IR 05000482/2023003: Difference between revisions

From kanterella
Jump to navigation Jump to search
(StriderTol Bot insert)
 
(No difference)

Latest revision as of 15:03, 21 May 2025

And Independent Spent Fuel Storage Installation - Integrated Inspection Report 05000482/2023003, 07200079/2023001 and Exercise of Enforcement Discretion
ML23293A193
Person / Time
Site: Wolf Creek, Peach Bottom  Wolf Creek Nuclear Operating Corporation icon.png
Issue date: 10/26/2023
From: Vincent Gaddy
NRC/RGN-IV/DORS/EB1
To: Reasoner C
Wolf Creek
References
EA-23-114 IR 2023001
Download: ML23293A193 (34)


Text

October 26, 2023

SUBJECT:

WOLF CREEK GENERATING STATION AND INDEPENDENT SPENT FUEL STORAGE INSTALLATION-INTEGRATED INSPECTION REPORT 05000482/2023003, 07200079/2023001 AND EXERCISE OF ENFORCEMENT DISCRETION

Dear Cleve Reasoner:

On September 30, 2023, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at Wolf Creek Generating Station. On October 2, 2023, the NRC inspectors discussed the results of this inspection with M. Boyce, Engineering Vice President, and other members of your staff. The results of this inspection are documented in the enclosed report.

Two findings of very low safety significance (Green) are documented in this report. Both of these findings involved violations of NRC requirements. We are treating these violations as non-cited violations (NCVs) consistent with section 2.3.2 of the Enforcement Policy.

A licensee-identified violation which was determined to be of very low safety significance is documented in this report. We are treating this violation as a non-cited violation (NCV)

consistent with Section 2.3.2 of the Enforcement Policy.

The licensee identified a violation of 10 CFR 72.212(b)(6), associated with tornado hazard protection. Because this violation was identified during the discretion period covered by Enforcement Guidance Memorandum 22-001, Enforcement Discretion for Noncompliance of Tornado Hazard Protection requirements at Independent Spent Fuel Storage Installations, and because the licensee was implementing compensatory measures and has taken or plans to take the necessary actions to restore compliance, the NRC is exercising enforcement discretion by not issuing an enforcement action for the violation and is allowing continued Independent Spent Fuel Storage Installation handling operations.

If you contest the violations or the significance or severity of the violations documented in this inspection report, you should provide a response within 30 days of the date of this inspection report, with the basis for your denial, to the U.S. Nuclear Regulatory Commission, ATTN:

Document Control Desk, Washington, DC 20555-0001; with copies to the Regional Administrator, Region IV; the Director, Office of Enforcement; and the NRC Resident Inspector at Wolf Creek Generating Station.

If you disagree with a cross-cutting aspect assignment in this report, you should provide a response within 30 days of the date of this inspection report, with the basis for your disagreement, to the U.S. Nuclear Regulatory Commission, ATTN: Document Control Desk, Washington, DC 20555-0001; with copies to the Regional Administrator, Region IV; and the NRC Resident Inspector at Wolf Creek Generating Station.

This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with Title 10 of the Code of Federal Regulations 2.390, Public Inspections, Exemptions, Requests for Withholding.

Sincerely, Gregory E. Werner, Chief Reactor Projects Branch B Division of Operating Reactor Safety Docket No. 05000482, 07200079 License No. NPF-42

Enclosure:

As stated

Inspection Report

Docket Number:

05000482 and 07200079

License Number:

NPF-42

Report Number:

05000482/2023003 and 07200075/2023001

Enterprise Identifier:

I-2023-003-0002 and I-2023-001-0016

Licensee:

Wolf Creek Nuclear Operating Corp.

Facility:

Wolf Creek Generating Station

Location:

Burlington, KS

Inspection Dates:

July 1 to September 30, 2023

Inspectors:

B. Baca, Health Physicist

L. Brookhart, Senior Spent Fuel Storage Inspector

J. Freeman, Spent Fuel Storage Inspector

C. Henderson, Senior Resident Inspector

J. Kirkland, Senior Operations Engineer

J. Vera, Resident Inspector

Approved By:

Gregory E. Werner, Chief

Reactor Projects Branch B

Division of Operating Reactor Safety

SUMMARY

The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees performance by conducting an integrated inspection at Wolf Creek Generating Station, in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for overseeing the safe operation of commercial nuclear power reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information. A licensee-identified non-cited violation is documented in report section: 71124.0

List of Findings and Violations

Failure to Properly Pre-Plan and Perform Maintenance for Safety-Related 4160 Volt Siemens Vacuum Breakers Cornerstone Significance Cross-Cutting Aspect Report Section Mitigating Systems Green NCV 05000482/2023003-01 Open/Closed None (NPP)71111.12 The inspectors reviewed a self-revealed Green finding and associated non-cited violation of technical specification 5.4.1.a, for the licensees failure to properly pre-plan and perform maintenance that can affect performance of safety-related equipment. Specifically, the licensee failed to maintain Procedure MPE E009Q-03, Inspection and Testing of Siemens Vacuum Circuit Breakers, revision 11, to perform maintenance on safety-related 4160 volt Siemens breaker closing spring charging motor electrical motor terminal set screws to verify they were snug tight. This resulted in the failure to charge the closing spring of safety injection pump B breaker NB0202 following surveillance testing, rendering safety injection pump B inoperable for approximately 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br />.

Inadvertent Entry into an Overhead High Radiation Area Cornerstone Significance Cross-Cutting Aspect Report Section Occupational Radiation Safety Green NCV 05000482/2023003-02 Open/Closed

[H.4] -

Teamwork 71124.01 The inspectors reviewed a self-revealed Green non-cited violation of technical specification 5.4.1.a for the licensees inadvertent entry into an overhead high radiation area (HRA). A non-licensed operator (operator) went outside the briefed work scope and work path to walkdown/review access to a valve in the overhead (an HRA) leading to a dose rate alarm.

Additional Tracking Items

Type Issue Number Title Report Section Status EDG EA-23-114 Enforcement Action 23-EA-114: Tornado Hazards Protection at Independent Spent Fuel Storage Installations (EGM 22-001)60855 Closed

PLANT STATUS

Wolf Creek Generating Station began the inspection period at full power. On July 14, 2023, the licensee reduced power to 62 percent at the request of the transmission system operator to facilitate unplanned outage of the 345 kV Rose Hill Line and the unit was returned to full power on July 19, 2023. On August 13, 2023, the licensee reduced power to 62 percent at the request of the transmission system operator to facilitate unplanned outage of the 345 kV Benton Line and the unit was returned to full power on August 14, 2023. The unit remained at full power for the reminder of the inspection period.

INSPECTION SCOPES

Inspections were conducted using the appropriate portions of the inspection procedures (IPs) in effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with their attached revision histories are located on the public website at http://www.nrc.gov/reading-rm/doc-collections/insp-manual/inspection-procedure/index.html. Samples were declared complete when the IP requirements most appropriate to the inspection activity were met consistent with Inspection Manual Chapter (IMC) 2515, Light-Water Reactor Inspection Program - Operations Phase. The inspectors performed activities described in IMC 2515, Appendix D, Plant Status, observed risk significant activities, and completed onsite portions of IPs. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel to assess licensee performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards.

REACTOR SAFETY

71111.04 - Equipment Alignment

Partial Walkdown Sample (IP Section 03.01) (4 Samples)

The inspectors evaluated system configurations during partial walkdowns of the following systems/trains:

(1)train A(B) boron injection tank to charging pumps on July 20, 2023 (2)train B safety injection system on July 28, 2023 (3)train B component cooling water pump room cooler on September 12, 2023 (4)train A residual heat removal minimum flow line on September 13, 2023

71111.05 - Fire Protection

Fire Area Walkdown and Inspection Sample (IP Section 03.01) (6 Samples)

The inspectors evaluated the implementation of the fire protection program by conducting a walkdown and performing a review to verify program compliance, equipment functionality, material condition, and operational readiness of the following fire areas:

(1)south electrical chase, fire area C-8, on July 10, 2023 (2)auxiliary shutdown panel room, fire area A-28, on July 12, 2023 (3)south electrical chase, fire area C-11, on July 28, 2023 (4)rod drive and motor generator set room failed fire detection detector, fire area A-27, on September 15, 2023 (5)electrical penetration room A degraded door, fire area A-18, on September 15, 2023 (6)emergency diesel generator B room during silencer welding activities and extended technical specification equipment outage, fire area D-2, on September 27, 2023

71111.11A - Licensed Operator Requalification Program and Licensed Operator Performance

Requalification Examination Results (IP Section 03.03) (1 Sample)

(1) The inspectors reviewed and evaluated the licensed operator examination failure rates for the requalification annual operating exam administered on May 8 - June 30, 2023.

71111.11Q - Licensed Operator Requalification Program and Licensed Operator Performance

Licensed Operator Performance in the Actual Plant/Main Control Room (IP Section 03.01) (1 Sample)

(1) The inspectors observed and evaluated licensed operator performance in the control room during train B centrifugal charging pump inservice testing and shutdown and control rod operability testing on July 14, 2023.

Licensed Operator Requalification Training/Examinations (IP Section 03.02) (1 Sample)

(1) The inspectors observed and evaluated the licensed operator evaluation scenarios on August 28, 2023.

71111.12 - Maintenance Effectiveness

Maintenance Effectiveness (IP Section 03.01) (2 Samples)

The inspectors evaluated the effectiveness of maintenance to ensure the following structures, systems, and components (SSCs) remain capable of performing their intended function:

(1)station blackout diesel generator maintenance effectiveness on September 5, 2023 (2)auxiliary building safety-related HVAC systems degraded airflow maintenance effectiveness review on September 19, 2023

Quality Control (IP Section 03.02) (1 Sample)

The inspectors evaluated the effectiveness of maintenance and quality control activities to ensure the following SSC remains capable of performing its intended function:

(1)train B safety injection pump breaker failure on September 13, 2023

71111.13 - Maintenance Risk Assessments and Emergent Work Control

Risk Assessment and Management Sample (IP Section 03.01) (5 Samples)

The inspectors evaluated the accuracy and completeness of risk assessments for the following planned and emergent work activities to ensure configuration changes and appropriate work controls were addressed:

(1)train B containment spray pump room cooler failure to automatically start emergency work and extension of technical equipment outage July 3, 2023 (2)loss of nonvital bus breaker PA0206 on July 19, 2023 (3)train A component cooling water technical specification equipment outage on August 10, 2023 (4)emergency diesel generator A, 7-day technical specification equipment outage on August 17, 2023 (5)turbine-driven auxiliary feedwater pump technical specification equipment outage on August 29, 2023

71111.15 - Operability Determinations and Functionality Assessments

Operability Determination or Functionality Assessment (IP Section 03.01) (5 Samples)

The inspectors evaluated the licensee's justifications and actions associated with the following operability determinations and functionality assessments:

(1)train B load shedder and emergency load sequencers failure past operability evaluation on August 31, 2023 (2)train B component cooling water room cooler below design airflow operability evaluation on August 31, 2023 (3)train B containment spray pump room cooler degraded airflow on August 31, 2023 (4)emergency diesel generator B jacket water keep warm pump abnormal noise and safety classification operability determination on September 26, 2023 (5)train B containment spray pump room cooler failure to start past operability determination on September 26, 2023

71111.24 - Testing and Maintenance of Equipment Important to Risk

The inspectors evaluated the following testing and maintenance activities to verify system operability and/or functionality:

Post-Maintenance Testing (PMT) (IP Section 03.01) (8 Samples)

(1)train B containment spray pump room cooler failure to start repair post-maintenance testing on July 6, 2023 (2)train A safety injection technical specification equipment outage on July 13, 2023 (3)train B motor driven auxiliary feedwater technical specification equipment outage on August 1, 2023 (4)train A component cooling water technical specification equipment outage on August 8, 2023 (5)train B component cooling water room cooler motor replacement post-maintenance testing on September 6, 2023 (6)train B component cooling water pump D discharge check valve, EGV0016, post-maintenance testing on September 6, 2023 (7)battery charger, NK022, card replacement post-maintenance testing on September 26, 2023 (8)emergency diesel generator B output breaker extent of condition corrective maintenance post-maintenance testing on September 26, 2023

Surveillance Testing (IP Section 03.01) (3 Samples)

(1)component cooling water pump A, B, C, and D discharger check valve surveillance testing on September 8, 2023 (2)train A residual heat removal pump discharge flow transmitter on September 12, 2023 (3)station blackout diesel generator and non-safety-related auxiliary feedwater pump quarterly run on September 13, 2023

71114.06 - Drill Evaluation

Select Emergency Preparedness Drills and/or Training for Observation (IP Section 03.01) (1 Sample)

(1)emergency preparedness drill involving an anticipated transient without a scram, loss of a main feed pump, and an extended loss of all AC power on August 30, 2023

Drill/Training Evolution Observation (IP Section 03.02) (1 Sample)

The inspectors evaluated:

(1)emergency preparedness drill involving an anticipated transient without a scram, loss of a main feed pump, and an extended loss of all AC power on August 9,

RADIATION SAFETY

71124.01 - Radiological Hazard Assessment and Exposure Controls

Radiological Hazard Assessment (IP Section 03.01) (1 Sample)

(1) The inspectors evaluated how the licensee identifies the magnitude and extent of radiation levels and the concentrations and quantities of radioactive materials and how the licensee assesses radiological hazards. The NRC credits a partial baseline sample from the International Atomic Energy Agency (IAEA) Operational Safety Review Team (OSART) review conducted March 6 through March 23, 2023.

Instructions to Workers (IP Section 03.02) (1 Sample)

(1) The inspectors evaluated how the licensee instructs workers on plant-related radiological hazards and the radiation protection requirements intended to protect workers from those hazards. The NRC credits a partial baseline sample from the IAEA OSART review conducted March 6 through March 23, 2023.

Contamination and Radioactive Material Control (IP Section 03.03) (3 Samples)

The inspectors observed/evaluated the following licensee processes for monitoring and controlling contamination and radioactive material:

(1)contamination control during a system breach and resulting radwaste from gaseous relief tank HA-709 relief valve replacement (2)workers processing out of the radiologically controlled area with personal items monitored in the small article monitors and workers crossing the boundary of a clean area in the fuel handling building truck bay

(3) NRC credits a baseline sample from the IAEA OSART review conducted March 6 through March 23, 2023

Radiological Hazards Control and Work Coverage (IP Section 03.04) (4 Samples)

The inspectors evaluated the licensee's control of radiological hazards for the following radiological work:

(1) Independent spent fuel storage installation (ISFSI) equipment shipments (shipments 23R21, 23R22, 23R23) from the fuel handling building into the public domain.
(2) The movement, survey, and weighing of a spent resin liner (PO 711397-8) from the shielded filling station to its storage location in the high-level radioactive waste storage area.
(3) Radiation work permit 2023-0050, "Contaminated system breaches including, valves, pumps, piping, and strainers for maintenance activities. Includes cutting, welding, grinding of components, technical specification equipment outage activities, and air operated valve & motor operated valve teams," revision 0, task 1 covering the gaseous relief tank HA-709 relief valve replacement.
(4) The NRC credits a baseline sample from the IAEA OSART review conducted March 6 through March 23, 2023.

High Radiation Area and Very High Radiation Area Controls (IP Section 03.05) (4 Samples)

The inspectors evaluated licensee controls of the following high radiation areas (HRAs) and very high radiation areas (VHRAs):

(1)auxiliary building locked high radiation area (LHRA) rooms 1302 (2000' demineralizer alley filter pits and filter high integrity container) and 1507A (2047' containment personnel hatch)

(2) ISFSI pad LHRA (3)radwaste building LHRA rooms 7218 (2000' round process shield), 7220 (primary spent resin valve room), and 7225 (low level storage)
(4) NRC credits a baseline sample from the IAEA OSART review conducted March 6 through March 23, 2023 Radiation Worker Performance and Radiation Protection Technician Proficiency (IP

Section 03.06) (1 Sample)

(1) The inspectors evaluated radiation worker and radiation protection technician performance as it pertains to radiation protection requirements.

71124.04 - Occupational Dose Assessment

Source Term Characterization (IP Section 03.01) (1 Sample)

(1) The inspectors evaluated licensee performance as it pertains to radioactive source term characterization. The NRC credits a partial baseline sample from the IAEA OSART review conducted March 6 through March 23, 2023.

External Dosimetry (IP Section 03.02) (1 Sample)

(1) The inspectors evaluated how the licensee processes, stores, and uses external dosimetry. The NRC credits a partial baseline sample from the IAEA OSART review conducted March 6 through March 23, 2023.

Internal Dosimetry (IP Section 03.03) (2 Samples)

The inspectors evaluated the following internal dose assessments:

(1) Three internal dose assessments involving work under the following radiation work permits (RWPs): RWP 222001, "Welding Activities," revision 2; RWP 222220, "Insulation Removal and Replacement," revision 1; and RWP 224001, "Letdown Heat Exchanger Eddy Current including Block Wall Replacement, Insulation Removal and Re-Installation, Endbell Removal and Re-Installation," revision 1.
(2) The NRC credits a baseline sample from the IAEA OSART review conducted March 6 through March 23, 2023.

Special Dosimetric Situations (IP Section 03.04) (3 Samples)

The inspectors evaluated the following special dosimetric situations:

(1) A declared pregnant worker package.
(2) Effective dose equivalent external assessments for RWP 221102,"Incore Tunnel Inspections, Maintenance & Decontamination," revision 1, task 1 and task 8; RWP

===223049, "Under Reactor Vessel Head - Full Body Entry and Outside Support,"

revision 1, task 1; and RWP 225048, "Reactor Head Cleaning - Whole Body Entry Inside Windows," revision 0, task 2.

(3) The NRC credits a baseline sample from the IAEA OSART review conducted March 6 through March 23,

OTHER ACTIVITIES - BASELINE

71151 - Performance Indicator Verification The inspectors verified licensee performance indicators submittals listed below:

MS05: Safety System Functional Failures (SSFFs) Sample (IP Section 02.04)===

(1) July 1, 2022, through June 30, 2023

MS06: Emergency AC Power Systems (IP Section 02.05) (1 Sample)

(1) July 1, 2022, through June 30, 2023

OR01: Occupational Exposure Control Effectiveness Sample (IP Section 02.15) (1 Sample)

(1) October 1, 2022, through June 30, 2023.

PR01: Radiological Effluent Technical Specifications/Offsite Dose Calculation Manual Radiological Effluent Occurrences (RETS/ODCM) Radiological Effluent Occurrences Sample (IP Section 02.16) (1 Sample)

(1) October 1, 2022, through June 30, 2023.

71152A - Annual Follow-up Problem Identification and Resolution Annual Follow-up of Selected Issues (Section 03.03)

The inspectors reviewed the licensees implementation of its corrective action program related to the following issues:

(1)train B residual heat removal minimum flow valve degraded nonconforming condition associated with motor operator on September 14, 2023 (2)emergency plan classification error trend on September 20,

OTHER ACTIVITIES

- TEMPORARY INSTRUCTIONS, INFREQUENT AND ABNORMAL

===60855 - Operation of an ISFSI The inspectors performed a review of the licensees Independent Spent Fuel Storage Installation (ISFSI) activities to verify compliance with requirements of the Transnuclear (TN)

Nutec Horizontal Modular Extended Optimized Storage (NUHOMS EOS) system's Certificate of Compliance 72-1042, Amendment 1, and Final Safety Analysis Report (FSAR), Revision 3. The inspectors observed licensee operations and reviewed selected procedures, corrective action reports, and records to verify ISFSI operations were compliant with the Certificate's technical specifications, requirements in the FSAR, and NRC regulations.

Operation of an ISFSI===

(1) The inspectors evaluated the licensees dry cask storage operations, from August 28 through September 1, 2023, during an onsite inspection. The Wolf Creek ISFSI is located within the Part 50 protected area. The EOS Matrix ISFSI pad was designed to hold 64 dry shielded canisters (DSCs), each with 37 spent fuel assemblies.

The EOS Matrix design contains two levels of HSM-MXs (horizontal storage module-matrix). Currently the licensee had constructed 11 HSM-MXs, each capable of receiving one DSC, on the southeast portion of the ISFSI pad. During the licensee's loading campaign Wolf Creek planned on loading 3 DSCs into the upper level of the EOS Matrix. Inspectors observed loading activities associated with the second DSC loaded into the upper level of the EOS Matrix. At the end of the loading campaign, the licensee had loaded a total of 8 DSCs into the EOS Matrix.

During the onsite inspection, the inspectors evaluated and observed the following activities:

  • fuel selection and spent fuel placement into the DSC for canister #7
  • removal of the loaded DSC from the spent fuel pool to the canister processing area
  • welding and nondestructive testing of the lid-to-shell welds of the DSC
  • canister vacuum drying and pneumatic testing of the DSC
  • welding, nondestructive testing, and helium leak testing of the top plate and vent/drain port covers The inspectors reviewed and evaluated the following documentation during the inspection:
  • fuel selection evaluations for the canisters loaded since the last NRC ISFSI inspection (canisters 2 - 7)
  • radiation surveys for radiological dose at the owner-controlled boundary to verify compliance with the requirements of 10 CFR 72.104 for 2022
  • selected ISFSI-related condition reports issued since the last NRC ISFSI inspection
  • quality assurance program implementation, including recent audits, surveillances, receipt inspection, and quality control activities related to ISFSI operations
  • compliance to technical specifications for operational surveillance activities and FSAR required maintenance activities
  • documentation of annual maintenance activities for the sites cask handling crane, EOS Matrix crane, and special lifting devices
  • reviewed selected licensee design changes and program changes for the ISFSI performed under the site's 10 CFR 72.48 program
  • reviewed changes made by the licensee in the site's 10 CFR Part 72.212 Evaluation report from revision 0 to revision

INSPECTION RESULTS

Enforcement Discretion Enforcement Action EA-23-114:: Tornado Hazards Protection at Independent Spent Fuel Storage Installations (EGM 22-001)60855

Description:

Upon issuance of U.S. NRC Enforcement Guidance Memorandum (EGM)22-001 (ML22087A496), dated April 15, 2022, the licensee performed an assessment of all outdoor dry cask storage activities that were not explicitly analyzed for tornado hazards in the system's FSAR. Five configurations were identified by the licensee where transport activities did not have a related tornado wind and hazard analysis consistent with the cask's design basis requirements. These situations occurred during both outside operations when the canister is being loaded into the HSM-MX and during indoor activities when the transfer cask is being lowered onto the low-profile transporter.

The TN NUHOMs EOS FSAR, Appendix A, Section A.2, which includes Section A.2.3 Design Criteria for Environmental Conditions and Natural Phenomena, describes the general design criteria for the cask system. Specifically, FSAR Section A.2.3 states, The HSM-MX SSCs described in Section A.2.1 are designed consistent with the 10 CFR Part 72 122(b)requirement for protection against environmental conditions and natural phenomena. The criterion used in the design of the NUHOMS EOS System ensures that exposure to credible site hazards does not impair their safety functions. This includes all off-normal condition loads, environmental phenomena, and accident conditions. Tornado hazards are evaluated in the FSAR Section A. 2.3.1 Tornado Wind and Tornado Missiles for HSM-MX, Section 2.3.2 Tornado Wind and Tornado Missiles for EOS-TC, Section 12.3.3 Tornado Wind and Tornado Missile Effect on EOS-HS, and Section 12.3.4 Tornado Wind and Tornado Missile Effect on EOS-TC. These sections of the FSAR do not include an analysis for tornado hazards when

(1) the loaded canister is lifted by the Matrix Loading Crane at a height > 65",
(2) the transfer cask outer cover is removed,
(3) the HSM-MX door is removed,
(4) the canister is being inserted into the HSM-MX, and
(5) while the transfer cask is being lowered onto the low-profile transporter inside the fuel building due to the fuel building door being potentially susceptible to a tornado missile.

Corrective Actions: The licensee followed the guidance actions as described in the EGM. The issue was entered into the corrective action program and the licensee established additional measures to mitigate tornado hazards, through procedures, during periods of ISFSI handling operations. These actions included, restricting outdoor dry cask storage activities during periods of adverse weather, establishing meteorological criteria, designating staff to monitor weather during ISFSI handling operations, describing actions to take in the event of severe weather necessary to place the cask in an analyzed condition, minimizing the duration of ISFSI handling operations during which ISFSI important to safety SSCs are in an unanalyzed condition, documentation that required weather checks were completed prior to the start of ISFSI handling operations, and documenting in the CAP a request for the Certificate of Compliance (CoC) holder to request an amendment within six months of the date of the EGM or implement physical design modifications and/or perform evaluations that demonstrate important to safety SSCs are designed to withstand the effects of natural phenomena, including tornadoes and tornado-generated missiles prior to the expiration date of the EGM (April 15, 2024).

Corrective Action References: Condition report 10018017

Enforcement:

Significance/Severity: This violation was dispositioned in accordance with the traditional enforcement process using section 2.3 of the NRCs Enforcement Policy. This issue was determined by inspectors to be of more than minor safety significance, since if left uncorrected, the deficiency could lead to a more significant safety concern. Consistent with the guidance in section 1.2.6.D of the NRC's Enforcement Manual, if a violation does not fit an example in the Enforcement Policy Violation Examples, it should be assigned a severity level:

(1) commensurate with its safety significance; and
(2) informed by similar violations addressed in the Violation Examples. The violation was evaluated to be similar to a Severity Level IV violation in Enforcement Policy section 6.5.d.2.

Violation: Title 10 of the Code of Federal Regulations (10 CFR) 72.212 (b)(6), states, in part, that the general licensee must: review the Safety Analysis Report referenced in the CoC or amended CoC and the related NRC Safety Evaluation Report, prior to use of the general

license, to determine whether or not the reactor site parameters, including analyses of earthquake intensity and tornado missiles, are enveloped by the cask design bases considered in these reports.

Contrary to the above, from August 21, through September 8, 2023, the licensee failed to determine whether or not reactor site parameters including analyses of tornado missiles were enveloped by the cask design bases. Specifically, the licensee failed to perform an analysis consistent with FSAR section A.2.3 to demonstrate the NUHOMs cask system ensures that exposure to credible site hazards does not impair their safety functions, such as, when

(1) the loaded canister is lifted by the Matrix Loading Crane at a height > 65",
(2) the transfer cask outer cover is removed,
(3) the HSM-MX door is removed,
(4) the canister is being inserted into the HSM-MX, and
(5) while the transfer cask is being lowered onto the low-profile transporter inside the fuel building due to the fuel building door being potentially susceptible to a tornado missile.

Basis for Discretion: The NRC is exercising enforcement discretion in accordance with section 3.0 of the NRC's Enforcement Policy. In general, the NRC has extensive history analyzing severe weather events including tornado hazard scenarios using probabilistic methods (or risk assessments) in licensing on a case-by-case basis to assess specific plant features to prevent a release of radioactivity exceeding regulatory limits. For ISFSIs, such methods can be employed, supported by analysis, to demonstrate that tornado hazards will not impair the capability of SSCs important to safety to perform their intended design functions.

The Office of Nuclear Reactor Regulation (NRR) completed a generic risk analysis of potential tornado missile protection non-compliances to examine the risk significance of tornado hazard scenarios (ML14114A556). In this case, the generic bounding risk analysis performed by NRR concluded that a tornado missile scenario is of low-risk significance at power reactor sites, due in part to the low probability of wind speeds exceeding 75 miles per hour (less than 4x10-4 per year). This generic analysis did not specifically address ISFSI handling operations but there are several key insights in the analysis that may apply to a risk assessment for this issue. Specifically, rather than evaluate site-specific configurations, the NRR generic analysis used bounding assumptions regarding tornado and high winds initiating event frequencies (IEFs) coupled with bounding assumptions for missile strike area to develop conservative estimates of core-damage frequency. This generic analysis assumes that plants are in a condition vulnerable to a tornado for a full reactor-year worth of exposure time.

For ISFSI handling operations, the vulnerable configuration would be typically limited to a few weeks of exposure time per year which would result in additional conservatism to the results documented in the NRR generic analysis. Furthermore, ISFSI handling operations that may lead to loss of confinement of radioactive material due to a missile strike or high winds should be bounded by the assumptions regarding tornado and high winds IEFs. Appropriate administrative controls including compensatory measures would provide defense-in-depth and further reduce the likelihood of occurrence and mitigate loss of confinement events. This defense-in-depth approach should include provisions to

(1) preclude ISFSI handling operations during periods of adverse weather or when adverse weather is predicted, and (2)provide compensatory measures to place important to safety SSCs in an analyzed condition or provide physical protection as necessary to maintain confinement of radioactive material during ISFSI handling operations.

In summary, the combination of the low probability of tornado events in conjunction with

formally documented administrative controls that

(1) restrict initiation of ISFSI handling operations during projected periods of adverse weather and,
(2) cease ISFSI handling operations and place important to safety SSCs in a protected configuration or analyzed condition at the outset of adverse weather conditions, form the basis for the exercise of enforcement discretion for ISFSI handling operations. As a further condition of this enforcement discretion, licensees will conduct a site-specific assessment to determine the appropriate corrective actions to ensure that important to safety SSCs will not be adversely impacted by tornado hazards. As such, the exercise of enforcement discretion limited to the conditions of this EGM will not impose significant additional risk to public health and safety.

Since this violation was identified during the discretion period covered by Enforcement Guidance Memorandum 22-001, Enforcement Discretion for Noncompliance of Tornado Hazard Protection requirements at Independent Spent Fuel Storage Installations, and because the licensee was implementing compensatory measures and has taken the necessary actions to restore compliance, the NRC is exercising enforcement discretion by not issuing an enforcement action for the violation and is allowing continued ISFSI handling operations.

Failure to Properly Pre-Plan and Perform Maintenance for Safety-Related 4160 Volt Siemens Vacuum Breakers Cornerstone Significance Cross-Cutting Aspect Report Section Mitigating Systems Green NCV 05000482/2023003-01 Open/Closed None (NPP)71111.12 The inspectors reviewed a self-revealed Green finding and associated non-cited violation of technical specification 5.4.1.a, for the licensees failure to properly pre-plan and perform maintenance that can affect performance of safety-related equipment. Specifically, the licensee failed to maintain Procedure MPE E009Q-03, Inspection and Testing of Siemens Vacuum Circuit Breakers, revision 11, to perform maintenance on safety-related 4160-volt Siemens breaker closing spring charging motor electrical motor terminal set screws to verify they were snug tight. This resulted in the failure to charge the closing spring of safety injection pump B breaker NB0202 following surveillance testing, rendering safety injection pump B inoperable for approximately 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br />.

Description:

On June 6, 2023, a licensee operator discovered the white indicating light demonstrating the closing spring is charged for the safety-related 4160-volt Siemens vacuum circuit breaker NB00202 was not lit. The operator replaced the bulb and determined the issue was not caused by a blown bulb. The licensee troubleshooting identified the charging spring motor electrical terminal set screws had loosened on breaker NB0202, preventing the spring charging motor from operating and recharging the closing spring following safety injection pump B surveillance testing. This condition prevented breaker NB0202 from closing and automatically starting safety injection pump B starting on a safety injection signal, rendering it inoperable for approximately 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br />. The licensees immediate corrective action was to tighten the terminal set screws and reconnect the associated wiring to restore NB0202 and safety injection pump B operability. The licensee entered this issue into their corrective action program and performed a performance assessment worksheet (PAW) and an equipment

performance evaluation (EPE). The licensee determined the cause of the event was due to an unsecure connection to the charging spring motor terminal connections. Specifically, the procedural guidance contained in Procedure MPE E009Q-03, Inspection and Testing of Siemens Vacuum Circuit Breakers, revision 11, did not have licensee personnel verify the charging spring motor terminal connections set screws were snug tight following maintenance activities.

The inspectors reviewed the PAW and EPE, vendor technical manual, procedure MPE E009Q-03 and concluded that the licensee failed to implement the vendors maintenance inspection checklist in procedure MPE E009Q-03. The vendor technical manuals maintenance section stated to check all terminal screws and check all screw connections and locking devices on mechanism parts. Procedure MPE E009Q-03 did not contain such instructions to verify component integrity. The inspectors did note that procedure MPE E009Q-03 contained a specific step to visually inspect torque seal on the mounting screws for the stationary auxiliary switch, which was implemented because of a failure of the essential service water pump A room supply fan to start in 1996. This failure was determined to be the result of loose mounting screws on the breaker NB0115 stationary auxiliary switch. A change was made to the procedure to add steps to check the stationary auxiliary switch mounting screws. However, the licensee did not expand the scope to include other mounting screws on similar breakers. The inspectors also identified NRC documentation with relevant information on integrity and maintenance of breaker internals. NRC Information Notice 87-41 Failures of Certain Brown Boveri Electric Circuit Breakers, outlined instances of circuit breakers that contained loose or missing charging motor mounting bolts. NRC Information Notice 2010-25 Inadequate Electrical Connections, noted operational experience that included failure to follow vendor-or industry-recommended torque requirements. Therefore, the inspectors concluded that the failure of NB0202 closing spring to recharge following safety injection pump B surveillance testing was foreseeable and could have been prevented by the licensee.

Corrective Actions: The license updated procedure MPE E009Q-03 to include verification of closing charging spring motor electrical motor terminal set screws.

Corrective Action References: Condition report 10025080

Performance Assessment:

Performance Deficiency: The licensees failure to properly pre-plan and perform maintenance to ensure safety-related 4160-volt Siemens breaker closing charging spring motor electrical motor terminal set screws were snug tight was a performance deficiency.

Screening: The inspectors determined the performance deficiency was more than minor because it was associated with the equipment performance attribute of the Mitigating Systems Cornerstone and adversely affected the cornerstone objective to ensure the availability, reliability, and capability of systems that respond to initiating events to prevent undesirable consequences. The inspectors determined the performance deficiency was more than minor because it was associated with the equipment performance attribute of the Mitigating Systems Cornerstone and adversely affected the cornerstone objective to ensure the availability, reliability, and capability of systems that respond to initiating events to prevent undesirable consequences. Specifically, the failure to properly pre-plan and perform maintenance for safety-related 4160-volt Siemens breaker resulted in rendering safety injection pump B inoperable for approximately 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br />.

Significance: The inspectors assessed the significance of the finding using IMC 0609 Appendix A, The Significance Determination Process (SDP) for Findings At-Power. The finding was determined to be of very low safety significance (Green) because it

(1) was not a deficiency affecting design or qualification of a mitigating system,
(2) does not represent a loss of the probability risk analysis (PRA) function of a single train technical specification system for greater than allowed outage time,
(3) does not represent a loss of PRA function of one train of a multi-train technical specification system for greater than its allowed outage time,
(4) does not represent a loss of the PRA function of two separate technical specification systems for greater than 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br />,
(5) does not represent a loss of PRA system and/or function as defined by the plant risk information e-book or the licensees PRA for greater than 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br />, and
(6) does not result in the loss of a high safety-significant, nontechnical specification train for greater than 3 days.

Cross-Cutting Aspect: Not Present Performance. No cross-cutting aspect was assigned to this finding because the inspectors determined the finding did not reflect present licensee performance.

Enforcement:

Violation: Technical specification 5.4.1.a, requires, in part, that written procedures be established, implemented, and maintained covering the applicable procedures in appendix A to Regulatory Guide 1.33. Appendix A, section 9.a, states, in part, that maintenance that can affect performance of safety-related equipment should be properly pre-planned and performed in accordance with written procedures, documented instructions, or drawings appropriate to the circumstances. The licensee established procedure MPE E009Q-03, Inspection and Testing of Siemens Vacuum Circuit Breakers, revision 11, to verify that screw connections are secure after maintenance activities associated with safety-related 4160 volt Siemens vacuum circuit breakers.

Contrary to above, until June 2023, the licensee failed to properly pre-plan and perform maintenance that can affect performance of safety-related equipment in accordance with written procedures, documented instructions, or drawings appropriate to the circumstances. Specifically, procedure MPE E009Q-03 revision 11, was not appropriate, in that it, did not verify that the 4160-volt Siemens breaker closing charging spring motor electrical terminal set screws were snug tight, resulting in the safety injection pump B being inoperable.

Enforcement Action: This violation is being treated as a non-cited violation, consistent with section 2.3.2 of the Enforcement Policy.

Inadvertent Entry into an Overhead High Radiation Area Cornerstone Significance Cross-Cutting Aspect Report Section Occupational Radiation Safety Green NCV 05000482/2023003-02 Open/Closed

[H.4] -

Teamwork 71124.01 The inspectors reviewed a self-revealed Green non-cited violation (NCV) of technical specification 5.4.1.a for the licensees inadvertent entry into an overhead high radiation area (HRA). A non-licensed operator (operator) went outside the briefed work scope and work path to walkdown/review access to a valve in the overhead (an HRA) leading to a dose rate alarm.

Description:

On October 30, 2022, an operator removing a clearance order received a dose rate alarm upon accessing an overhead area within the steam generator B/C secondary side platform in containment. The operator was trying to determine a safe way to reach an overhead valve and unknowingly entered an HRA. A radiological survey (M-20221030-3) was performed in the area of the dose rate alarm and identified a valve reading 450 millirem per hour (mR/hr) on contact and 260 mR/hr at 30 centimeters. The operators self-reading dosimeter had a dose rate set point of 200 mR/hr.

Procedure AP-25B-100, Radiation Worker Guidelines, revision 56A, step 5.3.9 required, in part, radiation workers contact radiation protection prior to accessing overhead areas.

Workers accessing platforms or plant ladders are not allowed to reach off into the overhead, they must remain within the boundaries of the ladder or platform.

The area where the operator accessed the valve had not been surveyed and was outside the briefed work location. The operator did not communicate a potential for accessing the overhead off the steam generator B/C secondary side platform when discussing the work scope and work path for removing the clearance order with radiation protection staff.

Corrective Actions: The licensee initiated corrective actions to restrict the operator from accessing the radiologically controlled area. Radiation protection and craft supervisors coached personnel involved on the requirements to access an overhead area and to clearly communicate the work scope and work path with radiation protection. The licensee performed a performance assessment worksheet (PAW 20036453) to identify associated human performance issues related to the incident.

Corrective Action References: The condition was entered into the corrective action program as condition report 10019497.

Performance Assessment:

Performance Deficiency: An inadvertent entry into an overhead HRA was a performance deficiency.

Screening: The inspectors determined the performance deficiency was more than minor because it was associated with the program & process attribute of the Occupational Radiation Safety Cornerstone and adversely affected the cornerstone objective to ensure the adequate protection of the worker health and safety from exposure to radiation from radioactive material during routine civilian nuclear reactor operation. Specifically, the failure to follow procedure requirements involving radiological controls had the potential to increase the workers dose. The failure to follow the procedural requirement to contact radiation protection prior to accessing an overhead area, which contained an HRA, led to a worker accessing an area 60 mR/hr greater than anticipated.

Significance: The inspectors assessed the significance of the finding using IMC 0609 Appendix C, Occupational Radiation Safety SDP. The finding was determined to be of very low safety significance (Green) because it was not:

(1) related to as low as is reasonably achievable (ALARA) planning,
(2) did not involve an overexposure,
(3) did not involve a substantial potential for overexposure, and
(4) the ability to assess dose was not compromised.

Cross-Cutting Aspect: H.4 - Teamwork: Individuals and work groups communicate and coordinate their activities within and across organizational boundaries to ensure nuclear

safety is maintained. Specifically, the communication between operator and radiation protection staff did not ensure a comprehensive understanding for the removal of the clearance order work scope and the areas needing to be accessed.

Enforcement:

Violation: Technical Specification 5.4.1.a, Procedures, required, in part, that written procedures shall be established, implemented, and maintained covering the applicable procedures recommended in NRC Regulatory Guide 1.33, revision 2, appendix A, February 1978. Appendix A, section 7.e.1 requires procedures for Access Control to Radiation Areas Including a Radiation Work Permit (RWP) System. The licensee established procedure AB 25B-100, Radiation Worker Guidelines, revision 56A, which in step 5.3.9, required workers to contact radiation protection prior to accessing overhead areas. Workers accessing platforms or plant ladders are not allowed to reach off into the overhead, they must remain within the boundaries of the ladder or platform.

Contrary to the above, on October 30, 2022, an operator did not contact radiation protection prior to accessing an overhead area beyond the boundaries of the steam generator B/C secondary side platform. The operator inadvertently entered an HRA in the overhead.

Enforcement Action: This violation is being treated as a non-cited violation, consistent with section 2.3.2 of the Enforcement Policy.

Licensee-Identified Non-Cited Violation 71124.01 This violation of very low safety significance was identified by the licensee and has been entered into the licensee corrective action program and is being treated as a non-cited violation, consistent with section 2.3.2 of the Enforcement Policy.

Violation: The licensee identified an improper entry into an HRA. Technical specification 5.7.1.d.4 stated, in part, entry into HRAs, with dose rates greater than 100 millirem per hour and not exceeding 1,000 millirem per hour at 30 centimeters from the radiation source or any surface penetrated by the radiation, required each individual or group entering such an area shall possess a self-reading dosimeter (e.g., pocket ionization chamber or electronic dosimeter). Contrary to the above, on June 28, 2022, an electrician entered the posted HRA of the independent spent fuel storage installation (survey M-20220629-8) without a self-reading dosimeter.

The licensee initiated corrective actions to

(1) promptly restrict the workers access to the radiologically controlled area until coaching from radiation protection and their supervision was completed,
(2) complete a performance assessment worksheet (PAW 20034880) to identify an associated human performance cause,
(3) provide a weekly observation coaching roll-up discussion to all maintenance groups, and
(4) discuss the issue during the directors morning kick-off meeting.

Significance/Severity: Green. The significance of the finding was assessed using IMC 0609, Appendix C, Occupational Radiation Safety SDP, and because the finding was not: (1)related to as low ALARA planning,

(2) did not involve an overexposure,
(3) did not involve a substantial potential for overexposure, and
(4) the ability to assess dose was not compromised, the finding was determined to be of very low safety significance (Green).

Corrective Action References: The condition was entered into the corrective action program as condition reports 10015652 and

EXIT MEETINGS AND DEBRIEFS

The inspectors verified no proprietary information was retained or documented in this report.

  • On September 13, 2023, the inspectors presented the triennial ISFSI loading inspection results to J. McCoy, Site Vice President, and other members of the licensee staff.
  • On September 25, 2023, the inspectors presented the occupational radiation safety inspection results to J. McCoy, Site Vice President, and other members of the licensee staff.
  • On October 2, 2023, the inspectors presented the integrated inspection results to M.

Boyce, Engineering Vice President, and other members of the licensee staff.

DOCUMENTS REVIEWED

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

60855

Miscellaneous

APF 26A-010-01

CFR 72.212 Evaluation Report Wolf Creek Generating

Station Dry Fuel Storage System for Spent Nuclear Fuel

Docket Number 72-1042

60855

Miscellaneous

CR 10025327

EGM 22-001, Enforcement Discretion for Noncompliance of

Tornado Hazards Protection Requirements at Independent

Spent Fuel Storage Installations, site response and

documentation.

08/28/2023

60855

Miscellaneous

K15-002-22-11-

ISFSI-Audit

ISFSI Program Audit Report

01/11/2023

60855

Miscellaneous

NUHOMS EOS

System Updated

Final Safety

Analysis Report

Docket Number 72-1042

60855

Procedures

AI 28A-010

Screening Condition Reports

60855

Procedures

AP 26A-009

CFR 72.48 Reviews

60855

Procedures

HTPT-DSC-

ORANO WOLF

CREEK

HIGH TEMPERATURE LIQUID PENETRANT (PT)

EXAMINATION USING THE COLOR CONTRAST

SOLVENT-REMOVABLE METHOD

6007-02

60855

Procedures

MSLT-DSC-

ORANO WOLF

CREEK

HELIUM MASS SPECTROMETER LEAK TEST

PROCEDURE DRY FUEL STORAGE CONTAINER

6007-01

60855

Procedures

PTIP 30501-

5.11B

EOS 37PTH Prep of the TC and DSC

60855

Procedures

PTIP 30501-

5.11C

EOS 37PTH TC Handling and Fuel Loading

60855

Procedures

PTIP 30501-

5.11D

DSC Insertion into HSM-MX

60855

Procedures

PTIP 30501-

5.11F

DSC Retraction into Transfer Cask

60855

Radiation

Surveys

RPF 02-210-01

Survey M-

220121-8

DFW-S13, Tech Spec Survey of HSM-MX Front Face, Lower

Compartment

01/21/2022

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

60855

Work Orders

WO 22-477380-

000

Preventative Maintenance - Spent Fuel Pool Bridge Crane

71111.04

Calculations

AN-07-009

GOTHIC Model for CCW Pump Room Temperature

71111.04

Calculations

EJ-M-018

Rate of Heat Up of RHR System in Recirculation Mode due

to Pump Heat with no CCW

71111.04

Calculations

GL-M-007

Calculate Cooling Load in SR Pump Rooms Post LOCA:

1107, 1108, 1109, 1110, 1111, 1112, 1113, 1114, 1401 &

1406

71111.04

Corrective Action

Documents

Condition Report

10012165

71111.04

Corrective Action

Documents

Resulting from

Inspection

Condition Report

10027276

71111.04

Drawings

M-12BG01

Piping & Instrumentation Diagram Chemical and Volume

Control System

71111.04

Drawings

M-12EG02

Piping and Instrumentation Diagram Component Cooling

Water System

71111.04

Drawings

M-12EJ01

Piping and Instrumentation Diagram Residual Heat Removal

System

71111.04

Drawings

M-12EM02

Piping & Instrumentation Diagram High Pressure Coolant

Injection System

71111.04

Drawings

M-12GL02

Piping and Instrumentation Diagram Auxiliary Building HVAC

71111.04

Drawings

M-13BG02

Piping Isometric CVCS-Max. Charging Flow A & B Train -

Auxiliary Bldg.

71111.04

Engineering

Changes

CCP 05927

Low Flow Cavitation Time Limit Exceeded on PEJ01A

71111.04

Miscellaneous

M-10GL

System Description Auxiliary Building Ventilation System

71111.04

Miscellaneous

M-721-00099

Instruction Manual for Residual Heat Removal Pump

W28

71111.04

Procedures

CKL BG-120

Chemical and Volume Control System Normal Valve Lineup

71111.04

Procedures

CKL EM-120

Safety Injection System Lineup Checklists

71111.04

Procedures

DB-EMG-ES-03

SI Termination

71111.04

Procedures

EMG E-0

Reactor Trip or Safety Injection

71111.04

Procedures

EMG E-1

Loss of Reactor or Secondary Coolant

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

71111.04

Procedures

EMG E-2

Faulted Steam Generator Isolation

24A

71111.04

Procedures

EMG E-3

Steam Generator Tube Rupture

71111.04

Procedures

EMG ES-03

SI Termination

71111.04

Procedures

STS EJ-100A

RHR System Inservice Pump A Test

71111.04

Procedures

SYS EJ-120

Startup of a Residual Heat Removal Train

71111.04

Procedures

SYS EJ-320

Placing RHR System in Safety Injection Standby Condition

71111.04

Work Orders

WO

2-477350-00

71111.05

Corrective Action

Documents

Condition Reports

10022531, 10024812, 10025040, 10025138, 10027144

71111.05

Miscellaneous

AP 10-106

Fire Preplans

71111.05

Miscellaneous

Breach

Authorization

Permit

17166, 17217

71111.05

Miscellaneous

E-1F9905

Fire Hazard Analysis

71111.05

Miscellaneous

Fire Impairment

Permit

2320, 12340, 12341, 16416, 16697, 17249

71111.05

Miscellaneous

WCRE-35

Boundary Matrix

71111.05

Procedures

AP 10-101

Control of Transient Ignition Sources

71111.05

Procedures

AP 10-103

Fire Protection Impairment Control

40A

71111.05

Procedures

AP 10-104

Breach Authorization

71111.05

Procedures

AP 22C-003

On-Line Nuclear Safety and Generation Risk Assessment

71111.05

Procedures

OFN RP-017

Control Room Evacuation

71111.05

Procedures

STN FP-440

Fire Door Visual Inspection

71111.05

Procedures

STN FP-817A

Trip Act. Device Oper. Test for Bechtel Zones 100, 103, 104,

105, 106, 107, 112, 113, and 114

11C

71111.05

Work Orders

WO

23-146042-000, 23-486877-000, 23-486877-001

71111.11Q

Miscellaneous

CPE #3 FR-H1

Exercise Summary

71111.11Q

Procedures

STN SF-001

Control Rod Parking

71111.11Q

Procedures

STS BG-100B

Centrifugal Charging System B Train Inservice Pump Test

56A

71111.11Q

Procedures

STS SF-001

Control and Shutdown Rod Operability Verification

71111.12

Calculations

JE-M-003

Emergency Fuel Oil Storage Tanks Access Vaults Minimum

Temperature

71111.12

Corrective Action

Condition Reports

10010613, 10011637, 10014687, 10021301, 10023115,

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Documents

10023358, 10023490, 10023690, 10024714, 10025080,

10025661, 10025714, 10025758, 10026147, 10026684,

10025470, 10025950, 10026106, 10027058, 10017625,

10027129, 10027136, 10027148

71111.12

Corrective Action

Documents

Resulting from

Inspection

Condition Reports

10023622, 10027120, 10027313, 10027402

71111.12

Drawings

E-11NG20

Low Voltage System Class 1E Motor Control Center

Summary

317

71111.12

Drawings

E-13GK35A

Schematic Diagram SGK05 Recirculation Air Flow Fans and

Dampers

71111.12

Drawings

E-13GK35B

Schematic Diagram SGK05 Recirculation Air Flow Fans and

Dampers

71111.12

Drawings

E-13GK35C

Schematic Diagram SGK05 Recirculation Air Flow Fans and

Dampers

71111.12

Drawings

E-13GL05

Schematic Diagram Pump Room Coolers

71111.12

Drawings

KD-7496

One Line Diagram

71111.12

Miscellaneous

Equipment Performance Evaluation - C071 - NB0202

breaker found not charged

71111.12

Miscellaneous

E-009B-00009

Instruction Manual for Siemens Type 3AF-GER Vertical Lift

Direct Replacement Vacuum Circuit Breakers

W06

71111.12

Miscellaneous

E-018-00190

Instruction Manual for Motor Control Centers

W41

71111.12

Miscellaneous

E-018-01029

Instruction Manual for Safety Related 5600 Series Motor

Control Center Cubicles

W01

71111.12

Miscellaneous

M-022-00001

Station Blackout Diesel Generator Kohler Instruction Manual

W03

71111.12

Miscellaneous

M-022-00002

Kohler Station Blackout Diesel Generator

W04

71111.12

Miscellaneous

M-022-00018

Station Blackout Diesel Operations and Maintenance Manual

W01

71111.12

Miscellaneous

RER No.

20038974

Reportability Determination for NB0202 SI Pump B breaker

found not charged

71111.12

Procedures

23M-001

WCGS Maintenance Rule Program

71111.12

Procedures

AI 23O-001

Functional Importance Determination

7A

71111.12

Procedures

AP 02-003

Chemistry Specification Manual

71111.12

Procedures

AP 23L-002

Heat Exchanger Program

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

71111.12

Procedures

EDI 23M-020

Engineering Desktop Instruction Determining the Safety

Significance of Structures, Systems, and Components within

the Scope of Maintenance Rule

71111.12

Procedures

MGE EOOP-11

Molded Case Circuit Breaker and Ground Fault Sensor

Testing

71111.12

Procedures

MGE LT-001

Wiring Termination and Lug/Connector Installation

26B

71111.12

Procedures

MPE E009Q-03

Inspection and Testing of Siemens Vacuum Circuit Breakers

71111.12

Procedures

MPM OS-001

Preventive Maintenance Lubricant Sampling and

Replenishment

27A

71111.12

Procedures

STN KU-010

Station Blackout Diesel and Non-Safety AFW Pump Test

71111.12

Procedures

STN NB-001B

B Train Breaker Operability and ECCS Pump Recirc

71111.12

Procedures

SYS GK-201

Mitigating Actions for Inoperable SGK05 Train

71111.12

Work Orders

WO 6006, 7366, 17-431704-000, 20-467159-000, 21-475640-

001, 21-475640-002, 21-475640-010, 21-476112-000, 22-

2572-000, 22-483529-000

71111.13

Corrective Action

Documents

Condition Reports

10024348, 10025470

71111.13

Drawings

E-13GL05

Schematic Diagram Pump Room Coolers

71111.13

Procedures

AI 22C-013

Protected Equipment Program

71111.13

Procedures

EMG C-0

Loss of All AC Power

45A

71111.13

Procedures

OFN NB-030

Loss of AC Emergency Bus NB01(NB02)

71111.13

Procedures

SYS NB-201

Transferring NB01 Power Sources

71111.13

Procedures

SYS NB-202

Transferring NB02 Power Sources

71111.13

Work Orders

WO 7366

71111.15

Calculations

AN-07-009

GOTHIC Model for CCW Pump Room Temperature

71111.15

Calculations

EF-M-046

UHS Analysis with Initial Lake Temperature Up to 94

degrees F

71111.15

Calculations

GL-M-007

Calculate Cooling Load in SR Pump Rooms Post LOCA:

1107, 1108, 1109, 1110, 1111, 1112, 1113, 1114, 1401 and

1406

71111.15

Corrective Action

Documents

Condition Reports

10017591, 10020251, 10021303, 10023022, 10024802,

10025246, 10025470, 10025366, 10025491, 10025950,

10025664, 10026106, 10026286

71111.15

Drawings

E-13GK02D

Schematic Diagram Control Room A/C Unit Fan Control

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

71111.15

Procedures

AP 10-106

Fire Preplans

71111.15

Procedures

AP 26C-004

Operability Determinations and Functionality Assessments

71111.15

Procedures

AP 28-007

Nonconformance Control

10A

71111.15

Procedures

AP 28-011

Resolving Degraded or Nonconforming Conditions Impacting

SSCS

71111.15

Procedures

AP 28A-100

Corrective Action Program

71111.15

Procedures

EMG E-0

Reactor Trip of Safety Injection

71111.15

Procedures

STN PE-037B

ESW Train B Heat Exchanger Flow and DP Trending

71111.15

Work Orders

WO

2-354664-000, 13-380154-007, 13-380154-010,

2-478811-000, 22-480069-000, 22-480994-000,

2-483479-000, 22-483480-002, 22-483530-000

71111.24

Calculations

EG-M-046

Hydraulic Analysis of the Component Cooling Water System

for Break Flow Determination and Orifice Sizing

71111.24

Corrective Action

Documents

Condition Reports

10021612, 10024045, 10025470, 10025491, 10026957,

10027028, 10027036, 10027040, 10027313

71111.24

Corrective Action

Documents

Resulting from

Inspection

Condition Reports

10026921, 10026959, 10027243

71111.24

Drawings

M-11EG01

System Flow Diagram Component Cooling Water

71111.24

Drawings

M-12EG01

Piping and Instrumentation Diagram Component Cooling

Water System

71111.24

Drawings

M-12EJ01

Piping and Instrumentation Diagram Residual Heat Removal

System

71111.24

Miscellaneous

WCOP-02

Inservice Testing Program for Pumps, Valves, and Snubbers

71111.24

Miscellaneous

WCRE-34

Fourth 10-Year Interval Inservice Testing Basis Document

71111.24

Procedures

AI 16C-007

Work Activity Planning

71111.24

Procedures

AP 16E-002

Post Maintenance Testing Development

21A, 21B

71111.24

Procedures

MPE FU-001

Fan Unit Maintenance

23A

71111.24

Procedures

STN AL-201

Auxiliary Feedwater System Valve Test

71111.24

Procedures

STN EM-201

Safety Injection System Valve Test

71111.24

Procedures

STN IC-252A

Calibration of RHR Pump A Mini Flow Valve Control Switch

8, 9

71111.24

Procedures

STN IC-252B

Calibration of RHR Pump B Mini Flow Valve Control Switch

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

71111.24

Procedures

STN KU-010

Station Blackout Diesel and Non-Safety AFW Pump Test

71111.24

Procedures

STS AL-102

MDAFW Pump B Inservice Pump Test

71111.24

Procedures

STS EG-100A

Component Cooling Water Pumps A/C Inservice Pump

Testing

34A

71111.24

Procedures

STS EG-100B

Component Cooling Water Pumps B/D Inservice Pump Test

30A

71111.24

Procedures

STS EM-100A

Safety Injection Pump A Inservice Pump Test

43A

71111.24

Procedures

STS PE-007

Periodic Verification of Motor Operated Valves

5A

71111.24

Procedures

SYS NK-131

Energizing NK Buses

71111.24

Work Orders

WO 13756, 13842, 17834, 7366, 16174, 17881, 19656,

15-408903-000, 17-427655-000, 18-445220-000,

20-460700-000, 21-468539-001, 21-468539-002,

21-475429-000, 22-480871-001, 22-481396-000,

2-482075-000, 22-482572-000, 22-483164-000,

2-483227-000, 22-483480-000, 22-483480-002,

2-484295-000, 23-483704-000, 23-484286-000,

23-484293-001, 23-485052-001, 23-485053-000,

23-485057-000, 23-486959-001, 23-486959-002,

23-487205-000, 23-488246-000, 23-488248-000

71114.06

Corrective Action

Documents

Condition Reports

10026590, 10026838

71124.01

Corrective Action

Documents

Condition Reports 10010214, 10012071, 10014238, 10014482, 10015213,

10015213, 10015652, 10015653, 10015653, 10016703,

10017250, 10017940, 10018714, 10018748, 10018831,

10019497, 10019533, 10019805, 10019923, 10020039,

10020144, 10020160, 10020527, 10021452, 10021471,

10021474, 10022101, 10022981, 10023240, 10026863

71124.01

Procedures

AP 25A-200

Access to Locked High or Very High Radiation Areas

29A

71124.01

Procedures

RPP 02-105

Radiation Work Permit (RWP)

71124.01

Procedures

RPP 02-205

Radiological Survey Frequency Requirements

71124.01

Procedures

RPP 02-210

Radiation Survey Methods

71124.01

Procedures

RPP 02-215

Posting of Radiological Controlled Areas

71124.01

Procedures

RPP 02-405

Radiologically Controlled Area Access Control

71124.01

Radiation

Surveys

M-20220519-3

Independent Spent Fuel Storage Installation pad RA down

post

05/19/2022

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

71124.01

Radiation

Surveys

M-20220606-3

Independent Spent Fuel Storage Installation pad area HRA

down post

06/06/2022

71124.01

Radiation

Surveys

M-20220620-5

Digging dirt and asphalt for Electrical box

06/20/2022

71124.01

Radiation

Surveys

M-20220628-2

Follow up survey for Entry into HRA with no dosimetry

06/28/2022

71124.01

Radiation

Surveys

M-20221018-42

2000' CTMT 'D' Loop, BB8949D Dose rate alarm follow up

10/18/2022

71124.01

Radiation

Surveys

M-20221030-29

CTMT 2068 dose alarm follow up

10/30/2022

71124.01

Radiation

Surveys

M-20221030-3

CTMT B/C Secondary follow up for dose rate alarm

10/30/2022

71124.01

Radiation

Surveys

M-20221109-5

Follow up survey for unsupported job, post Decon

11/09/2022

71124.01

Radiation

Surveys

M-20230905-10

DFS - S1, Transport of the loaded DSC #2/TC from CLP to

CWP

09/05/2023

71124.01

Radiation

Surveys

M-20230906-4

DFS, DSC #2 Post Blowdown/Dewatering Survey

09/06/2023

71124.01

Radiation

Surveys

M-20230908-9

DFS - S17 HSM-MX Roof Vents for DSC #2 in HSM 6

position

09/08/2023

71124.01

Radiation Work

Permits (RWPs)

RWP 220010

General Access to HRA.

71124.01

Radiation Work

Permits (RWPs)

RWP 221001

Operations Department RWP for pre-outage and outage

activities. RWP provides RCA access

for other support personnel working for Operations. RWP to

be used for RCA walk downs,

inspections, surveillances, valve line-ups, gauge hook-ups,

system venting & draining, and waste

processing activities.

71124.01

Radiation Work

Permits (RWPs)

RWP 222600

Routine Outage Access (No High Radiation Areas Access).

RWP provides access for escorting

visitors, Security rounds, work groups without a department

RWP, or access for work approved by

Radiation Protection for this RWP.

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

71124.01

Radiation Work

Permits (RWPs)

RWP 224461

Motor Operated Valve (MOV) Team activities. This RWP

includes valve operator and internals

work activities, inspection, repair, maintenance, boron

removal, valve adjustments, valve repacking,

valve internals overhaul, valve operator overhaul, and

diagnostic testing.

71124.01

Radiation Work

Permits (RWPs)

RWP 226020

Reactor Vessel Head Lift Preparation and Post Head Set

Work Activities

71124.01

Self-Assessments

NRC Inspection Procedures 71124.01, Radiological Hazard

Assessment

71124.01

Self-Assessments CR 10013108

Self-Assessment for NRC Inspection 71124 Attachment 04

71124.04

Corrective Action

Documents

Condition Reports

10021371, 10021376, 10021398, 10022464, 10022476,

10022483, 10023126, 10023981

71124.04

Miscellaneous

25% Variance External Exposure Review for nine employees

71124.04

Miscellaneous

5-Year ALARA Dose Reduction Plan: 2023 - 2028

07/31/2023

71124.04

Miscellaneous

Audit Report

  1. 25286

Wolf Creek Augmented Quality Audit of Landauer Inc.

2/06/2021

71124.04

Procedures

RPP 03-210

Internal Exposure Calculations and Evaluations

17D

71124.04

Procedures

RPP 03-406

RP Dosimetry/Records

71124.04

Radiation

Surveys

M-20230909-3

HSM-MX Front Face, Upper Compartment-Independent

Spent Fuel Storage Installation

09/08/2023

71151

Corrective Action

Documents

Condition Report

10014238

71151

Miscellaneous

22 Wolf Creek Generating Station (WCGS) Annual

Radioactive Effluent Release Report

04/27/2023

71151

Miscellaneous

Cumulative Doses and Projected Doses - Quarterly /Yearly

Surveillance - January - February 16, 2023

2/20/2023

71151

Miscellaneous

Cumulative Doses and Projected Doses - Quarterly /Yearly

Surveillance - January 1-January 16, 2023

01/17/2023

71151

Miscellaneous

Cumulative Doses and Projected Doses - Quarterly /Yearly

Surveillance - January 1 - April 17, 2023

04/24/2023

71151

Miscellaneous

Cumulative Doses and Projected Doses - Quarterly /Yearly

Surveillance - January 1 - March 15, 2023

03/15/2023

71151

Miscellaneous

Cumulative Doses and Projected Doses - Quarterly /Yearly

06/19/2023

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Surveillance - January 1-June 15, 2023

71151

Miscellaneous

STN CH-024

Cumulative Doses and Projected Doses - Quarterly /Yearly

Surveillance - January - July 17, 2023

07/18/2023

71152A

Corrective Action

Documents

Condition Reports

236, 75795, 75821, 81790, 81818, 10008050, 10023423,

10023559, 10024686, 10025432

71152A

Drawings

M-12AL01

Piping and Instrumentation Diagram Auxiliary Feedwater

System

71152A

Miscellaneous

23-Pre-Ex-01

Emergency Planning Drill

09/11/2023

71152A

Miscellaneous

E-025-00003

Limitorque Design Information

W13

71152A

Miscellaneous

WCRE-34

Fourth 10-Year Interval Inservice Testing Basis Document

71152A

Procedures

AI 28A-100

Condition Report Resolution

71152A

Procedures

AP 23D-001

Motor Operated Valve Program

4A

71152A

Procedures

AP 28-011

Resolving Degraded or Nonconforming Conditions Impacts

SSCS

71152A

Procedures

AP 28A-100

Corrective Action Program

71152A

Procedures

EMG E-0

Reactor Trip or Safety Injection

71152A

Procedures

EMG FR-H1

Response to Loss of Secondary Heat Sink

71152A

Procedures

MGE LT-001

Torque Switch Balancing

7B

71152A

Procedures

MGE LT-098

Limitorque Geared Limit Switch Overhaul

71152A

Procedures

OFN MA-001

Load Rejection or Turbine Trip

27