August 31, 2018
Mr. G. T. Powell
President and CEO
STP Nuclear Operating Company
P.O. Box 289
Wadsworth, TX 77483
SUBJECT:
UPDATED INSPECTION PLAN FOR SOUTH TEXAS PROJECT ELECTRIC
GENERATING STATION, UNITS 1 AND 2 (REPORTS 05000498/2018005 AND
Dear Mr. Powell:
The enclosed inspection plan lists the inspections scheduled through June 30, 2020, for South
Texas Project Electric Generating Station, Units 1 and 2. The NRC provides the inspection plan
to allow for the resolution of any scheduling conflicts and personnel availability issues. Routine
inspections performed by resident inspectors are not included in the inspection plan. The
inspections listed during the last twelve months of the inspection plan are tentative and may be
revised. The NRC will contact you as soon as possible to discuss changes to the inspection
plan should circumstances warrant any changes.
Additionally, as reflected in the enclosure, during this period the NRC staff will complete
Temporary Instruction 2515/194, Inspection of the Licensee's Implementation of Industry
Initiative Associated with the Open Phase Condition Design Vulnerabilities in Electric Power
Systems (NRC Bulletin 2012-01).
In order to verify the adequacy of the security controls for a new independent spent fuel storage
installation, the NRC will also conduct Inspection Procedure 81311, Physical Security
Requirements for Independent Spent Fuel Storage Installations, prior to the first loading of
spent fuel. The NRC will use the advance notification required under § 72.212 (b)(1) to
coordinate our initial inspection of this facility.
In accordance with Title 10 of the Code of Federal Regulations (10 CFR) 2.390 of the NRCs
Rules of Practice, a copy of this letter will be available electronically for public inspection in the
NRC Public Document Room or from the Publicly Available Records (PARS) component of
G. Powell
2
NRC's document system (ADAMS). ADAMS is accessible from the NRC Web site at
http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
Please contact me at 817-200-1141 with any questions you have regarding this letter.
Sincerely,
/RA/
Nicholas H. Taylor, Chief
Project Branch B
Division of Reactor Projects
Docket Nos. 50-498 and 50-499
License Nos. NPF-76 and NPF-80
Enclosure: Inspection Plan
South Texas Project
08/01/2018 - 06/30/2020
Unit
Start
End
Activity
Title
Staff Count
BIENNIAL PI&R
4
1, 2
08/06/2018
08/09/2018
IP 71152B
000747
Problem Identification and Resolution
1, 2
08/20/2018
08/23/2018
IP 71152B
000747
Problem Identification and Resolution
STP HEAT SINK PERFORMANCE
2
1, 2
09/10/2018
09/14/2018
000700
Heat Sink Performance -Triennial
INITIAL EXAM
4
1, 2
09/16/2018
09/22/2018
000956
VALIDATION OF INITIAL LICENSE EXAMINATION (OV)
1, 2
10/21/2018
11/03/2018
000500
LICENSE EXAM ADMINISTRATION (EXAD)
2
1, 2
12/03/2018
12/07/2018
000512
Inspection of the Licensees Implementation of Industry Initiative Associated With the
Open Phase Condition Design Vulnerabilities In Electric Power Systems (NRC Bulletin
2012-01)
Securiity Access Control .02
1
1, 2
02/11/2019
02/15/2019
000734
Access Control
1, 2
02/11/2019
02/15/2019
001338
Performance Indicator Verification
RP INSPECTION (2,4)
2
1, 2
03/11/2019
03/15/2019
000726
Occupational ALARA Planning and Controls
1, 2
03/11/2019
03/15/2019
000729
Occupational Dose Assessment
SOUTH TEXAS DBA TEAM INSPECTION
6
1, 2
03/25/2019
04/12/2019
000713
Design Bases Assurance Inspection (Teams)
INITIAL EXAM
5
1, 2
06/16/2019
06/22/2019
000956
VALIDATION OF INITIAL LICENSE EXAMINATION (OV)
1, 2
07/14/2019
07/20/2019
000500
LICENSE EXAM ADMINISTRATION (EXAD)
EP PROGRAM INSPECTION
1
1, 2
07/08/2019
07/12/2019
000717
Alert and Notification System Testing
1, 2
07/08/2019
07/12/2019
000718
Emergency Response Organization Staffing and Augmentation System
1, 2
07/08/2019
07/12/2019
000719
Emergency Action Level and Emergency Plan Changes
1, 2
07/08/2019
07/12/2019
000720
Correction of Emergency Preparedness Weaknesses and Deficiencies
8/22/2018 7:59:58 AM
Page 1 of 2
This report does not include INPO and OUTAGE activities.
This report shows only on-site and announced inspection procedures.
IP 22 Inspection Activity Plan Report
Enclosure
South Texas Project
08/01/2018 - 06/30/2020
Unit
Start
End
Activity
Title
Staff Count
EP PROGRAM INSPECTION
1
1, 2
07/08/2019
07/12/2019
001397
Performance Indicator Verification
BRQ
3
1, 2
08/25/2019
08/31/2019
000704
Licensed Operator Requalification Program and Licensed Operator Performance
(Biennial)
Security Protective Strategy and Target Set .05 / .14
4
1, 2
09/02/2019
11/08/2019
000743
Review of Power Reactor Target Sets
1, 2
09/23/2019
09/27/2019
000737
Protective Strategy Evaluation
2
1, 2
10/21/2019
10/25/2019
000725
Radiological Hazard Assessment and Exposure Controls
1, 2
10/21/2019
10/25/2019
000727
In-Plant Airborne Radioactivity Control and Mitigation
Triennial Fire Protection Inspection
4
1, 2
01/27/2020
01/31/2020
000696
Fire Protection (Triennial)
1, 2
02/10/2020
02/14/2020
000696
Fire Protection (Triennial)
RS12PI Radiation Safety
2
1, 2
03/30/2020
04/03/2020
000725
Radiological Hazard Assessment and Exposure Controls
1, 2
03/30/2020
04/03/2020
000726
Occupational ALARA Planning and Controls
South Texas 1, 2 - Evaluations of Changes, Tests, and Experiments
3
1, 2
05/11/2020
05/15/2020
000709
Evaluations of Changes, Tests, and Experiments
INITIAL EXAM
8
1, 2
06/07/2020
06/13/2020
000956
VALIDATION OF INITIAL LICENSE EXAMINATION (OV)
8/22/2018 7:59:58 AM
Page 2 of 2
This report does not include INPO and OUTAGE activities.
This report shows only on-site and announced inspection procedures.
IP 22 Inspection Activity Plan Report
SUNSI Review
ADAMS:
Non-Publicly Available
Non-Sensitive
Keyword:
By: NTaylor
Yes No
Publicly Available
Sensitive
OFFICE
C:PSB1
C:DRP/B
NAME
JGroom
NTaylor
SIGNATURE
/RA/
/RA/
DATE
8/9/18
8/31/18