revision 3
: 14. NRC letter to TVA, dated May 27, 1993, Regulatory Guide 1.97 - Boiling Water Reactor Neutron Flux Monitoring
: 15. TVA letter to NRC, dated July 30, 1993, Regulatory Guide 1.97 - Boiling Water Reactor Neutron Flux Monitoring
: 16. TVA letter to NRC, dated March 10, 1994, Regulatory Guide 1.97 - Boiling Water Reactor Neutron Flux Monitoring
: 17. NRC letter to TVA, dated May 3, 1994, Boiling Water Reactor Neutron Flux Monitoring for the Browns Ferry Nuclear Plant
: 18. NRC letter to TVA, dated August 15, 2005, Browns Ferry Nuclear Plant Unit 1 Recovery - NRC Integrated Inspection Report 05000259/2005007 April 13, 2007                  E1-53


Regulatory Guide 1.97 as Applied to Emergency
Generic Letter 83-08, Modification of Vacuum Breakers on Mark I Containments Commitment:   TVA will modify the torus vacuum breakers.
 
Discussion:   TVA responded to the Generic Letter in Reference 1 and committed to modify the torus vacuum breakers.
Response Facilities Dated June 23, 1988
NRC requested additional information in Reference 2, which was provided by TVA in Reference 3. The NRC Safety Evaluation Report was issued in Reference 4. It concluded that TVAs actions would be adequate to restore the original design margin of safety for its vacuum breakers under the revised loadings in the Mark I containment.
: 9. NRC letter to TVA, dated February 8, 1990, Emergency Response Capability - Conformance to
Status:       C-C TVA modified the torus vacuum breakers.
 
NRC closed this item in Inspection Report 2005-006 (Reference 5).
Regulatory Guide 1.97. Revision 3 1 0. TVA letter to NRC, dated September 14, 1990, Response to NRC's February 8, 1990 Safety
 
Evaluation Report Regarding Conformance to
 
Regulatory Guide 1.97, Revision 3 - Neutron Flux
 
Monitoring Instrumentation 1 1. TVA letter to NRC, dated October 15, 1990, Response to NRC Supplemental Safety Evaluation
 
Report (SER) on Regulatory Guide (RG) 1.97
 
Compliance dated February 8, 1990 1 2. TVA letter to NRC, dated December 21, 1990, Regulatory Guide (RG) 1.97 Emergency Ventilation
 
Dampers Position Indication 1 3. NRC letter to TVA, dated May 10, 1991, Safety Evaluation of Emergency Response Capability -
 
Conformance to Regulatory Guide 1.97, Revision 3 1 4. NRC letter to TVA, dated May 27, 1993, Regulatory Guide 1.97 - Boiling Water Reactor
 
Neutron Flux Monitoring 1 5. TVA letter to NRC, dated July 30, 1993, Regulatory Guide 1.97 - Boiling Water Reactor
 
Neutron Flux Monitoring 1 6. TVA letter to NRC, dated March 10, 1994, Regulatory Guide 1.97 - Boiling Water Reactor
 
Neutron Flux Monitoring 1 7. NRC letter to TVA, dated May 3, 1994, Boiling Water Reactor Neutron Flux Monitoring for the
 
Browns Ferry Nuclear Plant 1 8. NRC letter to TVA, dated August 15, 2005, Browns Ferry Nuclear Plant Unit 1 Recovery - NRC
 
Integrated Inspection Report 05000259/2005007
 
April 13, 2007 E1-54 Generic Letter 83-08, Modification of Vacuum Breakers on Mark I Containments  
 
Commitment: TVA will modify the torus vacuum breakers.  
 
Discussion: TVA responded to the Generic Letter in Reference 1 and committed to modify the torus vacuum breakers.  
 
NRC requested additional information in  
 
Reference 2, which was provided by TVA in  
 
Reference 3. The NRC Safety Evaluation Report was  
 
issued in Reference 4. It concluded that TVA's
 
actions would be adequate to restore the original  
 
design margin of safety for its vacuum breakers  
 
under the revised loadings in the Mark I  
 
containment.  
 
Status: C-C  
 
TVA modified the torus vacuum breakers.  
 
NRC closed this item in Inspection Report 2005-006 (Reference 5).  


==References:==
==References:==
1.
: 1. TVA letter to NRC, dated November 5, 1984, in regards to Generic Letter 83-08
TVA letter to NRC, dated November 5, 1984, in regards to Generic Letter 83-08
: 2. NRC letter to TVA, dated January 17, 1986, Modification of Vacuum Breakers on Mark I Containments (Generic Letter 83-08)
: 2. NRC letter to TVA, dated January 17, 1986, Modification of Vacuum Breakers on Mark I  
 
Containments (Generic Letter 83-08)
: 3. TVA letter to NRC, dated April 7, 1986, in regards to Generic Letter 83-08
: 3. TVA letter to NRC, dated April 7, 1986, in regards to Generic Letter 83-08
: 4. NRC letter to TVA, dated November 25, 1986, Modification of Vacuum Breakers on Mark I  
: 4. NRC letter to TVA, dated November 25, 1986, Modification of Vacuum Breakers on Mark I Containments (Generic Letter 83-08); MPA D-20
 
: 5. NRC letter to TVA, dated May 16, 2005, Browns Ferry Nuclear Plant Unit 1 Recovery - NRC Integrated Inspection Report 05000259/2005006 April 13, 2007                   E1-54
Containments (Generic Letter 83-08); MPA D-20
: 5. NRC letter to TVA, dated May 16, 2005, Browns Ferry Nuclear Plant Unit 1 Recovery - NRC  
 
Integrated Inspection Report 05000259/2005006  
 
April 13, 2007 E1-55 Generic Letter 83-28, Salem ATWS, Item 1.2, Post Trip Review (Data and Information Capability)
 
Commitment: TVA will complete Generic Letter, Item 1.2.
 
Discussion: In response to Generic Letter 83-28, Item 1.2, TVA committed in Reference 1 to the installation of an


upgraded process computer and an enhanced sequence  
Generic Letter 83-28, Salem ATWS, Item 1.2, Post Trip Review (Data and Information Capability)
 
Commitment:  TVA will complete Generic Letter, Item 1.2.
of events recording capability. TVA's response was  
Discussion:  In response to Generic Letter 83-28, Item 1.2, TVA committed in Reference 1 to the installation of an upgraded process computer and an enhanced sequence of events recording capability. TVA's response was found to be acceptable in the NRC's Safety Evaluation provided by Reference 2.
 
As discussed in Reference 3, the Unit 2 equipment was replaced with more modern and sophisticated hardware, since the time of the original TVA submittal. The previously described upgrade to a Digital VAX 11/750 process computer system was accomplished using a Digital VAX 6000 system. The functions previously performed by the sequence of events and time history recorder are now accomplished using the process computer system.
found to be acceptable in the NRC's Safety  
However, the guidance contained in the Generic Letter and the requirements of the Safety Evaluation continue to be met.
 
Status:       Closed NRC closed this item in Inspection Report 2006-007 (Reference 4).
Evaluation provided by Reference 2.  
 
As discussed in Reference 3, the Unit 2 equipment  
 
was replaced with more modern and sophisticated  
 
hardware, since the time of the original TVA  
 
submittal. The previously described upgrade to a  
 
Digital VAX 11/750 process computer system was  
 
accomplished using a Digital VAX 6000 system. The  
 
functions previously performed by the sequence of  
 
events and time history recorder are now  
 
accomplished using the process computer system.
 
However, the guidance contained in the Generic  
 
Letter and the requirements of the Safety  
 
Evaluation continue to be met.  
 
Status: Closed  
 
NRC closed this item in Inspection Report 2006-007 (Reference 4).  


==References:==
==References:==
1.
: 1. TVA letter to NRC, dated November 7, 1983, in regards to Generic Letter 83-28
TVA letter to NRC, dated November 7, 1983, in regards to Generic Letter 83-28
: 2. NRC letter to TVA, dated June 12, 1985, Safety Evaluation for Generic Letter 83-28, Item 1.2, Post Trip Review (Data and Information Capability)
: 2. NRC letter to TVA, dated June 12, 1985, Safety Evaluation for Generic Letter 83-28, Item 1.2, Post Trip Review (Data and Information  
: 3. TVA letter to NRC, dated November 9, 1993, Completion of Unit 2 Commitment for Generic Letter 83-28, Item 1.2 - Post-Trip Review - Data and Information Capability (GSI 75 / MPA B-085)
 
: 4. NRC letter to TVA, dated August 10, 2006, Browns Ferry Nuclear Plant Unit 1 Recovery - NRC Integrated Inspection Report 05000259/2006007 April 13, 2007                  E1-55
Capability)
: 3. TVA letter to NRC, dated November 9, 1993, Completion of Unit 2 Commitment for Generic  
 
Letter 83-28, Item 1.2 - Post-Trip Review - Data  
 
and Information Capability (GSI 75 / MPA B-085)
: 4. NRC letter to TVA, dated August 10, 2006, Browns Ferry Nuclear Plant Unit 1 Recovery - NRC  


Integrated Inspection Report 05000259/2006007
Generic Letter 83-28, Salem ATWS, Item 4.5.2, Periodic On-Line Testing Commitment:   TVA will complete Generic Letter, Item 4.5.2.
 
Discussion:   The NRCs position on this item was that plants not currently designed to permit periodic on-line testing shall justify not making modifications to permit such testing. Alternatives to on-line testing proposed by licensees will be considered where special circumstances exist and where the objective of high reliability can be met in another way. TVAs initial response to this item (Reference 1) stated that on-line testing was being evaluated. A description of the Reactor Protection System (RPS) functional testing and reliability was provided by TVA in Reference 2.
April 13, 2007 E1-56 Generic Letter 83-28, Salem ATWS, Item 4.5.2, Periodic On-Line Testing Commitment: TVA will complete Generic Letter, Item 4.5.2.  
The NRC Safety Evaluation states the on-line testing capability of BFNs RPS meets the intent of this item and is therefore acceptable (Reference 3).
 
Status:       Closed NRC closed this item in Inspection Report 2006-007 (Reference 4).
Discussion: The NRC's position on this item was that plants not currently designed to permit periodic on-line  
 
testing shall justify not making modifications to  
 
permit such testing. Alternatives to on-line  
 
testing proposed by licensees will be considered  
 
where special circumstances exist and where the  
 
objective of high reliability can be met in another  
 
way. TVA's initial response to this item (Reference 1) stated that on-line testing was being  
 
evaluated. A description of the Reactor Protection  
 
System (RPS) functional testing and reliability was  
 
provided by TVA in Reference 2.  
 
The NRC Safety Evaluation states the on-line  
 
testing capability of BFN's RPS meets the intent of  
 
this item and is therefore acceptable (Reference 3).  
 
Status: Closed  
 
NRC closed this item in Inspection Report 2006-007 (Reference 4).  


==References:==
==References:==
1.
: 1. TVA letter to NRC, dated November 7, 1983, in regards to Generic Letter 83-28
TVA letter to NRC, dated November 7, 1983, in regards to Generic Letter 83-28
: 2. TVA letter to NRC, dated March 15, 1984, in regards to Generic Letter 83-28
: 2. TVA letter to NRC, dated March 15, 1984, in regards to Generic Letter 83-28
: 3. NRC letter to TVA, dated September 2, 1986, Reactor Trip System Reliability, On-Line  
: 3. NRC letter to TVA, dated September 2, 1986, Reactor Trip System Reliability, On-Line Testing, Generic Letter 83-28, Item 4.5.2
 
: 4. NRC letter to TVA, dated August 10, 2006, Browns Ferry Nuclear Plant Unit 1 Recovery - NRC Integrated Inspection Report 05000259/2006007 April 13, 2007                 E1-56
Testing, Generic Letter 83-28, Item 4.5.2
: 4. NRC letter to TVA, dated August 10, 2006, Browns Ferry Nuclear Plant Unit 1 Recovery - NRC  
 
Integrated Inspection Report 05000259/2006007  
 
April 13, 2007 E1-57 Generic Letter 83-28, Salem ATWS, Item 4.5.3, Intervals for On-Line Testing
 
Commitment: TVA will complete Generic Letter 83-28, Item 4.5.3.
 
Discussion: The NRC Staff has reviewed the General Electric Topical Reports NEDC-30844, BWR Owners'


Group (BWROG) Response to NRC Generic Letter  
Generic Letter 83-28, Salem ATWS, Item 4.5.3, Intervals for On-Line Testing Commitment:  TVA will complete Generic Letter 83-28, Item 4.5.3.
 
Discussion:  The NRC Staff has reviewed the General Electric Topical Reports NEDC-30844, BWR Owners' Group (BWROG) Response to NRC Generic Letter 83-28, Item 4.5.3, and NEDC-30851P, Technical Specifications Improvement Analysis for BWR Reactor Protection System, and issued a favorable Safety Evaluation Report (Reference 1).
83-28, Item 4.5.3, and NEDC-30851P, Technical  
In Reference 2, TVA endorsed the BWROG position and stated the analysis presented in NEDC-30851P were applicable to BFN. No Technical Specifications instrument calibration frequency extensions were requested based on these reports. Differences between the parts of BFNs Reactor Protection System (RPS) that perform the trip functions and those of the base case plant were analyzed using the procedures of Appendix K of NEDC-30851P to demonstrate no appreciable change in RPS availability or public risk. The Safety Evaluation that closed this item was provided by Reference 3.
 
Status:       Closed NRC closed this item in Inspection Report 2006-007 (Reference 4).
Specifications Improvement Analysis for BWR Reactor  
 
Protection System, and issued a favorable Safety  
 
Evaluation Report (Reference 1).  
 
In Reference 2, TVA endorsed the BWROG position and  
 
stated the analysis presented in NEDC-30851P were  
 
applicable to BFN. No Technical Specifications  
 
instrument calibration frequency extensions were  
 
requested based on these reports. Differences  
 
between the parts of BFN's Reactor Protection  
 
System (RPS) that perform the trip functions and  
 
those of the base case plant were analyzed using  
 
the procedures of Appendix K of NEDC-30851P to  
 
demonstrate no appreciable change in RPS  
 
availability or public risk. The Safety Evaluation  
 
that closed this item was provided by Reference 3.  
 
Status: Closed  
 
NRC closed this item in Inspection Report 2006-007 (Reference 4).  


==References:==
==References:==
1.
: 1. NRC letter to BWR Owners Group, dated July 15, 1987, General Electric Company (GE)
NRC letter to BWR Owners Group, dated July 15, 1987, General Electric Company (GE)  
Topical Reports NEDC-30844, BWR Owners' Group Response to NRC Generic Letter 83-28, and NEDC-30851P, Technical Specifications Improvement Analysis for BWR RPS
 
: 2. TVA letter to NRC, dated July 5, 1990, Generic Letter 83-28, Required Actions Based on Generic Implications of Salem ATWS Events, Item 4.5.3, Reactor Trip System Reliability
Topical Reports NEDC-30844, BWR Owners'  
: 3. NRC letter to TVA, dated August 17, 1990, Safety Evaluation of Generic Letter 83-28, Item 4.5.3, Reactor Trip Reliability - On-Line Functional Testing of the Reactor Trip System
 
: 4. NRC letter to TVA, dated August 10, 2006, Browns Ferry Nuclear Plant Unit 1 Recovery - NRC Integrated Inspection Report 05000259/2006007 April 13, 2007                 E1-57
Group Response to NRC Generic Letter 83-28, and  
 
NEDC-30851P, Technical Specifications  
 
Improvement Analysis for BWR RPS
: 2. TVA letter to NRC, dated July 5, 1990, Generic Letter 83-28, Required Actions Based on Generic  
 
Implications of Salem ATWS Events, Item 4.5.3, Reactor Trip System Reliability
: 3. NRC letter to TVA, dated August 17, 1990, Safety Evaluation of Generic Letter 83-28, Item 4.5.3, Reactor Trip Reliability - On-Line Functional  
 
Testing of the Reactor Trip System
: 4. NRC letter to TVA, dated August 10, 2006, Browns Ferry Nuclear Plant Unit 1 Recovery - NRC  
 
Integrated Inspection Report 05000259/2006007  
 
April 13, 2007 E1-58 Generic Letter 87-02, Verification of Seismic Adequacy of Mechanical and Electrical Equipment in
 
Operating Reactors, Unresolved Safety Issue (USI) A-46
 
Commitment: TVA will resolve USI A-46.


Discussion: In Reference 1, TVA committed to use the Seismic Qualification Utility Group (SQUG) methodology as  
Generic Letter 87-02, Verification of Seismic Adequacy of Mechanical and Electrical Equipment in Operating Reactors, Unresolved Safety Issue (USI) A-46 Commitment:  TVA will resolve USI A-46.
 
Discussion:   In Reference 1, TVA committed to use the Seismic Qualification Utility Group (SQUG) methodology as documented in the Generic Implementation Procedure (GIP) to resolve USI A-46 at Browns Ferry Nuclear Plant. NRC requested clarification regarding TVAs approach in Reference 2, which TVA supplied in Reference 3. In Reference 4, the staff considered TVA's commitment to comply with GIP-2 an acceptable method for resolving USI A-46 at BFN.
documented in the Generic Implementation  
TVA provided its response to Generic Letter 87-02 for Unit 1 in Reference 5.
 
TVA completed the USI-A46 review and resolved outliers. TVA completed the operations review of Safe Shutdown Equipment List (SSEL) following the A-46 verification. The review determined that Unit 1 can be safely shutdown to Mode 3 and maintained while using only the equipment in the SSEL.
Procedure (GIP) to resolve USI A-46 at Browns Ferry  
IR 2006-006 (Reference 6) stated However, final closure of these items will be deferred until NRR completes their review in this area and any SERs, if required, are issued.
 
Status:       Complete The Safety Evaluation on this program was provided by Reference 7.
Nuclear Plant. NRC requested clarification  
 
regarding TVA's approach in Reference 2, which TVA  
 
supplied in Reference 3. In Reference 4, the staff  
 
considered TVA's commitment to comply with GIP-2 an  
 
acceptable method for resolving USI A-46 at BFN.
 
TVA provided its response to Generic Letter 87-02  
 
for Unit 1 in Reference 5.  
 
TVA completed the USI-A46 review and resolved  
 
outliers. TVA completed the operations review of  
 
Safe Shutdown Equipment List (SSEL) following the  
 
A-46 verification. The review determined that Unit  
 
1 can be safely shutdown to Mode 3 and maintained  
 
while using only the equipment in the SSEL.  
 
IR 2006-006 (Reference 6) stated "- However, final closure of these items will be deferred until NRR  
 
completes their review in this area and any SERs, if required, are issued."
Status: Complete  
 
The Safety Evaluation on this program was provided  
 
by Reference 7.


==References:==
==References:==
1.
: 1. TVA letter to NRC, dated September 21, 1992, Browns Ferry Nuclear Plant (BFN) - Supplement 1 to Generic Letter 87-02, Verification of Seismic Adequacy of Mechanical and Electrical Equipment in Operating Reactors, Unresolved Safety Issue (USI) A-46 and Supplement 4 to Generic Letter 88-20, Individual Plant Examination of External Events (IPEEE) for Severe Accident Vulnerabilities
TVA letter to NRC, dated September 21, 1992, Browns Ferry Nuclear Plant (BFN) - Supplement 1  
: 2. NRC letter to TVA, dated November 19, 1992, Generic Letter 87-02, Supplement 1 Response -
 
to Generic Letter 87-02, Verification of Seismic  
 
Adequacy of Mechanical and Electrical Equipment  
 
in Operating Reactors, Unresolved Safety Issue (USI) A-46 and Supplement 4 to Generic  
 
Letter 88-20, Individual Plant Examination of  
 
External Events (IPEEE) for Severe Accident  
 
Vulnerabilities
: 2. NRC letter to TVA, dated November 19, 1992, Generic Letter 87-02, Supplement 1 Response -  
 
Browns Ferry Nuclear Plant (TAC Nos. M69430, M69431, and M69432)
Browns Ferry Nuclear Plant (TAC Nos. M69430, M69431, and M69432)
April 13, 2007 E1-59
April 13, 2007                   E1-58
: 3. TVA letter to NRC, dated January 19, 1993, Browns Ferry Nuclear Plant (BFN) - Generic  
: 3. TVA letter to NRC, dated January 19, 1993, Browns Ferry Nuclear Plant (BFN) - Generic Letter (GL) 87-02, Supplement 1, 120-Day Response, Request for Additional Information
 
: 4. NRC letter to TVA, dated March 19, 1993, Generic Letter 87-02, Supplement 1 Response - Browns Ferry Nuclear Plant (TAC Nos. M69430, M69431, and M69432)
Letter (GL) 87-02, Supplement 1, 120-Day  
: 5. TVA letter, T. E. Abney to NRC, dated October 7, 2004, Browns Ferry Nuclear Plant (BFN) Unit 1 - Response to NRC Generic Letter (GL) 87-02, Supplement 1 that Transmits Supplemental Safety Evaluation Report No. 2 (SSER No. 2) on SQUG Generic Implementation Procedure, Revision 2, as Corrected on February 14, 1992 (GIP-2)
 
: 6. NRC letter to TVA, dated May 15, 2006, Browns Ferry Nuclear Plant Unit 1 Recovery - NRC Integrated Inspection Report 05000259/2006006
Response, Request for Additional Information
: 7. NRC letter to TVA, dated December 8, 2006, Review of Licensee Response to NRC Generic Letter 87-02, Supplement 1 That Transmits Supplemental Safety Evaluation Report No. 2 on SQUG Generic Implementation Procedure Revision 2, As Corrected on February 14, 1992 April 13, 2007                 E1-59
: 4. NRC letter to TVA, dated March 19, 1993, Generic Letter 87-02, Supplement 1 Response - Browns  
 
Ferry Nuclear Plant (TAC Nos. M69430, M69431, and M69432)
: 5. TVA letter, T. E. Abney to NRC, dated October 7, 2004, Browns Ferry Nuclear Plant (BFN) Unit 1 - Response to NRC Generic Letter (GL) 87-02, Supplement 1 that Transmits  
 
Supplemental Safety Evaluation Report No. 2 (SSER No. 2) on SQUG Generic Implementation  
 
Procedure, Revision 2, as Corrected on  
 
February 14, 1992 (GIP-2)
: 6. NRC letter to TVA, dated May 15, 2006, Browns Ferry Nuclear Plant Unit 1 Recovery - NRC  
 
Integrated Inspection Report 05000259/2006006
: 7. NRC letter to TVA, dated December 8, 2006, Review of Licensee Response to NRC Generic  
 
Letter 87-02, Supplement 1 That Transmits  
 
Supplemental Safety Evaluation Report No. 2 on  
 
SQUG Generic Implementation Procedure Revision  
 
2, As Corrected on February 14, 1992  
 
April 13, 2007 E1-60 Generic Letter 88-01, NRC Position on IGSCC in BWR Austenitic Stainless Steel Piping 
 
Commitment: TVA will complete Generic Letter 88-01.
 
Discussion: TVA's program to address Generic Letter 88-01 was provided by Reference 1. The Safety Evaluation


documenting the acceptability of the program was  
Generic Letter 88-01, NRC Position on IGSCC in BWR Austenitic Stainless Steel Piping Commitment:  TVA will complete Generic Letter 88-01.
 
Discussion:  TVA's program to address Generic Letter 88-01 was provided by Reference 1. The Safety Evaluation documenting the acceptability of the program was included in Reference 2. Supplemental information regarding Unit 1 was submitted in Reference 3. The Safety Evaluation for Unit 1 was provided by Reference 5.
included in Reference 2. Supplemental information  
Status:       C-C TVA has completed the Generic Letter 88-01 program.
 
NRC closed this item in Inspection Report 2006-007 (Reference 4).
regarding Unit 1 was submitted in Reference 3. The  
 
Safety Evaluation for Unit 1 was provided by  
 
Reference 5.  
 
Status: C-C  
 
TVA has completed the Generic Letter 88-01 program.  
 
NRC closed this item in Inspection Report 2006-007 (Reference 4).  


==References:==
==References:==
1.
: 1. TVA letter to NRC, dated December 28, 1992, Supplemental Response to Generic Letter (GL) 88-01, NRC Position on Intergranular Stress Corrosion Cracking (IGSCC) in BWR Austenitic Stainless Steel Piping
TVA letter to NRC, dated December 28, 1992, Supplemental Response to Generic Letter (GL)
: 2. NRC letter to TVA, dated December 3, 1993, Safety Evaluation of Supplemental Response to Generic Letter 88-01
 
: 3. TVA letter to NRC, dated July 21, 2004, Browns Ferry Nuclear Plant (BFN) Unit 1 - Supplemental Response to Generic Letter 88-01, NRC Position on Intergranular Stress Corrosion Cracking In BWR Austentic Stainless Steel Piping
88-01, NRC Position on Intergranular Stress  
: 4. NRC letter to TVA, dated August 10, 2006, Browns Ferry Nuclear Plant Unit 1 Recovery - NRC Integrated Inspection Report 05000259/2006007
 
: 5. NRC letter to TVA dated May 30, 2006, Browns Ferry Nuclear Plant Unit 1 - Supplemental Response to Generic Letter 88-01, NRC Position on Intergranular Stress Corrosion Cracking in BWR [Boiling Water Reactor] Austenitic Stainless Steel Piping April 13, 2007                   E1-60
Corrosion Cracking (IGSCC) in BWR Austenitic  
 
Stainless Steel Piping
: 2. NRC letter to TVA, dated December 3, 1993, Safety Evaluation of Supplemental Response to  
 
Generic Letter 88-01
: 3. TVA letter to NRC, dated July 21, 2004, Browns Ferry Nuclear Plant (BFN) Unit 1 - Supplemental  
 
Response to Generic Letter 88-01, NRC Position  
 
on Intergranular Stress Corrosion Cracking In  
 
BWR Austentic Stainless Steel Piping
: 4. NRC letter to TVA, dated August 10, 2006, Browns Ferry Nuclear Plant Unit 1 Recovery - NRC  
 
Integrated Inspection Report 05000259/2006007
: 5. NRC letter to TVA dated May 30, 2006, Browns Ferry Nuclear Plant Unit 1 - Supplemental  
 
Response to Generic Letter 88-01, NRC Position  
 
on Intergranular Stress Corrosion Cracking in  
 
BWR [Boiling Water Reactor] Austenitic Stainless  
 
Steel Piping  
 
April 13, 2007 E1-61 Generic Letter 88-11, Radiation Embrittlement of Reactor Vessel Materials and Its Impact on Plant
 
Operations


Commitment: TVA will complete Generic Letter 88-11.  
Generic Letter 88-11, Radiation Embrittlement of Reactor Vessel Materials and Its Impact on Plant Operations Commitment:   TVA will complete Generic Letter 88-11.
 
Discussion:   TVA responded to Generic Letter 88-11 in Reference 1. TVA concluded that the current pressure-temperature curves in each plant's Technical Specifications were valid through the next two fuel cycles when compared to the Regulatory Guide 1.99, Revision 2, methodology.
Discussion: TVA responded to Generic Letter 88-11 in Reference 1. TVA concluded that the current  
Supplemental information was provided for BFN in References 2 and 3.
 
In Reference 4, TVA proposed Technical Specifications changes for BFN Units 1, 2 and 3 to incorporate pressure-temperature curves calculated using Regulatory Guide 1.99, Revision 2, methodology. NRC requested additional information in Reference 5, which was provided by TVA in Reference 6. The proposed Technical Specifications were issued by Reference 7.
pressure-temperature curves in each plant's  
Status:       C-C NRC closed this item in Inspection Report 2006-007 (Reference 8).
 
Technical Specifications were valid through the  
 
next two fuel cycles when compared to the  
 
Regulatory Guide 1.99, Revision 2, methodology.  
 
Supplemental information was provided for BFN in  
 
References 2 and 3.  
 
In Reference 4, TVA proposed Technical  
 
Specifications changes for BFN Units 1, 2 and 3 to  
 
incorporate pressure-temperature curves calculated  
 
using Regulatory Guide 1.99, Revision 2, methodology. NRC requested additional information  
 
in Reference 5, which was provided by TVA in  
 
Reference 6. The proposed Technical Specifications  
 
were issued by Reference 7.  
 
Status: C-C  
 
NRC closed this item in Inspection Report 2006-007 (Reference 8).  


==References:==
==References:==
1.
: 1. TVA letter to NRC, dated November 30, 1988, Browns Ferry Nuclear Plant (BFN), Sequoyah Nuclear Plant (SQN), and Watts Bar Nuclear Plant (WBN) - Response to Generic Letter 88 NRC Position on Radiation Embrittlement of Reactor Vessel Materials and its Impact on Plant Operations
TVA letter to NRC, dated November 30, 1988, Browns Ferry Nuclear Plant (BFN), Sequoyah  
: 2. TVA letter to NRC, dated February 28, 1991, TVA Supplemental Response to Generic Letter 88-11, NRC Position of Radiation Embrittlement of Reactor Vessel Materials and its Impact on Plant Operations
 
: 3. TVA letter to NRC, dated April 30, 1991, TVA Supplemental Response to Generic Letter 88-11, NRC Position of Radiation Embrittlement of Reactor Vessel Materials and its Impact on Plant Operations
Nuclear Plant (SQN), and Watts Bar Nuclear  
: 4. TVA letter to NRC, dated July 19, 1991, TVA BFN Technical Specification (TS) No. 293 April 13, 2007                   E1-61
 
: 5. NRC letter to TVA, dated August 28, 1991, Pressure-Temperature Limits Pursuant to Generic Letter 88-11 as Reflected in Proposed Amendment to Technical Specification (TS 293)
Plant (WBN) - Response to Generic Letter
: 6. TVA letter to NRC, dated October 24, 1991, TVA BFN Technical Specification (TS) No. 293 -
 
Radiation Embrittlement of Reactor Vessel Material and its Impact on Plant Operations -
88 NRC Position on Radiation Embrittlement  
 
of Reactor Vessel Materials and its Impact on  
 
Plant Operations
: 2. TVA letter to NRC, dated February 28, 1991, TVA Supplemental Response to Generic Letter 88-11, NRC Position of Radiation Embrittlement of  
 
Reactor Vessel Materials and its Impact on Plant  
 
Operations
: 3. TVA letter to NRC, dated April 30, 1991, TVA Supplemental Response to Generic Letter 88-11, NRC Position of Radiation Embrittlement of  
 
Reactor Vessel Materials and its Impact on Plant  
 
Operations
: 4. TVA letter to NRC, dated July 19, 1991, TVA BFN Technical Specification (TS) No. 293  
 
April 13, 2007 E1-62
: 5. NRC letter to TVA, dated August 28, 1991, Pressure-Temperature Limits Pursuant to Generic  
 
Letter 88-11 as Reflected in Proposed Amendment  
 
to Technical Specification (TS 293)
: 6. TVA letter to NRC, dated October 24, 1991, TVA BFN Technical Specification (TS) No. 293 -  
 
Radiation Embrittlement of Reactor Vessel  
 
Material and its Impact on Plant Operations -  
 
Response to Request for Additional Information
Response to Request for Additional Information
: 7. NRC letter to TVA, dated January 8, 1993, Issuance of Amendments for the Browns Ferry  
: 7. NRC letter to TVA, dated January 8, 1993, Issuance of Amendments for the Browns Ferry Nuclear Plant (TS 293)
 
: 8. NRC letter to TVA, dated August 10, 2006, Browns Ferry Nuclear Plant Unit 1 Recovery - NRC Integrated Inspection Report 05000259/2006007 April 13, 2007                 E1-62
Nuclear Plant (TS 293)
: 8. NRC letter to TVA, dated August 10, 2006, Browns Ferry Nuclear Plant Unit 1 Recovery - NRC  
 
Integrated Inspection Report 05000259/2006007  
 
April 13, 2007 E1-63 Generic Letter 88-14, Instrument Air Supply System Problems Affecting Safety-Related Equipment


Commitment: TVA will complete Generic Letter 88-14.  
Generic Letter 88-14, Instrument Air Supply System Problems Affecting Safety-Related Equipment Commitment:   TVA will complete Generic Letter 88-14.
 
Discussion:   The original response to Generic Letter 88-14 was included as part of Reference 1. Additional information regarding the dew point of air being supplied to certain components was provided in Reference 2. NRC confirmed TVAs commitments in Reference 3.
Discussion: The original response to Generic Letter 88-14 was included as part of Reference 1. Additional  
Status:       Closed NRC closed this item in Inspection Report 2005-008 (Reference 4).
 
information regarding the dew point of air being  
 
supplied to certain components was provided in  
 
Reference 2. NRC confirmed TVA's commitments in  
 
Reference 3.  
 
Status: Closed  
 
NRC closed this item in Inspection Report 2005-008 (Reference 4).  


==References:==
==References:==
1.
: 1. TVA letter to NRC, dated February 23, 1989, Browns Ferry Nuclear Plant (BFN), Sequoyah Nuclear Plant (SQN), and Watts Bar Nuclear Plant (WBN) - Response to Generic Letter 88 Instrument Air Supply System Problems Affecting Safety-Related Equipment
TVA letter to NRC, dated February 23, 1989, Browns Ferry Nuclear Plant (BFN), Sequoyah  
: 2. TVA letter to NRC, dated July 30, 1993, Supplemental Response to Generic Letter (GL) 88-14, Instrument Air Supply System Problems Affecting Safety-Related Equipment
 
: 3. NRC letter to TVA, dated May 9, 1989, Generic Letter 88 Instrument Air Supply System Problems Affecting Safety-Related Equipment (TAC Nos. 71631/71632/71633)
Nuclear Plant (SQN), and Watts Bar Nuclear  
: 4. NRC letter to TVA, dated November 14, 2005, Browns Ferry Nuclear Plant Unit 1 Recovery - NRC Integrated Inspection Report 05000259/2005008 April 13, 2007                 E1-63
 
Plant (WBN) - Response to Generic Letter  
 
88 Instrument Air Supply System Problems  
 
Affecting Safety-Related Equipment
: 2. TVA letter to NRC, dated July 30, 1993, Supplemental Response to Generic Letter (GL)
 
88-14, Instrument Air Supply System Problems  
 
Affecting Safety-Related Equipment
: 3. NRC letter to TVA, dated May 9, 1989, Generic Letter 88 Instrument Air Supply System  
 
Problems Affecting Safety-Related Equipment (TAC Nos. 71631/71632/71633)
: 4. NRC letter to TVA, dated November 14, 2005, Browns Ferry Nuclear Plant Unit 1 Recovery - NRC  
 
Integrated Inspection Report 05000259/2005008  
 
April 13, 2007 E1-64 Generic Letter 88-20, Individual Plant Examination for Severe Accident Vulnerabilities
 
Issue: TVA will respond to Generic Letter 88-20.
 
Discussion: Generic Letter 88-20 requested licensees:
: 1. Perform a systematic examination to identify any plant specific vulnerabilities to severe
 
accidents; and
: 2. Identify and review proposed plant improvements (design changes and changes to operating
 
procedures, maintenance, surveillance, training, or staffing).
 
The Generic Letter did not request individual IPEs
 
be performed for each unit at a multi-unit site.
 
The BFN facility has been extensively reviewed by
 
the staff, beginning with an interim reliability
 
evaluation in 1982. This was followed by the
 
subsequent submittal of the November 20, 1986, BFN Unit 1 Probabilistic Risk Assessment (PRA) and
 
its subsequent NRC audit. TVA subsequently
 
submitted BFN's IPE in 1992 and the Multi-unit PRA (MUPRA) in 1995. Since then, TVA has performed


individual Unit 2 and Unit 3 PRAs. Neither the  
Generic Letter 88-20, Individual Plant Examination for Severe Accident Vulnerabilities Issue:        TVA will respond to Generic Letter 88-20.
 
Discussion:  Generic Letter 88-20 requested licensees:
MUPRA, nor the subsequently performed individual  
: 1. Perform a systematic examination to identify any plant specific vulnerabilities to severe accidents; and
 
: 2. Identify and review proposed plant improvements (design changes and changes to operating procedures, maintenance, surveillance, training, or staffing).
Unit 2 and Unit 3 PRAs have identified plant  
The Generic Letter did not request individual IPEs be performed for each unit at a multi-unit site.
 
The BFN facility has been extensively reviewed by the staff, beginning with an interim reliability evaluation in 1982. This was followed by the subsequent submittal of the November 20, 1986, BFN Unit 1 Probabilistic Risk Assessment (PRA) and its subsequent NRC audit. TVA subsequently submitted BFNs IPE in 1992 and the Multi-unit PRA (MUPRA) in 1995. Since then, TVA has performed individual Unit 2 and Unit 3 PRAs. Neither the MUPRA, nor the subsequently performed individual Unit 2 and Unit 3 PRAs have identified plant vulnerabilities when single or multiple units are in operation. These analyses have provided the staff with more than reasonable assurance that TVA has adequately analyzed the plant design and operations.
vulnerabilities when single or multiple units are  
In Reference 1, NRC identified the specific information needed for the closeout of Generic Letter 88-20 for Browns Ferry Unit 1. This information was provided in Reference 2.
 
Status:       Complete
in operation. These analyses have provided the  
 
staff with more than reasonable assurance that TVA  
 
has adequately analyzed the plant design and  
 
operations.  
 
In Reference 1, NRC identified the specific  
 
information needed for the closeout of Generic  
 
Letter 88-20 for Browns Ferry Unit 1. This  
 
information was provided in Reference 2.  
 
Status: Complete  


==References:==
==References:==
1.
: 1. NRC letter to TVA, dated June 21, 2004, Browns Ferry Nuclear Plant, Unit 1 - Request for Additional Information Related to Generic Letter 88-20, Individual Plant Examination For Severe Accident Vulnerability April 13, 2007                   E1-64
NRC letter to TVA, dated June 21, 2004, Browns Ferry Nuclear Plant, Unit 1 - Request for  
: 2. TVA letter to NRC, dated August 17, 2004, Browns Ferry Nuclear Plant (BFN) - Unit 1 - Response to Request for Additional Information Related to Generic Letter 88-20, Individual Plant Examination for Severe Accident Vulnerability April 13, 2007                 E1-65
 
Additional Information Related to Generic  
 
Letter 88-20, Individual Plant Examination For  
 
Severe Accident Vulnerability April 13, 2007 E1-65
: 2. TVA letter to NRC, dated August 17, 2004, Browns Ferry Nuclear Plant (BFN) - Unit 1 - Response to  
 
Request for Additional Information Related to  
 
Generic Letter 88-20, Individual Plant  
 
Examination for Severe Accident Vulnerability April 13, 2007 E1-66 Generic Letter 88-20, Supplement 4, Individual Plant Examination of External Events (IPEEE) for Severe
 
Accident Vulnerabilities
 
Commitment: TVA will complete an Individual Plant Examination of External Events (IPEEE).
 
Discussion: In Reference 1, TVA described BFN's program and schedule for completing the internal fires, high


winds, external floods, and transportation and  
Generic Letter 88-20, Supplement 4, Individual Plant Examination of External Events (IPEEE) for Severe Accident Vulnerabilities Commitment:  TVA will complete an Individual Plant Examination of External Events (IPEEE).
 
Discussion:  In Reference 1, TVA described BFNs program and schedule for completing the internal fires, high winds, external floods, and transportation and nearby facility accidents portions of the IPEEE.
nearby facility accidents portions of the IPEEE.  
NRC acceptance of the methods and schedules for the addressed portions of the IPEEE was documented in Reference 2.
 
TVA provided its initial program and schedule for responding to the seismic portion of the IPEEE in Reference 3. NRC requested additional information on this subject in Reference 4, which TVA provided in Reference 5.
NRC acceptance of the methods and schedules for the  
The summary report for the high winds, external floods, and transportation and nearby facility accidents IPEEE was provided by TVA in Reference 6 for all three BFN units. The seismic IPEEE Report and the Fire Induced Vulnerability Evaluation were provided in Reference 7.
 
Status:       Complete TVA completed corrective actions to address the seismic-induced fire vulnerability associated with the emergency lighting battery racks located in the BFN Unit 1 cable spreading room prior to restart.
addressed portions of the IPEEE was documented in  
 
Reference 2.  
 
TVA provided its initial program and schedule for  
 
responding to the seismic portion of the IPEEE in  
 
Reference 3. NRC requested additional information  
 
on this subject in Reference 4, which TVA provided  
 
in Reference 5.  
 
The summary report for the high winds, external  
 
floods, and transportation and nearby facility  
 
accidents IPEEE was provided by TVA in Reference 6  
 
for all three BFN units. The seismic IPEEE Report  
 
and the Fire Induced Vulnerability Evaluation were  
 
provided in Reference 7.  
 
Status: Complete  
 
TVA completed corrective actions to address the  
 
seismic-induced fire vulnerability associated with  
 
the emergency lighting battery racks located in the  
 
BFN Unit 1 cable spreading room prior to restart.  


==References:==
==References:==
1.
: 1. TVA letter to NRC, dated December 20, 1991, Individual Plant Examination of External Events (IPEEE) for Severe Accident Vulnerabilities (Generic Letter 88-20, Supplement 4)
TVA letter to NRC, dated December 20, 1991, Individual Plant Examination of External  
: 2. NRC letter to TVA, dated July 2, 1992, Review of Response to Generic Letter 88-20, Supplement No. 4 - Individual Plant Examinations for External Events April 13, 2007                   E1-66
 
: 3. TVA letter to NRC, dated September 21, 1992, Supplement 1 to Generic Letter 87-02, Verification of Seismic Adequacy of Mechanical and Electrical Equipment in Operating Reactors, Unresolved Safety Issue (USI) A-46 and Supplement 4 to Generic Letter 88-20, Individual Plant Examination of External Events (IPEEE) for Severe Accident Vulnerabilities
Events (IPEEE) for Severe Accident  
 
Vulnerabilities (Generic Letter 88-20, Supplement 4)
: 2. NRC letter to TVA, dated July 2, 1992, Review of Response to Generic Letter 88-20, Supplement  
 
No. 4 - Individual Plant Examinations for  
 
External Events  
 
April 13, 2007 E1-67
: 3. TVA letter to NRC, dated September 21, 1992, Supplement 1 to Generic Letter 87-02, Verification of Seismic Adequacy of Mechanical  
 
and Electrical Equipment in Operating Reactors, Unresolved Safety Issue (USI) A-46 and  
 
Supplement 4 to Generic Letter 88-20, Individual  
 
Plant Examination of External Events (IPEEE) for  
 
Severe Accident Vulnerabilities
: 4. NRC letter to TVA, dated November 19, 1992, Generic Letter 87-02, Supplement 1 Response
: 4. NRC letter to TVA, dated November 19, 1992, Generic Letter 87-02, Supplement 1 Response
: 5. TVA letter to NRC, dated January 19, 1993, Generic Letter (GL) 87-02, Supplement 1, 120-Day  
: 5. TVA letter to NRC, dated January 19, 1993, Generic Letter (GL) 87-02, Supplement 1, 120-Day Response, Request for Additional Information
 
: 6. TVA letter to NRC, dated July 24, 1995, Browns Ferry Nuclear Plant - Generic Letter 88-20, Supplement 4, Individual Plant Examination of External Events (IPEEE) for Severe Accident Vulnerabilities - Partial Submittal of Report
Response, Request for Additional Information
: 7. TVA letter to NRC, dated January 14, 2005, Browns Ferry Nuclear Plant (BFN) Unit 1 -
: 6. TVA letter to NRC, dated July 24, 1995, Browns Ferry Nuclear Plant - Generic Letter 88-20, Supplement 4, Individual Plant Examination of  
Response to NRC Generic Letter (GL) 88-20, Supplement 4 - Individual Plant Examination of External Events (IPEEE) for Severe Accident Vulnerabilities - Submittal of Browns Ferry Nuclear Plant Unit 1 Seismic and Internal Fires IPEEE Reports April 13, 2007                  E1-67
 
External Events (IPEEE) for Severe Accident  
 
Vulnerabilities - Partial Submittal of Report
: 7. TVA letter to NRC, dated January 14, 2005, Browns Ferry Nuclear Plant (BFN) Unit 1 -  
 
Response to NRC Generic Letter (GL) 88-20, Supplement 4 - Individual Plant Examination of  
 
External Events (IPEEE) for Severe Accident  


Vulnerabilities - Submittal of Browns Ferry
Generic Letter 89-06, Task Action Plan Item I.D.2 - Safety Parameter Display System Commitment:   TVA will install and make operational a Safety Parameter Display System (SPDS) and certify that the SPDS fully meets the requirements of NUREG-0737, Supplement 1, taking into account the information provided in NUREG-1342.
 
Discussion:   Certification that BFNs SPDS fully meets the requirements of NUREG-0737, Supplement 1, taking into account the information provided in NUREG-1342, was requested by Generic Letter 89-06 (Reference 1). TVA's commitment to implement an SPDS on Unit 1 before restart is contained in Reference 2. The final design description for the SPDS was provided by TVA in References 3 and 4.
Nuclear Plant Unit 1 Seismic and Internal Fires
The initial Safety Evaluation Report (SER) of the SPDS design description was documented in Reference 5. TVA responded to the SER open items in Reference 6. NRC concluded in a Supplemental SER that TVA's SPDS design description fully met the requirements of NUREG-0737, Supplement 1 (Reference 7).
 
Status:       Closed NRC closed this item in Inspection Report 2006-007 (Reference 8).
IPEEE Reports
 
April 13, 2007 E1-68 Generic Letter 89-06, Task Action Plan Item I.D.2 - Safety Parameter Display System  
 
Commitment: TVA will install and make operational a Safety Parameter Display System (SPDS) and certify that  
 
the SPDS fully meets the requirements of
 
NUREG-0737, Supplement 1, taking into account the  
 
information provided in NUREG-1342.  
 
Discussion: Certification that BFN's SPDS fully meets the requirements of NUREG-0737, Supplement 1, taking  
 
into account the information provided in
 
NUREG-1342, was requested by Generic Letter
 
89-06 (Reference 1). TVA's commitment to implement  
 
an SPDS on Unit 1 before restart is contained in  
 
Reference 2. The final design description for the  
 
SPDS was provided by TVA in References 3 and 4.
 
The initial Safety Evaluation Report (SER) of the  
 
SPDS design description was documented in  
 
Reference 5. TVA responded to the SER open items  
 
in Reference 6. NRC concluded in a Supplemental  
 
SER that TVA's SPDS design description fully met  
 
the requirements of NUREG-0737, Supplement 1 (Reference 7).  
 
Status: Closed  
 
NRC closed this item in Inspection Report 2006-007 (Reference 8).  


==References:==
==References:==
1.
: 1. NRC letter to All Licensees of Operating Plants, Applicants for Operating Licenses and Holders of Construction Permits, dated April 12, 1989, Task Action Plan Item I.D.2 - Safety Parameter Display System - 10 CFR 50.54(f) - (Generic Letter No. 89-06)
NRC letter to All Licensees of Operating Plants, Applicants for Operating Licenses and Holders of  
: 2. TVA letter to NRC, dated April 8, 1987, Safety Parameter Display System (SPDS) - Schedule for Response to Request for Additional Information
: 3. TVA letter to NRC, dated October 22, 1990, Notification of Implementation of NUREG-0737 (TMI Action Plan), Item I.D.2.1, Safety Parameter Display System (SPDS), Phase I Installation and Final Design Description
: 4. TVA letter to NRC, dated December 11, 1990, Notification of Implementation of NUREG-0737 (TMI Action Plan), Item I.D.2.1, Safety Parameter Display System (SPDS), Final Design Description April 13, 2007                  E1-68
: 5. NRC letter to TVA, dated March 6, 1991, Interim and Final Design of the Safety Parameter Display System at the Browns Ferry Nuclear Plant
: 6. TVA letter to NRC, dated December 17, 1991, Safety Parameter Display System (SPDS), Response to NRC Safety Evaluation Report (SER) Open Items
: 7. NRC letter to TVA, dated February 5, 1992, Safety Parameter Display System - Browns Ferry Nuclear Plant, Units 1, 2, and 3)
: 8. NRC letter to TVA, dated August 10, 2006, Browns Ferry Nuclear Plant Unit 1 Recovery - NRC Integrated Inspection Report 05000259/2006007 April 13, 2007                  E1-69


Construction Permits, dated April 12, 1989, Task
Generic Letter 89-08, Erosion/Corrosion-Induced Pipe Wall Thinning Commitment:   TVA will complete Generic Letter 89-08.
 
Discussion:   TVA responded to Generic Letter 89-08 in Reference 1 and committed to implement a long-term monitoring program (single and dual phase piping). NRC acceptance of the program was provided in Reference 2.
Action Plan Item I.D.2 - Safety Parameter
Status:       Closed NRC closed this item in Inspection Report 2005-009 (Reference 3).
 
Display System - 10 CFR 50.54(f) - (Generic
 
Letter No. 89-06)
: 2. TVA letter to NRC, dated April 8, 1987, Safety Parameter Display System (SPDS) - Schedule for
 
Response to Request for Additional Information
: 3. TVA letter to NRC, dated October 22, 1990, Notification of Implementation of NUREG-0737 (TMI Action Plan), Item I.D.2.1, Safety
 
Parameter Display System (SPDS), Phase I
 
Installation and Final Design Description
: 4. TVA letter to NRC, dated December 11, 1990, Notification of Implementation of NUREG-0737 (TMI Action Plan), Item I.D.2.1, Safety
 
Parameter Display System (SPDS), Final Design
 
Description
 
April 13, 2007 E1-69
: 5. NRC letter to TVA, dated March 6, 1991, Interim and Final Design of the Safety Parameter Display
 
System at the Browns Ferry Nuclear Plant
: 6. TVA letter to NRC, dated December 17, 1991, Safety Parameter Display System (SPDS), Response
 
to NRC Safety Evaluation Report (SER) Open Items
: 7. NRC letter to TVA, dated February 5, 1992, Safety Parameter Display System - Browns Ferry
 
Nuclear Plant, Units 1, 2, and 3)
: 8. NRC letter to TVA, dated August 10, 2006, Browns Ferry Nuclear Plant Unit 1 Recovery - NRC
 
Integrated Inspection Report 05000259/2006007
 
April 13, 2007 E1-70 Generic Letter 89-08, Erosion/Corrosion-Induced Pipe Wall Thinning Commitment: TVA will complete Generic Letter 89-08.  
 
Discussion: TVA responded to Generic Letter 89-08 in Reference 1 and committed to implement a
 
long-term monitoring program (single and dual phase  
 
piping). NRC acceptance of the program was  
 
provided in Reference 2.  
 
Status: Closed  
 
NRC closed this item in Inspection Report 2005-009 (Reference 3).  


==References:==
==References:==
1.
: 1. TVA letter to NRC, dated July 19, 1989, Response to Generic Letter 89 Erosion/Corrosion-Induced Pipe Wall Thinning
TVA letter to NRC, dated July 19, 1989, Response to Generic Letter 89 Erosion/Corrosion-
: 2. NRC letter to TVA, dated August 21, 1989, Licensee Confirmation of its Response to NRC Generic Letter 89-08
 
: 3. NRC letter to TVA, dated February 13, 2006, Browns Ferry Nuclear Plant Unit 1 Recovery - NRC Integrated Inspection Report 05000259/2005009 April 13, 2007                 E1-70
Induced Pipe Wall Thinning
: 2. NRC letter to TVA, dated August 21, 1989, Licensee Confirmation of its Response to NRC  
 
Generic Letter 89-08
: 3. NRC letter to TVA, dated February 13, 2006, Browns Ferry Nuclear Plant Unit 1 Recovery - NRC  
 
Integrated Inspection Report 05000259/2005009  
 
April 13, 2007 E1-71 Generic Letter 89-10, Safety-Related Motor-Operated Valve Testing and Surveillance
 
Commitment: TVA will complete Generic Letter 89-10.
 
Discussion: TVA responded to Generic Letter 89-10 in Reference 1 and committed to implement a


comprehensive motor operated valve program within  
Generic Letter 89-10, Safety-Related Motor-Operated Valve Testing and Surveillance Commitment:  TVA will complete Generic Letter 89-10.
Discussion:  TVA responded to Generic Letter 89-10 in Reference 1 and committed to implement a comprehensive motor operated valve program within the requested 5-year implementation schedule.
Additional schedule information was provided by NRC in Reference 2. TVA provided the 30-day response to Generic Letter 89-10, Supplement 3 by Reference 3 and informed the Staff that the plant specific safety assessment was available for review. TVA also responded to Reference 2 and informed the Staff in Reference 4 that the program description for implementing Generic Letter 89-10 was also available for review.
The 120-day response requested in Supplement 3 to the Generic Letter was provided by TVA in Reference 5. It stated that no deficiencies were identified in the motor-operated valves for primary containment isolation for the High Pressure Coolant Injection and Reactor Core Isolation Cooling steam supply lines or the Reactor Water Cleanup water supply line.
In Reference 6, TVA clarified the implementation schedule for Unit 1. Based on test requirements and system configurations, it would be necessary to perform differential pressure testing on some motor operated valves during the power ascension test program. Consequently, TVA committed to complete the required testing within 30 days following the completion of the power ascension test program.
This implementation schedule was acknowledged by the NRC Staff in Reference 7.
TVA submitted a Unit 1 specific program description in Reference 8. The Generic Letter 89-10 program for BFN Unit 1 has been developed.
TVAs review and documentation of the design basis for the operation of each Unit 1 MOV within the scope of the Generic Letter 89-10 program, the valves included in the program, the methods for determining and adjusting switch settings, testing, surveillance, and maintenance are the same as with the Units 2 and 3 program.
April 13, 2007                  E1-71


the requested 5-year implementation schedule. 
Status:       Closed NRC closed this item in Inspection Report 2006-009 (Reference 9).
 
Additional schedule information was provided by NRC
 
in Reference 2. TVA provided the 30-day response
 
to Generic Letter 89-10, Supplement 3 by
 
Reference 3 and informed the Staff that the plant
 
specific safety assessment was available for
 
review. TVA also responded to Reference 2 and
 
informed the Staff in Reference 4 that the program
 
description for implementing Generic Letter 89-10
 
was also available for review.
 
The 120-day response requested in Supplement 3 to
 
the Generic Letter was provided by TVA in
 
Reference 5. It stated that no deficiencies were
 
identified in the motor-operated valves for primary
 
containment isolation for the High Pressure Coolant
 
Injection and Reactor Core Isolation Cooling steam
 
supply lines or the Reactor Water Cleanup water
 
supply line.
 
In Reference 6, TVA clarified the implementation
 
schedule for Unit 1. Based on test requirements
 
and system configurations, it would be necessary to
 
perform differential pressure testing on some motor
 
operated valves during the power ascension test
 
program. Consequently, TVA committed to complete
 
the required testing within 30 days following the
 
completion of the power ascension test program. 
 
This implementation schedule was acknowledged by
 
the NRC Staff in Reference 7.
 
TVA submitted a Unit 1 specific program description
 
in Reference 8. The Generic Letter 89-10 program
 
for BFN Unit 1 has been developed.
 
TVA's review and documentation of the design basis
 
for the operation of each Unit 1 MOV within the
 
scope of the Generic Letter 89-10 program, the
 
valves included in the program, the methods for
 
determining and adjusting switch settings, testing, surveillance, and maintenance are the same as with
 
the Units 2 and 3 program.
 
April 13, 2007 E1-72 Status: Closed  
 
NRC closed this item in Inspection Report 2006-009 (Reference 9).  


==References:==
==References:==
1.
: 1. TVA letter to NRC, dated December 21, 1989, Browns Ferry Nuclear Plant (BFN), Sequoyah Nuclear Plant (SQN), and Watts Bar Nuclear Plant (WBN) - Response to Generic Letter 89 Safety-Related Motor-Operated Valve (MOV) Testing and Surveillance
TVA letter to NRC, dated December 21, 1989, Browns Ferry Nuclear Plant (BFN), Sequoyah  
: 2. NRC letter to TVA, dated September 14, 1990, Response to Generic Letter 89-10, Safety-Related Motor-Operated Valve Testing and Surveillance for the Browns Ferry, Sequoyah, Watts Bar and Bellefonte Nuclear Plants (MPA B-110)
 
: 3. TVA letter to NRC, dated December 10, 1990, Response to Generic Letter (GL) 89-10, Supplement 3 - Consideration of the Results of NRC-Sponsored Tests of Motor-Operated Valves (MOV)
Nuclear Plant (SQN), and Watts Bar Nuclear  
: 4. TVA letter to NRC, dated December 21, 1990, Response to Generic Letter 89-10, Safety-Related Motor-Operated Valve Testing and Surveillance
 
: 5. TVA letter to NRC, dated March 13, 1991, Response to Generic Letter (GL) 89-10, Supplement 3 - Consideration of the Results of NRC-Sponsored Tests of Motor-Operated Valves (MOV)
Plant (WBN) - Response to Generic Letter  
: 6. TVA letter to NRC, dated April 14, 1992, Generic Letter (GL) 89-10, Safety-Related Motor-Operated Valve Testing and Surveillance - Implementation Schedule
 
: 7. NRC letter to TVA, dated June 30, 1992, Browns Ferry Nuclear Plant, Units 1, 2, and 3 -
89 Safety-Related Motor-Operated  
 
Valve (MOV) Testing and Surveillance
: 2. NRC letter to TVA, dated September 14, 1990, Response to Generic Letter 89-10,
 
Safety-Related Motor-Operated Valve Testing and  
 
Surveillance for the Browns Ferry, Sequoyah, Watts Bar and Bellefonte Nuclear Plants (MPA B-110)
: 3. TVA letter to NRC, dated December 10, 1990, Response to Generic Letter (GL) 89-10, Supplement 3 - Consideration of the Results of  
 
NRC-Sponsored Tests of Motor-Operated Valves (MOV) 4. TVA letter to NRC, dated December 21, 1990, Response to Generic Letter 89-10, Safety-Related  
 
Motor-Operated Valve Testing and Surveillance
: 5. TVA letter to NRC, dated March 13, 1991, Response to Generic Letter (GL) 89-10, Supplement 3 - Consideration of the Results of  
 
NRC-Sponsored Tests of Motor-Operated Valves (MOV) 6. TVA letter to NRC, dated April 14, 1992, Generic Letter (GL) 89-10, Safety-Related Motor-Operated  
 
Valve Testing and Surveillance - Implementation  
 
Schedule 7. NRC letter to TVA, dated June 30, 1992, Browns Ferry Nuclear Plant, Units 1, 2, and 3 -  
 
Implementation Schedule for Generic Letter 89-10 (TAC Nos. M75635, M75636 and M75637)
Implementation Schedule for Generic Letter 89-10 (TAC Nos. M75635, M75636 and M75637)
: 8. TVA letter to NRC, dated May 5, 2004, Browns Ferry Nuclear Plant (BFN) Unit 1 - Generic  
: 8. TVA letter to NRC, dated May 5, 2004, Browns Ferry Nuclear Plant (BFN) Unit 1 - Generic Letter 89-10 and Supplements 1 to 7, Safety-Related Motor-Operated Valve (MOV)
 
Letter 89-10 and Supplements 1 to 7,
 
Safety-Related Motor-Operated Valve (MOV)  
 
Testing and Surveillance
Testing and Surveillance
: 9. NRC letter to TVA, dated March 5, 2007, Browns Ferry Nuclear Plant Unit 1 Recovery - NRC  
: 9. NRC letter to TVA, dated March 5, 2007, Browns Ferry Nuclear Plant Unit 1 Recovery - NRC Integrated Inspection Report 05000259/2006009 April 13, 2007                  E1-72
 
Integrated Inspection Report 05000259/2006009  


April 13, 2007 E1-73 Generic Letter 89-13, Service Water System Problems Affecting Safety-Related Equipment  
Generic Letter 89-13, Service Water System Problems Affecting Safety-Related Equipment Commitment:   TVA will complete Generic Letter 89-13.
 
Discussion:   TVA responded to Generic Letter 89-13 in Reference 1. Three of the near-term commitments were rescheduled in Reference 2. NRC was notified of the completion of the majority of the commitments made in response to Generic Letter 89-13 in Reference 3. The remaining commitment on Unit 1 is to verify that the Unit 1 portions of the Residual Heat Removal Service Water (RHRSW) and Emergency Equipment Cooling Water (EECW) systems satisfy their design criteria. Completion of NRCs review is documented in Reference 4.
Commitment: TVA will complete Generic Letter 89-13.  
Status:       C-C The Unit 1 RHRSW and EECW systems ability to satisfy their design basis has been verified.
 
NRC closed this item in Inspection Report 2006-007 (Reference 5).
Discussion: TVA responded to Generic Letter 89-13 in Reference 1. Three of the near-term commitments  
 
were rescheduled in Reference 2. NRC was notified  
 
of the completion of the majority of the  
 
commitments made in response to Generic Letter
 
89-13 in Reference 3. The remaining commitment on  
 
Unit 1 is to verify that the Unit 1 portions of the  
 
Residual Heat Removal Service Water (RHRSW) and  
 
Emergency Equipment Cooling Water (EECW) systems  
 
satisfy their design criteria. Completion of NRC's
 
review is documented in Reference 4.  
 
Status: C-C  
 
The Unit 1 RHRSW and EECW systems' ability to  
 
satisfy their design basis has been verified.  
 
NRC closed this item in Inspection Report 2006-007 (Reference 5).  


==References:==
==References:==
1.
: 1. TVA letter to NRC, dated March 16, 1990, Response to Generic Letter (GL) 89-13 Service Water System Problems Affecting Safety-Related Equipment
TVA letter to NRC, dated March 16, 1990, Response to Generic Letter (GL) 89-13 Service  
: 2. TVA letter to NRC, dated December 31, 1990, Generic Letter (GL) 89-13, Service Water System Problems Affecting Safety-Related Equipment
 
: 3. TVA letter to NRC, dated August 17, 1995, Browns Ferry Nuclear Plant (BFN) - Response to Generic Letter (GL) 89 Service Water System (SWS)
Water System Problems Affecting Safety-Related  
 
Equipment
: 2. TVA letter to NRC, dated December 31, 1990, Generic Letter (GL) 89-13, Service Water System  
 
Problems Affecting Safety-Related Equipment
: 3. TVA letter to NRC, dated August 17, 1995, Browns Ferry Nuclear Plant (BFN) - Response to Generic  
 
Letter (GL) 89 Service Water System (SWS)  
 
Problems Affecting Safety-Related Equipment
Problems Affecting Safety-Related Equipment
: 4. NRC letter to TVA, dated April 23, 1990, Licensee's Response To Generic Letter 89-13  
: 4. NRC letter to TVA, dated April 23, 1990, Licensee's Response To Generic Letter 89-13 Regarding Service Water Systems (TAC Nos. 73970, 73971, and 73972)
: 5. NRC letter to TVA, dated August 10, 2006, Browns Ferry Nuclear Plant Unit 1 Recovery - NRC Integrated Inspection Report 05000259/2006007 April 13, 2007                  E1-73


Regarding Service Water Systems (TAC Nos. 73970, 73971, and 73972)
Generic Letter 89-16, Installation of a Hardened Wetwell Vent Commitment:   TVA will complete Generic Letter 89-16.
: 5. NRC letter to TVA, dated August 10, 2006, Browns Ferry Nuclear Plant Unit 1 Recovery - NRC
Discussion:   In Reference 1, NRC requested licensees with Mark I containments to voluntarily install a hardened vent. In response, TVA committed to install a hardened vent prior to restart in Reference 2.
 
Status:       C-C TVA installed a hardened wetwell vent.
Integrated Inspection Report 05000259/2006007
NRC closed this item in Inspection Report 2005-006 (Reference 3).
 
April 13, 2007 E1-74 Generic Letter 89-16, Installation of a Hardened Wetwell Vent  
 
Commitment: TVA will complete Generic Letter 89-16.  
 
Discussion: In Reference 1, NRC requested licensees with Mark I containments to voluntarily install a hardened  
 
vent. In response, TVA committed to install a  
 
hardened vent prior to restart in Reference 2.  
 
Status: C-C  
 
TVA installed a hardened wetwell vent.  
 
NRC closed this item in Inspection Report 2005-006 (Reference 3).  


==References:==
==References:==
1.
: 1. NRC letter to All Operating Licensees with Mark I Containments, dated September 1, 1989, Installation of a Hardened Wetwell Vent (Generic Letter 89-16)
NRC letter to All Operating Licensees with Mark I Containments, dated September 1, 1989, Installation of a Hardened Wetwell Vent (Generic  
: 2. TVA letter to NRC, dated October 30, 1989, Response to Generic Letter 89-16, Installation of Hardened Wetwell Vent
 
: 3. NRC letter to TVA, dated May 16, 2005, Browns Ferry Nuclear Plant Unit 1 Recovery - NRC Integrated Inspection Report 05000259/2005006 April 13, 2007                   E1-74
Letter 89-16)
: 2. TVA letter to NRC, dated October 30, 1989, Response to Generic Letter 89-16, Installation  
 
of Hardened Wetwell Vent
: 3. NRC letter to TVA, dated May 16, 2005, Browns Ferry Nuclear Plant Unit 1 Recovery - NRC  
 
Integrated Inspection Report 05000259/2005006  
 
April 13, 2007 E1-75 Generic Letter 92-01, Reactor Vessel Structural Integrity, Revision 1, and Revision 1 Supplement 1
 
Commitment: TVA will submit a summary evaluation of the time and accumulated fluence during intervals of BFN operation below 525 F and its effect on the reference temperature and on the Charpy upper shelf
 
energy.
Discussion: TVA provided an initial response to Generic Letter 92-01 in Reference 1 and made the commitment reiterated above. The summary evaluation of the
 
time and accumulated fluence during intervals of BFN operation below 525 F was provided by TVA in Reference 2. Additional information was requested
 
by the NRC Staff in Reference 3 , which was provided by TVA in Reference 4.
 
In Reference 5, NRC requested TVA verify the data
 
entered into the Reactor Vessel Integrity Database.
 
TVA responded to this request in References 6
 
and 7. Updated material and fluence data was
 
provided by TVA in Reference 8.
 
In Reference 9, NRC requested Licensees verify the
 
completeness of the information previously
 
submitted by November 15, 1995. TVA's response was
 
provided in References 10 and 11.
 
As a result of new industry data, NRC again
 
requested updated information in Reference 12. The


requested information was provided by TVA in  
Generic Letter 92-01, Reactor Vessel Structural Integrity, Revision 1, and Revision 1 Supplement 1 Commitment:  TVA will submit a summary evaluation of the time and accumulated fluence during intervals of BFN operation below 525° F and its effect on the reference temperature and on the Charpy upper shelf energy.
 
Discussion:  TVA provided an initial response to Generic Letter 92-01 in Reference 1 and made the commitment reiterated above. The summary evaluation of the time and accumulated fluence during intervals of BFN operation below 525° F was provided by TVA in Reference 2. Additional information was requested by the NRC Staff in Reference 3, which was provided by TVA in Reference 4.
Reference 13 for Browns Ferry.  
In Reference 5, NRC requested TVA verify the data entered into the Reactor Vessel Integrity Database.
 
TVA responded to this request in References 6 and 7. Updated material and fluence data was provided by TVA in Reference 8.
Status: C-C for restart.  
In Reference 9, NRC requested Licensees verify the completeness of the information previously submitted by November 15, 1995. TVAs response was provided in References 10 and 11.
 
As a result of new industry data, NRC again requested updated information in Reference 12. The requested information was provided by TVA in Reference 13 for Browns Ferry.
As committed in TVA's May 23, 1 994 letter, TVA will inform NRC of the applicability of NEDO 32205  
Status:       C-C for restart.
 
As committed in TVAs May 23, 1994 letter, TVA will inform NRC of the applicability of NEDO 32205 within 90 days of the final surveillance capsules analysis report.
within 90 days of the final surveillance capsules  
NRC closed this item in Inspection Report 2006-007 (Reference 14).
 
analysis report.  
 
NRC closed this item in Inspection Report 2006-007 (Reference 14).  


==References:==
==References:==
1.
: 1. TVA letter to NRC, dated July 7, 1992, Browns Ferry Nuclear Plant (BFN), Sequoyah Nuclear Plant (SQN), and Watts Bar Nuclear Plant (WBN) -
TVA letter to NRC, dated July 7, 1992, Browns Ferry Nuclear Plant (BFN), Sequoyah Nuclear  
Response to generic Letter 92-01 (Reactor Vessel Structural Integrity)
 
April 13, 2007                 E1-75
Plant (SQN), and Watts Bar Nuclear Plant (WBN) -
: 2. TVA letter to NRC, dated December 1, 1992, Completion of Commitment Made in Response to Generic Letter 92-01, Reactor Vessel Structural Integrity
 
: 3. NRC letter to TVA, dated May 27, 1993, Request for Additional Information Regarding TVA Response to Generic Letter 92-01, Revision 1, Reactor Vessel Structural Integrity
Response to generic Letter 92-0 1 (Reactor Vessel Structural Integrity)
April 13, 2007 E1-76
: 2. TVA letter to NRC, dated December 1, 1992, Completion of Commitment Made in Response to  
 
Generic Letter 92-01, Reactor Vessel Structural  
 
Integrity
: 3. NRC letter to TVA, dated May 27, 1993, Request for Additional Information Regarding TVA  
 
Response to Generic Letter 92-01, Revision 1, Reactor Vessel Structural Integrity
: 4. TVA letter to NRC, dated August 2, 1993, Response to Request for Additional Information, Generic Letter 92-01, Revision 1
: 4. TVA letter to NRC, dated August 2, 1993, Response to Request for Additional Information, Generic Letter 92-01, Revision 1
: 5. NRC letter to TVA, dated April 19, 1994, Generic Letter 92-01, Revision 1, Reactor Vessel  
: 5. NRC letter to TVA, dated April 19, 1994, Generic Letter 92-01, Revision 1, Reactor Vessel Structural Integrity
 
: 6. TVA letter to NRC, dated May 23, 1994, TVA's Response to NRC's Letter Dated April 19, 1994, Generic Letter 92-01, Revision 1, Reactor Vessel Structural Integrity
Structural Integrity
: 7. TVA letter to NRC, dated July 28, 1994, Supplemental Response to TVA letter Dated May 23, 1994, Generic Letter 92-01, Revision 1, Reactor Vessel Structural Integrity
: 6. TVA letter to NRC, dated May 23, 1994, TVA's Response to NRC's Letter Dated April 19, 1994, Generic Letter 92-01, Revision 1 , Reactor Vessel Structural Integrity
: 8. TVA letter to NRC, dated March 27, 1995, Generic Letter 92-01, Reactor Vessel Structural Integrity - Update to the Initial Reference Nil-Ductility Temperature (RTNDT), Chemical Composition and Fluence Values
: 7. TVA letter to NRC, dated July 28, 1994, Supplemental Response to TVA letter Dated  
: 9. NRC letter to TVA, dated May 19, 1995, NRC Generic Letter 92-01, Revision 1, Supplement 1:
 
Reactor Vessel Structural Integrity
May 23, 1994, Generic Letter 92-01, Revision 1, Reactor Vessel Structural Integrity
: 10. TVA letter to NRC, dated August 7, 1995, in regards to Generic Letter 92-01
: 8. TVA letter to NRC, dated March 27, 1995, Generic Letter 92-01, Reactor Vessel Structural  
: 11. TVA letter to NRC, dated November 7, 1995, Response to NRC Generic Letter (GL) 92-01, Revision 1, Supplement 1; Reactor Vessel Structural Integrity - Browns Ferry (BFN),
Watts Bar (WBN), and Sequoyah (SQN) Nuclear Plants
: 12. NRC letter to TVA, dated June 10, 1998, Request for Additional Information Regarding Pressure Vessel Integrity at Browns Ferry Nuclear Plant, Units 1, 2, and 3 (TAC Nos. MA1179, MA1180, and MA1181)
April 13, 2007                  E1-76
: 13. TVA letter to NRC, dated September 8, 1998, Browns Ferry Nuclear Plant (BFN) - Units 1, 2, and 3 - Generic Letter (GL) 92-01, Revision 1, Supplement 1, Reactor Vessel Structural Integrity - Response to NRC Request for Additional Information (TAC Nos. MA1179, MA1180, and MA1181)
: 14. NRC letter to TVA, dated August 10, 2006, Browns Ferry Nuclear Plant Unit 1 Recovery - NRC Integrated Inspection Report 05000259/2006007 April 13, 2007                  E1-77


Integrity - Update to the Initial Reference 
Generic Letter 92-04, Resolution of the Issues Related to Reactor Vessel Water Level Instrumentation in BWRs Commitment:   TVA will continue to support the BWR Owners' Group (BWROG) program of analysis, testing, and development of possible hardware changes which is being conducted by the BWROG.
 
TVA will review the results of the BWROG program for potential training requirements for operators.
Nil-Ductility Temperature (RT NDT), Chemical Composition and Fluence Values
Discussion:   TVA responded to Generic Letter 92-04 by Reference 1. NRC approval of TVA's program for the resolution of Generic Letter 92-04 is documented in Reference 2. Interim training of the operators was provided as documented in Inspection Report 93-16 (Reference 3).
: 9. NRC letter to TVA, dated May 19, 1995, NRC Generic Letter 92-01, Revision 1, Supplement 1:
Long-term actions were addressed as part of the resolution of Bulletin 93 Resolution of Issues Related to Reactor Vessel Water Level Instrumentation in BWRs.
 
Status:       C-C NRC closed this item in Inspection Report 2006-009 (Reference 4).
Reactor Vessel Structural Integrity 1 0. TVA letter to NRC, dated August 7, 1995, in regards to Generic Letter 92-01 1 1. TVA letter to NRC, dated November 7, 1995, Response to NRC Generic Letter (GL) 92-01, Revision 1, Supplement 1; Reactor Vessel
 
Structural Integrity - Browns Ferry (BFN), 
 
Watts Bar (WBN), and Sequoyah (SQN) Nuclear
 
Plants 1 2. NRC letter to TVA, dated June 10, 1998, Request for Additional Information Regarding Pressure
 
Vessel Integrity at Browns Ferry Nuclear Plant, Units 1, 2, and 3 (TAC Nos. MA1179, MA1180, and
 
MA1181)
April 13, 2007 E1-77 1 3. TVA letter to NRC, dated September 8, 1998, Browns Ferry Nuclear Plant (BFN) - Units 1, 2, and 3 - Generic Letter (GL) 92-01, Revision 1, Supplement 1, Reactor Vessel Structural
 
Integrity - Response to NRC Request for
 
Additional Information (TAC Nos. MA1179, MA1180, and MA1181) 1 4. NRC letter to TVA, dated August 10, 2006, Browns Ferry Nuclear Plant Unit 1 Recovery - NRC
 
Integrated Inspection Report 05000259/2006007
 
April 13, 2007 E1-78 Generic Letter 92-04, Resolution of the Issues Related to Reactor Vessel Water Level Instrumentation in BWRs  
 
Commitment: TVA will continue to support the BWR Owners' Group (BWROG) program of analysis, testing, and  
 
development of possible hardware changes which is  
 
being conducted by the BWROG.  
 
TVA will review the results of the BWROG program  
 
for potential training requirements for operators.  
 
Discussion: TVA responded to Generic Letter 92-04 by Reference 1. NRC approval of TVA's program for the  
 
resolution of Generic Letter 92-0 4 is documented in Reference 2. Interim training of the operators was  
 
provided as documented in Inspection Report 93-16 (Reference 3).  
 
Long-term actions were addressed as part of the resolution of Bulletin 93-03 -Resolution of Issues  
 
Related to Reactor Vessel Water Level  
 
Instrumentation in BWRs.  
 
Status: C-C  
 
NRC closed this item in Inspection Report 2006-009 (Reference 4).  


==References:==
==References:==
1.
: 1. TVA letter to NRC, dated September 28, 1992, Response to Generic Letter (GL) 92                   Resolution of the Issues Related to Reactor Vessel Water Level Instrumentation in BWRs
TVA letter to NRC, dated September 28, 1992, Response to Generic Letter (GL) 92  
: 2. NRC letter to TVA, dated March 25, 1993, Response to Generic Letter 92-04, Resolution of the Issues Related to Reactor Vessel Water Level Instrumentation in Boiling Water Reactors
: 3. NRC letter to TVA, dated May 18, 1993, NRC Inspection Report No. 259/93-16, 260/93-16 and 296/93-16
: 4. NRC letter to TVA, dated March 5, 2007, Browns Ferry Nuclear Plant Unit 1 Recovery - NRC Integrated Inspection Report 05000259/2006009 April 13, 2007                  E1-78


Resolution of the Issues Related to Reactor
Generic Letter 94-02, Long-Term Solutions and Upgrade of Interim Operating Recommendations for Thermal-Hydraulic Instabilities in Boiling Water Reactors Commitment:   1. TVA will modify BFN operating procedures and training programs to make them consistent or more conservative than the BWR Owners' Group (BWROG) interim guidelines.
 
: 2. TVA will implement the BWROG Option III methodology for the stability long-term solution.
Vessel Water Level Instrumentation in BWRs
Discussion:   TVA responded to Generic Letter 94-02 in Reference 1. In Reference 2, TVA notified NRC that the Unit 1 procedure revisions would be completed prior to restart. In Reference 3, TVA stated its intent to implement the long-term stability solution on Unit 1 before the restart of that unit.
: 2. NRC letter to TVA, dated March 25, 1993, Response to Generic Letter 92-04, Resolution of
Status:       Closed NRC closed this item in Inspection Report 2006-007 (Reference 4).
 
the Issues Related to Reactor Vessel Water Level
 
Instrumentation in Boiling Water Reactors
: 3. NRC letter to TVA, dated May 18, 1993, NRC Inspection Report No. 259/93-16, 260/93-16 and
 
296/93-16
: 4. NRC letter to TVA, dated March 5, 2007, Browns Ferry Nuclear Plant Unit 1 Recovery - NRC
 
Integrated Inspection Report 05000259/2006009
 
April 13, 2007 E1-79 Generic Letter 94-02, Long-Term Solutions and Upgrade of Interim Operating Recommendations for
 
Thermal-Hydraulic Instabilities in Boiling  
 
Water Reactors  
 
Commitment: 1.
TVA will modify BFN operating procedures and training programs to make them consistent or  
 
more conservative than the BWR Owners'  
 
Group (BWROG) interim guidelines.
: 2. TVA will implement the BWROG Option III methodology for the stability long-term  
 
solution.
 
Discussion: TVA responded to Generic Letter 94-02 in Reference 1. In Reference 2 , TVA notified NRC that the Unit 1 procedure revisions would be completed  
 
prior to restart. In Reference 3, TVA stated its  
 
intent to implement the long-term stability  
 
solution on Unit 1 before the restart of that unit.
 
Status: Closed  
 
NRC closed this item in Inspection Report 2006-007 (Reference 4).  


==References:==
==References:==
1.
: 1. TVA letter to NRC, dated September 8, 1994, Response to NRC Generic Letter (GL) 94                 Long-Term Solutions and Upgrade of Interim Operating Recommendations for Thermal-Hydraulic Instabilities in Boiling Water Reactors
TVA letter to NRC, dated September 8, 1994, Response to NRC Generic Letter (GL) 94  
: 2. TVA letter to NRC, dated December 22, 1994, NRC Generic Letter (GL) 94-02, Long-Term Solutions and Upgrade of Interim Operating Recommendations for Thermal-Hydraulic Instabilities in Boiling Water Reactors - Completion of Requested Action 1, Interim Corrective Actions
 
: 3. TVA letter to NRC, dated October 4, 1995, Browns Ferry Nuclear Plant (BFN) - Units 1, 2, and 3 -
Long-Term Solutions and Upgrade of Interim  
TVA Confirmation of the Installation Schedule for the Stability Long-Term Solution for NRC Generic Letter (GL) 94-02
 
: 4. NRC letter to TVA, dated August 10, 2006, Browns Ferry Nuclear Plant Unit 1 Recovery - NRC Integrated Inspection Report 05000259/2006007 April 13, 2007                  E1-79
Operating Recommendations for Thermal-Hydraulic  
 
Instabilities in Boiling Water Reactors
: 2. TVA letter to NRC, dated December 22, 1994, NRC Generic Letter (GL) 94-02, Long-Term Solutions  
 
and Upgrade of Interim Operating Recommendations  
 
for Thermal-Hydraulic Instabilities in Boiling  
 
Water Reactors - Completion of Requested  
 
Action 1, Interim Corrective Actions
: 3. TVA letter to NRC, dated October 4, 1995, Browns Ferry Nuclear Plant (BFN) - Units 1, 2, and 3 -  


TVA Confirmation of the Installation Schedule
Generic Letter 94-03, Intergranular Stress Corrosion Cracking of Core Shrouds in Boiling Water Reactors Commitment:   TVA will inspect 100% of the accessible areas on core shroud welds Hl through H7. The inspections will be conducted using the best available technology (i.e., Smart-2000 system, suction cup scanners, Westinghouse 1250 camera, etc.) prior to restart.
 
Discussion:   In Reference 1, TVA committed to inspect the accessible areas of the core shroud prior to Unit 1 restart. The NRC's Safety Evaluation is contained in Reference 2.
for the Stability Long-Term Solution for NRC
Status:       C-C TVA inspected 100% of the accessible areas on core shroud welds Hl through H7. A structural margin analysis of the core shroud inspections results was performed. This analysis determined Unit 1 can resume operation without repair.
 
NRC closed this item in Inspection Report 2005-008 (Reference 3).
Generic Letter (GL) 94-02
: 4. NRC letter to TVA, dated August 10, 2006, Browns Ferry Nuclear Plant Unit 1 Recovery - NRC
 
Integrated Inspection Report 05000259/2006007
 
April 13, 2007 E1-80 Generic Letter 94-03, Intergranular Stress Corrosion Cracking of Core Shrouds in Boiling Water Reactors  
 
Commitment: TVA will inspect 100% of the accessible areas on core shroud welds Hl through H7. The inspections  
 
will be conducted using the best available  
 
technology (i.e., Smart-2000 system, suction cup  
 
scanners, Westinghouse 1250 camera, etc.) prior to  
 
restart.
Discussion: In Reference 1, TVA committed to inspect the accessible areas of the core shroud prior to Unit 1 restart. The NRC's Safety Evaluation is contained  
 
in Reference 2.  
 
Status: C-C  
 
TVA inspected 100% of the accessible areas on core  
 
shroud welds Hl through H7. A structural margin  
 
analysis of the core shroud inspections results was  
 
performed. This analysis determined Unit 1 can  
 
resume operation without repair.  
 
NRC closed this item in Inspection Report 2005-008 (Reference 3).  


==References:==
==References:==
1.
: 1. TVA letter to NRC, dated August 23, 1994, Response to NRC Generic Letter (GL) 94                   Intergranular Stress Corrosion Cracking (IGSCC) of Shrouds in Boiling Water Reactors.
TVA letter to NRC, dated August 23, 1994, Response to NRC Generic Letter (GL) 94  
: 2. NRC letter to TVA, dated January 13, 1995, Browns Ferry Nuclear Plant Units 1, 2, and 3 Safety Evaluation of Response to Generic Letter 94-03 (IGSCC of Core Shroud in BWRs)
: 3. NRC letter to TVA, dated November 14, 2005, Browns Ferry Nuclear Plant Unit 1 Recovery - NRC Integrated Inspection Report 05000259/2005008 April 13, 2007                  E1-80


Intergranular Stress Corrosion Cracking (IGSCC)
Generic Letter 95-07, Pressure Locking and Thermal Binding of Safety-Related Power-Operated Gate Valves Commitment:   Unit 1 will be evaluated for the requirements of Generic Letter 95-07 prior to restart.
 
Discussion:   TVA provided response to NRC in References 1 through 5 for BFN Units 2 and 3, Sequoyah Units 1 and 2, and Watts Bar. The NRCs Safety Evaluation for Generic Letter 95-07 was provided in Reference 6.
of Shrouds in Boiling Water Reactors.
TVA responded to Generic Letter 95-07 for BFN Unit 1 in Reference 7 and provided additional information in Reference 8. The review methodology used for Unit 1 is the same as that used for TVAs other operating nuclear plants.
: 2. NRC letter to TVA, dated January 13, 1995, Browns Ferry Nuclear Plant Units 1, 2, and 3
The safety related power operated gate valves in Unit 1 have been reviewed for potential susceptibility to the pressure locking and thermal binding phenomenon. There is one High Pressure Coolant Injection valve in Unit 1 which is susceptible to thermal binding. Prior to restart, this valve was replaced with a double disc valve of similar design as Units 2 and 3. Two Core Spray minimum flow valves in Unit 1 were replaced with double disc valves prior to Unit 1 restart. In addition, five safety related power operated gate valves were modified prior to Unit 1 restart to preclude the potential for pressure locking. The reactor side disc face of these five valves was modified by drilling a hole in the disc face into the cavity between the disc faces to avoid pressure locking. NRC found TVAs responses to be an acceptable resolution to the GL 95-07 concerns (Reference 9).
 
Status:       C-C NRC closed this item in Inspection Report 2006-006 (Reference 10).
Safety Evaluation of Response to Generic Letter
 
94-03 (IGSCC of Core Shroud in BWRs)
: 3. NRC letter to TVA, dated November 14, 2005, Browns Ferry Nuclear Plant Unit 1 Recovery -NRC
 
Integrated Inspection Report 05000259/2005008
 
April 13, 2007 E1-81 Generic Letter 95-07, Pressure Locking and Thermal Binding of Safety-Related Power-Operated Gate Valves  
 
Commitment: Unit 1 will be evaluated for the requirements of Generic Letter 95-07 prior to restart.  
 
Discussion: TVA provided response to NRC in References 1 through 5 for BFN Units 2 and 3, Sequoyah Units 1  
 
and 2, and Watts Bar. The NRC's Safety Evaluation  
 
for Generic Letter 95-07 was provided in  
 
Reference 6.  
 
TVA responded to Generic Letter 95-07 for BFN  
 
Unit 1 in Reference 7 and provided additional  
 
information in Reference
: 8. The review methodology used for Unit 1 is the same as that used for TVA's
 
other operating nuclear plants.  
 
The safety related power operated gate valves in  
 
Unit 1 have been reviewed for potential  
 
susceptibility to the pressure locking and thermal  
 
binding phenomenon. There is one High Pressure  
 
Coolant Injection valve in Unit 1 which is  
 
susceptible to thermal binding. Prior to restart, this valve wasreplaced with a double disc valve of  
 
similar design as Units 2 and 3. Two Core Spray  
 
minimum flow valves in Unit 1 were replaced with  
 
double disc valves prior to Unit 1 restart. In  
 
addition, five safety related power operated gate  
 
valves were modified prior to Unit 1 restart to  
 
preclude the potential for pressure locking. The  
 
reactor side disc face of these five valves was  
 
modified by drilling a hole in the disc face into  
 
the cavity between the disc faces to avoid pressure  
 
locking. NRC found TVA's responses to be an  
 
acceptable resolution to the GL 95-07 concerns (Reference 9).  
 
Status: C-C  
 
NRC closed this item in Inspection Report 2006-006 (Reference 10).  


==References:==
==References:==
1.
: 1. TVA letter to NRC, dated October 16, 1995, Browns Ferry (BFN), Sequoyah (SQN), and Watts Bar (WBN) Nuclear Plants - Response to Generic Letter, Pressure Locking and Thermal Binding of Safety-Related Power-Operated Gate Valves April 13, 2007                   E1-81
TVA letter to NRC, dated October 16, 1995, Browns Ferry (BFN), Sequoyah (SQN), and Watts  
: 2. TVA letter to NRC, dated December 15, 1995, Browns Ferry (BFN), Sequoyah (SQN), and Watts Bar (WBN) Nuclear Plants - Supplemental Response to Generic Letter, Pressure Locking and Thermal Binding of Safety-Related Power-Operated Gate Valves
 
: 3. TVA letter to NRC, dated February 13, 1996, Browns Ferry (BFN), Sequoyah (SQN), and Watts Bar (WBN) Nuclear Plants - 180-Day Response to Generic Letter, Pressure Locking and Thermal Binding of Safety-Related Power-Operated Gate Valves
Bar (WBN) Nuclear Plants - Response to Generic  
: 4. TVA letter to NRC, dated July 30, 1996, Browns Ferry Nuclear Plant (BFN) - Units 2 and 3, Pressure Locking and Thermal Binding of Safety-Related Power-Operated Gate Valves - Response to Request for Additional Information (TAC Nos. M93437 and M93438)
 
: 5. TVA letter to NRC, dated February 19, 1999, Browns Ferry Nuclear Plant (BFN) - Units 2 and 3
Letter, Pressure Locking and Thermal Binding of  
                - Generic Letter (GL) 95-07, Pressure Locking and Thermal Binding of Safety-Related Power-Operated Gate Valves - Supplemental Response (TAC Nos. M93437 and M93438)
 
: 6. NRC letter to TVA, dated June 23, 1999, Safety Evaluation for Generic Letter, Pressure Locking and Thermal Binding of Safety-Related Power-Operated Gate Valves, Browns Ferry Nuclear Plant (BFN) - (TAC Nos. M93436, M93437 and M93438)
Safety-Related Power-Operated Gate Valves  
: 7. TVA letter to NRC, dated May 11, 2004, Browns Ferry Nuclear Plant (BFN) Unit 1 - Generic Letter 95-07, Pressure Locking and Thermal Binding of Safety-Related Power-Operated Gate Valves
 
: 8. TVA letter to NRC, dated July 29, 2004, Browns Ferry Nuclear Plant (BFN) Unit 1 - Response to Request for Additional Information Regarding Generic Letter 95-07, Pressure Locking and Thermal Binding of Safety-Related Power Operated Gate Valves
April 13, 2007 E1-82
: 9. NRC letter to TVA, dated January 28, 2005, Browns Ferry Nuclear Plant, Unit 1 - Closeout of Generic Letter 95-07, Pressure Locking and Thermal Binding of Safety-Related Power-Operated Gate Valves, Browns Ferry Nuclear Plant, Unit 1 (TAC No. MC3125)
: 2. TVA letter to NRC, dated December 15, 1995, Browns Ferry (BFN), Sequoyah (SQN), and Watts Bar (WBN) Nuclear Plants -Supplemental Response  
: 10. NRC letter to TVA, dated May 15, 2006, Browns Ferry Nuclear Plant Unit 1 Recovery - NRC Integrated Inspection Report 05000259/2006006 April 13, 2007                  E1-82


to Generic Letter, Pressure Locking and Thermal
Generic Letter 96-01, Testing of Safety-Related Logic Circuits Commitment:   BFN Unit 1 will implement the recommendations of Generic Letter 96-01 prior to restart.
 
Discussion:   TVA committed to implement the recommendations of Generic Letter 96-01 prior to restart in Reference 1.
Binding of Safety-Related Power-Operated Gate
Status:       Closed NRC closed this item in Inspection Report 2006-009 (Reference 2).
 
Valves 3. TVA letter to NRC, dated February 13, 1996, Browns Ferry (BFN), Sequoyah (SQN), and Watts
 
Bar (WBN) Nuclear Plants - 180-Day Response to
 
Generic Letter, Pressure Locking and Thermal
 
Binding of Safety-Related Power-Operated Gate
 
Valves 4. TVA letter to NRC, dated July 30, 1996, Browns Ferry Nuclear Plant (BFN) - Units 2 and 3, Pressure Locking and Thermal Binding of Safety-
 
Related Power-Operated Gate Valves - Response to
 
Request for Additional Information (TAC Nos. M93437 and M93438)
: 5. TVA letter to NRC, dated February 19, 1999, Browns Ferry Nuclear Plant (BFN) - Units 2 and 3
- Generic Letter (GL) 95-07, Pressure Locking
 
and Thermal Binding of Safety-Related Power-
 
Operated Gate Valves - Supplemental Response (TAC Nos. M93437 and M93438)
: 6. NRC letter to TVA, dated June 23, 1999, Safety Evaluation for Generic Letter, Pressure Locking
 
and Thermal Binding of Safety-Related Power-
 
Operated Gate Valves, Browns Ferry Nuclear Plant (BFN) - (TAC Nos. M93436, M93437 and M93438)
: 7. TVA letter to NRC, dated May 11, 2004, Browns Ferry Nuclear Plant (BFN) Unit 1 - Generic
 
Letter 95-07, Pressure Locking and Thermal
 
Binding of Safety-Related Power-Operated Gate
 
Valves 8. TVA letter to NRC, dated July 29, 2004, Browns Ferry Nuclear Plant (BFN) Unit 1 - Response to
 
Request for Additional Information Regarding
 
Generic Letter 95-07, Pressure Locking and
 
Thermal Binding of Safety-R elated Power Operated Gate Valves
: 9. NRC letter to TVA, dated January 28, 2005, Browns Ferry Nuclear Plant, Unit 1 - Closeout of
 
Generic Letter 95-07, "Pressure Locking and
 
Thermal Binding of Safety-Related Power-Operated
 
Gate Valves," Browns Ferry Nuclear Plant, Unit 1 (TAC No. MC3125) 1 0. NRC letter to TVA, dated May 15, 2006, Browns Ferry Nuclear Plant Unit 1 Recovery - NRC
 
Integrated Inspection Report 05000259/2006006
.
April 13, 2007 E1-83 Generic Letter 96-01, Testing of Safety-Related Logic Circuits  
 
Commitment: BFN Unit 1 will implement the recommendations of Generic Letter 96-01 prior to restart.  
 
Discussion: TVA committed to implement the recommendations of Generic Letter 96-01 prior to restart in  
 
Reference 1.  
 
Status: Closed  
 
NRC closed this item in Inspection Report 2006-009 (Reference 2).  


==References:==
==References:==
1.
: 1. TVA letter to NRC, dated April 18, 1996, Response to Generic Letter (GL) 96-01, Testing of Safety-Related Logic Circuits (TAC Nos.
TVA letter to NRC, dated April 18, 1996, Response to Generic Letter (GL) 96-01, Testing  
 
of Safety-Related Logic Circuits (TAC Nos.  
 
M94650, M94651, M95652, M94732, M94733, M94750)
M94650, M94651, M95652, M94732, M94733, M94750)
: 2. NRC letter to TVA, dated March 5, 2007, Browns Ferry Nuclear Plant Unit 1 Recovery - NRC  
: 2. NRC letter to TVA, dated March 5, 2007, Browns Ferry Nuclear Plant Unit 1 Recovery - NRC Integrated Inspection Report 05000259/2006009 April 13, 2007                 E1-83
 
Integrated Inspection Report 05000259/2006009  
 
April 13, 2007 E1-84 Generic Letter 96-05, Periodic Verification of Design-Basis Capability of Motor-Operated Valves
 
Commitment: BFN Unit 1 will implement the Joint Owner's Group recommended GL 96-0 5 Periodic Verification Program, and begin testing during the first refueling outage
 
after restart.
 
Discussion: TVA responded for all its nuclear facilities in Reference 1 and supplemented the response in
 
Reference 2. TVA was a member of the Joint Owners'
 
Group (JOG), which culminated in the dynamic
 
testing of 176 Motor Operated Valves (MOVs) at 98
 
BWR and PWR plants. Each valve was tested three
 
times over five years to address potential
 
degradation in required thrust or torque. The
 
final Topical Report and recommendations for


periodic testing were submitted by Reference
Generic Letter 96-05, Periodic Verification of Design-Basis Capability of Motor-Operated Valves Commitment:  BFN Unit 1 will implement the Joint Owners Group recommended GL 96-05 Periodic Verification Program, and begin testing during the first refueling outage after restart.
: 3. No additional interim testing is required for Unit 1  
Discussion:  TVA responded for all its nuclear facilities in Reference 1 and supplemented the response in Reference 2. TVA was a member of the Joint Owners Group (JOG), which culminated in the dynamic testing of 176 Motor Operated Valves (MOVs) at 98 BWR and PWR plants. Each valve was tested three times over five years to address potential degradation in required thrust or torque. The final Topical Report and recommendations for periodic testing were submitted by Reference 3. No additional interim testing is required for Unit 1 since the industry program has been completed.
 
Status:       C-C NRC closed this item in Inspection Report 2005-009 (Reference 4).
since the industry program has been completed.  
 
Status: C-C  
 
NRC closed this item in Inspection Report 2005-009 (Reference 4).  


==References:==
==References:==
1.
: 1. TVA letter to NRC, dated March 17, 1997, Browns Ferry Nuclear Plant (BFN) (TAC Nos. M97020, M97021, M97022), Sequoyah Nuclear Plant (SQN),
TVA letter to NRC, dated March 17, 1997, Browns Ferry Nuclear Plant (BFN) (TAC Nos. M97020, M97021, M97022), Sequoyah Nuclear Plant (SQN),
Watts Bar Nuclear Plant (WBN), and Bellefonte Nuclear Plant (BLN) 180-Day Response to NRC Generic Letter (GL) 96-05, Periodic Verification of Design-Basis Capability of Safety-Related Motor-Operated Valves, Dated September 18, 1996
Watts Bar Nuclear Plant (WBN), and Bellefonte  
 
Nuclear Plant (BLN) 180-Day Response to NRC  
 
Generic Letter (GL) 96-0 5, Periodic Verification of Design-Basis Capability of Safety-Related  
 
Motor-Operated Valves, Dated September 18, 1996
: 2. TVA letter to NRC, dated April 28, 1998, Browns Ferry Nuclear Plant (BFN) (TAC Nos. M97020, M97021, M97022), Sequoyah Nuclear Plant (SQN),
: 2. TVA letter to NRC, dated April 28, 1998, Browns Ferry Nuclear Plant (BFN) (TAC Nos. M97020, M97021, M97022), Sequoyah Nuclear Plant (SQN),
Watts Bar Nuclear Plant (WBN), and Bellefonte  
Watts Bar Nuclear Plant (WBN), and Bellefonte Nuclear Plant (BLN) Response to NRC's Safety Evaluation Dated October 30, 1997, on Joint Owners Group's (JOG) Program for Generic Letter (GL) 96-05, Periodic Verification (PV) of Motor-Operated Valves (MOV) Described in Topical Report MPR-1807 (Revision 2)
 
: 3. JOG letter to NRC, dated February 27, 2004, Joint Owners Group Program on Motor-Operated Valve Periodic Verification
Nuclear Plant (BLN) Response to NRC's Safety  
: 4. NRC letter to TVA, dated February 13, 2006, Browns Ferry Nuclear Plant Unit 1 Recovery - NRC Integrated Inspection Report 05000259/2005009 April 13, 2007                  E1-84
 
Evaluation Dated October 30, 1997, on Joint  


Owners Group's (JOG) Program for Generic Letter (GL) 96-05, Periodic Verification (PV) of
Generic Letter 96-06, Assurance of Equipment Operability and Containment Integrity During Design-Basis Accident Conditions Commitment:  TVA will address Generic Letter 96-06 prior to restart.
Discussion:  On September 30, 1996, NRC issued Generic Letter 96-06, which requested licensees address the susceptibility for waterhammer and two-phase flow in the containment air cooler system and over pressurization of piping that penetrates containment.
As described in Reference 1, TVA evaluated the Unit 1 containment air cooler cooling water systems to determine if they are susceptible to either water hammer or two-phase flow conditions during postulated accident conditions. TVA has also evaluated piping systems that penetrate containment to determine if they are susceptible to thermal expansion of fluid such that overpressurization of piping may occur. Two commitments resulted from this evaluation:
The Drywell Floor and Equipment Drains system is acceptable based on leakage through valves which will avoid thermally induced pressure increases above the rated design pressure of the system.
However, TVA will modify the system to provide a designed method of overpressure protection.
The Demineralized Water system has the potential to be affected by overpressurization during a postulated LOCA if the piping is completely filled with water and isolated. In response, TVA will implement procedure changes to assure the system is sufficiently drained following use and is open to containment during power operation.
In Reference 2, NRC stated that TVA had provided an acceptable resolution to the concerns of the Generic Letter.
April 13, 2007                  E1-85


Motor-Operated Valves (MOV) Described in Topical
Status:       C-C
 
* TVA modified the Drywell Floor and Equipment Drains system to provide a designed method of overpressure protection.
Report MPR-1807 (Revision 2)
* Demineralized water piping in the Unit 1 drywell has been either removed or abandoned. Procedure changes were not required.
: 3. JOG letter to NRC, dated February 27, 2004, Joint Owners Group Program on Motor-Operated
NRC closed this item in Inspection Report 2005-008 (Reference 3).
 
Valve Periodic Verification
: 4. NRC letter to TVA, dated February 13, 2006, Browns Ferry Nuclear Plant Unit 1 Recovery -NRC
 
Integrated Inspection Report 05000259/2005009
 
April 13, 2007 E1-85 Generic Letter 96-06, Assurance of Equipment Operability and Containment Integrity During Design-Basis
 
Accident Conditions
 
Commitment: TVA will address Generic Letter 96-06 prior to restart.
Discussion: On September 30, 1996, NRC issued Generic Letter 96-06, which requested licensees address the
 
susceptibility for waterhammer and two-phase flow
 
in the containment air cooler system and over
 
pressurization of piping that penetrates
 
containment.
 
As described in Reference 1, TVA evaluated the
 
Unit 1 cont a inment air cooler cooling water systems to determine if they are susceptible to either
 
water hammer or two-phase flow conditions during
 
postulated accident conditions. TVA has also
 
evaluated piping systems that penetrate containment
 
to determine if they are susceptible to thermal
 
expansion of fluid such that overpressurization of
 
piping may occur. Two commitments resulted from
 
this evaluation:
 
The Drywell Floor and Equipment Drains system is acceptable based on leakage through valves which
 
will avoid thermally induced pressure increases
 
above the rated design pressure of the system. 
 
However, TVA will modify the system to provide a
 
designed method of overpressure protection.
The Demineralized Water system has the potential to be affected by overpressurization during a
 
postulated LOCA if the piping is completely
 
filled with water and isolated. In response, TVA will implement procedure changes to assure
 
the system is sufficiently drained following use
 
and is open to containment during power
 
operation.
 
In Reference 2 , NRC stated that TVA had provided an acceptable resolution to the concerns of the
 
Generic Letter.
 
April 13, 2007 E1-86 Status: C-C TVA modified the Drywell Floor and Equipment Drains system to provide a designed method of  
 
overpressure protection.
Demineraliz e d water piping in the Unit 1 drywell has been either removed or abandoned. Procedure  
 
changes were not required.  
 
NRC closed this item in Inspection Report 2005-008 (Reference 3).  


==References:==
==References:==
1.
: 1. TVA letter to NRC, dated May 12, 2004, Browns Ferry Nuclear Plant (BFN) Unit 1 - Generic Letter 96-06, Assurance of Equipment Operability and Containment Integrity During Design Basis Accident Conditions
TVA letter to NRC, dated May 12, 2004, Browns Ferry Nuclear Plant (BFN) Unit 1 - Generic  
: 2. NRC letter to TVA, dated February 7, 2005, Browns Ferry Nuclear Plant, Unit 1 - Closeout of Generic Letter 96-06, Assurance of Equipment Operability and Containment Integrity During Design-basis Accident Conditions (TAC No. MC3186)
 
: 3. NRC letter to TVA, dated November 14, 2005, Browns Ferry Nuclear Plant Unit 1 Recovery - NRC Integrated Inspection Report 05000259/2005008 April 13, 2007                   E1-86
Letter 96-0 6, Assurance of Equipment Operability and Containment Integrity During Design Basis  
 
Accident Conditions
: 2. NRC letter to TVA, dated February 7, 2005, Browns Ferry Nuclear Plant, Unit 1 - Closeout of  
 
Generic Letter 96-06, "Assurance of Equipment  
 
Operability and Containment Integrity During  
 
Design-basis Accident Conditions" (TAC No. MC3186)
: 3. NRC letter to TVA, dated November 14, 2005, Browns Ferry Nuclear Plant Unit 1 Recovery -NRC  
 
Integrated Inspection Report 05000259/2005008  
 
April 13, 2007 E1-87 Generic Letter 97-04, Assurance Of Sufficient Net Positive Suction Head For Emergency Core Cooling and
 
Containment Heat Removal Pumps
 
Commitment: TVA will address Generic Letter 97-04 prior to restart.
Discussion: On October 7, 1997, NRC issued Generic Letter 97-04, which requested licensees review the current
 
design-basis analyses used to determine the
 
available net positive suction head for the
 
emergency core cooling (including core spray and
 
decay heat removal) and containment heat removal
 
pumps.
 
TVA replied to Generic Letter 97-04 for BFN Unit 1
 
in Reference 1. TVA stated that it would request
 
approval to credit containment overpressure as part
 
of proposed Technical Specifications (TS) 431, the
 
BFN Unit 1 Extended Power Uprate application, which
 
was submitted in Reference 2.
U pon approval of the requested change, no additional information should
 
be required to close Generic Letter 97-04 for BFN
 
Unit 1.
Status: C-C
 
In a letter dated July 26, 2006 (Reference 3), NRR
 
issued an SER concluding BFN has satisfied this


Bulletin.  
Generic Letter 97-04, Assurance Of Sufficient Net Positive Suction Head For Emergency Core Cooling and Containment Heat Removal Pumps Commitment:  TVA will address Generic Letter 97-04 prior to restart.
 
Discussion:  On October 7, 1997, NRC issued Generic Letter 97-04, which requested licensees review the current design-basis analyses used to determine the available net positive suction head for the emergency core cooling (including core spray and decay heat removal) and containment heat removal pumps.
NRC closed this item in Inspection Report 2006-009 (Reference 4).  
TVA replied to Generic Letter 97-04 for BFN Unit 1 in Reference 1. TVA stated that it would request approval to credit containment overpressure as part of proposed Technical Specifications (TS) 431, the BFN Unit 1 Extended Power Uprate application, which was submitted in Reference 2. Upon approval of the requested change, no additional information should be required to close Generic Letter 97-04 for BFN Unit 1.
Status:      C-C In a letter dated July 26, 2006 (Reference 3), NRR issued an SER concluding BFN has satisfied this Bulletin.
NRC closed this item in Inspection Report 2006-009 (Reference 4).


==References:==
==References:==
1.
: 1. TVA letter to NRC, dated May 6, 2004, Browns Ferry Nuclear Plant (BFN) Unit 1 - Response to NRC Generic Letter (GL) 97-04, Assurance of Sufficient Net Positive Suction Head (NPSH) for Emergency Core Cooling and Containment Heat Removal Pumps
TVA letter to NRC, dated May 6, 2004, Browns Ferry Nuclear Plant (BFN) Unit 1 - Response to  
: 2. TVA letter to NRC, Browns Ferry Nuclear Plant (BFN) - Unit 1- Proposed Technical Specifications (TS) Change TS - 431 - Request For License Amendment - Extended Power Uprate (EPU) Operation, dated June 28, 2004 April 13, 2007                  E1-87
 
: 3. NRC Letter to TVA, dated July 27, 2006, Browns Ferry Nuclear Plant, Unit 1 - Review of Licensee Response To NRC Generic Letter 97-04, Assurance Of Sufficient Net Positive Suction Head for Emergency Core Cooling And Containment Heat Removal Pumps (TAC No. MC3392)
NRC Generic Letter (GL) 97-04, Assurance of  
: 4. NRC letter to TVA, dated March 5, 2007, Browns Ferry Nuclear Plant Unit 1 Recovery - NRC Integrated Inspection Report 05000259/2006009 April 13, 2007                  E1-88
 
Sufficient Net Positive Suction Head (NPSH) for


Emergency Core Cooling and Containment Heat
Generic Letter 98-01, Year 2000 Readiness of Computer Systems at Nuclear Power Plants Commitment:   None Discussion:   Generic Letter 98-01 requested information regarding year 2000 readiness at nuclear power plants. TVA certified the readiness of its nuclear facilities in Reference 1. In Reference 2, the NRC concluded that all requested information had been provided. Therefore, NRC considered GL 98-01 to be closed for TVAs nuclear facilities.
 
Status:       C-C NRC closed this item in Inspection Report 2005-006 (Reference 3).
Removal Pumps
: 2. TVA letter to NRC, "Browns Ferry Nuclear Plant (BFN) - Unit 1- Proposed Technical
 
Specifications (TS) Change TS - 431 - Request
 
For License Amendment - Extended Power Uprate (EPU) Operation," dated June 28, 2004 April 13, 2007 E1-88
: 3. NRC Letter to TVA, dated July 27, 2006, Browns Ferry Nuclear Plant, Unit 1 -Review of Licensee
 
Response To NRC Generic Letter 97-04, "Assurance
 
Of Sufficient Net Positive Suction Head for
 
Emergency Core Cooling And Containment Heat
 
Removal Pumps" (TAC No. MC3392)
: 4. NRC letter to TVA, dated March 5, 2007, Browns Ferry Nuclear Plant Unit 1 Recovery - NRC
 
Integrated Inspection Report 05000259/2006009
 
April 13, 2007 E1-89 Generic Letter 98-01, Year 2000 Readiness of Computer Systems at Nuclear Power Plants  
 
Commitment: None  
 
Discussion: Generic Letter 98-01 requested information regarding year 2000 readiness at nuclear power  
 
plants. TVA certified the readiness of its nuclear  
 
facilities in Reference 1. In Reference 2, the NRC  
 
concluded that all requested information had been  
 
provided. Therefore, NRC considered GL 98-01 to  
 
be closed for TVA's nuclear facilities.  
 
Status: C-C  
 
NRC closed this item in Inspection Report 2005-006 (Reference 3).  


==References:==
==References:==
1.
: 1. TVA letter to NRC, dated June 29, 1999, Browns Ferry Nuclear Plant (BFN) Units 1, 2, and 3, Sequoyah Nuclear Plant (SQN) Units 1 and 2, Watts Bar Nuclear Plant (WBN) Unit 1, Final Response to Generic Letter (GL) 98-01, Year 2000 (Y2K) Readiness of Computer Systems at Nuclear Power Plants
TVA letter to NRC, dated June 29, 1999, Browns Ferry Nuclear Plant (BFN) Units 1, 2, and 3, Sequoyah Nuclear Plant (SQN) Units 1 and 2, Watts Bar Nuclear Plant (WBN) Unit 1, Final  
: 2. NRC letter to TVA, dated October 18, 1999, Watts Bar, Browns Ferry and Sequoyah - Response to Generic Letter 98-01, "Year 2000 Readiness of Computer Systems at Nuclear Power Plants" (TAC Nos. MA1810, MA1811, MA1812, MAl888, MA1889 and MA1906)
 
: 3. NRC letter to TVA, dated May 16, 2005, Browns Ferry Nuclear Plant Unit 1 Recovery -
Response to Generic Letter (GL) 98-01, Year 2000 (Y2K) Readiness of Computer Systems at Nuclear  
NRC Integrated Inspection Report 05000259/2005006 April 13, 2007                  E1-89
 
Power Plants
: 2. NRC letter to TVA, dated October 18, 1999, Watts Bar, Browns Ferry and Sequoyah - Response to  
 
Generic Letter 98-01, "Year 2000 Readiness of  


Computer Systems at Nuclear Power Plants" (TAC Nos. MA1810, MA1811, MA1812, MAl888, MA1889
Generic Letter 98-04, Potential for Degradation of the Emergency Core Cooling System and the Containment Spray System after a Loss-Of-Coolant Accident Because of Construction and Protective Coating Deficiencies and Foreign Material in Containment Commitment:   TVA will address Generic Letter 98-04 prior to restart.
 
Discussion:   NRC issued GL 98-04 to alert licensees to concerns with the material condition of Service Level 1 protective coatings inside the containment.
and MA1906)
GL 98-04 requested that licensees describe their programs for ensuring that Service Level 1 protective coatings inside containment do not detach from their substrate and adversely affect the ability of the Emergency Core Cooling Systems (ECCS) and the safety-related Containment Spray System to perform their function following a Design Basis Loss of Coolant Accident (LOCA).
: 3. NRC letter to TVA, dated May 16, 2005, Browns Ferry Nuclear Plant Unit 1 Recovery - 
TVA responded to GL 98-04 for Unit 1 in Reference 1. In summary, TVA has implemented controls for the procurement, application, and maintenance of Service Level 1 protective coatings used inside the primary containment in a manner that is consistent with the licensing basis and regulatory requirements applicable to BFN. The NRC Safety Evaluation (Reference 3) concluded that BFN had provided the information required by GL 98-04.
 
Status:       C-C IR 2006-006 (Reference 2) stated However, final closure of this item will be deferred until NRR completes their review in this area.
NRC Integrated Inspection Report
NRC closed this item in Inspection Report 2006-008 (Reference 4).
 
05000259/2005006
 
April 13, 2007 E1-90 Generic Letter 98-04, Potential for Degradation of the Emergency Core Cooling System and the Containment  
 
Spray System after a Loss-Of-Coolant  
 
Accident Because of Construction and  
 
Protective Coating Deficiencies and Foreign  
 
Material in Containment  
 
Commitment: TVA will address Generic Letter 98-04 prior to restart.
Discussion: NRC issued GL 98-04 to alert licensees to concerns with the material condition of Service Level 1  
 
protective coatings inside the containment.  
 
GL 98-04 requested that licensees describe their  
 
programs for ensuring that Service Level 1  
 
protective coatings inside containment do not  
 
detach from their substrate and adversely affect  
 
the ability of the Emergency Core Cooling Systems (ECCS) and the safety-related Containment Spray  
 
System to perform their function following a Design  
 
Basis Loss of Coolant Accident (LOCA).  
 
TVA responded to GL 98-04 for Unit 1 in  
 
Reference 1. In summary, TVA has implemented  
 
controls for the procurement, application, and  
 
maintenance of Service Level 1 protective coatings  
 
used inside the primary containment in a manner  
 
that is consistent with the licensing basis and  
 
regulatory requirements applicable to BFN. The NRC  
 
Safety Evaluation (Reference 3) concluded that BFN  
 
had provided the information required by GL 98-04.  
 
Status: C-C IR 2006-006 (Reference 2) stated "- However, final closure of this item will be deferred until NRR  
 
completes their review in this area."
 
NRC closed this item in Inspection Report 2006-008 (Reference 4).  


==References:==
==References:==
1.
: 1. TVA letter to NRC, dated May 11, 2004, Browns Ferry Nuclear Plant (BFN) Unit 1 - Response to NRC Generic Letter (GL) 98-04, Potential for Degradation of the Emergency Core Cooling System and the Containment Spray System After a Loss-Of-Coolant Accident Because of Construction and Protective Coating Deficiencies and Foreign Material in Containment
TVA letter to NRC, dated May 11, 2004, Browns Ferry Nuclear Plant (BFN) Unit 1 - Response to  
: 2. NRC letter to TVA, dated May 15, 2006, Browns Ferry Nuclear Plant Unit 1 Recovery - NRC April 13, 2007                  E1-90


NRC Generic Letter (GL) 98-04, Potential for  
Integrated Inspection Report 05000259/2006006
 
: 3. NRC letter to TVA dated September 27, 2006, Browns Ferry Nuclear Plant, Unit 1 - Review of Licensee Response to NRC Generic Letter 98-04, Potential for Degradation of the Emergency Core Cooling System and the Containment Spray System After a Loss-Of-Coolant Accident Because of Construction and Protective Coating Deficiencies and Foreign Material in Containment
Degradation of the Emergency Core Cooling System  
: 4. NRC letter to TVA, dated November 9, 2006, Browns Ferry Nuclear Plant Unit 1 Recovery - NRC Integrated Inspection Report 05000259/2006008 April 13, 2007                  E1-91
 
and the Containment Spray System After a Loss-
 
Of-Coolant Accident Because of Construction and  


Protective Coating Deficiencies and Foreign
Generic Letter 2003-01, Control Room Habitability Commitment:   TVA will address Generic Letter 2003-01 prior to restart.
 
Discussion:   NRC issued GL 2003-01 to:
Material in Containment
: 1. alert addressees to findings at U.S. power reactor facilities suggesting that the control room licensing and design bases, and applicable regulatory requirements may not be met, and that existing technical specification surveillance requirements (SRs) may not be adequate,
: 2. NRC letter to TVA, dated May 15, 2006, Browns Ferry Nuclear Plant Unit 1 Recovery - NRC April 13, 2007 E1-91 Integrated Inspection Report 05000259/2006006
: 2. emphasize the importance of reliable, comprehensive surveillance testing to verify control room habitability,
: 3. NRC letter to TVA dated September 27, 2006, Browns Ferry Nuclear Plant, Unit 1 - Review of
: 3. request addressees to submit information that demonstrates that the control room at each of their respective facilities complies with the current licensing and design bases, and applicable regulatory requirements, and that suitable design, maintenance and testing control measures are in place for maintaining this compliance, and
 
: 4. collect the requested information to determine if additional regulatory action is required.
Licensee Response to NRC Generic Letter 98-04, "Potential for Degradation of the Emergency Core
TVA responded to GL 2003-01 in Reference 1. In summary, the BFN Units 1, 2, and 3 design basis and licensing basis are in compliance with the applicable regulatory requirements. The plant is constructed and maintained in accordance with its design, and the testing performed in accordance with the BFN Technical Specifications (TS) and their bases is adequate to demonstrate this compliance and material condition.
 
In Reference 2, the NRC provided a request for additional information (RAI) to TVA. TVA answered this RAI in Reference 3.
Cooling System and the Containment Spray System
Status:       Complete April 13, 2007                   E1-92
 
After a Loss-Of-Coolant Accident Because of
 
Construction and Protective Coating Deficiencies
 
and Foreign Material in Containment"
: 4. NRC letter to TVA, dated November 9, 2006, Browns Ferry Nuclear Plant Unit 1 Recovery -NRC
 
Integrated Inspection Report 05000259/2006008
 
April 13, 2007 E1-92 Generic Letter 2003-01, Control Room Habitability  
 
Commitment: TVA will address Generic Letter 2003-01 prior to restart.
Discussion: NRC issued GL 2003-01 to:
: 1. alert addressees to findings at U.S. power reactor facilities suggesting that the control  
 
room licensing and design bases, and applicable  
 
regulatory requirements may not be met, and that  
 
existing technical specification surveillance  
 
requirements (SRs) may not be adequate, 2. emphasize the importance of reliable, comprehensive surveillance testing to verify  
 
control room habitability, 3. request addressees to submit information that demonstrates that the control room at each of  
 
their respective facilities complies with the  
 
current licensing and design bases, and  
 
applicable regulatory requirements, and that  
 
suitable design, maintenance and testing control  
 
measures are in place for maintaining this  
 
compliance, and
: 4. collect the requested information to determine if additional regulatory action is required.
 
TVA responded to GL 2003-01 in Reference 1. In  
 
summary, the BFN Units 1, 2, and 3 design basis and  
 
licensing basis are in compliance with the  
 
applicable regulatory requirements. The plant is  
 
constructed and maintained in accordance with its  
 
design, and the testing performed in accordance  
 
with the BFN Technical Specifications (TS) and  
 
their bases is adequate to demonstrate this  
 
compliance and material condition.  
 
In Reference 2, the NRC provided a request for  
 
additional information (RAI) to TVA. TVA answered  
 
this RAI in Reference 3.  
 
Status: Complete  
 
April 13, 2007 E1-93


==References:==
==References:==
1.
: 1. TVA letter to NRC, dated December 8, 2003, Browns Ferry Nuclear Plant (BFN) Units 1, 2, and 3 Response to NRC Generic Letter (GL) 2003 Control Room Habitability
TVA letter to NRC, dated December 8, 2003, Browns Ferry Nuclear Plant (BFN) Units 1, 2, and 3 Response to NRC Generic Letter (GL)  
: 2. NRC letter to TVA, dated January 9, 2007, Browns Ferry Nuclear Plant, Units 1, 2 and 3, Request For Additional Information Regarding Generic Letter 2003-01, Control Room Habitability
 
: 3. TVA letter to NRC, dated February 8, 2007, Browns Ferry Nuclear Plant Units 1, 2 and 3 -
2003 Control Room Habitability
Request For Additional Information Regarding Generic Letter 2003-01, Control Room Habitability April 13, 2007                 E1-93
: 2. NRC letter to TVA, dated January 9, 2007, Browns Ferry Nuclear Plant, Units 1, 2 and 3, Request  
 
For Additional Information Regarding Generic  
 
Letter 2003-01, "Control Room Habitability"
: 3. TVA letter to NRC, dated February 8, 2007, Browns Ferry Nuclear Plant Units 1, 2 and 3 -  
 
Request For Additional Information Regarding  
 
Generic Letter 2003-01, "Control Room  
 
Habitability"
 
April 13, 2007 E1-94 Generic Safety Issue 75 / Multi-Plant Action B085, Generic Letter 83-28, Item 1.2, Post-Trip Review -
 
Data and Information Capability
 
Issue: This issue arose from the staff concerns resulting from analysis of events that occurred at the Salem
 
Nuclear Power Plant on February 22 and 25, 1983. 
 
The study of these events resulted in the issuance
 
of NUREG-1000 and Generic Letter 83-28. Item 1.2
 
of the Generic Letter requests licensees have the
 
capability to record, recall, and display data and
 
information to permit diagnosing the causes of


unscheduled reactor shutdowns and the proper  
Generic Safety Issue 75 / Multi-Plant Action B085, Generic Letter 83-28, Item 1.2, Post-Trip Review -
 
Data and Information Capability Issue:        This issue arose from the staff concerns resulting from analysis of events that occurred at the Salem Nuclear Power Plant on February 22 and 25, 1983.
functioning of safety-related equipment during  
The study of these events resulted in the issuance of NUREG-1000 and Generic Letter 83-28. Item 1.2 of the Generic Letter requests licensees have the capability to record, recall, and display data and information to permit diagnosing the causes of unscheduled reactor shutdowns and the proper functioning of safety-related equipment during these events using systematic safety assessment procedures.
 
Discussion:   Refer to previous topic entitled Generic Letter 83-28, Salem ATWS, Item 1.2, Post Trip Review (Data and Information Capability) (Page E1-55).
these events using systematic safety assessment  
Status:       Refer to previous topic entitled Generic Letter 83-28, Salem ATWS, Item 1.2, Post Trip Review (Data and Information Capability) (Page E1-55).
 
procedures.  
 
Discussion: Refer to previous topic entitled Generic Letter 83-28, Salem ATWS, Item 1.2, Post Trip Review (Data and Information Capability) (Page E1-55).  
 
Status: Refer to previous topic entitled Generic Letter 83-28, Salem ATWS, Item 1.2, Post Trip Review (Data and Information Capability) (Page E1-55).  


==References:==
==References:==
Refer to previous topic entitled Generic Letter 83-28, Salem ATWS, Item 1.2, Post Trip Review (Data and Information Capability) (Page E1-55).  
Refer to previous topic entitled Generic Letter 83-28, Salem ATWS, Item 1.2, Post Trip Review (Data and Information Capability) (Page E1-55).
April 13, 2007                  E1-94


April 13, 2007 E1-95 HVAC Duct Supports  
HVAC Duct Supports Commitment:   The HVAC Duct Supports program will be implemented in accordance with the Unit 2 precedent.
 
Discussion:   The approval of the program for the seismic qualification of HVAC duct supports is contained in References 1 and 2. The design criteria for the seismic qualification of the HVAC and supports was submitted in Reference 3. The NRC staff's Safety Evaluation Report (SER) on the criteria was included in Reference 4.
Commitment: The HVAC Duct Supports program will be implemented in accordance with the Unit 2 precedent.  
Status:       C-C For Unit 1, a review was performed to identify the areas of Class I HVAC ductwork that were not previously qualified for Units 2 and 3 operation.
 
The only areas specific to Unit 1 thus identified were the ductwork associated with the pump motor coolers for the Unit 1 Residual Heat Removal system and Core Spray system. Based upon the seismic qualification calculations, modifications have been completed to ensure that this ductwork is qualified to the long term requirements of the design criteria.
Discussion: The approval of the program for the seismic qualification of HVAC duct supports is contained in  
NRC closed this item in document dated March 9, 2007 (Reference 5).
 
References 1 and 2. The design criteria for the  
 
seismic qualification of the HVAC and supports was  
 
submitted in Reference 3. The NRC staff's Safety  
 
Evaluation Report (SER) on the criteria was  
 
included in Reference 4.  
 
Status: C-C  
 
For Unit 1, a review was performed to identify the  
 
areas of Class I HVAC ductwork that were not  
 
previously qualified for Units 2 and 3 operation.
 
The only areas specific to Unit 1 thus identified  
 
were the ductwork associated with the pump motor  
 
coolers for the Unit 1 Residual Heat Removal system  
 
and Core Spray system. Based upon the seismic  
 
qualification calculations, modifications have been  
 
completed to ensure that this ductwork is qualified  
 
to the long term requirements of the design  
 
criteria.  
 
NRC closed this item in document dated
 
March 9, 2007 (Reference 5).  


==References:==
==References:==
1.
: 1. NRC letter to TVA, dated August 22, 1990, Safety Evaluation of Inspection Open Item Regarding HVAC Ductworks and Supports for Browns Ferry Nuclear Plant, Unit 2 (TAC No. 62259)
NRC letter to TVA, dated August 22, 1990, Safety Evaluation of Inspection Open Item Regarding  
: 2. NRC letter to TVA, dated January 23, 1991, NUREG-1232, Volume 3, Supplement 2 - Browns Ferry, Unit 2, Section 2.2.2.4 (Page 2-5)
 
: 3. TVA letter to NRC, dated November 15, 1991, Heating, Ventilation and Air Conditioning (HVAC)
HVAC Ductworks and Supports for Browns Ferry  
 
Nuclear Plant, Unit 2 (TAC No. 62259)
: 2. NRC letter to TVA, dated January 23, 1991, NUREG-1232, Volume 3, Supplement 2 - Browns  
 
Ferry, Unit 2, Section 2.2.2.4 (Page 2-5)
: 3. TVA letter to NRC, dated November 15, 1991, Heating, Ventilation and Air Conditioning (HVAC)  
 
Seismic Design Criteria
Seismic Design Criteria
: 4. NRC letter to TVA, dated July 16, 1992, Evaluation of Seismic Design Criteria for  
: 4. NRC letter to TVA, dated July 16, 1992, Evaluation of Seismic Design Criteria for Heating Ventilation and Air Conditioning
 
: 5. NRC Meeting Summary dated March 9, 2007, Meeting Summary - Internal Meeting of the Browns Ferry Unit 1 Restart Panel - Docket No.
Heating Ventilation and Air Conditioning
50-259 April 13, 2007                   E1-95
: 5. NRC Meeting Summary dated March 9, 2007, "Meeting Summary - Internal Meeting of the  
 
Browns Ferry Unit 1 Restart Panel - Docket No.  
 
50-259" April 13, 2007 E1-96 Instrument Sensing Lines


Commitment: 1.
Instrument Sensing Lines Commitment:   1. The H2O2 analyzers will be modified in accordance with the Unit 2 precedent.
The H 2 O 2 analyzers will be modified in accordance with the Unit 2 precedent.
: 2. Where satisfactory operation can not be justified, the sensing lines will be reworked.
: 2. Where satisfactory operation can not be justified, the sensing lines will be reworked.
: 3. The 10 CFR 50, Appendix R, FSAR Appendix M, and Generic Evaluation of Internally Generated  
: 3. The 10 CFR 50, Appendix R, FSAR Appendix M, and Generic Evaluation of Internally Generated Missiles programs will require evaluations to maintain the integrity of instrument sense line separation.
 
Discussion:   The action plan for dispositioning instrument sensing line issues, including a discussion of lessons learned from the Unit 2 precedent, was provided in Reference 1. In Reference 2, NRC concluded that the program to address concerns related to instrument sensing lines was adequate.
Missiles programs will require evaluations to  
Status:       Complete The sample lines to the H2O2 analyzers were modified to assure that there are no moisture traps which would block the air sample flow from the drywell/torus to the analyzers.
 
Safety-related sensing lines were evaluated in order to maintain the integrity of instrument sensing line separation as required by the 10 CFR 50, Appendix R, FSAR Appendix M, and Generic Evaluation of Internally Generated Missiles programs. Sensing lines were either justified for use-as-is, or modified as required.
maintain the integrity of instrument sense line  
 
separation.  
 
Discussion: The action plan for dispositioning instrument sensing line issues, including a discussion of  
 
lessons learned from the Unit 2 precedent, was  
 
provided in Reference 1. In Reference 2, NRC  
 
concluded that the program to address concerns  
 
related to instrument sensing lines was adequate.  
 
Status: Complete  
 
The sample lines to the H 2 O 2 analyzers were modified to assure that there are no moisture traps  
 
which would block the air sample flow from the  
 
drywell/torus to the analyzers.  
 
Safety-related sensing lines were evaluated in  
 
order to maintain the integrity of instrument  
 
sensing line separation as required by the  
 
10 CFR 50, Appendix R, FSAR Appendix M, and Generic  
 
Evaluation of Internally Generated Missiles  
 
programs. Sensing lines were either justified for  
 
use-as-is, or modified as required.  


==References:==
==References:==
1.
: 1. TVA letter to NRC, dated February 13, 1991, Action Plan to Disposition Concerns Related to Instrument Sensing Lines for Units 1 and 3
TVA letter to NRC, dated February 13, 1991, Action Plan to Disposition Concerns Related to  
: 2. NRC letter to TVA, dated December 10, 1991, Safety Evaluation - TVA Action Plan to Resolve Concerns Related to Instrument Sensing Lines for the Browns Ferry Nuclear Plant, Units 1 and 3 April 13, 2007                   E1-96
 
Instrument Sensing Lines for Units 1 and 3
: 2. NRC letter to TVA, dated December 10, 1991, Safety Evaluation - TVA Action Plan to Resolve  
 
Concerns Related to Instrument Sensing Lines for  
 
the Browns Ferry Nuclear Plant, Units 1 and 3  
 
April 13, 2007 E1-97 Instrument Tubing
 
Commitment: Safety-related instrument tubing will be seismically qualified to meet the final design
 
criteria.
 
Discussion: The action plan for dispositioning concerns regarding the seismic qualification of instrument
 
tubing, including a discussion of lessons learned
 
from the Unit 2 precedent, was provided in
 
Reference 1. Additional information regarding


inspection attributes and sampling sizes was  
Instrument Tubing Commitment:  Safety-related instrument tubing will be seismically qualified to meet the final design criteria.
 
Discussion:  The action plan for dispositioning concerns regarding the seismic qualification of instrument tubing, including a discussion of lessons learned from the Unit 2 precedent, was provided in Reference 1. Additional information regarding inspection attributes and sampling sizes was provided in Reference 2. In Reference 3, NRC concluded that the program was an acceptable basis for restart of Unit 1 provided that the licensee also evaluates the instrument tubing populations in all units for any new attributes which may be identified during the implementation of the revised program.
provided in Reference 2. In Reference 3, NRC  
Status:       Complete The affected systems / supports were analyzed for Seismic Class I qualification, and necessary modifications were completed.
 
concluded that the program was an acceptable basis  
 
for restart of Unit 1 provided that the licensee  
 
also evaluates the instrument tubing populations in  
 
all units for any new attributes which may be  
 
identified during the implementation of the revised  
 
program.
Status: Complete  
 
The affected systems / supports were analyzed for  
 
Seismic Class I qualification, and necessary  
 
modifications were completed.  


==References:==
==References:==
1.
: 1. TVA letter to NRC, dated February 27, 1991, Action Plan to Disposition Concerns Regarding the Seismic Qualification of Units 1 and 3 Instrument Tubing
TVA letter to NRC, dated February 27, 1991, Action Plan to Disposition Concerns Regarding  
: 2. TVA letter to NRC, dated December 12, 1991, Small Bore Piping Program, Tubing, and Conduit Support Plans for Units 1 and 3 - Additional Information
 
: 3. NRC letter to TVA, dated February 4, 1992, Safety Evaluation of Small Bore Piping and Seismic Qualification of Instrument Tubing Programs for Browns Ferry Nuclear Plant, Units 1 and 3 April 13, 2007                  E1-97
the Seismic Qualification of Units 1 and 3  
 
Instrument Tubing
: 2. TVA letter to NRC, dated December 12, 1991, Small Bore Piping Program, Tubing, and Conduit  
 
Support Plans for Units 1 and 3 - Additional  


Information
Intergranular Stress Corrosion Cracking (IGSCC)
: 3. NRC letter to TVA, dated February 4, 1992, Safety Evaluation of Small Bore Piping and
Commitment:   The Intergranular Stress Corrosion Cracking (IGSCC) program will be implemented in accordance with the Unit 2 precedent.
 
Discussion:   Refer to previous topic entitled Generic Letter 88 NRC Position on IGSCC in BWR Austenitic Stainless Steel Piping (Page E1-60).
Seismic Qualification of Instrument Tubing
Status:       Refer to previous topic entitled Generic Letter 88 NRC Position on IGSCC in BWR Austenitic Stainless Steel Piping (Page E1-60).
 
Programs for Browns Ferry Nuclear Plant, Units 1 and 3 April 13, 2007 E1-98 Intergranular Stress Corrosion Cracking (IGSCC)  
 
Commitment: The Intergranular Stress Corrosion Cracking (IGSCC) program will be implemented in accordance with the  
 
Unit 2 precedent.  
 
Discussion: Refer to previous topic entitled Generic Letter 88 NRC Position on IGSCC in BWR Austenitic  
 
Stainless Steel Piping (Page E1-60).  
 
Status: Refer to previous topic entitled Generic Letter 88 NRC Position on IGSCC in BWR Austenitic  
 
Stainless Steel Piping (Page E1-60).  


==References:==
==References:==
None  
None April 13, 2007                  E1-98


April 13, 2007 E1-99 Large Bore Piping Supports  
Large Bore Piping Supports Commitment:   TVA will complete Bulletin 79-14.
 
Discussion:   Refer to previous topic entitled Bulletin 79-14, Seismic Analysis for As-Built Safety-Related Piping Systems (Page E1-6).
Commitment: TVA will complete Bulletin 79-14.  
Status:       Refer to previous topic entitled Bulletin 79-14, Seismic Analysis for As-Built Safety-Related Piping Systems (Page E1-6).
 
Discussion: Refer to previous topic entitled Bulletin 79-14, Seismic Analysis for As-Built Safety-Related Piping  
 
Systems (Page E1-6).
 
Status: Refer to previous topic entitled Bulletin 79-14, Seismic Analysis for As-Built Safety-Related Piping  
 
Systems (Page E1-6).  


==References:==
==References:==
None  
None April 13, 2007                  E1-99


April 13, 2007 E1-100 License Renewal - Appendix F Commitments
License Renewal - Appendix F Commitments Commitment:  TVA will implement the License Renewal - Appendix F commitments prior to Unit 1 restart.
Discussion:  On April 21, 2006, TVA sent the NRC a revised list of commitments for License Renewal (Reference 1).
Table 3 of Enclosure 1 of the letter contains the list of License Renewal commitments which are required for Unit 1 restart. The items originate from Appendix F of the License Renewal Application and are required to make the current licensing basis (CLB) of Unit 1 at restart the same as the CLB for Units 2 and 3. These commitments are contained in Table 3 of Appendix A of the Safety Evaluation Report related to the License Renewal of BFN (Reference 2).
Status:      Each of the 13 Appendix F commitments and its status is as follows:
F.1  Evaluate and modify, as required, main steam leakage path piping to ensure structural integrity.
Status:  Open F.2  Implement Containment Atmosphere Dilution (CAD) System modification.
Status:  Complete TVA completed the modifications to the CAD system.
F.3  Revise Fire Protection Report per Unit 1 License Condition 2.C.13.
Status:  Refer to previous topic entitled Fire Protection / 10 CFR 50, Appendix R (Page E1-46).
F.4  Implement Environmental Qualification Program.
Status:  Refer to previous topic entitled Environmental Qualification (Page E1-45).
April 13, 2007                   E1-100


Commitment: TVA will implement the License Renewal - Appendix F commitments prior to Unit 1 restart.  
F.5 Address GL 88-01, and make necessary plant modifications.
Status: Refer to previous topic entitled Generic Letter 88-01, NRC Position on IGSCC in BWR Austenitic Stainless Steel Piping (Page E1-60).
F.6 BWRVIP Programs used for Units 2 and 3 will be used for Unit 1.
Status:  Complete Required inspections have been completed, and examination reports have been filed. The required Unit 1 examinations have been incorporated into applicable procedure.
F.7 Install ATWS features.
Status:  Refer to the topic entitled Unresolved Safety Issue A-9, Anticipated Transients Without Scram (Page E1-134).
F.8 Remove Reactor Vessel Head Spray piping in drywell, and seal the primary containment penetrations.
Status:  Complete Piping has been removed, and penetrations have been capped.
F.9 Implement the Hardened Wetwell Vent modification.
Status:  C-C Refer to previous topic entitled Generic Letter 89-16, Installation of a Hardened Wetwell Vent (Page E1-74).
April 13, 2007                E1-101


Discussion: On April 21, 2006, TVA sent the NRC a revised list of commitments for License Renewal (Reference 1). 
F.10  Cap Service Air and Demineralized Water Primary Containment Penetrations.
 
Status:  Complete The Service Air and Demineralized Water Primary Containment Penetrations were capped.
Table 3 of Enclosure 1 of the letter contains the
F.11 Modify Auxiliary Decay Heat Removal (ADHR)
 
list of License Renewal commitments which are
 
required for Unit 1 restart. The items originate
 
from Appendix F of the License Renewal Application
 
and are required to make the current licensing
 
basis (CLB) of Unit 1 at restart the same as the
 
CLB for Units 2 and 3. These commitments are
 
contained in Table 3 of Appendix A of the Safety
 
Evaluation Report related to the License Renewal of
 
BFN (Reference 2).
 
Status: Each of the 13 Appendix F commitments and its status is as follows:  F.1 Evaluate and modify, as required, main steam leakage path piping to ensure structural
 
integrity.
Status:  Open  F.2 Implement Containment Atmosphere Dilution (CAD) System modification.
Status:  Complete TVA completed the modifications to the CAD system. F.3 Revise Fire Protection Report per Unit 1 License Condition 2.C.13.
Status:  Refer to previous topic entitled Fire Protection / 10 CFR 50, Appendix R (Page E1-46). F.4 Implement Environmental Qualification Program. Status:  Refer to previous topic entitled Environmental Qualification (Page E1-45).
April 13, 2007 E1-101 F.5 Address GL 88-01, and make necessary plant modifications.
Status:  Refer to previous topic entitled Generic Letter 88-01, NRC Position
 
on IGSCC in BWR Austenitic
 
Stainless Steel Piping (Page E1-60). F.6 BWRVIP Programs used for Units 2 and 3 will be used for Unit 1.
Status: Complete Required inspections have been completed, and examination reports
 
have been filed. The required
 
Unit 1 examinations have been
 
incorporated into applicable
 
procedure. F.7 Install ATWS features.
Status:  Refer to the topic entitled Unresolved Safety Issue A-9, Anticipated Transients Without
 
Scram (Page E1-134). F.8 Remove Reactor Vessel Head Spray piping in drywell, and seal the primary containment
 
penetrations.
Status:  Complete Piping has been removed, and penetrations have been capped. F.9 Implement the Hardened Wetwell Vent modification.
Status:  C-C Refer to previous topic entitled Generic Letter 89-16, Installation
 
of a Hardened Wetwell Vent (Page E1-74).
April 13, 2007 E1-102 F.10 Cap Service Air and Demineralized Water Primary Containment Penetrations.
Status:  Complete The Service Air and Demineralized Water Primary Containment  
 
Penetrations were capped. F.11 Modify Auxiliary Decay Heat Removal (ADHR)
System to serve Unit 1.
System to serve Unit 1.
Status:  Complete ADHR has been modified to serve Unit 1. F.12 Fully implement the Maintenance Rule.
Status:  Complete ADHR has been modified to serve Unit 1.
Unit 1's temporary exemption ceases to be  
F.12 Fully implement the Maintenance Rule.
 
Unit 1s temporary exemption ceases to be effective.
effective.
Status:  Open F.13
Status:  Open F.13 Replace RWCU piping outside of primary containment with IGSCC resistant piping.
* Replace RWCU piping outside of primary containment with IGSCC resistant piping.
Status:  Complete Implement actions requested in GL 89-10 for RWCU.
Status:  Complete
Status:  Complete  
* Implement actions requested in GL 89-10 for RWCU.
Status:  Complete


==References:==
==References:==
1.
: 1. TVA letter to NRC, dated April 21, 2006, Browns Ferry Nuclear Plant (BFN) - Units 1, 2, AND 3 -
TVA letter to NRC, dated April 21, 2006, Browns Ferry Nuclear Plant (BFN) - Units 1, 2, AND 3 -  
License Renewal Application (LRA) - Revised Commitment List (TAC Nos. MC1704, MC1705, and MC1706)
 
: 2. NUREG-1843, Supplement 1, Safety Evaluation Report Related to the License Renewal of the Browns Ferry Nuclear Plant, Units 1, 2, and 3, Docket Nos. 50-259, 50-260, and 50-296 April 13, 2007                   E1-102
License Renewal Application (LRA) - Revised  
 
Commitment List (TAC Nos. MC1704, MC1705, and  
 
MC1706) 2. NUREG-1843, Supplement 1, "Safety Evaluation Report Related to the License Renewal of the  
 
Browns Ferry Nuclear Plant, Units 1, 2, and 3, Docket Nos. 50-259, 50-260, and 50-296"
 
April 13, 2007 E1-103 License Renewal - Non-Appendix F Commitments


Commitment: TVA will implement applicable License Renewal -
License Renewal - Non-Appendix F Commitments Commitment:   TVA will implement applicable License Renewal -
Non-Appendix F Commitments prior to Unit 1 restart.
Non-Appendix F Commitments prior to Unit 1 restart.
 
Discussion:   On April 21, 2006, TVA sent the NRC a revised list of commitments for License Renewal (Reference 1).
Discussion: On April 21, 2006, TVA sent the NRC a revised list of commitments for License Renewal (Reference 1).
Enclosure 1 of the letter contains the list of License Renewal commitments which are required for Unit 1 restart. Certain of those commitments are not Appendix F items but are required to be implemented prior to Unit 1 restart. These commitments are contained in Appendix A of the Safety Evaluation Report related to the License Renewal of BFN (Reference 2).
of the letter contains the list of  
The applicable commitments are as follow:
 
* Table 1, Item 24., last portion; and
License Renewal commitments which are required for  
* Table 2 items with an Implementation Schedule of Prior to Unit 1 restart.
 
Status:       Open
Unit 1 restart. Certain of those commitments are  
 
not Appendix F items but are required to be  
 
implemented prior to Unit 1 restart. These  
 
commitments are contained in Appendix A of the  
 
Safety Evaluation Report related to the License  
 
Renewal of BFN (Reference 2).  
 
The applicable commitments are as follow: Table 1, Item 24., last portion; and Table 2 items with an Implementation Schedule of "Prior to Unit 1 restart."
 
Status: Open  


==References:==
==References:==
1.
: 1. TVA letter to NRC, dated April 21, 2006, Browns Ferry Nuclear Plant (BFN) - Units 1, 2, AND 3 -
TVA letter to NRC, dated April 21, 2006, Browns Ferry Nuclear Plant (BFN) - Units 1, 2, AND 3 -  
License Renewal Application (LRA) - Revised Commitment List (TAC Nos. MC1704, MC1705, and MC1706)
 
: 2. NUREG-1843, Supplement 1, Safety Evaluation Report Related to the License Renewal of the Browns Ferry Nuclear Plant, Units 1, 2, and 3, Docket Nos. 50-259, 50-260, and 50-296 April 13, 2007                 E1-103
License Renewal Application (LRA) - Revised  
 
Commitment List (TAC Nos. MC1704, MC1705, and  
 
MC1706) 2. NUREG-1843, Supplement 1, "Safety Evaluation Report Related to the License Renewal of the  
 
Browns Ferry Nuclear Plant, Units 1, 2, and 3, Docket Nos. 50-259, 50-260, and 50-296"
 
April 13, 2007 E1-104 Long Term Torus Integrity Program
 
Commitment: TVA committed to resolve torus attached piping support discrepancies in accordance with the Unit 2 criteria precedent. The inspection of the
 
nonsafety-related catwalk will be limited to welds
 
and bolted connections associated with maintaining
 
the integrity of the safety-related structures. 
 
The resolution of catwalk discrepancies will be in
 
accordance with the Unit 2 criteria.
 
Discussion: On January 13, 1981 (Reference 1), the Commission issued an Order that required the reassessment of
 
the containment design for suppression pool
 
hydrodynamic loading conditions. In Reference 2 , a subsequent Order extended the modification
 
completion date until prior to the start of
 
Cycle 6. NRC conducted a post-i mplementation audit review of the BFN Plant Unique Analysis Report for
 
the Mark I containment long-term program (Reference 3). The staff determined that all but a few of the modifications made by TVA were in
 
accordance with the generic acceptance criteria and
 
the deviations from the acceptance criteria were


found acceptable. Discrepancies were identified  
Long Term Torus Integrity Program Commitment:  TVA committed to resolve torus attached piping support discrepancies in accordance with the Unit 2 criteria precedent. The inspection of the nonsafety-related catwalk will be limited to welds and bolted connections associated with maintaining the integrity of the safety-related structures.
 
The resolution of catwalk discrepancies will be in accordance with the Unit 2 criteria.
between design drawings and the actual  
Discussion:  On January 13, 1981 (Reference 1), the Commission issued an Order that required the reassessment of the containment design for suppression pool hydrodynamic loading conditions. In Reference 2, a subsequent Order extended the modification completion date until prior to the start of Cycle 6. NRC conducted a post-implementation audit review of the BFN Plant Unique Analysis Report for the Mark I containment long-term program (Reference 3). The staff determined that all but a few of the modifications made by TVA were in accordance with the generic acceptance criteria and the deviations from the acceptance criteria were found acceptable. Discrepancies were identified between design drawings and the actual modifications. The action plan for dispositioning the long-term torus integrity discrepancies was provided by TVA in Reference 4 and approved by NRC in Reference 5.
 
In Reference 6, NRC identified a Violation with regards to activities associated with the Unit 1 LTTIP corrective actions. TVA responded in Reference 7.
modifications. The action plan for dispositioning  
Status:       Complete TVA performed modifications to resolve torus attached piping support discrepancies, safety-related torus and torus related structure discrepancies, and nonsafety-related catwalk discrepancies in accordance with the Unit 2 precedent.
 
the long-term torus integrity discrepancies was  
 
provided by TVA in Reference 4 and approved by NRC  
 
in Reference 5.  
 
In Reference 6, NRC identified a Violation with  
 
regards to activities associated with the Unit 1  
 
LTTIP corrective actions. TVA responded in  
 
Reference 7.  
 
Status: Complete  
 
TVA performed modifications to resolve torus  
 
attached piping support discrepancies, safety-
 
related torus and torus related structure  
 
discrepancies, and nonsafety-related catwalk  
 
discrepancies in accordance with the Unit 2  
 
precedent.  


==References:==
==References:==
1.
: 1. NRC letter to TVA, dated January 13, 1981, in regards to Orders for Modification of Licenses and Grant of Extension of Exemptions
NRC letter to TVA, dated January 13, 1981, in regards to Orders for Modification of Licenses  
: 2. NRC letter to TVA, dated January 19, 1982, in regards to Order Modifying the January 13, 1981 Order April 13, 2007                 E1-104
 
and Grant of Extension of Exemptions
: 2. NRC letter to TVA, dated January 19, 1982, in regards to Order Modifying the January 13, 1981  
 
Order April 13, 2007 E1-105
: 3. NRC letter to TVA, dated May 6, 1985, Mark I Containment Long Term Program
: 3. NRC letter to TVA, dated May 6, 1985, Mark I Containment Long Term Program
: 4. TVA letter to NRC, dated April 29, 1991, Program for Resolving Long-Term Torus Integrity Issue  
: 4. TVA letter to NRC, dated April 29, 1991, Program for Resolving Long-Term Torus Integrity Issue Prior to the Restart of Units 1 and 3
 
: 5. NRC letter to TVA, dated February 10, 1992, Evaluation of Long-Term Torus Integrity Program for Browns Ferry Nuclear Plant, Units 1 and 3
Prior to the Restart of Units 1 and 3
: 6. NRC letter to TVA, dated May 12, 2004, Notice of Violation (Browns Ferry Nuclear Plant Unit 1 Recovery - NRC Inspection Report No. 5000259/2004011)
: 5. NRC letter to TVA, dated February 10, 1992, Evaluation of Long-Term Torus Integrity Program  
: 7. TVA letter to NRC, dated June 2, 2004, Browns Ferry Nuclear Plant (BFN) - NRC Inspection Report 50-259/2004-011 - Reply to Notice Of Violation (NOV) EA-04-063 April 13, 2007                  E1-105
 
for Browns Ferry Nuclear Plant, Units 1 and 3
: 6. NRC letter to TVA, dated May 12, 2004, Notice of Violation (Browns Ferry Nuclear Plant Unit 1  
 
Recovery - NRC Inspection Report


No. 5000259/2004011)
Lower Drywell Platforms and Miscellaneous Steel Commitment:   The lower drywell steel platforms and miscellaneous steel will be evaluated and modified, if required, to meet the design criteria.
: 7. TVA letter to NRC, dated June 2, 2004, Browns Ferry Nuclear Plant (BFN) - NRC Inspection
Discussion:   The action plan for dispositioning the Lower Drywell Platforms and Miscellaneous Steel issue was provided in Reference 1. Additional information requested by the Staff was provided in Reference 2.
 
Additional information was requested by the Staff in Reference 3 and provided by TVA in Reference 4.
Report 50-259/2004-011 - Reply to Notice Of
An NRC position regarding the design criteria was issued by Reference 5 and a subsequent Safety Evaluation and request for additional information was issued as Reference 6. This additional information was provided by TVA in Reference 7.
 
A supplemental Safety Evaluation was issued by NRC in Reference 8. Additional information was provided by TVA in References 9 and 10. The final Safety Evaluation was issued in Reference 11 and the issue was closed after an audit of the design criteria implementation as documented in Reference 12.
Violation (NOV) EA-04-063
Status:       C-C The lower drywell steel platforms and miscellaneous steel were evaluated and modified, if required, to meet the design criteria.
 
NRC closed this item in document dated March 9, 2007 (Reference 13).
April 13, 2007 E1-106 Lower Drywell Platforms and Miscellaneous Steel  
 
Commitment: The lower drywell steel platforms and miscellaneous steel will be evaluated and modified, if required, to meet the design criteria.  
 
Discussion: The action plan for dispositioning the Lower Drywell Platforms and Miscellaneous Steel issue was  
 
provided in Reference 1. Additional information  
 
requested by the Staff was provided in Reference 2.
 
Additional information was requested by the Staff  
 
in Reference 3 and provided by TVA in Reference 4.  
 
An NRC position regarding the design criteria was  
 
issued by Reference 5 and a subsequent Safety  
 
Evaluation and request for additional information  
 
was issued as Reference 6. This additional  
 
information was provided by TVA in Reference 7.  
 
A supplemental Safety Evaluation was issued by NRC  
 
in Reference 8. Additional information was  
 
provided by TVA in References 9 and 10. The final  
 
Safety Evaluation was issued in Reference 11 and  
 
the issue was closed after an audit of the design  
 
criteria implementation as documented in  
 
Reference 12.  
 
Status: C-C  
 
The lower drywell steel platforms and miscellaneous  
 
steel were evaluated and modified, if required, to  
 
meet the design criteria.  
 
NRC closed this item in document dated March 9, 2007 (Reference 13).  


==References:==
==References:==
1.
: 1. TVA letter to NRC, dated June 12, 1991, Corrective Action Plan and Design Criteria for Lower Drywell Steel Platforms and Miscellaneous Steel
TVA letter to NRC, dated June 12, 1991, Corrective Action Plan and Design Criteria for  
: 2. TVA letter to NRC, dated November 8, 1991, Seismic Design Criteria for Lower Drywell Steel Platforms and Miscellaneous Steel
 
: 3. NRC letter to TVA, dated December 12, 1991, Request for Additional Information Regarding Browns Ferry Drywell and Miscellaneous Steel Design Criteria April 13, 2007                   E1-106
Lower Drywell Steel Platforms and Miscellaneous  
: 4. TVA letter to NRC, dated February 6, 1992, Lower Drywell Platforms and Miscellaneous Steel Seismic Criteria
 
: 5. NRC letter to TVA, dated March 19, 1992, NRC Staff Position on Proposed Ductility Ratio Design Criteria
Steel 2. TVA letter to NRC, dated November 8, 1991, Seismic Design Criteria for Lower Drywell Steel  
: 6. NRC letter to TVA, dated July 13, 1992, Safety Evaluation and Request for Additional Information Regarding Browns Ferry Nuclear Plant Units 1, 2, and 3 Design Criteria for Lower Drywell Steel Platforms and Miscellaneous Steel
 
: 7. TVA letter to NRC, dated July 31, 1992, Response to Request for Additional Information Regarding Design Criteria for Lower Drywell Steel Platforms and Miscellaneous Steel
Platforms and Miscellaneous Steel
: 8. NRC letter to TVA, dated October 29, 1992, Supplemental Safety Evaluation of Steel Design Criteria for the Browns Ferry Nuclear Power Plant
: 3. NRC letter to TVA, dated December 12, 1991, Request for Additional Information Regarding  
: 9. TVA letter to NRC, dated September 30, 1992, Resolution of the Thermal Growth Issue Outside Containment
 
: 10. TVA letter to NRC, dated June 29, 1993, Resolution of the Thermal Growth Issue
Browns Ferry Drywell and Miscellaneous Steel  
: 11. NRC letter to TVA, dated December 7, 1993, Supplemental Safety Evaluation of Structural Steel Thermal Growth Design Criteria
 
: 12. NRC letter to TVA, dated April 20, 1994, Audit of Structural Steel Design Criteria Implementation
Design Criteria April 13, 2007 E1-107
: 13. NRC Meeting Summary dated March 9, 2007, Meeting Summary - Internal Meeting of the Browns Ferry Unit 1 Restart Panel - Docket No.
: 4. TVA letter to NRC, dated February 6, 1992, Lower Drywell Platforms and Miscellaneous Steel  
50-259 April 13, 2007                  E1-107
 
Seismic Criteria
: 5. NRC letter to TVA, dated March 19, 1992, NRC Staff Position on Proposed Ductility Ratio  
 
Design Criteria
: 6. NRC letter to TVA, dated July 13, 1992, Safety Evaluation and Request for Additional  


Information Regarding Browns Ferry Nuclear Plant
Moderate Energy Line Break (MELB)
 
Commitment:   The Moderate Energy Line Break (MELB) program will be implemented in accordance with the Unit 2 precedent.
Units 1, 2, and 3 Design Criteria for Lower
Discussion:   As part of the restart effort on Unit 2, TVA committed to review the effects of flooding due to breaks in moderate energy lines outside primary containment (Reference 1). NRC approval of the program was documented in Reference 2.
 
The critical plant features that are required to mitigate or limit the consequences of moderate energy piping failures exist in the current BFN design. The results of the Unit 1 evaluation concluded that Browns Ferry conforms to the original licensing basis for MELB flooding and that the existing flooding studies and protective measures are adequate to justify continued operations (Reference 3).
Drywell Steel Platforms and Miscellaneous Steel
Status:       C-C NRC closed this item in Inspection Report 2006-007 (Reference 4).
: 7. TVA letter to NRC, dated July 31, 1992, Response to Request for Additional Information Regarding
 
Design Criteria for Lower Drywell Steel
 
Platforms and Miscellaneous Steel
: 8. NRC letter to TVA, dated October 29, 1992, Supplemental Safety Evaluation of Steel Design
 
Criteria for the Browns Ferry Nuclear Power
 
Plant 9. TVA letter to NRC, dated September 30, 1992, Resolution of the Thermal Growth Issue Outside
 
Containment 1 0. TVA letter to NRC, dated June 29, 1993, Resolution of the Thermal Growth Issue 1 1. NRC letter to TVA, dated December 7, 1993, Supplemental Safety Evaluation of Structural
 
Steel Thermal Growth Design Criteria 1 2. NRC letter to TVA, dated April 20, 1994, Audit of Structural Steel Design Criteria
 
Implementation 1 3. NRC Meeting Summary dated March 9, 2007, "Meeting Summary - Internal Meeting of the
 
Browns Ferry Unit 1 Restart Panel - Docket No.
 
50-259" April 13, 2007 E1-108 Moderate Energy Line Break (MELB)  
 
Commitment: The Moderate Energy Line Break (MELB) program will be implemented in accordance with the Unit 2  
 
precedent.  
 
Discussion: As part of the restart effort on Unit 2, TVA committed to review the effects of flooding due to  
 
breaks in moderate energy lines outside primary  
 
containment (Reference 1). NRC approval of the  
 
program was documented in Reference 2.  
 
The critical plant features that are required to  
 
mitigate or limit the consequences of moderate  
 
energy piping failures exist in the current BFN  
 
design. The results of the Unit 1 evaluation  
 
concluded that Browns Ferry conforms to the  
 
original licensing basis for MELB flooding and t h at the existing flooding studies and protective  
 
measures are adequate to justify continued  
 
operations (Reference 3).  
 
Status: C-C  
 
NRC closed this item in Inspection Report 2006-007 (Reference 4).  


==References:==
==References:==
1.
: 1. TVA letter to NRC, dated October 24, 1988, Browns Ferry Nuclear Plant (BFN) - Nuclear Performance Plan, Revision 2
TVA letter to NRC, dated October 24, 1988, Browns Ferry Nuclear Plant (BFN) - Nuclear  
: 2. NRC letter to TVA, dated January 23, 1991, NUREG-1232, Volume 3, Supplement 2 - Browns Ferry, Unit 2, Section 3.8 (Page 3-8)
 
: 3. TVA letter to NRC, dated June 25, 2004, Browns Ferry Nuclear Plant (BFN) Unit 1 - Completion of the Program - Moderate Energy Line Break (MELB)
Performance Plan, Revision 2
: 2. NRC letter to TVA, dated January 23, 1991, NUREG-1232, Volume 3, Supplement 2 - Browns  
 
Ferry, Unit 2, Section 3.8 (Page 3-8)
: 3. TVA letter to NRC, dated June 25, 2004, Browns Ferry Nuclear Plant (BFN) Unit 1 - Completion of  
 
the Program - Moderate Energy Line Break (MELB)  
 
Flooding Evaluation
Flooding Evaluation
: 4. NRC letter to TVA, dated August 10, 2006, Browns Ferry Nuclear Plant Unit 1 Recovery - NRC  
: 4. NRC letter to TVA, dated August 10, 2006, Browns Ferry Nuclear Plant Unit 1 Recovery - NRC Integrated Inspection Report 05000259/2006007 April 13, 2007                   E1-108
 
Integrated Inspection Report 05000259/2006007  
 
April 13, 2007 E1-109 NUREG-0737 (TMI Action Plan), Action Item I.D.1, Control Room Design Review
 
Commitment: TVA will complete NUREG-0737 (TMI Action Plan)
Action Item I.D.1 - Control Room Design Review.
 
Discussion: Pursuant to NUREG-0737 (TMI Action Plan) and Supplement 1, TVA provided its Control Room Design
 
Review (CRDR) corrective action plan and
 
commitments in Reference 1. NRC's initial Safety
 
Evaluation Report (SER) was issued as Reference 2.


NUREG-0737 (TMI Action Plan), Action Item I.D.1, Control Room Design Review Commitment:  TVA will complete NUREG-0737 (TMI Action Plan)
Action Item I.D.1 - Control Room Design Review.
Discussion:  Pursuant to NUREG-0737 (TMI Action Plan) and Supplement 1, TVA provided its Control Room Design Review (CRDR) corrective action plan and commitments in Reference 1. NRCs initial Safety Evaluation Report (SER) was issued as Reference 2.
TVA provided additional information in Reference 3.
TVA provided additional information in Reference 3.
 
In Reference 4, TVA also committed to complete all safety and non-safety significant Human Engineering Discrepancies (HEDs) prior to the restart of Units 1 and 3. The final SER for the BFN CRDR was provided in Reference 5.
In Reference 4, TVA also committed to complete all  
As part of BFNs Operating and Maintenance Cost Reduction Program, TVA submitted a Cost Beneficial Licensing Action to discontinue the cost-benefit analysis of non-safety significant HEDs (Reference 6). NRC approval of this request was contained in Reference 7.
 
Status:       Closed TVA is implementing its CRDR corrective action plan for Unit 1 and all safety significant HEDs will be corrected.
safety and non-s afety significant Human Engineering Discrepancies (HEDs) prior to the restart of  
NRC closed this item in Inspection Report 2006-007 (Reference 8).
 
Units 1 and 3. The final SER for the BFN CRDR was  
 
provided in Reference 5.  
 
As part of BFN's Operating and Maintenance Cost  
 
Reduction Program, TVA submitted a Cost Beneficial  
 
Licensing Action to discontinue the cost-benefit  
 
analysis of non-safety significant HEDs (Reference 6). NRC approval of this request was  
 
contained in Reference 7.  
 
Status: Closed  
 
TVA is implementing its CRDR c o rrective action plan for Unit 1 and all safety significant HEDs will be  
 
corrected.  
 
NRC closed this item in Inspection Report 2006-007 (Reference 8).  


==References:==
==References:==
1.
: 1. TVA letter to NRC, dated December 30, 1986, Detailed Control Room Design Review (DCRDR) -
TVA letter to NRC, dated December 30, 1986, Detailed Control Room Design Review (DCRDR) -  
 
NUREG-0737, Item I.D.1
NUREG-0737, Item I.D.1
: 2. NRC letter to TVA, dated August 9, 1988, Safety Evaluation for the Detailed Control Room Design, Browns Ferry Nuclear Plant, Units 1, 2 and 3 (TACs 56104, 56105, 56106)
: 2. NRC letter to TVA, dated August 9, 1988, Safety Evaluation for the Detailed Control Room Design, Browns Ferry Nuclear Plant, Units 1, 2 and 3 (TACs 56104, 56105, 56106)
: 3. TVA letter to NRC, dated November 3, 1988, Response to NRC Safety Evaluation for the BFN  
: 3. TVA letter to NRC, dated November 3, 1988, Response to NRC Safety Evaluation for the BFN Detailed Control Room Design Review (DCRDR)
: 4. TVA letter to NRC, dated August 22, 1991, Supplemental Response to NRC Safety Evaluation for the BFN Detailed Control Room Design Review (DCRDR)
April 13, 2007                  E1-109
: 5. NRC letter to TVA, dated October 29, 1991, Safety Evaluation of the Browns Ferry Nuclear Plant Detailed Control Room Design Review
: 6. TVA letter to NRC, dated December 15, 1993, Operating & Maintenance (O&M) Cost Reduction Program - Cost Beneficial Licensing Action -
Revision of Detailed Control Room Design Review (DCRDR) Program to Discontinue Cost-Benefit Analysis of Non-Safety Significant Human Engineering Discrepancies (HEDs)
: 7. NRC letter to TVA, dated February 4, 1994, Revision of Detailed Control Room Design Review Program to Discontinue Cost-Benefit Analysis of Non-Safety Significant Human Engineering Discrepancies
: 8. NRC letter to TVA, dated August 10, 2006, Browns Ferry Nuclear Plant Unit 1 Recovery - NRC Integrated Inspection Report 05000259/2006007 April 13, 2007                  E1-110


Detailed Control Room Design Review (DCRDR)
NUREG-0737 (TMI Action Plan), Action Item I.D.2, Safety Parameter Display Console Commitment:   TVA will complete NUREG-0737 (TMI Action Plan)
: 4. TVA letter to NRC, dated August 22, 1991, Supplemental Response to NRC Safety Evaluation
Action Item I.D.2 - Safety Parameter Display Console.
 
Discussion:   Refer to the previous item entitled Generic Letter 89 Task Action Plan Item I.D.2 - Safety Parameter Display System (Page E1-68).
for the BFN Detailed Control Room Design
Status:       Refer to the previous item entitled Generic Letter 89 Task Action Plan Item I.D.2 - Safety Parameter Display System (Page E1-68).
 
Review (DCRDR)
 
April 13, 2007 E1-110
: 5. NRC letter to TVA, dated October 29, 1991, Safety Evaluation of the Browns Ferry Nuclear
 
Plant Detailed Control Room Design Review
: 6. TVA letter to NRC, dated December 15, 1993, Operating & Maintenance (O&M) Cost Reduction
 
Program - Cost Beneficial Licensing Action -
 
Revision of Detailed Control Room Design
 
Review (DCRDR) Program to Discontinue Cost-
 
Benefit Analysis of Non-S afety Significant Human Engineering Discrepancies (HEDs)
: 7. NRC letter to TVA, dated February 4, 1994, Revision of Detailed Control Room Design Review
 
Program to Discontinue Cost-Benefit Analysis of
 
Non-Safety Significant Human Engineering
 
Discrepancies
: 8. NRC letter to TVA, dated August 10, 2006, Browns Ferry Nuclear Plant Unit 1 Recovery - NRC
 
Integrated Inspection Report 05000259/2006007
 
April 13, 2007 E1-111 NUREG-0737 (TMI Action Plan), Action ItemI.D.2, Safety Parameter Display Console  
 
Commitment: TVA will complete NUREG-0737 (TMI Action Plan)
Action Item I.D.2 - Safety Parameter Display  
 
Console.
Discussion: Refer to the previous item entitled Generic Letter 89 Task Action Plan Item I.D.2 - Safety  
 
Parameter Display System (Page E1-68).  
 
Status: Refer to the previous item entitled Generic Letter 89 Task Action Plan Item I.D.2 - Safety  
 
Parameter Display System (Page E1-68).  


==References:==
==References:==
None  
None April 13, 2007                  E1-111


April 13, 2007 E1-112 NUREG-0737 (TMI Action Plan), Action Item II.B.3, Post-Accident Sampling System  
NUREG-0737 (TMI Action Plan), Action Item II.B.3, Post-Accident Sampling System Commitment:   TVA will complete NUREG-0737 (TMI Action Plan)
 
Commitment: TVA will complete NUREG-0737 (TMI Action Plan)
Action Item II.B.3 - Post-Accident Sampling System (PASS).
Action Item II.B.3 - Post-Accident Sampling System (PASS).
Discussion: A description of BFN's PASS design was provided in References 1 and 2. The Safety Evaluation Report  
Discussion:   A description of BFNs PASS design was provided in References 1 and 2. The Safety Evaluation Report for this system was provided by Reference 3.
 
TVA submitted a request to decommit to the requirement for a PASS in Reference 4. NRC approved this request in Reference 5.
for this system was provided by Reference 3.  
TVA committed to:
 
* Develop contingency plans for obtaining and analyzing highly radioactive samples of reactor coolant, the suppression pool, and containment atmosphere prior to Unit 1 fuel load; and
TVA submitted a request to decommit to the  
* Describe in emergency plan implementing procedures the capability for classifying fuel damage events at the Alert level threshold at radioactivity levels of 300 uCi/ml dose equivalent I-131 prior to Unit 1 fuel load.
 
Status:       C-C TVA has implemented contingency plans for obtaining and analyzing highly radioactive samples of reactor coolant, the suppression pool, and containment atmosphere.
requirement for a PASS in Reference 4. NRC  
Emergency plan implementing procedures contain the capability for classifying fuel damage events at the Alert level threshold at radioactivity levels of 300 uCi/ml dose equivalent I-131.
 
NRC closed this item in Inspection Report 2006-006 (Reference 6).
approved this request in Reference 5.  
 
TVA committed to:  
 
Develop contingency plans for obtaining and analyzing highly radioactive samples of reactor  
 
coolant, the suppression pool, and containment  
 
atmosphere prior to Unit 1 fuel load; and Describe in emergency plan implementing procedures the capability for classifying fuel  
 
damage events at the Alert level threshold at  
 
radioactivity levels of 300 uCi/ml dose  
 
equivalent I-131 prior to Unit 1 fuel load.
 
Status: C-C  
 
TVA has implemented contingency plans for obtaining  
 
and analyzing highly radioactiv e samples of reactor coolant, the suppression pool, and containment  
 
atmosphere.
Emergency plan implementing procedures contain the capability for classifying fuel damage events at  
 
the Alert level threshold at radioactivity levels  
 
of 300 uCi/ml dose equivalent I-131.  
 
NRC closed this item in Inspection Report 2006-006 (Reference 6).  


==References:==
==References:==
1.
: 1. TVA letter to NRC, dated December 19, 1986, NUREG-0737, Item II.B.3 - Postaccident Sampling System
TVA letter to NRC, dated December 19, 1986, NUREG-0737, Item II.B.3 - Postaccident Sampling  
: 2. TVA letter to NRC, dated April 1, 1987, NUREG-0737, Item II.B.3 - Postaccident Sampling System
 
: 3. NRC letter to TVA, dated May 27, 1987, Post Accident Sampling System April 13, 2007                   E1-112
System 2. TVA letter to NRC, dated April 1, 1987, NUREG-0737, Item II.B.3 - Postaccident Sampling System
: 4. TVA letter to NRC, dated February 19, 2003, Browns Ferry Nuclear Plant (BFN) - Units 1, 2, and 3 - Technical Specifications (TS) Change 423
: 3. NRC letter to TVA, dated May 27, 1987, Post Accident Sampling System April 13, 2007 E1-113
                - Eliminate Requirements for Post Accident Sampling System (PASS) using the Consolidated Line Item Improvement Process and Delete Regulatory Commitment
: 4. TVA letter to NRC, dated February 19, 2003, Browns Ferry Nuclear Plant (BFN) - Units 1, 2, and 3 - Technical Specifications (TS) Change 423  
: 5. NRC letter to TVA, dated May 9, 2003, Browns Ferry Nuclear Plant, Units 1, 2 and 3, Re: Issuance of Amendments Eliminating Requirements for Postaccident Sampling (TAC Nos. MB7747, MB7748 and MB7749)
- Eliminate Requirements for Post Accident  
: 6. NRC letter to TVA, dated May 15, 2006, Browns Ferry Nuclear Plant Unit 1 Recovery - NRC Integrated Inspection Report 05000259/2006006 April 13, 2007                  E1-113
 
Sampling System (PASS) using the Consolidated  


Line Item Improvement Process and Delete
NUREG-0737 (TMI Action Plan), Action Item II.E.4.2.1-4, Containment Isolation Dependability - Implement Diverse Isolation Commitment:   TVA will complete NUREG-0737 (TMI Action Plan)
 
Action Item II.E.4.2.1 Containment Isolation Dependability - Implement Diverse Isolation.
Regulatory Commitment
Discussion:   In Reference 1, NRC requested additional information regarding Units 1 and 3 conformance with NUREG-0737, Item II.E.4.2 and 10 CFR 50, Appendix J. In order to minimize the number and scope of updates that would have to be provided to NRC on this issue, TVA replied in Reference 2 using the anticipated configuration at the time of the restart of Unit 1. NRC approval of the Unit 1 containment isolation design is provided in Reference 3. NRC was notified of subsequent changes to the containment isolation configuration, which were being made under the provisions of 10 CFR 50.59, in Reference 4.
: 5. NRC letter to TVA, dated May 9, 2003, Browns Ferry Nuclear Plant, Units 1, 2 and 3, 
Status:       Open
 
Re: Issuance of Amendments Eliminating
 
Requirements for Postaccident Sampling (TAC Nos. MB7747, MB7748 and MB7749)
: 6. NRC letter to TVA, dated May 15, 2006, Browns Ferry Nuclear Plant Unit 1 Recovery - NRC
 
Integrated Inspection Report 05000259/2006006
 
April 13, 2007 E1-114 NUREG-0737 (TMI Action Plan), Action Item II.E.4.2.1-4, Containment Isolation  
 
Dependability - Implement Diverse  
 
Isolation  
 
Commitment: TVA will complete NUREG-0737 (TMI Action Plan)
Action Item II.E.4.2.1 Containment Isolation  
 
Dependability - Implement Diverse Isolation.  
 
Discussion: In Reference 1, NRC requested additional information regarding Units 1 and 3 conformance  
 
with NUREG-0737, Item II.E.4.2 and 10 CFR 50, Appendix J. In order to minimize the number and  
 
scope of updates that would have to be provided to  
 
NRC on this issue, TVA replied in Reference 2 using  
 
the anticipated configuration at the time of the  
 
restart of Unit 1. NRC approval of the Unit 1  
 
containment isolation design is provided in  
 
Reference 3. NRC was notified of subsequent  
 
changes to the containment isolatio n configuration, which were being made under the provisions of  
 
10 CFR 50.59, in Reference 4.  
 
Status: Open  


==References:==
==References:==
1.
: 1. NRC letter to TVA, dated May 5, 1992, Request for Additional Information to Review Browns Ferry Nuclear Plant Units 1 and 3 Compliance with NUREG-0737 Item II.E.4.2 and 10CFR50, Appendix J
NRC letter to TVA, dated May 5, 1992, Request for Additional Information to Review Browns  
: 2. TVA letter to NRC, dated September 1, 1992, Response to NRC Request for Additional Information Regarding Units 1 and 3 Conformance with NUREG-0737, Item II.E.4.2 and 10CFR50, Appendix J
 
: 3. NRC letter to TVA, dated January 6, 1995, Browns Ferry Nuclear Plant Units 1 and 3 - NUREG-0737, Item II.E.4.2, Containment Isolation Dependability
Ferry Nuclear Plant Units 1 and 3 Compliance  
: 4. TVA letter to NRC, dated June 24, 2004, Browns Ferry Nuclear Plant (BFN) Unit 1 - Supplemental Information for Conformance with NUREG-0737, Item II.E.4.2, and 10 CFR 50, Appendix J April 13, 2007                   E1-114
 
with NUREG-0737 Item II.E.4.2 and 10CFR50, Appendix J
: 2. TVA letter to NRC, dated September 1, 1992, Response to NRC Request for Additional  
 
Information Regarding Units 1 and 3 Conformance  
 
with NUREG-0737, Item II.E.4.2 and 10CFR50, Appendix J
: 3. NRC letter to TVA, dated January 6, 1995, Browns Ferry Nuclear Plant Units 1 and 3 - NUREG-0737, Item II.E.4.2, Containment Isolation  
 
Dependability
: 4. TVA letter to NRC, dated June 24, 2004, Browns Ferry Nuclear Plant (BFN) Unit 1 - Supplemental  
 
Information for Conformance with NUREG-0737, Item II.E.4.2, and 10 CFR 50, Appendix J  
 
April 13, 2007 E1-115 NUREG-0737 (TMI Action Plan), Action Item II.F.1.2.C, Accident - Monitoring -Containment High Range
 
Radiation 
 
Commitment: TVA will complete NUREG-0737 (TMI Action Plan)
Action Item II.F.1.2.C - Accident - Monitoring -
 
Containment High Range Radiation.
 
Discussion: In Reference 1, TVA committed to install a containment high range radiation monitor. In
 
Reference 2, NRC stated no deviations from NRC
 
requirements had been identified; hence no NRC
 
review was required. Reference 3 issued a
 
Confirmatory Order for the installation of the
 
radiation monitors prior to start-up in Cycle 6.
 
Status: Closed
 
TVA will upgrade the two Unit 1 drywell radiation
 
monitor loops to meet the requirements of 
 
NUREG-0737 for Containment High Range Radiation
 
Monitors (CHRRM). The modifications will ensure


that the CHRRMs are capable of detecting and  
NUREG-0737 (TMI Action Plan), Action Item II.F.1.2.C, Accident -
 
Monitoring - Containment High Range Radiation Commitment:  TVA will complete NUREG-0737 (TMI Action Plan)
measuring the radiation level within the drywell  
Action Item II.F.1.2.C - Accident - Monitoring -
 
Containment High Range Radiation.
during and following an accident.  
Discussion:  In Reference 1, TVA committed to install a containment high range radiation monitor. In Reference 2, NRC stated no deviations from NRC requirements had been identified; hence no NRC review was required. Reference 3 issued a Confirmatory Order for the installation of the radiation monitors prior to start-up in Cycle 6.
 
Status:      Closed TVA will upgrade the two Unit 1 drywell radiation monitor loops to meet the requirements of NUREG-0737 for Containment High Range Radiation Monitors (CHRRM). The modifications will ensure that the CHRRMs are capable of detecting and measuring the radiation level within the drywell during and following an accident.
NRC closed this item in Inspection Report 2006-006 (Reference 4).  
NRC closed this item in Inspection Report 2006-006 (Reference 4).


==References:==
==References:==
1.
: 1. TVA letter to NRC, dated December 23, 1980, in regards to post-TMI requirements
TVA letter to NRC, dated December 23, 1980, in regards to post-TMI requirements
: 2. NRC letter to TVA, dated January 8, 1982, Re: Status of NUREG-0737 Item II.F.1.3 at Browns Ferry Unit Nos. 1, 2 and 3
: 2. NRC letter to TVA, dated January 8, 1982, Re: Status of NUREG-0737 ItemII.F.1.3 at Browns Ferry Unit Nos. 1, 2 and 3
: 3. NRC letter to TVA, dated March 25, 1983, in regards to Confirmatory Order for Post-TMI Related Items Set Forth in NUREG-0737
: 3. NRC letter to TVA, dated March 25, 1983, in regards to Confirmatory Order for Post-TMI  
: 4. NRC letter to TVA, dated May 15, 2006, Browns Ferry Nuclear Plant Unit 1 Recovery - NRC Integrated Inspection Report 05000259/2006006 April 13, 2007                  E1-115


Related Items Set Forth in NUREG-0737
NUREG-0737 (TMI Action Plan), Action Item II.F.1.2.D, Accident -
: 4. NRC letter to TVA, dated May 15, 2006, Browns Ferry Nuclear Plant Unit 1 Recovery - NRC
Monitoring - Containment Pressure Commitment:   TVA will complete NUREG-0737 (TMI Action Plan)
 
Action Item II.F.1.2.D - Accident - Monitoring -
Integrated Inspection Report 05000259/2006006
Containment Pressure.
 
Discussion:   In Reference 1, TVA committed to install a containment pressure monitor. NRC requested additional information in Reference 2, which was provided by TVA in Reference 3. Reference 4 issued a Confirmatory Order for the installation of the pressure monitor prior to start-up in Cycle 6. The Safety Evaluation Report for this item was issued in Reference 5. NRC closed this item in Inspection Report 90-29 (Reference 6).
April 13, 2007 E1-116 NUREG-0737 (TMI Action Plan), Action Item II.F.1.2.D, Accident -
Status:       C-C NRC closed this item in Inspection Report 2005-006 (Reference 7).
Monitoring - Containment Pressure  
 
Commitment: TVA will complete NUREG-0737 (TMI Action Plan)
Action Item II.F.1.2.D - Accident - Monitoring -  
 
Containment Pressure.  
 
Discussion: In Reference 1, TVA committed to install a containment pressure monitor. NRC requested  
 
additional information in Reference 2, which was  
 
provided by TVA in Reference 3. Reference 4 issued  
 
a Confirmatory Order for the installation of the  
 
pressure monitor prior to start-up in Cycle 6. The  
 
Safety Evaluation Report for this item was issued  
 
in Reference 5. NRC closed this item in Inspection  
 
Report 90-29 (Reference 6).  
 
Status: C-C  
 
NRC closed this item in Inspection Report 2005-006 (Reference 7).  


==References:==
==References:==
1.
: 1. TVA letter to NRC, dated December 23, 1980, in regards to post-TMI requirements
TVA letter to NRC, dated December 23, 1980, in regards to post-TMI requirements
: 2. NRC letter to TVA, dated March 22, 1982, NUREG-0737, Items II.F.1.4, Containment Pressure Monitor; II.F.1.5, Containment Water Level Monitor, and II.F.1.6, Containment Hydrogen Monitor
: 2. NRC letter to TVA, dated March 22, 1982, NUREG-0737, Items I I.F.1.4, Containment Pressure Monitor; II.F.1.5, Containment Water Level  
: 3. TVA letter to NRC, dated April 26, 1982, in regards to NUREG-0737, Items II.F.1.4, II.F.1.5, and II.F.1.6
: 4. NRC letter to TVA, dated March 25, 1983, in regards to Confirmatory Order for Post-TMI Related Items Set Forth in NUREG-0737
: 5. NRC letter to TVA, dated June 16, 1983, NUREG-0737, Item II.F.1.4 Containment Pressure Monitor, II.F.1.5 Containment Water Level Monitor, and II.F.1.6 Containment Hydrogen Monitor
: 6. NRC letter to TVA, dated November 8, 1990, Notice of Violation (NRC Inspection Report Nos.
50-259/90-29, 50-260/90-29, and 50-296/90-29)
: 7. NRC letter to TVA, dated May 16, 2005, Browns Ferry Nuclear Plant Unit 1 Recovery - NRC Integrated Inspection Report 05000259/2005006 April 13, 2007                    E1-116


Monitor, and II.F.1.6, Containment Hydrogen
NUREG-0737 (TMI Action Plan), Action Item II.F.1.2.E, Accident -
 
Monitoring - Containment Water Level Commitment:   TVA will complete NUREG-0737 (TMI Action Plan)
Monitor 3. TVA letter to NRC, dated April 26, 1982, in regards to NUREG-0 737, Items II.F.1.4, II.F.1.5, and II.F.1.6
Action Item II.F.1.2.E - Accident - Monitoring -
: 4. NRC letter to TVA, dated March 25, 1983, in regards to Confirmatory Order for Post-TMI
Containment Water Level.
 
Discussion:   In Reference 1, TVA committed to install a containment water level monitor. NRC requested additional information in Reference 2, which was provided by TVA in Reference 3. In Reference 4, NRC issued a Confirmatory Order for the installation of the water level monitor prior to start-up in Cycle 6 (July 1983). The Safety Evaluation Report for this item was issued in Reference 5. A Technical Specifications amendment was issued to reflect the modifications performed during that outage (Reference 6).
Related Items Set Forth in NUREG-0737
Status:       C-C NRC closed this item in Inspection Report 2005-006 (Reference 7).
: 5. NRC letter to TVA, dated June 16, 1983, NUREG-0737, Item II.F.1.4 Containment Pressure
 
Monitor, II.F.1.5 Containment Water Level
 
Monitor, and II.F.1.6 Containment Hydrogen
 
Monitor 6. NRC letter to TVA, dated November 8, 1990, Notice of Violation (NRC Inspection Report Nos.
 
50-259/90-29, 50-260/90-29, and 
 
50-296/90-29)
: 7. NRC letter to TVA, dated May 16, 2005, Browns Ferry Nuclear Plant Unit 1 Recovery - NRC
 
Integrated Inspection Report 05000259/2005006
 
April 13, 2007 E1-117 NUREG-0737 (TMI Action Plan), Action Item II.F.1.2.E, Accident -
Monitoring - Containment Water  
 
Level Commitment: TVA will complete NUREG-0737 (TMI Action Plan)
Action Item II.F.1.2.E - Accident - Monitoring -  
 
Containment Water Level.  
 
Discussion: In Reference 1, TVA committed to install a containment water level monitor. NRC requested  
 
additional information in Reference 2, which was  
 
provided by TVA in Reference 3. In Reference 4, NRC issued a Confirmatory Order for the  
 
installation of the water level monitor prior to  
 
start-up in Cycle 6 (July 1983). The Safety  
 
Evaluation Report for this item was issued in  
 
Reference 5. A Technical Specifications amendment  
 
was issued to reflect the modifications performed  
 
during that outage (Reference 6).  
 
Status: C-C  
 
NRC closed this item in Inspection Report 2005-006 (Reference 7).  


==References:==
==References:==
1.
: 1. TVA letter to NRC, dated December 23, 1980, in Regards to Post-TMI Requirements
TVA letter to NRC, dated December 23, 1980, in Regards to Post-TMI Requirements
: 2. NRC letter to TVA, dated March 22, 1982, NUREG-0737, Items II.F.1.4, Containment Pressure Monitor; II.F.1.5, Containment Water Level Monitor, and II.F.1.6, Containment Hydrogen Monitor
: 2. NRC letter to TVA, dated March 22, 1982, NUREG-0737, Items I I.F.1.4, Containment Pressure Monitor; II.F.1.5, Containment Water Level  
: 3. TVA letter to NRC, dated April 26, 1982, in regards to NUREG-0737, Items II.F.1.4, II.F.1.5, and II.F.1.6
 
: 4. NRC letter to TVA, dated March 25, 1983, in regards to Confirmatory Order for Post-TMI Related Items Set Forth in NUREG-0737
Monitor, and II.F.1.6, Containment Hydrogen  
: 5. NRC letter to TVA, dated June 16, 1983, NUREG-0737, Item II.F.1.4 Containment Pressure Monitor II.F.1.5 Containment Water Level Monitor II.F.1.6 Containment Hydrogen Monitor
 
Monitor 3. TVA letter to NRC, dated April 26, 1982, in regards to NUREG-0 737, Items II.F.1.4, II.F.1.5, and II.F.1.6
: 4. NRC letter to TVA, dated March 25, 1983, in regards to Confirmatory Order for Post-TMI  
 
Related Items Set Forth in NUREG-0737
: 5. NRC letter to TVA, dated June 16, 1983, NUREG-0737, Item II.F.1.4 Containment Pressure  
 
Monitor II.F.1.5 Containment Water Level Monitor  
 
II.F.1.6 Containment Hydrogen Monitor
: 6. NRC letter to TVA, dated December 12, 1983, in regards to Amendment 92 for Browns Ferry Unit 1
: 6. NRC letter to TVA, dated December 12, 1983, in regards to Amendment 92 for Browns Ferry Unit 1
: 7. NRC letter to TVA, dated May 16, 2005, Browns Ferry Nuclear Plant Unit 1 Recovery - NRC  
: 7. NRC letter to TVA, dated May 16, 2005, Browns Ferry Nuclear Plant Unit 1 Recovery - NRC Integrated Inspection Report 05000259/2005006 April 13, 2007                   E1-117
 
Integrated Inspection Report 05000259/2005006  
 
April 13, 2007 E1-118 NUREG-0737 (TMI Action Plan), Action Item II.F.2.4 (Generic Letter 84-23), Instrumentation for
 
Detection of Inadequate Core
 
Cooling Commitment: TVA committed to:
: 1. Convert level instruments which initiate the Reactor Protection System (RPS) and Emergency
 
Core Cooling System (ECCS) and provide class 1E
 
level indication in the control room to analog
 
trip units.
: 2. Minimize the effects of high drywell temperature on level indications by limiting the vertical
 
drop of the reference legs inside the drywell to
 
no more than two feet.
 
Discussion: The long-term modifications to improve the reliability and accuracy of BWR water level
 
measurement and instrumentation were requested by
 
Generic Letter 84-23. TVA committed in Reference 1 to replace the RPS and ECCS instruments with analog
 
trip units. TVA committed in Reference 2 to
 
minimize the vertical drop of the reference legs
 
inside containment by bringing the reference legs
 
outside the drywell at higher elevations. This
 
commitment was modified in accordance with the
 
commitment management process to limit the vertical


drop inside the drywell to be no more than 2 feet 5  
NUREG-0737 (TMI Action Plan), Action Item II.F.2.4 (Generic Letter 84-23), Instrumentation for Detection of Inadequate Core Cooling Commitment:  TVA committed to:
 
: 1. Convert level instruments which initiate the Reactor Protection System (RPS) and Emergency Core Cooling System (ECCS) and provide class 1E level indication in the control room to analog trip units.
inches. NRC found TVA's proposed modifications  
: 2. Minimize the effects of high drywell temperature on level indications by limiting the vertical drop of the reference legs inside the drywell to no more than two feet.
 
Discussion:  The long-term modifications to improve the reliability and accuracy of BWR water level measurement and instrumentation were requested by Generic Letter 84-23. TVA committed in Reference 1 to replace the RPS and ECCS instruments with analog trip units. TVA committed in Reference 2 to minimize the vertical drop of the reference legs inside containment by bringing the reference legs outside the drywell at higher elevations. This commitment was modified in accordance with the commitment management process to limit the vertical drop inside the drywell to be no more than 2 feet 5 inches. NRC found TVAs proposed modifications acceptable in Reference 3. The NRC was notified of this change by Reference 4.
acceptable in Reference
Status:       C-C TVA has:
: 3. The NRC was notified of this change by Reference 4.  
: 1. Converted level instruments which initiate the Reactor Protection System (RPS) and Emergency Core Cooling System (ECCS) and provided class 1E level indication in the control room to analog trip units.
 
: 2. Minimized the effects of high drywell temperature on level indications by limiting the vertical drop of the reference legs inside the drywell to no more than two feet.
Status: C-C TVA has: 1. Converted level instruments which initiate the Reactor Protection System (RPS) and Emergency  
NRC closed this item in Inspection Report 2005-007 (Reference 5).
 
April 13, 2007                   E1-118
Core Cooling System (ECCS) and provided class 1E  
 
level indication in the control room to analog  
 
trip units.
: 2. Minimized the effects of high drywell temperature on level indications by limiting the  
 
vertical drop of the reference legs inside the  
 
drywell to no more than two feet.  
 
NRC closed this item in Inspection Report 2005-007 (Reference 5).  
 
April 13, 2007 E1-119


==References:==
==References:==
1.
: 1. TVA letter to NRC, dated April 8, 1995, in regards to Generic Letter 84-23
TVA letter to NRC, dated April 8, 1995, in regards to Generic Letter 84-23
: 2. TVA letter to NRC, dated March 12, 1986, in regards to Generic Letter 84-23
: 2. TVA letter to NRC, dated March 12, 1986, in regards to Generic Letter 84-23
: 3. NRC letter to TVA, dated November 18, 1986, NUREG-0731, Item II.F.2, Inadequate Core Cooling  
: 3. NRC letter to TVA, dated November 18, 1986, NUREG-0731, Item II.F.2, Inadequate Core Cooling Instrumentation (Generic Letter 84-23); MPA-F-26
 
: 4. TVA letter to NRC, dated September 5, 1995, Browns Ferry Nuclear Plant (BFN) - Units 1 and 3 Revision to Commitments Concerning The Senior Management Assessment of Readiness Team (SMART) and The Vertical Drop of Reactor Vessel Reference Legs (Generic Letter 84-23)
Instrumentation (Generic Letter 84-23); MPA-F-26 4. TVA letter to NRC, dated September 5, 1995, Browns Ferry Nuclear Plant (BFN) - Units 1 and 3  
: 5. NRC letter to TVA, dated August 15, 2005, Browns Ferry Nuclear Plant Unit 1 Recovery - NRC Integrated Inspection Report 05000259/2005007 April 13, 2007                  E1-119
 
Revision to Commitments Concerning The Senior  
 
Management Assessment of Readiness Team (SMART)  


and The Vertical Drop of Reactor Vessel
NUREG-0737 (TMI Action Plan), Action Item II.K.3.13, HPCI/RCIC Initiation Levels Commitment:   TVA will complete NUREG-0737 (TMI Action Plan)
 
Action Item II.K.3.13 - HPCI/RCIC Initiation Levels.
Reference Legs (Generic Letter 84-23)
Discussion:   In Reference 1, TVA states that it concurs with the BWR Owners' Group recommendation that separation of the HPCI/RCIC level setpoints had no substantial benefit and committed to implement an automatic restart of RCIC. In Reference 2, NRC concurred that no significant benefit would be gained by the separation of the HPCI/RCIC initiation levels and requested TVA evaluate the acceptance criteria provided for the RCIC automatic restart. One exception to the criteria was identified in Reference 3 and approved by NRC in Reference 4.
: 5. NRC letter to TVA, dated August 15, 2005, Browns Ferry Nuclear Plant Unit 1 Recovery - NRC
TVA clarified Technical Specifications Bases Section 4.2 in Reference 5. The Bases were revised to state that the automatic restart feature is tested during the performance of logic system functional tests. The issuance of these Bases changes was documented in Reference 6. TVA modified the RCIC logic in order to automatically restart the RCIC system on vessel low water level (without operator action) following a vessel high water trip.
 
Status:       C-C NRC closed this item in Inspection Report 2005-007 (Reference 7).
Integrated Inspection Report 05000259/2005007
 
April 13, 2007 E1-120 NUREG-0737 (TMI Action Plan), Action Item II.K.3.13, HPCI/RCIC Initiation Levels  
 
Commitment: TVA will complete NUREG-0737 (TMI Action Plan)
Action Item II.K.3.13 - HPCI/RCIC Initiation  
 
Levels.
Discussion: In Reference 1 , TVA states that it concurs with the BWR Owners' Group recommendation that separation of  
 
the HPCI/RCIC level setpoints had no substantial  
 
benefit and committed to implement an automatic  
 
restart of RCIC. In Reference 2, NRC concurred  
 
that no significant benefit would be gained by the  
 
separation of the HPCI/RCIC initiation levels and  
 
requested TVA evaluate the acceptance criteria  
 
provided for the RCIC automatic restart. One  
 
exception to the criteria was identified in  
 
Reference 3 and approved by NRC in Reference 4.  
 
TVA clarified Technical Specifications Bases  
 
Section 4.2 in Reference
: 5. The Bases were revised to state that the automatic restart feature is  
 
tested during the performance of logic system  
 
functional tests. The issuance of these Bases  
 
changes was documented in Reference 6. TVA  
 
modified the RCIC logic in order to automatically  
 
restart the RCIC system on vessel low water level (without operator action) following a vessel high  
 
water trip.  
 
Status: C-C  
 
NRC closed this item in Inspection Report 2005-007 (Reference 7).  


==References:==
==References:==
1.
: 1. TVA letter to NRC, dated December 23, 1980, in Regards to Post-TMI Requirements
TVA letter to NRC, dated December 23, 1980, in Regards to Post-TMI Requirements
: 2. NRC letter to TVA, dated March 16, 1983, NUREG-0737, Item II.K.3.13, RCIC Automatic Restart
: 2. NRC letter to TVA, dated March 16, 1983, NUREG-0737, Item II.K.3.13, RCIC Automatic  
: 3. TVA letter to NRC, dated May 24, 1983, in Regards to NUREG-0737, Item II.K.3.13
: 4. NRC letter to TVA, dated September 19, 1983, NUREG-0737, Item II.K.3.13, RCIC Automatic Restart
: 5. TVA letter to NRC, dated January 14, 1992, TVA BFN Technical Specification (TS) No. 300 Reactor Core Thermal-Hydraulic Stability April 13, 2007                  E1-120
: 6. NRC letter to TVA, dated May 31, 1994, Issuance of Technical Specification Amendments for the Browns Ferry Nuclear Plant Units 1 and 3 (TS 300)
: 7. NRC letter to TVA, dated August 15, 2005, Browns Ferry Nuclear Plant Unit 1 Recovery - NRC Integrated Inspection Report 05000259/2005007 April 13, 2007                  E1-121


Restart 3. TVA letter to NRC, dated May 24, 1983, in Regards to NUREG-0737, Item II.K.3.13
NUREG-0737 (TMI Action Plan), Action Item II.K.3.18, ADS Actuation Modifications Commitment:   TVA will complete NUREG-0737 (TMI Action Plan)
: 4. NRC letter to TVA, dated September 19, 1983, NUREG-0737, Item II.K.3.13, RCIC Automatic
Action Item II.K.3.18 - ADS Actuation Modifications.
 
Discussion:   In response to Item II.K.3.18, the BWR Owners' Group performed an evaluation of options for compliance. Two of these options were found to be acceptable by the NRC Staff and TVA was requested in Reference 1 to commit to one of these options.
Restart 5. TVA letter to NRC, dated January 14, 1992, TVA BFN Technical Specification (TS) No. 300 Reactor
TVA chose Option 2, to modify the ADS logic to allow the ADS to initiate vessel depressurization, automatically bypassing the high drywell pressure signal 10 minutes after a sustained lo-lo-lo reactor vessel water level signal (Reference 2).
 
TVA will perform modifications to the ADS logic that will allow the ADS to initiate vessel depressurization.
Core Thermal-Hydraulic Stability April 13, 2007 E1-121
Status:       Closed NRC closed this item in Inspection Report 2005-007 (Reference 3).
: 6. NRC letter to TVA, dated May 31, 1994, Issuance of Technical Specification Amendments for the
 
Browns Ferry Nuclear Plant Units 1 and 3 (TS 300) 7. NRC letter to TVA, dated August 15, 2005, B r owns Ferry Nuclear Plant Unit 1 Recovery - NRC
 
Integrated Inspection Report 05000259/2005007
 
April 13, 2007 E1-122 NUREG-0737 (TMI Action Plan), Action Item II.K.3.18, ADS Actuation Modifications  
 
Commitment: TVA will complete NUREG-0737 (TMI Action Plan)
Action Item II.K.3.18 - ADS Actuation  
 
Modifications.
Discussion: In response to Item II.K.3.18, the BWR Owners' Group performed an evaluation of options for  
 
compliance. Two of these options were found to be  
 
acceptable by the NRC Staff and TVA was requested  
 
in Reference 1 to commit to one of these options.
 
TVA chose Option 2, to modify the ADS logic to  
 
allow the ADS to initiate vessel depressurization, automatically bypassing the high drywell pressure  
 
signal 10 minutes after a sustained lo-lo-lo  
 
reactor vessel water level signal (Reference 2).
 
TVA will perform modifications to the ADS logic  
 
that will allow the ADS to initiate vessel  
 
depressurization.
Status: Closed  
 
NRC closed this item in Inspection Report 2005-007 (Reference 3).  


==References:==
==References:==
1.
: 1. NRC letter to TVA, dated June 3, 1983, NUREG-0737, Item II.K.3.18, ADS Logic Modifications
NRC letter to TVA, dated June 3, 1983, NUREG-0737, Item II.K.3.18, ADS Logic  
: 2. TVA letter to NRC, dated March 5, 1987, Modifications to Automatic Depressurization System (ADS) Logic - NUREG-0737, Item II.K.3.18
: 3. NRC letter to TVA, dated August 15, 2005, Browns Ferry Nuclear Plant Unit 1 Recovery - NRC Integrated Inspection Report 05000259/2005007 April 13, 2007                  E1-122


Modifications
NUREG-0737 (TMI Action Plan), Action Item II.K.3.27, Common Reference Level for Vessel Level Instrumentation Issue:       Provide level instruments that are referenced to the same point.
: 2. TVA letter to NRC, dated March 5, 1987, Modifications to Automatic Depressurization
Discussion:   In Reference 1, NRC proposed that TVA incorporate the requirements of Action Item II.K.3.27 into the control room design review to be performed per NUREG-0737, Action Item I.D.1. This approach eliminates the possibility of changing water level instrument scales twice; once per Item II.K.3.27 and then possibly again per Item I.D.1. TVA accepted this proposal in Reference 2.
 
Status:       C-C NRC letter to TVA, dated December 30, 1982 (Reference 3), incorporated this item into NUREG-0737, Action Item II.K.3.27, Common Reference Level.
System (ADS) Logic - NUREG-0737, Item II.K.3.18
NRC closed this item in Inspection Report 2005-008 (Reference 4).
: 3. NRC letter to TVA, dated August 15, 2005, Brown s Ferry Nuclear Plant Unit 1 Recovery - NRC
 
Integrated Inspection Report 05000259/2005007
 
April 13, 2007 E1-123 NUREG-0737 (TMI Action Plan), Action Item II.K.3.27, Common Reference Level for Vessel Level  
 
Instrumentation  
 
Issue: Provide level instruments that are referenced to the same point.  
 
Discussion: In Reference 1, NRC proposed that TVA incorporate the requirements of Action Item II.K.3.27 into the  
 
control room design review to be performed per  
 
NUREG-0737, Action Item I.D.1. This approach  
 
eliminates the possibility of changing water level  
 
instrument scales twice; once per Item II.K.3.27  
 
and then possibly again per Item I.D.1. TVA  
 
accepted this proposal in Reference 2.  
 
Status: C-C  
 
NRC letter to TVA, dated December 30, 1982 (Reference 3), incorporated this item into
 
NUREG-0737, Action Item I I.K.3.27, Common Reference Level.  
 
NRC closed this item in Inspection Report 2005-008 (Reference 4).  


==References:==
==References:==
1.
: 1. NRC letter to TVA, dated October 28, 1982,
NRC letter to TVA, dated October 28, 1982,  


==Subject:==
==Subject:==
NUREG-0737 Action Item II.K.3.27 (Common Reference Level)
NUREG-0737 Action Item II.K.3.27 (Common Reference Level)
: 2. TVA letter to NRC, dated December 3, 1982, in regards to NUREG-0737, Item II.I.3.27 (Common  
: 2. TVA letter to NRC, dated December 3, 1982, in regards to NUREG-0737, Item II.I.3.27 (Common Reference Level)
 
: 3. NRC letter to TVA, dated December 30, 1982, NUREG-0737, Action Item II.K.3.27, Common Reference Level
Reference Level)
: 4. NRC letter to TVA, dated November 14, 2005, Browns Ferry Nuclear Plant Unit 1 Recovery - NRC Integrated Inspection Report 05000259/2005008 April 13, 2007                   E1-123
: 3. NRC letter to TVA, dated December 30, 1982, NUREG-0737, Action Item II.K.3.27, Common  
 
Reference Level
: 4. NRC letter to TVA, dated November 14, 2005, Browns Ferry Nuclear Plant Unit 1 Recovery -NRC  
 
Integrated Inspection Report 05000259/2005008  
 
April 13, 2007 E1-124 NUREG-0737 (TMI Action Plan), Action Item II.K.3.28, Qualification of ADS Accumulators


Commitment: TVA will complete NUREG-0737 (TMI Action Plan)
NUREG-0737 (TMI Action Plan), Action Item II.K.3.28, Qualification of ADS Accumulators Commitment:   TVA will complete NUREG-0737 (TMI Action Plan)
Action Item II.K.3.28 - Qualification of ADS  
Action Item II.K.3.28 - Qualification of ADS Accumulators.
 
Discussion:   TVA responded to Item II.K.3.28 by Reference 1. The NRC Staff requested additional information in Reference 2, which was provided by TVA in Reference 3. Additional information was requested in Reference 4 and provided in Reference 5. TVA responded to a verbal request for additional information in Reference 6. The Safety Evaluation that documents the acceptability of TVA's plan to satisfy Item II.K.3.28 was provided in Reference 7.
Accumulators.  
TVA performed modifications to upgrade the ADS accumulator system. This was accomplished by splitting the ring header into two sections, and providing an alternate nitrogen supply to the Drywell Control Air System.
 
Status:       C-C NRC closed this item in Inspection Report 2005-007 (Reference 8).
Discussion: TVA responded to Item II.K.3.28 by Reference
: 1. The NRC Staff requested additional information in  
 
Reference 2, which was provided by TVA in  
 
Reference 3. Additional information was requested  
 
in Reference 4 and provided in Reference 5. TVA  
 
responded to a verbal request for additional  
 
information in Reference 6. The Safety Evaluation  
 
that documents the acceptability of TVA's plan to  
 
satisfy Item II.K.3.28 was provided in Reference 7.
 
TVA performed modifications to upgrade the ADS  
 
accumulator system. This was accomplished by  
 
splitting the ring header into two sections, and  
 
providing an alternate nitrogen supply to the  
 
Drywell Control Air System.  
 
Status: C-C  
 
NRC closed this item in Inspection Report 2005-007 (Reference 8).


==References:==
==References:==
1.
: 1. TVA letter to NRC, dated December 30, 1981, in regards to NUREG-0737, Items II.K.3.24, II.K.3.28 and II.B.4
TVA letter to NRC, dated December 30, 1981, in regards to NUREG-0737, Items II.K.3.24, II.K.3.28 and II.B.4
: 2. NRC letter to TVA, dated May 11, 1983, Request for Additional Information - NUREG-0737, Item II.K.3.28, Qualification of ADS Accumulators
: 2. NRC letter to TVA, dated May 11, 1983, Request for Additional Information - NUREG-0737, Item II.K.3.28, Qualification of ADS  
 
Accumulators
: 3. TVA letter to NRC, dated July 8, 1983, in regards to NUREG-0737, Item II.K.3.28
: 3. TVA letter to NRC, dated July 8, 1983, in regards to NUREG-0737, Item II.K.3.28
: 4. NRC letter to TVA, dated May 29, 1984, Request for Additional Information - MPA F-55 (TMI II.K.3.28) Qualification of ADS  
: 4. NRC letter to TVA, dated May 29, 1984, Request for Additional Information - MPA F-55 (TMI II.K.3.28) Qualification of ADS Accumulators
 
Accumulators
: 5. TVA letter to NRC, dated July 12, 1984, in regards to NUREG-0737, Item II.K.3.28
: 5. TVA letter to NRC, dated July 12, 1984, in regards to NUREG-0737, Item II.K.3.28
: 6. TVA letter to NRC, dated July 11, 1985, in regards to NUREG-0737, Item II.K.3.28
: 6. TVA letter to NRC, dated July 11, 1985, in regards to NUREG-0737, Item II.K.3.28
: 7. NRC letter to TVA, dated July 24, 1985, NUREG-0737, Item II.K.3.28, Qualification of ADS
: 7. NRC letter to TVA, dated July 24, 1985, NUREG-0737, Item II.K.3.28, Qualification of ADS Accumulators April 13, 2007                   E1-124
 
: 8. NRC letter to TVA, dated August 15, 2005, Browns Ferry Nuclear Plant Unit 1 Recovery - NRC Integrated Inspection Report 05000259/2005007 April 13, 2007                 E1-125
Accumulators  
 
April 13, 2007 E1-125
: 8. NRC letter to TVA, dated August 15, 2005, Browns Ferry Nuclear Plant Unit 1 Recovery - NRC  
 
Integrated Inspection Report 05000259/2005007  
 
April 13, 2007 E1-126 Platform Thermal Growth
 
Issue: TVA will address thermal growth in drywell platforms and miscellaneous steel frames.
 
Discussion: In Reference 1 , TVA informed NRC that TVA's program for the resolution of issues associated with
 
drywell steel platforms for Unit 3 was incorporated
 
into the program "Lower Drywell Platforms and
 
Miscellaneous Steel."  This program includes upper
 
drywell platforms and platform thermal growth as


well.
Platform Thermal Growth Issue:        TVA will address thermal growth in drywell platforms and miscellaneous steel frames.
Status: C-C  
Discussion:  In Reference 1, TVA informed NRC that TVAs program for the resolution of issues associated with drywell steel platforms for Unit 3 was incorporated into the program Lower Drywell Platforms and Miscellaneous Steel. This program includes upper drywell platforms and platform thermal growth as well.
 
Status:       C-C Refer to previous topic entitled Lower Drywell Platforms and Miscellaneous Steel (Page E1-106).
Refer to previous topic entitled Lower Drywell  
 
Platforms and Miscellaneous Steel (Page E1-106).  


==References:==
==References:==
1.
: 1. TVA letter, T. E. Abney to NRC, dated December 13, 2002, Browns Ferry Nuclear Plant (BFN) - Unit 1 - Regulatory Framework for the Restart of Unit 1 April 13, 2007                  E1-126
TVA letter, T. E. Abney to NRC, dated December 13, 2002, Browns Ferry Nuclear Plant (BFN) - Unit 1 - Regulatory Framework for the  


Restart of Unit 1
Q-List Commitment:   TVA will develop a Q-list which provides a list of safety-related systems, structures, and components necessary to ensure:
 
* The integrity of the reactor coolant pressure boundary;
April 13, 2007 E1-127 Q-List Commitment: TVA will develop a Q-list which provides a list of safety-related systems, structures, and components  
* The capability to shut down the reactor and maintain it in a safe shutdown condition; and
 
* The capability to prevent or mitigate the consequences of accidents which could result in potential offsite radiation exposures comparable to the 10 CFR 100 limits.
necessary to ensure: The integrity of the reactor coolant pressure boundary; The capability to shut down the reactor and maintain it in a safe shutdown condition; and The capability to prevent or mitigate the consequences of accidents which could result in  
Discussion:   BFNs Q-List Program is described in Section III.14.1 of the Browns Ferry Nuclear Performance Plan (Reference 1).
 
Status:       Complete TVA has incorporated Unit 1 into BFNs Q-List Program.
potential offsite radiation exposures comparable  
 
to the 10 CFR 100 limits.  
 
Discussion: BFN's Q-List Program is described in Section III.14.1 of the Browns Ferry Nuclear  
 
Performance Plan (Reference 1).  
 
Status: Complete TVA has incorporated Unit 1 into BFN's Q-List  
 
Program.  


==References:==
==References:==
1.
: 1. TVA letter to NRC, dated October 24, 1988, Browns Ferry Nuclear Plant (BFN) - Nuclear Performance Plan, Revision 2 April 13, 2007                 E1-127
TVA letter to NRC, dated October 24, 1988, Browns Ferry Nuclear Plant (BFN) - Nuclear  
 
Performance Plan, Revision 2  
 
April 13, 2007 E1-128 Restart Test Program
 
Commitment: For those systems that support safe shutdown, administrative controls for the Restart Test


Program will be implemented to insure that an  
Restart Test Program Commitment:  For those systems that support safe shutdown, administrative controls for the Restart Test Program will be implemented to insure that an assessment of the Unit 3 System Test Specifications, test procedures, and test results is performed. Administrative controls will be used to insure that the status of the operating units is considered during the planning and scheduling of restart tests.
 
Discussion:   The restart test program was submitted in Reference 1 and supplemented by References 2 through 6.
assessment of the Unit 3 System Test  
Status:       Open
 
Specifications, test procedures, and test results  
 
is performed. Administrative controls will be used  
 
to insure that the sta t us of the operating units is considered during the planning and scheduling of  
 
restart tests.  
 
Discussion: The restart test program was submitted in Reference 1 and supplemented by References 2  
 
through 6.  
 
Status: Open  


==References:==
==References:==
1.
: 1. TVA letter to NRC, dated September 27, 1991, Restart Test Program (RTP) Description for Units 1 and 3
TVA letter to NRC, dated September 27, 1991, Restart Test Program (RTP) Description for  
: 2. TVA letter to NRC, dated February 18, 1992, Request for Additional Information Regarding the Restart Test Program for Units 1 and 3
 
: 3. TVA letter to NRC, dated December 28, 1992, Update of Restart Test Program (RTP) Submittal for Units 1 and 3
Units 1 and 3
: 2. TVA letter to NRC, dated February 18, 1992, Request for Additional Information Regarding the  
 
Restart Test Program for Units 1 and 3
: 3. TVA letter to NRC, dated December 28, 1992, Update of Restart Test Program (RTP) Submittal  
 
for Units 1 and 3
: 4. TVA letter to NRC, dated July 19, 1993, Restart Test Program (RTP) Update for Units 1 and 3
: 4. TVA letter to NRC, dated July 19, 1993, Restart Test Program (RTP) Update for Units 1 and 3
: 5. TVA letter to NRC, dated February 2, 1994, Restart Test Program (RTP) Update for
: 5. TVA letter to NRC, dated February 2, 1994, Restart Test Program (RTP) Update for Units 1 and 3
 
: 6. TVA letter to NRC, dated June 15, 2005, Browns Ferry Nuclear Plant, Unit 1 Request for Additional Information Regarding Restart Testing Program April 13, 2007                 E1-128
Units 1 and 3
: 6. TVA letter to NRC, dated June 15, 2005, Browns Ferry Nuclear Plant, Unit 1 - Request for  
 
Additional Information Regarding Restart Testing  
 
Program April 13, 2007 E1-129 Seismic Class II Over I / Spatial Systems Interactions and Water Spray
 
Commitment: The Seismic Class II Over I / Spatial Systems Interactions and Water Spray program will be
 
implemented in accordance with the Unit 2
 
precedent.
 
Discussion: TVA is utilizing a two phase program to address Class II systems. The action plan for Unit 1 was
 
provided to th e NRC in Reference 1. The first part involves the evaluation of potential 
 
seismic-induced water spray effects of Class II
 
systems on Class I systems. The second part
 
involves the evaluation of potential 
 
seismic-induced, spatial interaction effects of
 
Class II systems on Class I systems. The approval
 
of the Seismic Class II Over I / Spatial Systems
 
Interactions and Water Spray program is contained
 
in References 2 and 3.
 
Status: Complete


Walk downs were completed. Outliers were resolved  
Seismic Class II Over I / Spatial Systems Interactions and Water Spray Commitment:  The Seismic Class II Over I / Spatial Systems Interactions and Water Spray program will be implemented in accordance with the Unit 2 precedent.
 
Discussion:  TVA is utilizing a two phase program to address Class II systems. The action plan for Unit 1 was provided to the NRC in Reference 1. The first part involves the evaluation of potential seismic-induced water spray effects of Class II systems on Class I systems. The second part involves the evaluation of potential seismic-induced, spatial interaction effects of Class II systems on Class I systems. The approval of the Seismic Class II Over I / Spatial Systems Interactions and Water Spray program is contained in References 2 and 3.
by either further analysis, plant modification, or  
Status:      Complete Walk downs were completed. Outliers were resolved by either further analysis, plant modification, or maintenance action.
 
maintenance action.  


==References:==
==References:==
1.
: 1. TVA letter to NRC dated February 27, 1991, Browns Ferry Nuclear Plant (BFN) - Action Plan to Disposition Concerns Related to Units 1 and 3 Seismic Class II Piping Over Class I Commodities
TVA letter to NRC dated February 27, 1991, Browns Ferry Nuclear Plant (BFN) - Action Plan  
: 2. NRC letter to TVA, dated January 23, 1991, NUREG-1232, Volume 3, Supplement 2 -
 
to Disposition Concerns Related to Units 1 and 3  
 
Seismic Class II Piping Over Class I Commodities
: 2. NRC letter to TVA, dated January 23, 1991, NUREG-1232, Volume 3, Supplement 2 -
 
Browns Ferry, Unit 2, Section 2.2.4.2 (Page 2-10)
Browns Ferry, Unit 2, Section 2.2.4.2 (Page 2-10)
: 3. NRC letter to TVA, dated November 19, 1992, Generic Letter 87-02, Supplement 1 Response -  
: 3. NRC letter to TVA, dated November 19, 1992, Generic Letter 87-02, Supplement 1 Response -
Browns Ferry Nuclear Plant (TAC Nos. M69430, M69431, and M69432)
April 13, 2007                  E1-129


Browns Ferry Nuclear Plant (TAC Nos. M69430, M69431, and M69432)
Small Bore Piping Commitment:   The Seismic Class I small bore piping will be qualified to meet the final design criteria.
 
Discussion:   TVA's action plan to disposition concerns related to Units 1 and 3 small bore piping was provided in Reference 1 and augmented by Reference 2. NRC approval of this program is documented in the Safety Evaluation transmitted by Reference 3.
April 13, 2007 E1-130 Small Bore Piping  
Status:       Complete TVA qualified the Class I small bore piping to meet the final design criteria.
 
Commitment: The Seismic Class I small bore piping will be qualified to meet the final design criteria.  
 
Discussion: TVA's action plan to disposition concerns related to Units 1 and 3 small bore piping was provided in  
 
Reference 1 and augmented by Reference 2. NRC  
 
approval of this program is documented in the  
 
Safety Evaluation transmitted by Reference 3.  
 
Status: Complete  
 
TVA qualified the Class I small bore piping to meet  
 
the final design criteria.  


==References:==
==References:==
1.
: 1. TVA letter to NRC, dated February 27, 1991, Action Plan to Disposition concerns Related to Units 1 and 3 Small Bore Piping
TVA letter to NRC, dated February 27, 1991, Action Plan to Disposition concerns Related to  
: 2. TVA letter to NRC, dated December 12, 1991, Small Bore Piping Program, Tubing, and Conduit Support Plans for Units 1 and 3 - Additional Information
 
: 3. NRC letter to TVA, dated February 4, 1992, Safety Evaluation of Small Bore Piping and Seismic Qualification of Instrument Tubing Programs for Browns Ferry Nuclear Plant, Units 1 and 3 April 13, 2007                 E1-130
Units 1 and 3 Small Bore Piping
: 2. TVA letter to NRC, dated December 12, 1991, Small Bore Piping Program, Tubing, and Conduit  
 
Support Plans for Units 1 and 3 - Additional  
 
Information
: 3. NRC letter to TVA, dated February 4, 1992, Safety Evaluation of Small Bore Piping and  
 
Seismic Qualification of Instrument Tubing  
 
Programs for Browns Ferry Nuclear Plant,
 
Units 1 and 3  
 
April 13, 2007 E1-131 Thermal Overloads
 
Commitment: TVA will resolve the thermal overload issue on Unit 1 prior to restart.
 
Discussion: A review of BFN design drawings identified that thermal overload (TOL) heater sizes for 480 VAC and
 
250 VDC motor control centers (MCs) were not
 
specified. Consequently, there was no
 
documentation to verify that TOL heater
 
installations are properly sized.
 
TVA's plan for addressing the TOL issue was
 
submitted in Reference
: 1. NRC requested additional information in Reference 2, which TVA provided in
 
Reference 3. Supplemental information was provided
 
in References 4 and 5. NRC approval of the program
 
is documented in Reference 6.
 
Status: C-C
 
TVA completed a walkdown program to document the
 
nameplate data for each load and replaced the TOLs
 
with ones of the proper size. The criteria for
 
sizing has been determined and documented. 
 
Calculations have been performed to ensure the TOL
 
heaters are the proper size for their loads.


Thermal Overloads Commitment:  TVA will resolve the thermal overload issue on Unit 1 prior to restart.
Discussion:  A review of BFN design drawings identified that thermal overload (TOL) heater sizes for 480 VAC and 250 VDC motor control centers (MCs) were not specified. Consequently, there was no documentation to verify that TOL heater installations are properly sized.
TVAs plan for addressing the TOL issue was submitted in Reference 1. NRC requested additional information in Reference 2, which TVA provided in Reference 3. Supplemental information was provided in References 4 and 5. NRC approval of the program is documented in Reference 6.
Status:      C-C TVA completed a walkdown program to document the nameplate data for each load and replaced the TOLs with ones of the proper size. The criteria for sizing has been determined and documented.
Calculations have been performed to ensure the TOL heaters are the proper size for their loads.
NRC closed this item in document dated March 9, 2007 (Reference 7).
NRC closed this item in document dated March 9, 2007 (Reference 7).


==References:==
==References:==
1.
: 1. TVA letter to NRC, dated April 28, 1988, Browns Ferry Nuclear Plant (BFN)- Electrical Issues (NRC TAC No. 62260)
TVA letter to NRC, dated April 28, 1988, Browns Ferry Nuclear Plant (BFN)- Electrical Issues (NRC TAC No. 62260)
: 2. NRC letter to TVA, dated August 10, 1988, Request For Additional Information - Browns Ferry Nuclear Plant, Unit 2
: 2. NRC letter to TVA, dated August 10, 1988, Request For Additional Information - Browns  
: 3. TVA letter to NRC, dated September 21, 1988, Browns Ferry Nuclear Plant (BFN) - Response to Request for Additional Information - Electric Circuit Protection by Current Limiting Fuses (TAC No. 62260-F)
 
: 4. TVA letter to NRC, dated February 28, 1989, Browns Ferry Nuclear Plant (BFN) - Thermal Overload (TOL) Heaters (TAC No. 62260-F)
Ferry Nuclear Plant, Unit 2
: 3. TVA letter to NRC, dated September 21, 1988, Browns Ferry Nuclear Plant (BFN) - Response to  
 
Request for Additional Information - Electric  
 
Circuit Protection by Current Limiting Fuses (TAC No. 62260-F)
: 4. TVA letter to NRC, dated February 28, 1989, Browns Ferry Nuclear Plant (BFN) - Thermal  
 
Overload (TOL) Heaters (TAC No. 62260-F)
: 5. TVA letter to NRC, dated May 15, 1989, Browns Ferry Nuclear Plant (BFN) - Thermal Overload (TOL) Heaters - Sizing Criteria Clarification -
: 5. TVA letter to NRC, dated May 15, 1989, Browns Ferry Nuclear Plant (BFN) - Thermal Overload (TOL) Heaters - Sizing Criteria Clarification -
(TAC No. 62260-F)
(TAC No. 62260-F)
April 13, 2007 E1-132
April 13, 2007                   E1-131
: 6. NRC letter to TVA, dated January 23, 1991, NUREG-1232, Volume 3, Supplement 2 -
: 6. NRC letter to TVA, dated January 23, 1991, NUREG-1232, Volume 3, Supplement 2 -
 
Browns Ferry, Unit 2, Section 3.11.1 (Page 3-8)
Browns Ferry, Unit 2, Section 3.11.1 (Page 3-8)
: 7. NRC Meeting Summary dated March 9, 2007, "Meeting Summary - Internal Meeting of  
: 7. NRC Meeting Summary dated March 9, 2007, Meeting Summary - Internal Meeting of the Browns Ferry Unit 1 Restart Panel -
Docket No. 50-259 April 13, 2007                  E1-132


the Browns Ferry Unit 1 Restart Panel -
Unresolved Safety Issue A-7, Mark I Long-Term Program Issue:       This Unresolved Safety Issue was resolved in August 1982, with the publication of Supplement 1 to NUREG-0661, Safety Evaluation Report, Mark I Containment Long-Term Program and Standard Review Plan Section 6.2.1.1.C.
 
Discussion:   Refer to previous topic entitled Long Term Torus Integrity Program (Page E1-104).
Docket No. 50-259"
Status:       C-C Refer to previous topic entitled Long Term Torus Integrity Program (Page E1-104).
 
NRC administratively closed this item in Inspection Report 2006-007 (Reference 1). Since this item was added only as a tracking means for this Unresolved Safety Issue, TVA considers it complete also.
April 13, 2007 E1-133 Unresolved Safety Issue A-7, Mark I Long-Term Program  
 
Issue: This Unresolved Safety Issue was resolved in August 1982, with the publication of Supplement 1 to
 
NUREG-0661, "Safety Evaluation Report, Mark I  
 
Containment Long-Term Program" and Standard Review  
 
Plan Section 6.2.1.1.C.  
 
Discussion: Refer to previous topic entitled Long Term Torus Integrity Program (Page E1-104).  
 
Status: C-C  
 
Refer to previous topic entitled Long Term Torus  
 
Integrity Program (Page E1-104).  
 
NRC administratively c l osed this item in Inspection Report 2006-007 (Reference 1). Since this item was  
 
added only as a tracking means for this Unresolved  
 
Safety Issue, TVA considers it complete also.  


==References:==
==References:==
: 1. NRC letter to TVA, dated August 10, 2006, Browns Ferry Nuclear Plant Unit 1 Recovery - NRC  
: 1. NRC letter to TVA, dated August 10, 2006, Browns Ferry Nuclear Plant Unit 1 Recovery - NRC Integrated Inspection Report 05000259/2006007 April 13, 2007                  E1-133


Integrated Inspection Report 05000259/2006007
Unresolved Safety Issue A-9, Anticipated Transients Without Scram Issue:       This Unresolved Safety Issue was resolved in June 1983, with the publication of a final rule (10 CFR 50.62) to require improvements in plants to reduce the likelihood of failure of the reactor protection system (RPS) to shut down the reactor following anticipated transients and to mitigate the consequences of an anticipated transient without scram (ATWS) event.
 
Discussion:   TVA provided conceptual design information for conformance with the ATWS Rule in Reference 1. In Reference 2, the NRC found that TVAs design conformance with the ATWS Rule with exception that the Browns Ferry's Alternate Rod Injection and Reactor Pump Trip designs utilized the same analog trip units for both the ATWS system and the reactor trip system (RTS). TVAs response to the diversity issue was provided in Reference 3.
April 13, 2007 E1-134 Unresolved Safety Issue A-9, Anticipated Transients Without Scram Issue: This Unresolved Safety Issue was resolved in June 1983, with the publication of a final rule  
Status:       C-C TVA implemented the requirements, actions, and conceptual design modifications submitted. The analog trip units utilized for the ATWS and RPS systems were from different manufacturers.
 
NRC administratively closed this item in Inspection Report 2006-007 (Reference 4).
(10 CFR 50.62) to require improvements in plants to  
 
reduce the likelihood of failure of the reactor  
 
protection system (RPS) to shut down the reactor  
 
following anticipated transients and to mitigate  
 
the consequences of an anticipated transient  
 
without scram (ATWS) event.  
 
Discussion: TVA provided conceptual design information for conformance with the ATWS Rule in Reference 1. In  
 
Reference 2, the NRC found that TVA's design  
 
conformance with the ATWS Rule with exception that  
 
the Browns Ferry's Alternate Rod Injection and  
 
Reactor Pump Trip designs utilized the same analog  
 
trip units for both the ATWS system and the reactor  
 
trip system (RTS). TVA's response to the diversity  
 
issue was provided in Reference 3.  
 
Status: C-C  
 
TVA implemented the requirements, actions, and  
 
conceptual design modifications submitted. The  
 
analog trip units utilized for the ATWS and RPS  
 
systems were from different manufacturers.  
 
NRC administratively closed this item in Inspection  
 
Report 2006-007 (Reference 4).  


==References:==
==References:==
1.
: 1. TVA letter to NRC, dated March 1, 1988, Browns Ferry Nuclear Plant (BFN) - Anticipated Transients Without Scram (ATWS) Rule (10 CFR 50.62) - Plant Specific Design
TVA letter to NRC, dated March 1, 1988, Browns Ferry Nuclear Plant (BFN) - Anticipated  
: 2. NRC letter to TVA, dated January 22, 1989, Compliance with Rule 10 CFR 50.62 Relating to Alternate Rod Injection and Reactor Pump Trip Systems (TAC 59072, 59073 and 59074)
 
: 3. TVA letter to NRC, dated November 29, 1990, Browns Ferry Nuclear Plant (BFN) - Response to NRC Followup Items Received During ATWS Inspection
Transients Without Scram (ATWS) Rule
: 4. NRC letter to TVA, dated August 10, 2006, Browns Ferry Nuclear Plant Unit 1 Recovery - NRC Integrated Inspection Report 05000259/2006007 April 13, 2007                  E1-134
 
(10 CFR 50.62) - Plant Specific Design
: 2. NRC letter to TVA, dated January 22, 1989, Compliance with Rule 10 CFR 50.62 Relating to  
 
Alternate Rod Injection and Reactor Pump Trip  


Systems (TAC 59072, 59073 and 59074)
Unresolved Safety Issue A-24, Qualification of Class 1E Safety Related Equipment Issue:       This Unresolved Safety Issue was resolved in July 1981, with the publication of NUREG-0588, Revision 1, Interim Staff Position on Environmental Qualification of Safety-Related Electrical Equipment. In summary, the resolution of A-24 is embodied in 10 CFR 50.49.
: 3. TVA letter to NRC, dated November 29, 1990, Browns Ferry Nuclear Plant (BFN) - Response to
Discussion:   Refer to previous topic entitled Environmental Qualification (Page E1-45).
 
Status:       C-C Refer to previous topic entitled Environmental Qualification (Page E1-45).
NRC Followup Items Received During ATWS
NRC administratively closed this item in Inspection Report 2006-007 (Reference 1). Since this item was added only as a tracking means for this Unresolved Safety Issue, TVA considers it complete also.
 
Inspection
: 4. NRC letter to TVA, dated August 10, 2006, B r owns Ferry Nuclear Plant Unit 1 Recovery - NRC
 
Integrated Inspection Report 05000259/2006007
 
April 13, 2007 E1-135 Unresolved Safety Issue A-24, Qualification of Class 1E Safety Related Equipment  
 
Issue: This Unresolved Safety Issue was resolved in July 1981, with the publication of NUREG-0588, Revision 1, "Interim Staff Position on  
 
Environmental Qualification of Safety-Related  
 
Electrical Equipment.In summary, the resolution  
 
of A-24 is embodied in 10 CFR 50.49.  
 
Discussion: Refer to previous topic entitled Environmental Qualification (Page E1-45).  
 
Status: C-C  
 
Refer to previous topic entitled Environmental  
 
Qualification (Page E1-45).  
 
NRC administratively closed this item in Inspection  
 
Report 2006-007 (Reference 1). Since this item was  
 
added only as a tracking means for this Unresolved  
 
Safety Issue, TVA considers it complete also.  


==References:==
==References:==
1.
: 1. NRC letter to TVA, dated August 10, 2006, Browns Ferry Nuclear Plant Unit 1 Recovery - NRC Integrated Inspection Report 05000259/2006007
NRC letter to TVA, dated August 10, 2006, Browns Ferry Nuclear Plant Unit 1 Recovery - NRC  
: 2. Refer to previous topic entitled Environmental Qualification (Page E1-45).
April 13, 2007                  E1-135


Integrated Inspection Report 05000259/2006007
Unresolved Safety Issue A-26, Reactor Vessel Pressure Transient Protection Issue:       This Unresolved Safety Issue was resolved in September 1978, with the publication of NUREG-0224, Reactor Vessel Pressure Transient Protection for PWRs, and Standard Review Plan Section 5.2. NRC subsequently issued Generic Letter 88-11, NRC Position on Radiation Embrittlement of Reactor Vessel Materials and Its Impact on Plant Operations, which provided guidance regarding the review of pressure-temperature limits.
: 2. Refer to previous topic entitled Environmental Qualification (Page E1-45).
Discussion:   Refer to previous topic entitled Generic Letter 88-11, Radiation Embrittlement of Reactor Vessel Materials and Its Impact on Plant Operations (Page E1-61).
 
Status:       C-C Refer to previous topic entitled Generic Letter 88-11, Radiation Embrittlement of Reactor Vessel Materials and Its Impact on Plant Operations (Page E1-61).
April 13, 2007 E1-136 Unresolved Safety Issue A-26, Reactor Vessel Pressure Transient Protection  
NRC administratively closed this item in Inspection Report 2006-007 (Reference 1). Since this item was added only as a tracking means for this Unresolved Safety Issue, TVA considers it complete also.
 
Issue: This Unresolved Safety Issue was resolved in September 1978, with the publication of
 
NUREG-0224, "Reactor Vessel Pressure Transient  
 
Protection for PWRs," and Standard Review Plan  
 
Section 5.2. NRC subsequently issued Generic  
 
Letter 88-11, "NRC Position on Radiation  
 
Embrittlement of Reactor Vessel Materials and Its  
 
Impact on Plant Operations," which provided  
 
guidance regarding the review of
 
pressure-temperature limits.  
 
Discussion: Refer to previous topic entitled Generic Letter 88-11, Radiation Embrittlement of Reactor Vessel  
 
Materials and Its Impact on Plant Operations (Page E1-61).  
 
Status: C-C  
 
Refer to previous topic entitled Generic Letter
 
88-11, Radiation Embrittlement of Reactor Vessel  
 
Materials and Its Impact on Plant Operations (Page E1-61).  
 
NRC administrat i vely closed this item in Inspection Report 2006-007 (Reference 1). Since this item was  
 
added only as a tracking means for this Unresolved  
 
Safety Issue, TVA considers it complete also.  


==References:==
==References:==
1.
: 1. NRC letter to TVA, dated August 10, 2006, Browns Ferry Nuclear Plant Unit 1 Recovery - NRC Integrated Inspection Report 05000259/2006007
NRC letter to TVA, dated August 10, 2006, Browns Ferry Nuclear Plant Unit 1 Recovery - NRC  
: 2. Refer to previous topic entitled Generic Letter 88-11, Radiation Embrittlement of Reactor Vessel Materials and its Impact on Plant Operations (Page E1-61).
 
April 13, 2007                   E1-136
Integrated Inspection Report 05000259/2006007
: 2. Refer to previous topic entitled Generic Letter 88-1 1, Radiation Embrittlement of Reactor Vessel Materials and its Impact on Plant  
 
Operations (Page E1-61).  
 
April 13, 2007 E1-137 Unresolved Safety Issue A-44, Station Blackout
 
Issue: This Unresolved Safety Issue was resolved in June 1988,with the publication of the Station Blackout
 
Rule (10 CFR 50.63) and Regulatory Guide 1.155.
 
Discussion: In Reference 1, the staff Safety Evaluation concluded that TVA's proposed methodology for


coping with a Station Blackout event at BFN,
Unresolved Safety Issue A-44, Station Blackout Issue:        This Unresolved Safety Issue was resolved in June 1988,with the publication of the Station Blackout Rule (10 CFR 50.63) and Regulatory Guide 1.155.
 
Discussion:  In Reference 1, the staff Safety Evaluation concluded that TVA's proposed methodology for coping with a Station Blackout event at BFN, Units 1, 2, and 3 conforms with 10 CFR 50.63. As requested in the NRCs Safety Evaluation Report, TVA provided its implementation schedule in Reference 2. This letter included a commitment to complete the Unit 1 equipment and associated procedure modifications required for SBO rule compliance prior to restart.
Units 1, 2, and 3 conforms with 10 CFR 50.63. As  
Status:       Complete TVA implemented the modifications to the DC power supply system and the DC connected loads.
 
requested in the NRC's Safety Evaluation Report, TVA provided its implementation schedule in  
 
Reference 2. This letter included a commitment to  
 
complete the Unit 1 equipment and associated  
 
procedure modifications required for SBO rule  
 
compliance prior to restart.  
 
Status: Complete TVA implemented the modifications to the DC power supply system and the DC connected loads.


==References:==
==References:==
1.
: 1. NRC letter to TVA, dated September 16, 1992, Station Blackout - Browns Ferry Units 1, 2, and 3 (MPA-A022) (TAC Nos. M68517, M68518, and M68519)
NRC letter to TVA, dated September 16, 1992, Station Blackout - Browns Ferry Units 1, 2,
: 2. TVA letter to NRC, dated October 15, 1992, Browns Ferry Nuclear Plant (BFN) - Response to NRC Supplemental Safety Evaluation on the Conformance of BFN with the Station Blackout (SBO) Rule April 13, 2007                  E1-137


and 3 (MPA-A022) (TAC Nos. M68517, M68518, and
Unresolved Safety Issue A-46, Seismic Qualification of Equipment in Operating Plants Issue:       This Unresolved Safety Issue was resolved with the issuance of Generic Letter 87-02 on February 19, 1987, which endorsed the approach of using the seismic and test experience data proposed by the Seismic Qualification Utility Group (SQUG) and Electric Power Research Institute (EPRI). This approach was endorsed by the Senior Seismic Review and Advisory Panel (SSRAP) and approved by the NRC staff.
 
Discussion:   Refer to previous topic entitled Generic Letter 87-02, Verification of Seismic Adequacy of Mechanical and Electrical Equipment In Operating Reactors, Unresolved Safety Issue (USI) A-46 (Page E1-58).
M68519) 2. TVA letter to NRC, dated October 15, 1992, Browns Ferry Nuclear Plant (BFN) - Response to
Status:       Refer to previous topic entitled Generic Letter 87-02, Verification of Seismic Adequacy of Mechanical and Electrical Equipment In Operating Reactors, Unresolved Safety Issue (USI) A-46 (Page E1-58).
 
NRC Supplemental Safety Evaluation on the
 
Conformance of BFN with the Station Blackout (SBO) Rule
 
April 13, 2007 E1-138 Unresolved Safety Issue A-46, Seismic Qualification of Equipment in Operating Plants  
 
Issue: This Unresolved Safety Issue was resolved with the issuance of Generic Letter 87-02 on  
 
February 19, 1987, which endorsed the approach of  
 
using the seismic and test experience data proposed  
 
by the Seismic Qualification Utility Group (SQUG)  
 
and Electric Power Research Institute (EPRI). This  
 
approach was endorsed by the Senior Seismic Review  
 
and Advisory Panel (SSRAP) and approved by the NRC  
 
staff.
Discussion: Refer to previous topic entitled Generic Letter 87-02, Verification of Seismic Adequacy of  
 
Mechanical and Electrical Equipment In Operating  
 
Reactors, Unresolved Safety Issue (USI) A-46 (Page E1-58).  
 
Status: Refer to previous topic entitled Generic Letter 87-02, Verification of Seismic Adequacy of  
 
Mechanical and Electrical Equipment In Operating  
 
Reactors, Unresolved Safety Issue (USI) A-46 (Page E1-58).  


==References:==
==References:==
Refer to previous topic entitled Generic Letter 87-02, Verification of Seismic Adequacy of  
Refer to previous topic entitled Generic Letter 87-02, Verification of Seismic Adequacy of Mechanical and Electrical Equipment In Operating Reactors, Unresolved Safety Issue (USI) A-46 (Page E1-58).
April 13, 2007                  E1-138


Mechanical and Electrical Equipment In Operating
ENCLOSURE 2 TENNESSEE VALLEY AUTHORITY BROWNS FERRY NUCLEAR PLANT (BFN)
 
Reactors, Unresolved Safety Issue (USI) A-46 (Page E1-58).
 
April 13, 2007 E2-1 ENCLOSURE 2 TENNESSEE VALLEY AUTHORITY BROWNS FERRY NUCLEAR PLANT (BFN)  


==SUMMARY==
==SUMMARY==
OF REMAINING UNIT 1 RESTART ISSUES  
OF REMAINING UNIT 1 RESTART ISSUES TOPIC                       COMMITMENT                   SCHEDULE   PAGE Generic Letter 92-01,     TVA has submitted the available   Ninety days after E1-75 Reactor Vessel            data requested by NRC. TVA         the final Structural Integrity,      will inform NRC of the             surveillance Revision 1, and            applicability of NEDO 32205       capsules analysis Revision 1 Supplement 1    within 90 days of the final       report.
 
surveillance capsules analysis report.
TOPIC COMMITMENT SCHEDULE PAGE Generic Letter 92-01, Reactor Vessel
April 13, 2007                            E2-1}}
 
Structural Integrity, Revision 1, and
 
Revision 1 Supplement 1  TVA has submitted the available data requested by NRC. TVA  
 
will inform NRC of the  
 
applicability of NEDO 32205  
 
within 90 days of the final  
 
surveillance capsules analysis
 
report. Ninety days after the final
 
surveillance  
 
capsules analysis  
 
report. E1-75}}

Latest revision as of 16:39, 13 March 2020

Status of Unit 1 Restart Issues, Revision 12
ML071030397
Person / Time
Site: Browns Ferry Tennessee Valley Authority icon.png
Issue date: 04/13/2007
From: Crouch W
Tennessee Valley Authority
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
Download: ML071030397 (151)


Text

April 13, 2007 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, D.C. 20555 Gentlemen:

In the Matter of ) Docket No. 50-259 Tennessee Valley Authority )

BROWNS FERRY NUCLEAR PLANT (BFN) - STATUS OF UNIT 1 RESTART ISSUES, REVISION 12 This letter updates the status of the Unit 1 Bulletins, Generic Letters, Nuclear Performance Plan Special Programs, and TMI Action Items identified in TVA's regulatory framework letters to NRC (References 1 and 2). As documented in the NRCs approval of TVAs regulatory framework (References 3 and 4), the staff requested and TVA agreed to provide formal notification of the completion of each generic communication within 90 days of its internal commitment completion. This letter is part of the process that is being used to satisfy this request. Additional items from the NRCs Browns Ferry Unit 1 Recovery Issues List (Reference 5) have also been included. to this letter provides background information regarding the regulatory framework for the restart of Unit 1, lists the individual issues cited in the framework letters and the NRCs Recovery Issues List, describes TVAs commitment or outstanding action for each issue, references key correspondence, discusses the background of the issue, and describes the completion or status of each issue, as appropriate. A summary of the issues that will be completed after restart for Unit 1 is provided as Enclosure 2.

U.S. Nuclear Regulatory Commission Page 2 April 13, 2007 TVA intends to periodically update this submittal until the Unit 1 commitments related to restart or power operation are completed (TVA committed actions are completed). The first status of these generic communications was provided in Reference 6. The updates will provide the formal notification of the completion of each Unit 1 Bulletin, Generic Letter, Nuclear Performance Plan Special Program, and TMI Action Item required for restart. Changes to the completion status and newly added issues are bolded in the table of contents.

Changes to the completion status are also bolded in the text which describes each item. Other changes are noted by revision bars on the right hand side of the page.

There are no new positions or commitments contained in this letter. If you have any questions, please contact me at (205) 729-2636.

Sincerely, Original signed by:

William D. Crouch Manager of Licensing and Industry Affairs

References:

1. TVA letter, T. E. Abney to NRC, dated December 13, 2002, Browns Ferry Nuclear Plant (BFN) - Unit 1 - Regulatory Framework for the Restart of Unit 1
2. TVA letter, T. E. Abney to NRC, dated February 28, 2003, Browns Ferry Nuclear Plant (BFN) - Unit 1 - Regulatory Framework for the Restart of Unit 1
3. NRC memorandum from K. N. Jabbour, dated May 13, 2003, Summary of April 24, 2003, Meeting Regarding the Regulatory Framework for Browns Ferry Unit 1 Restart Project (TAC No. MB7679)
4. NRC letter, K. N. Jabbour to J. A. Scalice, dated August 14, 2003, Regulatory Framework for the Restart of Browns Ferry Nuclear Plan, Unit 1 (TAC MB7679)

U.S. Nuclear Regulatory Commission Page 3 April 13, 2007

5. NRC letter, J. W. Shea to K. W. Singer, dated January 6, 2006, Meeting Summaries: 1.) Category 1 Public Meeting with Tennessee Valley Authority (TVA) RE. Browns Ferry Unit 1 Recovery Status; 2.) Meeting of the NRC Restart Panel for the Browns Ferry Unit 1 Recovery -

Docket No. 50-259

6. TVA letter, T. E. Abney to NRC, dated November 19, 2004, Browns Ferry Nuclear Plant (BFN) - Status of Unit 1 Restart Issues Enclosures cc (Enclosures):

(Via NRC Electronic Distribution)

U.S. Nuclear Regulatory Commission Region II Sam Nunn Atlanta Federal Center 61 Forsyth Street, SW, Suite 23T85 Atlanta, Georgia 30303-3415 Mr. Malcolm T. Widmann, Branch Chief U.S. Nuclear Regulatory Commission Region II Sam Nunn Atlanta Federal Center 61 Forsyth Street, SW, Suite 23T85 Atlanta, Georgia 30303-8931 NRC Senior Resident Inspector Browns Ferry Nuclear Plant 10833 Shaw Road Athens, AL 35611-6970 Ms. Margaret Chernoff, Senior Project Manager U.S. Nuclear Regulatory Commission (MS 08G9)

One White Flint, North 11555 Rockville Pike Rockville, Maryland 20852-2739 Ms. Eva A. Brown, Project Manager U.S. Nuclear Regulatory Commission (MS 08G9)

One White Flint, North 11555 Rockville Pike Rockville, Maryland 20852-2739

U.S. Nuclear Regulatory Commission Page 4 April 13, 2007 JEM:TLE:BAB Enclosures cc (Enclosures):

M. Bajestani, NAB 1A-BFN A. S. Bhatnagar, LP 6A-C R. H. Bryan, Jr., LP 4J-C R. G. Jones, POB 2C-BFN R. F. Marks, PAB 1A-BFN B. J. OGrady, PAB 1E-BFN P. D. Swafford, LP 6A-C J. Valente, NAB 1E-BFN E. J. Vigluicci, WT 6A-K B. A. Wetzel, BR 4X-C NSRB Support, LP 5M-C EDMS WT CA-K S:lic/submit/subs/Status of Unit 1 Restart Issues - R12.doc

INDEX TO ENCLOSURE 1 TENNESSEE VALLEY AUTHORITY BROWNS FERRY NUCLEAR PLANT (BFN)

STATUS OF UNIT 1 ISSUES TABLE OF COMMENTS STATUS FOR TOPIC PAGE RESTART Background E1-1 -

Bulletin 79-02, Pipe Support Base Plate Designs Using Concrete Expansion Anchor Bolts E1-4 C-C Bulletin 79-12, Short Period Scrams at BWR Facilities E1-5 C-C Bulletin 79-14, Seismic Analysis for As-Built Safety-Related Piping Systems E1-6 C-C Bulletin 80-06, Engineered Safety Feature (ESF)

Reset Controls E1-7 C-C Bulletin 84-02, Failures of General Electric Type HFA Relays in Use in Class 1E Safety Systems E1-8 Closed Bulletin 86-02, Static "O" Ring Differential Pressure Switches E1-9 C-C Bulletin 88-03, Inadequate Latch Engagement in HFA Type Relays Manufactured by General Electric (GE) Company E1-11 Closed Bulletin 88-04, Potential Safety-Related Pump Loss E1-12 C-C Bulletin 88-07, Power Oscillations in Boiling Water Reactors, and Supplement 1 E1-14 C-C Bulletin 88-10, Nonconforming Molded-Case Circuit Breakers E1-15 C-C Open: TVA committed actions are not complete.

Closed: Item has been closed by NRC document.

Complete: TVA committed actions are completed.

C-C: Issue is Closed and Complete.

E1-i

STATUS FOR TOPIC PAGE RESTART Bulletin 90-01, Loss of Fill Oil in Transmitters Manufactured by Rosemount E1-16 C-C Bulletin 93-02, Debris Plugging of Emergency Core Cooling Suction Strainers, and Supplement 1 E1-18 C-C Bulletin 93-03, Resolution of Issues Related To Reactor Vessel Water Level Instrumentation in BWRs E1-20 C-C Bulletin 95-02, Unexpected Clogging of a Residual Heat Removal (RHR) Pump Strainer While Operating in Suppression Pool Cooling Mode E1-21 C-C Bulletin 96-03, Potential Plugging of Emergency Core Cooling Suction Strainers by Debris in Boiling-Water Reactors E1-22 C-C Cable Ampacity E1-23 Complete Cable Installation Issue Number 1, Brand Rex Cable Issues E1-24 Open Cable Installation Issue Number 2, Cable Separations Issues E1-25 Complete Cable Installation Issue Number 3, Low Voltage Vertical Cable Supports E1-28 Open Cable Installation Issue Number 4, Medium Voltage Cable Bend Radius E1-29 Open Cable Installation Issue Number 5, Missing Conduit Bushings E1-31 Open Cable Installation Issue Number 6, Sidewall Pressure, Cable Pullbys, Cable Jamming, Pulling Around 90 Degree Condulets and Thru Mid-Run Flex Conduit Issues E1-32 Open Open: TVA committed actions are not complete.

Closed: Item has been closed by NRC document.

Complete: TVA committed actions are completed.

C-C: Issue is Closed and Complete.

E1-ii

STATUS FOR TOPIC PAGE RESTART Cable Installation Issue Number 7, Use of Condulets as Pull Points E1-33 Open Cable Installation Issue Number 8, Medium Voltage Vertical Cable Supports E1-34 Open Cable Splices E1-35 Complete Cable Tray Supports E1-36 C-C Component and Piece Part Qualification E1-38 Complete Conduit Supports E1-39 C-C Configuration Management/Design Baseline E1-41 C-C Containment Coatings E1-42 Complete Control Rod Drive (CRD) Insert and Withdrawal Piping E1-43 C-C Design Calculation Review E1-44 C-C Environmental Qualification E1-45 Open Fire Protection / 10 CFR 50, Appendix R E1-46 Open Flexible Conduits E1-48 Complete Fuses E1-50 Complete Generic Letter 82-33, Instrumentation to Follow the Course of an Accident - Regulatory Guide 1.97 E1-51 C-C Generic Letter 83-08, Modification of Vacuum Breakers on Mark 1 Containments E1-54 C-C Generic Letter 83-28, Salem ATWS, Item 1.2, Post Trip Review (Data and Information Capability) E1-55 Closed Open: TVA committed actions are not complete.

Closed: Item has been closed by NRC document.

Complete: TVA committed actions are completed.

C-C: Issue is Closed and Complete.

E1-iii

STATUS FOR TOPIC PAGE RESTART Generic Letter 83-28, Salem ATWS, Item 4.5.2, Periodic On-Line Testing E1-56 Closed Generic Letter 83-28, Salem ATWS, Item 4.5.3, Intervals for On-Line Testing E1-57 Closed Generic Letter 87-02, Verification of Seismic Adequacy of Mechanical and Electrical Equipment In Operating Reactors, Unresolved Safety Issue (USI) A-46 E1-58 Complete Generic Letter 88-01, NRC Position on IGSCC in BWR Austenitic Stainless Steel Piping E1-60 C-C Generic Letter 88-11, Radiation Embrittlement of Reactor Vessel Materials and Its Impact on Plant Operations E1-61 C-C Generic Letter 88-14, Instrument Air Supply System Problems Affecting Safety-Related Equipment E1-63 Closed Generic Letter 88-20, Individual Plant Examination for Severe Accident Vulnerabilities E1-64 Complete Generic Letter 88-20, Supplement 4, Individual Plant Examination of External Events (IPEEE) for Severe Accident Vulnerabilities E1-66 Complete Generic Letter 89-06, Task Action Plan Item I.D.2 - Safety Parameter Display System E1-68 Closed Generic Letter 89-08, Erosion/Corrosion-Induced Pipe Wall Thinning E1-70 Closed Generic Letter 89-10, Safety-Related Motor-Operated Valve Testing and Surveillance E1-71 Closed Generic Letter 89-13, Service Water System Problems Affecting Safety-Related Equipment E1-73 C-C Open: TVA committed actions are not complete.

Closed: Item has been closed by NRC document.

Complete: TVA committed actions are completed.

C-C: Issue is Closed and Complete.

E1-iv

STATUS FOR TOPIC PAGE RESTART Generic Letter 89-16, Installation of a Hardened Wetwell Vent E1-74 C-C Generic Letter 92-01, Reactor Vessel Structural Integrity, Revision 1, and Revision 1 Supplement 1 E1-75 C-C Generic Letter 92-04, Resolution of the Issues Related to Reactor Vessel Water Level Instrumentation in BWRs E1-78 C-C Generic Letter 94-02, Long-Term Solutions and Upgrade of Interim Operating Recommendations for Thermal-Hydraulic Instabilities in Boiling Water Reactors E1-79 Closed Generic Letter 94-03, Intergranular Stress Corrosion Cracking of Core Shrouds in Boiling Water Reactors E1-80 C-C Generic Letter 95-07, Pressure Locking and Thermal Binding of Safety-Related and Power-Operated Gate Valves E1-81 C-C Generic Letter 96-01, Testing of Safety-Related Logic Circuits E1-83 Closed Generic Letter 96-05, Periodic Verification of Design-Basis Capability of Motor-Operated Valves E1-84 C-C Generic Letter 96-06, Assurance of Equipment Operability and Containment Integrity During Design-Basis Accident Conditions E1-85 C-C Generic Letter 97-04, Assurance of Sufficient Net Positive Suction Head for Emergency Core Cooling and Containment Heat Removal Pumps E1-87 C-C Generic Letter 98-01, Year 2000 Readiness of Computer Systems at Nuclear Power Plants E1-89 C-C Open: TVA committed actions are not complete.

Closed: Item has been closed by NRC document.

Complete: TVA committed actions are completed.

C-C: Issue is Closed and Complete.

E1-v

STATUS FOR TOPIC PAGE RESTART Generic Letter 98-04, Potential for Degradation of the Emergency Core Cooling System and the Containment Spray System After a Loss-of-Coolant Accident Because of Construction and Protective Coating Deficiencies and Foreign Material in Containment E1-90 C-C Generic Letter 2003-01, Control Room Habitability E1-92 Complete Generic Safety Issue 75 / Multi-Plant Action B085, Generic Letter 83-28, Item 1.2, Post-Trip Review - Data and Information Capability E1-94 Closed HVAC Duct Supports E1-95 C-C Instrument Sensing Lines E1-96 Complete Instrument Tubing E1-97 Complete Intergranular Stress Corrosion Cracking (IGSCC) E1-98 C-C Large Bore Piping Supports E1-99 C-C License Renewal - Appendix F Commitments E1-100 Open License Renewal - Non-Appendix F Commitments E1-103 Open Long Term Torus Integrity Program E1-104 Complete Lower Drywell Platforms and Miscellaneous Steel E1-106 C-C Moderate Energy Line Break (MELB) E1-108 C-C NUREG-0737 (TMI Action Plan), Action Item I.D.1, Control Room Design Review E1-109 Closed NUREG-0737 (TMI Action Plan), Action Item I.D.2, Safety Parameter Display Console E1-111 Closed Open: TVA committed actions are not complete.

Closed: Item has been closed by NRC document.

Complete: TVA committed actions are completed.

C-C: Issue is Closed and Complete.

E1-vi

STATUS FOR TOPIC PAGE RESTART NUREG-0737 (TMI Action Plan), Action Item II.B.3, Post-Accident Sampling System E1-112 C-C NUREG-0737 (TMI Action Plan), Action Item II.E.4.2.1-4, Containment Isolation Dependability - Implement Diverse Isolation E1-114 Open NUREG-0737 (TMI Action Plan), Action Item II.F.1.2.C, Accident - Monitoring -

Containment High Range Radiation E1-115 Closed NUREG-0737 (TMI Action Plan), Action Item II.F.1.2.D, Accident - Monitoring -

Containment Pressure E1-116 C-C NUREG-0737 (TMI Action Plan), Action Item II.F.1.2.E, Accident - Monitoring -

Containment Water Level E1-117 C-C NUREG-0737 (TMI Action Plan), Action Item II.F.2.4 (Generic Letter 84-23),

Instrumentation for Detection of Inadequate Core Cooling E1-118 C-C NUREG-0737 (TMI Action Plan), Action Item II.K.3.13, HPCI/RCIC Initiation Levels E1-120 C-C NUREG-0737 (TMI Action Plan), Action Item II.K.3.18, ADS Actuation Modifications E1-122 Closed NUREG-0737 (TMI Action Plan), Action Item II.K.3.27, Common Reference Level for Vessel Level Instrumentation E1-123 C-C NUREG-0737 (TMI Action Plan), Action Item II.K.3.28, Qualification of ADS Accumulators E1-124 C-C Platform Thermal Growth E1-126 C-C Q-List E1-127 Complete Restart Test Program E1-128 Open Open: TVA committed actions are not complete.

Closed: Item has been closed by NRC document.

Complete: TVA committed actions are completed.

C-C: Issue is Closed and Complete.

E1-vii

STATUS FOR TOPIC PAGE RESTART Seismic Class II Over I / Spatial Systems Interactions and Water Spray E1-129 Complete Small Bore Piping E1-130 Complete Thermal Overloads E1-131 C-C Unresolved Safety Issue A-7, Mark I Long-Term Program E1-133 C-C Unresolved Safety Issue A-9, Anticipated Transients Without Scram E1-133 C-C Unresolved Safety Issue A-24, Qualification of Class 1E Safety Related Equipment E1-135 C-C Unresolved Safety Issue A-26, Reactor Vessel Pressure Transient Protection E1-136 C-C Unresolved Safety Issue A-44, Station Blackout E1-137 Complete Unresolved Safety Issue A-46, Seismic Qualification of Equipment in Operating Plants E1-138 Complete Open: TVA committed actions are not complete.

Closed: Item has been closed by NRC document.

Complete: TVA committed actions are completed.

C-C: Issue is Closed and Complete.

E1-viii

ENCLOSURE 1 TENNESSEE VALLEY AUTHORITY BROWNS FERRY NUCLEAR PLANT (BFN)

STATUS OF UNIT 1 ISSUES BACKGROUND The Browns Ferry Nuclear Plant (BFN) consists of three units.

Units 1 and 3 were voluntarily shut down by the Tennessee Valley Authority (TVA) in March 1985 because of questions about the primary containment isolation leak rate testing for Unit 1 and reactor water level instrumentation for Unit 3. Unit 2 was in a refueling outage at the time. Additional questions and concerns were subsequently raised about the overall adequacy of TVA's nuclear program, and Browns Ferry remained shut down until adequate corrective actions were defined to address the root causes of TVA's nuclear program problems.

On September 17, 1985, NRC requested, pursuant to 10 CFR 50.54(f), that TVA submit information about its plans for correcting Browns Ferrys problems and for correcting problems in the overall management of its nuclear program. NRC also requested that this information be submitted before TVA restarted Browns Ferry. In response to this request, TVA prepared a Corporate Nuclear Performance Plan (CNPP) Volume 1 which identified the root causes of the problems in the management of TVA's nuclear program and described TVA's plans for correcting those problems.

Additionally, TVA prepared a Browns Ferry Nuclear Performance Plan (BFNPP) Volume 3 which identified the root causes of problems specifically related to Browns Ferry, defined plans for correcting those problems, and responded to the NRC's request for Browns Ferry specific information. Taken together, these two plans provided a complete account of the actions which TVA undertook to improve its nuclear program for Browns Ferry.

The regulatory framework for the restart of Unit 2 after its extended outage was unusual. TVA's submittal of the Browns Ferry Nuclear Performance Plan and NRC's review and issuance of Safety Evaluation Reports for each individual program was atypical.

While this level of NRC involvement did result in added confidence for the approval of Unit 2 restart, it required significant TVA and NRC resources for the approval of individual programs and criteria. In most cases, TVA began the implementation of these programs "at risk, which meant prior to NRC approval. Significant redesign and additional modifications were required whenever the criteria was changed during the approval process. NRC evaluation of the BFNPP special programs was documented by the issuance of issue specific Safety April 13, 2007 E1-1

Evaluation Reports (SERs) or in NUREG-1232, Volume 3, Safety Evaluation Report on the Browns Ferry Nuclear Performance Plan, and its supplements. Following implementation of these recovery programs, Unit 2 returned to service on May 24, 1991, and was removed from the Problem Plant List in June 1992.

TVAs proposed regulatory framework for the restart of Units 1 and 3 (Reference 1) was more consistent with normal industry practice. The proposed programs were established to provide a high degree of confidence that the facility and personnel were ready to restart and operate Units 1 and 3 in a safe and reliable manner, and promote the efficient utilization of TVA and NRC resources. TVA's plans for the restart of Units 1 and 3 were based on the regulatory requirements, corrective action programs, commitments, Technical Specifications improvements, and internally identified deficiencies and concerns that were resolved prior to the restart of Unit 2. NRC approval of the framework for the restart of Units 1 and 3 was documented in Reference 2. Changes to the implementation of BFNPP special programs on Unit 3 was documented by the issuance of issue specific SERs. The NRC Staffs request that the Commission authorize the Region II Administrator to allow restart of Unit 3 was forwarded by SECY 95-264. Following restart plan completion and NRC restart approval, Unit 3 restarted on November 19, 1995.

Units 1 and 3 were removed from the Watch List in June 1996.

Since restart of Unit 3, there were changes in regulations, TVAs processes, and NRCs processes which warranted revision to the regulatory framework for restart of Unit 1. TVAs successful restart and operation of Units 2 and 3 and the proposed revision to the Unit 1 restart program (References 3 and 4) will establish a high degree of confidence that the facility and personnel are ready to restart and operate Unit 1 in a safe and reliable manner, and promote the efficient utilization of TVA and NRC resources. TVAs plans for the restart of Unit 1 continue to be based on the regulatory requirements, corrective action special programs, commitments, Technical Specifications improvements, and internally identified deficiencies and concerns that were resolved prior to restart of Units 2 and 3. TVA proposed that, at its discretion, it could modify the implementation precedent for BFNPP Special Programs to incorporate efficiencies or experience gained from use of those precedents in restarting Unit 3 or from changes in TVA internal processes.

As documented in the NRCs approval of TVAs proposed regulatory framework (References 5 and 6), the staff requested and TVA agreed to provide formal notification of the completion of each generic communication within 90 days of its internal commitment completion. This letter provides the process that will be used to satisfy this request. Additional items for restart were also identified in the NRCs Browns Ferry Unit 1 Recovery Issues List (Reference 7).

April 13, 2007 E1-2

This enclosure lists the individual issues cited in the framework letters and the NRCs Recovery Issues List, describes TVAs commitment or outstanding action for each issue, references key correspondence, discusses the background of the issue, and describes the completion or status of each issue, as appropriate.

A summary of the issues that will be completed after restart for Unit 1 is provided as Enclosure 2.

TVA intends to update this submittal until the Unit 1 commitments related to restart or power operation are completed (TVA committed actions are completed). Changes to the completion status and newly added issues are bolded in the table of contents. Changes to the completion status are also bolded in the text which describes each item. In addition, the bottom of each page will contain a stamp that will show the submittal date.

Other changes are noted by revision bars on the right hand side of the page. These updates will provide the formal notification of the completion of each Unit 1 Bulletin, Generic Letter, Nuclear Performance Plan Special Program, and TMI Action Item required for restart and listed in the regulatory framework letters.

REFERENCES

1. TVA letter to NRC, dated July 10, 1991, Regulatory Framework for the Restart of Units 1 and 3
2. NRC letter to TVA, dated April 1, 1992, Return to Service of Browns Ferry, Units 1 and 3
3. TVA letter to NRC, dated December 13, 2002, Regulatory Framework for the Restart of Unit 1
4. TVA letter to NRC, dated February 28, 2003, Regulatory Framework for the Restart of Unit 1
5. NRC memorandum from K. N. Jabbour, dated May 13, 2003, Summary of April 24, 2003, Meeting Regarding the Regulatory Framework for Browns Ferry Unit 1 Restart Project (TAC No.

MB7679)

6. NRC letter to TVA, dated August 14, 2003, Regulatory Framework for the Restart of Browns Ferry Nuclear Plant, Unit 1
7. NRC letter, J. W. Shea to K. W. Singer, dated January 6, 2006, Meeting Summaries: 1.) Category 1 Public Meeting with Tennessee Valley Authority (TVA) RE. Browns Ferry Unit 1 Recovery Status; 2.) Meeting of the NRC Restart Panel for the Browns Ferry Unit 1 Recovery - Docket No. 50-259 April 13, 2007 E1-3

Bulletin 79-02, Pipe Support Base Plate Designs Using Concrete Expansion Anchor Bolts Commitment: TVA will complete Bulletin 79-02.

Discussion: TVA initiated programs in 1979 to comply with Bulletins 79-02 and 79-14 regarding the adequacy of piping system supports and anchor bolts. BFNs programs involved the reanalysis of pipe stress problems using the as-built configuration and amplified response spectra for Seismic Class I structures and the evaluation of the acceptability of the associated pipe supports. The scope of the program included Unit 1 safety-related large bore (greater than 22 inches in diameter) piping and computer analyzed small bore piping that was not included in the Small Bore Piping Program.

Pipe stress analysis and pipe support evaluations are based on walkdown inspection data for the safety-related piping systems. The walkdown inspections were instituted to determine the actual field configuration of the Class I piping systems and supports. NRC approval of TVA's program for the resolution of Bulletins 79-02 and 79-14 is documented in Reference 1.

Status: C-C Piping stress analysis and pipe support calculations were prepared for Class I piping.

Where required, design modifications were implemented.

NRC closed this item in Inspection Report 2006-009 (Reference 2).

References:

1. NRC letter to TVA, dated January 23, 1991, NUREG-1232, Volume 3, Supplement 2 -

Browns Ferry, Unit 2, Section 2.2.3.1 (Page 2-8)

2. NRC letter to TVA, dated March 5, 2007, Browns Ferry Nuclear Plant Unit 1 Recovery - NRC Integrated Inspection Report 05000259/2006009 April 13, 2007 E1-4

Bulletin 79-12, Short Period Scrams at BWR Facilities Commitment: TVA will complete Bulletin 79-12.

Discussion: In response to Bulletin 79-12, TVA committed to perform unit and cycle specific analyses of control rod withdrawal sequences in order to ensure that rod notch worths were acceptable (References 1 and 2). In Reference 3, TVA notified NRC that it was implementing the generic Banked Position Withdrawal Sequence and Reduced Notch Worth Procedure. The resulting withdrawal sequences ensure that the notch worths are sufficiently small so as to minimize the possibility of a fast period scram. Therefore, cycle specific analyses of control rod withdrawal sequences were no longer required.

Status: C-C The Banked Position Withdrawal Sequence and Reduced Notch Worth Procedures have been incorporated into plant procedures.

NRC closed this item in Inspection Report 2006-007 (Reference 4).

References:

1. TVA letter to NRC, dated July 30, 1979, Office of Inspection and Enforcement Bulletin 79 RII:JPO 50-259, -260, -296 - Browns Ferry Nuclear Plant Units 1, 2, and 3
2. TVA letter to NRC, dated August 19, 1981, Office of Inspection and Enforcement Bulletin 79 RII:JPO 50-259, -260, -296 - Browns Ferry Nuclear Plant
3. TVA letter to NRC, dated January 4, 1990, Office of Inspection and Enforcement Bulletin 79 Commitment Revisions Regarding Fast Period Scrams
4. NRC letter to TVA, dated August 10, 2006, Browns Ferry Nuclear Plant Unit 1 Recovery - NRC Integrated Inspection Report 05000259/2006007 April 13, 2007 E1-5

Bulletin 79-14, Seismic Analysis for As-Built Safety-Related Piping Systems Commitment: TVA will complete Bulletin 79-14.

Discussion: TVA initiated programs in 1979 to comply with Bulletins 79-02 and 79-14 regarding the adequacy of piping system supports and anchor bolts. BFNs programs involved the reanalysis of pipe stress problems using the as-built configuration and amplified response spectra for Seismic Class I structures and the evaluation of the acceptability of the associated pipe supports. The scope of the program included Unit 1 safety-related large bore (greater than 22 inches in diameter) piping and computer analyzed small bore piping that was not included in the Small Bore Piping Program.

Pipe stress analysis and pipe support evaluations were based on walkdown inspection data for the safety-related piping systems. The walkdown inspections were instituted to determine the actual field configuration of the Class I piping systems and supports. NRC approval of TVA's program for the resolution of Bulletins 79-02 and 79-14 is documented in Reference 1.

Status: C-C Piping stress analysis and pipe support calculations were prepared for Class I piping.

Where required, design modifications were implemented.

NRC closed this item in Inspection Report 2006-009 (Reference 2).

References:

1. NRC letter to TVA, dated January 23, 1991, NUREG-1232, Volume 3, Supplement 2 -

Browns Ferry, Unit 2, Section 2.2.3.1 (Page 2-8)

2. NRC letter to TVA, dated March 5, 2007, Browns Ferry Nuclear Plant Unit 1 Recovery - NRC Integrated Inspection Report 05000259/2006009 April 13, 2007 E1-6

Bulletin 80-06, Engineered Safety Feature (ESF) Reset Controls Commitment: TVA will complete Bulletin 80-06.

Discussion: In Reference 1, TVA stated that the need for modification to the Traversing Incore Probe (TIP) system was identified as a result of the reviews performed for Bulletin 80-06. In Reference 2, TVA committed to perform the modification to the TIP system prior to restart.

Status: C-C TVA modified TIP circuitry for ESF reset.

NRC closed this item in Inspection Report 2006-008 (Reference 3).

References:

1. TVA letter to NRC, dated December 4, 1981, in Regards to Bulletin 80-06
2. TVA letter to NRC, dated April 28, 1988, IE Bulletin No. 80 Engineered Safety Feature (ESF) Reset Control
3. NRC letter to TVA, dated November 9, 2006, Browns Ferry Nuclear Plant Unit 1 Recovery - NRC Integrated Inspection Report 05000259/2006008 April 13, 2007 E1-7

Bulletin 84-02, Failures of General Electric Type HFA Relays in Use in Class 1E Safety Systems Commitment: TVA will replace relay coil spools in HFA relays in the reactor protection system (RPS) and other safety systems.

Discussion: TVA responded to Bulletin 84-02 by Reference 1.

Status: Closed NRC closed this item in Inspection Report 2004-009 (Reference 2).

References:

1. TVA letter to NRC, dated July 10, 1984, Inspection and Enforcement Bulletin 84 Failures of General Electric Type HFA Relays in Use in Class 1E Safety Systems - Browns Ferry, Sequoyah, Watts Bar, and Bellefonte Nuclear Plants
2. NRC letter to TVA, dated February 11, 2005, Browns Ferry Nuclear Plant Unit 1 Recovery - NRC Integrated Inspection Report 05000259/2004009 April 13, 2007 E1-8

Bulletin 86-02, Static "O" Ring Differential Pressure Switches Commitment: TVA will complete Bulletin 86-02.

Discussion: TVA responded to Bulletin 86-02 by Reference 1.

Two Static "O" Ring (SOR) differential pressure switches were installed (or planned for installation) in the Residual Heat Removal (RHR) system minimum flow recirculation lines. TVA committed to:

1. Revise the RHR pump flow rate test to include steps to verify minimum flow switch operability;
2. Perform maintenance instructions semiannually until two consecutive tests were attained; and
3. Evaluate the SOR test report and adjust setpoints, as required.

Status: C-C TVA installed two Static "O" Ring differential pressure switches in the Unit 1 RHR system and the RHR Pump Surveillance Instructions were revised to include steps to verify proper switch operation.

TVA installed two Static "O" Ring differential pressure switches in the Unit 1 Core Spray system and the Core Spray Pump Surveillance Instructions were revised to include steps to verify proper switch operation.

The commitment to perform the maintenance instruction semiannually has been evaluated in accordance with the commitment management process and deleted. NRC was notified of the commitment deletion by Reference 2.

The SOR test report has been evaluated; the accuracy values used for these switches are bounded by the data used in the SOR test report.

NRC closed this item in Inspection Report 2005-06 (Reference 3).

References:

1. TVA letter to NRC, dated July 20, 1987, NRC Office of Inspection and Enforcement (IE)

Bulletin 86 Static "O" Ring (SOR)

Differential Pressure Switches April 13, 2007 E1-9

2. TVA letter to NRC, dated August 17, 1995, BFN Revision to Commitments to Perform Testing of Static-O-Ring Differential Pressure Switches and Voltage Verification Testing of Reactor Protective System Equipment
3. NRC letter to TVA, dated May 16, 2005, Browns Ferry Nuclear Plant Unit 1 Recovery - NRC Integrated Inspection Report 05000259/2005006 April 13, 2007 E1-10

Bulletin 88-03, Inadequate Latch Engagement in HFA Type Relays Manufactured by General Electric (GE) Company Commitment: TVA will complete Bulletin 88-03.

Discussion: TVA originally responded to Bulletin 88-03 in Reference 1. TVA stated the BFN inspections and the repair or replacement of the relays which fail the inspection criteria are scheduled to be completed before restart of each unit. In Reference 2, NRC closed Bulletin 88-03. However, TVA was still required to notify the NRC of inspection results for Unit 1.

Status: Closed NRC closed this item in Inspection Report 2004-009 (Reference 3).

References:

1. TVA letter to NRC, dated July 6, 1988, Nuclear Regulatory Commission (NRC)Bulletin 88-03, Inadequate Latch Engagement in HFA-Type Latching Relays Manufactured by General Electric (GE)

Company

2. NRC letter to TVA, dated August 2, 1990, Closure of NRC Bulletin 88-03 for the Browns Ferry Nuclear Plant (TAC Nos. 73852, 73853, and 73854)
3. NRC letter to TVA, dated February 11, 2005, Browns Ferry Nuclear Plant Unit 1 Recovery - NRC Integrated Inspection Report 05000259/2004009 April 13, 2007 E1-11

Bulletin 88-04, Potential Safety-Related Pump Loss Commitment: TVA will complete Bulletin 88-04.

Discussion: NRC Bulletin 88-04 requested licensees to investigate and correct, as applicable, two miniflow design concerns for safety-related system pumps. The first concern involved the potential for dead-heading one or more pumps. The second concern was whether or not the installed miniflow capacity was adequate.

TVA responded to the Bulletin (Reference 1),

endorsing the BWR Owners Group response and providing BFN specific information. NRC requested additional information in Reference 2, which was provided by TVA in Reference 3. Reference 4 documents NRR closure of this issue for Unit 1.

NRC addressed this issue for Unit 1 in Inspection Report 95-31 (Reference 5). TVA notified NRC that its actions were complete in Reference 6.

Status: C-C NRC closed this item in Inspection Report 2004-009 (Reference 7).

References:

1. Letter from TVA to NRC dated September 30, 1988, Browns Ferry (BFN), Watts Bar (WBN), and Bellefonte (BLN) Nuclear Plants - NRC Bulletin (NRCB) 88-04, Potential Safety-Related Pump Loss
2. Letter from NRC to TVA dated March 1, 1989, Response to NRC Bulletin 88 Browns Ferry Nuclear Plant, Units 1, 2, and 3
3. Letter from TVA to NRC dated April 05, 1989, Browns Ferry Nuclear Plant (BFN) Units 1 and 3 -

Additional Response to NRC Bulletin 88-04 (NRCB 88-04) - Potential Safety-Related Pump Loss

4. Letter from NRC to TVA, dated May 8, 1989, Response to NRC Bulletin 88 Browns Ferry Nuclear Plant, Units 1 and 3
5. NRC letter to TVA, dated June 28, 1995, NRC Inspection Report 95-31 [Section 7.b., page 18]

April 13, 2007 E1-12

6. TVA letter to NRC, dated May 7, 2004, Browns Ferry Nuclear Plant (BFN) Unit 1 - Completion of NRC Bulletin 88-04, Potential Safety-Related Pump Loss
7. NRC letter to TVA, dated February 11, 2005, Browns Ferry Nuclear Plant Unit 1 Recovery - NRC Integrated Inspection Report 05000259/2004009 April 13, 2007 E1-13

Bulletin 88-07, Power Oscillations in Boiling Water Reactors, and Supplement 1 Commitment: TVA will complete Bulletin 88-07.

Discussion: TVA responded to Bulletin 88-07 by Reference 1 and confirmed that the actions required by the Bulletin were implemented. TVA responded to Supplement 1 to Bulletin 88-07 by Reference 2 and confirmed its plans to implement the General Electric interim stability recommendations. The proposed Technical Specification changes to implement the reactor core thermal-hydraulic stability recommendations contained in Supplement 1 to Bulletin 88-07 were provided by Reference 3 and approved in Reference 4.

Status: C-C Refer to the topic entitled Generic Letter 94 Long-Term Solutions and Upgrade of Interim Operating Recommendations for Thermal-Hydraulic Instabilities in Boiling Water Reactors for additional actions TVA has taken to address this issue.

NRC closed this item in Inspection Report 2006-007 (Reference 5).

References:

1. TVA letter to NRC, dated November 4, 1988, NRC Bulletin 88-07: Power Oscillations in Boiling Water Reactors
2. TVA letter to NRC, dated March 6, 1989, NRC Bulletin 88-07, Supplement 1 - Power Oscillations in Boiling Water Reactors (BWRs)
3. TVA letter to NRC, dated January 14, 1992, TVA BFN Technical Specification (TS) No. 300 Reactor Core Thermal-Hydraulic Stability
4. NRC letter to TVA, dated May 31, 1994, Issuance of Technical Specification Amendments for the Browns Ferry Nuclear Plant Units 1 and 3 (TS 300)
5. NRC letter to TVA, dated August 10, 2006, Browns Ferry Nuclear Plant Unit 1 Recovery - NRC Integrated Inspection Report 05000259/2006007 April 13, 2007 E1-14

Bulletin 88-10, Nonconforming Molded-Case Circuit Breakers Commitment: TVA will complete Bulletin 88-10.

Discussion: TVA provided a revised response to Bulletin 88-10 in Reference 1. TVA stated that it had completed itsBulletin 88-10 effort for Units 1, 2 and 3.

TVA had removed the Class 1E Molded Case Circuit Breakers (MCCBs) without adequate traceability from installed service and the warehouse. NRC closed this Bulletin for Unit 1 in Reference 2.

Status: C-C For Unit 1, TVA has removed the Class 1E MCCBs which did not have adequate traceability from both installed service and the warehouse.

NRC closed this item in Inspection Report 2005-009 (Reference 3).

References:

1. TVA letter to NRC, dated November 29, 1990, Browns Ferry Nuclear Plant (BFN) - Revised Response and Notification of Implementation of NRC Bulletin 88-10 Nonconforming Molded Case Circuit Breakers (MCCBs)
2. NRC letter to TVA, dated March 10, 1992, NRC Inspection Report Nos. 50-259/92-03, 50-260/92-03, and 50-296/92-03)
3. NRC letter to TVA, dated February 13, 2006, Browns Ferry Nuclear Plant Unit 1 Recovery - NRC Integrated Inspection Report 05000259/2005009 April 13, 2007 E1-15

Bulletin 90-01, Loss of Fill Oil in Transmitters Manufactured by Rosemount Commitment: TVA will complete Bulletin 90-01.

Discussion: TVA originally responded to Bulletin 90-01 in Reference 1. TVA responded to Supplement 1 to Bulletin 90-01 in Reference 2. The commitments made in Reference 2 superseded the commitments made in Reference 1. In Reference 2, TVA stated that it would formally notify the NRC of the proposed resolution of the Rosemount transmitter issue for Unit 1 prior to Unit 1 startup. NRCs Safety Evaluation (Reference 3) applied to all three units but stated additional information would be required on Unit 1.

In Reference 4, TVA notified NRC of its plan to replace the BFN Unit 1 Rosemount transmitters that meet the criteria specified in NRC Bulletin 90-01, Supplement 1 with new or refurbished transmitters prior to Unit 1 restart. NRC found TVAs response acceptable in Reference 5.

Status: C-C TVA has replaced the BFN Unit 1 Rosemount transmitters that meet the criteria specified in NRC Bulletin 90-01, Supplement 1 with new or refurbished transmitters.

NRC closed this item in Inspection Report 2005-009 (Reference 6).

April 13, 2007 E1-16

References:

1. TVA letter to NRC, dated July 18, 1990, Response to NRC Bulletin No. 90-01: Loss of Fill-Oil in Transmitters Manufactured by Rosemount
2. TVA letter to NRC, dated March 5, 1993, Response to NRC Bulletin No. 90-01, Supplement 1 - Loss of Fill Oil in Transmitters Manufactured by Rosemount
3. NRC letter to TVA, dated April 4, 1995, NRC Bulletin 90-01, Supplement 1, Loss of Fill-Oil in Transmitters Manufactured by Rosemount -

Browns Ferry Nuclear Plant Units 1, 2, and 3 (TAC Nos. M85361, M85362, and M85363)

4. TVA letter to NRC, dated June 7, 2004, Browns Ferry Nuclear Plant (BFN) - Unit 1 - Response to NRC Bulletin no. 90-01, Supplement 1 - Loss of Fill Oil in Transmitters Manufactured by Rosemount
5. NRC letter to TVA, dated February 7, 2005, Browns Ferry Nuclear Plant, Unit 1 - Closeout of Bulletin 90-01, Supplement 1, Loss of Fill-Oil in Transmitters Manufactured by Rosemount (TAC No. MC3381)
6. NRC letter to TVA, dated February 13, 2006, Browns Ferry Nuclear Plant Unit 1 Recovery - NRC Integrated Inspection Report 05000259/2005009 April 13, 2007 E1-17

Bulletin 93-02, Debris Plugging of Emergency Core Cooling Suction Strainers, and Supplement 1 Commitment: TVA will complete Bulletin 93-02 and Supplement 1 prior to restart.

Discussion: TVA responded to Bulletin 93-02 in Reference 1 and committed to:

1. Evaluate Unit 1 for permanent fibrous material.
2. Inspect Unit 1 and remove temporary fibrous material.
3. Confirm completion of the above listed activities before startup.

In TVA's response to Supplement 1 of Bulletin 93-02 (Reference 2), TVA committed to augment the operator's required reading program, conduct classroom and/or simulator training, revise appendices in BFNs Emergency Operating Instructions (EOIs) to include caution statements and actions for monitoring net positive suction head, and change the applicable design control procedure to require evaluation of fibrous material being introduced into the drywell.

In Reference 3, NRC stated that TVA's response to Supplement 1 adequately addressed the actions TVA would take to assure continued Emergency Core Cooling System (ECCS) suction capability. TVA notified NRC of the completion of the commitments made in response to Supplement 1 of Bulletin 93-02 for all three units in Reference 4.

TVA updated its response to the Bulletin for Unit 1 in Reference 5.

Status: C-C TVA has evaluated the drywell for permanent fibrous material. The results were similar to Units 2 and 3. Limited amounts of fibrous material are permanently installed in several containment penetrations. Also, in accordance with the Units 2 and 3s precedent, TVA has revised its Unit 1 General Operating Instruction on Drywell Closeout to ensure temporary fibrous air filters or other temporary sources of fibrous material are removed.

April 13, 2007 E1-18

Inspection Report 2006-006 (Reference 6) stated However, final closure of this item will be deferred until NRR completes their review in this area and any SERs, if required, are issued.

In a letter dated July 26, 2006 (Reference 7), NRR issued an SER concluding BFN has satisfied this Bulletin.

NRC closed this item in Inspection Report 2006-008 (Reference 8).

References:

1. TVA letter to NRC, dated May 23, 1993, NRC Bulletin No. 93-02, Debris Plugging of Emergency Core Cooling Suction Strainers
2. TVA letter to NRC, dated April 18, 1994, NRC Bulletin 93-02, Supplement 1 - Debris Plugging of Emergency Core Cooling System (ECCS) Suction Strainers
3. NRC letter to TVA, dated July 19, 1994, Response to NRC Bulletin 93 Supplement 1, Debris Plugging of Emergency Core Cooling Suction Strainers
4. TVA letter to NRC, dated July 29, 1994, NRC Bulletin 93-02, Supplement 1 - Debris Plugging of Emergency Core Cooling System (ECCS) Suction Strainers - Commitment Completion
5. TVA letter to NRC, dated May 6, 2004, Browns Ferry Nuclear Plant (BFN) Unit 1 - Update to TVA Response to NRC Bulletin No. 93-02, Debris Plugging of Emergency Core Cooling Suction Strainers
6. NRC letter to TVA, dated May 15, 2006, Browns Ferry Nuclear Plant Unit 1 Recovery - NRC Integrated Inspection Report 05000259/2006006
7. NRC Letter To TVA, dated July 26, 2006, Browns Ferry Nuclear Plant, Unit 1 - Review Of Licensee Response To NRC Bulletin 93-02, Debris Plugging of Emergency Core Cooling Suction Strainers (TAC No. Mc3393)
8. NRC letter to TVA, dated November 9, 2006, Browns Ferry Nuclear Plant Unit 1 Recovery - NRC Integrated Inspection Report 05000259/2006008 April 13, 2007 E1-19

Bulletin 93-03, Resolution of Issues Related to Reactor Vessel Water Level Instrumentation in BWRs Commitment: TVA intends to complete a modification which will prevent the buildup of non-condensibles in water level reference legs by injecting CRD system charging water into the reference legs.

Discussion: TVA's response to Bulletin 93-03 was provided by Reference 1. TVA committed to perform modifications on Unit 1 prior to restart. NRC accepted TVAs response to the Bulletin in Reference 2. A detailed description of the modification installed on Unit 2 was provided in Reference 3.

Status: C-C TVA completed the described modification.

NRC closed this item in Inspection Report 2006-009 (Reference 4).

References:

1. TVA letter to NRC, dated July 30, 1993, Response to NRC Bulletin (NRCB) 93-03, Resolution of Issues Related to Reactor Vessel Water Level Instrumentation in Boiling Water Reactors
2. NRC letter to TVA, dated April 20, 1994, Browns Ferry Nuclear Plant Units 1, 2, and 3 - Response To NRC Bulletin 93-03, "Resolution of Issues Related to Reactor Vessel Water Level Instrumentation in BWRs," (TAC Nos. M86882, M86883, and M86884)
3. TVA letter to NRC, dated December 14, 1994, Hardware Modification Completion and Description in Response to Bulletin 93-03, Resolution of Issues Related to Reactor Vessel Water Level Instrumentation in Boiling Water Reactors
4. NRC letter to TVA, dated March 5, 2007, Browns Ferry Nuclear Plant Unit 1 Recovery - NRC Integrated Inspection Report 05000259/2006009 April 13, 2007 E1-20

Bulletin 95-02, Unexpected Clogging of a Residual Heat Removal (RHR) Pump Strainer While Operating in Suppression Pool Cooling Mode Commitment: Appropriate actions will be taken prior to Unit 1 restart.

Discussion: TVA's response to Bulletin 95-02 was provided in Reference 1. For Units 2 and 3, TVA committed to clean the suppression pool and perform confirmatory inspection and test prior to restart. TVA also committed to perform a visual inspection of the Emergency Core Cooling System pump suction strainers during each refueling outage and a program for suppression pool cleaning will be developed prior to restart. TVA stated that the programs established to ensure Emergency Core Cooling System pump operability on Units 2 and 3 would apply to Unit 1 when it was returned to service. NRC found TVAs response acceptable in Reference 2.

Status: C-C The Unit 1 suppression pool was drained, cleaned, inspected and recoated as necessary. Program to ensure suppression pool cleanliness and control of foreign material has been implemented.

NRC closed this item in Inspection Report 2006-006 (Reference 3).

References:

1. TVA letter to NRC, dated November 15, 1995, Browns Ferry Nuclear Plant (BFN) - NRC Bulletin 95-02, Unexpected Clogging of a Residual Heat Removal (RHR) Pump Strainer While Operating In Suppression Pool Cooling Mode
2. NRC letter to TVA, dated March 14, 1996, Browns Ferry Nuclear Plant Units 1, 2, and 3 - Response to Bulletin 95-02 (TAC Nos. M93876, M93877, and M93878)
3. NRC letter to TVA, dated May 15, 2006, Browns Ferry Nuclear Plant Unit 1 Recovery - NRC Integrated Inspection Report 05000259/2006006 April 13, 2007 E1-21

Bulletin 96-03, Potential Plugging of Emergency Core Cooling Suction Strainers By Debris In Boiling-Water Reactors Commitment: Appropriate modifications to addressBulletin 96-03 will be implemented on Unit 1 prior to its restart.

Discussion: TVA originally responded to the Bulletin in Reference 1 and committed to describing planned actions and schedules to be utilized to resolve the Bulletin within 90 days following the approval of the Utility Resolution Guidelines. TVA described its plans for resolution of the Bulletin in Reference 2 and committed to resolve the Bulletin prior to restart for Unit 1.

Status: C-C TVA has installed new, high capacity passive strainers on Unit 1, which are of the same design as on Units 2 and 3.

NRC closed this item in Inspection Report 2006-009 (Reference 3).

References:

1. TVA letter to NRC, dated November 4, 1996, Browns Ferry Nuclear Plant (BFN) - NRC Bulletin No. 96-03, Potential Plugging of Emergency Core Cooling Suction Strainers by Debris in Boiling-Water Reactors (TAC Nos. M96135, M96136, M96137)
2. TVA letter to NRC, dated July 25, 1997, Browns Ferry Nuclear Plant (BFN) - NRC Bulletin No.

96-03, Potential Plugging of Emergency Core Cooling Suction (ECCS) Strainers by Debris in Boiling Water Reactors (TAC Nos. M96135, M96136, M96137)

3. NRC letter to TVA, dated March 5, 2007, Browns Ferry Nuclear Plant Unit 1 Recovery - NRC Integrated Inspection Report 05000259/2006009 April 13, 2007 E1-22

Cable Ampacity Commitment: The cable ampacity issue will be resolved in accordance with the Unit 2 precedent.

Discussion: TVA developed a new electrical design standard to address ampacities for cables in conduits, cable trays, and duct banks, as well as derating factors for cable coatings, fire wraps, cable tray covers, and cable tray bottoms. Approval of this program is contained in NUREG-1232 (Reference 1).

Status: Complete TVA has resolved the cable ampacity issue.

References:

1. NRC letter to TVA, dated January 23, 1991, NUREG-1232, Volume 3, Supplement 2 -

Browns Ferry Unit 2 [Section 3.11.3, Page 3-9]

April 13, 2007 E1-23

Cable Installation Issue Number 1, Brand Rex Cable Issues Commitment: To resolve the Brand Rex cable issue, corrective actions will be implemented prior to the restart of Unit 1 in accordance with the Unit 2 precedent.

Discussion: The action plan to disposition concerns related to cable installation issues, including Brand Rex, was provided in Reference 1. The Safety Evaluation on this program was provided by Reference 2. In summary, the Staff found implementing the corrective actions for the Brand Rex cable issue in accordance with the Unit 2 precedent to be acceptable pending the results of additional qualification testing being performed by TVA.

TVA has identified contract number 80K6-825419 as the source of the Brand Rex cables issue for BFN.

Additional testing demonstrated the ability of the cables to perform their intended safety function for a qualified life of 40 years. TVA has removed all non-installed Brand Rex cable furnished on contract 80K6-825419. Administrative controls are in place to prevent future applications of this cable type and manufacturer from being installed at BFN.

Status: Open

References:

1. TVA letter to NRC, dated May 10, 1991, Action Plan to Disposition Concerns Related to Units 1 and 3 Cable Installation Issues Including Cable Separations
2. NRC letter to TVA, dated April 8, 1992, Safety Evaluation of TVA Plans to Resolve Electrical Cable Installation and Separation Issues April 13, 2007 E1-24

Cable Installation Issue Number 2, Cable Separations Issues Commitment: TVA committed to the following:

1. Prior to fuel load of Unit 1, TVA will implement all corrective actions in accordance with the Unit 2 criteria and implementation precedent for the following cable separations issues:
  • V4 and V5 cables which originate from safety-related power supplies,
  • Nondivisional V4 and V5 cables which originate from nonsafety-related power supplies,
  • V3 cables which originate from safety-related and from nonsafety-related power supplies,
  • Nondivisional V1 and V2 cables which originate from both safety-related and nonsafety-related power supplies,
  • Divisional and nondivisional cables designated with an IE and IES suffix, and
  • Divisional V1 and V2 cables.
2. As documented in References 1 through 6, Unit 2 validated the use of the cable schedule drawings (45C800 series) in determining the installed configuration of cables in the plant.

Unit 1 cables were included in the population of cables that were used in the validation process during the Unit 2 restart effort. As documented in Reference 7, the Unit 1 cables have always been routed manually. The Unit 1 circuit schedule was not an electronic database. Therefore, TVA will use the 45C800 series drawings as the document of record in the determination of acceptable routing for Unit 1.

April 13, 2007 E1-25

3. The Unit 1 Master Equipment List (MEL) will establish the list of equipment and device IDs for safety-related and quality-related systems.

For nondivisional V1, V2, V3, V4 and V5 cables identified in the MEL as safety-related for Unit 1, cable separation issues will be resolved by analyzing design drawings to identify cables required to support the safety-related and quality-related devices.

The resulting list will be compared against the 45C800 drawings to determine if cables are correctly identified as divisional. If it is determined that a change in divisional status is required, the respective cables will be evaluated against separations criteria.

Corrective actions will be completed prior to fuel load.

4. For cables contained in divisional and nondivisional cable trays that physically connect on Unit 1, corrective actions will be implemented prior to Unit 1 fuel load.

Discussion: TVA had identified instances where the electrical separation requirements had not been met at BFN.

The Units 1 and 3 specific action plan to disposition concerns related to cable installation issues, including cable separation, was provided in Reference 1. The Safety Evaluation on this program was provided by Reference 2. Additional information was requested regarding the corrective actions to be implemented for discrepancies associated with the two cables contained in divisional and nondivisional cable trays that physically connect. This additional information was provided by TVA in Reference 3. The NRC Staff accepted this information in Reference 4.

Status: Complete Evaluations have been completed and noted discrepancies have been completed.

April 13, 2007 E1-26

References:

1. TVA letter to NRC, dated January 6, 1989, Browns Ferry Nuclear Plant (BFN) - Electrical Cable Separation
2. TVA letter to NRC, dated June 9, 1989, Browns Ferry Nuclear Plant (BFN) - Electrical Cable Separation
3. TVA letter to NRC, dated October 23, 1989, Browns Ferry Nuclear Plant (BFN) - Electrical Cable Separation
4. TVA letter to NRC, dated December 14, 1989, Browns Ferry Nuclear Plant (BFN) - Electrical Cable Separation
5. NRC letter to TVA, dated February 23, 1990, NRC Inspection Report No. 50-260/89-59
6. NRC letter to TVA, dated August 10, 1990, NRC Inspection Report No. 50-260/90-13
7. TVA letter to NRC, dated December 29, 1992, Response to Request for Additional Information on Electrical Cables in Divisional and Nondivisional Trays Which Are Physically Connected April 13, 2007 E1-27

Cable Installation Issue Number 3, Low Voltage Vertical Cable Supports Commitment: TVA will resolve the low voltage vertical cable supports issue in accordance with the Unit 2 precedent.

Discussion: The action plan to disposition concerns related to cable installation issues, including vertical cable supports, was provided in Reference 1. The Safety Evaluation on this program was provided by Reference 2. In summary, since no Unit 2 cables with acceptable sidewall bearing pressure failed Hi-Pot testing, the walkdown and evaluation of Unit 1 safety-related low voltage power, control and instrumentation cable is adequate to satisfactorily resolve the vertical support issue.

Status: Open

References:

1. TVA letter to NRC, dated May 10, 1991, Action Plan to Disposition Concerns Related to Units 1 and 3 Cable Installation Issues Including Cable Separations
2. NRC letter to TVA, dated April 8, 1992, Safety Evaluation of TVA Plans to Resolve Electrical Cable Installation and Separation Issues April 13, 2007 E1-28

Cable Installation Issue Number 4, Medium Voltage Cable Bend Radius Commitment: Safety-related medium voltage cables will be identified, walked down and evaluated against the bend radius criteria used for Unit 2 (General Construction Specification G-38). The following corrective actions will be completed:

A. Group 1 cables with bend radius of less than 6 times the cable outside diameter (OD) will be replaced.

B. Group 2 cables with bend radius from 6 times the cable OD to less than 8 times the cable OD will be tested prior to restart and during subsequent outages to facilitate a trend analysis.

C. Group 3 cables, with bend radius 8 times or greater than the cable OD will be allowed to remain in service and be subjected to only normal maintenance testing.

Discussion: The action plan to disposition concerns related to cable installation issues, including medium voltage cable bend radius, was provided in Reference 1.

The Safety Evaluation of this program was provided by Reference 2. In summary, since safety-related medium voltage cables are to be identified, walked down and evaluated against the bend radius acceptance criteria contained in Construction Specification G-38 and dispositioned in accordance with the same criteria used for Unit 2, the proposed corrective actions are adequate.

In Reference 3, TVA proposed a new program and corrective actions for medium cable bend radius issues. Results of reinspections were presented to NRC and Hi-Pot testing was replaced with Load Cycle and Corona Testing. Additional information regarding the revised program was requested in Reference 4, which was provided by TVA in Reference 5. NRC issuance of a Safety Evaluation for this program and a request for additional information was contained in Reference 6. TVA replied in Reference 7, and the Supplemental Safety Evaluation Report was provided in Reference 8.

Status: Open April 13, 2007 E1-29

References:

1. TVA letter to NRC, dated May 10, 1991, Action Plan to Disposition Concerns Related to Units 1 and 3 Cable Installation Issues Including Cable Separations
2. NRC letter to TVA, dated April 8, 1992, Safety Evaluation of TVA Plans to Resolve Electrical Cable Installation and Separation Issues
3. TVA letter to NRC, dated March 17, 1993, Medium Voltage Cable Bend Radius Issues
4. NRC letter to TVA, dated August 23, 1993, Request for Additional Information Regarding Medium Voltage Cable Bend Radius
5. TVA letter to NRC, dated January 10, 1994, Response to Request for Additional Information Regarding Medium Voltage Cable Bend Radius
6. NRC letter to TVA, dated July 1, 1994, Safety Evaluation and Request for Additional Information Regarding Medium Voltage Cable Bend Radius Issues
7. TVA letter to NRC, dated September 15, 1994, Reply to NRC Request for Additional Information (RAI) Regarding Medium Voltage Cable Bend Radius Issues
8. NRC letter to TVA, dated January 9, 1995, Supplemental Safety Evaluation for Medium Voltage Cable Bend Radius April 13, 2007 E1-30

Cable Installation Issue Number 5, Missing Conduit Bushings Commitment: Type PN cables in 10 CFR 50.49 circuits will be replaced under the Environmental Qualification program.

Discussion: The action plan to disposition concerns related to cable installation issues, including missing conduit bushings, was provided in Reference 1. The Safety Evaluation on this program was provided by Reference 2. In summary, the only cables found damaged on Unit 2 as a result of pulling the cables over a conduit end with a missing bushing were the Type PN. Replacing this type of cable in Unit 1 10 CFR 50.49 circuits was considered adequate to resolve this issue.

Status: Open

References:

1. TVA letter to NRC, dated May 10, 1991, Action Plan to Disposition Concerns Related to Units 1 and 3 Cable Installation Issues Including Cable Separations
2. NRC letter to TVA, dated April 8, 1992, Safety Evaluation of TVA Plans to Resolve Electrical Cable Installation and Separation Issues April 13, 2007 E1-31

Cable Installation Issue Number 6, Sidewall Pressure, Cable Pullbys, Cable Jamming, Pulling Around 90 Degree Condulets and Thru Mid-Run Flex Conduit Issues Commitment: The cables identified in the Master Equipment List (MEL) as safety-related cables for Unit 1, which are not replaced by other programs, will be reviewed to determine the configuration of their associated raceway. If the design of the raceway meets the criteria for sidewall pressure, jamming, pullbys, mid-run flex or pulling around 90 degree condulet concerns, a walkdown will be performed to confirm the installed configuration. Confirmatory walkdowns will be completed prior to Unit 1 restart.

Discussion: The action plan to disposition concerns related to cable installation issues, including sidewall pressure, cable pullbys, cable jamming, pulling around 90 degree condulets and thru mid-run flex conduit issues, was provided in Reference 1.

Information regarding cable walkdowns and cable routing system database validation was provided in Reference 2.

A Safety Evaluation on cable installation and separation and request for additional information on divisional/nondivisional separation discrepancies was provided in Reference 3. In summary, cable damage was not identified on Unit 2 during the resolution of the sidewall pressure, cable pullbys, cable jamming and pulling around 90-degree condulets and through mid-run flex conduits issues.

Status: Open

References:

1. TVA letter to NRC, dated May 10, 1991, Action Plan to Disposition Concerns Related to Units 1 and 3 Cable Installation Issues Including Cable Separations
2. TVA letter to NRC, dated March 6, 1992, Additional Information on TVA's Action Plan for Units 1 and 3 Cable Installation Issues Including Cable Separations
3. NRC letter to TVA, dated April 8, 1992, Safety Evaluation of TVA Plans to Resolve Electrical Cable Installation and Separation Issues April 13, 2007 E1-32

Cable Installation Issue Number 7, Use of Condulets as Pull Points Commitment: The 600V safety-related cables that are susceptible to damage from the use of condulets as pull points will be resolved in accordance with the Unit 2 precedent.

Discussion: The action plan to disposition concerns related to cable installation issues, including the use of condulets as pull points, was provided in Reference 1. The Safety Evaluation on this program was provided by Reference 2. In summary, TVA's evaluation of this issue for Unit 2 determined that the type of conduit configurations susceptible to this problem was limited to several cases of large 600 volt cables in three inch conduits. Therefore, TVA will review the Unit 1 600 volts cables installed in conduit in accordance with the Unit 2 program guidelines / The required corrective actions will be completed prior to fuel load.

Status: Open

References:

1. TVA letter to NRC, dated May 10, 1991, Action Plan to Disposition Concerns Related to Units 1 and 3 Cable Installation Issues Including Cable Separations
2. NRC letter to TVA, dated April 8, 1992, Safety Evaluation of TVA Plans to Resolve Electrical Cable Installation and Separation Issues April 13, 2007 E1-33

Cable Installation Issue Number 8, Medium Voltage Vertical Cable Supports Commitment: The medium voltage vertical cable supports issue will be resolved by evaluating cables not meeting the vertical cable support criteria for static sidewall bearing pressure (SSBP). Cables with unacceptable SSBP will be Hi-Pot tested. Cables passing the Hi-Pot test will be supported in accordance with G-38. Cables failing the Hi-Pot test will be replaced.

Discussion: The action plan to disposition concerns related to cable installation issues, including medium voltage vertical cable supports, was provided in Reference 1. The Safety Evaluation on this program was provided by Reference 2. In summary, since no Unit 2 cables with acceptable sidewall bearing pressure failed Hi-Pot testing, the walkdowns and evaluation of Class 1E medium voltage cables is adequate to satisfactorily resolve the vertical support issue.

Status: Open

References:

1. TVA letter to NRC, dated May 10, 1991, Action Plan to Disposition Concerns Related to Units 1 and 3 Cable Installation Issues Including Cable Separations
2. NRC letter to TVA, dated April 8, 1992, Safety Evaluation of TVA Plans to Resolve Electrical Cable Installation and Separation Issues April 13, 2007 E1-34

Cable Splices Commitment: TVA will identify Class IE cable splices located in harsh environment and ensure they are qualified for their intended service during a design basis accident (DBA).

Discussion: TVAs program to resolve the splice issue was submitted in Reference 1. TVA performed a field walkdown of safety-related conduits to identify and document Class 1E cable splices which are required to be environmentally qualified and to verify the installed splice configuration. The field data was evaluated against construction specification requirements to determine which splices require rework. Actions were taken to either rework the splice or rework both the splice and raceway system to accommodate a qualified splice.

Status: Complete

References:

1. TVA letter to NRC, dated April 28, 1988, Browns Ferry Nuclear Plant (BFN) - Electrical Issues (NRC TAC No. 62260)

April 13, 2007 E1-35

Cable Tray Supports Commitment: TVA intends to utilize the Seismic Qualification Utility Group (SQUG) Generic Implementation Procedure (GIP) for seismic qualification of cable trays.

Discussion: The original action plan to disposition concerns related to Unit 1 cable tray supports was provided in Reference 1. However, due to the issuance of Supplement 1 to Generic Letter 87-02, Verification of Seismic Adequacy of Mechanical and Electrical Equipment in Operating Reactors, Unresolved Safety Issue (USI) A-46, BFN submitted a revised program in order to take advantage of the NRC approved process for resolving USI A-46 (Reference 2). NRC accepted the schedule for implementing the revised program for Unit 1 in Reference 3 and requested additional information regarding the revised methodology and criteria. This information was provided in Reference 4 and accepted by NRC in Reference 5.

Status: C-C The Unit 1 cable tray supports have been evaluated utilizing the GIP in accordance with USI A-46. A summary report was provided to NRC in Reference 6.

Necessary modifications and repairs have been completed.

NRC closed this item in document dated March 9, 2007 (Reference 7).

References:

1. TVA letter to NRC, dated March 27, 1991, Action Plan to Disposition Concerns Related to Units 1 and 3 Cable Tray Supports
2. TVA letter to NRC, dated September 21, 1992, Supplement 1 to Generic Letter 87-02, Verification of Seismic Adequacy of Mechanical and Electrical Equipment in Operating Reactors, Unresolved Safety Issue (USI) A-46 and Supplement 4 to Generic Letter 88-20, Individual Plant Examination of External Events (IPEEE) for Severe Accident Vulnerabilities
3. NRC letter to TVA, dated November 19, 1992, Generic Letter 87-02, Supplement 1 Response -

Browns Ferry Nuclear Plant April 13, 2007 E1-36

4. TVA letter to NRC, dated January 19, 1993, Generic Letter (GL) 87-02, Supplement 1, 120-Day Response, Request for Additional Information
5. NRC letter to TVA, dated March 19, 1993, Generic Letter 87-02, Supplement 1 Response - Browns Ferry Nuclear Plant
6. TVA letter to NRC, dated October 7, 2004, Browns Ferry Nuclear Plant (BFN) Unit 1 - Response to NRC Generic Letter (GL) 87-02, Supplement 1 that Transmits Supplemental Safety Evaluation Report No. 2 (SSER No. 2) on SQUG Generic Implementation Procedure, Revision 2, as corrected on February 14, 1992 (GIP-2)
7. NRC Meeting Summary dated March 9, 2007, Meeting Summary - Internal Meeting of the Browns Ferry Unit 1 Restart Panel - Docket No.

50-259 April 13, 2007 E1-37

Component and Piece Part Qualification Commitment: TVA will implement a component and piece part qualification program.

Discussion: In Reference 1, TVA provided a change in methodology in performing the component and piece part qualification for safety-related components in 10 CFR 50.49 applications. TVA proposed to use statistical sampling techniques to achieve a 95/95 confidence level of qualification adequacy as opposed to the 100% verification performed for Unit 2. Additional information was requested by the NRC Staff in Reference 2, which was provided by TVA in Reference 3. In Reference 4, NRC responded that this issue would be addressed by inspection rather than a revision to the Safety Evaluation.

Since this correspondence, TVA decided to perform a 100% verification as performed on Unit 2.

Status: Complete The Unit 1 component and piece part qualification program for safety-related components in 10 CFR 50.49 applications has been implemented.

References:

1. TVA letter to NRC, dated June 12, 1992, Request for Revision to Safety Evaluation Issued by NRC on January 10, 1990, Related to Component and Piece Part Qualification Plan
2. NRC letter to TVA, dated October 29, 1992, Request for Additional Information Regarding Browns Ferry Nuclear Plant Units 1 and 3 Component and Piece Parts Qualification Program
3. TVA letter to NRC, dated December 17, 1992, Request for Additional Information (RAI)

Regarding BFN Units 1 and 3 Component and Piece Parts Qualification Plan

4. NRC letter to TVA, dated December 7, 1993, Browns Ferry Nuclear Plant Units 1 and 3 Component and Piece Parts Qualification Program April 13, 2007 E1-38

Conduit Supports Commitment: TVA intends to utilize the Seismic Qualification Utility Group (SQUG) Generic Implementation Procedure (GIP) for seismic qualification of conduit supports.

Discussion: The original action plan to disposition concerns related to Unit 1 conduits and conduit supports was provided in References 1 through 3 and approved in Reference 4. However, due to the issuance of Supplement 1 to Generic Letter 87-02, Verification of Seismic Adequacy of Mechanical and Electrical Equipment in Operating Reactors, Unresolved Safety Issue (USI) A-46, BFN submitted a revised program in order to take advantage of the NRC approved process for resolving USI A-46 (Reference 5). NRC requested additional information regarding the schedule for implementing the revised program in Reference 6.

In Reference 7, TVA committed to implement the long-term qualification of conduits and conduit supports prior to Unit 1 restart. In Reference 8, NRC determined that it was acceptable for TVA to complete the portion of its USI A-46 program that pertain to conduits and conduit supports, prior to Unit 1 restart in lieu of its prior restart commitments.

Status: C-C The Unit 1 conduit supports have been evaluated utilizing the GIP in accordance with USI A-46.

A summary report was provided to NRC in Reference 9. Necessary modifications and repairs have been completed.

NRC closed this item in document dated March 9, 2007 (Reference 10).

References:

1. TVA letter to NRC, dated May 6, 1991, Program for Resolving Conduit and Conduit Supports Issue Prior to the Restart of Units 1 and 3
2. TVA letter to NRC, dated December 12, 1991, Small Bore Piping Program, Tubing, and Conduit Support Plans for Units 1 and 3 - Additional Information April 13, 2007 E1-39
3. TVA letter to NRC, dated January 29, 1992, Action Plan to Disposition Concerns Related to Units 1 and 3 Conduit and Conduit Support -

Additional Information

4. NRC letter to TVA, dated March 20, 1992, Safety Evaluation of Action Plan to Resolve Conduit and Conduit Supports Issues for the Browns Ferry Nuclear Plant Units 1 and 3
5. TVA letter to NRC, dated September 21, 1992, Supplement 1 to Generic Letter 87-02, Verification of Seismic Adequacy of Mechanical and Electrical Equipment in Operating Reactors, Unresolved Safety Issue (USI) A-46 and Supplement 4 to Generic Letter 88-20, Individual Plant Examination of External Events (IPEEE) for Severe Accident Vulnerabilities
6. NRC letter to TVA, dated November 19, 1992, Generic Letter 87-02, Supplement 1 Response -

Browns Ferry Nuclear Plant

7. TVA letter to NRC, dated January 19, 1993, Generic Letter (GL) 87-02, Supplement 1, 120-Day Response, Request for Additional Information
8. NRC letter to TVA, dated March 19, 1993, Generic Letter 87-02, Supplement 1 Response - Browns Ferry Nuclear Plant
9. TVA letter to NRC, dated October 7, 2004, Browns Ferry Nuclear Plant (BFN) Unit 1 - Response to NRC Generic Letter (GL) 87-02, Supplement 1 that Transmits Supplemental Safety Evaluation Report No. 2 (SSER No. 2) on SQUG Generic Implementation Procedure, Revision 2, as corrected on February 14, 1992 (GIP-2)
10. NRC Meeting Summary dated March 9, 2007, Meeting Summary - Internal Meeting of the Browns Ferry Unit 1 Restart Panel - Docket No.

50-259 April 13, 2007 E1-40

Configuration Management/Design Baseline Commitment: The Unit 1 Design Baseline Verification Program (DBVP) will consolidate the two-phase (pre- and post-restart) approach performed on Unit 2.

Discussion: The objective of the DBVP was to re-establish the design basis and evaluate the plant configuration to ensure that it satisfies the design basis. The DBVP, including a discussion of lessons learned from the Unit 2 precedent, was provided in Reference 1. In Reference 2, NRC determined that this commitment was more comprehensive than that accepted by the staff for Unit 2, and was therefore acceptable.

Status: C-C Unit 1 satisfies its design basis, safety related structures, systems, and components are supported by engineering analysis and documentation, and the plant configuration is in conformance with TVAs commitments.

NRC closed this item in document dated March 9, 2007 (Reference 3).

References:

1. TVA letter to NRC, dated June 13, 1991, Design Baseline Verification Program (DBVP)
2. NRC letter to TVA, dated November 21, 1991, Assessment of Browns Ferry Nuclear Plant, Units 1 and 3 Design Baseline Verification Program
3. NRC Meeting Summary dated March 9, 2007, Meeting Summary - Internal Meeting of the Browns Ferry Unit 1 Restart Panel - Docket No.

50-259 April 13, 2007 E1-41

Containment Coatings Commitment: The containment coating program will be implemented in accordance with the Unit 2 precedent.

Discussion: The containment coatings program was described in the Nuclear Performance Plan (Reference 1). TVA performed walkdown inspections of unqualified coating on components installed inside primary containment on Unit 2 to baseline the uncontrolled coating log. An analysis was performed to determine the maximum allowable quantity of coating debris which could be transported to the suction strainers without affecting the ability of the ECCS pumps to perform their post-Loss of Coolant Accident (LOCA) function. Corrective actions were taken to ensure that the amount of unqualified coating is maintained below the maximum allowable quantity. NRC approval of the program is documented in Reference 2.

Status: Complete The containment coatings program was completed, and the Uncontrolled Coatings Log was issued.

References:

1. TVA letter to NRC, dated October 24, 1988, Browns Ferry Nuclear Plant (BFN) - Nuclear Performance Plan, Revision 2
2. NRC letter to TVA, dated January 23, 1991, NUREG-1232, Volume 3, Supplement 2 - Browns Ferry, Unit 2, Section 3.7 (Page 3-7)

April 13, 2007 E1-42

Control Rod Drive (CRD) Insert and Withdrawal Piping Commitment: The seismic qualification of the CRD insert and withdrawal piping will be implemented in accordance with the Unit 2 precedent.

Discussion: TVA's program for the seismic qualification of the 185 CRD insert and withdrawal lines on Unit 2 was provided in Reference 1 and approved by NRC in Reference 2.

Status: C-C Based on reanalysis, pipe supports for CRD insert and withdrawal piping were replaced with new support frames.

NRC closed this item in document dated March 9, 2007 (Reference 3).

References:

1. TVA letter to NRC, dated December 11, 1989, Revised Program Plan - Seismic Qualification of the Control Rod Drive Hydraulic (CRDH) Piping System
2. NRC letter to TVA, dated January 23, 1991, NUREG-1232, Volume 3, Supplement 2 -

Browns Ferry, Unit 2, Section 2.2.3.2 (Page 2-9)

3. NRC Meeting Summary dated March 9, 2007, Meeting Summary - Internal Meeting of the Browns Ferry Unit 1 Restart Panel - Docket No.

50-259 April 13, 2007 E1-43

Design Calculation Review Issue: Complete a design calculation review.

Discussion: The objective of the design calculation review was to:

a. Identify calculations considered to be essential;
b. Ensure that essential calculations support the plant licensing commitments and design basis requirements;
c. Ensure that essential calculations are technically adequate and consistent with the plant configuration; and
d. Ensure that essential calculations supporting the Design Baseline and Verification Program (DBVP) are consistent with the plant functional configuration.

Status: C-C The design calculation review was incorporated into the Configuration Management / Design Baseline Verification Program in Reference 1.

NRC closed this item in document dated March 9, 2007 (Reference 2).

References:

1. TVA letter to NRC, dated June 13, 1991, Design Baseline Verification Program (DBVP)
2. NRC Meeting Summary dated March 9, 2007, Meeting Summary - Internal Meeting of the Browns Ferry Unit 1 Restart Panel - Docket No.

50-259 April 13, 2007 E1-44

Environmental Qualification Commitment: TVA will complete the qualification of Class IE safety-related equipment.

Discussion: The qualification of Class IE safety-related equipment will be accomplished when BFN certifies compliance with 10 CFR 50.49, Environmental qualification of electric equipment important to safety for nuclear power plants.

Status: Open

References:

None April 13, 2007 E1-45

Fire Protection / 10 CFR 50, Appendix R Commitment: TVA will comply with License Condition 2.C(13).

Discussion: License Condition 2.C(13) states:

Browns Ferry Nuclear Plant shall implement and maintain in effect all provisions of the approved Fire Protection Program as described in the Final Safety Analysis Report for BFN as approved in the SEs dated December 8, 1988, March 6, 1991, March 31, 1993, November 2, 1995 and Supplement dated November 3, 1989 subject to the following provision:

The licensee may make changes to the approved fire protection program without prior approval of the Commission only if those changes would not adversely affect the ability to achieve and maintain safe shutdown in the event of a fire.

NRC issued its Safety Evaluation Report (SER) for BFNs Safe Shutdown Analysis in Reference 1 and approved the associated License Amendment in Reference 2. The SER for the BFN Fire Protection Plan and Fire Hazards Analysis was provided in Reference 3. The NRC staff issued a License amendment for the 10 CFR 50, Appendix R Post-fire Safe Shutdown Program in Reference 4 and issued a supplemental Safety Evaluation in Reference 5.

As requested by the NRC in a letter to TVA dated September 21, 2006 (Reference 6), TVA will notify the NRC of each of the following items:

1. TVA, in its letter of April 24, 2006 (Reference 7), committed to identify the Appendix R, Paragraph III.G.2, noncompliances involving operator manual actions, to place them into TVAs corrective action program, and to implement compensatory measures. Therefore, TVA should complete the commitments made in its April 24, 2006, letter, as well as any other restart related commitments made previously to the NRC regarding post-fire operator manual actions.

April 13, 2007 E1-46

2. Safe Shutdown Instructions used to direct those actions needed to bring the unit to safe shutdown in the event of a fire will be completed by January 1, 2007.
3. Concerning the Unit 1 safe-shutdown analysis design assumptions.

Status: Open

References:

1. NRC letter to TVA, dated December 8, 1988, Units 1, 2 and 3 - Appendix R Safe Shutdown System Analysis (TAC 60627, 60628, 60629)
2. NRC letter to TVA, dated March 6, 1991, Issuance of Amendment (TAC No. 72965) (TS 268)
3. NRC letter to TVA, dated March 31, 1993, Fire Protection Program - Browns Ferry Nuclear Plant Units 1, 2 and 3 (TAC Nos. M82687, M82688 and M82689)
4. NRC letter to TVA, dated November 2, 1995, Safety Evaluation of Post-Fire Safe Shutdown Capability and Issuance of Technical Specification Amendments for the Browns Ferry Nuclear Plant Units 1, 2, and 3 (TAC Nos.

M85254, N87900, M87901, and M87902) (TS 337)

5. NRC letter to TVA, dated November 3, 1989, Supplemental Safety Evaluation on Post-Fire Safe Shutdown Systems and Final Review of the National Fire Protection Association Code Deviations - Browns Ferry Nuclear Plant, Unit 2 (TAC Nos. 72908 and 00459)
6. NRC letter to TVA, dated September 21, 2006, Browns Ferry Nuclear Plant, Unit 1 - Status of Fire Protection Program (TAC No. MC8826)
7. TVA letter to NRC dated April 24, 2006, Browns Ferry Nuclear Plant (BFN) - Units 1, 2 and 3 -

Fire Protection Program - Post-Fire Operator Manual Actions April 13, 2007 E1-47

Flexible Conduits Commitment: Actions necessary to disposition flexible conduit concerns for the 10 CFR 50.49 equipment will be completed prior to restart. Flexible conduits attached to safety-related electrical equipment not covered by 10 CFR 50.49 and within the scope of USI A-46 will be evaluated for seismic adequacy using BFNs A-46 program.

Discussion: The program and schedule for the resolution of flexible conduit issues for Unit 1 has been provided to the NRC as part of the resolution of Generic Letter 87-02. In Reference 1, TVA provided a schedule for flexible conduits associated with the resolution of USI A-46. NRC requested additional information regarding the schedule in Reference 2. In Reference 3, TVA provided the schedule for completing flexible conduit concerns in two phases. Flexible conduits attached to electrical equipment covered by 10 CFR 50.49 would be resolved prior to restart of Unit 1. Seismic qualification of flexible conduit other than those connected to electrical equipment covered by 10 CFR 50.49 (i.e., important to safety, but in a mild environment) and within the scope of USI A-46 would be included as part of the resolution of USI A-46.

In Reference 4, NRC found this program acceptable; however, additional information was requested regarding two separate issues regarding flexible conduit. TVA provided the requested information in Reference 5. Additional information was provided by TVA in Reference 6. NRC subsequently provided a supplemental safety evaluation in Reference 7.

Status: Complete Safety related flexible conduits were evaluated.

Breakages (conduit failures) from this evaluation were resolved.

References:

1. TVA letter to NRC, dated September 21, 1992, Supplement 1 to Generic Letter 87-02, Verification of Seismic Adequacy of Mechanical and Electrical Equipment in Operating Reactors, Unresolved Safety Issue (USI) A-46 and Supplement 4 to Generic Letter 88-20, Individual Plant Examination of External Events (IPEEE) for Severe Accident Vulnerabilities.

April 13, 2007 E1-48

2. NRC letter to TVA, dated November 19, 1992, Generic Letter 87-02, Supplement 1 Response -

Browns Ferry Nuclear Plant

3. TVA letter to NRC, dated January 19, 1993, Generic Letter (GL) 87-02, Supplement 1, 120-Day Response, Request for Additional Information
4. NRC letter to TVA, dated March 19, 1993, Generic Letter 87-02, Supplement 1 Response - Browns Ferry Nuclear Plant
5. TVA letter to NRC, dated October 15, 1993, Generic Letter (GL) 87-02, Supplement 1, Verification of Seismic Adequacy of Mechanical and Electrical Equipment in Operating Reactors, Unresolved Safety Issue (USI) A Response to Request for Additional Information Regarding the Evaluation of the Seismic Adequacy of Flexible Conduit
6. TVA letter to NRC, dated September 28, 1995, Browns Ferry Nuclear Plant (BFN)- Units 1, 2, and 3 - Seismic Adequacy of Flexible Conduits
7. NRC letter to TVA, dated October 3, 1995, Supplemental Safety Evaluation of Flexible Conduit Seismic Design and Installation Criteria April 13, 2007 E1-49

Fuses Commitment: The fuse issue will be resolved in accordance with the Unit 2 precedent.

Discussion: NRC approval of TVA's fuse program is documented in NUREG-1232 (Reference 1). The completion plan for the fuse program was provided by Reference 2. TVA has removed the reference to amperage from drawings and replaced them with the appropriate unique identifier for Class 1E fuses. TVA has installed permanent fuse labeling.

Status: Complete

References:

1. NRC letter to TVA, dated January 23, 1991, NUREG-1232, Volume 3, Supplement 2 - Browns Ferry, Unit 2, Section 3.11.2 (Page 3-9)
2. TVA letter to NRC, dated January 29, 1992, Completion Plan for the Fuse Program April 13, 2007 E1-50

Generic Letter 82-33, Instrumentation to Follow the Course of an Accident - Regulatory Guide 1.97 Commitment: TVA will complete Generic Letter 82-33.

Discussion: Supplement 1 to NUREG-0737, which included the request to review Regulatory Guide 1.97, was sent to TVA in Generic Letter 82-33 (Reference 1). TVA originally responded to Generic Letter 82-33 in Reference 2.

TVA was ordered to submit a report to NRC describing how the requirements of Supplement 1 to NUREG-0737 have been or will be met and an implementation schedule (Reference 3).

NRC requested additional information and/or justification in Reference 4. TVA responded to this request in Reference 5. TVA provided updated information regarding Reactor Coolant System pressure indication in Reference 6. A Safety Evaluation Report (SER) was issued by NRC in Reference 7. As part of this SER, TVA was directed to qualify the instrumentation that measures seven variables in accordance with 10 CFR 50.49. TVA either provided additional justification or committed to upgrade the instrumentation discussed in the SER in Reference 8. A revised SER was issued as part of the NRC's February 8, 1990 letter (Reference 9). This revised SER also directed TVA to install a qualified neutron monitoring system.

In Reference 10, TVA requested further BFN specific actions regarding the neutron flux monitoring instrumentation be deferred pending the resolution of the BWR Owners' Group appeal.

In Reference 11, TVA identified previously submitted deviation to Regulatory Guide 1.97 for which NRC review was still required, addressed discrepancies between TVA letters and NRC SERs, and identified new deviations for NRC review.

Additional information regarding emergency damper position indication was provided by TVA in Reference 12. The deviations addressed above were addressed in the NRC's May 10, 1991, SER (Reference 13). In addition, implementation of qualified neutron flux monitoring capability was deferred pending review of an appeal by the BWR Owners Group.

April 13, 2007 E1-51

A revised SER regarding neutron flux monitoring instrumentation was issued in Reference 14. TVA's review of BFNs neutron flux monitoring instrumentation against the criteria referenced by the SER was provided in References 15 and 16. As part of Reference 16, TVA committed to evaluate the neutron monitoring system cables, electrical penetrations and connectors for conformance to the criteria reference by the SER. This evaluation has been completed. Consistent with the conclusions reached for Units 2 and 3, the Unit 1 neutron monitoring system cables, electrical penetrations, and electrical connectors are capable of operating throughout the one hour duration of the ATWS event.

NRC acceptance of the deviation requested by TVA was documented in the May 3, 1994 SER (Reference 17).

Status: C-C TVA has replaced the subject instrumentation with qualified devices.

NRC closed this item in Inspection Report 2005-07 (Reference 18).

References:

1. NRC letter to All Licensees of Operating Reactors, Applicants for Operating Licenses, and Holders of Construction Permits, dated December 17, 1982, Supplement 1 to NUREG-0737 -

Requirements for Emergency Response Capability (Generic Letter 82-33)

2. TVA letter to NRC, dated April 30, 1984, in regards to Generic Letter 82-33
3. NRC letter to TVA, dated June 12, 1984, Issuance of Orders Confirming Licensee Commitments on Emergency Response Capability
4. NRC letter to TVA, dated January 23, 1985, Emergency Response Capability - Conformance to R.G. 1.97, Rev. 2
5. TVA letter to NRC, dated May 7, 1985, in regards to conformance with Regulatory Guide 1.97
6. TVA letter to NRC, dated November 20, 1985, in regards to conformance with Regulatory Guide 1.97
7. NRC letter to TVA, date June 23, 1988, Generic Letter 82-33, Request for Compliance with the Guidelines of Regulatory Guide (R.G.) 1.97 as Applied to Emergency Response Facilities April 13, 2007 E1-52
8. TVA letter to NRC, dated August 23, 1988, Response to NRC's Safety Evaluation Report on Regulatory Guide 1.97 as Applied to Emergency Response Facilities Dated June 23, 1988
9. NRC letter to TVA, dated February 8, 1990, Emergency Response Capability - Conformance to Regulatory Guide 1.97. Revision 3
10. TVA letter to NRC, dated September 14, 1990, Response to NRC's February 8, 1990 Safety Evaluation Report Regarding Conformance to Regulatory Guide 1.97, Revision 3 - Neutron Flux Monitoring Instrumentation
11. TVA letter to NRC, dated October 15, 1990, Response to NRC Supplemental Safety Evaluation Report (SER) on Regulatory Guide (RG) 1.97 Compliance dated February 8, 1990
12. TVA letter to NRC, dated December 21, 1990, Regulatory Guide (RG) 1.97 Emergency Ventilation Dampers Position Indication
13. NRC letter to TVA, dated May 10, 1991, Safety Evaluation of Emergency Response Capability -

Conformance to Regulatory Guide 1.97, Revision 3

14. NRC letter to TVA, dated May 27, 1993, Regulatory Guide 1.97 - Boiling Water Reactor Neutron Flux Monitoring
15. TVA letter to NRC, dated July 30, 1993, Regulatory Guide 1.97 - Boiling Water Reactor Neutron Flux Monitoring
16. TVA letter to NRC, dated March 10, 1994, Regulatory Guide 1.97 - Boiling Water Reactor Neutron Flux Monitoring
17. NRC letter to TVA, dated May 3, 1994, Boiling Water Reactor Neutron Flux Monitoring for the Browns Ferry Nuclear Plant
18. NRC letter to TVA, dated August 15, 2005, Browns Ferry Nuclear Plant Unit 1 Recovery - NRC Integrated Inspection Report 05000259/2005007 April 13, 2007 E1-53

Generic Letter 83-08, Modification of Vacuum Breakers on Mark I Containments Commitment: TVA will modify the torus vacuum breakers.

Discussion: TVA responded to the Generic Letter in Reference 1 and committed to modify the torus vacuum breakers.

NRC requested additional information in Reference 2, which was provided by TVA in Reference 3. The NRC Safety Evaluation Report was issued in Reference 4. It concluded that TVAs actions would be adequate to restore the original design margin of safety for its vacuum breakers under the revised loadings in the Mark I containment.

Status: C-C TVA modified the torus vacuum breakers.

NRC closed this item in Inspection Report 2005-006 (Reference 5).

References:

1. TVA letter to NRC, dated November 5, 1984, in regards to Generic Letter 83-08
2. NRC letter to TVA, dated January 17, 1986, Modification of Vacuum Breakers on Mark I Containments (Generic Letter 83-08)
3. TVA letter to NRC, dated April 7, 1986, in regards to Generic Letter 83-08
4. NRC letter to TVA, dated November 25, 1986, Modification of Vacuum Breakers on Mark I Containments (Generic Letter 83-08); MPA D-20
5. NRC letter to TVA, dated May 16, 2005, Browns Ferry Nuclear Plant Unit 1 Recovery - NRC Integrated Inspection Report 05000259/2005006 April 13, 2007 E1-54

Generic Letter 83-28, Salem ATWS, Item 1.2, Post Trip Review (Data and Information Capability)

Commitment: TVA will complete Generic Letter, Item 1.2.

Discussion: In response to Generic Letter 83-28, Item 1.2, TVA committed in Reference 1 to the installation of an upgraded process computer and an enhanced sequence of events recording capability. TVA's response was found to be acceptable in the NRC's Safety Evaluation provided by Reference 2.

As discussed in Reference 3, the Unit 2 equipment was replaced with more modern and sophisticated hardware, since the time of the original TVA submittal. The previously described upgrade to a Digital VAX 11/750 process computer system was accomplished using a Digital VAX 6000 system. The functions previously performed by the sequence of events and time history recorder are now accomplished using the process computer system.

However, the guidance contained in the Generic Letter and the requirements of the Safety Evaluation continue to be met.

Status: Closed NRC closed this item in Inspection Report 2006-007 (Reference 4).

References:

1. TVA letter to NRC, dated November 7, 1983, in regards to Generic Letter 83-28
2. NRC letter to TVA, dated June 12, 1985, Safety Evaluation for Generic Letter 83-28, Item 1.2, Post Trip Review (Data and Information Capability)
3. TVA letter to NRC, dated November 9, 1993, Completion of Unit 2 Commitment for Generic Letter 83-28, Item 1.2 - Post-Trip Review - Data and Information Capability (GSI 75 / MPA B-085)
4. NRC letter to TVA, dated August 10, 2006, Browns Ferry Nuclear Plant Unit 1 Recovery - NRC Integrated Inspection Report 05000259/2006007 April 13, 2007 E1-55

Generic Letter 83-28, Salem ATWS, Item 4.5.2, Periodic On-Line Testing Commitment: TVA will complete Generic Letter, Item 4.5.2.

Discussion: The NRCs position on this item was that plants not currently designed to permit periodic on-line testing shall justify not making modifications to permit such testing. Alternatives to on-line testing proposed by licensees will be considered where special circumstances exist and where the objective of high reliability can be met in another way. TVAs initial response to this item (Reference 1) stated that on-line testing was being evaluated. A description of the Reactor Protection System (RPS) functional testing and reliability was provided by TVA in Reference 2.

The NRC Safety Evaluation states the on-line testing capability of BFNs RPS meets the intent of this item and is therefore acceptable (Reference 3).

Status: Closed NRC closed this item in Inspection Report 2006-007 (Reference 4).

References:

1. TVA letter to NRC, dated November 7, 1983, in regards to Generic Letter 83-28
2. TVA letter to NRC, dated March 15, 1984, in regards to Generic Letter 83-28
3. NRC letter to TVA, dated September 2, 1986, Reactor Trip System Reliability, On-Line Testing, Generic Letter 83-28, Item 4.5.2
4. NRC letter to TVA, dated August 10, 2006, Browns Ferry Nuclear Plant Unit 1 Recovery - NRC Integrated Inspection Report 05000259/2006007 April 13, 2007 E1-56

Generic Letter 83-28, Salem ATWS, Item 4.5.3, Intervals for On-Line Testing Commitment: TVA will complete Generic Letter 83-28, Item 4.5.3.

Discussion: The NRC Staff has reviewed the General Electric Topical Reports NEDC-30844, BWR Owners' Group (BWROG) Response to NRC Generic Letter 83-28, Item 4.5.3, and NEDC-30851P, Technical Specifications Improvement Analysis for BWR Reactor Protection System, and issued a favorable Safety Evaluation Report (Reference 1).

In Reference 2, TVA endorsed the BWROG position and stated the analysis presented in NEDC-30851P were applicable to BFN. No Technical Specifications instrument calibration frequency extensions were requested based on these reports. Differences between the parts of BFNs Reactor Protection System (RPS) that perform the trip functions and those of the base case plant were analyzed using the procedures of Appendix K of NEDC-30851P to demonstrate no appreciable change in RPS availability or public risk. The Safety Evaluation that closed this item was provided by Reference 3.

Status: Closed NRC closed this item in Inspection Report 2006-007 (Reference 4).

References:

1. NRC letter to BWR Owners Group, dated July 15, 1987, General Electric Company (GE)

Topical Reports NEDC-30844, BWR Owners' Group Response to NRC Generic Letter 83-28, and NEDC-30851P, Technical Specifications Improvement Analysis for BWR RPS

2. TVA letter to NRC, dated July 5, 1990, Generic Letter 83-28, Required Actions Based on Generic Implications of Salem ATWS Events, Item 4.5.3, Reactor Trip System Reliability
3. NRC letter to TVA, dated August 17, 1990, Safety Evaluation of Generic Letter 83-28, Item 4.5.3, Reactor Trip Reliability - On-Line Functional Testing of the Reactor Trip System
4. NRC letter to TVA, dated August 10, 2006, Browns Ferry Nuclear Plant Unit 1 Recovery - NRC Integrated Inspection Report 05000259/2006007 April 13, 2007 E1-57

Generic Letter 87-02, Verification of Seismic Adequacy of Mechanical and Electrical Equipment in Operating Reactors, Unresolved Safety Issue (USI) A-46 Commitment: TVA will resolve USI A-46.

Discussion: In Reference 1, TVA committed to use the Seismic Qualification Utility Group (SQUG) methodology as documented in the Generic Implementation Procedure (GIP) to resolve USI A-46 at Browns Ferry Nuclear Plant. NRC requested clarification regarding TVAs approach in Reference 2, which TVA supplied in Reference 3. In Reference 4, the staff considered TVA's commitment to comply with GIP-2 an acceptable method for resolving USI A-46 at BFN.

TVA provided its response to Generic Letter 87-02 for Unit 1 in Reference 5.

TVA completed the USI-A46 review and resolved outliers. TVA completed the operations review of Safe Shutdown Equipment List (SSEL) following the A-46 verification. The review determined that Unit 1 can be safely shutdown to Mode 3 and maintained while using only the equipment in the SSEL.

IR 2006-006 (Reference 6) stated However, final closure of these items will be deferred until NRR completes their review in this area and any SERs, if required, are issued.

Status: Complete The Safety Evaluation on this program was provided by Reference 7.

References:

1. TVA letter to NRC, dated September 21, 1992, Browns Ferry Nuclear Plant (BFN) - Supplement 1 to Generic Letter 87-02, Verification of Seismic Adequacy of Mechanical and Electrical Equipment in Operating Reactors, Unresolved Safety Issue (USI) A-46 and Supplement 4 to Generic Letter 88-20, Individual Plant Examination of External Events (IPEEE) for Severe Accident Vulnerabilities
2. NRC letter to TVA, dated November 19, 1992, Generic Letter 87-02, Supplement 1 Response -

Browns Ferry Nuclear Plant (TAC Nos. M69430, M69431, and M69432)

April 13, 2007 E1-58

3. TVA letter to NRC, dated January 19, 1993, Browns Ferry Nuclear Plant (BFN) - Generic Letter (GL) 87-02, Supplement 1, 120-Day Response, Request for Additional Information
4. NRC letter to TVA, dated March 19, 1993, Generic Letter 87-02, Supplement 1 Response - Browns Ferry Nuclear Plant (TAC Nos. M69430, M69431, and M69432)
5. TVA letter, T. E. Abney to NRC, dated October 7, 2004, Browns Ferry Nuclear Plant (BFN) Unit 1 - Response to NRC Generic Letter (GL) 87-02, Supplement 1 that Transmits Supplemental Safety Evaluation Report No. 2 (SSER No. 2) on SQUG Generic Implementation Procedure, Revision 2, as Corrected on February 14, 1992 (GIP-2)
6. NRC letter to TVA, dated May 15, 2006, Browns Ferry Nuclear Plant Unit 1 Recovery - NRC Integrated Inspection Report 05000259/2006006
7. NRC letter to TVA, dated December 8, 2006, Review of Licensee Response to NRC Generic Letter 87-02, Supplement 1 That Transmits Supplemental Safety Evaluation Report No. 2 on SQUG Generic Implementation Procedure Revision 2, As Corrected on February 14, 1992 April 13, 2007 E1-59

Generic Letter 88-01, NRC Position on IGSCC in BWR Austenitic Stainless Steel Piping Commitment: TVA will complete Generic Letter 88-01.

Discussion: TVA's program to address Generic Letter 88-01 was provided by Reference 1. The Safety Evaluation documenting the acceptability of the program was included in Reference 2. Supplemental information regarding Unit 1 was submitted in Reference 3. The Safety Evaluation for Unit 1 was provided by Reference 5.

Status: C-C TVA has completed the Generic Letter 88-01 program.

NRC closed this item in Inspection Report 2006-007 (Reference 4).

References:

1. TVA letter to NRC, dated December 28, 1992, Supplemental Response to Generic Letter (GL) 88-01, NRC Position on Intergranular Stress Corrosion Cracking (IGSCC) in BWR Austenitic Stainless Steel Piping
2. NRC letter to TVA, dated December 3, 1993, Safety Evaluation of Supplemental Response to Generic Letter 88-01
3. TVA letter to NRC, dated July 21, 2004, Browns Ferry Nuclear Plant (BFN) Unit 1 - Supplemental Response to Generic Letter 88-01, NRC Position on Intergranular Stress Corrosion Cracking In BWR Austentic Stainless Steel Piping
4. NRC letter to TVA, dated August 10, 2006, Browns Ferry Nuclear Plant Unit 1 Recovery - NRC Integrated Inspection Report 05000259/2006007
5. NRC letter to TVA dated May 30, 2006, Browns Ferry Nuclear Plant Unit 1 - Supplemental Response to Generic Letter 88-01, NRC Position on Intergranular Stress Corrosion Cracking in BWR [Boiling Water Reactor] Austenitic Stainless Steel Piping April 13, 2007 E1-60

Generic Letter 88-11, Radiation Embrittlement of Reactor Vessel Materials and Its Impact on Plant Operations Commitment: TVA will complete Generic Letter 88-11.

Discussion: TVA responded to Generic Letter 88-11 in Reference 1. TVA concluded that the current pressure-temperature curves in each plant's Technical Specifications were valid through the next two fuel cycles when compared to the Regulatory Guide 1.99, Revision 2, methodology.

Supplemental information was provided for BFN in References 2 and 3.

In Reference 4, TVA proposed Technical Specifications changes for BFN Units 1, 2 and 3 to incorporate pressure-temperature curves calculated using Regulatory Guide 1.99, Revision 2, methodology. NRC requested additional information in Reference 5, which was provided by TVA in Reference 6. The proposed Technical Specifications were issued by Reference 7.

Status: C-C NRC closed this item in Inspection Report 2006-007 (Reference 8).

References:

1. TVA letter to NRC, dated November 30, 1988, Browns Ferry Nuclear Plant (BFN), Sequoyah Nuclear Plant (SQN), and Watts Bar Nuclear Plant (WBN) - Response to Generic Letter 88 NRC Position on Radiation Embrittlement of Reactor Vessel Materials and its Impact on Plant Operations
2. TVA letter to NRC, dated February 28, 1991, TVA Supplemental Response to Generic Letter 88-11, NRC Position of Radiation Embrittlement of Reactor Vessel Materials and its Impact on Plant Operations
3. TVA letter to NRC, dated April 30, 1991, TVA Supplemental Response to Generic Letter 88-11, NRC Position of Radiation Embrittlement of Reactor Vessel Materials and its Impact on Plant Operations
4. TVA letter to NRC, dated July 19, 1991, TVA BFN Technical Specification (TS) No. 293 April 13, 2007 E1-61
5. NRC letter to TVA, dated August 28, 1991, Pressure-Temperature Limits Pursuant to Generic Letter 88-11 as Reflected in Proposed Amendment to Technical Specification (TS 293)
6. TVA letter to NRC, dated October 24, 1991, TVA BFN Technical Specification (TS) No. 293 -

Radiation Embrittlement of Reactor Vessel Material and its Impact on Plant Operations -

Response to Request for Additional Information

7. NRC letter to TVA, dated January 8, 1993, Issuance of Amendments for the Browns Ferry Nuclear Plant (TS 293)
8. NRC letter to TVA, dated August 10, 2006, Browns Ferry Nuclear Plant Unit 1 Recovery - NRC Integrated Inspection Report 05000259/2006007 April 13, 2007 E1-62

Generic Letter 88-14, Instrument Air Supply System Problems Affecting Safety-Related Equipment Commitment: TVA will complete Generic Letter 88-14.

Discussion: The original response to Generic Letter 88-14 was included as part of Reference 1. Additional information regarding the dew point of air being supplied to certain components was provided in Reference 2. NRC confirmed TVAs commitments in Reference 3.

Status: Closed NRC closed this item in Inspection Report 2005-008 (Reference 4).

References:

1. TVA letter to NRC, dated February 23, 1989, Browns Ferry Nuclear Plant (BFN), Sequoyah Nuclear Plant (SQN), and Watts Bar Nuclear Plant (WBN) - Response to Generic Letter 88 Instrument Air Supply System Problems Affecting Safety-Related Equipment
2. TVA letter to NRC, dated July 30, 1993, Supplemental Response to Generic Letter (GL) 88-14, Instrument Air Supply System Problems Affecting Safety-Related Equipment
3. NRC letter to TVA, dated May 9, 1989, Generic Letter 88 Instrument Air Supply System Problems Affecting Safety-Related Equipment (TAC Nos. 71631/71632/71633)
4. NRC letter to TVA, dated November 14, 2005, Browns Ferry Nuclear Plant Unit 1 Recovery - NRC Integrated Inspection Report 05000259/2005008 April 13, 2007 E1-63

Generic Letter 88-20, Individual Plant Examination for Severe Accident Vulnerabilities Issue: TVA will respond to Generic Letter 88-20.

Discussion: Generic Letter 88-20 requested licensees:

1. Perform a systematic examination to identify any plant specific vulnerabilities to severe accidents; and
2. Identify and review proposed plant improvements (design changes and changes to operating procedures, maintenance, surveillance, training, or staffing).

The Generic Letter did not request individual IPEs be performed for each unit at a multi-unit site.

The BFN facility has been extensively reviewed by the staff, beginning with an interim reliability evaluation in 1982. This was followed by the subsequent submittal of the November 20, 1986, BFN Unit 1 Probabilistic Risk Assessment (PRA) and its subsequent NRC audit. TVA subsequently submitted BFNs IPE in 1992 and the Multi-unit PRA (MUPRA) in 1995. Since then, TVA has performed individual Unit 2 and Unit 3 PRAs. Neither the MUPRA, nor the subsequently performed individual Unit 2 and Unit 3 PRAs have identified plant vulnerabilities when single or multiple units are in operation. These analyses have provided the staff with more than reasonable assurance that TVA has adequately analyzed the plant design and operations.

In Reference 1, NRC identified the specific information needed for the closeout of Generic Letter 88-20 for Browns Ferry Unit 1. This information was provided in Reference 2.

Status: Complete

References:

1. NRC letter to TVA, dated June 21, 2004, Browns Ferry Nuclear Plant, Unit 1 - Request for Additional Information Related to Generic Letter 88-20, Individual Plant Examination For Severe Accident Vulnerability April 13, 2007 E1-64
2. TVA letter to NRC, dated August 17, 2004, Browns Ferry Nuclear Plant (BFN) - Unit 1 - Response to Request for Additional Information Related to Generic Letter 88-20, Individual Plant Examination for Severe Accident Vulnerability April 13, 2007 E1-65

Generic Letter 88-20, Supplement 4, Individual Plant Examination of External Events (IPEEE) for Severe Accident Vulnerabilities Commitment: TVA will complete an Individual Plant Examination of External Events (IPEEE).

Discussion: In Reference 1, TVA described BFNs program and schedule for completing the internal fires, high winds, external floods, and transportation and nearby facility accidents portions of the IPEEE.

NRC acceptance of the methods and schedules for the addressed portions of the IPEEE was documented in Reference 2.

TVA provided its initial program and schedule for responding to the seismic portion of the IPEEE in Reference 3. NRC requested additional information on this subject in Reference 4, which TVA provided in Reference 5.

The summary report for the high winds, external floods, and transportation and nearby facility accidents IPEEE was provided by TVA in Reference 6 for all three BFN units. The seismic IPEEE Report and the Fire Induced Vulnerability Evaluation were provided in Reference 7.

Status: Complete TVA completed corrective actions to address the seismic-induced fire vulnerability associated with the emergency lighting battery racks located in the BFN Unit 1 cable spreading room prior to restart.

References:

1. TVA letter to NRC, dated December 20, 1991, Individual Plant Examination of External Events (IPEEE) for Severe Accident Vulnerabilities (Generic Letter 88-20, Supplement 4)
2. NRC letter to TVA, dated July 2, 1992, Review of Response to Generic Letter 88-20, Supplement No. 4 - Individual Plant Examinations for External Events April 13, 2007 E1-66
3. TVA letter to NRC, dated September 21, 1992, Supplement 1 to Generic Letter 87-02, Verification of Seismic Adequacy of Mechanical and Electrical Equipment in Operating Reactors, Unresolved Safety Issue (USI) A-46 and Supplement 4 to Generic Letter 88-20, Individual Plant Examination of External Events (IPEEE) for Severe Accident Vulnerabilities
4. NRC letter to TVA, dated November 19, 1992, Generic Letter 87-02, Supplement 1 Response
5. TVA letter to NRC, dated January 19, 1993, Generic Letter (GL) 87-02, Supplement 1, 120-Day Response, Request for Additional Information
6. TVA letter to NRC, dated July 24, 1995, Browns Ferry Nuclear Plant - Generic Letter 88-20, Supplement 4, Individual Plant Examination of External Events (IPEEE) for Severe Accident Vulnerabilities - Partial Submittal of Report
7. TVA letter to NRC, dated January 14, 2005, Browns Ferry Nuclear Plant (BFN) Unit 1 -

Response to NRC Generic Letter (GL) 88-20, Supplement 4 - Individual Plant Examination of External Events (IPEEE) for Severe Accident Vulnerabilities - Submittal of Browns Ferry Nuclear Plant Unit 1 Seismic and Internal Fires IPEEE Reports April 13, 2007 E1-67

Generic Letter 89-06, Task Action Plan Item I.D.2 - Safety Parameter Display System Commitment: TVA will install and make operational a Safety Parameter Display System (SPDS) and certify that the SPDS fully meets the requirements of NUREG-0737, Supplement 1, taking into account the information provided in NUREG-1342.

Discussion: Certification that BFNs SPDS fully meets the requirements of NUREG-0737, Supplement 1, taking into account the information provided in NUREG-1342, was requested by Generic Letter 89-06 (Reference 1). TVA's commitment to implement an SPDS on Unit 1 before restart is contained in Reference 2. The final design description for the SPDS was provided by TVA in References 3 and 4.

The initial Safety Evaluation Report (SER) of the SPDS design description was documented in Reference 5. TVA responded to the SER open items in Reference 6. NRC concluded in a Supplemental SER that TVA's SPDS design description fully met the requirements of NUREG-0737, Supplement 1 (Reference 7).

Status: Closed NRC closed this item in Inspection Report 2006-007 (Reference 8).

References:

1. NRC letter to All Licensees of Operating Plants, Applicants for Operating Licenses and Holders of Construction Permits, dated April 12, 1989, Task Action Plan Item I.D.2 - Safety Parameter Display System - 10 CFR 50.54(f) - (Generic Letter No. 89-06)
2. TVA letter to NRC, dated April 8, 1987, Safety Parameter Display System (SPDS) - Schedule for Response to Request for Additional Information
3. TVA letter to NRC, dated October 22, 1990, Notification of Implementation of NUREG-0737 (TMI Action Plan), Item I.D.2.1, Safety Parameter Display System (SPDS), Phase I Installation and Final Design Description
4. TVA letter to NRC, dated December 11, 1990, Notification of Implementation of NUREG-0737 (TMI Action Plan), Item I.D.2.1, Safety Parameter Display System (SPDS), Final Design Description April 13, 2007 E1-68
5. NRC letter to TVA, dated March 6, 1991, Interim and Final Design of the Safety Parameter Display System at the Browns Ferry Nuclear Plant
6. TVA letter to NRC, dated December 17, 1991, Safety Parameter Display System (SPDS), Response to NRC Safety Evaluation Report (SER) Open Items
7. NRC letter to TVA, dated February 5, 1992, Safety Parameter Display System - Browns Ferry Nuclear Plant, Units 1, 2, and 3)
8. NRC letter to TVA, dated August 10, 2006, Browns Ferry Nuclear Plant Unit 1 Recovery - NRC Integrated Inspection Report 05000259/2006007 April 13, 2007 E1-69

Generic Letter 89-08, Erosion/Corrosion-Induced Pipe Wall Thinning Commitment: TVA will complete Generic Letter 89-08.

Discussion: TVA responded to Generic Letter 89-08 in Reference 1 and committed to implement a long-term monitoring program (single and dual phase piping). NRC acceptance of the program was provided in Reference 2.

Status: Closed NRC closed this item in Inspection Report 2005-009 (Reference 3).

References:

1. TVA letter to NRC, dated July 19, 1989, Response to Generic Letter 89 Erosion/Corrosion-Induced Pipe Wall Thinning
2. NRC letter to TVA, dated August 21, 1989, Licensee Confirmation of its Response to NRC Generic Letter 89-08
3. NRC letter to TVA, dated February 13, 2006, Browns Ferry Nuclear Plant Unit 1 Recovery - NRC Integrated Inspection Report 05000259/2005009 April 13, 2007 E1-70

Generic Letter 89-10, Safety-Related Motor-Operated Valve Testing and Surveillance Commitment: TVA will complete Generic Letter 89-10.

Discussion: TVA responded to Generic Letter 89-10 in Reference 1 and committed to implement a comprehensive motor operated valve program within the requested 5-year implementation schedule.

Additional schedule information was provided by NRC in Reference 2. TVA provided the 30-day response to Generic Letter 89-10, Supplement 3 by Reference 3 and informed the Staff that the plant specific safety assessment was available for review. TVA also responded to Reference 2 and informed the Staff in Reference 4 that the program description for implementing Generic Letter 89-10 was also available for review.

The 120-day response requested in Supplement 3 to the Generic Letter was provided by TVA in Reference 5. It stated that no deficiencies were identified in the motor-operated valves for primary containment isolation for the High Pressure Coolant Injection and Reactor Core Isolation Cooling steam supply lines or the Reactor Water Cleanup water supply line.

In Reference 6, TVA clarified the implementation schedule for Unit 1. Based on test requirements and system configurations, it would be necessary to perform differential pressure testing on some motor operated valves during the power ascension test program. Consequently, TVA committed to complete the required testing within 30 days following the completion of the power ascension test program.

This implementation schedule was acknowledged by the NRC Staff in Reference 7.

TVA submitted a Unit 1 specific program description in Reference 8. The Generic Letter 89-10 program for BFN Unit 1 has been developed.

TVAs review and documentation of the design basis for the operation of each Unit 1 MOV within the scope of the Generic Letter 89-10 program, the valves included in the program, the methods for determining and adjusting switch settings, testing, surveillance, and maintenance are the same as with the Units 2 and 3 program.

April 13, 2007 E1-71

Status: Closed NRC closed this item in Inspection Report 2006-009 (Reference 9).

References:

1. TVA letter to NRC, dated December 21, 1989, Browns Ferry Nuclear Plant (BFN), Sequoyah Nuclear Plant (SQN), and Watts Bar Nuclear Plant (WBN) - Response to Generic Letter 89 Safety-Related Motor-Operated Valve (MOV) Testing and Surveillance
2. NRC letter to TVA, dated September 14, 1990, Response to Generic Letter 89-10, Safety-Related Motor-Operated Valve Testing and Surveillance for the Browns Ferry, Sequoyah, Watts Bar and Bellefonte Nuclear Plants (MPA B-110)
3. TVA letter to NRC, dated December 10, 1990, Response to Generic Letter (GL) 89-10, Supplement 3 - Consideration of the Results of NRC-Sponsored Tests of Motor-Operated Valves (MOV)
4. TVA letter to NRC, dated December 21, 1990, Response to Generic Letter 89-10, Safety-Related Motor-Operated Valve Testing and Surveillance
5. TVA letter to NRC, dated March 13, 1991, Response to Generic Letter (GL) 89-10, Supplement 3 - Consideration of the Results of NRC-Sponsored Tests of Motor-Operated Valves (MOV)
6. TVA letter to NRC, dated April 14, 1992, Generic Letter (GL) 89-10, Safety-Related Motor-Operated Valve Testing and Surveillance - Implementation Schedule
7. NRC letter to TVA, dated June 30, 1992, Browns Ferry Nuclear Plant, Units 1, 2, and 3 -

Implementation Schedule for Generic Letter 89-10 (TAC Nos. M75635, M75636 and M75637)

8. TVA letter to NRC, dated May 5, 2004, Browns Ferry Nuclear Plant (BFN) Unit 1 - Generic Letter 89-10 and Supplements 1 to 7, Safety-Related Motor-Operated Valve (MOV)

Testing and Surveillance

9. NRC letter to TVA, dated March 5, 2007, Browns Ferry Nuclear Plant Unit 1 Recovery - NRC Integrated Inspection Report 05000259/2006009 April 13, 2007 E1-72

Generic Letter 89-13, Service Water System Problems Affecting Safety-Related Equipment Commitment: TVA will complete Generic Letter 89-13.

Discussion: TVA responded to Generic Letter 89-13 in Reference 1. Three of the near-term commitments were rescheduled in Reference 2. NRC was notified of the completion of the majority of the commitments made in response to Generic Letter 89-13 in Reference 3. The remaining commitment on Unit 1 is to verify that the Unit 1 portions of the Residual Heat Removal Service Water (RHRSW) and Emergency Equipment Cooling Water (EECW) systems satisfy their design criteria. Completion of NRCs review is documented in Reference 4.

Status: C-C The Unit 1 RHRSW and EECW systems ability to satisfy their design basis has been verified.

NRC closed this item in Inspection Report 2006-007 (Reference 5).

References:

1. TVA letter to NRC, dated March 16, 1990, Response to Generic Letter (GL) 89-13 Service Water System Problems Affecting Safety-Related Equipment
2. TVA letter to NRC, dated December 31, 1990, Generic Letter (GL) 89-13, Service Water System Problems Affecting Safety-Related Equipment
3. TVA letter to NRC, dated August 17, 1995, Browns Ferry Nuclear Plant (BFN) - Response to Generic Letter (GL) 89 Service Water System (SWS)

Problems Affecting Safety-Related Equipment

4. NRC letter to TVA, dated April 23, 1990, Licensee's Response To Generic Letter 89-13 Regarding Service Water Systems (TAC Nos. 73970, 73971, and 73972)
5. NRC letter to TVA, dated August 10, 2006, Browns Ferry Nuclear Plant Unit 1 Recovery - NRC Integrated Inspection Report 05000259/2006007 April 13, 2007 E1-73

Generic Letter 89-16, Installation of a Hardened Wetwell Vent Commitment: TVA will complete Generic Letter 89-16.

Discussion: In Reference 1, NRC requested licensees with Mark I containments to voluntarily install a hardened vent. In response, TVA committed to install a hardened vent prior to restart in Reference 2.

Status: C-C TVA installed a hardened wetwell vent.

NRC closed this item in Inspection Report 2005-006 (Reference 3).

References:

1. NRC letter to All Operating Licensees with Mark I Containments, dated September 1, 1989, Installation of a Hardened Wetwell Vent (Generic Letter 89-16)
2. TVA letter to NRC, dated October 30, 1989, Response to Generic Letter 89-16, Installation of Hardened Wetwell Vent
3. NRC letter to TVA, dated May 16, 2005, Browns Ferry Nuclear Plant Unit 1 Recovery - NRC Integrated Inspection Report 05000259/2005006 April 13, 2007 E1-74

Generic Letter 92-01, Reactor Vessel Structural Integrity, Revision 1, and Revision 1 Supplement 1 Commitment: TVA will submit a summary evaluation of the time and accumulated fluence during intervals of BFN operation below 525° F and its effect on the reference temperature and on the Charpy upper shelf energy.

Discussion: TVA provided an initial response to Generic Letter 92-01 in Reference 1 and made the commitment reiterated above. The summary evaluation of the time and accumulated fluence during intervals of BFN operation below 525° F was provided by TVA in Reference 2. Additional information was requested by the NRC Staff in Reference 3, which was provided by TVA in Reference 4.

In Reference 5, NRC requested TVA verify the data entered into the Reactor Vessel Integrity Database.

TVA responded to this request in References 6 and 7. Updated material and fluence data was provided by TVA in Reference 8.

In Reference 9, NRC requested Licensees verify the completeness of the information previously submitted by November 15, 1995. TVAs response was provided in References 10 and 11.

As a result of new industry data, NRC again requested updated information in Reference 12. The requested information was provided by TVA in Reference 13 for Browns Ferry.

Status: C-C for restart.

As committed in TVAs May 23, 1994 letter, TVA will inform NRC of the applicability of NEDO 32205 within 90 days of the final surveillance capsules analysis report.

NRC closed this item in Inspection Report 2006-007 (Reference 14).

References:

1. TVA letter to NRC, dated July 7, 1992, Browns Ferry Nuclear Plant (BFN), Sequoyah Nuclear Plant (SQN), and Watts Bar Nuclear Plant (WBN) -

Response to generic Letter 92-01 (Reactor Vessel Structural Integrity)

April 13, 2007 E1-75

2. TVA letter to NRC, dated December 1, 1992, Completion of Commitment Made in Response to Generic Letter 92-01, Reactor Vessel Structural Integrity
3. NRC letter to TVA, dated May 27, 1993, Request for Additional Information Regarding TVA Response to Generic Letter 92-01, Revision 1, Reactor Vessel Structural Integrity
4. TVA letter to NRC, dated August 2, 1993, Response to Request for Additional Information, Generic Letter 92-01, Revision 1
5. NRC letter to TVA, dated April 19, 1994, Generic Letter 92-01, Revision 1, Reactor Vessel Structural Integrity
6. TVA letter to NRC, dated May 23, 1994, TVA's Response to NRC's Letter Dated April 19, 1994, Generic Letter 92-01, Revision 1, Reactor Vessel Structural Integrity
7. TVA letter to NRC, dated July 28, 1994, Supplemental Response to TVA letter Dated May 23, 1994, Generic Letter 92-01, Revision 1, Reactor Vessel Structural Integrity
8. TVA letter to NRC, dated March 27, 1995, Generic Letter 92-01, Reactor Vessel Structural Integrity - Update to the Initial Reference Nil-Ductility Temperature (RTNDT), Chemical Composition and Fluence Values
9. NRC letter to TVA, dated May 19, 1995, NRC Generic Letter 92-01, Revision 1, Supplement 1:

Reactor Vessel Structural Integrity

10. TVA letter to NRC, dated August 7, 1995, in regards to Generic Letter 92-01
11. TVA letter to NRC, dated November 7, 1995, Response to NRC Generic Letter (GL) 92-01, Revision 1, Supplement 1; Reactor Vessel Structural Integrity - Browns Ferry (BFN),

Watts Bar (WBN), and Sequoyah (SQN) Nuclear Plants

12. NRC letter to TVA, dated June 10, 1998, Request for Additional Information Regarding Pressure Vessel Integrity at Browns Ferry Nuclear Plant, Units 1, 2, and 3 (TAC Nos. MA1179, MA1180, and MA1181)

April 13, 2007 E1-76

13. TVA letter to NRC, dated September 8, 1998, Browns Ferry Nuclear Plant (BFN) - Units 1, 2, and 3 - Generic Letter (GL) 92-01, Revision 1, Supplement 1, Reactor Vessel Structural Integrity - Response to NRC Request for Additional Information (TAC Nos. MA1179, MA1180, and MA1181)
14. NRC letter to TVA, dated August 10, 2006, Browns Ferry Nuclear Plant Unit 1 Recovery - NRC Integrated Inspection Report 05000259/2006007 April 13, 2007 E1-77

Generic Letter 92-04, Resolution of the Issues Related to Reactor Vessel Water Level Instrumentation in BWRs Commitment: TVA will continue to support the BWR Owners' Group (BWROG) program of analysis, testing, and development of possible hardware changes which is being conducted by the BWROG.

TVA will review the results of the BWROG program for potential training requirements for operators.

Discussion: TVA responded to Generic Letter 92-04 by Reference 1. NRC approval of TVA's program for the resolution of Generic Letter 92-04 is documented in Reference 2. Interim training of the operators was provided as documented in Inspection Report 93-16 (Reference 3).

Long-term actions were addressed as part of the resolution of Bulletin 93 Resolution of Issues Related to Reactor Vessel Water Level Instrumentation in BWRs.

Status: C-C NRC closed this item in Inspection Report 2006-009 (Reference 4).

References:

1. TVA letter to NRC, dated September 28, 1992, Response to Generic Letter (GL) 92 Resolution of the Issues Related to Reactor Vessel Water Level Instrumentation in BWRs
2. NRC letter to TVA, dated March 25, 1993, Response to Generic Letter 92-04, Resolution of the Issues Related to Reactor Vessel Water Level Instrumentation in Boiling Water Reactors
3. NRC letter to TVA, dated May 18, 1993, NRC Inspection Report No. 259/93-16, 260/93-16 and 296/93-16
4. NRC letter to TVA, dated March 5, 2007, Browns Ferry Nuclear Plant Unit 1 Recovery - NRC Integrated Inspection Report 05000259/2006009 April 13, 2007 E1-78

Generic Letter 94-02, Long-Term Solutions and Upgrade of Interim Operating Recommendations for Thermal-Hydraulic Instabilities in Boiling Water Reactors Commitment: 1. TVA will modify BFN operating procedures and training programs to make them consistent or more conservative than the BWR Owners' Group (BWROG) interim guidelines.

2. TVA will implement the BWROG Option III methodology for the stability long-term solution.

Discussion: TVA responded to Generic Letter 94-02 in Reference 1. In Reference 2, TVA notified NRC that the Unit 1 procedure revisions would be completed prior to restart. In Reference 3, TVA stated its intent to implement the long-term stability solution on Unit 1 before the restart of that unit.

Status: Closed NRC closed this item in Inspection Report 2006-007 (Reference 4).

References:

1. TVA letter to NRC, dated September 8, 1994, Response to NRC Generic Letter (GL) 94 Long-Term Solutions and Upgrade of Interim Operating Recommendations for Thermal-Hydraulic Instabilities in Boiling Water Reactors
2. TVA letter to NRC, dated December 22, 1994, NRC Generic Letter (GL) 94-02, Long-Term Solutions and Upgrade of Interim Operating Recommendations for Thermal-Hydraulic Instabilities in Boiling Water Reactors - Completion of Requested Action 1, Interim Corrective Actions
3. TVA letter to NRC, dated October 4, 1995, Browns Ferry Nuclear Plant (BFN) - Units 1, 2, and 3 -

TVA Confirmation of the Installation Schedule for the Stability Long-Term Solution for NRC Generic Letter (GL) 94-02

4. NRC letter to TVA, dated August 10, 2006, Browns Ferry Nuclear Plant Unit 1 Recovery - NRC Integrated Inspection Report 05000259/2006007 April 13, 2007 E1-79

Generic Letter 94-03, Intergranular Stress Corrosion Cracking of Core Shrouds in Boiling Water Reactors Commitment: TVA will inspect 100% of the accessible areas on core shroud welds Hl through H7. The inspections will be conducted using the best available technology (i.e., Smart-2000 system, suction cup scanners, Westinghouse 1250 camera, etc.) prior to restart.

Discussion: In Reference 1, TVA committed to inspect the accessible areas of the core shroud prior to Unit 1 restart. The NRC's Safety Evaluation is contained in Reference 2.

Status: C-C TVA inspected 100% of the accessible areas on core shroud welds Hl through H7. A structural margin analysis of the core shroud inspections results was performed. This analysis determined Unit 1 can resume operation without repair.

NRC closed this item in Inspection Report 2005-008 (Reference 3).

References:

1. TVA letter to NRC, dated August 23, 1994, Response to NRC Generic Letter (GL) 94 Intergranular Stress Corrosion Cracking (IGSCC) of Shrouds in Boiling Water Reactors.
2. NRC letter to TVA, dated January 13, 1995, Browns Ferry Nuclear Plant Units 1, 2, and 3 Safety Evaluation of Response to Generic Letter 94-03 (IGSCC of Core Shroud in BWRs)
3. NRC letter to TVA, dated November 14, 2005, Browns Ferry Nuclear Plant Unit 1 Recovery - NRC Integrated Inspection Report 05000259/2005008 April 13, 2007 E1-80

Generic Letter 95-07, Pressure Locking and Thermal Binding of Safety-Related Power-Operated Gate Valves Commitment: Unit 1 will be evaluated for the requirements of Generic Letter 95-07 prior to restart.

Discussion: TVA provided response to NRC in References 1 through 5 for BFN Units 2 and 3, Sequoyah Units 1 and 2, and Watts Bar. The NRCs Safety Evaluation for Generic Letter 95-07 was provided in Reference 6.

TVA responded to Generic Letter 95-07 for BFN Unit 1 in Reference 7 and provided additional information in Reference 8. The review methodology used for Unit 1 is the same as that used for TVAs other operating nuclear plants.

The safety related power operated gate valves in Unit 1 have been reviewed for potential susceptibility to the pressure locking and thermal binding phenomenon. There is one High Pressure Coolant Injection valve in Unit 1 which is susceptible to thermal binding. Prior to restart, this valve was replaced with a double disc valve of similar design as Units 2 and 3. Two Core Spray minimum flow valves in Unit 1 were replaced with double disc valves prior to Unit 1 restart. In addition, five safety related power operated gate valves were modified prior to Unit 1 restart to preclude the potential for pressure locking. The reactor side disc face of these five valves was modified by drilling a hole in the disc face into the cavity between the disc faces to avoid pressure locking. NRC found TVAs responses to be an acceptable resolution to the GL 95-07 concerns (Reference 9).

Status: C-C NRC closed this item in Inspection Report 2006-006 (Reference 10).

References:

1. TVA letter to NRC, dated October 16, 1995, Browns Ferry (BFN), Sequoyah (SQN), and Watts Bar (WBN) Nuclear Plants - Response to Generic Letter, Pressure Locking and Thermal Binding of Safety-Related Power-Operated Gate Valves April 13, 2007 E1-81
2. TVA letter to NRC, dated December 15, 1995, Browns Ferry (BFN), Sequoyah (SQN), and Watts Bar (WBN) Nuclear Plants - Supplemental Response to Generic Letter, Pressure Locking and Thermal Binding of Safety-Related Power-Operated Gate Valves
3. TVA letter to NRC, dated February 13, 1996, Browns Ferry (BFN), Sequoyah (SQN), and Watts Bar (WBN) Nuclear Plants - 180-Day Response to Generic Letter, Pressure Locking and Thermal Binding of Safety-Related Power-Operated Gate Valves
4. TVA letter to NRC, dated July 30, 1996, Browns Ferry Nuclear Plant (BFN) - Units 2 and 3, Pressure Locking and Thermal Binding of Safety-Related Power-Operated Gate Valves - Response to Request for Additional Information (TAC Nos. M93437 and M93438)
5. TVA letter to NRC, dated February 19, 1999, Browns Ferry Nuclear Plant (BFN) - Units 2 and 3

- Generic Letter (GL) 95-07, Pressure Locking and Thermal Binding of Safety-Related Power-Operated Gate Valves - Supplemental Response (TAC Nos. M93437 and M93438)

6. NRC letter to TVA, dated June 23, 1999, Safety Evaluation for Generic Letter, Pressure Locking and Thermal Binding of Safety-Related Power-Operated Gate Valves, Browns Ferry Nuclear Plant (BFN) - (TAC Nos. M93436, M93437 and M93438)
7. TVA letter to NRC, dated May 11, 2004, Browns Ferry Nuclear Plant (BFN) Unit 1 - Generic Letter 95-07, Pressure Locking and Thermal Binding of Safety-Related Power-Operated Gate Valves
8. TVA letter to NRC, dated July 29, 2004, Browns Ferry Nuclear Plant (BFN) Unit 1 - Response to Request for Additional Information Regarding Generic Letter 95-07, Pressure Locking and Thermal Binding of Safety-Related Power Operated Gate Valves
9. NRC letter to TVA, dated January 28, 2005, Browns Ferry Nuclear Plant, Unit 1 - Closeout of Generic Letter 95-07, Pressure Locking and Thermal Binding of Safety-Related Power-Operated Gate Valves, Browns Ferry Nuclear Plant, Unit 1 (TAC No. MC3125)
10. NRC letter to TVA, dated May 15, 2006, Browns Ferry Nuclear Plant Unit 1 Recovery - NRC Integrated Inspection Report 05000259/2006006 April 13, 2007 E1-82

Generic Letter 96-01, Testing of Safety-Related Logic Circuits Commitment: BFN Unit 1 will implement the recommendations of Generic Letter 96-01 prior to restart.

Discussion: TVA committed to implement the recommendations of Generic Letter 96-01 prior to restart in Reference 1.

Status: Closed NRC closed this item in Inspection Report 2006-009 (Reference 2).

References:

1. TVA letter to NRC, dated April 18, 1996, Response to Generic Letter (GL) 96-01, Testing of Safety-Related Logic Circuits (TAC Nos.

M94650, M94651, M95652, M94732, M94733, M94750)

2. NRC letter to TVA, dated March 5, 2007, Browns Ferry Nuclear Plant Unit 1 Recovery - NRC Integrated Inspection Report 05000259/2006009 April 13, 2007 E1-83

Generic Letter 96-05, Periodic Verification of Design-Basis Capability of Motor-Operated Valves Commitment: BFN Unit 1 will implement the Joint Owners Group recommended GL 96-05 Periodic Verification Program, and begin testing during the first refueling outage after restart.

Discussion: TVA responded for all its nuclear facilities in Reference 1 and supplemented the response in Reference 2. TVA was a member of the Joint Owners Group (JOG), which culminated in the dynamic testing of 176 Motor Operated Valves (MOVs) at 98 BWR and PWR plants. Each valve was tested three times over five years to address potential degradation in required thrust or torque. The final Topical Report and recommendations for periodic testing were submitted by Reference 3. No additional interim testing is required for Unit 1 since the industry program has been completed.

Status: C-C NRC closed this item in Inspection Report 2005-009 (Reference 4).

References:

1. TVA letter to NRC, dated March 17, 1997, Browns Ferry Nuclear Plant (BFN) (TAC Nos. M97020, M97021, M97022), Sequoyah Nuclear Plant (SQN),

Watts Bar Nuclear Plant (WBN), and Bellefonte Nuclear Plant (BLN) 180-Day Response to NRC Generic Letter (GL) 96-05, Periodic Verification of Design-Basis Capability of Safety-Related Motor-Operated Valves, Dated September 18, 1996

2. TVA letter to NRC, dated April 28, 1998, Browns Ferry Nuclear Plant (BFN) (TAC Nos. M97020, M97021, M97022), Sequoyah Nuclear Plant (SQN),

Watts Bar Nuclear Plant (WBN), and Bellefonte Nuclear Plant (BLN) Response to NRC's Safety Evaluation Dated October 30, 1997, on Joint Owners Group's (JOG) Program for Generic Letter (GL) 96-05, Periodic Verification (PV) of Motor-Operated Valves (MOV) Described in Topical Report MPR-1807 (Revision 2)

3. JOG letter to NRC, dated February 27, 2004, Joint Owners Group Program on Motor-Operated Valve Periodic Verification
4. NRC letter to TVA, dated February 13, 2006, Browns Ferry Nuclear Plant Unit 1 Recovery - NRC Integrated Inspection Report 05000259/2005009 April 13, 2007 E1-84

Generic Letter 96-06, Assurance of Equipment Operability and Containment Integrity During Design-Basis Accident Conditions Commitment: TVA will address Generic Letter 96-06 prior to restart.

Discussion: On September 30, 1996, NRC issued Generic Letter 96-06, which requested licensees address the susceptibility for waterhammer and two-phase flow in the containment air cooler system and over pressurization of piping that penetrates containment.

As described in Reference 1, TVA evaluated the Unit 1 containment air cooler cooling water systems to determine if they are susceptible to either water hammer or two-phase flow conditions during postulated accident conditions. TVA has also evaluated piping systems that penetrate containment to determine if they are susceptible to thermal expansion of fluid such that overpressurization of piping may occur. Two commitments resulted from this evaluation:

The Drywell Floor and Equipment Drains system is acceptable based on leakage through valves which will avoid thermally induced pressure increases above the rated design pressure of the system.

However, TVA will modify the system to provide a designed method of overpressure protection.

The Demineralized Water system has the potential to be affected by overpressurization during a postulated LOCA if the piping is completely filled with water and isolated. In response, TVA will implement procedure changes to assure the system is sufficiently drained following use and is open to containment during power operation.

In Reference 2, NRC stated that TVA had provided an acceptable resolution to the concerns of the Generic Letter.

April 13, 2007 E1-85

Status: C-C

  • TVA modified the Drywell Floor and Equipment Drains system to provide a designed method of overpressure protection.
  • Demineralized water piping in the Unit 1 drywell has been either removed or abandoned. Procedure changes were not required.

NRC closed this item in Inspection Report 2005-008 (Reference 3).

References:

1. TVA letter to NRC, dated May 12, 2004, Browns Ferry Nuclear Plant (BFN) Unit 1 - Generic Letter 96-06, Assurance of Equipment Operability and Containment Integrity During Design Basis Accident Conditions
2. NRC letter to TVA, dated February 7, 2005, Browns Ferry Nuclear Plant, Unit 1 - Closeout of Generic Letter 96-06, Assurance of Equipment Operability and Containment Integrity During Design-basis Accident Conditions (TAC No. MC3186)
3. NRC letter to TVA, dated November 14, 2005, Browns Ferry Nuclear Plant Unit 1 Recovery - NRC Integrated Inspection Report 05000259/2005008 April 13, 2007 E1-86

Generic Letter 97-04, Assurance Of Sufficient Net Positive Suction Head For Emergency Core Cooling and Containment Heat Removal Pumps Commitment: TVA will address Generic Letter 97-04 prior to restart.

Discussion: On October 7, 1997, NRC issued Generic Letter 97-04, which requested licensees review the current design-basis analyses used to determine the available net positive suction head for the emergency core cooling (including core spray and decay heat removal) and containment heat removal pumps.

TVA replied to Generic Letter 97-04 for BFN Unit 1 in Reference 1. TVA stated that it would request approval to credit containment overpressure as part of proposed Technical Specifications (TS) 431, the BFN Unit 1 Extended Power Uprate application, which was submitted in Reference 2. Upon approval of the requested change, no additional information should be required to close Generic Letter 97-04 for BFN Unit 1.

Status: C-C In a letter dated July 26, 2006 (Reference 3), NRR issued an SER concluding BFN has satisfied this Bulletin.

NRC closed this item in Inspection Report 2006-009 (Reference 4).

References:

1. TVA letter to NRC, dated May 6, 2004, Browns Ferry Nuclear Plant (BFN) Unit 1 - Response to NRC Generic Letter (GL) 97-04, Assurance of Sufficient Net Positive Suction Head (NPSH) for Emergency Core Cooling and Containment Heat Removal Pumps
2. TVA letter to NRC, Browns Ferry Nuclear Plant (BFN) - Unit 1- Proposed Technical Specifications (TS) Change TS - 431 - Request For License Amendment - Extended Power Uprate (EPU) Operation, dated June 28, 2004 April 13, 2007 E1-87
3. NRC Letter to TVA, dated July 27, 2006, Browns Ferry Nuclear Plant, Unit 1 - Review of Licensee Response To NRC Generic Letter 97-04, Assurance Of Sufficient Net Positive Suction Head for Emergency Core Cooling And Containment Heat Removal Pumps (TAC No. MC3392)
4. NRC letter to TVA, dated March 5, 2007, Browns Ferry Nuclear Plant Unit 1 Recovery - NRC Integrated Inspection Report 05000259/2006009 April 13, 2007 E1-88

Generic Letter 98-01, Year 2000 Readiness of Computer Systems at Nuclear Power Plants Commitment: None Discussion: Generic Letter 98-01 requested information regarding year 2000 readiness at nuclear power plants. TVA certified the readiness of its nuclear facilities in Reference 1. In Reference 2, the NRC concluded that all requested information had been provided. Therefore, NRC considered GL 98-01 to be closed for TVAs nuclear facilities.

Status: C-C NRC closed this item in Inspection Report 2005-006 (Reference 3).

References:

1. TVA letter to NRC, dated June 29, 1999, Browns Ferry Nuclear Plant (BFN) Units 1, 2, and 3, Sequoyah Nuclear Plant (SQN) Units 1 and 2, Watts Bar Nuclear Plant (WBN) Unit 1, Final Response to Generic Letter (GL) 98-01, Year 2000 (Y2K) Readiness of Computer Systems at Nuclear Power Plants
2. NRC letter to TVA, dated October 18, 1999, Watts Bar, Browns Ferry and Sequoyah - Response to Generic Letter 98-01, "Year 2000 Readiness of Computer Systems at Nuclear Power Plants" (TAC Nos. MA1810, MA1811, MA1812, MAl888, MA1889 and MA1906)
3. NRC letter to TVA, dated May 16, 2005, Browns Ferry Nuclear Plant Unit 1 Recovery -

NRC Integrated Inspection Report 05000259/2005006 April 13, 2007 E1-89

Generic Letter 98-04, Potential for Degradation of the Emergency Core Cooling System and the Containment Spray System after a Loss-Of-Coolant Accident Because of Construction and Protective Coating Deficiencies and Foreign Material in Containment Commitment: TVA will address Generic Letter 98-04 prior to restart.

Discussion: NRC issued GL 98-04 to alert licensees to concerns with the material condition of Service Level 1 protective coatings inside the containment.

GL 98-04 requested that licensees describe their programs for ensuring that Service Level 1 protective coatings inside containment do not detach from their substrate and adversely affect the ability of the Emergency Core Cooling Systems (ECCS) and the safety-related Containment Spray System to perform their function following a Design Basis Loss of Coolant Accident (LOCA).

TVA responded to GL 98-04 for Unit 1 in Reference 1. In summary, TVA has implemented controls for the procurement, application, and maintenance of Service Level 1 protective coatings used inside the primary containment in a manner that is consistent with the licensing basis and regulatory requirements applicable to BFN. The NRC Safety Evaluation (Reference 3) concluded that BFN had provided the information required by GL 98-04.

Status: C-C IR 2006-006 (Reference 2) stated However, final closure of this item will be deferred until NRR completes their review in this area.

NRC closed this item in Inspection Report 2006-008 (Reference 4).

References:

1. TVA letter to NRC, dated May 11, 2004, Browns Ferry Nuclear Plant (BFN) Unit 1 - Response to NRC Generic Letter (GL) 98-04, Potential for Degradation of the Emergency Core Cooling System and the Containment Spray System After a Loss-Of-Coolant Accident Because of Construction and Protective Coating Deficiencies and Foreign Material in Containment
2. NRC letter to TVA, dated May 15, 2006, Browns Ferry Nuclear Plant Unit 1 Recovery - NRC April 13, 2007 E1-90

Integrated Inspection Report 05000259/2006006

3. NRC letter to TVA dated September 27, 2006, Browns Ferry Nuclear Plant, Unit 1 - Review of Licensee Response to NRC Generic Letter 98-04, Potential for Degradation of the Emergency Core Cooling System and the Containment Spray System After a Loss-Of-Coolant Accident Because of Construction and Protective Coating Deficiencies and Foreign Material in Containment
4. NRC letter to TVA, dated November 9, 2006, Browns Ferry Nuclear Plant Unit 1 Recovery - NRC Integrated Inspection Report 05000259/2006008 April 13, 2007 E1-91

Generic Letter 2003-01, Control Room Habitability Commitment: TVA will address Generic Letter 2003-01 prior to restart.

Discussion: NRC issued GL 2003-01 to:

1. alert addressees to findings at U.S. power reactor facilities suggesting that the control room licensing and design bases, and applicable regulatory requirements may not be met, and that existing technical specification surveillance requirements (SRs) may not be adequate,
2. emphasize the importance of reliable, comprehensive surveillance testing to verify control room habitability,
3. request addressees to submit information that demonstrates that the control room at each of their respective facilities complies with the current licensing and design bases, and applicable regulatory requirements, and that suitable design, maintenance and testing control measures are in place for maintaining this compliance, and
4. collect the requested information to determine if additional regulatory action is required.

TVA responded to GL 2003-01 in Reference 1. In summary, the BFN Units 1, 2, and 3 design basis and licensing basis are in compliance with the applicable regulatory requirements. The plant is constructed and maintained in accordance with its design, and the testing performed in accordance with the BFN Technical Specifications (TS) and their bases is adequate to demonstrate this compliance and material condition.

In Reference 2, the NRC provided a request for additional information (RAI) to TVA. TVA answered this RAI in Reference 3.

Status: Complete April 13, 2007 E1-92

References:

1. TVA letter to NRC, dated December 8, 2003, Browns Ferry Nuclear Plant (BFN) Units 1, 2, and 3 Response to NRC Generic Letter (GL) 2003 Control Room Habitability
2. NRC letter to TVA, dated January 9, 2007, Browns Ferry Nuclear Plant, Units 1, 2 and 3, Request For Additional Information Regarding Generic Letter 2003-01, Control Room Habitability
3. TVA letter to NRC, dated February 8, 2007, Browns Ferry Nuclear Plant Units 1, 2 and 3 -

Request For Additional Information Regarding Generic Letter 2003-01, Control Room Habitability April 13, 2007 E1-93

Generic Safety Issue 75 / Multi-Plant Action B085, Generic Letter 83-28, Item 1.2, Post-Trip Review -

Data and Information Capability Issue: This issue arose from the staff concerns resulting from analysis of events that occurred at the Salem Nuclear Power Plant on February 22 and 25, 1983.

The study of these events resulted in the issuance of NUREG-1000 and Generic Letter 83-28. Item 1.2 of the Generic Letter requests licensees have the capability to record, recall, and display data and information to permit diagnosing the causes of unscheduled reactor shutdowns and the proper functioning of safety-related equipment during these events using systematic safety assessment procedures.

Discussion: Refer to previous topic entitled Generic Letter 83-28, Salem ATWS, Item 1.2, Post Trip Review (Data and Information Capability) (Page E1-55).

Status: Refer to previous topic entitled Generic Letter 83-28, Salem ATWS, Item 1.2, Post Trip Review (Data and Information Capability) (Page E1-55).

References:

Refer to previous topic entitled Generic Letter 83-28, Salem ATWS, Item 1.2, Post Trip Review (Data and Information Capability) (Page E1-55).

April 13, 2007 E1-94

HVAC Duct Supports Commitment: The HVAC Duct Supports program will be implemented in accordance with the Unit 2 precedent.

Discussion: The approval of the program for the seismic qualification of HVAC duct supports is contained in References 1 and 2. The design criteria for the seismic qualification of the HVAC and supports was submitted in Reference 3. The NRC staff's Safety Evaluation Report (SER) on the criteria was included in Reference 4.

Status: C-C For Unit 1, a review was performed to identify the areas of Class I HVAC ductwork that were not previously qualified for Units 2 and 3 operation.

The only areas specific to Unit 1 thus identified were the ductwork associated with the pump motor coolers for the Unit 1 Residual Heat Removal system and Core Spray system. Based upon the seismic qualification calculations, modifications have been completed to ensure that this ductwork is qualified to the long term requirements of the design criteria.

NRC closed this item in document dated March 9, 2007 (Reference 5).

References:

1. NRC letter to TVA, dated August 22, 1990, Safety Evaluation of Inspection Open Item Regarding HVAC Ductworks and Supports for Browns Ferry Nuclear Plant, Unit 2 (TAC No. 62259)
2. NRC letter to TVA, dated January 23, 1991, NUREG-1232, Volume 3, Supplement 2 - Browns Ferry, Unit 2, Section 2.2.2.4 (Page 2-5)
3. TVA letter to NRC, dated November 15, 1991, Heating, Ventilation and Air Conditioning (HVAC)

Seismic Design Criteria

4. NRC letter to TVA, dated July 16, 1992, Evaluation of Seismic Design Criteria for Heating Ventilation and Air Conditioning
5. NRC Meeting Summary dated March 9, 2007, Meeting Summary - Internal Meeting of the Browns Ferry Unit 1 Restart Panel - Docket No.

50-259 April 13, 2007 E1-95

Instrument Sensing Lines Commitment: 1. The H2O2 analyzers will be modified in accordance with the Unit 2 precedent.

2. Where satisfactory operation can not be justified, the sensing lines will be reworked.
3. The 10 CFR 50, Appendix R, FSAR Appendix M, and Generic Evaluation of Internally Generated Missiles programs will require evaluations to maintain the integrity of instrument sense line separation.

Discussion: The action plan for dispositioning instrument sensing line issues, including a discussion of lessons learned from the Unit 2 precedent, was provided in Reference 1. In Reference 2, NRC concluded that the program to address concerns related to instrument sensing lines was adequate.

Status: Complete The sample lines to the H2O2 analyzers were modified to assure that there are no moisture traps which would block the air sample flow from the drywell/torus to the analyzers.

Safety-related sensing lines were evaluated in order to maintain the integrity of instrument sensing line separation as required by the 10 CFR 50, Appendix R, FSAR Appendix M, and Generic Evaluation of Internally Generated Missiles programs. Sensing lines were either justified for use-as-is, or modified as required.

References:

1. TVA letter to NRC, dated February 13, 1991, Action Plan to Disposition Concerns Related to Instrument Sensing Lines for Units 1 and 3
2. NRC letter to TVA, dated December 10, 1991, Safety Evaluation - TVA Action Plan to Resolve Concerns Related to Instrument Sensing Lines for the Browns Ferry Nuclear Plant, Units 1 and 3 April 13, 2007 E1-96

Instrument Tubing Commitment: Safety-related instrument tubing will be seismically qualified to meet the final design criteria.

Discussion: The action plan for dispositioning concerns regarding the seismic qualification of instrument tubing, including a discussion of lessons learned from the Unit 2 precedent, was provided in Reference 1. Additional information regarding inspection attributes and sampling sizes was provided in Reference 2. In Reference 3, NRC concluded that the program was an acceptable basis for restart of Unit 1 provided that the licensee also evaluates the instrument tubing populations in all units for any new attributes which may be identified during the implementation of the revised program.

Status: Complete The affected systems / supports were analyzed for Seismic Class I qualification, and necessary modifications were completed.

References:

1. TVA letter to NRC, dated February 27, 1991, Action Plan to Disposition Concerns Regarding the Seismic Qualification of Units 1 and 3 Instrument Tubing
2. TVA letter to NRC, dated December 12, 1991, Small Bore Piping Program, Tubing, and Conduit Support Plans for Units 1 and 3 - Additional Information
3. NRC letter to TVA, dated February 4, 1992, Safety Evaluation of Small Bore Piping and Seismic Qualification of Instrument Tubing Programs for Browns Ferry Nuclear Plant, Units 1 and 3 April 13, 2007 E1-97

Intergranular Stress Corrosion Cracking (IGSCC)

Commitment: The Intergranular Stress Corrosion Cracking (IGSCC) program will be implemented in accordance with the Unit 2 precedent.

Discussion: Refer to previous topic entitled Generic Letter 88 NRC Position on IGSCC in BWR Austenitic Stainless Steel Piping (Page E1-60).

Status: Refer to previous topic entitled Generic Letter 88 NRC Position on IGSCC in BWR Austenitic Stainless Steel Piping (Page E1-60).

References:

None April 13, 2007 E1-98

Large Bore Piping Supports Commitment: TVA will complete Bulletin 79-14.

Discussion: Refer to previous topic entitled Bulletin 79-14, Seismic Analysis for As-Built Safety-Related Piping Systems (Page E1-6).

Status: Refer to previous topic entitled Bulletin 79-14, Seismic Analysis for As-Built Safety-Related Piping Systems (Page E1-6).

References:

None April 13, 2007 E1-99

License Renewal - Appendix F Commitments Commitment: TVA will implement the License Renewal - Appendix F commitments prior to Unit 1 restart.

Discussion: On April 21, 2006, TVA sent the NRC a revised list of commitments for License Renewal (Reference 1).

Table 3 of Enclosure 1 of the letter contains the list of License Renewal commitments which are required for Unit 1 restart. The items originate from Appendix F of the License Renewal Application and are required to make the current licensing basis (CLB) of Unit 1 at restart the same as the CLB for Units 2 and 3. These commitments are contained in Table 3 of Appendix A of the Safety Evaluation Report related to the License Renewal of BFN (Reference 2).

Status: Each of the 13 Appendix F commitments and its status is as follows:

F.1 Evaluate and modify, as required, main steam leakage path piping to ensure structural integrity.

Status: Open F.2 Implement Containment Atmosphere Dilution (CAD) System modification.

Status: Complete TVA completed the modifications to the CAD system.

F.3 Revise Fire Protection Report per Unit 1 License Condition 2.C.13.

Status: Refer to previous topic entitled Fire Protection / 10 CFR 50, Appendix R (Page E1-46).

F.4 Implement Environmental Qualification Program.

Status: Refer to previous topic entitled Environmental Qualification (Page E1-45).

April 13, 2007 E1-100

F.5 Address GL 88-01, and make necessary plant modifications.

Status: Refer to previous topic entitled Generic Letter 88-01, NRC Position on IGSCC in BWR Austenitic Stainless Steel Piping (Page E1-60).

F.6 BWRVIP Programs used for Units 2 and 3 will be used for Unit 1.

Status: Complete Required inspections have been completed, and examination reports have been filed. The required Unit 1 examinations have been incorporated into applicable procedure.

F.7 Install ATWS features.

Status: Refer to the topic entitled Unresolved Safety Issue A-9, Anticipated Transients Without Scram (Page E1-134).

F.8 Remove Reactor Vessel Head Spray piping in drywell, and seal the primary containment penetrations.

Status: Complete Piping has been removed, and penetrations have been capped.

F.9 Implement the Hardened Wetwell Vent modification.

Status: C-C Refer to previous topic entitled Generic Letter 89-16, Installation of a Hardened Wetwell Vent (Page E1-74).

April 13, 2007 E1-101

F.10 Cap Service Air and Demineralized Water Primary Containment Penetrations.

Status: Complete The Service Air and Demineralized Water Primary Containment Penetrations were capped.

F.11 Modify Auxiliary Decay Heat Removal (ADHR)

System to serve Unit 1.

Status: Complete ADHR has been modified to serve Unit 1.

F.12 Fully implement the Maintenance Rule.

Unit 1s temporary exemption ceases to be effective.

Status: Open F.13

Status: Complete

Status: Complete

References:

1. TVA letter to NRC, dated April 21, 2006, Browns Ferry Nuclear Plant (BFN) - Units 1, 2, AND 3 -

License Renewal Application (LRA) - Revised Commitment List (TAC Nos. MC1704, MC1705, and MC1706)

2. NUREG-1843, Supplement 1, Safety Evaluation Report Related to the License Renewal of the Browns Ferry Nuclear Plant, Units 1, 2, and 3, Docket Nos. 50-259, 50-260, and 50-296 April 13, 2007 E1-102

License Renewal - Non-Appendix F Commitments Commitment: TVA will implement applicable License Renewal -

Non-Appendix F Commitments prior to Unit 1 restart.

Discussion: On April 21, 2006, TVA sent the NRC a revised list of commitments for License Renewal (Reference 1).

Enclosure 1 of the letter contains the list of License Renewal commitments which are required for Unit 1 restart. Certain of those commitments are not Appendix F items but are required to be implemented prior to Unit 1 restart. These commitments are contained in Appendix A of the Safety Evaluation Report related to the License Renewal of BFN (Reference 2).

The applicable commitments are as follow:

  • Table 1, Item 24., last portion; and
  • Table 2 items with an Implementation Schedule of Prior to Unit 1 restart.

Status: Open

References:

1. TVA letter to NRC, dated April 21, 2006, Browns Ferry Nuclear Plant (BFN) - Units 1, 2, AND 3 -

License Renewal Application (LRA) - Revised Commitment List (TAC Nos. MC1704, MC1705, and MC1706)

2. NUREG-1843, Supplement 1, Safety Evaluation Report Related to the License Renewal of the Browns Ferry Nuclear Plant, Units 1, 2, and 3, Docket Nos. 50-259, 50-260, and 50-296 April 13, 2007 E1-103

Long Term Torus Integrity Program Commitment: TVA committed to resolve torus attached piping support discrepancies in accordance with the Unit 2 criteria precedent. The inspection of the nonsafety-related catwalk will be limited to welds and bolted connections associated with maintaining the integrity of the safety-related structures.

The resolution of catwalk discrepancies will be in accordance with the Unit 2 criteria.

Discussion: On January 13, 1981 (Reference 1), the Commission issued an Order that required the reassessment of the containment design for suppression pool hydrodynamic loading conditions. In Reference 2, a subsequent Order extended the modification completion date until prior to the start of Cycle 6. NRC conducted a post-implementation audit review of the BFN Plant Unique Analysis Report for the Mark I containment long-term program (Reference 3). The staff determined that all but a few of the modifications made by TVA were in accordance with the generic acceptance criteria and the deviations from the acceptance criteria were found acceptable. Discrepancies were identified between design drawings and the actual modifications. The action plan for dispositioning the long-term torus integrity discrepancies was provided by TVA in Reference 4 and approved by NRC in Reference 5.

In Reference 6, NRC identified a Violation with regards to activities associated with the Unit 1 LTTIP corrective actions. TVA responded in Reference 7.

Status: Complete TVA performed modifications to resolve torus attached piping support discrepancies, safety-related torus and torus related structure discrepancies, and nonsafety-related catwalk discrepancies in accordance with the Unit 2 precedent.

References:

1. NRC letter to TVA, dated January 13, 1981, in regards to Orders for Modification of Licenses and Grant of Extension of Exemptions
2. NRC letter to TVA, dated January 19, 1982, in regards to Order Modifying the January 13, 1981 Order April 13, 2007 E1-104
3. NRC letter to TVA, dated May 6, 1985, Mark I Containment Long Term Program
4. TVA letter to NRC, dated April 29, 1991, Program for Resolving Long-Term Torus Integrity Issue Prior to the Restart of Units 1 and 3
5. NRC letter to TVA, dated February 10, 1992, Evaluation of Long-Term Torus Integrity Program for Browns Ferry Nuclear Plant, Units 1 and 3
6. NRC letter to TVA, dated May 12, 2004, Notice of Violation (Browns Ferry Nuclear Plant Unit 1 Recovery - NRC Inspection Report No. 5000259/2004011)
7. TVA letter to NRC, dated June 2, 2004, Browns Ferry Nuclear Plant (BFN) - NRC Inspection Report 50-259/2004-011 - Reply to Notice Of Violation (NOV) EA-04-063 April 13, 2007 E1-105

Lower Drywell Platforms and Miscellaneous Steel Commitment: The lower drywell steel platforms and miscellaneous steel will be evaluated and modified, if required, to meet the design criteria.

Discussion: The action plan for dispositioning the Lower Drywell Platforms and Miscellaneous Steel issue was provided in Reference 1. Additional information requested by the Staff was provided in Reference 2.

Additional information was requested by the Staff in Reference 3 and provided by TVA in Reference 4.

An NRC position regarding the design criteria was issued by Reference 5 and a subsequent Safety Evaluation and request for additional information was issued as Reference 6. This additional information was provided by TVA in Reference 7.

A supplemental Safety Evaluation was issued by NRC in Reference 8. Additional information was provided by TVA in References 9 and 10. The final Safety Evaluation was issued in Reference 11 and the issue was closed after an audit of the design criteria implementation as documented in Reference 12.

Status: C-C The lower drywell steel platforms and miscellaneous steel were evaluated and modified, if required, to meet the design criteria.

NRC closed this item in document dated March 9, 2007 (Reference 13).

References:

1. TVA letter to NRC, dated June 12, 1991, Corrective Action Plan and Design Criteria for Lower Drywell Steel Platforms and Miscellaneous Steel
2. TVA letter to NRC, dated November 8, 1991, Seismic Design Criteria for Lower Drywell Steel Platforms and Miscellaneous Steel
3. NRC letter to TVA, dated December 12, 1991, Request for Additional Information Regarding Browns Ferry Drywell and Miscellaneous Steel Design Criteria April 13, 2007 E1-106
4. TVA letter to NRC, dated February 6, 1992, Lower Drywell Platforms and Miscellaneous Steel Seismic Criteria
5. NRC letter to TVA, dated March 19, 1992, NRC Staff Position on Proposed Ductility Ratio Design Criteria
6. NRC letter to TVA, dated July 13, 1992, Safety Evaluation and Request for Additional Information Regarding Browns Ferry Nuclear Plant Units 1, 2, and 3 Design Criteria for Lower Drywell Steel Platforms and Miscellaneous Steel
7. TVA letter to NRC, dated July 31, 1992, Response to Request for Additional Information Regarding Design Criteria for Lower Drywell Steel Platforms and Miscellaneous Steel
8. NRC letter to TVA, dated October 29, 1992, Supplemental Safety Evaluation of Steel Design Criteria for the Browns Ferry Nuclear Power Plant
9. TVA letter to NRC, dated September 30, 1992, Resolution of the Thermal Growth Issue Outside Containment
10. TVA letter to NRC, dated June 29, 1993, Resolution of the Thermal Growth Issue
11. NRC letter to TVA, dated December 7, 1993, Supplemental Safety Evaluation of Structural Steel Thermal Growth Design Criteria
12. NRC letter to TVA, dated April 20, 1994, Audit of Structural Steel Design Criteria Implementation
13. NRC Meeting Summary dated March 9, 2007, Meeting Summary - Internal Meeting of the Browns Ferry Unit 1 Restart Panel - Docket No.

50-259 April 13, 2007 E1-107

Moderate Energy Line Break (MELB)

Commitment: The Moderate Energy Line Break (MELB) program will be implemented in accordance with the Unit 2 precedent.

Discussion: As part of the restart effort on Unit 2, TVA committed to review the effects of flooding due to breaks in moderate energy lines outside primary containment (Reference 1). NRC approval of the program was documented in Reference 2.

The critical plant features that are required to mitigate or limit the consequences of moderate energy piping failures exist in the current BFN design. The results of the Unit 1 evaluation concluded that Browns Ferry conforms to the original licensing basis for MELB flooding and that the existing flooding studies and protective measures are adequate to justify continued operations (Reference 3).

Status: C-C NRC closed this item in Inspection Report 2006-007 (Reference 4).

References:

1. TVA letter to NRC, dated October 24, 1988, Browns Ferry Nuclear Plant (BFN) - Nuclear Performance Plan, Revision 2
2. NRC letter to TVA, dated January 23, 1991, NUREG-1232, Volume 3, Supplement 2 - Browns Ferry, Unit 2, Section 3.8 (Page 3-8)
3. TVA letter to NRC, dated June 25, 2004, Browns Ferry Nuclear Plant (BFN) Unit 1 - Completion of the Program - Moderate Energy Line Break (MELB)

Flooding Evaluation

4. NRC letter to TVA, dated August 10, 2006, Browns Ferry Nuclear Plant Unit 1 Recovery - NRC Integrated Inspection Report 05000259/2006007 April 13, 2007 E1-108

NUREG-0737 (TMI Action Plan), Action Item I.D.1, Control Room Design Review Commitment: TVA will complete NUREG-0737 (TMI Action Plan)

Action Item I.D.1 - Control Room Design Review.

Discussion: Pursuant to NUREG-0737 (TMI Action Plan) and Supplement 1, TVA provided its Control Room Design Review (CRDR) corrective action plan and commitments in Reference 1. NRCs initial Safety Evaluation Report (SER) was issued as Reference 2.

TVA provided additional information in Reference 3.

In Reference 4, TVA also committed to complete all safety and non-safety significant Human Engineering Discrepancies (HEDs) prior to the restart of Units 1 and 3. The final SER for the BFN CRDR was provided in Reference 5.

As part of BFNs Operating and Maintenance Cost Reduction Program, TVA submitted a Cost Beneficial Licensing Action to discontinue the cost-benefit analysis of non-safety significant HEDs (Reference 6). NRC approval of this request was contained in Reference 7.

Status: Closed TVA is implementing its CRDR corrective action plan for Unit 1 and all safety significant HEDs will be corrected.

NRC closed this item in Inspection Report 2006-007 (Reference 8).

References:

1. TVA letter to NRC, dated December 30, 1986, Detailed Control Room Design Review (DCRDR) -

NUREG-0737, Item I.D.1

2. NRC letter to TVA, dated August 9, 1988, Safety Evaluation for the Detailed Control Room Design, Browns Ferry Nuclear Plant, Units 1, 2 and 3 (TACs 56104, 56105, 56106)
3. TVA letter to NRC, dated November 3, 1988, Response to NRC Safety Evaluation for the BFN Detailed Control Room Design Review (DCRDR)
4. TVA letter to NRC, dated August 22, 1991, Supplemental Response to NRC Safety Evaluation for the BFN Detailed Control Room Design Review (DCRDR)

April 13, 2007 E1-109

5. NRC letter to TVA, dated October 29, 1991, Safety Evaluation of the Browns Ferry Nuclear Plant Detailed Control Room Design Review
6. TVA letter to NRC, dated December 15, 1993, Operating & Maintenance (O&M) Cost Reduction Program - Cost Beneficial Licensing Action -

Revision of Detailed Control Room Design Review (DCRDR) Program to Discontinue Cost-Benefit Analysis of Non-Safety Significant Human Engineering Discrepancies (HEDs)

7. NRC letter to TVA, dated February 4, 1994, Revision of Detailed Control Room Design Review Program to Discontinue Cost-Benefit Analysis of Non-Safety Significant Human Engineering Discrepancies
8. NRC letter to TVA, dated August 10, 2006, Browns Ferry Nuclear Plant Unit 1 Recovery - NRC Integrated Inspection Report 05000259/2006007 April 13, 2007 E1-110

NUREG-0737 (TMI Action Plan), Action Item I.D.2, Safety Parameter Display Console Commitment: TVA will complete NUREG-0737 (TMI Action Plan)

Action Item I.D.2 - Safety Parameter Display Console.

Discussion: Refer to the previous item entitled Generic Letter 89 Task Action Plan Item I.D.2 - Safety Parameter Display System (Page E1-68).

Status: Refer to the previous item entitled Generic Letter 89 Task Action Plan Item I.D.2 - Safety Parameter Display System (Page E1-68).

References:

None April 13, 2007 E1-111

NUREG-0737 (TMI Action Plan), Action Item II.B.3, Post-Accident Sampling System Commitment: TVA will complete NUREG-0737 (TMI Action Plan)

Action Item II.B.3 - Post-Accident Sampling System (PASS).

Discussion: A description of BFNs PASS design was provided in References 1 and 2. The Safety Evaluation Report for this system was provided by Reference 3.

TVA submitted a request to decommit to the requirement for a PASS in Reference 4. NRC approved this request in Reference 5.

TVA committed to:

  • Develop contingency plans for obtaining and analyzing highly radioactive samples of reactor coolant, the suppression pool, and containment atmosphere prior to Unit 1 fuel load; and
  • Describe in emergency plan implementing procedures the capability for classifying fuel damage events at the Alert level threshold at radioactivity levels of 300 uCi/ml dose equivalent I-131 prior to Unit 1 fuel load.

Status: C-C TVA has implemented contingency plans for obtaining and analyzing highly radioactive samples of reactor coolant, the suppression pool, and containment atmosphere.

Emergency plan implementing procedures contain the capability for classifying fuel damage events at the Alert level threshold at radioactivity levels of 300 uCi/ml dose equivalent I-131.

NRC closed this item in Inspection Report 2006-006 (Reference 6).

References:

1. TVA letter to NRC, dated December 19, 1986, NUREG-0737, Item II.B.3 - Postaccident Sampling System
2. TVA letter to NRC, dated April 1, 1987, NUREG-0737, Item II.B.3 - Postaccident Sampling System
3. NRC letter to TVA, dated May 27, 1987, Post Accident Sampling System April 13, 2007 E1-112
4. TVA letter to NRC, dated February 19, 2003, Browns Ferry Nuclear Plant (BFN) - Units 1, 2, and 3 - Technical Specifications (TS) Change 423

- Eliminate Requirements for Post Accident Sampling System (PASS) using the Consolidated Line Item Improvement Process and Delete Regulatory Commitment

5. NRC letter to TVA, dated May 9, 2003, Browns Ferry Nuclear Plant, Units 1, 2 and 3, Re: Issuance of Amendments Eliminating Requirements for Postaccident Sampling (TAC Nos. MB7747, MB7748 and MB7749)
6. NRC letter to TVA, dated May 15, 2006, Browns Ferry Nuclear Plant Unit 1 Recovery - NRC Integrated Inspection Report 05000259/2006006 April 13, 2007 E1-113

NUREG-0737 (TMI Action Plan), Action Item II.E.4.2.1-4, Containment Isolation Dependability - Implement Diverse Isolation Commitment: TVA will complete NUREG-0737 (TMI Action Plan)

Action Item II.E.4.2.1 Containment Isolation Dependability - Implement Diverse Isolation.

Discussion: In Reference 1, NRC requested additional information regarding Units 1 and 3 conformance with NUREG-0737, Item II.E.4.2 and 10 CFR 50, Appendix J. In order to minimize the number and scope of updates that would have to be provided to NRC on this issue, TVA replied in Reference 2 using the anticipated configuration at the time of the restart of Unit 1. NRC approval of the Unit 1 containment isolation design is provided in Reference 3. NRC was notified of subsequent changes to the containment isolation configuration, which were being made under the provisions of 10 CFR 50.59, in Reference 4.

Status: Open

References:

1. NRC letter to TVA, dated May 5, 1992, Request for Additional Information to Review Browns Ferry Nuclear Plant Units 1 and 3 Compliance with NUREG-0737 Item II.E.4.2 and 10CFR50, Appendix J
2. TVA letter to NRC, dated September 1, 1992, Response to NRC Request for Additional Information Regarding Units 1 and 3 Conformance with NUREG-0737, Item II.E.4.2 and 10CFR50, Appendix J
3. NRC letter to TVA, dated January 6, 1995, Browns Ferry Nuclear Plant Units 1 and 3 - NUREG-0737, Item II.E.4.2, Containment Isolation Dependability
4. TVA letter to NRC, dated June 24, 2004, Browns Ferry Nuclear Plant (BFN) Unit 1 - Supplemental Information for Conformance with NUREG-0737, Item II.E.4.2, and 10 CFR 50, Appendix J April 13, 2007 E1-114

NUREG-0737 (TMI Action Plan), Action Item II.F.1.2.C, Accident -

Monitoring - Containment High Range Radiation Commitment: TVA will complete NUREG-0737 (TMI Action Plan)

Action Item II.F.1.2.C - Accident - Monitoring -

Containment High Range Radiation.

Discussion: In Reference 1, TVA committed to install a containment high range radiation monitor. In Reference 2, NRC stated no deviations from NRC requirements had been identified; hence no NRC review was required. Reference 3 issued a Confirmatory Order for the installation of the radiation monitors prior to start-up in Cycle 6.

Status: Closed TVA will upgrade the two Unit 1 drywell radiation monitor loops to meet the requirements of NUREG-0737 for Containment High Range Radiation Monitors (CHRRM). The modifications will ensure that the CHRRMs are capable of detecting and measuring the radiation level within the drywell during and following an accident.

NRC closed this item in Inspection Report 2006-006 (Reference 4).

References:

1. TVA letter to NRC, dated December 23, 1980, in regards to post-TMI requirements
2. NRC letter to TVA, dated January 8, 1982, Re: Status of NUREG-0737 Item II.F.1.3 at Browns Ferry Unit Nos. 1, 2 and 3
3. NRC letter to TVA, dated March 25, 1983, in regards to Confirmatory Order for Post-TMI Related Items Set Forth in NUREG-0737
4. NRC letter to TVA, dated May 15, 2006, Browns Ferry Nuclear Plant Unit 1 Recovery - NRC Integrated Inspection Report 05000259/2006006 April 13, 2007 E1-115

NUREG-0737 (TMI Action Plan), Action Item II.F.1.2.D, Accident -

Monitoring - Containment Pressure Commitment: TVA will complete NUREG-0737 (TMI Action Plan)

Action Item II.F.1.2.D - Accident - Monitoring -

Containment Pressure.

Discussion: In Reference 1, TVA committed to install a containment pressure monitor. NRC requested additional information in Reference 2, which was provided by TVA in Reference 3. Reference 4 issued a Confirmatory Order for the installation of the pressure monitor prior to start-up in Cycle 6. The Safety Evaluation Report for this item was issued in Reference 5. NRC closed this item in Inspection Report 90-29 (Reference 6).

Status: C-C NRC closed this item in Inspection Report 2005-006 (Reference 7).

References:

1. TVA letter to NRC, dated December 23, 1980, in regards to post-TMI requirements
2. NRC letter to TVA, dated March 22, 1982, NUREG-0737, Items II.F.1.4, Containment Pressure Monitor; II.F.1.5, Containment Water Level Monitor, and II.F.1.6, Containment Hydrogen Monitor
3. TVA letter to NRC, dated April 26, 1982, in regards to NUREG-0737, Items II.F.1.4, II.F.1.5, and II.F.1.6
4. NRC letter to TVA, dated March 25, 1983, in regards to Confirmatory Order for Post-TMI Related Items Set Forth in NUREG-0737
5. NRC letter to TVA, dated June 16, 1983, NUREG-0737, Item II.F.1.4 Containment Pressure Monitor, II.F.1.5 Containment Water Level Monitor, and II.F.1.6 Containment Hydrogen Monitor
6. NRC letter to TVA, dated November 8, 1990, Notice of Violation (NRC Inspection Report Nos.

50-259/90-29, 50-260/90-29, and 50-296/90-29)

7. NRC letter to TVA, dated May 16, 2005, Browns Ferry Nuclear Plant Unit 1 Recovery - NRC Integrated Inspection Report 05000259/2005006 April 13, 2007 E1-116

NUREG-0737 (TMI Action Plan), Action Item II.F.1.2.E, Accident -

Monitoring - Containment Water Level Commitment: TVA will complete NUREG-0737 (TMI Action Plan)

Action Item II.F.1.2.E - Accident - Monitoring -

Containment Water Level.

Discussion: In Reference 1, TVA committed to install a containment water level monitor. NRC requested additional information in Reference 2, which was provided by TVA in Reference 3. In Reference 4, NRC issued a Confirmatory Order for the installation of the water level monitor prior to start-up in Cycle 6 (July 1983). The Safety Evaluation Report for this item was issued in Reference 5. A Technical Specifications amendment was issued to reflect the modifications performed during that outage (Reference 6).

Status: C-C NRC closed this item in Inspection Report 2005-006 (Reference 7).

References:

1. TVA letter to NRC, dated December 23, 1980, in Regards to Post-TMI Requirements
2. NRC letter to TVA, dated March 22, 1982, NUREG-0737, Items II.F.1.4, Containment Pressure Monitor; II.F.1.5, Containment Water Level Monitor, and II.F.1.6, Containment Hydrogen Monitor
3. TVA letter to NRC, dated April 26, 1982, in regards to NUREG-0737, Items II.F.1.4, II.F.1.5, and II.F.1.6
4. NRC letter to TVA, dated March 25, 1983, in regards to Confirmatory Order for Post-TMI Related Items Set Forth in NUREG-0737
5. NRC letter to TVA, dated June 16, 1983, NUREG-0737, Item II.F.1.4 Containment Pressure Monitor II.F.1.5 Containment Water Level Monitor II.F.1.6 Containment Hydrogen Monitor
6. NRC letter to TVA, dated December 12, 1983, in regards to Amendment 92 for Browns Ferry Unit 1
7. NRC letter to TVA, dated May 16, 2005, Browns Ferry Nuclear Plant Unit 1 Recovery - NRC Integrated Inspection Report 05000259/2005006 April 13, 2007 E1-117

NUREG-0737 (TMI Action Plan), Action Item II.F.2.4 (Generic Letter 84-23), Instrumentation for Detection of Inadequate Core Cooling Commitment: TVA committed to:

1. Convert level instruments which initiate the Reactor Protection System (RPS) and Emergency Core Cooling System (ECCS) and provide class 1E level indication in the control room to analog trip units.
2. Minimize the effects of high drywell temperature on level indications by limiting the vertical drop of the reference legs inside the drywell to no more than two feet.

Discussion: The long-term modifications to improve the reliability and accuracy of BWR water level measurement and instrumentation were requested by Generic Letter 84-23. TVA committed in Reference 1 to replace the RPS and ECCS instruments with analog trip units. TVA committed in Reference 2 to minimize the vertical drop of the reference legs inside containment by bringing the reference legs outside the drywell at higher elevations. This commitment was modified in accordance with the commitment management process to limit the vertical drop inside the drywell to be no more than 2 feet 5 inches. NRC found TVAs proposed modifications acceptable in Reference 3. The NRC was notified of this change by Reference 4.

Status: C-C TVA has:

1. Converted level instruments which initiate the Reactor Protection System (RPS) and Emergency Core Cooling System (ECCS) and provided class 1E level indication in the control room to analog trip units.
2. Minimized the effects of high drywell temperature on level indications by limiting the vertical drop of the reference legs inside the drywell to no more than two feet.

NRC closed this item in Inspection Report 2005-007 (Reference 5).

April 13, 2007 E1-118

References:

1. TVA letter to NRC, dated April 8, 1995, in regards to Generic Letter 84-23
2. TVA letter to NRC, dated March 12, 1986, in regards to Generic Letter 84-23
3. NRC letter to TVA, dated November 18, 1986, NUREG-0731, Item II.F.2, Inadequate Core Cooling Instrumentation (Generic Letter 84-23); MPA-F-26
4. TVA letter to NRC, dated September 5, 1995, Browns Ferry Nuclear Plant (BFN) - Units 1 and 3 Revision to Commitments Concerning The Senior Management Assessment of Readiness Team (SMART) and The Vertical Drop of Reactor Vessel Reference Legs (Generic Letter 84-23)
5. NRC letter to TVA, dated August 15, 2005, Browns Ferry Nuclear Plant Unit 1 Recovery - NRC Integrated Inspection Report 05000259/2005007 April 13, 2007 E1-119

NUREG-0737 (TMI Action Plan), Action Item II.K.3.13, HPCI/RCIC Initiation Levels Commitment: TVA will complete NUREG-0737 (TMI Action Plan)

Action Item II.K.3.13 - HPCI/RCIC Initiation Levels.

Discussion: In Reference 1, TVA states that it concurs with the BWR Owners' Group recommendation that separation of the HPCI/RCIC level setpoints had no substantial benefit and committed to implement an automatic restart of RCIC. In Reference 2, NRC concurred that no significant benefit would be gained by the separation of the HPCI/RCIC initiation levels and requested TVA evaluate the acceptance criteria provided for the RCIC automatic restart. One exception to the criteria was identified in Reference 3 and approved by NRC in Reference 4.

TVA clarified Technical Specifications Bases Section 4.2 in Reference 5. The Bases were revised to state that the automatic restart feature is tested during the performance of logic system functional tests. The issuance of these Bases changes was documented in Reference 6. TVA modified the RCIC logic in order to automatically restart the RCIC system on vessel low water level (without operator action) following a vessel high water trip.

Status: C-C NRC closed this item in Inspection Report 2005-007 (Reference 7).

References:

1. TVA letter to NRC, dated December 23, 1980, in Regards to Post-TMI Requirements
2. NRC letter to TVA, dated March 16, 1983, NUREG-0737, Item II.K.3.13, RCIC Automatic Restart
3. TVA letter to NRC, dated May 24, 1983, in Regards to NUREG-0737, Item II.K.3.13
4. NRC letter to TVA, dated September 19, 1983, NUREG-0737, Item II.K.3.13, RCIC Automatic Restart
5. TVA letter to NRC, dated January 14, 1992, TVA BFN Technical Specification (TS) No. 300 Reactor Core Thermal-Hydraulic Stability April 13, 2007 E1-120
6. NRC letter to TVA, dated May 31, 1994, Issuance of Technical Specification Amendments for the Browns Ferry Nuclear Plant Units 1 and 3 (TS 300)
7. NRC letter to TVA, dated August 15, 2005, Browns Ferry Nuclear Plant Unit 1 Recovery - NRC Integrated Inspection Report 05000259/2005007 April 13, 2007 E1-121

NUREG-0737 (TMI Action Plan), Action Item II.K.3.18, ADS Actuation Modifications Commitment: TVA will complete NUREG-0737 (TMI Action Plan)

Action Item II.K.3.18 - ADS Actuation Modifications.

Discussion: In response to Item II.K.3.18, the BWR Owners' Group performed an evaluation of options for compliance. Two of these options were found to be acceptable by the NRC Staff and TVA was requested in Reference 1 to commit to one of these options.

TVA chose Option 2, to modify the ADS logic to allow the ADS to initiate vessel depressurization, automatically bypassing the high drywell pressure signal 10 minutes after a sustained lo-lo-lo reactor vessel water level signal (Reference 2).

TVA will perform modifications to the ADS logic that will allow the ADS to initiate vessel depressurization.

Status: Closed NRC closed this item in Inspection Report 2005-007 (Reference 3).

References:

1. NRC letter to TVA, dated June 3, 1983, NUREG-0737, Item II.K.3.18, ADS Logic Modifications
2. TVA letter to NRC, dated March 5, 1987, Modifications to Automatic Depressurization System (ADS) Logic - NUREG-0737, Item II.K.3.18
3. NRC letter to TVA, dated August 15, 2005, Browns Ferry Nuclear Plant Unit 1 Recovery - NRC Integrated Inspection Report 05000259/2005007 April 13, 2007 E1-122

NUREG-0737 (TMI Action Plan), Action Item II.K.3.27, Common Reference Level for Vessel Level Instrumentation Issue: Provide level instruments that are referenced to the same point.

Discussion: In Reference 1, NRC proposed that TVA incorporate the requirements of Action Item II.K.3.27 into the control room design review to be performed per NUREG-0737, Action Item I.D.1. This approach eliminates the possibility of changing water level instrument scales twice; once per Item II.K.3.27 and then possibly again per Item I.D.1. TVA accepted this proposal in Reference 2.

Status: C-C NRC letter to TVA, dated December 30, 1982 (Reference 3), incorporated this item into NUREG-0737, Action Item II.K.3.27, Common Reference Level.

NRC closed this item in Inspection Report 2005-008 (Reference 4).

References:

1. NRC letter to TVA, dated October 28, 1982,

Subject:

NUREG-0737 Action Item II.K.3.27 (Common Reference Level)

2. TVA letter to NRC, dated December 3, 1982, in regards to NUREG-0737, Item II.I.3.27 (Common Reference Level)
3. NRC letter to TVA, dated December 30, 1982, NUREG-0737, Action Item II.K.3.27, Common Reference Level
4. NRC letter to TVA, dated November 14, 2005, Browns Ferry Nuclear Plant Unit 1 Recovery - NRC Integrated Inspection Report 05000259/2005008 April 13, 2007 E1-123

NUREG-0737 (TMI Action Plan), Action Item II.K.3.28, Qualification of ADS Accumulators Commitment: TVA will complete NUREG-0737 (TMI Action Plan)

Action Item II.K.3.28 - Qualification of ADS Accumulators.

Discussion: TVA responded to Item II.K.3.28 by Reference 1. The NRC Staff requested additional information in Reference 2, which was provided by TVA in Reference 3. Additional information was requested in Reference 4 and provided in Reference 5. TVA responded to a verbal request for additional information in Reference 6. The Safety Evaluation that documents the acceptability of TVA's plan to satisfy Item II.K.3.28 was provided in Reference 7.

TVA performed modifications to upgrade the ADS accumulator system. This was accomplished by splitting the ring header into two sections, and providing an alternate nitrogen supply to the Drywell Control Air System.

Status: C-C NRC closed this item in Inspection Report 2005-007 (Reference 8).

References:

1. TVA letter to NRC, dated December 30, 1981, in regards to NUREG-0737, Items II.K.3.24, II.K.3.28 and II.B.4
2. NRC letter to TVA, dated May 11, 1983, Request for Additional Information - NUREG-0737, Item II.K.3.28, Qualification of ADS Accumulators
3. TVA letter to NRC, dated July 8, 1983, in regards to NUREG-0737, Item II.K.3.28
4. NRC letter to TVA, dated May 29, 1984, Request for Additional Information - MPA F-55 (TMI II.K.3.28) Qualification of ADS Accumulators
5. TVA letter to NRC, dated July 12, 1984, in regards to NUREG-0737, Item II.K.3.28
6. TVA letter to NRC, dated July 11, 1985, in regards to NUREG-0737, Item II.K.3.28
7. NRC letter to TVA, dated July 24, 1985, NUREG-0737, Item II.K.3.28, Qualification of ADS Accumulators April 13, 2007 E1-124
8. NRC letter to TVA, dated August 15, 2005, Browns Ferry Nuclear Plant Unit 1 Recovery - NRC Integrated Inspection Report 05000259/2005007 April 13, 2007 E1-125

Platform Thermal Growth Issue: TVA will address thermal growth in drywell platforms and miscellaneous steel frames.

Discussion: In Reference 1, TVA informed NRC that TVAs program for the resolution of issues associated with drywell steel platforms for Unit 3 was incorporated into the program Lower Drywell Platforms and Miscellaneous Steel. This program includes upper drywell platforms and platform thermal growth as well.

Status: C-C Refer to previous topic entitled Lower Drywell Platforms and Miscellaneous Steel (Page E1-106).

References:

1. TVA letter, T. E. Abney to NRC, dated December 13, 2002, Browns Ferry Nuclear Plant (BFN) - Unit 1 - Regulatory Framework for the Restart of Unit 1 April 13, 2007 E1-126

Q-List Commitment: TVA will develop a Q-list which provides a list of safety-related systems, structures, and components necessary to ensure:

  • The capability to shut down the reactor and maintain it in a safe shutdown condition; and
  • The capability to prevent or mitigate the consequences of accidents which could result in potential offsite radiation exposures comparable to the 10 CFR 100 limits.

Discussion: BFNs Q-List Program is described in Section III.14.1 of the Browns Ferry Nuclear Performance Plan (Reference 1).

Status: Complete TVA has incorporated Unit 1 into BFNs Q-List Program.

References:

1. TVA letter to NRC, dated October 24, 1988, Browns Ferry Nuclear Plant (BFN) - Nuclear Performance Plan, Revision 2 April 13, 2007 E1-127

Restart Test Program Commitment: For those systems that support safe shutdown, administrative controls for the Restart Test Program will be implemented to insure that an assessment of the Unit 3 System Test Specifications, test procedures, and test results is performed. Administrative controls will be used to insure that the status of the operating units is considered during the planning and scheduling of restart tests.

Discussion: The restart test program was submitted in Reference 1 and supplemented by References 2 through 6.

Status: Open

References:

1. TVA letter to NRC, dated September 27, 1991, Restart Test Program (RTP) Description for Units 1 and 3
2. TVA letter to NRC, dated February 18, 1992, Request for Additional Information Regarding the Restart Test Program for Units 1 and 3
3. TVA letter to NRC, dated December 28, 1992, Update of Restart Test Program (RTP) Submittal for Units 1 and 3
4. TVA letter to NRC, dated July 19, 1993, Restart Test Program (RTP) Update for Units 1 and 3
5. TVA letter to NRC, dated February 2, 1994, Restart Test Program (RTP) Update for Units 1 and 3
6. TVA letter to NRC, dated June 15, 2005, Browns Ferry Nuclear Plant, Unit 1 Request for Additional Information Regarding Restart Testing Program April 13, 2007 E1-128

Seismic Class II Over I / Spatial Systems Interactions and Water Spray Commitment: The Seismic Class II Over I / Spatial Systems Interactions and Water Spray program will be implemented in accordance with the Unit 2 precedent.

Discussion: TVA is utilizing a two phase program to address Class II systems. The action plan for Unit 1 was provided to the NRC in Reference 1. The first part involves the evaluation of potential seismic-induced water spray effects of Class II systems on Class I systems. The second part involves the evaluation of potential seismic-induced, spatial interaction effects of Class II systems on Class I systems. The approval of the Seismic Class II Over I / Spatial Systems Interactions and Water Spray program is contained in References 2 and 3.

Status: Complete Walk downs were completed. Outliers were resolved by either further analysis, plant modification, or maintenance action.

References:

1. TVA letter to NRC dated February 27, 1991, Browns Ferry Nuclear Plant (BFN) - Action Plan to Disposition Concerns Related to Units 1 and 3 Seismic Class II Piping Over Class I Commodities
2. NRC letter to TVA, dated January 23, 1991, NUREG-1232, Volume 3, Supplement 2 -

Browns Ferry, Unit 2, Section 2.2.4.2 (Page 2-10)

3. NRC letter to TVA, dated November 19, 1992, Generic Letter 87-02, Supplement 1 Response -

Browns Ferry Nuclear Plant (TAC Nos. M69430, M69431, and M69432)

April 13, 2007 E1-129

Small Bore Piping Commitment: The Seismic Class I small bore piping will be qualified to meet the final design criteria.

Discussion: TVA's action plan to disposition concerns related to Units 1 and 3 small bore piping was provided in Reference 1 and augmented by Reference 2. NRC approval of this program is documented in the Safety Evaluation transmitted by Reference 3.

Status: Complete TVA qualified the Class I small bore piping to meet the final design criteria.

References:

1. TVA letter to NRC, dated February 27, 1991, Action Plan to Disposition concerns Related to Units 1 and 3 Small Bore Piping
2. TVA letter to NRC, dated December 12, 1991, Small Bore Piping Program, Tubing, and Conduit Support Plans for Units 1 and 3 - Additional Information
3. NRC letter to TVA, dated February 4, 1992, Safety Evaluation of Small Bore Piping and Seismic Qualification of Instrument Tubing Programs for Browns Ferry Nuclear Plant, Units 1 and 3 April 13, 2007 E1-130

Thermal Overloads Commitment: TVA will resolve the thermal overload issue on Unit 1 prior to restart.

Discussion: A review of BFN design drawings identified that thermal overload (TOL) heater sizes for 480 VAC and 250 VDC motor control centers (MCs) were not specified. Consequently, there was no documentation to verify that TOL heater installations are properly sized.

TVAs plan for addressing the TOL issue was submitted in Reference 1. NRC requested additional information in Reference 2, which TVA provided in Reference 3. Supplemental information was provided in References 4 and 5. NRC approval of the program is documented in Reference 6.

Status: C-C TVA completed a walkdown program to document the nameplate data for each load and replaced the TOLs with ones of the proper size. The criteria for sizing has been determined and documented.

Calculations have been performed to ensure the TOL heaters are the proper size for their loads.

NRC closed this item in document dated March 9, 2007 (Reference 7).

References:

1. TVA letter to NRC, dated April 28, 1988, Browns Ferry Nuclear Plant (BFN)- Electrical Issues (NRC TAC No. 62260)
2. NRC letter to TVA, dated August 10, 1988, Request For Additional Information - Browns Ferry Nuclear Plant, Unit 2
3. TVA letter to NRC, dated September 21, 1988, Browns Ferry Nuclear Plant (BFN) - Response to Request for Additional Information - Electric Circuit Protection by Current Limiting Fuses (TAC No. 62260-F)
4. TVA letter to NRC, dated February 28, 1989, Browns Ferry Nuclear Plant (BFN) - Thermal Overload (TOL) Heaters (TAC No. 62260-F)
5. TVA letter to NRC, dated May 15, 1989, Browns Ferry Nuclear Plant (BFN) - Thermal Overload (TOL) Heaters - Sizing Criteria Clarification -

(TAC No. 62260-F)

April 13, 2007 E1-131

6. NRC letter to TVA, dated January 23, 1991, NUREG-1232, Volume 3, Supplement 2 -

Browns Ferry, Unit 2, Section 3.11.1 (Page 3-8)

7. NRC Meeting Summary dated March 9, 2007, Meeting Summary - Internal Meeting of the Browns Ferry Unit 1 Restart Panel -

Docket No. 50-259 April 13, 2007 E1-132

Unresolved Safety Issue A-7, Mark I Long-Term Program Issue: This Unresolved Safety Issue was resolved in August 1982, with the publication of Supplement 1 to NUREG-0661, Safety Evaluation Report, Mark I Containment Long-Term Program and Standard Review Plan Section 6.2.1.1.C.

Discussion: Refer to previous topic entitled Long Term Torus Integrity Program (Page E1-104).

Status: C-C Refer to previous topic entitled Long Term Torus Integrity Program (Page E1-104).

NRC administratively closed this item in Inspection Report 2006-007 (Reference 1). Since this item was added only as a tracking means for this Unresolved Safety Issue, TVA considers it complete also.

References:

1. NRC letter to TVA, dated August 10, 2006, Browns Ferry Nuclear Plant Unit 1 Recovery - NRC Integrated Inspection Report 05000259/2006007 April 13, 2007 E1-133

Unresolved Safety Issue A-9, Anticipated Transients Without Scram Issue: This Unresolved Safety Issue was resolved in June 1983, with the publication of a final rule (10 CFR 50.62) to require improvements in plants to reduce the likelihood of failure of the reactor protection system (RPS) to shut down the reactor following anticipated transients and to mitigate the consequences of an anticipated transient without scram (ATWS) event.

Discussion: TVA provided conceptual design information for conformance with the ATWS Rule in Reference 1. In Reference 2, the NRC found that TVAs design conformance with the ATWS Rule with exception that the Browns Ferry's Alternate Rod Injection and Reactor Pump Trip designs utilized the same analog trip units for both the ATWS system and the reactor trip system (RTS). TVAs response to the diversity issue was provided in Reference 3.

Status: C-C TVA implemented the requirements, actions, and conceptual design modifications submitted. The analog trip units utilized for the ATWS and RPS systems were from different manufacturers.

NRC administratively closed this item in Inspection Report 2006-007 (Reference 4).

References:

1. TVA letter to NRC, dated March 1, 1988, Browns Ferry Nuclear Plant (BFN) - Anticipated Transients Without Scram (ATWS) Rule (10 CFR 50.62) - Plant Specific Design
2. NRC letter to TVA, dated January 22, 1989, Compliance with Rule 10 CFR 50.62 Relating to Alternate Rod Injection and Reactor Pump Trip Systems (TAC 59072, 59073 and 59074)
3. TVA letter to NRC, dated November 29, 1990, Browns Ferry Nuclear Plant (BFN) - Response to NRC Followup Items Received During ATWS Inspection
4. NRC letter to TVA, dated August 10, 2006, Browns Ferry Nuclear Plant Unit 1 Recovery - NRC Integrated Inspection Report 05000259/2006007 April 13, 2007 E1-134

Unresolved Safety Issue A-24, Qualification of Class 1E Safety Related Equipment Issue: This Unresolved Safety Issue was resolved in July 1981, with the publication of NUREG-0588, Revision 1, Interim Staff Position on Environmental Qualification of Safety-Related Electrical Equipment. In summary, the resolution of A-24 is embodied in 10 CFR 50.49.

Discussion: Refer to previous topic entitled Environmental Qualification (Page E1-45).

Status: C-C Refer to previous topic entitled Environmental Qualification (Page E1-45).

NRC administratively closed this item in Inspection Report 2006-007 (Reference 1). Since this item was added only as a tracking means for this Unresolved Safety Issue, TVA considers it complete also.

References:

1. NRC letter to TVA, dated August 10, 2006, Browns Ferry Nuclear Plant Unit 1 Recovery - NRC Integrated Inspection Report 05000259/2006007
2. Refer to previous topic entitled Environmental Qualification (Page E1-45).

April 13, 2007 E1-135

Unresolved Safety Issue A-26, Reactor Vessel Pressure Transient Protection Issue: This Unresolved Safety Issue was resolved in September 1978, with the publication of NUREG-0224, Reactor Vessel Pressure Transient Protection for PWRs, and Standard Review Plan Section 5.2. NRC subsequently issued Generic Letter 88-11, NRC Position on Radiation Embrittlement of Reactor Vessel Materials and Its Impact on Plant Operations, which provided guidance regarding the review of pressure-temperature limits.

Discussion: Refer to previous topic entitled Generic Letter 88-11, Radiation Embrittlement of Reactor Vessel Materials and Its Impact on Plant Operations (Page E1-61).

Status: C-C Refer to previous topic entitled Generic Letter 88-11, Radiation Embrittlement of Reactor Vessel Materials and Its Impact on Plant Operations (Page E1-61).

NRC administratively closed this item in Inspection Report 2006-007 (Reference 1). Since this item was added only as a tracking means for this Unresolved Safety Issue, TVA considers it complete also.

References:

1. NRC letter to TVA, dated August 10, 2006, Browns Ferry Nuclear Plant Unit 1 Recovery - NRC Integrated Inspection Report 05000259/2006007
2. Refer to previous topic entitled Generic Letter 88-11, Radiation Embrittlement of Reactor Vessel Materials and its Impact on Plant Operations (Page E1-61).

April 13, 2007 E1-136

Unresolved Safety Issue A-44, Station Blackout Issue: This Unresolved Safety Issue was resolved in June 1988,with the publication of the Station Blackout Rule (10 CFR 50.63) and Regulatory Guide 1.155.

Discussion: In Reference 1, the staff Safety Evaluation concluded that TVA's proposed methodology for coping with a Station Blackout event at BFN, Units 1, 2, and 3 conforms with 10 CFR 50.63. As requested in the NRCs Safety Evaluation Report, TVA provided its implementation schedule in Reference 2. This letter included a commitment to complete the Unit 1 equipment and associated procedure modifications required for SBO rule compliance prior to restart.

Status: Complete TVA implemented the modifications to the DC power supply system and the DC connected loads.

References:

1. NRC letter to TVA, dated September 16, 1992, Station Blackout - Browns Ferry Units 1, 2, and 3 (MPA-A022) (TAC Nos. M68517, M68518, and M68519)
2. TVA letter to NRC, dated October 15, 1992, Browns Ferry Nuclear Plant (BFN) - Response to NRC Supplemental Safety Evaluation on the Conformance of BFN with the Station Blackout (SBO) Rule April 13, 2007 E1-137

Unresolved Safety Issue A-46, Seismic Qualification of Equipment in Operating Plants Issue: This Unresolved Safety Issue was resolved with the issuance of Generic Letter 87-02 on February 19, 1987, which endorsed the approach of using the seismic and test experience data proposed by the Seismic Qualification Utility Group (SQUG) and Electric Power Research Institute (EPRI). This approach was endorsed by the Senior Seismic Review and Advisory Panel (SSRAP) and approved by the NRC staff.

Discussion: Refer to previous topic entitled Generic Letter 87-02, Verification of Seismic Adequacy of Mechanical and Electrical Equipment In Operating Reactors, Unresolved Safety Issue (USI) A-46 (Page E1-58).

Status: Refer to previous topic entitled Generic Letter 87-02, Verification of Seismic Adequacy of Mechanical and Electrical Equipment In Operating Reactors, Unresolved Safety Issue (USI) A-46 (Page E1-58).

References:

Refer to previous topic entitled Generic Letter 87-02, Verification of Seismic Adequacy of Mechanical and Electrical Equipment In Operating Reactors, Unresolved Safety Issue (USI) A-46 (Page E1-58).

April 13, 2007 E1-138

ENCLOSURE 2 TENNESSEE VALLEY AUTHORITY BROWNS FERRY NUCLEAR PLANT (BFN)

SUMMARY

OF REMAINING UNIT 1 RESTART ISSUES TOPIC COMMITMENT SCHEDULE PAGE Generic Letter 92-01, TVA has submitted the available Ninety days after E1-75 Reactor Vessel data requested by NRC. TVA the final Structural Integrity, will inform NRC of the surveillance Revision 1, and applicability of NEDO 32205 capsules analysis Revision 1 Supplement 1 within 90 days of the final report.

surveillance capsules analysis report.

April 13, 2007 E2-1