IR 05000333/2018002: Difference between revisions

From kanterella
Jump to navigation Jump to search
(Created page by program invented by StriderTol)
(StriderTol Bot change)
 
(8 intermediate revisions by the same user not shown)
Line 5: Line 5:
| author name = Dimitriadis A
| author name = Dimitriadis A
| author affiliation = NRC/RGN-I/DRP/PB5
| author affiliation = NRC/RGN-I/DRP/PB5
| addressee name = Hanson B C
| addressee name = Hanson B
| addressee affiliation = Exelon Generation Co, LLC, Exelon Nuclear
| addressee affiliation = Exelon Generation Co, LLC, Exelon Nuclear
| docket = 05000333
| docket = 05000333
Line 18: Line 18:


=Text=
=Text=
{{#Wiki_filter:
{{#Wiki_filter:August 6, 2018
[[Issue date::August 6, 2018]]


Mr. Bryan Senior Vice President, Exelon Generation Company, LLC President and Chief Nuclear Officer, Exelon Nuclear 4300 Winfield Road Warrenville, IL 60555
==SUBJECT:==
 
JAMES A. FITZPATRICK NUCLEAR POWER PLANT - INTEGRATED INSPECTION REPORT 05000333/2018002
SUBJECT: JAMES A. FITZPATRICK NUCLEAR POWER PLANT - INTEGRATED INSPECTION REPORT 05000333/2018002


==Dear Mr. Hanson:==
==Dear Mr. Hanson:==
On June 30, 2018, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at the James A. FitzPatrick Nuclear Power Plant (FitzPatrick). On July 18, 2018, the NRC inspectors discussed the results of this inspection with Mr. Timothy Peter, Plant Manager, and other members of your staff. The results of this inspection are documented in the enclosed report.
On June 30, 2018, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at the James A. FitzPatrick Nuclear Power Plant (FitzPatrick). On July 18, 2018, the NRC inspectors discussed the results of this inspection with Mr. Timothy Peter, Plant Manager, and other members of your staff. The results of this inspection are documented in the enclosed report.


No NRC-identified or self-revealing findings were identified during this inspection. NRC inspectors documented one licensee-identified violation which was determined to be of very low safety significance in this report. The NRC is tr eating this violation as a non-cited violation (NCV) consistent with Section 2.3.2.a of the Enforcement Policy.
No NRC-identified or self-revealing findings were identified during this inspection. NRC inspectors documented one licensee-identified violation which was determined to be of very low safety significance in this report. The NRC is treating this violation as a non-cited violation (NCV) consistent with Section 2.3.2.a of the Enforcement Policy.


If you contest the violation or significance of this NCV, you should provide a response within 30 days of the date of this inspection report, with the basis for your denial, to the U.S. Nuclear Regulatory Commission, ATTN: Document Control Desk, Washington, DC 20555-0001; with copies to the Regional Administrator, Region I; the Director, Office of Enforcement; and the NRC Resident Inspector at FitzPatrick. This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and the NRC Public Document Room in accordance with Title 10 of the Code of Federal Regulations (10 CFR), Part 2.390, "Public Inspections, Exemptions, Requests for Withholding."
If you contest the violation or significance of this NCV, you should provide a response within 30 days of the date of this inspection report, with the basis for your denial, to the U.S. Nuclear Regulatory Commission, ATTN: Document Control Desk, Washington, DC 20555-0001; with copies to the Regional Administrator, Region I; the Director, Office of Enforcement; and the NRC Resident Inspector at FitzPatrick. This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and the NRC Public Document Room in accordance with Title 10 of the Code of Federal Regulations (10 CFR), Part 2.390, Public Inspections, Exemptions, Requests for Withholding.


Sincerely,
Sincerely,
/RA/ Anthony Dimitriadis, Chief Reactor Projects Branch 5  
/RA/  
 
Anthony Dimitriadis, Chief Reactor Projects Branch 5 Division of Reactor Projects
 
Docket Number: 50-333 License Number: DPR-59


Division of Reactor Projects Docket Number: 50-333 License Number: DPR-59
===Enclosure:===
Inspection Report 05000333/2018002


Enclosure:
==Inspection Report==
Inspection Report 05000333/2018002 cc w/encl: Distribution via ListServ
Docket Number:
50-333


ML18218A120 SUNSI Review Non-Sensitive Sensitive Publicly Available Non-Publicly Available OFFICE RI/DRP RI/DRP RI/DRP NAME GStock via email MCatts via email ADimitriadis DATE 8/3/18 8/2/18 8/6/18
License Number:
DPR-59


1 Enclosure U.S. NUCLEAR REGULATORY COMMISSION
Report Number:
05000333/2018002


==Inspection Report==
Enterprise Identifier: I-2018-002-0058
 
Licensee:
Exelon Generation Company, LLC (Exelon)
 
Facility:
James A. FitzPatrick Nuclear Power Plant
 
Location:
Scriba, NY
 
Inspection Dates:
April 1, 2018 to June 30, 2018
 
Inspectors:
K. Kolaczyk, Senior Resident Inspector
 
S. Ghrayeb, Resident Inspector


Docket Number: 50-333
G. Stock, Resident Inspector


License Number: DPR-59
T. Dunn, Operations Engineer


Report Number: 05000333/2018002
B. Fuller, Senior Operations Engineer


Enterprise Identifier: I-2018-002-0058
J. Furia, Senior Health Physicist


Licensee: Exelon Generation Company, LLC (Exelon)
M. Hardgrove, Projects Engineer


Facility: James A. FitzPatrick Nuclear Power Plant
C. Hobbs, Reactor Inspector


Location: Scriba, NY
J. Schoppy, Senior Reactor Inspector


Inspection Dates: April 1, 2018 to June 30, 2018
Approved By:
Anthony Dimitriadis, Chief


Inspectors: K. Kolaczyk, Senior Resident Inspector S. Ghrayeb, Resident Inspector G. Stock, Resident Inspector T. Dunn, Operations Engineer B. Fuller, Senior Operations Engineer J. Furia, Senior Health Physicist M. Hardgrove, Projects Engineer C. Hobbs, Reactor Inspector J. Schoppy, Senior Reactor Inspector Approved By: Anthony Dimitriadis, Chief Reactor Projects Branch 5 Division of Reactor Projects
Reactor Projects Branch 5  


2
Division of Reactor Projects


=SUMMARY=
=SUMMARY=
The U.S. Nuclear Regulatory Commission (NRC) continued monitoring Exelon's performance at FitzPatrick by conducting the baseline inspections described in this report in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRC's program for overseeing the safe operation of commercial nuclear power reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information. A licensee-identified non-cited violation (NCV) is documented in the Inspection Results section of the report.
The U.S. Nuclear Regulatory Commission (NRC) continued monitoring Exelons performance at  


3
FitzPatrick by conducting the baseline inspections described in this report in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for overseeing the safe operation of commercial nuclear power reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information. A licensee-identified non-cited violation (NCV) is documented in the Inspection Results section of the report.


=PLANT STATUS=
=PLANT STATUS=
FitzPatrick began the inspection period at rated thermal power. On May 14, 2018, the unit was down powered to 45 percent power to remove the 'A' recirculation pump from service for a motor-generator set motor replacement. The unit was returned to rated thermal power on May 24, 2018. On June 1, 2018, the unit was down-powered to 65 percent power for planned control rod pattern adjustment, main steam isolation valve testing, and turbine valve testing.
 
FitzPatrick began the inspection period at rated thermal power. On May 14, 2018, the unit was down powered to 45 percent power to remove the A recirculation pump from service for a motor-generator set motor replacement. The unit was returned to rated thermal power on May 24, 2018. On June 1, 2018, the unit was down-powered to 65 percent power for planned control rod pattern adjustment, main steam isolation valve testing, and turbine valve testing.


The unit was returned to rated thermal power on June 3, 2018. On June 22, 2018, the unit was down-powered to 70 percent power for a planned control rod pattern adjustment and condenser backwashing. The unit was returned to rated thermal power on June 23, 2018, and remained at or near rated thermal power for the remainder of the inspection period.
The unit was returned to rated thermal power on June 3, 2018. On June 22, 2018, the unit was down-powered to 70 percent power for a planned control rod pattern adjustment and condenser backwashing. The unit was returned to rated thermal power on June 23, 2018, and remained at or near rated thermal power for the remainder of the inspection period.


==INSPECTION SCOPES==
==INSPECTION SCOPES==
Inspections were conducted using the appropriate portions of the inspection procedures (IPs) in effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with their attached revision histories are located on the public website at http://www.nrc.gov/reading-rm/doc-collections/insp-manual/inspection-procedure/index.html. Samples were declared complete when the IP requirements most appropriate to the inspection activity were met consistent with Inspection Manual Chapter (IMC) 2515, "Light-Water Reactor Inspection Program - Operations Phase.The inspectors performed plant status activities described in IMC 2515, Appendix D, "Plant Status," and conducted routine reviews using IP 71152, "Problem Identification and Resolution.The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel to assess Exelon's performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards.
Inspections were conducted using the appropriate portions of the inspection procedures (IPs) in effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with their attached revision histories are located on the public website at http://www.nrc.gov/reading-rm/doc-collections/insp-manual/inspection-procedure/index.html. Samples were declared complete when the IP requirements most appropriate to the inspection activity were met consistent with Inspection Manual Chapter (IMC) 2515, Light-Water Reactor Inspection Program - Operations Phase. The inspectors performed plant status activities described in IMC 2515, Appendix D, Plant Status, and conducted routine reviews using IP 71152, Problem Identification and Resolution. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel to assess Exelons performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards.


==REACTOR SAFETY==
==REACTOR SAFETY==
==71111.01 - Adverse Weather Protection==
==71111.01 - Adverse Weather Protection==
===Summer Readiness (1 Sample)===
===Summer Readiness (1 Sample)===
The inspectors evaluated summer readiness of offsite and alternating current (AC) power systems on June 29, 2018.
The inspectors evaluated summer readiness of offsite and alternating current (AC) power systems on June 29, 2018.


==71111.04 - Equipment Alignment==
==71111.04 - Equipment Alignment==
===Partial Walkdowns (3 Samples)===
===Partial Walkdowns (3 Samples)===
The inspectors evaluated system configurations during partial walkdowns of the following systems:
The inspectors evaluated system configurations during partial walkdowns of the following systems:
: (1) 'A' and 'B' standby liquid control systems on April 17, 2018
: (1) A and B standby liquid control systems on April 17, 2018
: (2) Offsite AC distribution system on April 19, 2018
: (2) Offsite AC distribution system on April 19, 2018
: (3) High pressure coolant injection system on May 16, 2018
: (3) High pressure coolant injection system on May 16, 2018


==71111.05A/Q - Fire Protection Annual/Quarterly==
==71111.05A/Q - Fire Protection Annual/Quarterly==
===Quarterly Inspection (4 Samples)===
===Quarterly Inspection (4 Samples)===
 
The inspectors evaluated fire protection program implementation in the following selected areas:
The inspectors evaluated fire protection program implementation in the following selected  
 
areas:
: (1) Technical support center computer rooms, fire zone AD-3 on April 10, 2018
: (1) Technical support center computer rooms, fire zone AD-3 on April 10, 2018
: (2) Independent spent fuel installation pad, fire area yard on April 12, 2018
: (2) Independent spent fuel installation pad, fire area yard on April 12, 2018
: (3) Condensate storage tank vault, fire zone CST-V on April 23, 2018
: (3) Condensate storage tank vault, fire zone CST-V on April 23, 2018
: (4) Motor generator set room/elevation 300', fire area MG-1 on April 23, 2018 Annual Inspection (1 Sample)
: (4) Motor generator set room/elevation 300, fire area MG-1 on April 23, 2018  


The inspectors evaluated a fire drill at 272' turbine building south on June 5, 2018.
===Annual Inspection (1 Sample)===
The inspectors evaluated a fire drill at 272 turbine building south on June 5, 2018.


==71111.06 - Flood Protection Measures==
==71111.06 - Flood Protection Measures==
===Internal Flooding (1 Sample)===
===Internal Flooding (1 Sample)===
The inspectors evaluated leaking fire protection piping in east pipe tunnel on May 24, 2018.
The inspectors evaluated leaking fire protection piping in east pipe tunnel on May 24, 2018.


==71111.07 - Heat Sink Performance==
==71111.07 - Heat Sink Performance==
===Heat Sink (1 Sample)===
===Heat Sink (1 Sample)===
 
The inspectors evaluated the C reactor building closed loop cooling (RBCLC) heat exchanger retube on June 22, 2018.
The inspectors evaluated the 'C' reactor building closed loop cooling (RBCLC) heat exchanger retube on June 22, 2018.


===Heat Sink (Triennial) (3 Samples)===
===Heat Sink (Triennial) (3 Samples)===
The inspectors evaluated heat exchanger/heat sink performance on the following structures, systems, and components:
The inspectors evaluated heat exchanger/heat sink performance on the following structures, systems, and components:
: (1) 'C' emergency diesel generator (EDG) jacket water heat exchanger (93WE-1C), Section 02.02b
: (1) C emergency diesel generator (EDG) jacket water heat exchanger (93WE-1C),
Section 02.02b
: (2) East cable tunnel/emergency switchgear room cooler (67E-14), Section 02.02b
: (2) East cable tunnel/emergency switchgear room cooler (67E-14), Section 02.02b
: (3) One ultimate heat sink sample (associated with service water system operation and intake structure condition), Sections 02.02d.4 and 02.02d.7, respectively
: (3) One ultimate heat sink sample (associated with service water system operation and intake structure condition), Sections 02.02d.4 and 02.02d.7, respectively


==71111.11 - Licensed Operator Requalification Program and Licensed Operator Performance==
==71111.11 - Licensed Operator Requalification Program and Licensed Operator Performance==
===Operator Requalification (1 Sample)===
===Operator Requalification (1 Sample)===
The inspectors observed flexible mitigating strategies training on April 13, 2018.
The inspectors observed flexible mitigating strategies training on April 13, 2018.


===Operator Performance (1 Sample)===
===Operator Performance (1 Sample)===
 
The inspectors observed and evaluated A reactor water recirculation pump start and power ascension following generator replacement on May 19, 2018.
The inspectors observed and evaluated 'A' reactor water recirculation pump start and power ascension following generator replacement on May 19, 2018.


===Operator Requalification Exam Results (Annual) (1 Sample)===
===Operator Requalification Exam Results (Annual) (1 Sample)===
Line 139: Line 153:


===Operator Requalification Program and Operator Performance (Biennial) (1 Sample)===
===Operator Requalification Program and Operator Performance (Biennial) (1 Sample)===
The inspectors reviewed and evaluated operator, evaluator, and simulator performance during requalification examinations completed on March 22, 2018.
The inspectors reviewed and evaluated operator, evaluator, and simulator performance during requalification examinations completed on March 22, 2018.


==71111.12 - Maintenance Effectiveness==
==71111.12 - Maintenance Effectiveness==
 
===Routine Maintenance Effectiveness (1 Sample)===
Routine Maintenance Effectiveness (1 Sample)
The inspectors evaluated the effectiveness of routine maintenance activities associated with the following equipment and/or safety significant functions:
The inspectors evaluated the effectiveness of routine maintenance activities associated with the following equipment and/or safety significant functions:
: (1) Structural monitoring program diesel building and cable tunnel roof on April 11, 2018  
: (1) Structural monitoring program diesel building and cable tunnel roof on April 11, 2018  


===Quality Control (1 Sample)===
===Quality Control (1 Sample)===
The inspectors evaluated maintenance and quality control activities associated with the following equipment performance issues:
The inspectors evaluated maintenance and quality control activities associated with the following equipment performance issues:
: (1) Unit cooler water box gasket
: (1) Unit cooler water box gasket
Line 159: Line 170:


The inspectors evaluated the risk assessments for the following planned and emergent work activities:
The inspectors evaluated the risk assessments for the following planned and emergent work activities:
: (1) 'B' residual heat removal (RHR) maintenance on April 4, 2018
: (1) B residual heat removal (RHR) maintenance on April 4, 2018
: (2) Line 3 outage on April 11, 2018
: (2) Line 3 outage on April 11, 2018
: (3) 'A' containment air dilution system planned maintenance on April 16, 2018
: (3) A containment air dilution system planned maintenance on April 16, 2018
: (4) 'A' recirculation generator heavy lift on May 15, 2018
: (4) A recirculation generator heavy lift on May 15, 2018
: (5) 'A' core spray maintenance and operability test June 13, 2018
: (5) A core spray maintenance and operability test June 13, 2018


==71111.15 - Operability Determinations and Functionality Assessments==
==71111.15 - Operability Determinations and Functionality Assessments==
Line 184: Line 195:


The inspectors evaluated post maintenance testing for the following maintenance/repair activities:
The inspectors evaluated post maintenance testing for the following maintenance/repair activities:
: (1) ST-2AM, 'B' RHR quarterly operability testing on April 5, 2018
: (1) ST-2AM, B RHR quarterly operability testing on April 5, 2018
: (2) 'A' reactor recirculation pump generator replacement on May 19, 2018
: (2) A reactor recirculation pump generator replacement on May 19, 2018
: (3) 76P-1, West diesel fire pump testing on June 8, 2018
: (3) 76P-1, West diesel fire pump testing on June 8, 2018
: (4) 'A' core spray system operability testing on June 13, 2018
: (4) A core spray system operability testing on June 13, 2018
: (5) 'C' EDG circulating oil pump maintenance on June 20, 2018
: (5) C EDG circulating oil pump maintenance on June 20, 2018
: (6) 'B' standby gas treatment system motor replacement on June 27, 2018
: (6) B standby gas treatment system motor replacement on June 27, 2018


==71111.20 - Refueling and Other Outage Activities==
==71111.20 - Refueling and Other Outage Activities==
The inspectors evaluated new fuel receipt inspection activities on June 26, 2018.
The inspectors evaluated new fuel receipt inspection activities on June 26, 2018.


==71111.22 - Surveillance Testing==
==71111.22 - Surveillance Testing==
The inspectors evaluated the following surveillance tests:  
The inspectors evaluated the following surveillance tests:  


===Routine (3 Samples)===
===Routine===
{{IP sample|IP=IP 71111.22|count=3}}
: (1) ST-9R, EDG System Quick-Start Operability Test and Offsite Circuitry Verification, on April 24, 2018
: (1) ST-9R, EDG System Quick-Start Operability Test and Offsite Circuitry Verification, on April 24, 2018
: (2) ST-9BA, EDG 'A' and 'C' Full Load Test and ESW Pump Operability Test, on May 17, 2018
: (2) ST-9BA, EDG A and C Full Load Test and ESW Pump Operability Test, on May 17, 2018
: (3) ST-1L, Main Turbine Control Valve Instrument Channel and Valve Operability Check, on June 2, 2018  
: (3) ST-1L, Main Turbine Control Valve Instrument Channel and Valve Operability Check, on June 2, 2018  


===Inservice (2 Samples)===
===Inservice (2 Samples)===
: (1) ST-6HA, Standby Liquid Control 'A' Side Quarterly Operability Test, on May 23, 2018
: (1) ST-6HA, Standby Liquid Control A Side Quarterly Operability Test, on May 23, 2018
: (2) ST-24J, Reactor Core Isolation Cooling Flow Rate and Inservice Test, on May 30, 2018  
: (2) ST-24J, Reactor Core Isolation Cooling Flow Rate and Inservice Test, on May 30, 2018  


===Reactor Coolant Leak Detection (1 Sample)===
===Reactor Coolant Leak Detection (1 Sample)===
: (1) SP-01.02, Reactor Water Sampling and Analysis, on May 31, 2018
: (1) SP-01.02, Reactor Water Sampling and Analysis, on May 31,


==RADIATION SAFETY==
==RADIATION SAFETY==
==71124.08 - Radioactive Solid Waste Processing and Radioactive Material Handling, Storage,==
and Transportation


==71124.08 - Radioactive Solid Waste Processing and Radioactive Material Handling, Storage, and Transportation==
===Radioactive Material Storage===
{{IP sample|IP=IP 71124.08|count=1}}


===Radioactive Material Storage (1 Sample)===
The inspectors observed radioactive waste container storage areas and verified the postings and controls and that Exelon had established a process for monitoring the impact of long-term storage of the waste.
The inspectors observed radioactive waste container storage areas and verified the postings and controls and that Exelon had established a process for monitoring the impact of long-term storage of the waste.


===Radioactive Waste System Walkdown (1 Sample)===
===Radioactive Waste System Walkdown (1 Sample)===
The inspectors walked down the following:
The inspectors walked down the following:
: (1) Accessible portions of liquid and solid radioactive waste processing systems to verify current system alignment and material condition
: (1) Accessible portions of liquid and solid radioactive waste processing systems to verify current system alignment and material condition
Line 228: Line 239:


===Waste Characterization and Classification (1 Sample)===
===Waste Characterization and Classification (1 Sample)===
The inspectors identified radioactive waste streams and reviewed radiochemical sample analysis results to support radioactive waste characterization. The inspectors reviewed the use of scaling factors and calculations to account for difficult-to-measure radionuclides.
The inspectors identified radioactive waste streams and reviewed radiochemical sample analysis results to support radioactive waste characterization. The inspectors reviewed the use of scaling factors and calculations to account for difficult-to-measure radionuclides.


Line 238: Line 248:


==OTHER ACTIVITIES - BASELINE==
==OTHER ACTIVITIES - BASELINE==
===71151 - Performance Indicator Verification===
===71151 - Performance Indicator Verification===
{{IP sample|IP=IP 71151|count=2}}
{{IP sample|IP=IP 71151|count=2}}
The inspectors verified Exelon's performance indicator submittals listed below for the period from April 1, 2017 to March 31, 2018:
 
The inspectors verified Exelons performance indicator submittals listed below for the period from April 1, 2017 to March 31, 2018:
: (1) BI01, Reactor Coolant System Specific Activity
: (1) BI01, Reactor Coolant System Specific Activity
: (2) BI02, Reactor Coolant System Leak Rate
: (2) BI02, Reactor Coolant System Leak Rate


==71152 - Problem Identification and Resolution==
==71152 - Problem Identification and Resolution==
===Semiannual Trend Review (1 Sample)===
===Semiannual Trend Review (1 Sample)===
 
The inspectors reviewed Exelons implementation of its corrective action program (CAP) for trends that might be indicative of a more significant safety issue for a sample of issues and events that occurred between October 2017 and March 2018.
The inspectors reviewed Exelon's implementation of its corrective action program (CAP) for trends that might be indicative of a more significant safety issue for a sample of issues and events that occurred between October 2017 and March 2018.


===Annual Follow-up of Selected Issues (1 Samples)===
===Annual Follow-up of Selected Issues (1 Samples)===
The inspectors reviewed Exelons implementation of its CAP related to the following issues:
: (1) Issue Report (IR) 4097375, FitzPatrick Cycle 23 Fuel Defects


The inspectors reviewed Exelon's implementation of its CAP related to the following issues:
==INSPECTION RESULTS==
: (1) Issue Report (IR) 4097375, FitzPatrick Cycle 23 Fuel Defects
Licensee Identified Non-Cited Violation 71124.08 This violation of very low safety significance was identified by Exelon and has been entered into Exelons CAP and is being treated as an NCV, consistent with Section 2.3.2 of the Enforcement Policy.


==INSPECTION RESULTS==
Violation: 10 CFR 71.5 requires that licensees who transport licensed material comply with the applicable requirements of the Department of Transportation (49 CFR). 49 CFR 172.202(a)(1) and (a)(2) require that the shipping description on the shipping paper include the proper shipping name and identification number for the material. 49 CFR 172.302(a)requires that shipments in bulk packages be marked with the identification number.
Licensee Identified Non-Cited Violation 71124.08 This violation of very low safety significance was identified by Exelon and has been entered into Exelon's CAP and is being treated as an NCV, consistent with Section 2.3.2 of the Enforcement Policy. Violation: 10 CFR 71.5 requires that licensees who transport licensed material comply with the applicable requirements of the Department of Transportation (49 CFR). 49 CFR 172.202(a)(1) and (a)(2) require that the shipping description on the shipping paper include the proper shipping name and identification number for the material. 49 CFR 172.302(a)requires that shipments in bulk packages be marked with the identification number.


Contrary to the above, on July 12, 2016, the shipping description on the shipping paper for shipment JAF-2016-1613 from FitzPatrick to Tennessee did not include the proper shipping name and identification number for the material. Exelon identified the error during a subsequent review of the shipping paperwork.
Contrary to the above, on July 12, 2016, the shipping description on the shipping paper for shipment JAF-2016-1613 from FitzPatrick to Tennessee did not include the proper shipping name and identification number for the material. Exelon identified the error during a subsequent review of the shipping paperwork.


Significance/Severity Level: No examples of transportation issues are presented in IMC 0612, Appendix E (Examples of Minor Issues). IMC 0609, Appendix D, Section VII.C.e.1 lists  
Significance/Severity Level: No examples of transportation issues are presented in IMC 0612, Appendix E (Examples of Minor Issues). IMC 0609, Appendix D, Section VII.C.e.1 lists examples of Green findings that include documentation deficiencies including failure to properly document compliance with 49 CFR requirements such as shipping papers.


examples of Green findings that include documentation deficiencies including failure to properly document compliance with 49 CFR requirements such as shipping papers.
Corrective Action Reference: Exelon placed this issue into its CAP as CR-JAF-2016-02857.


Corrective Action Reference:  Exelon placed this issue into its CAP as CR-JAF-2016-02857.
Corrective actions included providing a corrected shipping paper to the facility in Tennessee that had received the package.


Corrective actions included providing a corrected shipping paper to the facility in Tennessee that had received the package.
Minor Performance Deficiency and Observations 71152 Semiannual Trend Review During the trend review, inspectors identified multiple IRs associated with deficiencies in the RBCLC system where functionality assessments were not performed when required by OP-A-108-115, Operability Determinations. The failure to complete required functionality assessments for RBCLC system issues is a performance deficiency; however, it was determined to be minor because the RBCLC system was always functional and the performance deficiency did not adversely affect the Mitigating System cornerstone objective.


Minor Performance Deficiency and Observations 71152 Semiannual Trend Review During the trend review, inspectors identified multiple IRs associated with deficiencies in the RBCLC system where functionality assessments were not performed when required by OP- A-108-115, "Operability Determinations."  The failure to complete required functionality assessments for RBCLC system issues is a performance deficiency; however, it was determined to be minor because the RBCLC system was always functional and the performance deficiency did not adversely affect the Mitigating System cornerstone objective. Exelon acknowledged the issue and reopened relevant IRs for shift review and performed the necessary functionality determinations. Additional corrective actions included discretionary crew clock resets for all operations crews (IR 04153271).
Exelon acknowledged the issue and reopened relevant IRs for shift review and performed the necessary functionality determinations. Additional corrective actions included discretionary crew clock resets for all operations crews (IR 04153271).


The inspectors also noted that Exelon documented a number of trends over the inspection timeframe. Exelon documented a trend from June 2017 to November 2017 of eight IRs concerning inadequate foreign material exclusion (FME) controls (IR 04071678). Poor FME practices have the potential to impact fuel leaks. The inspectors noted that Exelon has taken a number of actions to resolve the issue and implemented appropriate corrective actions pertaining to their FME control program onsite. Exelon also identified a trend in failures to enter requisite information into operations narrative logs (IR 04071531). Exelon independently identified several examples where a log entry was warranted but not entered in accordance with OP-AA-111-101. Corrective actions included the review of procedural requirements by all operations crews, crew clock resets and shift briefings.
The inspectors also noted that Exelon documented a number of trends over the inspection timeframe. Exelon documented a trend from June 2017 to November 2017 of eight IRs concerning inadequate foreign material exclusion (FME) controls (IR 04071678). Poor FME practices have the potential to impact fuel leaks. The inspectors noted that Exelon has taken a number of actions to resolve the issue and implemented appropriate corrective actions pertaining to their FME control program onsite. Exelon also identified a trend in failures to enter requisite information into operations narrative logs (IR 04071531). Exelon independently identified several examples where a log entry was warranted but not entered in accordance with OP-AA-111-101. Corrective actions included the review of procedural requirements by all operations crews, crew clock resets and shift briefings.


Minor Performance Deficiency 71152 Annual Follow-up of Selected Issues FitzPatrick Cycle 23 Fuel Defects  
Minor Performance Deficiency 71152 Annual Follow-up of Selected Issues FitzPatrick Cycle 23 Fuel Defects  


On November 5, 2017, Exelon identified a third fuel defect in the cycle 23 core that has resulted in full insertion of five control rods to date to mitigate the consequences of operating with defective fuel in the current fuel cycle. Exelon initiated a root cause investigation under IR 4097375 that will not be complete until the defective fuel is cleaned and examined in detail following completion of the next refueling outage. The inspectors identified a minor performance deficiency for the calculation of shutdown margin (SDM). Exelon procedure NF-AB-110-3050 for calculation of cold SDM requires in Step 4.2 that SDM be calculated when  
On November 5, 2017, Exelon identified a third fuel defect in the cycle 23 core that has resulted in full insertion of five control rods to date to mitigate the consequences of operating with defective fuel in the current fuel cycle. Exelon initiated a root cause investigation under IR 4097375 that will not be complete until the defective fuel is cleaned and examined in detail following completion of the next refueling outage. The inspectors identified a minor performance deficiency for the calculation of shutdown margin (SDM). Exelon procedure NF-AB-110-3050 for calculation of cold SDM requires in Step 4.2 that SDM be calculated when there is uncertainty between actual core operating strategies and the core design of record.


there is uncertainty between actual core operating strategies and the core design of record. In addition, Exelon procedure NF-AB-110-3040 for calculation of control rod pattern development and projections to end of cycle, contains a design verification check in Attachment 2, Section B, to verify that SDM is acceptable for the remainder of the fuel cycle.
In addition, Exelon procedure NF-AB-110-3040 for calculation of control rod pattern development and projections to end of cycle, contains a design verification check in 2, Section B, to verify that SDM is acceptable for the remainder of the fuel cycle.


Contrary to the above two procedures, from the first change in core configuration that was completed on May 18, 2017, for the first discovered fuel defect, until a re-calculation of SDM was performed on May 1, 2018, SDM was not verified to be in compliance with the SDM technical specification (TS). Corrective action to re-calculate SDM was not timely considering the potential safety significance of violating the SDM TS.
Contrary to the above two procedures, from the first change in core configuration that was completed on May 18, 2017, for the first discovered fuel defect, until a re-calculation of SDM was performed on May 1, 2018, SDM was not verified to be in compliance with the SDM technical specification (TS). Corrective action to re-calculate SDM was not timely considering the potential safety significance of violating the SDM TS.
Line 283: Line 292:
Re-calculation of SDM on May 1, 2018, confirmed that insertion of control rod 6-31 on May 18, 2017, ensured sufficient margin at that time, and for the remainder of fuel cycle 23, between the calculated value of SDM and the TS specified value. Exelon documented this issue in IR 4133208 and completed an extent of condition review to confirm there were no other deviations from design requirements for the cycle 23 core. In addition, an action has been assigned to Nuclear Fuels to review applicable processes to ensure the appropriate level of review is completed when revising rod patterns for the operating fuel cycle.
Re-calculation of SDM on May 1, 2018, confirmed that insertion of control rod 6-31 on May 18, 2017, ensured sufficient margin at that time, and for the remainder of fuel cycle 23, between the calculated value of SDM and the TS specified value. Exelon documented this issue in IR 4133208 and completed an extent of condition review to confirm there were no other deviations from design requirements for the cycle 23 core. In addition, an action has been assigned to Nuclear Fuels to review applicable processes to ensure the appropriate level of review is completed when revising rod patterns for the operating fuel cycle.


The performance deficiency was evaluated for significance in accordance with IMC 0612, Appendix B, "Issue Screening," dated January 1, 2018, and IMC 0612, Appendix E, "Examples of Minor Issues," dated August 11, 2009. The inspectors determined that this issue was minor because the SDM TS was not violated, and a re-configuration of the plant was not required to prevent violating the SDM TS (such as reducing plant power or changing the core rod pattern). This performance deficiency is similar to Example 2.a. in IMC 0612, Appendix E.
The performance deficiency was evaluated for significance in accordance with IMC 0612, Appendix B, Issue Screening, dated January 1, 2018, and IMC 0612, Appendix E, Examples of Minor Issues, dated August 11, 2009. The inspectors determined that this issue was minor because the SDM TS was not violated, and a re-configuration of the plant was not required to prevent violating the SDM TS (such as reducing plant power or changing the core rod pattern). This performance deficiency is similar to Example 2.a. in IMC 0612, Appendix E.


==EXIT MEETINGS AND DEBRIEFS==
==EXIT MEETINGS AND DEBRIEFS==
Line 292: Line 301:
On June 14, 2018, the inspector presented the inspection results to Mr. Alex Sterio, Director, Site Engineering, and other members of the Exelon staff.
On June 14, 2018, the inspector presented the inspection results to Mr. Alex Sterio, Director, Site Engineering, and other members of the Exelon staff.


On June 29, 2018, the inspector presented the radiation safety inspection results to Mr. Joseph Pacher, Site Vice President, and other members of the Exelon staff.
On June 29, 2018, the inspector presented the radiation safety inspection results to Mr. Joseph Pacher, Site Vice President, and other members of the Exelon staff.


On July 18, 2018, the inspectors presented the quarterly resident inspection results to Mr. Timothy Peter, Plant Manager, and other members of the Exelon staff.
On July 18, 2018, the inspectors presented the quarterly resident inspection results to Mr. Timothy Peter, Plant Manager, and other members of the Exelon staff.
Line 299: Line 308:


71111.01
71111.01
Procedures AOP-72, 115kV Grid Loss, Instability, or Degradation, Revision 11
Procedures
AOP-72, 115kV Grid Loss, Instability, or Degradation, Revision 11
AP-12.04, Seasonal Weather Preparedness, Revision 027
AP-12.04, Seasonal Weather Preparedness, Revision 027
WC-AA-107, Seasonal Readiness, Revision 20
WC-AA-107, Seasonal Readiness, Revision 20
71111.04 Procedures OP-17, Standby Liquid Control System, Revision 52
71111.04
Procedures
OP-17, Standby Liquid Control System, Revision 52
OP-44, 115kV System, Revision 24
OP-44, 115kV System, Revision 24
Drawings FM-21A, Flow diagram Standby Li
Drawings
quid Control System, Revision 37 FM-25A, Flow Diagram, High Pressure Coolant Injection System, Revision 75  
FM-21A, Flow diagram Standby Liquid Control System, Revision 37
 
FM-25A, Flow Diagram, High Pressure Coolant Injection System, Revision 75
71111.05 Procedures JAF-RPT-04-00478, JAF Fire Hazards Analysis, Revision 3
71111.05
Procedures
JAF-RPT-04-00478, JAF Fire Hazards Analysis, Revision 3
OP-AA-201-003, Fire Drill Performance, Revision 16
OP-AA-201-003, Fire Drill Performance, Revision 16
PFP-OUT39, ISFSI Pad Location Elevation 272' Fire Area Zone Yard, Revision 2 PFP-PWR23, Fire Response Plan Motor Generator Set Room, Revision 5
PFP-OUT39, ISFSI Pad Location Elevation 272 Fire Area Zone Yard, Revision 2
PFP-PWR23, Fire Response Plan Motor Generator Set Room, Revision 5
Issue Report
Issue Report
04079478
04079478
Work Order
Work Order
23332 71111.07 - Heat Sink Performance
23332
Procedures AOP-10, Loss of Service Water Cooling, Revision 14
71111.07 - Heat Sink Performance
Procedures
AOP-10, Loss of Service Water Cooling, Revision 14
AOP-13, Severe Weather, Revision 32
AOP-13, Severe Weather, Revision 32
AOP-56, Intake Water Level Trouble, Revision 15
AOP-56, Intake Water Level Trouble, Revision 15
ER-AA-340, GL 89-13 Program Implementing Procedure, Revision 9
ER-AA-340, GL 89-13 Program Implementing Procedure, Revision 9
ER-AA-5400-1001, Raw Water Piping Integrity Management Guide, Revision 11
ER-AA-5400-1001, Raw Water Piping Integrity Management Guide, Revision 11
JAF-RPT-MULTI-01267, Generic Letter 89-13 Program Plan, Revision 4 OP-13C, RHR Service Water, Revision 14
JAF-RPT-MULTI-01267, Generic Letter 89-13 Program Plan, Revision 4
OP-13C, RHR Service Water, Revision 14
OP-21, Emergency Service Water, Revision 38
OP-21, Emergency Service Water, Revision 38
OP-22, Diesel Generator Emergency Power, Revision 62
OP-22, Diesel Generator Emergency Power, Revision 62
OP-42, Service Water System, Revision 52
OP-42, Service Water System, Revision 52
OP-AA-108-111-1001, Severe Weather and Natural Disaster Guidelines, Revision 17
OP-AA-108-111-1001, Severe Weather and Natural Disaster Guidelines, Revision 17
SEP-SW-JAF-001, NRC Generic Letter 89-13 Service Water Program, Revision 0 ST-8Q, Testing of the ESW System (IST), Revision 050
SEP-SW-JAF-001, NRC Generic Letter 89-13 Service Water Program, Revision 0
ST-8Q, Testing of the ESW System (IST), Revision 050
ST-9BA, EDG A and C Full Load Test and ESW Pump Operability Test, Revision 016  
ST-9BA, EDG A and C Full Load Test and ESW Pump Operability Test, Revision 016  


ST-9HA, EDG A and C Lube Oil and Cooling Water Systems Class 3 Piping Leakage Test (ISI), Revision 001 ST-9QA, EDG A and C Full Load Test (8 Hour Run), Revision 012 SY-AA-101-146, Severe Weather Preparation and Response, Revision 2
ST-9HA, EDG A and C Lube Oil and Cooling Water Systems Class 3 Piping Leakage Test (ISI),
Issue Reports 04014925 04062019 04072267 04084863
Revision 001
04107913 04123471 04138318 04145660
ST-9QA, EDG A and C Full Load Test (8 Hour Run), Revision 012
04145770 04146131 04146725* 04147154* 2012-0366 2013-2413 2015-2494 2015-4416 2016-1069 2016-1070 2016-1260 2017-1164  
SY-AA-101-146, Severe Weather Preparation and Response, Revision 2
 
Issue Reports
04014925
04062019
04072267
04084863
04107913
04123471
04138318
04145660
04145770
04146131
04146725*
04147154*
2012-0366
2013-2413
2015-2494
2015-4416
2016-1069
2016-1070
2016-1260
2017-1164  
* IR written as a result of this inspection
* IR written as a result of this inspection
Drawings 2137-23, 67E-14 As-Built Drawing, Revision 2 FM-20B, Residual Heat Removal System 10 Flow Diagram, Revision 72
Drawings
2137-23, 67E-14 As-Built Drawing, Revision 2
FM-20B, Residual Heat Removal System 10 Flow Diagram, Revision 72
FM-46A, Service Water System 46 Flow Diagram, Revision 92
FM-46A, Service Water System 46 Flow Diagram, Revision 92
FM-46B, Emergency Service Water System 46 and 15 Flow Diagram, Revision 57 FM-93C, Engine Cooling and Lubrication Oil Emergency Diesel Generators System 93 Flow
FM-46B, Emergency Service Water System 46 and 15 Flow Diagram, Revision 57
FM-93C, Engine Cooling and Lubrication Oil Emergency Diesel Generators System 93 Flow
Diagram, Revision 9
Diagram, Revision 9
Work Orders 04654692 04682358 82626362  82691362
Work Orders
Miscellaneous   04088187-02, NRC Tri-Annual Ultimate Heatsink Inspection Self-Assessment, dated June 5, 2018
04654692
EPRI NP-7552M, Heat Exchanger Performance Monitoring Guidelines, December 1991 EPRI TR-107397, Service Water Heat Exchanger Testing Guidelines, March 1998 W981-0001, Installation, Operation, and Maintenance Manual for Shell and Tube Heat
04682358
Exchangers, Revision 0 DBD-093, Design Basis Document for the Emergency Diesel Generator, Revision 13
2626362
71111.11 Procedure
2691362
Miscellaneous
04088187-02, NRC Tri-Annual Ultimate Heatsink Inspection Self-Assessment, dated
June 5, 2018
EPRI NP-7552M, Heat Exchanger Performance Monitoring Guidelines, December 1991
EPRI TR-107397, Service Water Heat Exchanger Testing Guidelines, March 1998
W981-0001, Installation, Operation, and Maintenance Manual for Shell and Tube Heat
Exchangers, Revision 0
DBD-093, Design Basis Document for the Emergency Diesel Generator, Revision 13
71111.11
Procedure
OP-27, Recirculation System, Revision 81
OP-27, Recirculation System, Revision 81
Work Order
Work Order
80455505 71111.12 Procedure ER-AA-450, Structures Monitoring, Revision 7
80455505
Miscellaneous Commercial Grade Dedications Sheet
71111.12
Procedure
ER-AA-450, Structures Monitoring, Revision 7
Miscellaneous
Commercial Grade Dedications Sheet
Document Number 00649438
Document Number 00649438
EN-MP-112, Rev 5, Shelf Life Program
EN-MP-112, Rev 5, Shelf Life Program  
Item Equivalency Evaluation 00155498 Procurement Engineering Evaluation 00135975
 
Procurement Engineering Evaluation 00138962 Procurement Engineering Evaluation 00163368
Item Equivalency Evaluation 00155498
Procurement Engineering Evaluation 00135975
Procurement Engineering Evaluation 00138962
Procurement Engineering Evaluation 00163368
Purchase Order 10497183
Purchase Order 10497183
Purchase Order 1049919
Purchase Order 1049919
71111.13 Procedure OP-AA-108-117, Protected Equipment Program, Revision 5
71111.13
71111.15 Procedure OP-AA-108-115, Operability Determinations, Revision 20
Procedure
Condition Report CR-JAF-2017-02196, Action Plan for Spent Fuel Pool Liner Leakage, dated January 2, 2018
OP-AA-108-117, Protected Equipment Program, Revision 5
Issue Reports 03992646 04008472 04013475 04060217
71111.15
04137701   04138318  04142498
Procedure
OP-AA-108-115, Operability Determinations, Revision 20
Condition Report
CR-JAF-2017-02196, Action Plan for Spent Fuel Pool Liner Leakage, dated January 2, 2018
Issue Reports
03992646
04008472
04013475
04060217
04137701  


04138318
04142498
Work Order
Work Order
1366682
1366682
Drawings 11825, Spent Fuel Pool Liner Details, Sheets 1-4, Revision 6
Drawings
11825, Spent Fuel Pool Liner Details, Sheets 1-4, Revision 6
AP-17.03, Spent Fuel Pool Map, Revision 11
AP-17.03, Spent Fuel Pool Map, Revision 11
Miscellaneous Engineering Change 624309
Miscellaneous
Engineering Change 624309
JAF Control Room Operator Logs dated May 13, 2017 through May 4, 2018
JAF Control Room Operator Logs dated May 13, 2017 through May 4, 2018
UT Erosion/Corrosion Examination Report No. B18UT012 and B18UT013  
UT Erosion/Corrosion Examination Report No. B18UT012 and B18UT013
 
71111.18
71111.18
Procedures EN-DC-136, Attachment 9.4, Temporary Modification Control Form, TMOD No. 618981, Revision 14 EN-DC-173, Attachment 9.4, Engineering Leak Repair Evaluation Checklist, TMOD No. 618981, Revision 2
Procedures
OP-27, Recirculation System, Revision 81  
EN-DC-136, Attachment 9.4, Temporary Modification Control Form, TMOD No. 618981,
 
Revision 14
EN-DC-173, Attachment 9.4, Engineering Leak Repair Evaluation Checklist, TMOD No. 618981,
Revision 2
OP-27, Recirculation System, Revision 81
Work Orders
Work Orders
04622631-01
04622631-01
Line 375: Line 449:
04622631-13  
04622631-13  


Drawing FM-26A, Flow Diagram Reactor Water Recirculation System 02-2, Revision 62
Drawing
Miscellaneous MP-059.85, Temporary Leak Repair, Revision 7
FM-26A, Flow Diagram Reactor Water Recirculation System 02-2, Revision 62
Miscellaneous
MP-059.85, Temporary Leak Repair, Revision 7
TRP-3401, Hot Tap Rings, Revision 3
TRP-3401, Hot Tap Rings, Revision 3
71111.19 Procedures
71111.19
OP-27, Recirculation System, Revision 81 ST-3NA, Core Spray Loop 'A' Class 2 Piping Leakage Test, Revision 0
Procedures
ST-3PA, Core Spray Loop 'A' Quarterly Operability Test, Revision 23
OP-27, Recirculation System, Revision 81
ST-3NA, Core Spray Loop A Class 2 Piping Leakage Test, Revision 0
ST-3PA, Core Spray Loop A Quarterly Operability Test, Revision 23
ST-76J23, West Diesel Fire Pump 76P-1 Performance Test, June 8, 2018
ST-76J23, West Diesel Fire Pump 76P-1 Performance Test, June 8, 2018
Work Orders 4635346-05 4721820-01 80455505 82569126
Work Orders
2570201 82707442-01 82746386-01  
4635346-05
21820-01
80455505
2569126
2570201
2707442-01
2746386-01  


71111.22 Procedures SP-01.02, Reactor Water Sampling and Analysis, Revision 29 SP-05.02, Chemistry Surveillance and Scheduling System, Revision 4
71111.22
ST-1L, Main Turbine Control Valve Instrument Channel and Valve Operability Check, Revision 37 ST-6HA, Standby Liquid Control A Side Quarterly Operability Test, Revision 10
Procedures
ST-9R, EDG System Quick-Start Operability Test and Offsite Circuitry Verification, Revision 8 ST-24J, RCIC Flow Rate and Inservice Test, Revision 48
SP-01.02, Reactor Water Sampling and Analysis, Revision 29
SP-05.02, Chemistry Surveillance and Scheduling System, Revision 4
ST-1L, Main Turbine Control Valve Instrument Channel and Valve Operability Check,
Revision 37
ST-6HA, Standby Liquid Control A Side Quarterly Operability Test, Revision 10
ST-9R, EDG System Quick-Start Operability Test and Offsite Circuitry Verification, Revision 8
ST-24J, RCIC Flow Rate and Inservice Test, Revision 48
Issue Report
Issue Report
04753369
04753369
Work Order
Work Order
04753562
04753562
71151 Procedures EN-LI-114, Performance Indicator Process, Revision 7 NEI 99-02, Regulatory Assessment Performance Indicator Guideline, Revision 7 SP-01.02, Reactor Water Sampling and Analysis, Revision 29 SP-05.02, Chemistry Surveillance and Scheduling System, Revision 4
71151
71152 Procedures MA-AA-716-008, Foreign Material Exclusion Program, Revision 13
Procedures
MA-AA-716-008-1008, Reactor Services Refuel Floor FME Plan, Revision 13 NF-AB-110-1160, Generation of 3D Simulator Output Files for ShuffleWorks, Revision 9
EN-LI-114, Performance Indicator Process, Revision 7
NF-AB-110-1170, Generation of Fuel Moves Using ShuffleWorks, Revision 11
NEI 99-02, Regulatory Assessment Performance Indicator Guideline, Revision 7
SP-01.02, Reactor Water Sampling and Analysis, Revision 29
SP-05.02, Chemistry Surveillance and Scheduling System, Revision 4
71152
Procedures
MA-AA-716-008, Foreign Material Exclusion Program, Revision 13
MA-AA-716-008-1008, Reactor Services Refuel Floor FME Plan, Revision 13
NF-AB-110-1160, Generation of 3D Simulator Output Files for ShuffleWorks, Revision 9
NF-AB-110-1170, Generation of Fuel Moves Using ShuffleWorks, Revision 11  
 
NF-AB-110-3040, Control Rod Pattern Development and Projections to EOC, Revision 19
NF-AB-110-3040, Control Rod Pattern Development and Projections to EOC, Revision 19
NF-AB-110-3050, Cold Shutdown Margin, Revision 13
NF-AB-110-3050, Cold Shutdown Margin, Revision 13
NF-AB-430, Failed Fuel Action Plan, Revision 14 NF-AB-431, Power Suppression Testing, Revision 8 OP-AA-108-111, Attachment 1, Adverse C
NF-AB-430, Failed Fuel Action Plan, Revision 14
ondition Monitoring and Contingency Plan - JAF Failed Fuel Monitoring, Revision 3 OSP-66.001, Management of Refueling Activities, Revision 9
NF-AB-431, Power Suppression Testing, Revision 8
OP-AA-108-111, Attachment 1, Adverse Condition Monitoring and Contingency Plan - JAF
Failed Fuel Monitoring, Revision 3
OSP-66.001, Management of Refueling Activities, Revision 9
RAP-7.4.04, Reactivity Anomaly Surveillance Test, Revision 18
RAP-7.4.04, Reactivity Anomaly Surveillance Test, Revision 18
Issue Reports 4008275 4008472 4019299 4019299 4039343 4040606 4040620 4049121
Issue Reports
4071227 4074581 4081475 4081555
4008275
4081564 4083992 4097375 4133208 4133209 4138890 4138892
4008472
4019299
4019299
4039343
4040606
4040620
4049121
4071227
4074581
4081475
4081555
4081564
4083992
4097375
4133208
4133209
4138890
4138892
Work Order
Work Order
4755156-01
4755156-01
Calculations NF-AB-110-3040, Attachment 2, Design Verification Guide-Control Rod Pattern Development and Projections to EOC, dated November 27, 2017 NF-AB-110-3050, Attachment 5, Design Verification Guide-Cold Shutdown Margin, dated May 1, 2018
Calculations
Miscellaneous JAF Chemistry Logs, Offgas Release Rate and Sum of Six Isotopes, May 2, 2017 through
NF-AB-110-3040, Attachment 2, Design Verification Guide-Control Rod Pattern Development
May 2, 2018 JAF Renewed Facility Operating License, DPR-59, Amendment 317
and Projections to EOC, dated November 27, 2017
NF-AB-110-3050, Attachment 5, Design Verification Guide-Cold Shutdown Margin, dated
May 1, 2018
Miscellaneous
JAF Chemistry Logs, Offgas Release Rate and Sum of Six Isotopes, May 2, 2017 through
May 2, 2018
JAF Renewed Facility Operating License, DPR-59, Amendment 317
JAF Technical Requirements Manual, Revision 70
JAF Technical Requirements Manual, Revision 70
JAF UFSAR LER 2012-004-01, Control Rods Inoperable While Entering Plant Outage, dated
JAF UFSAR
January 24, 2013 LER 2015-001, COLR Thermal Limits Exceeded with Elevated Fuel Support Piece, dated June 29, 2015 Root Cause Report, FitzPatrick Cycle 23 Fuel Defects, dated January 26, 2018 Technical Evaluation 622819, FitzPatrick Control Blade Replacement Projections: Replacement Strategy for FitzPatrick Cycle 24 (Reload 23), dated February 2, 2018
LER 2012-004-01, Control Rods Inoperable While Entering Plant Outage, dated
January 24, 2013
LER 2015-001, COLR Thermal Limits Exceeded with Elevated Fuel Support Piece, dated
June 29, 2015
Root Cause Report, FitzPatrick Cycle 23 Fuel Defects, dated January 26, 2018
Technical Evaluation 622819, FitzPatrick Control Blade Replacement Projections: Replacement
Strategy for FitzPatrick Cycle 24 (Reload 23), dated February 2, 2018
}}
}}

Latest revision as of 15:50, 5 January 2025

Integrated Inspection Report 05000333/2018002
ML18218A120
Person / Time
Site: FitzPatrick Constellation icon.png
Issue date: 08/06/2018
From: Anthony Dimitriadis
NRC/RGN-I/DRP/PB5
To: Bryan Hanson
Exelon Generation Co, Exelon Nuclear
Dimitriadis A
References
IR 2018002
Download: ML18218A120 (18)


Text

August 6, 2018

SUBJECT:

JAMES A. FITZPATRICK NUCLEAR POWER PLANT - INTEGRATED INSPECTION REPORT 05000333/2018002

Dear Mr. Hanson:

On June 30, 2018, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at the James A. FitzPatrick Nuclear Power Plant (FitzPatrick). On July 18, 2018, the NRC inspectors discussed the results of this inspection with Mr. Timothy Peter, Plant Manager, and other members of your staff. The results of this inspection are documented in the enclosed report.

No NRC-identified or self-revealing findings were identified during this inspection. NRC inspectors documented one licensee-identified violation which was determined to be of very low safety significance in this report. The NRC is treating this violation as a non-cited violation (NCV) consistent with Section 2.3.2.a of the Enforcement Policy.

If you contest the violation or significance of this NCV, you should provide a response within 30 days of the date of this inspection report, with the basis for your denial, to the U.S. Nuclear Regulatory Commission, ATTN: Document Control Desk, Washington, DC 20555-0001; with copies to the Regional Administrator, Region I; the Director, Office of Enforcement; and the NRC Resident Inspector at FitzPatrick. This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and the NRC Public Document Room in accordance with Title 10 of the Code of Federal Regulations (10 CFR), Part 2.390, Public Inspections, Exemptions, Requests for Withholding.

Sincerely,

/RA/

Anthony Dimitriadis, Chief Reactor Projects Branch 5 Division of Reactor Projects

Docket Number: 50-333 License Number: DPR-59

Enclosure:

Inspection Report 05000333/2018002

Inspection Report

Docket Number:

50-333

License Number:

DPR-59

Report Number:

05000333/2018002

Enterprise Identifier: I-2018-002-0058

Licensee:

Exelon Generation Company, LLC (Exelon)

Facility:

James A. FitzPatrick Nuclear Power Plant

Location:

Scriba, NY

Inspection Dates:

April 1, 2018 to June 30, 2018

Inspectors:

K. Kolaczyk, Senior Resident Inspector

S. Ghrayeb, Resident Inspector

G. Stock, Resident Inspector

T. Dunn, Operations Engineer

B. Fuller, Senior Operations Engineer

J. Furia, Senior Health Physicist

M. Hardgrove, Projects Engineer

C. Hobbs, Reactor Inspector

J. Schoppy, Senior Reactor Inspector

Approved By:

Anthony Dimitriadis, Chief

Reactor Projects Branch 5

Division of Reactor Projects

SUMMARY

The U.S. Nuclear Regulatory Commission (NRC) continued monitoring Exelons performance at

FitzPatrick by conducting the baseline inspections described in this report in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for overseeing the safe operation of commercial nuclear power reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information. A licensee-identified non-cited violation (NCV) is documented in the Inspection Results section of the report.

PLANT STATUS

FitzPatrick began the inspection period at rated thermal power. On May 14, 2018, the unit was down powered to 45 percent power to remove the A recirculation pump from service for a motor-generator set motor replacement. The unit was returned to rated thermal power on May 24, 2018. On June 1, 2018, the unit was down-powered to 65 percent power for planned control rod pattern adjustment, main steam isolation valve testing, and turbine valve testing.

The unit was returned to rated thermal power on June 3, 2018. On June 22, 2018, the unit was down-powered to 70 percent power for a planned control rod pattern adjustment and condenser backwashing. The unit was returned to rated thermal power on June 23, 2018, and remained at or near rated thermal power for the remainder of the inspection period.

INSPECTION SCOPES

Inspections were conducted using the appropriate portions of the inspection procedures (IPs) in effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with their attached revision histories are located on the public website at http://www.nrc.gov/reading-rm/doc-collections/insp-manual/inspection-procedure/index.html. Samples were declared complete when the IP requirements most appropriate to the inspection activity were met consistent with Inspection Manual Chapter (IMC) 2515, Light-Water Reactor Inspection Program - Operations Phase. The inspectors performed plant status activities described in IMC 2515, Appendix D, Plant Status, and conducted routine reviews using IP 71152, Problem Identification and Resolution. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel to assess Exelons performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards.

REACTOR SAFETY

71111.01 - Adverse Weather Protection

Summer Readiness (1 Sample)

The inspectors evaluated summer readiness of offsite and alternating current (AC) power systems on June 29, 2018.

71111.04 - Equipment Alignment

Partial Walkdowns (3 Samples)

The inspectors evaluated system configurations during partial walkdowns of the following systems:

(1) A and B standby liquid control systems on April 17, 2018
(2) Offsite AC distribution system on April 19, 2018
(3) High pressure coolant injection system on May 16, 2018

71111.05A/Q - Fire Protection Annual/Quarterly

Quarterly Inspection (4 Samples)

The inspectors evaluated fire protection program implementation in the following selected areas:

(1) Technical support center computer rooms, fire zone AD-3 on April 10, 2018
(2) Independent spent fuel installation pad, fire area yard on April 12, 2018
(3) Condensate storage tank vault, fire zone CST-V on April 23, 2018
(4) Motor generator set room/elevation 300, fire area MG-1 on April 23, 2018

Annual Inspection (1 Sample)

The inspectors evaluated a fire drill at 272 turbine building south on June 5, 2018.

71111.06 - Flood Protection Measures

Internal Flooding (1 Sample)

The inspectors evaluated leaking fire protection piping in east pipe tunnel on May 24, 2018.

71111.07 - Heat Sink Performance

Heat Sink (1 Sample)

The inspectors evaluated the C reactor building closed loop cooling (RBCLC) heat exchanger retube on June 22, 2018.

Heat Sink (Triennial) (3 Samples)

The inspectors evaluated heat exchanger/heat sink performance on the following structures, systems, and components:

(1) C emergency diesel generator (EDG) jacket water heat exchanger (93WE-1C),

Section 02.02b

(2) East cable tunnel/emergency switchgear room cooler (67E-14), Section 02.02b
(3) One ultimate heat sink sample (associated with service water system operation and intake structure condition), Sections 02.02d.4 and 02.02d.7, respectively

71111.11 - Licensed Operator Requalification Program and Licensed Operator Performance

Operator Requalification (1 Sample)

The inspectors observed flexible mitigating strategies training on April 13, 2018.

Operator Performance (1 Sample)

The inspectors observed and evaluated A reactor water recirculation pump start and power ascension following generator replacement on May 19, 2018.

Operator Requalification Exam Results (Annual) (1 Sample)

The inspectors reviewed and evaluated requalification examination results, operating test only, on June 5, 2018.

Operator Requalification Program and Operator Performance (Biennial) (1 Sample)

The inspectors reviewed and evaluated operator, evaluator, and simulator performance during requalification examinations completed on March 22, 2018.

71111.12 - Maintenance Effectiveness

Routine Maintenance Effectiveness (1 Sample)

The inspectors evaluated the effectiveness of routine maintenance activities associated with the following equipment and/or safety significant functions:

(1) Structural monitoring program diesel building and cable tunnel roof on April 11, 2018

Quality Control (1 Sample)

The inspectors evaluated maintenance and quality control activities associated with the following equipment performance issues:

(1) Unit cooler water box gasket
(2) RBCLC to drywell cooling assembly filter regulator
(3) Lubricant for GQ 600V motor control center cabinets

71111.13 - Maintenance Risk Assessments and Emergent Work Control

The inspectors evaluated the risk assessments for the following planned and emergent work activities:

(1) B residual heat removal (RHR) maintenance on April 4, 2018
(2) Line 3 outage on April 11, 2018
(3) A containment air dilution system planned maintenance on April 16, 2018
(4) A recirculation generator heavy lift on May 15, 2018
(5) A core spray maintenance and operability test June 13, 2018

71111.15 - Operability Determinations and Functionality Assessments

The inspectors evaluated the following operability determinations and functionality assessments:

(1) Station battery cell flaking on May 17, 2018
(2) Fully inserted control rods 06-27, 06-31, 18-31, 34-35, and 38-31 on May 30, 2018
(3) Spent fuel pool leakage on May 31, 2018
(4) Emergency service water (ESW) following through wall leak discovery and evaluation on June 19, 2018

71111.18 - Plant Modifications

The inspectors evaluated the following temporary modification:

(1) Engineering Change Package 618981, Isolation of Lines in the Drywell Floor Drain System, focusing on the 02-2MOV-53A valve body drain

71111.19 - Post Maintenance Testing

The inspectors evaluated post maintenance testing for the following maintenance/repair activities:

(1) ST-2AM, B RHR quarterly operability testing on April 5, 2018
(2) A reactor recirculation pump generator replacement on May 19, 2018
(3) 76P-1, West diesel fire pump testing on June 8, 2018
(4) A core spray system operability testing on June 13, 2018
(5) C EDG circulating oil pump maintenance on June 20, 2018
(6) B standby gas treatment system motor replacement on June 27, 2018

71111.20 - Refueling and Other Outage Activities

The inspectors evaluated new fuel receipt inspection activities on June 26, 2018.

71111.22 - Surveillance Testing

The inspectors evaluated the following surveillance tests:

Routine

(1) ST-9R, EDG System Quick-Start Operability Test and Offsite Circuitry Verification, on April 24, 2018
(2) ST-9BA, EDG A and C Full Load Test and ESW Pump Operability Test, on May 17, 2018
(3) ST-1L, Main Turbine Control Valve Instrument Channel and Valve Operability Check, on June 2, 2018

Inservice (2 Samples)

(1) ST-6HA, Standby Liquid Control A Side Quarterly Operability Test, on May 23, 2018
(2) ST-24J, Reactor Core Isolation Cooling Flow Rate and Inservice Test, on May 30, 2018

Reactor Coolant Leak Detection (1 Sample)

(1) SP-01.02, Reactor Water Sampling and Analysis, on May 31,

RADIATION SAFETY

71124.08 - Radioactive Solid Waste Processing and Radioactive Material Handling, Storage,

and Transportation

Radioactive Material Storage

The inspectors observed radioactive waste container storage areas and verified the postings and controls and that Exelon had established a process for monitoring the impact of long-term storage of the waste.

Radioactive Waste System Walkdown (1 Sample)

The inspectors walked down the following:

(1) Accessible portions of liquid and solid radioactive waste processing systems to verify current system alignment and material condition
(2) Abandoned in-place radioactive waste processing equipment to review the controls in place to ensure protection of personnel
(3) Changes made to the radioactive waste processing systems since the last inspection
(4) Processes for mixing and transferring radioactive waste resin and/or sludge discharges into shipping/disposal containers
(5) Current methods and procedures for dewatering waste

Waste Characterization and Classification (1 Sample)

The inspectors identified radioactive waste streams and reviewed radiochemical sample analysis results to support radioactive waste characterization. The inspectors reviewed the use of scaling factors and calculations to account for difficult-to-measure radionuclides.

Shipment Preparation (1 Sample)

The inspectors reviewed the records of shipment packaging, surveying, labeling, marking, placarding, vehicle checks, emergency instructions, disposal manifest, shipping papers provided to the driver, and Exelon verification of shipment readiness.

Shipping Records (1 Sample)

The inspectors reviewed selected non-excepted package shipment records.

OTHER ACTIVITIES - BASELINE

71151 - Performance Indicator Verification

The inspectors verified Exelons performance indicator submittals listed below for the period from April 1, 2017 to March 31, 2018:

(1) BI01, Reactor Coolant System Specific Activity
(2) BI02, Reactor Coolant System Leak Rate

71152 - Problem Identification and Resolution

Semiannual Trend Review (1 Sample)

The inspectors reviewed Exelons implementation of its corrective action program (CAP) for trends that might be indicative of a more significant safety issue for a sample of issues and events that occurred between October 2017 and March 2018.

Annual Follow-up of Selected Issues (1 Samples)

The inspectors reviewed Exelons implementation of its CAP related to the following issues:

(1) Issue Report (IR) 4097375, FitzPatrick Cycle 23 Fuel Defects

INSPECTION RESULTS

Licensee Identified Non-Cited Violation 71124.08 This violation of very low safety significance was identified by Exelon and has been entered into Exelons CAP and is being treated as an NCV, consistent with Section 2.3.2 of the Enforcement Policy.

Violation: 10 CFR 71.5 requires that licensees who transport licensed material comply with the applicable requirements of the Department of Transportation (49 CFR). 49 CFR 172.202(a)(1) and (a)(2) require that the shipping description on the shipping paper include the proper shipping name and identification number for the material. 49 CFR 172.302(a)requires that shipments in bulk packages be marked with the identification number.

Contrary to the above, on July 12, 2016, the shipping description on the shipping paper for shipment [[::JAF-2016-1613|JAF-2016-1613]] from FitzPatrick to Tennessee did not include the proper shipping name and identification number for the material. Exelon identified the error during a subsequent review of the shipping paperwork.

Significance/Severity Level: No examples of transportation issues are presented in IMC 0612, Appendix E (Examples of Minor Issues). IMC 0609, Appendix D,Section VII.C.e.1 lists examples of Green findings that include documentation deficiencies including failure to properly document compliance with 49 CFR requirements such as shipping papers.

Corrective Action Reference: Exelon placed this issue into its CAP as CR-JAF-2016-02857.

Corrective actions included providing a corrected shipping paper to the facility in Tennessee that had received the package.

Minor Performance Deficiency and Observations 71152 Semiannual Trend Review During the trend review, inspectors identified multiple IRs associated with deficiencies in the RBCLC system where functionality assessments were not performed when required by OP-A-108-115, Operability Determinations. The failure to complete required functionality assessments for RBCLC system issues is a performance deficiency; however, it was determined to be minor because the RBCLC system was always functional and the performance deficiency did not adversely affect the Mitigating System cornerstone objective.

Exelon acknowledged the issue and reopened relevant IRs for shift review and performed the necessary functionality determinations. Additional corrective actions included discretionary crew clock resets for all operations crews (IR 04153271).

The inspectors also noted that Exelon documented a number of trends over the inspection timeframe. Exelon documented a trend from June 2017 to November 2017 of eight IRs concerning inadequate foreign material exclusion (FME) controls (IR 04071678). Poor FME practices have the potential to impact fuel leaks. The inspectors noted that Exelon has taken a number of actions to resolve the issue and implemented appropriate corrective actions pertaining to their FME control program onsite. Exelon also identified a trend in failures to enter requisite information into operations narrative logs (IR 04071531). Exelon independently identified several examples where a log entry was warranted but not entered in accordance with OP-AA-111-101. Corrective actions included the review of procedural requirements by all operations crews, crew clock resets and shift briefings.

Minor Performance Deficiency 71152 Annual Follow-up of Selected Issues FitzPatrick Cycle 23 Fuel Defects

On November 5, 2017, Exelon identified a third fuel defect in the cycle 23 core that has resulted in full insertion of five control rods to date to mitigate the consequences of operating with defective fuel in the current fuel cycle. Exelon initiated a root cause investigation under IR 4097375 that will not be complete until the defective fuel is cleaned and examined in detail following completion of the next refueling outage. The inspectors identified a minor performance deficiency for the calculation of shutdown margin (SDM). Exelon procedure NF-AB-110-3050 for calculation of cold SDM requires in Step 4.2 that SDM be calculated when there is uncertainty between actual core operating strategies and the core design of record.

In addition, Exelon procedure NF-AB-110-3040 for calculation of control rod pattern development and projections to end of cycle, contains a design verification check in 2, Section B, to verify that SDM is acceptable for the remainder of the fuel cycle.

Contrary to the above two procedures, from the first change in core configuration that was completed on May 18, 2017, for the first discovered fuel defect, until a re-calculation of SDM was performed on May 1, 2018, SDM was not verified to be in compliance with the SDM technical specification (TS). Corrective action to re-calculate SDM was not timely considering the potential safety significance of violating the SDM TS.

Re-calculation of SDM on May 1, 2018, confirmed that insertion of control rod 6-31 on May 18, 2017, ensured sufficient margin at that time, and for the remainder of fuel cycle 23, between the calculated value of SDM and the TS specified value. Exelon documented this issue in IR 4133208 and completed an extent of condition review to confirm there were no other deviations from design requirements for the cycle 23 core. In addition, an action has been assigned to Nuclear Fuels to review applicable processes to ensure the appropriate level of review is completed when revising rod patterns for the operating fuel cycle.

The performance deficiency was evaluated for significance in accordance with IMC 0612, Appendix B, Issue Screening, dated January 1, 2018, and IMC 0612, Appendix E, Examples of Minor Issues, dated August 11, 2009. The inspectors determined that this issue was minor because the SDM TS was not violated, and a re-configuration of the plant was not required to prevent violating the SDM TS (such as reducing plant power or changing the core rod pattern). This performance deficiency is similar to Example 2.a. in IMC 0612, Appendix E.

EXIT MEETINGS AND DEBRIEFS

Inspectors verified no proprietary information was retained or documented in this report.

On June 6, 2018, the inspector presented the inspection results by phone to Mr. Christopher Adner, Operations Director, and other members of the Exelon staff.

On June 14, 2018, the inspector presented the inspection results to Mr. Alex Sterio, Director, Site Engineering, and other members of the Exelon staff.

On June 29, 2018, the inspector presented the radiation safety inspection results to Mr. Joseph Pacher, Site Vice President, and other members of the Exelon staff.

On July 18, 2018, the inspectors presented the quarterly resident inspection results to Mr. Timothy Peter, Plant Manager, and other members of the Exelon staff.

DOCUMENTS REVIEWED

71111.01

Procedures

AOP-72, 115kV Grid Loss, Instability, or Degradation, Revision 11

AP-12.04, Seasonal Weather Preparedness, Revision 027

WC-AA-107, Seasonal Readiness, Revision 20

71111.04

Procedures

OP-17, Standby Liquid Control System, Revision 52

OP-44, 115kV System, Revision 24

Drawings

FM-21A, Flow diagram Standby Liquid Control System, Revision 37

FM-25A, Flow Diagram, High Pressure Coolant Injection System, Revision 75

71111.05

Procedures

JAF-RPT-04-00478, JAF Fire Hazards Analysis, Revision 3

OP-AA-201-003, Fire Drill Performance, Revision 16

PFP-OUT39, ISFSI Pad Location Elevation 272 Fire Area Zone Yard, Revision 2

PFP-PWR23, Fire Response Plan Motor Generator Set Room, Revision 5

Issue Report

04079478

Work Order 23332

71111.07 - Heat Sink Performance

Procedures

AOP-10, Loss of Service Water Cooling, Revision 14

AOP-13, Severe Weather, Revision 32

AOP-56, Intake Water Level Trouble, Revision 15

ER-AA-340, GL 89-13 Program Implementing Procedure, Revision 9

ER-AA-5400-1001, Raw Water Piping Integrity Management Guide, Revision 11

JAF-RPT-MULTI-01267, Generic Letter 89-13 Program Plan, Revision 4

OP-13C, RHR Service Water, Revision 14

OP-21, Emergency Service Water, Revision 38

OP-22, Diesel Generator Emergency Power, Revision 62

OP-42, Service Water System, Revision 52

OP-AA-108-111-1001, Severe Weather and Natural Disaster Guidelines, Revision 17

SEP-SW-JAF-001, NRC Generic Letter 89-13 Service Water Program, Revision 0

ST-8Q, Testing of the ESW System (IST), Revision 050

ST-9BA, EDG A and C Full Load Test and ESW Pump Operability Test, Revision 016

ST-9HA, EDG A and C Lube Oil and Cooling Water Systems Class 3 Piping Leakage Test (ISI),

Revision 001

ST-9QA, EDG A and C Full Load Test (8 Hour Run), Revision 012

SY-AA-101-146, Severe Weather Preparation and Response, Revision 2

Issue Reports

04014925

04062019

04072267

04084863

04107913

04123471

04138318

04145660

04145770

04146131

04146725*

04147154*

2012-0366

2013-2413

2015-2494

2015-4416

2016-1069

2016-1070

2016-1260

2017-1164

  • IR written as a result of this inspection

Drawings

2137-23, 67E-14 As-Built Drawing, Revision 2

FM-20B, Residual Heat Removal System 10 Flow Diagram, Revision 72

FM-46A, Service Water System 46 Flow Diagram, Revision 92

FM-46B, Emergency Service Water System 46 and 15 Flow Diagram, Revision 57

FM-93C, Engine Cooling and Lubrication Oil Emergency Diesel Generators System 93 Flow

Diagram, Revision 9

Work Orders

04654692

04682358

2626362

2691362

Miscellaneous

04088187-02, NRC Tri-Annual Ultimate Heatsink Inspection Self-Assessment, dated

June 5, 2018

EPRI NP-7552M, Heat Exchanger Performance Monitoring Guidelines, December 1991

EPRI TR-107397, Service Water Heat Exchanger Testing Guidelines, March 1998

W981-0001, Installation, Operation, and Maintenance Manual for Shell and Tube Heat

Exchangers, Revision 0

DBD-093, Design Basis Document for the Emergency Diesel Generator, Revision 13

71111.11

Procedure

OP-27, Recirculation System, Revision 81

Work Order 80455505

71111.12

Procedure

ER-AA-450, Structures Monitoring, Revision 7

Miscellaneous

Commercial Grade Dedications Sheet

Document Number 00649438

EN-MP-112, Rev 5, Shelf Life Program

Item Equivalency Evaluation 00155498

Procurement Engineering Evaluation 00135975

Procurement Engineering Evaluation 00138962

Procurement Engineering Evaluation 00163368

Purchase Order 10497183

Purchase Order 1049919

71111.13

Procedure

OP-AA-108-117, Protected Equipment Program, Revision 5

71111.15

Procedure

OP-AA-108-115, Operability Determinations, Revision 20

Condition Report

CR-JAF-2017-02196, Action Plan for Spent Fuel Pool Liner Leakage, dated January 2, 2018

Issue Reports

03992646

04008472

04013475

04060217

04137701

04138318

04142498

Work Order 1366682

Drawings

11825, Spent Fuel Pool Liner Details, Sheets 1-4, Revision 6

AP-17.03, Spent Fuel Pool Map, Revision 11

Miscellaneous

Engineering Change 624309

JAF Control Room Operator Logs dated May 13, 2017 through May 4, 2018

UT Erosion/Corrosion Examination Report No. B18UT012 and B18UT013

71111.18

Procedures

EN-DC-136, Attachment 9.4, Temporary Modification Control Form, TMOD No. 618981,

Revision 14

EN-DC-173, Attachment 9.4, Engineering Leak Repair Evaluation Checklist, TMOD No. 618981,

Revision 2

OP-27, Recirculation System, Revision 81

Work Orders

04622631-01

04622631-04

04622631-13

Drawing

FM-26A, Flow Diagram Reactor Water Recirculation System 02-2, Revision 62

Miscellaneous

MP-059.85, Temporary Leak Repair, Revision 7

TRP-3401, Hot Tap Rings, Revision 3

71111.19

Procedures

OP-27, Recirculation System, Revision 81

ST-3NA, Core Spray Loop A Class 2 Piping Leakage Test, Revision 0

ST-3PA, Core Spray Loop A Quarterly Operability Test, Revision 23

ST-76J23, West Diesel Fire Pump 76P-1 Performance Test, June 8, 2018

Work Orders

4635346-05

21820-01

80455505

2569126

2570201

2707442-01

2746386-01

71111.22

Procedures

SP-01.02, Reactor Water Sampling and Analysis, Revision 29

SP-05.02, Chemistry Surveillance and Scheduling System, Revision 4

ST-1L, Main Turbine Control Valve Instrument Channel and Valve Operability Check,

Revision 37

ST-6HA, Standby Liquid Control A Side Quarterly Operability Test, Revision 10

ST-9R, EDG System Quick-Start Operability Test and Offsite Circuitry Verification, Revision 8

ST-24J, RCIC Flow Rate and Inservice Test, Revision 48

Issue Report

04753369

Work Order 04753562

71151

Procedures

EN-LI-114, Performance Indicator Process, Revision 7

NEI 99-02, Regulatory Assessment Performance Indicator Guideline, Revision 7

SP-01.02, Reactor Water Sampling and Analysis, Revision 29

SP-05.02, Chemistry Surveillance and Scheduling System, Revision 4

71152

Procedures

MA-AA-716-008, Foreign Material Exclusion Program, Revision 13

MA-AA-716-008-1008, Reactor Services Refuel Floor FME Plan, Revision 13

NF-AB-110-1160, Generation of 3D Simulator Output Files for ShuffleWorks, Revision 9

NF-AB-110-1170, Generation of Fuel Moves Using ShuffleWorks, Revision 11

NF-AB-110-3040, Control Rod Pattern Development and Projections to EOC, Revision 19

NF-AB-110-3050, Cold Shutdown Margin, Revision 13

NF-AB-430, Failed Fuel Action Plan, Revision 14

NF-AB-431, Power Suppression Testing, Revision 8

OP-AA-108-111, Attachment 1, Adverse Condition Monitoring and Contingency Plan - JAF

Failed Fuel Monitoring, Revision 3

OSP-66.001, Management of Refueling Activities, Revision 9

RAP-7.4.04, Reactivity Anomaly Surveillance Test, Revision 18

Issue Reports

4008275

4008472

4019299

4019299

4039343

4040606

4040620

4049121

4071227

4074581

4081475

4081555

4081564

4083992

4097375

4133208

4133209

4138890

4138892

Work Order 4755156-01

Calculations

NF-AB-110-3040, Attachment 2, Design Verification Guide-Control Rod Pattern Development

and Projections to EOC, dated November 27, 2017

NF-AB-110-3050, Attachment 5, Design Verification Guide-Cold Shutdown Margin, dated

May 1, 2018

Miscellaneous

JAF Chemistry Logs, Offgas Release Rate and Sum of Six Isotopes, May 2, 2017 through

May 2, 2018

JAF Renewed Facility Operating License, DPR-59, Amendment 317

JAF Technical Requirements Manual, Revision 70

JAF UFSAR

LER 2012-004-01, Control Rods Inoperable While Entering Plant Outage, dated

January 24, 2013

LER 2015-001, COLR Thermal Limits Exceeded with Elevated Fuel Support Piece, dated

June 29, 2015

Root Cause Report, FitzPatrick Cycle 23 Fuel Defects, dated January 26, 2018

Technical Evaluation 622819, FitzPatrick Control Blade Replacement Projections: Replacement

Strategy for FitzPatrick Cycle 24 (Reload 23), dated February 2, 2018