Summary of February 16, 2021, Teleconference with Energy Harbor Nuclear Corp. to Discuss Potential License Amendment Request Related to Revising Flood Mitigation for Perry Nuclear Power Plant, Unit No. 1
ML21055A264
Person / Time
Site: Perry FirstEnergy icon.png
Issue date: 03/02/2021
From: Scott Wall
Plant Licensing Branch III
To:
Energy Harbor Nuclear Corp
Wall S
References
EPID L-2021-LRM-0016
Download: ML21055A264 (4)


Text

March 2, 2021 LICENSEE: Energy Harbor Nuclear Corp.

FACILITY: Perry Nuclear Power Plant, Unit No. 1

SUBJECT:

SUMMARY

OF FEBRUARY 16, 2021, TELECONFERENCE WITH ENERGY HARBOR NUCLEAR CORP. TO DISCUSS POTENTIAL LICENSE AMENDMENT REQUEST RELATED TO REVISING FLOOD MITIGATION FOR PERRY NUCLEAR POWER PLANT, UNIT NO. 1 (EPID L-2021-LRM-0016)

On February 16, 2021, a Category 1 public meeting was held between the U.S. Nuclear Regulatory Commission (NRC) and representatives of Energy Harbor Nuclear Corp. (EHNC, the licensee) via teleconference. The purpose of this meeting was for EHNC to provide information on a planned amendment request for Perry Nuclear Power Plant, Unit No. 1 (PNPP), related to revising the methodology used for flooding hazard analysis, with exemptions to support flood mitigation. The meeting notice and agenda dated February 3, 2021, are available in the Agencywide Documents Access and Management System (ADAMS) at Accession No. ML21047A216 and ENHCs presentation slides are available at ADAMS Accession No. ML21047A152. A list of attendees is enclosed.

During the meeting, EHNCs presentation described the scope and schedule for the proposed license amendment and associated exemptions. During the meeting, EHNC stated that it has reconstituted the site design basis minor stream probable maximum flood and local intense precipitation analyses. As a result, it plans to submit a license amendment request (LAR) to add a technical specification section to use a time-based warning method. EHNC also plans to propose the incorporation of barriers, e.g., permanent ramps, door thresholds, and permanent or temporary flood panels. EHNC will use the FLO-2D computer program for LIP analysis reconstitution. The FLO-2D program uses an unsteady state modeling technique which is a change in the analytical methodology; therefore, a LAR will be necessary. EHNC also mentioned the need for requesting exemptions to permit the crediting of all building exteriors as flood boundaries and crediting of the nonsafety-related plant storm and roof drain systems for event mitigation.

EHNC currently plans to submit the LAR and exemption requests in March 2021.

No members of the public participated in the meeting. No regulatory decisions were made at this meeting.

Please direct any inquiries to me at 301-415-2855, or Scott.Wall@nrc.gov.

Sincerely,

/RA/

Scott P. Wall, Senior Project Manager Plant Licensing Branch III Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-440

Enclosure:

List of Attendees cc: Listserv

LIST OF ATTENDEES FEBRUARY 16, 2021, PUBLIC MEETING WITH ENERGY HARBOR NUCLEAR CORP.

PERRY NUCLEAR POWER PLANT, UNIT 1 PLANNED LICENSE AMENDMENT REQUEST RELATED TO FLOOD MITIGATION Name Organization Scott Wall Nuclear Regulatory Commission (NRC)

Barbara Hayes NRC Kenneth See NRC Hosung Ahn NRC Phil Lashley Energy Harbor Nuclear Corp. (EHNC)

Stanley Gorski EHNC Mark Mlachak EHNC Daniel Lieb EHNC Jeremy Schudel EHNC Mark Bensi EHNC Kathleen Nevins EHNC Enclosure

ML21055A264 *via e-mail OFFICE NRR/DORL/LPL3/PM* NRR/DORL/LPL3/LA* NRR/DEX/EXHB/BC*

NAME SWall SRohrer BHayes DATE 02/23/2021 02/25/2021 02/26/2021 OFFICE NRR/DORL/LPL3/BC* NRR/DORL/LPL3/PM*

NAME NSalgado SWall DATE 03/02/2021 03/02/2021