Notification of NRC Baseline Inspection and Request for Information 05000440/2017001
ML16364A248
Person / Time
Site: Perry FirstEnergy icon.png
Issue date: 12/28/2016
From: Vijay Meghani
NRC/RGN-III/DRS/EB1
To: Hamilton D
FirstEnergy Nuclear Operating Co
References
IR 2017001
Download: ML16364A248 (6)


See also: IR 05000440/2017001

Text

UNITED STATES

NUCLEAR REGULATORY COMMISSION

REGION III

2443 WARRENVILLE RD. SUITE 210

LISLE, IL 60532-4352

December 28, 2016

Mr. David Hamilton

Site Vice President

FirstEnergy Nuclear Operating Company

Perry Nuclear Power Plant

P. O. Box 97, 10 Center Road, A-PY-A290

Perry, OH 44081-0097

SUBJECT: PERRY NUCLEAR POWER PLANT - NOTIFICATION OF NRC BASELINE

INSPECTION AND REQUEST FOR INFORMATION 05000440/2017001

Dear Mr. Hamilton:

On March 6, 2017, the U.S. Nuclear Regulatory Commission (NRC) will begin the Baseline

Inservice Inspection Procedure 71111.08. This onsite inspection is scheduled to be performed

March 6 - 10, 2017.

Experience has shown that this inspection is resource intensive both for the NRC inspector and

your staff. In order to minimize the impact to your onsite resources, and to ensure a productive

inspection for both sides, we have enclosed a request for documents needed for this inspection.

These documents have been divided into two groups.

The first group identifies information necessary to ensure that the inspector is adequately

prepared. The second group identifies the information the inspector will need upon arrival at

the site. It is important that all of these documents are up-to-date, and complete, in order to

minimize the number of additional documents requested during the preparation and/or the

onsite portions of the inspection.

We have discussed the schedule for inspection activities with your staff and understand that our

regulatory contact for this inspection will be Mr. L. Zerr, of your organization. If there are any

questions about this inspection or the material requested, please contact the lead inspector

Mr. V. Meghani at 630-829-9751, or via e-mail at Vijay.Meghani@nrc.gov.

This letter does not contain new or amended information collection requirements subject to

the Paperwork Reduction Act of 1995 (44 U.S.C. 3501 et seq.). Existing information collection

requirements were approved by the Office of Management and Budget, Control Number

3150-0011. The NRC may not conduct or sponsor, and a person is not required to respond to,

a request for information or an information collection requirement unless the requesting

document displays a currently valid Office of Management and Budget Control Number.

D. Hamilton -2-

In accordance with Title 10 of the Code of Federal Regulations (10 CFR) 2.390, Public

Inspections, Exemptions, Requests for Withholding, of the NRC's "Rules of Practice," a copy

of this letter and its enclosure will be available electronically for public inspection in the NRCs

Public Document Room or from the Publicly Available Records (PARS) component of the NRC's

Agencywide Documents Access and Management System (ADAMS). ADAMS is accessible

from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic

Reading Room).

Sincerely,

/RA/

Vijay Meghani, Reactor Inspector

Engineering Branch 1

Division of Reactor Safety

Docket No. 50-440

License No. NPF-58

Enclosure:

Baseline Inservice Inspection Document Request

cc: Distribution via LISTSERV

BASELINE INSERVICE INSPECTION DOCUMENT REQUEST

Inspection Report: 05000440/2017001

Inspection Dates: March 6 - 10, 2017

Inspection Procedures: Inspection Procedure 71111-08, Inservice Inspection

Lead Inspector: Vijay Meghani, DRS

630-829-9751

Vijay.Meghani@nrc.gov

A. Information for the In-Office Preparation Week

The following information (electronic copy CD ROM if possible) is requested by

February 27, 2017, to facilitate the selection of specific items that will be reviewed during

the onsite inspection week. The inspector will select specific items from the information

requested below and request a list of additional documents needed onsite to your staff.

We request that the specific items selected from the lists be available and ready for

review on the first day of inspection. If you have any questions regarding this

information, please call the inspector as soon as possible.

1. For the upcoming outage, a detailed schedule and description of:

a. Non-Destructive Examinations (NDEs) planned for Class 1 and 2 Systems

and containment, performed as part of your American Society of Mechanical

Engineers (ASME) Code Inservice Inspection (ISI) Program (include edition

and addenda of Code committed to), and NDEs planned for other systems

performed as part of a Risk-Informed ISI Program, or other augmented

inspection programs commitments, as part of an industry initiative. For each

weld examination, include the weld identification number, description of weld

(component name), category, class, type of exam and procedure number, and

date of examination; and

b. welding on Code Class 1, 2, or 3 components

2. A copy of the NDE procedures and welding procedures used to perform the activities

identified in A.1 (including NDE calibration and flaw characterization/sizing procedures

and Welding Procedure Qualification Records). For ultrasonic examination procedures

qualified in accordance with Appendix VIII, of Section XI of the ASME Code, provide

documentation supporting the procedure qualification (e.g., the Electric Power

Research Institute performance demonstration qualification summary sheets).

3. A copy of ASME Section XI, Code Relief Requests applicable to the examinations

identified in A.1. A copy of the 10-year ISI Program showing those required exams

scheduled to be performed this outage, and those which have been completed.

4. A list identifying NDE reports (ultrasonic, radiography, magnetic particle, or dye

penetrant), which have identified relevant indications on Code Class 1 and 2

Systems since the beginning of the last refueling outage.

Enclosure

BASELINE INSERVICE INSPECTION DOCUMENT REQUEST

5. List with short description of the welds in Code Class 1 and 2 Systems, which have

been fabricated due to component repair/replacement activities since the beginning

of the last refueling outage and identify the system, weld number, and reference

applicable documentation (e.g., NIS-2 forms with definitions of system and

component acronyms).

6. If reactor vessel weld examinations required by the ASME Code are scheduled to

occur during the inspection period, provide a detailed description of the welds to be

examined, and the extent of the planned examination.

7. List with description of ISI related issues such as piping degradation or damage

(e.g., cracks, wall thinning, wear, microbiologically induced corrosion) or errors

identified in piping examinations that have been entered into your corrective action

system since the beginning of the last refueling outage. Also, include a list of

corrective action records associated with foreign material introduced/identified in

the reactor vessel or reactor coolant system since the beginning of the last refueling

outage.

8. Copy of any Title 10 Code of Federal Regulations, Part 21 reports applicable to your

structures, systems, or components within the scope of Section XI of the ASME

Code that have been identified since the beginning of the last refueling outage.

B. Onsite Information to be Provided to the Inspector on the First Day of the

Inspection (e.g., Following the Entrance Meeting). Please Provide Hard Copies

(e.g., Paper Records) of the Following Documents.

1. For welds selected by the inspector from A.1.b and A.6 above, provide copies of the

following documents:

a. Document of the weld number and location (e.g., system, train, branch);

b. Document with a detail of the weld construction (e.g., drawing);

c. Applicable portions of the Design Specification and applicable Code of

construction for the weldment (e.g., B31.1 or ASME Section III);

d. Applicable Code Edition and Addenda for weld procedure qualification;

e. Applicable weld procedures and completed weld data sheets used to fabricate

the welds;

f. Copies of procedure qualification records supporting the weld procedures;

g. Copies of welders performance qualification records;

h. Copies of mechanical test reports identified in the procedure qualification

records above;

i. Copies of the non-conformance reports for the selected welds;

j. Access to radiographs and equipment to view radiographs of the selected welds;

and

2

BASELINE INSERVICE INSPECTION DOCUMENT REQUEST

k. Copies of the pre-service examination records for the selected welds.

2. For the ISI-related corrective action issues selected by the inspector from Item A.7

above, provide a copy of the corrective actions and supporting documentation.

3. For the NDE reports with relevant indications on Code Class 1 and 2 Systems

selected by the inspector from Item A.4 above, provide a copy of the examination

records and associated corrective action documents.

4. Updated schedules for Item A.1 (including schedule showing contingency repair

plans if available).

5. Fabrication Drawings (D size) of the reactor vessel welds if any are to be examined

during the outage. Also provide any drawings used by NDE vendors to locate these

welds.

6. Provide copies of the following standards at the onsite U.S. Nuclear Regulatory

Commission inspection location for the duration of the inspection:

a. Sections V, IX, and XI of the ASME Code with Editions applicable to the

Inservice Inspection Program and the Repair/Replacement Program; and

b. Copy of the performance demonstration initiative (PDI) generic procedures with

the latest applicable Revisions that support site qualified ultrasonic examination

of piping welds and components (e.g., PDI-UT-1, PDI-UT-2, PDI-UT-3, PDI-UT-

10 etc.).

7. Provide training (e.g., Scaffolding, Fall Protection, Foreign Material Exclusion) if

required to access the NDEs selected by the inspector for observation.

If you have questions regarding the information requested, please contact the lead inspector.

3

D. Hamilton -3-

Letter to David Hamilton from Vijay Meghani dated December 28, 2016

SUBJECT: PERRY NUCLEAR POWER PLANT - NOTIFICATION OF NRC BASELINE

INSPECTION AND REQUEST FOR INFORMATION 05000440/2017001

DISTRIBUTION:

Jeremy Bowen

RidsNrrPMPerry Resource

RidsNrrDorlLpl3-2 Resource

RidsNrrDirsIrib Resource

Cynthia Pederson

Darrell Roberts

Richard Skokowski

Allan Barker

Carole Ariano

Linda Linn

DRPIII

DRSIII

ADAMS Accession Number ML16364A248

OFFICE RIII RIII RIII RIII

NAME VMeghani:cl

DATE 12/28/16

OFFICIAL RECORD COPY