Similar Documents at Perry |
---|
Category:Inspection Plan
MONTHYEARML24003A8032024-01-0303 January 2024 Notification of NRC Fire Protection Team Inspection Request for Information IR 05000440/20230052023-08-24024 August 2023 Updated Inspection Plan for Perry Nuclear Power Plant (Report 05000440/2023005) IR 05000440/20220062023-03-0101 March 2023 Annual Assessment Letter for Perry Nuclear Power Plant, Unit 1 (Report 05000440/2022006) ML23026A2112023-01-26026 January 2023 Notification of Nrc Baseline Inspection and Request for Information Inspection Report 05000440/2023002 ML22336A1222022-12-0505 December 2022 Request for Information for the NRC Quadrennial Comprehensive Engineering Team Inspection: Inspection Report 05000440/2023010 IR 05000440/20220052022-08-26026 August 2022 Updated Inspection Plan for Perry Nuclear Power Plant (Report 05000440/2022005) ML22234A1482022-08-22022 August 2022 Notification of an NRC Biennial Licensed Operator Requalification Program Inspection and Request for Information L-22-052, Deviation from BWRVIP-42 Revision 1-A, BWR Vessel and Internals Project, Low Pressure Coolant Injection (LPCI) Coupling Inspection and Flaw Evaluation Guidelines2022-03-16016 March 2022 Deviation from BWRVIP-42 Revision 1-A, BWR Vessel and Internals Project, Low Pressure Coolant Injection (LPCI) Coupling Inspection and Flaw Evaluation Guidelines IR 05000440/20210062022-03-0202 March 2022 Annual Assessment Letter for Perry Nuclear Power Plant, Unit 1 (Report 05000440/2021006) ML21257A4602021-09-15015 September 2021 Information Request to Support Upcoming Problem Identification and Resolution (Pi&R) Inspection at Perry Nuclear Power Plant IR 05000440/20210052021-09-0101 September 2021 Updated Inspection Plan for Perry Nuclear Power Plant (Report 05000440/2021005) ML21168A0662021-06-17017 June 2021 Notification of NRC Fire Protection Team Inspection Request for Information; Inspection Report 05000440/2021010 ML21099A0872021-04-0808 April 2021 Notification of NRC Design Bases Assurance Inspection (Programs) and Initial Request for Information: Inspection Report 05000440/2021012 IR 05000440/20200062021-03-0404 March 2021 Annual Assessment Letter Perry Nuclear Power Plant (Report 05000440/2020006) ML21020A0392021-01-20020 January 2021 Information Request to Support Upcoming Temporary Instruction 2515/194 Inspection; Inspection Report 05000440/2021010 ML21004A0922021-01-0404 January 2021 Notification of NRC Baseline Inspection and Request for Information, Inspection Report 05000440/2021001 ML20294A0462020-10-19019 October 2020 Notification of an NRC Biennial Licensed Operator Requalification Program Inspection and Request for Information IR 05000440/20200052020-09-0101 September 2020 Updated Inspection Plan for Perry Nuclear Power Plant (Report 05000440/2020005) IR 05000440/20190062020-03-0303 March 2020 Annual Assessment Letter Perry Nuclear Power Plant (Report 05000440/2019006) IR 05000440/20190052019-08-28028 August 2019 Updated Inspection Plan for Perry Nuclear Power Plant (Report 05000440/2019005) ML19205A4252019-07-23023 July 2019 Ltr. 07/23/19 Perry Nuclear Power Plant, Unit 1 - Notification of an NRC Triennial Heat Sink Performance Inspection and Request for Information; Inspection Report 05000440/2019004 (DRS-L.Rodriguez) IR 05000440/20180062019-03-0404 March 2019 Annual Assessment Letter for Perry Nuclear Power Plant (Report 05000440/2018006) IR 05000440/20180052018-08-28028 August 2018 Updated Inspection Plan for Perry, Unit 1 (Report 05000440/2018005) IR 05000440/20170062018-03-0202 March 2018 Annual Assessment Letter for Perry Nuclear Power Plant; Report 05000440/2017006 ML18005A6092018-01-0505 January 2018 Notification of NRC Supplemental Inspection (95001) and Request for Information IR 05000440/20170072017-12-21021 December 2017 NRC Problem Identification and Resolution Inspection Report 05000440/2017007 IR 05000440/20170052017-08-28028 August 2017 Updated Inspection Plan for Perry Nuclear Plant, Unit 1 (Report 05000440/2017005) IR 05000440/20160062017-03-0101 March 2017 Annual Assessment Letter for Perry Nuclear Power Plant, Unit 1 (Report 05000440/2016006) IR 05000440/20160052016-08-31031 August 2016 Mid-Cycle Assessment Letter for Perry Nuclear Power Plant (Report 05000440/2016005) ML16237A0812016-08-24024 August 2016 Notification of an NRC Triennial Heat Sink Performance Inspection and Request for Information; Inspection Report 05000440/2016004 IR 05000440/20150062016-03-0202 March 2016 Annual Assessment Letter for Perry, Unit 1 (Inspection Report 05000440/2015006) ML16042A1672016-02-10010 February 2016 Ltr. 02/10/16 Perry Nuclear Power Plant - Information Request for an NRC Triennial Permanent Modifications and 10 CFR 50.59 (MOD/50.59) Baseline Inspection 05000440/2016007 (AAS) IR 05000440/20150052015-09-0101 September 2015 Mid-Cycle Assessment Letter for Perry Nuclear Power Plant (Report 05000440/2015005) ML15204A8292015-07-23023 July 2015 IR 05000440/2015008, 09/21/15, Perry Nuclear Power Plant - Notification of NRC Triennial Fire Protection Baseline ML15062A6042015-03-0404 March 2015 Annual Assessment Letter for Perry Nuclear Power Plant (Report 050003440/2014001) ML14245A3172014-09-0202 September 2014 Mid-Cycle Assessment Letter for Perry Nuclear Power Plant IR 05000440/20130012014-03-0404 March 2014 Annual Assessment Letter for Perry Nuclear Power Plant (Report 05000440/2013001) ML13351A3232013-12-16016 December 2013 CDBI Request for Information ML13246A2372013-09-0303 September 2013 2013 Perry Nuclear Power Plant Mid-Cycle Letter Combined IR 05000440/20120012013-03-0404 March 2013 Annual Assessment Letter for Perry Nuclear Power Plant (Report 05000440/2012001) ML12248A3122012-09-0404 September 2012 Mid-Cycle Assessment Letter for Perry Nuclear Power Plant ML12166A1902012-06-11011 June 2012 Temporary Instruction 2515/177 Inspection Document Request IR 05000220/20110012012-03-0505 March 2012 Annual Assessment Letter (Report 05000220/2011001 and 05000440/2011001) IR 05000440/20110072012-03-0505 March 2012 Annual Assessment Letter for Perry Nuclear Power Plant (Report 05000440/2011007) IR 05000440/20110062011-09-0101 September 2011 Inspection Plan 05000440-11-006, 9/1/2011 - 12/31/2012, for Perry Nuclear Power Plant ML1106203062011-03-0404 March 2011 EOC Annual Assessment Letter and Inspection/Activity Plan ML1024400842010-09-0101 September 2010 Mid-Cycle Performance Review and Inspection Plan - Perry Nuclear Power Plant ML1006102812010-03-0303 March 2010 EOC Assessment Letter, Inspection/Activity Plan ML0924404092009-09-0101 September 2009 Perry - Mid-Cycle Performance Review and Inspection Plan IR 05000440/20090012009-03-0404 March 2009 Annual Assessment Letter - Perry Nuclear Plant (050000440/2009001) 2024-01-03
[Table view] Category:Letter
MONTHYEARIR 05000440/20230042024-01-30030 January 2024 Integrated Inspection Report 05000440/2023004 L-23-207, License Amendment Request (LAR) for Adoption of TSTF-264-A Revision 0, 3.3.9 and 3.3.10 - Delete Flux Monitors Specific Overlap Requirement SRs2024-01-24024 January 2024 License Amendment Request (LAR) for Adoption of TSTF-264-A Revision 0, 3.3.9 and 3.3.10 - Delete Flux Monitors Specific Overlap Requirement SRs L-24-017, 30-Day Voluntary Report in Accordance with Industry Groundwater Protection Initiative2024-01-24024 January 2024 30-Day Voluntary Report in Accordance with Industry Groundwater Protection Initiative IR 05000440/20234022024-01-10010 January 2024 Cyber Security Inspection Report 05000440/2023402 ML24003A8032024-01-0303 January 2024 Notification of NRC Fire Protection Team Inspection Request for Information ML23321A0472023-12-20020 December 2023 Letter to Rod L. Penfield - Perry Nuclear Power Plant, Unit 1 - License Renewal Regulatory Audit Regarding the Environmental Review of the License Renewal Application L-23-171, CFR 50.55a Request Number VR-9. Revision 0, Feedwater Check Valve Exercising Test Frequency2023-12-0808 December 2023 CFR 50.55a Request Number VR-9. Revision 0, Feedwater Check Valve Exercising Test Frequency L-23-244, Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation2023-12-0606 December 2023 Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation IR 05000440/20230112023-11-28028 November 2023 Biennial Problem Identification and Resolution Inspection Report 05000440/2023011 IR 05000440/20234032023-11-27027 November 2023 Security Baseline Inspection Report 05000440/2023403 ML23292A2972023-11-17017 November 2023 Table of Contents LAR (L-2023-LLA-0111) L-23-238, Mid-Cycle Revision to the Core Operating Limits Report for Operating Cycle 202023-11-10010 November 2023 Mid-Cycle Revision to the Core Operating Limits Report for Operating Cycle 20 L-23-052, Submittal of the Updated Safety Analysis Report, Revision 232023-10-27027 October 2023 Submittal of the Updated Safety Analysis Report, Revision 23 ML23292A2482023-10-19019 October 2023 Fws to NRC, Federal Agency Coordination Under ESA Section 7 for Perry Nuclear Plant, Unit 1, License Renewal, and Concurrence with Not Likely to Adversely Affect Determination for Northern Long-eared Bat ML23292A2472023-10-19019 October 2023 Fws to NRC, Perry Nuclear Plant, Unit 1, License Renewal List of Threatened and Endangered Species That May Occur in Your Proposed Project Location or May Be Affected IR 05000440/20230032023-10-11011 October 2023 Integrated Inspection Report 05000440/2023003 ML23249A1032023-10-0303 October 2023 Letter to Rod L. Penfield, Site Vice President-Perry Nuclear Power Plant, Unit 1-Notice of Intent to Conduct Scoping Process and Prepare an Environmental Impact Statement ML23237B4222023-09-28028 September 2023 Energy Harbor Nuclear Corp. - Vistra Operations Company LLC - Letter Regarding Order Approving Transfer of Licenses and Draft Conforming License Amendments ML23269A1242023-09-27027 September 2023 Request for Withholding Information from Public Disclosure ML23261C3642023-09-25025 September 2023 License Renewal Application Online Reference Portal ML23261B0192023-09-25025 September 2023 Aging Management Audit Plan Regarding the License Renewal Application Review ML23256A3592023-09-22022 September 2023 Determination of Acceptability and Sufficiency for Docketing, Proposed Review Schedule, and Opportunity for a Hearing Regarding the Energy Harbor Nuclear Corp. Application for License Renewal L-23-205, Supplement to Application for Order Consenting to Transfer of Licenses and Conforming License Amendments2023-09-12012 September 2023 Supplement to Application for Order Consenting to Transfer of Licenses and Conforming License Amendments L-23-206, Ohio National Pollutant Discharge Elimination System (NPDES) Permit 3IB00016 MD2023-09-12012 September 2023 Ohio National Pollutant Discharge Elimination System (NPDES) Permit 3IB00016 MD L-23-172, Quality Assurance Program Manual2023-08-31031 August 2023 Quality Assurance Program Manual IR 05000440/20234012023-08-28028 August 2023 Public - Perry Nuclear Power Plant Security Baseline Inspection Report 05000440/2023401 ML23129A1722023-08-25025 August 2023 Request for Withholding Information from Public Disclosure for Beaver Valley Power Station, Units 1 and 2; Davis Besse Nuclear Power Station, Unit 1; and Perry Nuclear Power Plant, Unit 1 IR 05000440/20230052023-08-24024 August 2023 Updated Inspection Plan for Perry Nuclear Power Plant (Report 05000440/2023005) ML23172A2852023-08-23023 August 2023 Safety Evaluation Irradiated Fuel Management Plan and Preliminary Decommissioning Cost Estimate ML23227A2202023-08-15015 August 2023 Information Request to Support Upcoming Problem Identification and Resolution Inspection at Perry Nuclear Power Plant L-23-188, Energy Harbor Nuclear Corp., Supplement to Application for Order Consenting to Transfer of Licenses and Conforming License Amendments2023-08-0707 August 2023 Energy Harbor Nuclear Corp., Supplement to Application for Order Consenting to Transfer of Licenses and Conforming License Amendments L-23-001, License Amendment Request to Remove the Table of Contents from the Technical Specifications2023-08-0707 August 2023 License Amendment Request to Remove the Table of Contents from the Technical Specifications IR 05000440/20230022023-08-0202 August 2023 Integrated Inspection Report 05000440/2023002 L-23-174, 30-Day Voluntary Report in Accordance with Industry Groundwater Protection Initiative2023-07-19019 July 2023 30-Day Voluntary Report in Accordance with Industry Groundwater Protection Initiative ML23198A2842023-07-17017 July 2023 Information Request for the Cyber-Security Baseline Inspection, Notification to Perform Inspection L-23-146, License Renewal Application for the Perry Nuclear Power Plant2023-07-0303 July 2023 License Renewal Application for the Perry Nuclear Power Plant IR 05000440/20230102023-06-29029 June 2023 Comprehensive Engineering Team Inspection Report 05000440/2023010 ML23178A2422023-06-28028 June 2023 Reassignment of the U.S. Nuclear Regulatory Commission Branch Chief in the Division of Operating Reactor Licensing for Plant Licensing Branch III L-23-050, 2022 Annual 10 CFR 50.46 Report of Changes to or Errors in Emergency Core Cooling System Evaluation Models2023-06-22022 June 2023 2022 Annual 10 CFR 50.46 Report of Changes to or Errors in Emergency Core Cooling System Evaluation Models L-23-051, Plan, Nineteenth Inservice Inspection Summary Report2023-06-22022 June 2023 Plan, Nineteenth Inservice Inspection Summary Report L-22-249, License Amendment Request for Adoption of Technical Specification Task Force Traveler TSTF-276-A Revision 2, Change TS 3.8.1. AC Sources-Operating. to Clarify the Power Factor Requirements When Performing Diesel Gener2023-06-0505 June 2023 License Amendment Request for Adoption of Technical Specification Task Force Traveler TSTF-276-A Revision 2, Change TS 3.8.1. AC Sources-Operating. to Clarify the Power Factor Requirements When Performing Diesel Gener ML23144A3562023-05-25025 May 2023 Information Meeting with a Question and Answer Session to Discuss NRC 2022 End of Cycle Plant Performance Assessment of Perry Nuclear Power Plant, Unit 1 L-23-134, Response to NRC Regulatory Issue Summary 2023-01 Preparation and Scheduling of Operator Licensing Examinations2023-05-23023 May 2023 Response to NRC Regulatory Issue Summary 2023-01 Preparation and Scheduling of Operator Licensing Examinations L-23-065, Annual Financial Report2023-05-22022 May 2023 Annual Financial Report ML23124A1742023-05-17017 May 2023 Energy Harbor Fleet Vistra License Transfer - Request for Withholding Information from Public Disclosure for Commance Peak Plant, Units 1 & 2, Beaver Valley Station, Units 1 & 2, Davis Besse Station, Unit 1 and Perry Plant, Unit 1 ML23129A0112023-05-16016 May 2023 Notice of Consideration of Approval of Indirect and Direct License Transfer for Comanche Peak Plant, Units 1 & 2, Beaver Valley Station, Units 1 & 2, Davis Besse Station, Unit 1 and Perry Plant, Unit 1 (EPID L-2023-LLM-0000) (Letter) IR 05000440/20230012023-05-0404 May 2023 Integrated Inspection Report (05000440/2023001) L-23-122, Annual Radiological Environmental Operating Report2023-04-26026 April 2023 Annual Radiological Environmental Operating Report L-23-121, Annual Radiological Effluent Release Report2023-04-26026 April 2023 Annual Radiological Effluent Release Report 2024-01-30
[Table view] Category:Request for Additional Information (RAI)
MONTHYEARML23227A2202023-08-15015 August 2023 Information Request to Support Upcoming Problem Identification and Resolution Inspection at Perry Nuclear Power Plant ML23198A2842023-07-17017 July 2023 Information Request for the Cyber-Security Baseline Inspection, Notification to Perform Inspection ML22234A1482022-08-22022 August 2022 Notification of an NRC Biennial Licensed Operator Requalification Program Inspection and Request for Information ML22182A4442022-07-0202 July 2022 Information Request for NRC Triennial Evaluations of Changes, Tests, and Experiments (50.59) Baseline Inspection Report 05000440/2022010 ML22136A2122022-05-16016 May 2022 NRR E-mail Capture - Perry Nuclear Power Plant - Request for Additional Information Regarding Proposed Inservice Inspection Alternative IR-063 ML22130A5662022-05-12012 May 2022 Information Request to Support the NRC Annual Baseline Emergency Action Level and Emergency Plan Changes Inspection ML22089A2452022-03-30030 March 2022 NRR E-mail Capture - Perry Nuclear Power Plant - Request for Additional Information for Proposed Alternative Request VR-12 ML21168A0662021-06-17017 June 2021 Notification of NRC Fire Protection Team Inspection Request for Information; Inspection Report 05000440/2021010 ML21110A6852021-04-19019 April 2021 NRR E-mail Capture - Final RAI - Perry - Request to Review the Emergency Plan ML21050A1112021-02-18018 February 2021 NRR E-mail Capture - Perry Nuclear Power Plant - Request for Additional Information for Proposed Alternative Requests VR-4, Rev. 0 and VR-6, Rev. 0 ML21050A1072021-02-18018 February 2021 NRR E-mail Capture - Perry Nuclear Power Plant - Request for Additional Information for Proposed Alternative Request VR-7, Rev. 0 ML21050A1032021-02-18018 February 2021 NRR E-mail Capture - Perry Nuclear Power Plant - Request for Additional Information for Proposed Alternative Requests VR-3, Rev. 0 and VR-5, Rev. 0 ML21049A2702021-02-16016 February 2021 NRR E-mail Capture - Perry Nuclear Power Plant - Request for Additional Information for Proposed Alternative Request SR-2, Rev. 0 (EPID: L-2021-LLR-0005) (2nd Round RAI) ML21032A3422021-02-0101 February 2021 NRR E-mail Capture - Final RAI - Perry Request for Relief - Proposed Alternative Request SR-2, Rev. 0 ML21020A0392021-01-20020 January 2021 Information Request to Support Upcoming Temporary Instruction 2515/194 Inspection; Inspection Report 05000440/2021010 ML20325A2782020-11-20020 November 2020 NRR E-mail Capture - Perry Nuclear Power Plant - Request for Additional Information for Part 73 Force-on-Force Exemption ML20289A1012020-10-0505 October 2020 NRR E-mail Capture - Final 2nd Round RAI - Perry Request for Relief - Proposed Alternative Request IR-056, Rev. 3 ML20191A0192020-07-0101 July 2020 NRR E-mail Capture - Perry Nuclear Power Plant - Request for Additional Information for Proposed Extension to License Expiration Date by Recapturing Low-Power Testing Time ML20133K0632020-05-14014 May 2020 Information Request to Support the NRC Annual Baseline Emergency Action Level and Emergency Plan Changes Inspection ML20127H8672020-05-0606 May 2020 NRR E-mail Capture - Beaver Valley, Davis-Besse, and Perry - Request for Additional Information Regarding Request for Exemptions from Part 73 Security Requalification Requirements ML20127H8692020-05-0606 May 2020 NRR E-mail Capture - Perry Nuclear Power Plant - Request for Additional Information for Proposed Alternative Request IR-054, Rev. 2 ML19192A2222019-07-18018 July 2019 Request for Additional Information Regarding Application for Order Consenting to Transfer of Licenses and Conforming License Amendments ML19143A0732019-05-29029 May 2019 FENOC Fleet - Beaver Valley, Units 1 and 2; Davis-Besse, Unit 1, Perry, Unit 1 - Supplemental Information Needed for Acceptance of Requested Licensing Action; Application for Order Consenting to License Transfer and Conforming Amendments ML19035A6552019-02-19019 February 2019 Request for Additional Information Related to the Deferral of Actions Related to Beyond-Design-Basis Flooding Hazard Reevaluations for Perry Nuclear Power Plant. ML18277A2372018-10-0202 October 2018 NRR E-mail Capture - RAI Related to Perry Request for Alternative PR-2 ML18271A2082018-09-27027 September 2018 NRR E-mail Capture - RAI Related to Request to Revise Perry'S Technical Specifications to Extend Containment Leak Rate Test Intervals ML18102B0852018-04-12012 April 2018 NRR E-mail Capture - Follow-up Request for Additional Information (RAI) FENOC FLEET-- Exemption Request for a Physical Barrier Requirement for Beaver ML18043A0102018-02-0909 February 2018 NRR E-mail Capture - FENOC--MG0010-MG0011, MG-0012, MG0013-- Request for Additional Information (RAI) - Exemption Request Security Barrier in Physical Plans ML18009A0112018-01-0808 January 2018 NRR E-mail Capture - Final RAI for Perry LAR Related to AST Implementation ML18008A0282017-12-13013 December 2017 NRR E-mail Capture - Draft RAI for Perry LAR to Revise TSs for AST ML17303B1582017-11-0707 November 2017 FENOC-Beaver Valley Power Station, Units 1 and 2, Davis-Besse Nuclear Power Station, Unit 1, Perry Nuclear Power Plant Unit 1 - Generic Letter 2016-01, Request for Supplemental Information ML17160A1102017-06-0707 June 2017 17 Perry Nuclear Power Plant - Information Request to Support the NRC Annual Baseline Emergency Action Level and Emergency Plan Changes Inspection (Mxg) ML17143A3592017-05-22022 May 2017 Request for Information for an NRC Triennial Baseline Design Bases Assurance Inspection (Team): Inspection Report 05000440/2017008 (Njfa) ML17115A4212017-04-25025 April 2017 NRR E-mail Capture - Withdrawal of Draft RAI Regarding Perry'S LAR Re TSTF-501, Revision 1 ML17114A1532017-04-0606 April 2017 NRR E-mail Capture - Draft RAI for Perry LAR Re TSTF-501, Revision 1 ML16364A2482016-12-28028 December 2016 Notification of NRC Baseline Inspection and Request for Information 05000440/2017001 ML16327A0182016-11-23023 November 2016 Request for Additional Information Related to License Amendment Request for Upper Containment Pool Gate Installation and Drain Down of the Reactor Cavity Portion of the Upper Containment Pool (TAC MF7476) (L-16-083) ML16279A0432016-10-0606 October 2016 Request for Additional Information Related to License Amendment Request for Upper Containment Pool Gate Installation During Modes 1, 2, & Drain Down of Upper Containment Pool During Mode 3 IR 05000440/20215012016-04-19019 April 2016 Perry Nuclear Power Plant - Request for Additional Information Regarding VIO 05000440/215010-01 ML16067A2812016-03-10010 March 2016 Request for Additional Information Related to Emergency Action Level Scheme Change License Amendment Request (CAC No. MF7046)(L-15-257) ML16064A2792016-03-0101 March 2016 NRR E-mail Capture - Perry EAL Scheme Change LAR (CAC No. MF7046) Draft Request for Additional Information IR 05000440/20150102016-02-0101 February 2016 Ltr. 02/01/16 Request for Additional Information VIO 05000440/2015010-01. (Jgc) ML15351A0312015-12-18018 December 2015 Request for Additional Information Related to Application for Transfer of Control of License and Conforming License Amendment (CAC No. MF6412)(L-15-195) ML15096A0512015-04-13013 April 2015 Unit, No. 1 - Request for Additional Information Concerning Battery Surveillance Test Frequencies ML15034A6132015-03-0303 March 2015 Request for Additional Information Regarding Phase 2 Staffing Assessment Provided Pursuant to Title 10 of the Code of Federal Regulations Part 50, Section 50.54(f) Request Regarding Near-Term Task Force Recommendation 9.3 ML15022A1802015-01-21021 January 2015 Request for Inspection ML15012A6572015-01-20020 January 2015 Request for Additional Information Concerning Changes to Safety Limit Minimum Critical Power Ratio During Single Loop Operation (TAC No. Mf 5007)(L-14-325) ML15014A2832015-01-15015 January 2015 Request for Additional Information Concerning Alternative Accident Source Term Design Bases (TAC No. MF3197)(L-13-306) ML14323A6662014-12-0303 December 2014 Request for Additional Information Concerning Changes to Pressure Temperature Curves (TAC No. MF4351)(L-14-150) ML14232A2252014-09-0909 September 2014 Request for Additional Information Concerning Relocation of Surveillance Frequencies to Control Licensee Control (TAC No. MF3720)(L-14-106) 2023-08-15
[Table view] |
See also: IR 05000440/2021010
Text
June 17, 2021
Mr. Rod Penfield
Site Vice President
Energy Harbor Nuclear Corp.
Perry Nuclear Power Plant
10 Center Road,
Perry, OH 44081
SUBJECT: PERRY NUCLEAR POWER PLANTNOTIFICATION OF NRC FIRE
PROTECTION TEAM INSPECTION REQUEST FOR INFORMATION;
INSPECTION REPORT 05000440/2021010
Dear Mr. Penfield:
The purpose of this letter is to notify you that the U.S. Nuclear Regulatory Commission (NRC)
Region III staff will conduct a Fire Protection Team Inspection at your Perry Nuclear Power
Plant beginning September 13, 2021. The inspection will be conducted in accordance with
Inspection Procedure 71111.21N.05, Fire Protection Team Inspection, dated June 12, 2019.
The inspection will verify that plant SSCs and/or administrative controls credited in the approved
Fire Protection Program can perform their licensing basis function.
The schedule for the inspection is as follows:
Preparation week (R-III office): September 6 - 10, 2021
Week 1 of onsite inspection: September 13 - 17, 2021
Week 2 of onsite inspection: September 27 - October 1, 2021
Experience has shown that the baseline fire protection team inspections are extremely resource
intensive, both for the NRC inspectors and the licensee staff. In order to minimize the
inspection impact on the site and to ensure a productive inspection for both organizations, we
have enclosed a request for documents needed for the inspection. These documents have
been divided into three groups.
The first group lists information necessary to aid the inspection team in choosing specific
focus areas for the inspection and to ensure that the inspection team is adequately
prepared for the inspection. It is requested that this information be provided to the lead
inspector via mail or electronically no later than August 20, 2021.
The second group of requested documents consists of those items that the team will
review, or need access to, during the inspection. Please have this information available
by the first day of the first onsite inspection week September 13, 2021.
R. Penfield -2-
The third group lists the information necessary to aid the inspection team in tracking
issues identified as a result of the inspection. It is requested that this information be
provided to the lead inspector as the information is generated during the inspection. It is
important that all of these documents are up to date and complete in order to minimize
the number of additional documents requested during the preparation and/or the onsite
portions of the inspection.
The lead inspector for this inspection is Mr. A. Dahbur. We understand that our regulatory
contact for this inspection is Mr. G. Dujanevic of your organization. If there are any questions
about the inspection or the material requested, please contact the lead inspector at
630-829-9810 or via e-mail at Alan.Dahbur@nrc.gov.
This letter does not contain new or amended information collection requirements subject to the
Paperwork Reduction Act of 1995 (44 U.S.C. 3501 et seq.). Existing information collection
requirements were approved by the Office of Management and Budget, Control Number
3150-0011. The NRC may not conduct or sponsor, and a person is not required to respond to,
a request for information or an information collection requirement unless the requesting
document displays a currently valid Office of Management and Budget Control Number.
This letter and its enclosure will be made available for public inspection and copying at
http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in
accordance with Title 10 of the Code of Federal Regulations, Part 2.390, Public Inspections,
Exemptions, Requests for Withholding.
Sincerely,
/RA/
Alan Dahbur, Senior Reactor Inspector
Engineering Branch 3
Division of Reactor Safety
Docket No. 50-440
License No. NPF-58
Enclosure:
Fire Protection Team Inspection
Supporting Documentation
cc: Distribution via LISTSERV
R. Penfield -3-
Letter to Rod Penfield from Alan Dahbur dated June 17, 2021.
SUBJECT: PERRY NUCLEAR POWER PLANTNOTIFICATION OF NRC FIRE
PROTECTION TEAM INSPECTION REQUEST FOR INFORMATION;
INSPECTION REPORT 05000440/2021010
DISTRIBUTION:
Jessie Quichocho
Aaron McCraw
RidsNrrPMPerry Resource
RidsNrrDorlLpl3
RidsNrrDroIrib Resource
John Giessner
Mohammed Shuaibi
Jamnes Cameron
Allan Barker
DRPIII
DRSIII
ADAMS Accession Number: ML21168A066
Publicly Available Non-Publicly Available Sensitive Non-Sensitive
OFFICE RIII
NAME ADahbur:mb
DATE 06/17/2021
OFFICIAL RECORD COPY
FIRE PROTECTION TEAM INSPECTION SUPPORTING DOCUMENTATION
I. Information Requested prior to the Inspection Preparation Week
The following information is requested by August 20, 2021. If you have any questions
regarding this request, please call the lead inspector as soon as possible. All information
should be sent to Alan Dahbur (e-mail address Alan.Dahbur@nrc.gov). Electronic media is
preferred. The preferred file format is a searchable pdf or Microsoft Excel file on a
compact disk (CD). The CD should be indexed and hyper-linked to facilitate ease of use, if
possible. Please provide three copies of each CD submitted (one for each inspector).
1. One set of hard-copy documents for facility layout drawings which identify plant fire area
delineation; areas protected by automatic fire suppression and detection; and locations
of fire protection equipment.
2. Licensing Information:
a. All Nuclear Regulatory Commission (NRC) Safety Evaluation Reports (SERs)
applicable to fire protection (specifically including those SERs referenced by the
plant fire protection license condition) and all licensing correspondence referenced
by the SERs;
b. All licensing correspondence associated with the comparison to Standard Review
Plan (NUREG-0800), Section 9.5.1 or equivalent for licensing purposes;
c. Exemptions from Title 10 of the Code of Federal Regulations (CFR), Part 50.48 and
10 CFR Part 50, Appendix R, and associated licensing correspondence;
d. For pre-1979 plants, all licensing correspondence associated with those sections of
10 CFR Part 50, Appendix R, that are not applicable to the plant under
10 CFR 50.48(b)(1). Specifically, the licensing correspondence associated with
those fire protection features proposed or implemented by the licensee that have
been accepted by the NRC staff as satisfying the provisions of Appendix A to Branch
Technical Position APCSB 9.5-1 reflected in the NRC fire protection SERs issued
before February 19, 1981, (10 CFR 50.48(b)(1)(i)); or those fire protection features,
which were accepted by the NRC staff in comprehensive fire protection SERs issued
before Appendix A to Branch Technical Position APCSB 9.5-1 was published in
August 1976 (10 CFR 50.48(b)(1)(ii)); and
e. The final safety analysis report sections applicable to fire protection, FHA, and SSA
in effect at the time of original licensing.
3. Fire Protection Program:
a. A listing of changes made to the Fire Protection Program since the last triennial fire
protection inspection;
b. For pre-1979 plants, a listing of the protection methodologies identified under
10 CFR Part 50, Appendix R, Section III.G used to achieve compliance for
fire zones/areas. That is, please specify whether 3-hour rated fire barriers;
(Section III.G.2.a), 20-foot separation along with detection and suppression;
(Section III.G.2.b), 1-hour rated fire barriers with detection and suppression;
Enclosure
FIRE PROTECTION TEAM INSPECTION SUPPORTING DOCUMENTATION
(Section III.G.2.c), or alternative shutdown capability; (Section III.G.3) is used as a
strategy for each selected fire zone/area;
c. A list of Generic Letter 86-10 evaluations (i.e., a list of adverse to safe shutdown
evaluations);
d. A list of applicable codes and standards related to the design of plant fire protection
features. The list should include National Fire Protection Association (NFPA) code
versions committed to (i.e., the NFPA Codes of Record);
e. List of plant deviations from code commitments and associated evaluations;
f. Fire Protection Program and/or Fire Protection Plan document;
g. (If available) Fire Probabilistic Risk Assessment (PRA) Summary Report or full PRA
document (if summary document not available);
h. List of the top 25 highest fire CDF scenarios for each unit;
i. List of Fire Areas/Zones ranked by contribution to CDF, (i.e., ranking of highest to
lowest risk fire areas/zones);
j. List of the top 25 highest fire LERF scenarios for each unit; and
k. Risk ranking of operator actions and/or recovery actions from your site-specific PRA
sorted by RAW and human reliability worksheets for these items.
4. Facility Information:
a. Piping and instrumentation (flow) diagrams showing the components used to achieve
and maintain hot standby and cold shutdown for fires outside the control room, and
those components used for those areas requiring alternative shutdown capability;
b. One-line schematic drawings of the electrical distribution system for 4160 Volts
alternating current (Vac) down to 480 Vac;
c. One-line schematic drawings of the electrical distribution system for 250 Volts direct
current (Vdc) and 125 Vdc systems as applicable;
d. Logic diagrams showing the components used to achieve and maintain hot standby
and cold shutdown; and
e. Safe shutdown cable routing database (requested electronically, such as on compact
disc, if available).
5. Operations Response for Fire Protection:
a. Pre-fire plans for fire zones/areas; and
2
FIRE PROTECTION TEAM INSPECTION SUPPORTING DOCUMENTATION
b. Plant operating procedures which specify the initial operations response to a fire
alarm or annunciator.
6. Corrective Actions:
a. Listing of open and closed fire protection condition reports (i.e., problem identification
forms and their resolution reports) since the date of the last triennial fire protection
inspection; and
b. List of current fire impairments, including duration.
7. General Information:
a. A listing of abbreviations and/or designators for plant systems;
b. Organization charts of site personnel down to the level of fire protection staff
personnel; and
c. A phone list for onsite licensee personnel.
II. Information Requested to Be Available on First Day of the FIRST ONSITE Inspection
Week (SEPTEMBER 13, 2021)
The following information is requested to be provided on the first day of inspection. It is
requested that this information be provided on three sets of CDs (searchable, if possible).
1. Program Procedures:
a. Procedures for:
i. Administrative controls (such as allowed out of service times and compensatory
measures) for fire protection systems and components;
ii. Control of transient combustibles; and
iii. Control of hot work.
b. List of maintenance and surveillance testing procedures for alternative shutdown
capability and fire barriers, detectors, pumps, and suppression systems; and
c. List of maintenance procedures which routinely verify fuse breaker coordination in
accordance with the post-fire safe shutdown coordination analysis.
2. Design and Equipment Information (for only selected fire zone/area(s) and/or SSCs
to be determined during inspection preparation week):
a. Coordination calculations and/or justifications that verify fuse/breaker coordination for
SSCs that are fed off of the same electrical buses as components in the protected
safe shutdown train;
3
FIRE PROTECTION TEAM INSPECTION SUPPORTING DOCUMENTATION
b. Copies of significant fire protection and post-fire safe shutdown related design
change package descriptions (including their associated 10 CFR 50.59 evaluations)
and Generic Letter 86-10 (or adverse to safe shutdown) evaluations;
c. Gaseous suppression system pre-operational testing, if applicable, for selected fire
zones/areas;
d. Hydraulic calculations and supporting test data which demonstrate operability for
water suppression systems;
e. Alternating current (ac) coordination calculations for 4160 Vac down to 480 Vac
electrical systems; and
f. List of all fire protection or Appendix R calculations.
3. Assessment and Corrective Actions:
The three most recent fire protection Quality Assurance audits and/or fire protection
self-assessments.
4. Any updates to information previously provided.
5. Classic Fire Protection (for only selected fire zone/area(s) and/or SSCs to be
determined during inspection preparation week):
a. Copy of fire protection program implementing procedures (e.g., administrative
controls, surveillance testing, and fire brigade);
b. Pre-fire plans for selected fire area(s); and
c. List of fire protection system design changes completed in the last 3 years.
6. Electrical (for only selected fire zone/area(s) and/or SSCs to be determined during
inspection preparation week):
a. Nuclear safety circuit coordination analysis for fuse and breaker coordination of safe
shutdown components;
b. Administrative or configuration control procedures that govern fuse replacement
(e.g., fuse control procedures);
c. Maintenance procedures that verify breaker over-current trip settings to ensure
coordination remains functional, for post-fire nuclear safety capability components;
d. Last surveillance demonstrating operability of those components operated from the
primary control stations;
e. Schematic or elementary diagrams for circuits (only for selected SSCs) to be
reviewed (C-size paper drawings);
4
FIRE PROTECTION TEAM INSPECTION SUPPORTING DOCUMENTATION
f. Cable routing for components and equipment credited for post-fire nuclear safety
capability systems and components;
g. List of post-fire nuclear safety capability system and component design changes
completed, in the last 3 years; and
h. List of identified fire induced circuit failure analyses.
7. Operations:
a. List of procedures that implement Cold Shutdown Repairs (if applicable for selected
fire area);
b. For Cold Shutdown Repairs, provide the following:
i. Procedure for inventory and inspection (i.e., needed tools, material, etc.); and
ii. Most recent inspection and inventory results.
c. List of licensed operator Job Performance Measures for operator actions required to
achieve and maintain post-fire nuclear safety performance criteria (for selected SSCs
and fire area);
d. For Radio communications, provide the following:
i. Communications Plan for firefighting and post-fire safe shutdown manual actions;
ii. Repeater locations;
iii. Cable routing for repeater power supply cables;
iv. Radio coverage test results; and
v. Radio Dead Spot locations in the plant.
e. Environmental and habitability evaluations for post-fire operator actions
(temperature, smoke, humidity, SCBAs, etc.).
8. Administrative Control, Oversight, and Corrective Action Programs:
a. Self-assessments, peer assessments, and audits of fire protection activities for the
last 3 years;
b. Self-assessments, peer assessments, and audits of post-fire nuclear safety
capability methodology for the last 3 years; and
c. List of fire event analysis reports for the last 3 years.
9. Any updates to information previously provided.
III. Information Requested to Be Provided Throughout the Inspection
1. Copies of any corrective action documents generated as a result of the inspection
teams questions or queries during this inspection.
5
FIRE PROTECTION TEAM INSPECTION SUPPORTING DOCUMENTATION
2. Copies of the list of questions submitted by the inspection team members and the
status/resolution of the information requested (provided daily during the inspection
to each inspection team member).
6