IR 05000498/2020005: Difference between revisions
StriderTol (talk | contribs) (StriderTol Bot change) |
StriderTol (talk | contribs) (StriderTol Bot change) |
||
Line 18: | Line 18: | ||
=Text= | =Text= | ||
{{#Wiki_filter: | {{#Wiki_filter:ber 1, 2020 | ||
==SUBJECT:== | |||
UPDATED INSPECTION PLAN FOR SOUTH TEXAS PROJECT ELECTRIC GENERATING STATION, UNITS 1 AND 2 - (REPORT 05000498/2020005 AND 05000499/2020005) | |||
==Dear Mr. Powell:== | |||
The enclosed inspection plan lists the inspections scheduled through June 30, 2022, for South Texas Project Electric Generating Station, Units 1 and 2. The U.S. Nuclear Regulatory Commission (NRC) provides the inspection plan to allow for the resolution of any scheduling conflicts and personnel availability issues. Routine inspections performed by resident inspectors are not included in the inspection plan. You should be aware that the agency is pursuing potential changes to the Reactor Oversight Process (ROP), including changes to engineering inspections (SECY-18-0113, Recommendations for Modifying the Reactor Oversight Process Engineering Inspections), and other changes to the baseline inspection program described in SECY-19-0067, Recommendations for Enhancing the Reactor Oversight Process. Should these changes to the ROP be implemented, the engineering and other region-based inspections are subject to change in scope, as well as schedule, beginning in January 2020. The inspections listed during the last 12 months of the inspection plan are tentative and may be revised. The NRC will contact you as soon as possible to discuss changes to the inspection plan should circumstances warrant any changes. | |||
In response to the COVID-19 public health emergency (PHE), the NRC is adjusting inspection plans and schedules in order to safeguard the health and safety of both NRC and licensee staff while still effectively implementing the ROP. Each planned inspection is being carefully reviewed in order to determine if any portions of the inspection can be performed remotely, determine how best to perform on-site portions to minimize personnel health risks, and adjust inspection schedules if needed. This is done in accordance with guidance contained in the May 28, 2020, memorandum, Inspection Guidance During Transition From COVID-19 Mandatory Telework (Agencywide Documents Access and Management System (ADAMS) | |||
Accession Number ML20141L766). For inspections requiring extensive coordination with offsite organizations, such as evaluated emergency preparedness exercises, NRC guidance and frequently asked questions for security and emergency preparedness can be found here: | |||
https://www.nrc.gov/about-nrc/covid-19/security-ep/. Similarly, the NRC has developed guidance if force-on-force inspections cannot be completed as scheduled due to an emergency, such as the COVID-19 PHE. These changes help ensure the health and safety of both NRC and licensee staff while maintaining the NRCs important safety and security mission during the COVID-19 PHE. The attached inspection plan is accurate on the date of issuance, but remains subject to change based on approval of potential exemption requests or other changes needed due to changing conditions in the COVID-19 PHE. NRC staff will contact your appropriate regulatory affairs staff in order to coordinate inspection planning and scheduling. | |||
The NRC will also be performing baseline inspections of licensee cyber security programs. The specific schedule and procedure to be used for these inspections are being developed by the NRC staff. The staff expects to communicate the schedule for these inspections to each utility separately. | |||
In accordance with Title 10 of the Code of Federal Regulations (10 CFR) 2.390 of the NRCs Rules of Practice, a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS). ADAMS is accessible from the NRC Web site at https://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room). | |||
Please contact me at 817-200-1148 with any questions you have regarding this letter. | |||
Sincerely, Jeffrey Digitally signed by Jeffrey Josey Josey Date: 2020.08.31 07:57:06 -05'00' | |||
Jeffrey E. Josey, Chief Reactor Projects Branch A Division of Reactor Projects Docket Nos. 05000498 and 05000499 License Nos. NPF-76 and NPF-80 Enclosure: | |||
Inspection Plan cc w/ encl: Distribution via LISTSERV | |||
ML20240A321 SUNSI Review Non-Sensitive Publicly Available | |||
Sensitive Non-Publicly Available OFFICE SPE:DRP/A C:DRP/A NAME HFreeman JJosey SIGNATURE /RA/ /RA/ | |||
DATE 08/24/2020 08/25/2020 | |||
IP 22 Inspection Activity Plan Report South Texas Project 07/01/2020 - 06/30/2022 Unit Start End Activity CAC Title Staff Count 2020 Initial Exam - STP 6 1, 2 07/12/2020 07/18/2020 EXAD 000500 LICENSE EXAM ADMINISTRATION (EXAD) | |||
1, 2 07/19/2020 07/25/2020 EXAD 000500 LICENSE EXAM ADMINISTRATION (EXAD) | |||
Heat Sink Performance (Triennial) - STP 2 1, 2 07/20/2020 07/24/2020 IP 71111.07T 000700 Heat Sink Performance Security Access Control .02 - STP 1 1, 2 08/24/2020 08/28/2020 IP 71130.02 000734 Access Control 1, 2 08/24/2020 08/28/2020 IP 71130.09 001656 Security Plan Changes 1, 2 08/24/2020 08/28/2020 IP 71151 001338 Performance Indicator Verification Security Equipment .04 and Training .07 - STP 2 1, 2 08/24/2020 08/28/2020 IP 71130.04 000736 Equipment Performance, Testing, and Maintenance 1, 2 08/24/2020 08/28/2020 IP 71130.07 000739 Security Training RS58 Radiation Safety - STP 4 1, 2 09/14/2020 09/18/2020 IP 71124.05 000729 Radiation Monitoring Instrumentation 1, 2 09/14/2020 09/18/2020 IP 71124.08 000732 Radioactive Solid Waste Processing & Radioactive Material Handling, Storage, & | |||
Transportation MC&A - Material Control & Accounting - STP 1 1, 2 09/14/2020 09/18/2020 IP 71130.11 000742 Material Control and Accounting (MC&A) | |||
Biennial PI&R - STP 4 1, 2 10/18/2020 11/14/2020 IP 71152B 000747 Problem Identification and Resolution EP Program Inspection - STP 1 1, 2 10/26/2020 10/30/2020 IP 71114.02 000717 Alert and Notification System Testing 1, 2 10/26/2020 10/30/2020 IP 71114.03 000718 Emergency Response Organization Staffing and Augmentation System 1, 2 10/26/2020 10/30/2020 IP 71114.04 000719 Emergency Action Level and Emergency Plan Changes 1, 2 10/26/2020 10/30/2020 IP 71114.05 000720 Maintenance of Emergency Preparedness 1, 2 10/26/2020 10/30/2020 IP 71151 001397 Performance Indicator Verification FORCE-ON-FORCE PLANNING AND EXERCISE WEEKS - STP 6 1, 2 01/11/2021 01/15/2021 IP 71130.03 000735 Contingency Response - Force-On-Force Testing This report does not include INPO and OUTAGE activities. Page 1 of 3 This report shows only on-site and announced inspection procedures. | |||
8/27/2020 8:20:16 AM | |||
IP 22 Inspection Activity Plan Report South Texas Project 07/01/2020 - 06/30/2022 Unit Start End Activity CAC Title Staff Count FORCE-ON-FORCE PLANNING AND EXERCISE WEEKS - STP 6 1, 2 02/01/2021 02/05/2021 IP 71130.03 000735 Contingency Response - Force-On-Force Testing Security FFD .08 - STP 1 1, 2 01/25/2021 01/29/2021 IP 71130.08 000740 Fitness For Duty Program Inservice Inspection 2RF21 - STP 1 2 03/22/2021 04/02/2021 IP 71111.08P 000702 Inservice Inspection Activities (PWR) | |||
RP 1,3,PI 2 1, 2 03/29/2021 04/02/2021 IP 71124.01 000725 Radiological Hazard Assessment and Exposure Controls 1, 2 03/29/2021 04/02/2021 IP 71124.03 000727 In-Plant Airborne Radioactivity Control and Mitigation In-Office EP Exercise Scenario Review - STP 4 1, 2 05/02/2021 06/30/2021 IP 71114.08 000723 Exercise Evaluation Scenario Review STP 2021 INITIAL EXAM 6 1, 2 06/06/2021 06/12/2021 OV 000956 VALIDATION OF INITIAL LICENSE EXAMINATION (OV) | |||
1, 2 07/11/2021 07/17/2021 EXAD 000500 LICENSE EXAM ADMINISTRATION (EXAD) | |||
EP Biennial Exercise and PI Inspection 4 1, 2 07/12/2021 07/16/2021 IP 71114.01 000716 Exercise Evaluation 1, 2 07/12/2021 07/16/2021 IP 71151 001397 Performance Indicator Verification RP 6,7 2 1, 2 07/19/2021 07/23/2021 IP 71124.06 000730 Radioactive Gaseous and Liquid Effluent Treatment 1, 2 07/19/2021 07/23/2021 IP 71124.07 000731 Radiological Environmental Monitoring Program Security Access Authorization .01 and Access Control .02 w/PIV 2 1, 2 07/26/2021 07/30/2021 IP 71130.01 000733 Access Authorization 1, 2 07/26/2021 07/30/2021 IP 71130.02 000734 Access Control 1, 2 07/26/2021 07/30/2021 IP 71130.09 001656 Security Plan Changes 1, 2 07/26/2021 07/30/2021 IP 71151 001338 Performance Indicator Verification RP 2,4 2 1, 2 08/30/2021 09/03/2021 IP 71124.02 000726 Occupational ALARA Planning and Controls 1, 2 08/30/2021 09/03/2021 IP 71124.04 000728 Occupational Dose Assessment This report does not include INPO and OUTAGE activities. Page 2 of 3 This report shows only on-site and announced inspection procedures. | |||
8/27/2020 8:20:16 AM | |||
IP 22 Inspection Activity Plan Report South Texas Project 07/01/2020 - 06/30/2022 Unit Start End Activity CAC Title Staff Count STP 2021 BRQ 3 1, 2 09/12/2021 09/18/2021 IP 71111.11B 000704 Licensed Operator Requalification Program and Licensed Operator Performance Inservice Inspection 1RF23 - STP 1 1 10/11/2021 10/22/2021 IP 71111.08P 000702 Inservice Inspection Activities (PWR) | |||
Design Bases Assurance (Program) 21N - South Texas 3 1, 2 11/01/2021 11/19/2021 IP 71111.21N 000714 Design Bases Assurance Inspection (Programs) | |||
RP 5,8 2 1, 2 01/31/2022 02/04/2022 IP 71124.05 000729 Radiation Monitoring Instrumentation 1, 2 01/31/2022 02/04/2022 IP 71124.08 000732 Radioactive Solid Waste Processing & Radioactive Material Handling, Storage, & | |||
Transportation South Texas Project ISFSI Loading Inspection (1 week in April) 2 1 04/01/2022 04/29/2022 IP 60855 001001 Operation Of An ISFSI 1 04/01/2022 04/29/2022 IP 60857 001004 Review of 10 CFR 72.48 Evaluations In-Office EP Exercise Scenario Review - STP 4 1, 2 05/09/2022 06/18/2022 IP 71114.08 000723 Exercise Evaluation Scenario Review This report does not include INPO and OUTAGE activities. Page 3 of 3 This report shows only on-site and announced inspection procedures. | |||
8/27/2020 8:20:16 AM | |||
}} | }} |
Revision as of 00:46, 25 September 2020
ML20240A321 | |
Person / Time | |
---|---|
Site: | South Texas |
Issue date: | 09/01/2020 |
From: | Jeffrey Josey NRC/RGN-IV/DRP/RPB-A |
To: | Gerry Powell South Texas |
References | |
IR 2020005 | |
Download: ML20240A321 (6) | |
Text
ber 1, 2020
SUBJECT:
UPDATED INSPECTION PLAN FOR SOUTH TEXAS PROJECT ELECTRIC GENERATING STATION, UNITS 1 AND 2 - (REPORT 05000498/2020005 AND 05000499/2020005)
Dear Mr. Powell:
The enclosed inspection plan lists the inspections scheduled through June 30, 2022, for South Texas Project Electric Generating Station, Units 1 and 2. The U.S. Nuclear Regulatory Commission (NRC) provides the inspection plan to allow for the resolution of any scheduling conflicts and personnel availability issues. Routine inspections performed by resident inspectors are not included in the inspection plan. You should be aware that the agency is pursuing potential changes to the Reactor Oversight Process (ROP), including changes to engineering inspections (SECY-18-0113, Recommendations for Modifying the Reactor Oversight Process Engineering Inspections), and other changes to the baseline inspection program described in SECY-19-0067, Recommendations for Enhancing the Reactor Oversight Process. Should these changes to the ROP be implemented, the engineering and other region-based inspections are subject to change in scope, as well as schedule, beginning in January 2020. The inspections listed during the last 12 months of the inspection plan are tentative and may be revised. The NRC will contact you as soon as possible to discuss changes to the inspection plan should circumstances warrant any changes.
In response to the COVID-19 public health emergency (PHE), the NRC is adjusting inspection plans and schedules in order to safeguard the health and safety of both NRC and licensee staff while still effectively implementing the ROP. Each planned inspection is being carefully reviewed in order to determine if any portions of the inspection can be performed remotely, determine how best to perform on-site portions to minimize personnel health risks, and adjust inspection schedules if needed. This is done in accordance with guidance contained in the May 28, 2020, memorandum, Inspection Guidance During Transition From COVID-19 Mandatory Telework (Agencywide Documents Access and Management System (ADAMS)
Accession Number ML20141L766). For inspections requiring extensive coordination with offsite organizations, such as evaluated emergency preparedness exercises, NRC guidance and frequently asked questions for security and emergency preparedness can be found here:
https://www.nrc.gov/about-nrc/covid-19/security-ep/. Similarly, the NRC has developed guidance if force-on-force inspections cannot be completed as scheduled due to an emergency, such as the COVID-19 PHE. These changes help ensure the health and safety of both NRC and licensee staff while maintaining the NRCs important safety and security mission during the COVID-19 PHE. The attached inspection plan is accurate on the date of issuance, but remains subject to change based on approval of potential exemption requests or other changes needed due to changing conditions in the COVID-19 PHE. NRC staff will contact your appropriate regulatory affairs staff in order to coordinate inspection planning and scheduling.
The NRC will also be performing baseline inspections of licensee cyber security programs. The specific schedule and procedure to be used for these inspections are being developed by the NRC staff. The staff expects to communicate the schedule for these inspections to each utility separately.
In accordance with Title 10 of the Code of Federal Regulations (10 CFR) 2.390 of the NRCs Rules of Practice, a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS). ADAMS is accessible from the NRC Web site at https://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
Please contact me at 817-200-1148 with any questions you have regarding this letter.
Sincerely, Jeffrey Digitally signed by Jeffrey Josey Josey Date: 2020.08.31 07:57:06 -05'00'
Jeffrey E. Josey, Chief Reactor Projects Branch A Division of Reactor Projects Docket Nos. 05000498 and 05000499 License Nos. NPF-76 and NPF-80 Enclosure:
Inspection Plan cc w/ encl: Distribution via LISTSERV
ML20240A321 SUNSI Review Non-Sensitive Publicly Available
Sensitive Non-Publicly Available OFFICE SPE:DRP/A C:DRP/A NAME HFreeman JJosey SIGNATURE /RA/ /RA/
DATE 08/24/2020 08/25/2020
IP 22 Inspection Activity Plan Report South Texas Project 07/01/2020 - 06/30/2022 Unit Start End Activity CAC Title Staff Count 2020 Initial Exam - STP 6 1, 2 07/12/2020 07/18/2020 EXAD 000500 LICENSE EXAM ADMINISTRATION (EXAD)
1, 2 07/19/2020 07/25/2020 EXAD 000500 LICENSE EXAM ADMINISTRATION (EXAD)
Heat Sink Performance (Triennial) - STP 2 1, 2 07/20/2020 07/24/2020 IP 71111.07T 000700 Heat Sink Performance Security Access Control .02 - STP 1 1, 2 08/24/2020 08/28/2020 IP 71130.02 000734 Access Control 1, 2 08/24/2020 08/28/2020 IP 71130.09 001656 Security Plan Changes 1, 2 08/24/2020 08/28/2020 IP 71151 001338 Performance Indicator Verification Security Equipment .04 and Training .07 - STP 2 1, 2 08/24/2020 08/28/2020 IP 71130.04 000736 Equipment Performance, Testing, and Maintenance 1, 2 08/24/2020 08/28/2020 IP 71130.07 000739 Security Training RS58 Radiation Safety - STP 4 1, 2 09/14/2020 09/18/2020 IP 71124.05 000729 Radiation Monitoring Instrumentation 1, 2 09/14/2020 09/18/2020 IP 71124.08 000732 Radioactive Solid Waste Processing & Radioactive Material Handling, Storage, &
Transportation MC&A - Material Control & Accounting - STP 1 1, 2 09/14/2020 09/18/2020 IP 71130.11 000742 Material Control and Accounting (MC&A)
Biennial PI&R - STP 4 1, 2 10/18/2020 11/14/2020 IP 71152B 000747 Problem Identification and Resolution EP Program Inspection - STP 1 1, 2 10/26/2020 10/30/2020 IP 71114.02 000717 Alert and Notification System Testing 1, 2 10/26/2020 10/30/2020 IP 71114.03 000718 Emergency Response Organization Staffing and Augmentation System 1, 2 10/26/2020 10/30/2020 IP 71114.04 000719 Emergency Action Level and Emergency Plan Changes 1, 2 10/26/2020 10/30/2020 IP 71114.05 000720 Maintenance of Emergency Preparedness 1, 2 10/26/2020 10/30/2020 IP 71151 001397 Performance Indicator Verification FORCE-ON-FORCE PLANNING AND EXERCISE WEEKS - STP 6 1, 2 01/11/2021 01/15/2021 IP 71130.03 000735 Contingency Response - Force-On-Force Testing This report does not include INPO and OUTAGE activities. Page 1 of 3 This report shows only on-site and announced inspection procedures.
8/27/2020 8:20:16 AM
IP 22 Inspection Activity Plan Report South Texas Project 07/01/2020 - 06/30/2022 Unit Start End Activity CAC Title Staff Count FORCE-ON-FORCE PLANNING AND EXERCISE WEEKS - STP 6 1, 2 02/01/2021 02/05/2021 IP 71130.03 000735 Contingency Response - Force-On-Force Testing Security FFD .08 - STP 1 1, 2 01/25/2021 01/29/2021 IP 71130.08 000740 Fitness For Duty Program Inservice Inspection 2RF21 - STP 1 2 03/22/2021 04/02/2021 IP 71111.08P 000702 Inservice Inspection Activities (PWR)
RP 1,3,PI 2 1, 2 03/29/2021 04/02/2021 IP 71124.01 000725 Radiological Hazard Assessment and Exposure Controls 1, 2 03/29/2021 04/02/2021 IP 71124.03 000727 In-Plant Airborne Radioactivity Control and Mitigation In-Office EP Exercise Scenario Review - STP 4 1, 2 05/02/2021 06/30/2021 IP 71114.08 000723 Exercise Evaluation Scenario Review STP 2021 INITIAL EXAM 6 1, 2 06/06/2021 06/12/2021 OV 000956 VALIDATION OF INITIAL LICENSE EXAMINATION (OV)
1, 2 07/11/2021 07/17/2021 EXAD 000500 LICENSE EXAM ADMINISTRATION (EXAD)
EP Biennial Exercise and PI Inspection 4 1, 2 07/12/2021 07/16/2021 IP 71114.01 000716 Exercise Evaluation 1, 2 07/12/2021 07/16/2021 IP 71151 001397 Performance Indicator Verification RP 6,7 2 1, 2 07/19/2021 07/23/2021 IP 71124.06 000730 Radioactive Gaseous and Liquid Effluent Treatment 1, 2 07/19/2021 07/23/2021 IP 71124.07 000731 Radiological Environmental Monitoring Program Security Access Authorization .01 and Access Control .02 w/PIV 2 1, 2 07/26/2021 07/30/2021 IP 71130.01 000733 Access Authorization 1, 2 07/26/2021 07/30/2021 IP 71130.02 000734 Access Control 1, 2 07/26/2021 07/30/2021 IP 71130.09 001656 Security Plan Changes 1, 2 07/26/2021 07/30/2021 IP 71151 001338 Performance Indicator Verification RP 2,4 2 1, 2 08/30/2021 09/03/2021 IP 71124.02 000726 Occupational ALARA Planning and Controls 1, 2 08/30/2021 09/03/2021 IP 71124.04 000728 Occupational Dose Assessment This report does not include INPO and OUTAGE activities. Page 2 of 3 This report shows only on-site and announced inspection procedures.
8/27/2020 8:20:16 AM
IP 22 Inspection Activity Plan Report South Texas Project 07/01/2020 - 06/30/2022 Unit Start End Activity CAC Title Staff Count STP 2021 BRQ 3 1, 2 09/12/2021 09/18/2021 IP 71111.11B 000704 Licensed Operator Requalification Program and Licensed Operator Performance Inservice Inspection 1RF23 - STP 1 1 10/11/2021 10/22/2021 IP 71111.08P 000702 Inservice Inspection Activities (PWR)
Design Bases Assurance (Program) 21N - South Texas 3 1, 2 11/01/2021 11/19/2021 IP 71111.21N 000714 Design Bases Assurance Inspection (Programs)
RP 5,8 2 1, 2 01/31/2022 02/04/2022 IP 71124.05 000729 Radiation Monitoring Instrumentation 1, 2 01/31/2022 02/04/2022 IP 71124.08 000732 Radioactive Solid Waste Processing & Radioactive Material Handling, Storage, &
Transportation South Texas Project ISFSI Loading Inspection (1 week in April) 2 1 04/01/2022 04/29/2022 IP 60855 001001 Operation Of An ISFSI 1 04/01/2022 04/29/2022 IP 60857 001004 Review of 10 CFR 72.48 Evaluations In-Office EP Exercise Scenario Review - STP 4 1, 2 05/09/2022 06/18/2022 IP 71114.08 000723 Exercise Evaluation Scenario Review This report does not include INPO and OUTAGE activities. Page 3 of 3 This report shows only on-site and announced inspection procedures.
8/27/2020 8:20:16 AM