Updated Inspection Plan for South Texas Project Electric Generating Station, Units 1 and 2 (Reports 05000498/2018005 and 05000499/2018005)
ML18234A418
Person / Time
Site: South Texas  
(NPF-076, NPF-080)
Issue date: 08/31/2018
From: Nick Taylor
NRC Region 4, NRC/RGN-IV/DRP
To: Gerry Powell
South Texas
References
IR 2018005
Download: ML18234A418 (5)


See also: IR 05000498/2018005

Text

August 31, 2018

Mr. G. T. Powell

President and CEO

STP Nuclear Operating Company

P.O. Box 289

Wadsworth, TX 77483

SUBJECT:

UPDATED INSPECTION PLAN FOR SOUTH TEXAS PROJECT ELECTRIC

GENERATING STATION, UNITS 1 AND 2 (REPORTS 05000498/2018005 AND

05000499/2018005)

Dear Mr. Powell:

The enclosed inspection plan lists the inspections scheduled through June 30, 2020, for South

Texas Project Electric Generating Station, Units 1 and 2. The NRC provides the inspection plan

to allow for the resolution of any scheduling conflicts and personnel availability issues. Routine

inspections performed by resident inspectors are not included in the inspection plan. The

inspections listed during the last twelve months of the inspection plan are tentative and may be

revised. The NRC will contact you as soon as possible to discuss changes to the inspection

plan should circumstances warrant any changes.

Additionally, as reflected in the enclosure, during this period the NRC staff will complete

Temporary Instruction 2515/194, Inspection of the Licensee's Implementation of Industry

Initiative Associated with the Open Phase Condition Design Vulnerabilities in Electric Power

Systems (NRC Bulletin 2012-01).

In order to verify the adequacy of the security controls for a new independent spent fuel storage

installation, the NRC will also conduct Inspection Procedure 81311, Physical Security

Requirements for Independent Spent Fuel Storage Installations, prior to the first loading of

spent fuel. The NRC will use the advance notification required under § 72.212 (b)(1) to

coordinate our initial inspection of this facility.

In accordance with Title 10 of the Code of Federal Regulations (10 CFR) 2.390 of the NRCs

Rules of Practice, a copy of this letter will be available electronically for public inspection in the

NRC Public Document Room or from the Publicly Available Records (PARS) component of

G. Powell

2

NRC's document system (ADAMS). ADAMS is accessible from the NRC Web site at

http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).

Please contact me at 817-200-1141 with any questions you have regarding this letter.

Sincerely,

/RA/

Nicholas H. Taylor, Chief

Project Branch B

Division of Reactor Projects

Docket Nos. 50-498 and 50-499

License Nos. NPF-76 and NPF-80

Enclosure: Inspection Plan

South Texas Project

08/01/2018 - 06/30/2020

Unit

Start

End

Activity

CAC

Title

Staff Count

BIENNIAL PI&R

4

1, 2

08/06/2018

08/09/2018

IP 71152B

000747

Problem Identification and Resolution

1, 2

08/20/2018

08/23/2018

IP 71152B

000747

Problem Identification and Resolution

STP HEAT SINK PERFORMANCE

2

1, 2

09/10/2018

09/14/2018

IP 71111.07T

000700

Heat Sink Performance -Triennial

INITIAL EXAM

4

1, 2

09/16/2018

09/22/2018

OV

000956

VALIDATION OF INITIAL LICENSE EXAMINATION (OV)

1, 2

10/21/2018

11/03/2018

EXAD

000500

LICENSE EXAM ADMINISTRATION (EXAD)

TI 2515/194

2

1, 2

12/03/2018

12/07/2018

TI 2515/194

000512

Inspection of the Licensees Implementation of Industry Initiative Associated With the

Open Phase Condition Design Vulnerabilities In Electric Power Systems (NRC Bulletin

2012-01)

Securiity Access Control .02

1

1, 2

02/11/2019

02/15/2019

IP 71130.02

000734

Access Control

1, 2

02/11/2019

02/15/2019

IP 71151

001338

Performance Indicator Verification

RP INSPECTION (2,4)

2

1, 2

03/11/2019

03/15/2019

IP 71124.02

000726

Occupational ALARA Planning and Controls

1, 2

03/11/2019

03/15/2019

IP 71124.04

000729

Occupational Dose Assessment

SOUTH TEXAS DBA TEAM INSPECTION

6

1, 2

03/25/2019

04/12/2019

IP 71111.21M

000713

Design Bases Assurance Inspection (Teams)

INITIAL EXAM

5

1, 2

06/16/2019

06/22/2019

OV

000956

VALIDATION OF INITIAL LICENSE EXAMINATION (OV)

1, 2

07/14/2019

07/20/2019

EXAD

000500

LICENSE EXAM ADMINISTRATION (EXAD)

EP PROGRAM INSPECTION

1

1, 2

07/08/2019

07/12/2019

IP 71114.02

000717

Alert and Notification System Testing

1, 2

07/08/2019

07/12/2019

IP 71114.03

000718

Emergency Response Organization Staffing and Augmentation System

1, 2

07/08/2019

07/12/2019

IP 71114.04

000719

Emergency Action Level and Emergency Plan Changes

1, 2

07/08/2019

07/12/2019

IP 71114.05

000720

Correction of Emergency Preparedness Weaknesses and Deficiencies

8/22/2018 7:59:58 AM

Page 1 of 2

This report does not include INPO and OUTAGE activities.

This report shows only on-site and announced inspection procedures.

IP 22 Inspection Activity Plan Report

Enclosure

South Texas Project

08/01/2018 - 06/30/2020

Unit

Start

End

Activity

CAC

Title

Staff Count

EP PROGRAM INSPECTION

1

1, 2

07/08/2019

07/12/2019

IP 71151

001397

Performance Indicator Verification

BRQ

3

1, 2

08/25/2019

08/31/2019

IP 71111.11B

000704

Licensed Operator Requalification Program and Licensed Operator Performance

(Biennial)

Security Protective Strategy and Target Set .05 / .14

4

1, 2

09/02/2019

11/08/2019

IP 71130.14

000743

Review of Power Reactor Target Sets

1, 2

09/23/2019

09/27/2019

IP 71130.05

000737

Protective Strategy Evaluation

RP INSPECTION (1,3) - RFO

2

1, 2

10/21/2019

10/25/2019

IP 71124.01

000725

Radiological Hazard Assessment and Exposure Controls

1, 2

10/21/2019

10/25/2019

IP 71124.03

000727

In-Plant Airborne Radioactivity Control and Mitigation

Triennial Fire Protection Inspection

4

1, 2

01/27/2020

01/31/2020

IP 71111.05T

000696

Fire Protection (Triennial)

1, 2

02/10/2020

02/14/2020

IP 71111.05T

000696

Fire Protection (Triennial)

RS12PI Radiation Safety

2

1, 2

03/30/2020

04/03/2020

IP 71124.01

000725

Radiological Hazard Assessment and Exposure Controls

1, 2

03/30/2020

04/03/2020

IP 71124.02

000726

Occupational ALARA Planning and Controls

South Texas 1, 2 - Evaluations of Changes, Tests, and Experiments

3

1, 2

05/11/2020

05/15/2020

IP 71111.17T

000709

Evaluations of Changes, Tests, and Experiments

INITIAL EXAM

8

1, 2

06/07/2020

06/13/2020

OV

000956

VALIDATION OF INITIAL LICENSE EXAMINATION (OV)

8/22/2018 7:59:58 AM

Page 2 of 2

This report does not include INPO and OUTAGE activities.

This report shows only on-site and announced inspection procedures.

IP 22 Inspection Activity Plan Report

ML18234A418

SUNSI Review

ADAMS:

Non-Publicly Available

Non-Sensitive

Keyword:

By: NTaylor

Yes No

Publicly Available

Sensitive

NRC-002

OFFICE

C:PSB1

C:DRP/B

NAME

JGroom

NTaylor

SIGNATURE

/RA/

/RA/

DATE

8/9/18

8/31/18