| number = ML14007A681
| number = ML14007A681
| issue date = 02/21/2014
| issue date = 02/21/2014
| title = James A. FitzPatrick Nuclear Power Plant, Interim Staff Evaluation Relating to Overall Integrated Plan in Response to Order EA-12-049 (Mitigation Strategies) (TAC No. MF1077)
| title = Interim Staff Evaluation Relating to Overall Integrated Plan in Response to Order EA-12-049 (Mitigation Strategies)
| author name = Bowen J S
| author name = Bowen J
| author affiliation = NRC/NRR/DPR/MSD/MSPB
| author affiliation = NRC/NRR/DPR/MSD/MSPB
| addressee name =  
| addressee name =  
Line 9: Line 9:
| docket = 05000333
| docket = 05000333
| license number =  
| license number =  
| contact person = Lent S M, NRR/DPR, 415-1365
| contact person = Lent S, NRR/DPR, 415-1365
| case reference number = EA-12-049, Job Code J4672, NRC-HQ-13-C-03-0039, TAC MF1077
| case reference number = EA-12-049, Job Code J4672, NRC-HQ-13-C-03-0039, TAC MF1077
| package number = ML14007A679
| package number = ML14007A679
Line 15: Line 15:
| page count = 76
| page count = 76
| project = TAC:MF1077
| project = TAC:MF1077
| stage = Other
| stage = Acceptance Review
}}
}}


=Text=
=Text=
{{#Wiki_filter:UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 Vice President, Operations Entergy Nuclear Operations, Inc. February 21, 2014 James A. FitzPatrick Nuclear Power Plant P.O. Box 110 Lycoming, NY 13093  
{{#Wiki_filter:UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 February 21, 2014 Vice President, Operations Entergy Nuclear Operations, Inc.
James A. FitzPatrick Nuclear Power Plant P.O. Box 110 Lycoming, NY 13093


==SUBJECT:==
==SUBJECT:==
JAMES A. FITZPATRICK NUCLEAR POWER PLANT- INTERIM STAFF EVALUATION RELATING TO OVERALL INTEGRATED PLAN IN RESPONSE TO ORDER EA-12-049 (MITIGATION STRATEGIES) (TAC NO. MF1077)


JAMES A. FITZPATRICK NUCLEAR POWER PLANT-INTERIM STAFF EVALUATION RELATING TO OVERALL INTEGRATED PLAN IN RESPONSE TO ORDER EA-12-049 (MITIGATION STRATEGIES)
==Dear Sir or Madam:==
(TAC NO. MF1077)


==Dear Sir or Madam:==
On March 12, 2012, the U.S. Nuclear Regulatory Commission (NRC) issued Order EA-12-049, "Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events" (Agencywide Documents Access and Management System (ADAMS) Accession No. ML12054A736). By letter dated February 28, 2013 (ADAMS Accession No. ML13063A262), Entergy Nuclear Operations, Inc. (Entergy, the licensee) submitted its Overall Integrated Plan for James A. FitzPatrick Nuclear Power Plant in response to Order EA-12-049. By letter dated August 28, 2013 (ADAMS Accession No. ML13241A204),
On March 12, 2012, the U.S. Nuclear Regulatory Commission (NRC) issued Order EA-12-049, "Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Design-Basis External Events" (Agencywide Documents Access and Management System (ADAMS) Accession No. ML 12054A736).
Entergy submitted a six-month update to the Overall Integrated Plan.
By letter dated February 28, 2013 (ADAMS Accession No. ML 13063A262),
Based on a review of Entergy's plan, including the six-month update dated August 28, 2013, and information obtained through the mitigation strategies audit process, 1 the NRC concludes that the licensee has provided sufficient information to determine that there is reasonable assurance that the plan, when properly implemented, will meet the requirements of Order EA-12-049 at James A. FitzPatrick Nuclear Power Plant. This conclusion is based on the assumption that the licensee will implement the plan as described, including the satisfactory resolution of the open and confirmatory items detailed in the enclosed Interim Staff Evaluation and Audit Report. As identified in Section 4.0 of the enclosed report, the open item warranting the greatest attention to ensure successful implementation is to demonstrate adequate protection of FLEX equipment from a potential tornado hazard.
Entergy Nuclear Operations, Inc. (Entergy, the licensee) submitted its Overall Integrated Plan for James A. FitzPatrick Nuclear Power Plant in response to Order EA-12-049.
1 A description of the mitigation strategies audit process may be found at ADAMS Accession No. ML13234A503.
By letter dated August 28, 2013 (ADAMS Accession No. ML 13241A204),
 
Entergy submitted a six-month update to the Overall Integrated Plan. Based on a review of Entergy's plan, including the six-month update dated August 28, 2013, and information obtained through the mitigation strategies audit process, 1 the NRC concludes that the licensee has provided sufficient information to determine that there is reasonable assurance that the plan, when properly implemented, will meet the requirements of Order EA-12-049 at James A. FitzPatrick Nuclear Power Plant. This conclusion is based on the assumption that the licensee will implement the plan as described, including the satisfactory resolution of the open and confirmatory items detailed in the enclosed Interim Staff Evaluation and Audit Report. As identified in Section 4.0 of the enclosed report, the open item warranting the greatest attention to ensure successful implementation is to demonstrate adequate protection of FLEX equipment from a potential tornado hazard. 1 A description of the mitigation strategies audit process may be found at ADAMS Accession No. ML 13234A503. If you have any questions, please contact John Boska at 301-415-2901.
If you have any questions, please contact John Boska at 301-415-2901.
Docket No. 50-333  
Sincerely, Jeremy S. Bowen, Chief Mitigating Strategies Projects Branch Mitigating Strategies Directorate Office of Nuclear Reactor Regulation Docket No. 50-333


==Enclosures:==
==Enclosures:==
: 1. Interim Staff Evaluation  
: 1. Interim Staff Evaluation
: 2. Technical Evaluation Report cc w/encl: Distribution via Listserv Sincerely, Jeremy S. Bowen, Chief Mitigating Strategies Projects Branch Mitigating Strategies Directorate Office of Nuclear Reactor Regulation UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 INTERIM STAFF EVALUATION AND AUDIT REPORT BY THE OFFICE OF NUCLEAR REACTOR REGULATION RELATED TO ORDER EA-12-049 MODIFYING LICENSES WITH REGARD TO REQUIREMENTS FOR MITIGATION STRATEGIES FOR BEYOND-DESIGN-BASIS EXTERNAL EVENTS ENTERGY NUCLEAR OPERATIONS.
: 2. Technical Evaluation Report cc w/encl: Distribution via Listserv
INC. JAMES A FITZPATRICK NUCLEAR POWER PLANT DOCKET NO. 50-333  
 
UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 INTERIM STAFF EVALUATION AND AUDIT REPORT BY THE OFFICE OF NUCLEAR REACTOR REGULATION RELATED TO ORDER EA-12-049 MODIFYING LICENSES WITH REGARD TO REQUIREMENTS FOR MITIGATION STRATEGIES FOR BEYOND-DESIGN-BASIS EXTERNAL EVENTS ENTERGY NUCLEAR OPERATIONS. INC.
JAMES A FITZPATRICK NUCLEAR POWER PLANT DOCKET NO. 50-333


==1.0 INTRODUCTION==
==1.0   INTRODUCTION==


The earthquake and tsunami at the Fukushima Dai-ichi nuc:ear power plant in March 2011, highlighted the possibility that extreme natural phenomena could challenge the prevention, mitigation and emergency preparedness defense-in-de;Jth layers. At Fukushima, limitations in time and unpredictable conditions associated with the accident significantly challenged attempts by the responders to preclude core damage and containment failure.
The earthquake and tsunami at the Fukushima Dai-ichi nuc:ear power plant in March 2011, highlighted the possibility that extreme natural phenomena could challenge the prevention, mitigation and emergency preparedness defense-in-de;Jth layers. At Fukushima, limitations in time and unpredictable conditions associated with the accident significantly challenged attempts by the responders to preclude core damage and containment failure. During the events in Fukushima, the challenges faced by the operators were beyond any faced previously at a commercial nuclear reactor. The Nuclear Regulato1y Commission (NRC) determined that additional requirements needed to be imposed to mitigate beyond-design-basis external events (BDBEEs). Accordingly, by letter dated March 12. 2012, the NRC issued Order EA-12-049, "Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events" [Reference 1]. The order directed licensees to develop, implement, and maintain guidance and strategies to maintain or restore core cooling, containment, and spent fuel pool (SFP) cooling capabilities in the event of a BDBEE.
During the events in Fukushima, the challenges faced by the operators were beyond any faced previously at a commercial nuclear reactor.
By letter dated February 28, 2013 [Reference 2], Entergy Nuclear Operations, Inc. (Entergy or the licensee) submitted its Overall Integrated Plan (hereafter referred to as the Integrated Plan) for James A FitzPatrick Nuclear Power P!ant (JAF) in response to Order EA-12-049. By letter dated August 28, 2013 [Reference 3], F.ntergy submitted a six-month update to the Integrated Plan.
The Nuclear Regulato1y Commission (NRC) determined that additional requirements needed to be imposed to mitigate beyond-design-basis external events (BDBEEs).
Enclosure 1
Accordingly, by letter dated March 12. 2012, the NRC issued Order EA-12-049, "Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Design-Basis External Events" [Reference 1]. The order directed licensees to develop, implement, and maintain guidance and strategies to maintain or restore core cooling, containment, and spent fuel pool (SFP) cooling capabilities in the event of a BDBEE. By letter dated February 28, 2013 [Reference 2], Entergy Nuclear Operations, Inc. (Entergy or the licensee) submitted its Overall Integrated Plan (hereafter referred to as the Integrated Plan) for James A FitzPatrick Nuclear Power P!ant (JAF) in response to Order EA-12-049.
 
By letter dated August 28, 2013 [Reference 3], F.ntergy submitted a six-month update to the Integrated Plan. Enclosure 1   2.0 REGULATORY EVALUATION Following the events at the Fukushima Dai-ichi nuclear power plant on March 11, 2011, the NRC established a senior-level agency task force referred to as the Near-Term Task Force (NTTF). The NTTF was tasked with conducting a systematic and methodical review of the NRC's regulations and processes, and with determining whether the agency should make improvements to these programs in light of the events at Fukushima Dai-ichi.
==2.0     REGULATORY EVALUATION==
As a result of this review, the NTTF developed a comprehensive set of recommendations, documented in SECY-11-0093, "Near-Term Report and Recommendations for Agency Actions Following the Events in Japan," dated July 12, 2011 [Reference 4]. These recommendations were enhanced by the NRC staff following interactions with stakeholders.
 
Documentation of the NRC staff's efforts is contained in SECY-11-0124, "Recommended Actions to be Taken without Delay from the Term Task Force Report,"
Following the events at the Fukushima Dai-ichi nuclear power plant on March 11, 2011, the NRC established a senior-level agency task force referred to as the Near-Term Task Force (NTTF). The NTTF was tasked with conducting a systematic and methodical review of the NRC's regulations and processes, and with determining whether the agency should make improvements to these programs in light of the events at Fukushima Dai-ichi. As a result of this review, the NTTF developed a comprehensive set of recommendations, documented in SECY-11-0093, "Near-Term Report and Recommendations for Agency Actions Following the Events in Japan," dated July 12, 2011 [Reference 4]. These recommendations were enhanced by the NRC staff following interactions with stakeholders. Documentation of the NRC staff's efforts is contained in SECY-11-0124, "Recommended Actions to be Taken without Delay from the Near-Term Task Force Report," dated September 9, 2011 [Reference 5] and SECY-11-0137, "Prioritization of Recommended Actions to be Taken in Response to Fukushima Lessons Learned," dated October 3, 2011 [Reference 6].
dated September 9, 2011 [Reference 5] and SECY-11-0137, "Prioritization of Recommended Actions to be Taken in Response to Fukushima Lessons Learned,"
As directed by the Commission's Staff Requirement Memorandum (SRM) for SECY-11-0093
dated October 3, 2011 [Reference 6]. As directed by the Commission's Staff Requirement Memorandum (SRM) for SECY-11-0093  
[Reference 7], the NRC staff reviewed the NTTF recommendations within the context of the NRC's existing regulatory framework and considered the various regulatory vehicles available to the NRC to implement the recommendations. SECY-11-0124 and SECY-11-0137 established the NRC staff's prioritization of the recommendations based upon the potential safety enhancements.
[Reference 7], the NRC staff reviewed the NTTF recommendations within the context of the NRC's existing regulatory framework and considered the various regulatory vehicles available to the NRC to implement the recommendations.
After receiving the Commission's direction in SRM-SECY-11-0124 [Reference 8] and SRM-SECY-11-0137 [Reference 9], the NRC staff conducted public meetings to discuss enhanced mitigation strategies intended to maintain or restore core cooling, containment, and SFP cooling capabilities following beyond-design-basis external events. At these meetings, the industry described its proposal for a Diverse and Flexible Mitigation Capability (FLEX), as documented in the Nuclear Energy Institute's (NEI's) letter dated December 16, 2011
SECY-11-0124 and SECY-11-0137 established the NRC staff's prioritization of the recommendations based upon the potential safety enhancements.
[Reference 10]. FLEX was proposed as a strategy to fulfill the key safety functions of core cooling, containment integrity, and spent fuel cooling. Stakeholder input influenced the NRC staff to pursue a more performance-based approach to improve the safety of operating power reactors than envisioned in NTTF Recommendation 4.2, SECY-11-0124, and SECY-11-0137.
After receiving the Commission's direction in SRM-SECY-11-0124  
On February 17, 2012, the NRC staff provided SECY-12-0025, "Proposed Orders and Requests for Information in Response to Lessons Learned from Japan's March 11, 2011, Great Tohoku Earthquake and Tsunami," [Reference 11] to the Commission, including the proposed order to implement the enhanced mitigation strategies. As directed by SRM-SECY-12-0025
[Reference 8] and SRM-SECY-11-0137  
[Reference 12], the NRC staff issued Order EA-12-049, "Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events"
[Reference 9], the NRC staff conducted public meetings to discuss enhanced mitigation strategies intended to maintain or restore core cooling, containment, and SFP cooling capabilities following beyond-design-basis external events. At these meetings, the industry described its proposal for a Diverse and Flexible Mitigation Capability (FLEX), as documented in the Nuclear Energy Institute's (NEI's) letter dated December 16, 2011 [Reference 1 0]. FLEX was proposed as a strategy to fulfill the key safety functions of core cooling, containment integrity, and spent fuel cooling.
[Reference 1].
Stakeholder input influenced the NRC staff to pursue a more performance-based approach to improve the safety of operating power reactors than envisioned in NTTF Recommendation 4.2, SECY-11-0124, and SECY-11-0137.
Order EA-12-049, Attachment 2, 1 requires that operating power reactor licensees and construction permit holders use a three-phase approach for mitigating BDBEEs. The initial phase requires the use of installed equipment and resources to maintain or restore core cooling, 1
On February 17, 2012, the NRC staff provided SECY-12-0025, "Proposed Orders and Requests for Information in Response to Lessons Learned from Japan's March 11, 2011, Great Tohoku Earthquake and Tsunami,"  
Attachment 3 provides requirements for Combined License holders.
[Reference 11] to the Commission, including the proposed order to implement the enhanced mitigation strategies.
 
As directed by SRM-SECY-12-0025  
containment and SFP cooling capabilities. The transition phase requires providing sufficient, portable, onsite equipment and consumables to maintain or restore these functions until they can be accomplished with resources brought from off site. The final phase requires obtaining sufficient offsite resources to sustain those functions indefinitely. Specific operational requirements of the order are listed below:
[Reference 12], the NRC staff issued Order EA-12-049, "Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events" [Reference 1]. Order EA-12-049, Attachment 2,1 requires that operating power reactor licensees and construction permit holders use a three-phase approach for mitigating BDBEEs. The initial phase requires the use of installed equipment and resources to maintain or restore core cooling, 1 Attachment 3 provides requirements for Combined License holders. containment and SFP cooling capabilities.
: 1) Licensees or construction permit (CP) holders shall develop, implement, and maintain guidance and strategies to maintain or restore core cooling, containment, and SFP cooling capabilities following a beyond-design-basis external event.
The transition phase requires providing sufficient,  
: 2) These strategies must be capable of mitigating a simultaneous loss of all alternating current (ac) power and loss of normal access to the ultimate heat sink and have adequate capacity to address challenges to core cooling, containment, and SFP cooling capabilities at all units on a site subject to the order.
: portable, onsite equipment and consumables to maintain or restore these functions until they can be accomplished with resources brought from off site. The final phase requires obtaining sufficient offsite resources to sustain those functions indefinitely.
: 3) Licensees or CP holders must provide reasonable protection for the associated equipment from external events. Such protection must demonstrate that there is adequate capacity to address challenges to core cooling, containment, and SFP cooling capabilities at all units on a site subject to the order.
Specific operational requirements of the order are listed below: 1) Licensees or construction permit (CP) holders shall develop, implement, and maintain guidance and strategies to maintain or restore core cooling, containment, and SFP cooling capabilities following a beyond-design-basis external event. 2) These strategies must be capable of mitigating a simultaneous loss of all alternating current (ac) power and loss of normal access to the ultimate heat sink and have adequate capacity to address challenges to core cooling, containment, and SFP cooling capabilities at all units on a site subject to the order. 3) Licensees or CP holders must provide reasonable protection for the associated equipment from external events. Such protection must demonstrate that there is adequate capacity to address challenges to core cooling, containment, and SFP cooling capabilities at all units on a site subject to the order. 4) Licensees or CP holders must be capable of implementing the strategies in all modes. 5) Full compliance shall include procedures,  
: 4) Licensees or CP holders must be capable of implementing the strategies in all modes.
: guidance, training, and acquisition,  
: 5) Full compliance shall include procedures, guidance, training, and acquisition, staging, or installing of equipment needed for the strategies.
: staging, or installing of equipment needed for the strategies.
On May 4, 2012, NEI submitted document 12-06, "Diverse and Flexible Coping Strategies (FLEX) Implementation Guide," Revision B [Reference 13] to provide specifications for an industry developed methodology for the development, implementation, and maintenance of guidance and strategies in response to the Mitigating Strategies order. On May 13, 2012, NEI submitted NEI 12-06, Revision B 1 [Reference 14]. The guidance and strategies described in NEI 12-06 expand on those that industry developed and implemented to address the limited set of BDBEE that involve the loss of a large area of the plant due to explosions and fire required pursuant to paragraph (hh)(2) in Section 50.54, "Conditions of licenses" of Title 10 of the Code of Federal Regulations.
On May 4, 2012, NEI submitted document 12-06, "Diverse and Flexible Coping Strategies (FLEX) Implementation Guide," Revision B [Reference 13] to provide specifications for an industry developed methodology for the development, implementation, and maintenance of guidance and strategies in response to the Mitigating Strategies order. On May 13, 2012, NEI submitted NEI 12-06, Revision B 1 [Reference 14]. The guidance and strategies described in NEI 12-06 expand on those that industry developed and implemented to address the limited set of BDBEE that involve the loss of a large area of the plant due to explosions and fire required pursuant to paragraph (hh)(2) in Section 50.54, "Conditions of licenses" of Title 10 of the Code of Federal Regulations.
On May 31, 2012, the NRC staff issued a draft version of the interim staff guidance (ISG) document JLD-ISG-2012-01, "Compliance with Order EA-12-049, Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events,"  
On May 31, 2012, the NRC staff issued a draft version of the interim staff guidance (ISG) document JLD-ISG-2012-01, "Compliance with Order EA-12-049, Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events," [Reference 15] and published a notice of its availability for public comment in the Federal Register(?? FR 33779), with the comment period running through July 7, 2012.
[Reference 15] and published a notice of its availability for public comment in the Federal Register(??
JLD-ISG-2012-01 proposed endorsing NEI 12-06, Revision B1, as providing an acceptable method of meeting the requirements of Order EA-12-049. The NRC staff received seven comments during this time. The NRC staff documented its analysis of these comments in "NRC Response to Public Comments, JLD-ISG-2012-01 (Docket ID NRC-2012-0068)" [Reference 16].
FR 33779), with the comment period running through July 7, 2012. JLD-ISG-2012-01 proposed endorsing NEI 12-06, Revision B1, as providing an acceptable method of meeting the requirements of Order EA-12-049.
 
The NRC staff received seven comments during this time. The NRC staff documented its analysis of these comments in "NRC Response to Public Comments, JLD-ISG-2012-01 (Docket ID NRC-2012-0068)"  
On July 3, 2012, NEI submitted comments on JLD-ISG-2012-01, including Revision C to NEI 12-06 [Reference 17], incorporating many of the exceptions and clarifications included in the draft version of the ISG. Following a public meeting held July 26, 2012, to discuss the remaining exceptions and clarifications, on August 21, 2012, NEI submitted Revision 0 to NEI 12-06 [Reference 18].
[Reference 16]. On July 3, 2012, NEI submitted comments on JLD-ISG-2012-01, including Revision C to NEI 12-06 [Reference 17], incorporating many of the exceptions and clarifications included in the draft version of the ISG. Following a public meeting held July 26, 2012, to discuss the remaining exceptions and clarifications, on August 21, 2012, NEI submitted Revision 0 to NEI 12-06 [Reference 18]. On August 29, 2012, the NRC staff issued the final version of JLD-ISG-2012-01, "Compliance with Order EA-12-049, Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events" [Reference 19], endorsing NEI 12-06, Revision 0, as an acceptable means of meeting the requirements of Order EA-12-049, and published a notice of its availability in the Federal Register (77 FR 55230). The NRC staff determined that the overall integrated plans submitted by licensees in response to Order EA-12-049, Section IV.C.1.a should follow the guidance in NEI 12-06, Section 13, which states that: The Overall Integrated Plan should include a complete description of the FLEX strategies, including important operational characteristics.
On August 29, 2012, the NRC staff issued the final version of JLD-ISG-2012-01, "Compliance with Order EA-12-049, Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events" [Reference 19], endorsing NEI 12-06, Revision 0, as an acceptable means of meeting the requirements of Order EA-12-049, and published a notice of its availability in the Federal Register (77 FR 55230).
The level of detail generally considered adequate is consistent to the level of detail contained in the Licensee's Final Safety Analysis Report (FSAR). The plan should provide the following information:  
The NRC staff determined that the overall integrated plans submitted by licensees in response to Order EA-12-049, Section IV.C.1.a should follow the guidance in NEI 12-06, Section 13, which states that:
: 1. Extent to which this guidance, NEI 12-06, is being followed including a description of any alternatives to the guidance, and provide a milestone schedule of planned actions.  
The Overall Integrated Plan should include a complete description of the FLEX strategies, including important operational characteristics. The level of detail generally considered adequate is consistent to the level of detail contained in the Licensee's Final Safety Analysis Report (FSAR). The plan should provide the following information:
: 2. Description of the strategies and guidance to be developed to meet the requirements contained in Attachment 2 or Attachment 3 of the order. 3. Description of major installed and portable FLEX components used in the strategies, the applicable reasonable protection for the FLEX portable equipment, and the applicable maintenance requirements for the portable equipment.  
: 1. Extent to which this guidance, NEI 12-06, is being followed including a description of any alternatives to the guidance, and provide a milestone schedule of planned actions.
: 4. Description of the steps for the development of the necessary procedures,  
: 2. Description of the strategies and guidance to be developed to meet the requirements contained in Attachment 2 or Attachment 3 of the order.
: guidance, and training for the strategies; FLEX equipment acquisition, staging or installation, including necessary modifications.  
: 3. Description of major installed and portable FLEX components used in the strategies, the applicable reasonable protection for the FLEX portable equipment, and the applicable maintenance requirements for the portable equipment.
: 5. Conceptual  
: 4. Description of the steps for the development of the necessary procedures, guidance, and training for the strategies; FLEX equipment acquisition, staging or installation, including necessary modifications.
: sketches, as necessary to indicate equipment which is installed or equipment hookups necessary for the strategies.  
: 5. Conceptual sketches, as necessary to indicate equipment which is installed or equipment hookups necessary for the strategies. (As-built piping and instrumentation diagrams (P&ID) will be available upon completion of plant modifications.)
(As-built piping and instrumentation diagrams (P&ID) will be available upon completion of plant modifications.)  
: 6. Description of how the portable FLEX equipment will be available to be deployed in all modes.
: 6. Description of how the portable FLEX equipment will be available to be deployed in all modes. By letter dated August 28, 2013 [Reference 20], the NRC notified all licensees and construction permit holders that the staff is conducting audits of their responses to Order EA-12-049.
By letter dated August 28, 2013 [Reference 20], the NRC notified all licensees and construction permit holders that the staff is conducting audits of their responses to Order EA-12-049. That
That  letter described the process to be used by the staff in its reviews, leading to the issuance of this interim staff evaluation and audit report for each site. The purpose of the staff's audits is to determine the extent to which licensees are proceeding on a path towards successful implementation of the actions needed to achieve full compliance with the order. Additional NRC staff review and inspection may be necessary following full implementation of those actions to verify licensees' compliance with the order. 3.0 TECHNICAL EVALUATION The NRC staff contracted with Mega Tech Services, LLC (MTS) for technical support in the evaluation of the Integrated Plan for JAF, submitted by Entergy's letter dated February 28, 2013, as supplemented.
 
NRC and MTS staff have reviewed the submitted information and held clarifying discussions with Entergy in evaluating the licensee's plans for addressing BDBEEs and its progress towards implementing those plans. JAF is a boiling water reactor with a Mark I containment.
letter described the process to be used by the staff in its reviews, leading to the issuance of this interim staff evaluation and audit report for each site. The purpose of the staff's audits is to determine the extent to which licensees are proceeding on a path towards successful implementation of the actions needed to achieve full compliance with the order. Additional NRC staff review and inspection may be necessary following full implementation of those actions to verify licensees' compliance with the order.
A simplified description of the JAF Integrated Plan to mitigate the postulated extended loss of ac power (ELAP) event is that the licensee will initially remove the core decay heat by using the Reactor Core Isolation Cooling (RCIC) system and the High Pressure Coolant Injection (HPCI) system. The steam-driven RCIC pump and HPCI pump will initially supply water to the reactor pressure vessel (RPV) from the condensate storage tank (CST). The licensee noted that the CST has a robust design for the lower half and that most of the water volume should survive the BDBEE. The larger HPCI pump will be stopped by the operators about 20 minutes into the event, as RPV level is restored to its normal level. Steam from the RPV will be vented through the safety/relief valves (SRVs) to the suppression pool (SP) in the torus in order to control the pressure in the RPV. Once it has been determined to be an ELAP event (about the 60 minute point), operators will shift the RCIC suction to the SP in order to utilize the SP water before it becomes too hot for the RCIC pump. When the SP temperature reaches about 170 degrees Fahrenheit  
 
(°F), operators will shift the RCIC suction back to the CST. Steam from the RPV will then be vented through the SRVs to the SP to cool down the RPV. RPV depressurization will be stopped at a pressure between 200 to 400 pounds per square inch gauge (psig) to ensure sufficient steam pressure for continued RCIC operation.
==3.0     TECHNICAL EVALUATION==
Before the containment reaches its design pressure, the SP (torus) will be vented to atmosphere using the hardened vents to release steam and stop the pressure increase.
 
The licensee estimates that this will occur at about 23 hours into the event. When RCIC can no longer be operated  
The NRC staff contracted with Mega Tech Services, LLC (MTS) for technical support in the evaluation of the Integrated Plan for JAF, submitted by Entergy's letter dated February 28, 2013, as supplemented. NRC and MTS staff have reviewed the submitted information and held clarifying discussions with Entergy in evaluating the licensee's plans for addressing BDBEEs and its progress towards implementing those plans.
: reliably, operators will depressurize the RPV below 50 psig and use either the diesel-driven fire pump or FLEX pumps to inject water into the RPV from the ultimate heat sink (UHS), Lake Ontario.
JAF is a boiling water reactor with a Mark I containment. A simplified description of the JAF Integrated Plan to mitigate the postulated extended loss of ac power (ELAP) event is that the licensee will initially remove the core decay heat by using the Reactor Core Isolation Cooling (RCIC) system and the High Pressure Coolant Injection (HPCI) system. The steam-driven RCIC pump and HPCI pump will initially supply water to the reactor pressure vessel (RPV) from the condensate storage tank (CST). The licensee noted that the CST has a robust design for the lower half and that most of the water volume should survive the BDBEE. The larger HPCI pump will be stopped by the operators about 20 minutes into the event, as RPV level is restored to its normal level. Steam from the RPV will be vented through the safety/relief valves (SRVs) to the suppression pool (SP) in the torus in order to control the pressure in the RPV. Once it has been determined to be an ELAP event (about the 60 minute point), operators will shift the RCIC suction to the SP in order to utilize the SP water before it becomes too hot for the RCIC pump. When the SP temperature reaches about 170 degrees Fahrenheit (°F), operators will shift the RCIC suction back to the CST. Steam from the RPV will then be vented through the SRVs to the SP to cool down the RPV. RPV depressurization will be stopped at a pressure between 200 to 400 pounds per square inch gauge (psig) to ensure sufficient steam pressure for continued RCIC operation. Before the containment reaches its design pressure, the SP (torus) will be vented to atmosphere using the hardened vents to release steam and stop the pressure increase. The licensee estimates that this will occur at about [[estimated NRC review hours::23 hours]] into the event.
FLEX generators will be used to reenergize the installed battery chargers to keep the necessary direct current (de) buses energized, which will then keep the 120 volt ac instrument buses energized.
When RCIC can no longer be operated reliably, operators will depressurize the RPV below 50 psig and use either the diesel-driven fire pump or FLEX pumps to inject water into the RPV from the ultimate heat sink (UHS), Lake Ontario.
The licensee's long term plan is that they will utilize the industry Regional Response Centers (RRCs) for additional Phase 3 equipment.
FLEX generators will be used to reenergize the installed battery chargers to keep the necessary direct current (de) buses energized, which will then keep the 120 volt ac instrument buses energized. The licensee's long term plan is that they will utilize the industry Regional Response Centers (RRCs) for additional Phase 3 equipment. The Phase 3 generators from the RRC will be used to energize a plant residual heat removal (RHR) pump, and the plant systems needed for support, and reactor coolant system shutdown cooling will be established.
The Phase 3 generators from the RRC will be used to energize a plant residual heat removal (RHR) pump, and the plant systems needed for support, and reactor coolant system shutdown cooling will be established.
In the postulated ELAP event, the SFP will initially heat up due to the unavailability of the normal cooling system. A FLEX pump will be aligned and used to add water to the SFP to maintain
In the postulated ELAP event, the SFP will initially heat up due to the unavailability of the normal cooling system. A FLEX pump will be aligned and used to add water to the SFP to maintain   level as the pool boils. This will maintain a sufficient amount of water above the top of the fuel assemblies for cooling and shielding purposes.
 
To control containment parameters, Entergy plans to use containment (torus) venting to maintain containment pressure and temperature within acceptable values. By letter dated February 6, 2014 [Reference 21], MTS documented the interim results of the Integrated Plan review in the attached technical evaluation report (TER). The NRC staff has reviewed this TER for consistency with NRC policy and technical accuracy and finds that it accurately reflects the state of completeness of the Integrated Plan. The NRC staff therefore adopts the findings of the TER with respect to individual aspects of the requirements of Order EA-12-049.
level as the pool boils. This will maintain a sufficient amount of water above the top of the fuel assemblies for cooling and shielding purposes.
4.0 OPEN AND CONFIRMATORY ITEMS This section contains a summary of the open and confirmatory items identified as part of the technical evaluation.
To control containment parameters, Entergy plans to use containment (torus) venting to maintain containment pressure and temperature within acceptable values.
The NRC and MTS have assigned each review item to one of the following categories:
By letter dated February 6, 2014 [Reference 21], MTS documented the interim results of the Integrated Plan review in the attached technical evaluation report (TER). The NRC staff has reviewed this TER for consistency with NRC policy and technical accuracy and finds that it accurately reflects the state of completeness of the Integrated Plan. The NRC staff therefore adopts the findings of the TER with respect to individual aspects of the requirements of Order EA-12-049.
Confirmatory Item -an item that is considered conceptually acceptable, but for which resolution may be incomplete.
4.0     OPEN AND CONFIRMATORY ITEMS This section contains a summary of the open and confirmatory items identified as part of the technical evaluation. The NRC and MTS have assigned each review item to one of the following categories:
These items are expected to be acceptable, but are expected to require some minimal follow up review or audit prior to the licensee's compliance with Order EA-12-049.
Confirmatory Item - an item that is considered conceptually acceptable, but for which resolution may be incomplete. These items are expected to be acceptable, but are expected to require some minimal follow up review or audit prior to the licensee's compliance with Order EA-12-049.
Open Item -an item for which the licensee has not presented a sufficient basis to determine that the issue is on a path to resolution.
Open Item - an item for which the licensee has not presented a sufficient basis to determine that the issue is on a path to resolution. The intent behind designating an issue as an Open Item is to document items that need resolution during the review process, rather than being verified after the compliance date through the inspection process.
The intent behind designating an issue as an Open Item is to document items that need resolution during the review process, rather than being verified after the compliance date through the inspection process.
As discussed in Section 3.0, above, the NRC staff has reviewed MTS' TER for consistency with NRC policy and technical accuracy and finds that it accurately reflects the state of completeness of the licensee's Integrated Plan. The NRC staff therefore adopts the open and confirmatory items identified in the TER and listed in the tables below. Minor editorial changes were made by the NRC staff to some items. These summary tables provide a brief description of the issue of concern. Further details for each open and confirmatory item are provided in the corresponding sections of the TER, identified by the item number.
As discussed in Section 3.0, above, the NRC staff has reviewed MTS' TER for consistency with NRC policy and technical accuracy and finds that it accurately reflects the state of completeness of the licensee's Integrated Plan. The NRC staff therefore adopts the open and confirmatory items identified in the TER and listed in the tables below. Minor editorial changes were made by the NRC staff to some items. These summary tables provide a brief description of the issue of concern.
In the tables below, the NRC staff made the following change compared to the original summary tables in the TER, due to a determination that since the licensee has expertise in modifications, a detailed review is unnecessary:
Further details for each open and confirmatory item are provided in the corresponding sections of the TER, identified by the item number. In the tables below, the NRC staff made the following change compared to the original summary tables in the TER, due to a determination that since the licensee has expertise in modifications, a detailed review is unnecessary:  
: 1.       Open Item 3.4.A was moved to be Confirmatory Item 3.4.A to conform to previous NRC staff treatment of similar items.
: 1. Open Item 3.4.A was moved to be Confirmatory Item 3.4.A to conform to previous NRC staff treatment of similar items. 4.1 OPEN ITEMS Item Number Description Notes 3.1.1.3.A Procedural Interface (Seismic Hazard) -Evaluate the impacts from large internal flooding sources.
 
3.1.3.1.A Protection of FLEX Equipment (High Wind Hazard) -Evaluate Significant the separation distance and the axis of separation considering the predominant path of tornados in the geographic area to demonstrate that at least N sets of FLEX equipment would remain deployable in the context of a tornado missile hazard. 3.1.4.2.8 Deployment of FLEX Equipment (Snow, Ice and Extreme Cold) -Evaluate the potential impact on the UHS due to ice blockage or formation of frazil ice as a result of extreme cold. 3.2.3.A Containment-Verify that the implementation of Boiling Water Reactor Owners Group (BWROG) Emergency Procedure Guideline (EPG)/Severe Accident Guideline (SAG), Revision 3, including any associated plant-specific evaluations, has been completed in accordance with the provisions of NRC letter dated January 9, 2014 [Reference 23]. 4.2 CONFIRMATORY ITEMS Item Number Description Notes 3.1.1.2.A Deployment of FLEX Equipment-Confirm that soil liquefaction will not impede vehicle movement following a seismic event. 3.1.1.2.8 Deployment of FLEX Equipment-Confirm final design features of the new storage building including the susceptibility to the loss of ac power to deploy equipment.
4.1     OPEN ITEMS Item Number     Description                                                     Notes 3.1.1.3.A       Procedural Interface (Seismic Hazard) - Evaluate the impacts from large internal flooding sources.
3.1.1.2.C Deployment of FLEX Equipment  
3.1.3.1.A       Protection of FLEX Equipment (High Wind Hazard) - Evaluate       Significant the separation distance and the axis of separation considering the predominant path of tornados in the geographic area to demonstrate that at least N sets of FLEX equipment would remain deployable in the context of a tornado missile hazard.
-Confirm the storage locations and means of protection against the seismic hazard of the super duty pickup trucks and the two flatbed trailers used for deployment of FLEX equipment.
3.1.4.2.8       Deployment of FLEX Equipment (Snow, Ice and Extreme Cold)
3.1.1.4.A Offsite Resources-Confirm location of offsite staging area(s),
                  - Evaluate the potential impact on the UHS due to ice blockage or formation of frazil ice as a result of extreme cold.
3.2.3.A         Containment- Verify that the implementation of Boiling Water Reactor Owners Group (BWROG) Emergency Procedure Guideline (EPG)/Severe Accident Guideline (SAG), Revision 3, including any associated plant-specific evaluations, has been completed in accordance with the provisions of NRC letter dated January 9, 2014 [Reference 23].
4.2     CONFIRMATORY ITEMS Item Number     Description                                                       Notes 3.1.1.2.A       Deployment of FLEX Equipment- Confirm that soil liquefaction will not impede vehicle movement following a seismic event.
3.1.1.2.8       Deployment of FLEX Equipment- Confirm final design features of the new storage building including the susceptibility to the loss of ac power to deploy equipment.
3.1.1.2.C       Deployment of FLEX Equipment - Confirm the storage locations and means of protection against the seismic hazard of the super duty pickup trucks and the two flatbed trailers used for deployment of FLEX equipment.
3.1.1.4.A       Offsite Resources- Confirm location of offsite staging area(s),
access routes and methods of delivery of equipment to the site considering the seismic, flood, high wind, snow, ice and extreme cold hazards.
access routes and methods of delivery of equipment to the site considering the seismic, flood, high wind, snow, ice and extreme cold hazards.
3.1.3.2.A Deployment of FLEX Equipment (High Wind Hazard)-Confirm availability of debris removal equipment to facilitate deployment of FLEX equipment.
3.1.3.2.A       Deployment of FLEX Equipment (High Wind Hazard)- Confirm availability of debris removal equipment to facilitate deployment of FLEX equipment.
3.1.3.2.8 Deployment of FLEX Equipment (High Wind Hazard)-Confirm protection of the means to move FLEX equipment.
3.1.3.2.8       Deployment of FLEX Equipment (High Wind Hazard)- Confirm protection of the means to move FLEX equipment.
3.1.4.2.A Deployment of FLEX Equipment (Snow, Ice and Extreme Cold) -Confirm availability of snow removal equipment to facilitate   deployment of FLEX equipment.
3.1.4.2.A       Deployment of FLEX Equipment (Snow, Ice and Extreme Cold)
3.2.1.1.A Computer Code Used for ELAP Analysis  
                - Confirm availability of snow removal equipment to facilitate
-Benchmarks need to be identified and discussed which demonstrate that Modular Accident Analysis Program (MAAP) is an appropriate code for the simulation of an ELAP event at JAF. 3.2.1.1.8 Computer Code Used for ELAP Analysis  
 
-Confirm that the collapsed level remains above Top of Active Fuel (TAF) and the cool down rate is within technical specifications limits. 3.2.1.1.C Computer Code Used for ELAP Analysis  
deployment of FLEX equipment.
-Confirm that MAAP was used in accordance with Sections 4.1, 4.2, 4.3, 4.4, and 4.5 of the June 2013 position paper (ADAMS Accession No. ML 13190A201
3.2.1.1.A Computer Code Used for ELAP Analysis - Benchmarks need to be identified and discussed which demonstrate that Modular Accident Analysis Program (MAAP) is an appropriate code for the simulation of an ELAP event at JAF.
). 3.2.1.1.D Computer Code Used for ELAP Analysis  
3.2.1.1.8 Computer Code Used for ELAP Analysis -Confirm that the collapsed level remains above Top of Active Fuel (TAF) and the cool down rate is within technical specifications limits.
-Confirm that the licensee, in using MAAP, identified and justified the subset of key modeling parameters cited from Tables 4-1 through 4-6 of the "MAAP Application  
3.2.1.1.C Computer Code Used for ELAP Analysis - Confirm that MAAP was used in accordance with Sections 4.1, 4.2, 4.3, 4.4, and 4.5 of the June 2013 position paper (ADAMS Accession No. ML13190A201 ).
: Guidance, Desktop Reference for Using MAAP Software, Revision 2" (Electric Power Research Institute Report 1 020236).
3.2.1.1.D Computer Code Used for ELAP Analysis - Confirm that the licensee, in using MAAP, identified and justified the subset of key modeling parameters cited from Tables 4-1 through 4-6 of the "MAAP Application Guidance, Desktop Reference for Using MAAP Software, Revision 2" (Electric Power Research Institute Report 1020236).
3.2.1.1.E Computer Code Used for ELAP Analysis  
3.2.1.1.E Computer Code Used for ELAP Analysis - Confirm that the specific MAAP analysis case that was used to validate the timing of mitigating strategies in the Integrated Plan has been identified and is available for NRC staff to review. Alternately, a comparable level of information has been included in the supplemental response. In either case, the analysis should include a plot of the collapsed vessel level to confirm that TAF is not reached {the elevation of the TAF should be provided) and a plot of the temperature cool down to confirm that the cool down is within technical specifications limits.
-Confirm that the specific MAAP analysis case that was used to validate the timing of mitigating strategies in the Integrated Plan has been identified and is available for NRC staff to review. Alternately, a comparable level of information has been included in the supplemental response.
3.2.1.2.A Recirculation Pump Seal Leakage Models - Confirm the seal leakage model used in the updated MAAP analysis (which will address the MAAP code limitations when used for ELAP analysis). Evaluate the seal leakage rate model used, the details of the seal qualification tests and supporting test data, and leakage rate pressure-dependence.
In either case, the analysis should include a plot of the collapsed vessel level to confirm that TAF is not reached {the elevation of the TAF should be provided) and a plot of the temperature cool down to confirm that the cool down is within technical specifications limits. 3.2.1.2.A Recirculation Pump Seal Leakage Models -Confirm the seal leakage model used in the updated MAAP analysis (which will address the MAAP code limitations when used for ELAP analysis).
3.2.1.3.A Sequence of Events (SOE)- Confirm the SOE timeline after reanalysis using the MAAP code which will address the limitations when used for the ELAP analysis.
Evaluate the seal leakage rate model used, the details of the seal qualification tests and supporting test data, and leakage rate pressure-dependence.
3.2.1.4.A Systems and Components for Consequence Mitigation -
3.2.1.3.A Sequence of Events (SOE)-Confirm the SOE timeline after reanalysis using the MAAP code which will address the limitations when used for the ELAP analysis.
Confirm sizing of the FLEX pumps and 600 Vac FLEX diesel generator (DG) and the 4160 Vac generator to be obtained from the RRC.
3.2.1.4.A Systems and Components for Consequence Mitigation  
3.2.1.5.A Monitoring Instrumentation and Controls- Confirm ac powered torus temperature, pressure and level and drywell temperature and pressure instrumentation is modified to remain powered during an ELAP.
-Confirm sizing of the FLEX pumps and 600 Vac FLEX diesel generator (DG) and the 4160 Vac generator to be obtained from the RRC. 3.2.1.5.A Monitoring Instrumentation and Controls-Confirm ac powered torus temperature, pressure and level and drywell temperature and pressure instrumentation is modified to remain powered during an ELAP. 3.2.1.8.A Use of Portable Pumps -Confirm that the use of raw water from   Lake Ontario for long term core and spent fuel pool cooling strategies is acceptable.
3.2.1.8.A Use of Portable Pumps - Confirm that the use of raw water from
3.2.2.A Spent Fuel Pool Cooling -Confirm the method of ventilation and power requirements, if any, of the spent fuel pool area. 3.2.4.2.A Ventilation (Equipment Cooling)-
 
Confirm that additional evaluations of the RCIC room temperature demonstrate that an acceptable environment is maintained during the transition phase both for equipment in the room and habitability for operators who may need to enter the room. 3.2.4.2.8 Ventilation (Equipment Cooling)-
Lake Ontario for long term core and spent fuel pool cooling strategies is acceptable.
Confirm that evaluations of the battery room temperature demonstrate that an acceptable environment, during both high ambient temperature and during extreme cold ambient temperature, is maintained during Phases 2 and 3. 3.2.4.2.C Ventilation (Equipment Cooling)-
3.2.2.A           Spent Fuel Pool Cooling - Confirm the method of ventilation and power requirements, if any, of the spent fuel pool area.
Confirm the required ventilation flow or the size of the portable fans to maintain acceptable environmental conditions in the DC equipment room. 3.2.4.3.A Heat Tracing -Confirm completion of walkdowns and evaluation of where heat tracing may be needed for freeze protection of equipment or instruments used in the ELAP mitigation strategies.
3.2.4.2.A         Ventilation (Equipment Cooling)- Confirm that additional evaluations of the RCIC room temperature demonstrate that an acceptable environment is maintained during the transition phase both for equipment in the room and habitability for operators who may need to enter the room.
3.2.4.4.A Lighting  
3.2.4.2.8         Ventilation (Equipment Cooling)- Confirm that evaluations of the battery room temperature demonstrate that an acceptable environment, during both high ambient temperature and during extreme cold ambient temperature, is maintained during Phases 2 and 3.
-Confirm need for additional portable  
3.2.4.2.C         Ventilation (Equipment Cooling)- Confirm the required ventilation flow or the size of the portable fans to maintain acceptable environmental conditions in the DC equipment room.
: lighting, such as de powered lights. 3.2.4.4.8 Communications  
3.2.4.3.A         Heat Tracing - Confirm completion of walkdowns and evaluation of where heat tracing may be needed for freeze protection of equipment or instruments used in the ELAP mitigation strategies.
-Confirm that upgrades to the site's communication system have been completed.
3.2.4.4.A         Lighting - Confirm need for additional portable lighting, such as de powered lights.
3.2.4.8.A Electrical Power Sources -Confirm the technical basis for the selection and size of the FLEX generators to be used in support of the coping strategies.
3.2.4.4.8         Communications - Confirm that upgrades to the site's communication system have been completed.
3.2.4.10.A Load Reduction to Conserve DC Power -Confirm final load shed list and the evaluation of any potential adverse effects of shedding those loads. 3.2.4.10.8 Load Reduction to Conserve DC Power -Confirm the final de load profile with the required loads and the finalized minimum battery voltage.
3.2.4.8.A         Electrical Power Sources - Confirm the technical basis for the selection and size of the FLEX generators to be used in support of the coping strategies.
3.2.4.10.C Load Reduction to Conserve DC Power-Confirm time after the ELAP for connecting the FLEX DG to the battery chargers.
3.2.4.10.A       Load Reduction to Conserve DC Power - Confirm final load shed list and the evaluation of any potential adverse effects of shedding those loads.
3.4.A Off-site Resources-Confirm that NEI 12-06, Section 12.2 guidelines 2 through 10 are addressed, or that an appropriate alternative is justified.
3.2.4.10.8       Load Reduction to Conserve DC Power - Confirm the final de load profile with the required loads and the finalized minimum battery voltage.
Based on a review of Entergy's plan, including the six-month update dated August 28, 2013, and information obtained through the mitigation strategies audit process, the NRC concludes that the licensee has provided sufficient information to determine that there is reasonable assurance that the plan, when properly implemented, will meet the requirements of Order EA-12-049 at JAF. This conclusion is based on the assumption that the licensee will implement the plan as described, including the satisfactory resolution of the open and confirmatory items. 5.0 SUMMARY As required by Order EA-12-049, the licensee is developing, and will implement and maintain, guidance and strategies to restore or maintain core cooling, containment, and SFP cooling capabilities in the event of a BDBEE. These new requirements provide a greater mitigation capability consistent with the overall defense-in-depth philosophy, and, therefore, greater assurance that the challenges posed by BDBEEs to power reactors do not pose an undue risk to public health and safety. The NRC's objective in preparing this interim staff evaluation and audit report is to provide a finding to the licensee on whether or not their integrated plan, if implemented as described, provides a reasonable path for compliance with the order. For areas where the NRC staff has insufficient information to make this finding (identified above in Section 4.0), the staff will review these areas as they become available or address them as part of the inspection process.
3.2.4.10.C       Load Reduction to Conserve DC Power- Confirm time after the ELAP for connecting the FLEX DG to the battery chargers.
The staff notes that the licensee has the ability to modify their plans as stated in NEI 12-06, Section 11.8. However, additional NRC review and/or inspection may be necessary to verify compliance.
3.4.A             Off-site Resources- Confirm that NEI 12-06, Section 12.2 guidelines 2 through 10 are addressed, or that an appropriate alternative is justified.
Based on a review of Entergy's plan, including the six-month update dated August 28, 2013, and information obtained through the mitigation strategies audit process, the NRC concludes that the licensee has provided sufficient information to determine that there is reasonable assurance that the plan, when properly implemented, will meet the requirements of Order EA-12-049 at JAF. This conclusion is based on the assumption that the licensee will implement the plan as described, including the satisfactory resolution of the open and confirmatory items.
 
5.0    
 
==SUMMARY==
 
As required by Order EA-12-049, the licensee is developing, and will implement and maintain, guidance and strategies to restore or maintain core cooling, containment, and SFP cooling capabilities in the event of a BDBEE. These new requirements provide a greater mitigation capability consistent with the overall defense-in-depth philosophy, and, therefore, greater assurance that the challenges posed by BDBEEs to power reactors do not pose an undue risk to public health and safety.
The NRC's objective in preparing this interim staff evaluation and audit report is to provide a finding to the licensee on whether or not their integrated plan, if implemented as described, provides a reasonable path for compliance with the order. For areas where the NRC staff has insufficient information to make this finding (identified above in Section 4.0), the staff will review these areas as they become available or address them as part of the inspection process. The staff notes that the licensee has the ability to modify their plans as stated in NEI 12-06, Section 11.8. However, additional NRC review and/or inspection may be necessary to verify compliance.
The NRC staff has reviewed the licensee's plans for additional defense-in-depth measures.
The NRC staff has reviewed the licensee's plans for additional defense-in-depth measures.
With the exception of the items noted in Section 4.0 above, the staff finds that the proposed  
With the exception of the items noted in Section 4.0 above, the staff finds that the proposed measures, properly implemented, will meet the intent of Order EA-12-049, thereby enhancing the licensee's capability to mitigate the consequences of a BDBEE that impacts the availability of ac power and the UHS. Full compliance with the order will enable the NRC to continue to have reasonable assurance of adequate protection of public health and safety. The staff will issue a safety evaluation confirming compliance with the order and may conduct inspections to verify proper implementation of the licensee's proposed measures.
: measures, properly implemented, will meet the intent of Order EA-12-049, thereby enhancing the licensee's capability to mitigate the consequences of a BDBEE that impacts the availability of ac power and the UHS. Full compliance with the order will enable the NRC to continue to have reasonable assurance of adequate protection of public health and safety. The staff will issue a safety evaluation confirming compliance with the order and may conduct inspections to verify proper implementation of the licensee's proposed measures.  


==6.0 REFERENCES==
==6.0     REFERENCES==
: 1. Order EA-12-049, "Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events,"
: 1.     Order EA-12-049, "Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events," March 12, 2012 (ADAMS Accession No. ML12054A736)
March 12, 2012 (ADAMS Accession No. ML 12054A736)  
: 2.       Letter from Entergy to NRC, "Overall Integrated Plan in Response to March 12, 2012 Commission Order to Modify Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049)," dated February 28, 2013 (ADAMS Accession No. ML13063A287)
: 2. Letter from Entergy to NRC, "Overall Integrated Plan in Response to March 12, 2012 Commission Order to Modify Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049),"
: 3.     Letter from Entergy to NRC, "First Six-Month Status Report In Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond Design Basis External Events (Order Number EA-12-049)," dated August 28, 2013 (ADAMS Accession No. ML13241A204)
dated February 28, 2013 (ADAMS Accession No. ML 13063A287)  
: 4.     SECY-11-0093, "Near-Term Report and Recommendations for Agency Actions Following the Events in Japan," July 12, 2011 (ADAMS Accession No. ML11186A950)
: 3. Letter from Entergy to NRC, "First Six-Month Status Report In Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond Design Basis External Events (Order Number EA-12-049),"
: 5.     SECY-11-0124, "Recommended Actions to be Taken without Delay from the Near-Term Task Force Report," September 9, 2011 (ADAMS Accession No. ML11245A158)
dated August 28, 2013 (ADAMS Accession No. ML 13241A204)  
: 6. SECY-11-0137, "Prioritization of Recommended Actions to be Taken in Response to Fukushima Lessons Learned," October 3, 2011 (ADAMS Accession No. ML11272A111)
: 4. SECY-11-0093, "Near-Term Report and Recommendations for Agency Actions Following the Events in Japan," July 12, 2011 (ADAMS Accession No. ML 11186A950)  
: 7. SRM-SECY-11-0093, "Staff Requirements- SECY-11-0093- Near-Term Report and Recommendations for Agency Actions following the Events in Japan," August 19, 2011 (ADAMS Accession No. ML112310021)
: 5. SECY-11-0124, "Recommended Actions to be Taken without Delay from the Near-Term Task Force Report,"
: 8. SRM-SECY-11-0124, "Staff Requirements- SECY-11-0124- Recommended Actions to be Take without Delay from the Near-Term Task Force Report," October 18, 2011 (ADAMS Accession No. ML112911571)
September 9, 2011 (ADAMS Accession No. ML 11245A158)   6. SECY-11-0137, "Prioritization of Recommended Actions to be Taken in Response to Fukushima Lessons Learned,"
: 9. SRM-SECY-11-0137, "Staff Requirements- SECY-11-0137- Prioritization of Recommended Actions to be Taken in Response to Fukushima Lessons Learned,"
October 3, 2011 (ADAMS Accession No. ML 11272A 111) 7. SRM-SECY-11-0093, "Staff Requirements-SECY-11-0093-Near-Term Report and Recommendations for Agency Actions following the Events in Japan," August 19, 2011 (ADAMS Accession No. ML 11231 0021) 8. SRM-SECY-11-0124, "Staff Requirements-SECY-11-0124-Recommended Actions to be Take without Delay from the Near-Term Task Force Report,"
December 15, 2011 (ADAMS Accession No. ML113490055)
October 18, 2011 (ADAMS Accession No. ML 112911571)  
: 10. Letter from Adrian Heymer (NEI) to David L. Skeen (NRC), "An Integrated, Safety-Focused Approach to Expediting Implementation of Fukushima Dai-ichi Lessons Learned," December 16, 2011 (ADAMS Accession No. ML11353A008)
: 9. SRM-SECY-11-0137, "Staff Requirements-SECY-11-0137-Prioritization of Recommended Actions to be Taken in Response to Fukushima Lessons Learned,"
: 11. SECY-12-0025, "Proposed Orders and Requests for Information in Response to Lessons Learned from Japan's March 11, 2011, Great Tohoku Earthquake and Tsunami," February 17, 2012 (ADAMS Accession No. ML12039A103)
December 15, 2011 (ADAMS Accession No. ML 113490055)  
: 12. SRM-SECY-12-0025, "Staff Requirements- SECY-12-0025- Proposed Orders and Requests for Information in Response to Lessons Learned from Japan's March 11, 2011, Great Tohoku Earthquake and Tsunami," March 9, 2012 (ADAMS Accession No. ML120690347)
: 10. Letter from Adrian Heymer (NEI) to David L. Skeen (NRC), "An Integrated, Safety-Focused Approach to Expediting Implementation of Fukushima Dai-ichi Lessons Learned,"
: 13. Nuclear Energy Institute (NEI) document 12-06, "Diverse and Flexible Coping Strategies (FLEX) Implementation Guide," Revision B, May 4, 2012 (ADAMS Accession No. ML12144A419)
December 16, 2011 (ADAMS Accession No. ML 11353A008)  
: 14. NEI document NEI 12-06, "Diverse and Flexible Coping Strategies (FLEX)
: 11. SECY-12-0025, "Proposed Orders and Requests for Information in Response to Lessons Learned from Japan's March 11, 2011, Great Tohoku Earthquake and Tsunami,"
Implementation Guide," Revision B1, May 13, 2012 (ADAMS Accession No. ML12143A232)
February 17, 2012 (ADAMS Accession No. ML 12039A 1 03) 12. SRM-SECY-12-0025, "Staff Requirements-SECY-12-0025-Proposed Orders and Requests for Information in Response to Lessons Learned from Japan's March 11, 2011, Great Tohoku Earthquake and Tsunami,"
: 15. Draft JLD-ISG-2012-01, "Compliance with Order EA-12-049, Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events," May 31, 2012 (ADAMS Accession No. ML12146A014)
March 9, 2012 (ADAMS Accession No. ML 120690347)  
: 13. Nuclear Energy Institute (NEI) document 12-06, "Diverse and Flexible Coping Strategies (FLEX) Implementation Guide," Revision B, May 4, 2012 (ADAMS Accession No. ML 12144A419)  
: 14. NEI document NEI 12-06, "Diverse and Flexible Coping Strategies (FLEX) Implementation Guide," Revision B1, May 13, 2012 (ADAMS Accession No. ML 12143A232)  
: 15. Draft JLD-ISG-2012-01, "Compliance with Order EA-12-049, Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events,"
May 31, 2012 (ADAMS Accession No. ML 12146A014)  
: 16. NRC Response to Public Comments, JLD-ISG-2012-01 (Docket ID NRC-2012-0068),
: 16. NRC Response to Public Comments, JLD-ISG-2012-01 (Docket ID NRC-2012-0068),
August 29, 2012 (ADAMS Accession No. ML 12229A253)  
August 29, 2012 (ADAMS Accession No. ML12229A253)
: 17. NEI comments to draft JLD-ISG-2012-01 and document 12-06, "Diverse and Flexible Coping Strategies (FLEX) Implementation Guide," Revision C, July 3, 2012 (ADAMS Accession No. ML 121910390)   18. NEI document 12-06, "Diverse and Flexible Coping Strategies (FLEX) Implementation Guide," Revision 0, August 21, 2012 (ADAMS Accession No. ML 12242A378)  
: 17. NEI comments to draft JLD-ISG-2012-01 and document 12-06, "Diverse and Flexible Coping Strategies (FLEX) Implementation Guide," Revision C, July 3, 2012 (ADAMS Accession No. ML121910390)
: 19. Final Interim Staff Guidance JLD-ISG-2012-01, "Compliance with Order EA-12-049, Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events,"
: 18. NEI document 12-06, "Diverse and Flexible Coping Strategies (FLEX) Implementation Guide," Revision 0, August 21, 2012 (ADAMS Accession No. ML12242A378)
August 29, 2012 (ADAMS Accession No. ML 12229A174)  
: 19. Final Interim Staff Guidance JLD-ISG-2012-01, "Compliance with Order EA-12-049, Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events," August 29, 2012 (ADAMS Accession No. ML12229A174)
: 20. Letter from Jack R. Davis (NRC) to All Operating Reactor Licensees and Holders of Construction  
: 20. Letter from Jack R. Davis (NRC) to All Operating Reactor Licensees and Holders of Construction Permits, "Nuclear Regulatory Commission Audits of Licensee Responses to Mitigation Strategies Order EA-12-049," August 28, 2013 (ADAMS Accession No. ML13234A503)
: Permits, "Nuclear Regulatory Commission Audits of Licensee Responses to Mitigation Strategies Order EA-12-049,"
: 21. Letter from John Bowen, MegaTech Services, LLC, to Eric Bowman, NRC, submitting "Technical Evaluation Reports Related to Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events, EA 12-049," dated February 15, 2014 (ADAMS Accession No. ML14049A207)
August 28, 2013 (ADAMS Accession No. ML 13234A503)  
: 22. Order EA-13-1 09, "Order to Modify Licenses with Regard to Reliable Hardened Containment Vents Capable of Operation Under Severe Accident Conditions," June 6, 2013 (ADAMS Accession No. ML13143A321)
: 21. Letter from John Bowen, MegaTech  
: 23. Letter from Jack R. Davis (NRC) to Joseph E. Pollock (NEI) dated January 9, 2014, regarding Boiling Water Reactor Containment Venting (ADAMS Accession No. ML13358A206)
: Services, LLC, to Eric Bowman, NRC, submitting "Technical Evaluation Reports Related to Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events, EA 12-049," dated February 15, 2014 (ADAMS Accession No. ML 14049A207)  
Principal Contributors:       E. Bowman B. Lee R. Fitzpatrick G. Armstrong K. Heller J. Boska Date: February 21, 2014
: 22. Order EA-13-1 09, "Order to Modify Licenses with Regard to Reliable Hardened Containment Vents Capable of Operation Under Severe Accident Conditions,"
 
June 6, 2013 (ADAMS Accession No. ML 13143A321)  
Enclosure 2 Technical Evaluation Report
: 23. Letter from Jack R. Davis (NRC) to Joseph E. Pollock (NEI) dated January 9, 2014, regarding Boiling Water Reactor Containment Venting (ADAMS Accession No. ML 13358A206)
 
Principal Contributors:
Mega-Tech Services, LLC Technical Evaluation Report Related to Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events, EA-12-049 Revision 1 February 15, 2014 Entergy Nuclear Northeast Entergy Nuclear Operations, Inc.
Date: February 21, 2014 E. Bowman B. Lee R. Fitzpatrick G. Armstrong K. Heller J. Boska Enclosure 2 Technical Evaluation Report Mega-Tech  
James A. FitzPatrick Nuclear Power Plant Docket No. 50-333 Prepared for:
: Services, LLC Technical Evaluation Report Related to Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events, EA-12-049 Revision 1 February 15, 2014 Entergy Nuclear Northeast Entergy Nuclear Operations, Inc. James A. FitzPatrick Nuclear Power Plant Docket No. 50-333 Prepared for: U.S. Nuclear Regulatory Commission Washington, D.C. 20555 Contract N RC-HQ-13-C-03-0039 Task Order No. NRC-HQ-13-T-03-0001 Job Code: J4672 TAC No. MF1077 Prepared by: Mega-Tech  
U.S. Nuclear Regulatory Commission Washington, D.C. 20555 Contract N RC-HQ-13-C-03-0039 Task Order No. NRC-HQ-13-T-03-0001 Job Code: J4672 TAC No. MF1077 Prepared by:
: Services, LLC 11118 Manor View Drive Mechanicsville, Virginia 23116 11118 Manor View Drive
Mega-Tech Services, LLC 11118 Manor View Drive Mechanicsville, Virginia 23116 11118 Manor View Drive
* Mechanicsville, Virginia 23116 804.789.1577
* Mechanicsville, Virginia 23116 804.789.1577
* Fax: 804.789.1578 www.mega-techservices.biz 1.0 BACKGROUND Technical Evaluation Report James A FitzPatrick Nuclear Power Plant Order EA-12-049 Evaluation Following the events at the Fukushima Dai-ichi nuclear power plant on March 11, 2011, the U.S. Nuclear Regulatory Commission (NRC) established a senior-level agency task force referred to as the Near-Term Task Force (NTTF). The NTTF was tasked with conducting a systematic, methodical review of NRC regulations and processes to determine if the agency should make additional improvements to these programs in light of the events at Fukushima Dai-ichi.
* Fax: 804.789.1578 www.mega-techservices.biz
As a result of this review, the NTTF developed a comprehensive set of recommendations, documented in SECY-11-0093, "Near-Term Report and Recommendations for Agency Actions Following the Events in Japan," dated July 12, 2011. These recommendations were enhanced by the NRC staff following interactions with stakeholders.
 
Documentation of the staff's efforts is contained in SECY-11-0124, "Recommended Actions to be Taken without Delay from the Near-Term Task Force Report,"
Technical Evaluation Report James A FitzPatrick Nuclear Power Plant Order EA-12-049 Evaluation
dated September 9, 2011, and SECY-11-0137, "Prioritization of Recommended Actions to be Taken in Response to Fukushima Lessons Learned,"
 
dated October 3, 2011. As directed by the Commission's staff requirement memorandum (SRM) for SECY-11-0093, the NRC staff reviewed the NTTF recommendations within the context of the NRC's existing regulatory framework and considered the various regulatory vehicles available to the NRC to implement the recommendations.
==1.0      BACKGROUND==
SECY-11-0124 and SECY-11-0137 established the staff's prioritization of the recommendations.
 
After receiving the Commission's direction in SRM-SECY-11-0124 and SRM-SECY-11-0137, the NRC staff conducted public meetings to discuss enhanced mitigation strategies intended to maintain or restore core cooling, containment, and spent fuel pool (SFP) cooling capabilities following beyond-design-basis external events (BDBEEs).
Following the events at the Fukushima Dai-ichi nuclear power plant on March 11, 2011, the U.S. Nuclear Regulatory Commission (NRC) established a senior-level agency task force referred to as the Near-Term Task Force (NTTF). The NTTF was tasked with conducting a systematic, methodical review of NRC regulations and processes to determine if the agency should make additional improvements to these programs in light of the events at Fukushima Dai-ichi. As a result of this review, the NTTF developed a comprehensive set of recommendations, documented in SECY-11-0093, "Near-Term Report and Recommendations for Agency Actions Following the Events in Japan," dated July 12, 2011. These recommendations were enhanced by the NRC staff following interactions with stakeholders.
At these meetings, the industry described its proposal for a Diverse and Flexible Mitigation Capability (FLEX), as documented in Nuclear Energy Institute's (NEI) letter, dated December 16, 2011 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML 11353A008).
Documentation of the staff's efforts is contained in SECY-11-0124, "Recommended Actions to be Taken without Delay from the Near-Term Task Force Report," dated September 9, 2011, and SECY-11-0137, "Prioritization of Recommended Actions to be Taken in Response to Fukushima Lessons Learned," dated October 3, 2011.
FLEX was proposed as a strategy to fulfill the key safety functions of core cooling, containment integrity, and spent fuel cooling.
As directed by the Commission's staff requirement memorandum (SRM) for SECY-11-0093, the NRC staff reviewed the NTTF recommendations within the context of the NRC's existing regulatory framework and considered the various regulatory vehicles available to the NRC to implement the recommendations. SECY-11-0124 and SECY-11-0137 established the staff's prioritization of the recommendations.
Stakeholder input influenced the NRC staff to pursue a more performance-based approach to improve the safety of operating power reactors relative to the approach that was envisioned in NTTF Recommendation 4.2, SECY-11-0124, and SECY-11-0137. On February 17, 2012, the NRC staff provided SECY-12-0025, "Proposed Orders and Requests for Information in Response to Lessons Learned from Japan's March 11, 2011, Great Tohoku Earthquake and Tsunami,"
After receiving the Commission's direction in SRM-SECY-11-0124 and SRM-SECY-11-0137, the NRC staff conducted public meetings to discuss enhanced mitigation strategies intended to maintain or restore core cooling, containment, and spent fuel pool (SFP) cooling capabilities following beyond-design-basis external events (BDBEEs). At these meetings, the industry described its proposal for a Diverse and Flexible Mitigation Capability (FLEX), as documented in Nuclear Energy Institute's (NEI) letter, dated December 16, 2011 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML11353A008). FLEX was proposed as a strategy to fulfill the key safety functions of core cooling, containment integrity, and spent fuel cooling. Stakeholder input influenced the NRC staff to pursue a more performance-based approach to improve the safety of operating power reactors relative to the approach that was envisioned in NTTF Recommendation 4.2, SECY-11-0124, and SECY 0137.
to the Commission, including the proposed order to implement the enhanced mitigation strategies.
On February 17, 2012, the NRC staff provided SECY-12-0025, "Proposed Orders and Requests for Information in Response to Lessons Learned from Japan's March 11, 2011, Great Tohoku Earthquake and Tsunami," to the Commission, including the proposed order to implement the enhanced mitigation strategies. As directed by SRM-SECY-12-0025, the NRC staff issued Order EA-12-049, "Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events."
As directed by SRM-SECY-12-0025, the NRC staff issued Order EA-12-049, "Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events."
Guidance and strategies required by the Order would be available if a loss of power, motive force and normal access to the ultimate heat sink needed to prevent fuel damage in the reactor and SFP affected all units at a site simultaneously. The Order requires a three-phase approach for mitigating BDBEEs. The initial phase requires the use of installed equipment and resources Revision 1                                   Page 2 of 60                               2014-02-15
Guidance and strategies required by the Order would be available if a loss of power, motive force and normal access to the ultimate heat sink needed to prevent fuel damage in the reactor and SFP affected all units at a site simultaneously.
 
The Order requires a three-phase approach for mitigating BDBEEs. The initial phase requires the use of installed equipment and resources Revision 1 Page 2 of 60 2014-02-15 to maintain or restore key safety functions including core cooling, containment, and SFP cooling.
to maintain or restore key safety functions including core cooling, containment, and SFP cooling. The transition phase requires providing sufficient portable onsite equipment and consumables to maintain or restore these functions until they can be accomplished with resources brought from offsite. The final phase requires obtaining sufficient offsite resources to sustain those functions indefinitely.
The transition phase requires providing sufficient portable onsite equipment and consumables to maintain or restore these functions until they can be accomplished with resources brought from offsite.
NEI submitted its document NEI 12-06, "Diverse and Flexible Coping Strategies (FLEX)
The final phase requires obtaining sufficient offsite resources to sustain those functions indefinitely.
Implementation Guide" in August 2012 (ADAMS Accession No. ML12242A378) to provide specifications for an industry-developed methodology for the development, implementation, and maintenance of guidance and strategies in response to Order EA-12-049. The guidance and strategies described in NEI 12-06 expand on those that industry developed and implemented to address the limited set of BDBEEs that involve the loss of a large area of the plant due to explosions and fire required pursuant to paragraph (hh)(2) of 10 CFR 50.54, "Conditions of licenses."
NEI submitted its document NEI 12-06, "Diverse and Flexible Coping Strategies (FLEX) Implementation Guide" in August 2012 (ADAMS Accession No. ML 12242A378) to provide specifications for an industry-developed methodology for the development, implementation, and maintenance of guidance and strategies in response to Order EA-12-049.
As described in Interim Staff Guidance (ISG), JLD-ISG-2012-01, "Compliance with Order EA-12-049, Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events," the NRC staff considers that the development, implementation, and maintenance of guidance and strategies in conformance with the guidelines provided in NEI 12-06, Revision 0, subject to the clarifications in Attachment 1 of the ISG are an acceptable means of meeting the requirements of Order EA-12-049.
The guidance and strategies described in NEI 12-06 expand on those that industry developed and implemented to address the limited set of BDBEEs that involve the loss of a large area of the plant due to explosions and fire required pursuant to paragraph (hh)(2) of 10 CFR 50.54, "Conditions of licenses."
As described in Interim Staff Guidance (ISG), JLD-ISG-2012-01, "Compliance with Order EA-12-049, Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events,"
the NRC staff considers that the development, implementation, and maintenance of guidance and strategies in conformance with the guidelines provided in NEI 12-06, Revision 0, subject to the clarifications in Attachment 1 of the ISG are an acceptable means of meeting the requirements of Order EA-12-049.
In response to Order EA-12-049, licensees submitted Overall Integrated Plans (hereafter, the Integrated Plan) describing their course of action for mitigation strategies that are to conform with the guidance of NEI 12-06, or provide an acceptable alternative to demonstrate compliance with the requirements of Order EA-12-049.
In response to Order EA-12-049, licensees submitted Overall Integrated Plans (hereafter, the Integrated Plan) describing their course of action for mitigation strategies that are to conform with the guidance of NEI 12-06, or provide an acceptable alternative to demonstrate compliance with the requirements of Order EA-12-049.
2.0 EVALUATION PROCESS In accordance with the provisions of Contract NRC-HQ-13-C-03-0039, Task Order No. NRC-HQ-13-T-03-0001, Mega-Tech  
2.0     EVALUATION PROCESS In accordance with the provisions of Contract NRC-HQ-13-C-03-0039, Task Order No.
: Services, LLC (MTS) performed an evaluation of each licensee's Integrated Plan. As part of the evaluation, MTS, in parallel with the NRC staff, reviewed the original Integrated Plan and the first 6-month status update, and conducted an audit of the licensee documents.
NRC-HQ-13-T-03-0001, Mega-Tech Services, LLC (MTS) performed an evaluation of each licensee's Integrated Plan. As part of the evaluation, MTS, in parallel with the NRC staff, reviewed the original Integrated Plan and the first 6-month status update, and conducted an audit of the licensee documents. The staff and MTS also reviewed the licensee's answers to the NRC staff's and MTS's questions as part of the audit process. The objective of the evaluation was to assess whether the proposed mitigation strategies conformed to the guidance in NEI 12-06, as endorsed by the positions stated in JLD-ISG-2012-01, or an acceptable alternative had been proposed that would satisfy the requirements of Order EA-12-049. The audit plan that describes the audit process was provided to all licensees in a letter dated August 28, 2013 from Jack R. Davis, Director, Mitigation Strategies Directorate (ADAMS Accession No. ML13234A503).
The staff and MTS also reviewed the licensee's answers to the NRC staff's and MTS's questions as part of the audit process.
The objective of the evaluation was to assess whether the proposed mitigation strategies conformed to the guidance in NEI 12-06, as endorsed by the positions stated in JLD-ISG-2012-01, or an acceptable alternative had been proposed that would satisfy the requirements of Order EA-12-049.
The audit plan that describes the audit process was provided to all licensees in a letter dated August 28, 2013 from Jack R. Davis, Director, Mitigation Strategies Directorate (ADAMS Accession No. ML 13234A503).
The review and evaluation of the licensee's Integrated Plan was performed in the following areas consistent with NEI 12-06 and the regulatory guidance of JLD-ISG-2012-01:
The review and evaluation of the licensee's Integrated Plan was performed in the following areas consistent with NEI 12-06 and the regulatory guidance of JLD-ISG-2012-01:
* Evaluation of External Hazards
* Evaluation of External Hazards
* Phased Approach Initial Response Phase Transition Phase Final Phase
* Phased Approach
* Core Cooling Strategies Revision 1 Page 3 of 60 2014-02-15
        ~ Initial Response Phase
        ~ Transition Phase
        ~ Final Phase
* Core Cooling Strategies Revision 1                                 Page 3 of 60                                 2014-02-15
* SFP Cooling Strategies
* SFP Cooling Strategies
* Containment Function Strategies
* Containment Function Strategies
* Programmatic Controls Equipment Protection,  
* Programmatic Controls
: Storage, and Deployment Equipment Quality The technical evaluation in Section 3.0 documents the results of the MTS evaluation and audit results.
          ~ Equipment Protection, Storage, and Deployment
Section 4.0 summarizes Confirmatory Items and Open Items that require further evaluation before a conclusion can be reached that the Integrated Plan is consistent with the guidance in NEI 12-06 or an acceptable alternative has been proposed that would satisfy the requirements of Order EA-12-049.
          ~ Equipment Quality The technical evaluation in Section 3.0 documents the results of the MTS evaluation and audit results. Section 4.0 summarizes Confirmatory Items and Open Items that require further evaluation before a conclusion can be reached that the Integrated Plan is consistent with the guidance in NEI 12-06 or an acceptable alternative has been proposed that would satisfy the requirements of Order EA-12-049. For the purpose of this evaluation, the following definitions are used for Confirmatory Item and Open Item.
For the purpose of this evaluation, the following definitions are used for Confirmatory Item and Open Item. Confirmatory Item -an item that is considered conceptually acceptable, but for which resolution may be incomplete.
Confirmatory Item - an item that is considered conceptually acceptable, but for which resolution may be incomplete. These items are expected to be acceptable, but are expected to require some minimal follow up review or audit prior to the licensee's compliance with Order EA-12-049.
These items are expected to be acceptable, but are expected to require some minimal follow up review or audit prior to the licensee's compliance with Order EA-12-049.
Open Item - an item for which the licensee has not presented a sufficient basis to determine that the issue is on a path to resolution. The intent behind designating an issue as an Open Item is to document items that need resolution during the review process, rather than being verified after the compliance date through the inspection process.
Open Item -an item for which the licensee has not presented a sufficient basis to determine that the issue is on a path to resolution.
Additionally, for the purpose of this evaluation and the NRC staff's interim staff evaluation (ISE),
The intent behind designating an issue as an Open Item is to document items that need resolution during the review process, rather than being verified after the compliance date through the inspection process.
licensee statements, commitments, and references to existing programs that are subject to routine NRC oversight (Updated Final Safety Analysis Report (UFSAR) program, procedure program, quality assurance program, modification configuration control program, etc.) will generally be accepted. For example, references to existing UFSAR information that supports the licensee's overall mitigating strategies plan, will be assumed to be correct, unless there is a specific reason to question its accuracy. Likewise, if a licensee states that they will generate a procedure to implement a specific mitigating strategy, assuming that the procedure would otherwise support the licensee's plan, this evaluation accepts that a proper procedure will be prepared. This philosophy for this evaluation and the ISE does not imply that there are any limits in this area to future NRC inspection activities.
Additionally, for the purpose of this evaluation and the NRC staff's interim staff evaluation (ISE), licensee statements, commitments, and references to existing programs that are subject to routine NRC oversight (Updated Final Safety Analysis Report (UFSAR) program, procedure  
 
: program, quality assurance  
==3.0       TECHNICAL EVALUATION==
: program, modification configuration control program, etc.) will generally be accepted.
 
For example, references to existing UFSAR information that supports the licensee's overall mitigating strategies plan, will be assumed to be correct, unless there is a specific reason to question its accuracy.  
By letter dated February 28, 2013, (ADAMS Accession No. ML13063A287), and as supplemented by the first six-month status report in a letter dated August 28, 2013 (ADAMS Accession No. ML13241A204), Entergy Nuclear Northeast, Entergy Nuclear Operations, Inc.
: Likewise, if a licensee states that they will generate a procedure to implement a specific mitigating  
(the licensee or Entergy) provided the James A. FitzPatrick Nuclear Power Plant (JAF)
: strategy, assuming that the procedure would otherwise support the licensee's plan, this evaluation accepts that a proper procedure will be prepared.
Integrated Plan for Compliance with Order EA-12-049. The Integrated Plan describes the strategies and guidance under development for implementation by the licensee for the maintenance or restoration of core cooling, containment, and SFP cooling capabilities following a BDBEE, including modifications necessary to support this implementation, pursuant to Order EA-12-049. By letter dated August 28, 2013 (ADAMS Accession No. ML13234A503), the NRC notified all licensees and construction permit holders that the staff is conducting audits of their responses to Order EA-12-049. That letter described the process used by the NRC staff in its review, leading to the issuance of an interim staff evaluation and audit report. The purpose of the staff's audit is to determine the extent to which the licensees are proceeding on a path Revision 1                                   Page 4 of 60                                 2014-02-15
This philosophy for this evaluation and the ISE does not imply that there are any limits in this area to future NRC inspection activities.
 
3.0 TECHNICAL EVALUATION By letter dated February 28, 2013, (ADAMS Accession No. ML 13063A287),
towards successful implementation of the actions needed to achieve full compliance with the Order.
and as supplemented by the first six-month status report in a letter dated August 28, 2013 (ADAMS Accession No. ML 13241A204),
3.1     EVALUATION OF EXTERNAL HAZARDS Sections 4 through 9 of NEI 12-06 provide the NRC-endorsed methodology for the determination of applicable extreme external hazards in order to identify potential complicating factors for the protection and deployment of equipment needed for mitigation of BDBEEs leading to an extended loss of all alternating current (ac) power (ELAP) and loss of normal access to the ultimate heat sink (UHS). These hazards are broadly grouped into the categories discussed below in Sections 3.1.1 through 3.1.5 of this evaluation. Characterization of the applicable hazards for a specific site includes the identification of realistic timelines for the hazard; characterization of the functional threats due to the hazard; development of a strategy for responding to events with warning; and development of a strategy for responding to events without warning.
Entergy Nuclear Northeast, Entergy Nuclear Operations, Inc. (the licensee or Entergy) provided the James A. FitzPatrick Nuclear Power Plant (JAF) Integrated Plan for Compliance with Order EA-12-049.
3.1.1   Seismic Events.
The Integrated Plan describes the strategies and guidance under development for implementation by the licensee for the maintenance or restoration of core cooling, containment, and SFP cooling capabilities following a BDBEE, including modifications necessary to support this implementation, pursuant to Order EA-12-049.
NEI 12-06, Section 5.2 states:
By letter dated August 28, 2013 (ADAMS Accession No. ML 13234A503),
All sites will address BOB [beyond-design-basis] seismic considerations in the implementation of FLEX strategies, as described below. The basis for this is that, while some sites are in areas with lower seismic activity, their design basis generally reflects that lower activity. There are large, and unavoidable, uncertainties in the seismic hazard for all U.S. plants. In order to provide an increased level of safety, the FLEX deployment strategy will address seismic hazards at all sites.
the NRC notified all licensees and construction permit holders that the staff is conducting audits of their responses to Order EA-12-049.
These considerations will be treated in four primary areas: protection of FLEX equipment, deployment of FLEX equipment, procedural interfaces, and considerations in utilizing off-site resources.
That letter described the process used by the NRC staff in its review, leading to the issuance of an interim staff evaluation and audit report. The purpose of the staff's audit is to determine the extent to which the licensees are proceeding on a path Revision 1 Page 4 of 60 2014-02-15 towards successful implementation of the actions needed to achieve full compliance with the Order. 3.1 EVALUATION OF EXTERNAL HAZARDS Sections 4 through 9 of NEI 12-06 provide the NRC-endorsed methodology for the determination of applicable extreme external hazards in order to identify potential complicating factors for the protection and deployment of equipment needed for mitigation of BDBEEs leading to an extended loss of all alternating current (ac) power (ELAP) and loss of normal access to the ultimate heat sink (UHS). These hazards are broadly grouped into the categories discussed below in Sections 3.1.1 through 3.1.5 of this evaluation.
On page 1 of the Integrated Plan, in the section regarding determination of applicable extreme external hazards, the licensee stated that the seismic design for Class I structures and equipment is based on dynamic analysis using acceleration response spectrum curves normalized to a ground motion of 0.08g for the Operating Basis Earthquake and 0.15g for the Design Basis Earthquake. The NRC also refers to the Design Basis Earthquake as the Safe Shutdown Earthquake (SSE). The basis for these criteria is presented in the JAF Final Safety Analysis Report [JAF Final Safety Analysis Report, updated 2011] Section 2.6.
Characterization of the applicable hazards for a specific site includes the identification of realistic timelines for the hazard; characterization of the functional threats due to the hazard; development of a strategy for responding to events with warning; and development of a strategy for responding to events without warning.
The licensee stated that in accordance with NEI 12-06, all sites will consider the seismic hazard and that the seismic hazard is applicable to JAF.
3.1.1 Seismic Events. NEI 12-06, Section 5.2 states: All sites will address BOB [beyond-design-basis]
The licensee also stated on page 3 that the seismic re-evaluations pursuant to the 10 CFR 50.54(f) letter of March 12, 2012 had not been completed and therefore were not assumed in their Integrated Plan. As the re-evaluations are completed, appropriate issues will be entered into the corrective action system and addressed.
seismic considerations in the implementation of FLEX strategies, as described below. The basis for this is that, while some sites are in areas with lower seismic activity, their design basis generally reflects that lower activity.
The licensee's approach described above, as currently understood, is consistent with the guidance found in NEI 12-06, as endorsed by JLD-ISG-2012-01, and provides reasonable assurance that the requirements of Order EA-12-049 will be met with respect to seismic Revision 1                                   Page 5 of 60                                 2014-02-15
There are large, and unavoidable, uncertainties in the seismic hazard for all U.S. plants. In order to provide an increased level of safety, the FLEX deployment strategy will address seismic hazards at all sites. These considerations will be treated in four primary areas: protection of FLEX equipment, deployment of FLEX equipment, procedural interfaces, and considerations in utilizing off-site resources.
 
On page 1 of the Integrated Plan, in the section regarding determination of applicable extreme external  
screening if these requirements are implemented as described.
: hazards, the licensee stated that the seismic design for Class I structures and equipment is based on dynamic analysis using acceleration response spectrum curves normalized to a ground motion of 0.08g for the Operating Basis Earthquake and 0.15g for the Design Basis Earthquake.
3.1.1.1 Protection of FLEX Equipment - Seismic Hazard NEI 12-06, Section 5.3.1 states:
The NRC also refers to the Design Basis Earthquake as the Safe Shutdown Earthquake (SSE). The basis for these criteria is presented in the JAF Final Safety Analysis Report [JAF Final Safety Analysis Report, updated 2011] Section 2.6. The licensee stated that in accordance with NEI 12-06, all sites will consider the seismic hazard and that the seismic hazard is applicable to JAF. The licensee also stated on page 3 that the seismic re-evaluations pursuant to the 10 CFR 50.54(f) letter of March 12, 2012 had not been completed and therefore were not assumed in their Integrated Plan. As the re-evaluations are completed, appropriate issues will be entered into the corrective action system and addressed.
: 1. FLEX equipment should be stored in one or more of following three configurations:
The licensee's approach described above, as currently understood, is consistent with the guidance found in NEI 12-06, as endorsed by JLD-ISG-2012-01, and provides reasonable assurance that the requirements of Order EA-12-049 will be met with respect to seismic Revision 1 Page 5 of 60 2014-02-15 screening if these requirements are implemented as described.
: a. In a structure that meets the plant's design basis for the Safe Shutdown Earthquake (SSE) (e.g., existing safety-related structure).
3.1.1.1 Protection of FLEX Equipment  
: b. In a structure designed to or evaluated equivalent to [American Society of Civil Engineers] ASCE 7-10, Minimum Design Loads for Buildings and Other Structures.
-Seismic Hazard NEI 12-06, Section 5.3.1 states: 1. FLEX equipment should be stored in one or more of following three configurations:  
: c. Outside a structure and evaluated for seismic interactions to ensure equipment is not damaged by non-seismically robust components or structures.
: a. In a structure that meets the plant's design basis for the Safe Shutdown Earthquake (SSE) (e.g., existing safety-related structure).  
: 2. Large portable FLEX equipment such as pumps and power supplies should be secured as appropriate to protect them during a seismic event (i.e., Safe Shutdown Earthquake (SSE) level).
: b. In a structure designed to or evaluated equivalent to [American Society of Civil Engineers]
: 3. Stored equipment and structures should be evaluated and protected from seismic interactions to ensure that unsecured and/or non-seismic components do not damage the equipment.
ASCE 7-10, Minimum Design Loads for Buildings and Other Structures.  
On pages 19, 26, 34, and 41 in the sections of the Integrated Plan regarding the strategies for maintaining core cooling, containment, spent fuel cooling and for safety systems support, respectively, the licensee stated that protection of associated portable equipment from seismic hazards will be provided by constructing structures that meet the guidelines of NEI 12-06 Section 11 which references Sections 5 through 9 for more detailed guidance for protection of FLEX equipment during specific external events. With respect to consideration (1), during the audit process, the licensee stated that two storage facilities are planned. The selected locations are in the northeast area of the protected area just east of the radwaste building and outside the protected area to the south and east of the protected area near the off-site wellness center. The storage buildings will be designed for seismic criteria equivalent to ASCE 7-10, and local building codes.
: c. Outside a structure and evaluated for seismic interactions to ensure equipment is not damaged by non-seismically robust components or structures.  
With respect to considerations 2 and 3, the licensee stated during the audit process that storage of large FLEX equipment will take into consideration protection of the equipment by location or securing the equipment to ensure that there are no seismic interactions between the FLEX equipment during a seismic event.
: 2. Large portable FLEX equipment such as pumps and power supplies should be secured as appropriate to protect them during a seismic event (i.e., Safe Shutdown Earthquake (SSE) level). 3. Stored equipment and structures should be evaluated and protected from seismic interactions to ensure that unsecured and/or non-seismic components do not damage the equipment.
The licensee's approach described above, as currently understood, is consistent with the guidance found in NEI 12-06, as endorsed by JLD-ISG-2012-01, and provides reasonable assurance that the requirements of Order EA-12-049 will be met with respect to protection of FLEX equipment considering the seismic hazard if these requirements are implemented as described.
On pages 19, 26, 34, and 41 in the sections of the Integrated Plan regarding the strategies for maintaining core cooling, containment, spent fuel cooling and for safety systems support, respectively, the licensee stated that protection of associated portable equipment from seismic hazards will be provided by constructing structures that meet the guidelines of NEI 12-06 Section 11 which references Sections 5 through 9 for more detailed guidance for protection of FLEX equipment during specific external events. With respect to consideration (1), during the audit process, the licensee stated that two storage facilities are planned.
Revision 1                                 Page 6 of 60                               2014-02-15
The selected locations are in the northeast area of the protected area just east of the radwaste building and outside the protected area to the south and east of the protected area near the off-site wellness center. The storage buildings will be designed for seismic criteria equivalent to ASCE 7-10, and local building codes. With respect to considerations 2 and 3, the licensee stated during the audit process that storage of large FLEX equipment will take into consideration protection of the equipment by location or securing the equipment to ensure that there are no seismic interactions between the FLEX equipment during a seismic event. The licensee's approach described above, as currently understood, is consistent with the guidance found in NEI 12-06, as endorsed by JLD-ISG-2012-01, and provides reasonable assurance that the requirements of Order EA-12-049 will be met with respect to protection of FLEX equipment considering the seismic hazard if these requirements are implemented as described.
 
Revision 1 Page 6 of 60 2014-02-15 3.1.1.2 Deployment of FLEX Equipment  
3.1.1.2 Deployment of FLEX Equipment - Seismic Hazard NEI 12-06, Section 5.3.2 states:
-Seismic Hazard NEI 12-06, Section 5.3.2 states: The baseline capability requirements already address loss of non-seismically robust equipment and tanks as well as loss of all AC. So, these seismic considerations are implicitly addressed.
The baseline capability requirements already address loss of non-seismically robust equipment and tanks as well as loss of all AC. So, these seismic considerations are implicitly addressed.
There are five considerations for the deployment of FLEX equipment following a seismic event: 1. If the equipment needs to be moved from a storage location to a different point for deployment, the route to be traveled should be reviewed for potential soil liquefaction that could impede movement following a severe seismic event. 2. At least one connection point for the FLEX equipment will only require access through seismically robust structures.
There are five considerations for the deployment of FLEX equipment following a seismic event:
This includes both the connection point and any areas that plant operators will have to access to deploy or control the capability.  
: 1. If the equipment needs to be moved from a storage location to a different point for deployment, the route to be traveled should be reviewed for potential soil liquefaction that could impede movement following a severe seismic event.
: 3. If the plant FLEX strategy relies on a water source that is not seismically robust, e.g., a downstream dam, the deployment of FLEX coping capabilities should address how water will be accessed.
: 2. At least one connection point for the FLEX equipment will only require access through seismically robust structures. This includes both the connection point and any areas that plant operators will have to access to deploy or control the capability.
Most sites with this configuration have an underwater berm that retains a needed volume of water. However, accessing this water may require new or different equipment.  
: 3. If the plant FLEX strategy relies on a water source that is not seismically robust, e.g., a downstream dam, the deployment of FLEX coping capabilities should address how water will be accessed. Most sites with this configuration have an underwater berm that retains a needed volume of water. However, accessing this water may require new or different equipment.
: 4. If power is required to move or deploy the equipment (e.g., to open the door from a storage location),
: 4. If power is required to move or deploy the equipment (e.g., to open the door from a storage location), then power supplies should be provided as part of the FLEX deployment.
then power supplies should be provided as part of the FLEX deployment.  
: 5. A means to move FLEX equipment should be provided that is also reasonably protected from the event.
: 5. A means to move FLEX equipment should be provided that is also reasonably protected from the event. Two locations for storage of the FLEX equipment have been selected and haul routes of the FLEX equipment to the staging areas have been identified as shown in Figure 3, page 55, in the Integrated Plan. During the audit process, the licensee stated that potential for soil liquefaction along the deployment routes has not yet been evaluated.
Two locations for storage of the FLEX equipment have been selected and haul routes of the FLEX equipment to the staging areas have been identified as shown in Figure 3, page 55, in the Integrated Plan. During the audit process, the licensee stated that potential for soil liquefaction along the deployment routes has not yet been evaluated. This is identified as Confirmatory Item 3.1.1.2.A in Section 4.2.
This is identified as Confirmatory Item 3.1.1.2.A in Section 4.2. On page 3, in the section of the Integrated Plan discussing key site assumptions to implement NEI 12-06 strategies, Entergy stated that the designed hardened connections are protected against external events or are established at multiple and diverse locations.
On page 3, in the section of the Integrated Plan discussing key site assumptions to implement NEI 12-06 strategies, Entergy stated that the designed hardened connections are protected against external events or are established at multiple and diverse locations. On pages 19, 22, 23, 33, and 40 in the Integrated Plan, Entergy provided details on the new connections required to support the FLEX strategies. Furthermore during the audit the licensee stated that FLEX equipment connection points will be located in seismically qualified or seismically robust structures. At least one connection point will only require access through seismic structures. If located outside a structure, connection points will be evaluated for seismic interactions, extreme cold, high wind and high temperature.
On pages 19, 22, 23, 33, and 40 in the Integrated Plan, Entergy provided details on the new connections required to support the FLEX strategies.
With regard to consideration 4 above, the Integrated Plan did not address whether power would Revision 1                                   Page 7 of 60                               2014-02-15
Furthermore during the audit the licensee stated that FLEX equipment connection points will be located in seismically qualified or seismically robust structures.
 
At least one connection point will only require access through seismic structures.
be required to move or deploy equipment. During the audit process, the licensee stated that design details of the structures have not been completed. This is identified as Confirmatory Item 3.1.1.2.B in Section 4.2.
If located outside a structure, connection points will be evaluated for seismic interactions, extreme cold, high wind and high temperature.
On page 45 of the Integrated Plan, the licensee identified four super duty pickup trucks and two flatbed trailers as portable FLEX equipment. However, it is not clear where this equipment is stored and how it is protected from the seismic event. This is identified as Confirmatory Item 3.1.1.2.C in Section 4.2.
With regard to consideration 4 above, the Integrated Plan did not address whether power would Revision 1 Page 7 of 60 2014-02-15 be required to move or deploy equipment.
The licensee's approach described above, as currently understood, is consistent with the guidance found in NEI 12-06, as endorsed by JLD-ISG-2012-01, and subject to the successful closure of issues related to the Confirmatory Items provides reasonable assurance that the requirements of Order EA-12-049 will be met with respect to deployment of FLEX equipment considering the seismic hazard if these requirements are implemented as described.
During the audit process, the licensee stated that design details of the structures have not been completed.
3.1.1.3 Procedural Interfaces- Seismic Hazard NEI 12-06, Section 5.3.3 states:
This is identified as Confirmatory Item 3.1.1.2.B in Section 4.2. On page 45 of the Integrated Plan, the licensee identified four super duty pickup trucks and two flatbed trailers as portable FLEX equipment.  
There are four procedural interface considerations that should be addressed.
: However, it is not clear where this equipment is stored and how it is protected from the seismic event. This is identified as Confirmatory Item 3.1.1.2.C in Section 4.2. The licensee's approach described above, as currently understood, is consistent with the guidance found in NEI 12-06, as endorsed by JLD-ISG-2012-01, and subject to the successful closure of issues related to the Confirmatory Items provides reasonable assurance that the requirements of Order EA-12-049 will be met with respect to deployment of FLEX equipment considering the seismic hazard if these requirements are implemented as described.
: 1. Seismic studies have shown that even seismically qualified electrical equipment can be affected by BOB seismic events. In order to address these considerations, each plant should compile a reference source for the plant operators that provides approaches to obtaining necessary instrument readings to support the implementation of the coping strategy (see Section 3.2.1.1 0). This reference source should include control room and non-control room readouts and should also provide guidance on how and where to measure key instrument readings at containment penetrations, where applicable, using a portable instrument (e.g., a Fluke meter). Such a resource could be provided as an attachment to the plant procedures/guidance. Guidance should include critical actions to perform until alternate indications can be connected and on how to control critical equipment without associated control power.
3.1.1.3 Procedural Interfaces-Seismic Hazard NEI 12-06, Section 5.3.3 states: There are four procedural interface considerations that should be addressed.  
: 2. Consideration should be given to the impacts from large internal flooding sources that are not seismically robust and do not require ac [alternating current] power (e.g., gravity drainage from lake or cooling basins for non-safety-related cooling water systems).
: 1. Seismic studies have shown that even seismically qualified electrical equipment can be affected by BOB seismic events. In order to address these considerations, each plant should compile a reference source for the plant operators that provides approaches to obtaining necessary instrument readings to support the implementation of the coping strategy (see Section 3.2.1.1 0). This reference source should include control room and non-control room readouts and should also provide guidance on how and where to measure key instrument readings at containment penetrations, where applicable, using a portable instrument (e.g., a Fluke meter). Such a resource could be provided as an attachment to the plant procedures/guidance.
: 3. For sites that use ac power to mitigate ground water in critical locations, a strategy to remove this water will be required.
Guidance should include critical actions to perform until alternate indications can be connected and on how to control critical equipment without associated control power. 2. Consideration should be given to the impacts from large internal flooding sources that are not seismically robust and do not require ac [alternating current]
: 4. Additional guidance may be required to address the deployment of FLEX for those plants that could be impacted by failure of a not seismically robust downstream dam.
power (e.g., gravity drainage from lake or cooling basins for safety-related cooling water systems).  
On pages 15, 16 and 25 of the Integrated Plan, the licensee listed the installed instrumentation credited for monitoring the effectiveness of the FLEX coping strategies. These instruments are discussed in more detail in Section 3.2.1.5. The licensee's Integrated Plan with regard to procedural interface (seismic) did not address 1) reference sources for the plant operators that Revision 1                                   Page 8 of 60                               2014-02-15
: 3. For sites that use ac power to mitigate ground water in critical locations, a strategy to remove this water will be required.  
 
: 4. Additional guidance may be required to address the deployment of FLEX for those plants that could be impacted by failure of a not seismically robust downstream dam. On pages 15, 16 and 25 of the Integrated Plan, the licensee listed the installed instrumentation credited for monitoring the effectiveness of the FLEX coping strategies.
provide approaches to obtaining necessary instrument readings using a portable instrument and
These instruments are discussed in more detail in Section 3.2.1.5.
: 2) guidance for critical actions to perform until alternate indications can be connected and on how to control critical equipment without associated control power. During the audit process, the licensee stated that the FLEX support guidelines (FSGs) and supporting procedures will be developed addressing the guidance in NEI 12-06 Section 5.3.3.
The licensee's Integrated Plan with regard to procedural interface (seismic) did not address 1) reference sources for the plant operators that Revision 1 Page 8 of 60 2014-02-15 provide approaches to obtaining necessary instrument readings using a portable instrument and 2) guidance for critical actions to perform until alternate indications can be connected and on how to control critical equipment without associated control power. During the audit process, the licensee stated that the FLEX support guidelines (FSGs) and supporting procedures will be developed addressing the guidance in NEI 12-06 Section 5.3.3. The licensee's Integrated Plan does not address large internal flooding sources.
The licensee's Integrated Plan does not address large internal flooding sources. During the audit process, the licensee addressed this consideration by stating that the evaluation has not yet been performed. This is identified as Open Item 3.1.1. 3.A in Section 4.1.
During the audit process, the licensee addressed this consideration by stating that the evaluation has not yet been performed.
The licensee's Integrated Plan does not address the use of alternating current (ac) power to mitigate ground water in critical locations. During the audit process, the licensee addressed this consideration by stating that the levels in the perimeter pits will be monitored and temporary power will be provided to the perimeter drain pumps as needed.
This is identified as Open Item 3.1.1. 3.A in Section 4.1. The licensee's Integrated Plan does not address the use of alternating current (ac) power to mitigate ground water in critical locations.
The licensee's approach described above, as currently understood, is consistent with the guidance found in NEI 12-06, as endorsed by JLD-ISG-2012-01, and subject to the successful closure of issues related to the Open Item, provides reasonable assurance that the requirements of Order EA-12-049 will be met with respect to procedural interfaces if these requirements are implemented as described.
During the audit process, the licensee addressed this consideration by stating that the levels in the perimeter pits will be monitored and temporary power will be provided to the perimeter drain pumps as needed. The licensee's approach described above, as currently understood, is consistent with the guidance found in NEI 12-06, as endorsed by JLD-ISG-2012-01, and subject to the successful closure of issues related to the Open Item, provides reasonable assurance that the requirements of Order EA-12-049 will be met with respect to procedural interfaces if these requirements are implemented as described.
3.1.1.4 Considerations in Using Offsite Resources - Seismic Hazard NEI 12-06, Section 5.3.4 states:
3.1.1.4 Considerations in Using Offsite Resources  
Severe seismic events can have far-reaching effects on the infrastructure in and around a plant. While nuclear power plants are designed for large seismic events, many parts of the Owner Controlled Area and surrounding infrastructure (e.g., roads, bridges, dams, etc.) may be designed to lesser standards.
-Seismic Hazard NEI 12-06, Section 5.3.4 states: Severe seismic events can have far-reaching effects on the infrastructure in and around a plant. While nuclear power plants are designed for large seismic events, many parts of the Owner Controlled Area and surrounding infrastructure (e.g., roads, bridges, dams, etc.) may be designed to lesser standards.
Obtaining off-site resources may require use of alternative transportation (such as air-lift capability) that can overcome or circumvent damage to the existing local infrastructure.
Obtaining off-site resources may require use of alternative transportation (such as air-lift capability) that can overcome or circumvent damage to the existing local infrastructure.  
: 1. The FLEX strategies will need to assess the best means to obtain resources from off-site following a seismic event.
: 1. The FLEX strategies will need to assess the best means to obtain resources from off-site following a seismic event. On page 10, in the section of the Integrated Plan discussing the Regional Response Center (RRC), Entergy stated that the industry has selected a vendor to manage two RRCs to provide large equipment in support of the response to BDBEEs. Each RRC will store and maintain five sets of equipment, four of which are expected to be fully deployable upon request.
On page 10, in the section of the Integrated Plan discussing the Regional Response Center (RRC), Entergy stated that the industry has selected a vendor to manage two RRCs to provide large equipment in support of the response to BDBEEs. Each RRC will store and maintain five sets of equipment, four of which are expected to be fully deployable upon request. The fifth set is provided to account for equipment that may be unavailable due to its maintenance and testing cycle.
The fifth set is provided to account for equipment that may be unavailable due to its maintenance and testing cycle. The licensee stated that JAF will utilize the industry RRCs for Phase 3 equipment.
The licensee stated that JAF will utilize the industry RRCs for Phase 3 equipment. In an ELAP event, communications would be established between JAF and the industry Strategic Alliance for FLEX Emergency Response (SAFER) team and required equipment mobilized as needed.
In an ELAP event, communications would be established between JAF and the industry Strategic Alliance for FLEX Emergency Response (SAFER) team and required equipment mobilized as needed. JAF will enter into a contractual agreement with the SAFER team. Equipment will initially be moved from an RRC to a local staging area, established by the SAFER team and JAF. The equipment will be prepared at the staging area prior to transport to the site. First arriving equipment, as established during development of the SAFER Response Plan (RRC playbook),
JAF will enter into a contractual agreement with the SAFER team. Equipment will initially be moved from an RRC to a local staging area, established by the SAFER team and JAF. The equipment will be prepared at the staging area prior to transport to the site. First arriving equipment, as established during development of the SAFER Response Plan (RRC playbook),
will be delivered to the site within 24 hours from the initial request.
will be delivered to the site within [[estimated NRC review hours::24 hours]] from the initial request.
Revision 1 Page 9 of 60 2014-02-15 On page 22, in the section of the Integrated Plan discussing coping strategies to maintain core cooling during Phase 3, Entergy stated that equipment transported to the site will be either immediately staged at the point of use or temporarily stored at the lay down area. The lay down area is located outside the protected area on the south side of the plant near the main entrance.
Revision 1                                     Page 9 of 60                             2014-02-15
Entergy has not yet identified the local offsite staging area(s) for the RRC FLEX equipment nor evaluated the methods for delivery of equipment from the offsite staging area to the site under various conditions such as seismic,  
 
: flooding, high winds, and snow, ice and extreme cold. The identification of local offsite staging areas and evaluation of delivery methods following a seismic event has been identified as Confirmatory Item 3.1.1.4.A in Section 4.2. The licensee's approach described above, as currently understood, is consistent with the guidance found in NEI 12-06, as endorsed by JLD-ISG-2012-01, and subject to the successful closure of issues related to the Confirmatory Item, provides reasonable assurance that the requirements of Order EA-12-049 will be met with respect to offsite resources if these requirements are implemented as described.
On page 22, in the section of the Integrated Plan discussing coping strategies to maintain core cooling during Phase 3, Entergy stated that equipment transported to the site will be either immediately staged at the point of use or temporarily stored at the lay down area. The lay down area is located outside the protected area on the south side of the plant near the main entrance.
3.1.2 Flooding NEI 12-06, Section 6.2 states: The evaluation of external flood-induced challenges has three parts. The first part is determining whether the site is susceptible to external flooding.
Entergy has not yet identified the local offsite staging area(s) for the RRC FLEX equipment nor evaluated the methods for delivery of equipment from the offsite staging area to the site under various conditions such as seismic, flooding, high winds, and snow, ice and extreme cold. The identification of local offsite staging areas and evaluation of delivery methods following a seismic event has been identified as Confirmatory Item 3.1.1.4.A in Section 4.2.
The second part is the characterization of the applicable external flooding threat. The third part is the application of the flooding characterization to the protection and deployment of FLEX strategies.
The licensee's approach described above, as currently understood, is consistent with the guidance found in NEI 12-06, as endorsed by JLD-ISG-2012-01, and subject to the successful closure of issues related to the Confirmatory Item, provides reasonable assurance that the requirements of Order EA-12-049 will be met with respect to offsite resources if these requirements are implemented as described.
NEI 12-06, Section 6.2.1 states in part: Susceptibility to external flooding is based on whether the site is a "dry" site, i.e., the plant is built above the design basis flood level (DBFL). For sites that are not "dry", water intrusion is prevented by barriers and there could be a potential for those barriers to be exceeded or compromised.
3.1.2 Flooding NEI 12-06, Section 6.2 states:
Such sites would include those that are kept "dry" by permanently installed  
The evaluation of external flood-induced challenges has three parts. The first part is determining whether the site is susceptible to external flooding. The second part is the characterization of the applicable external flooding threat. The third part is the application of the flooding characterization to the protection and deployment of FLEX strategies.
: barriers, e.g., seawall, levees, etc., and those that install temporary barriers or rely on watertight doors to keep the design basis flood from impacting safe shutdown equipment.
NEI 12-06, Section 6.2.1 states in part:
On page 1, in the section of the Integrated Plan discussing the external flood hazard assessment, Entergy stated that JAF is built above the design basis flood level. Per JAF FSAR (JAF Final Safety Analysis Report, updated 2011, Sections 2.4.3.2 and 2.4.3.7),
Susceptibility to external flooding is based on whether the site is a "dry" site, i.e.,
the Probable Maximum Flood (PMF) elevation at the screenwell is 255 ft. This is based on a maximum lake level of Elevation 250 feet, and considers the setup (4.1 feet) and maximum precipitation (0.35 feet). In this section of the Integrated Plan, the licensee stated that the maximum probable flood lake level is determined considering the maximum lake level, a maximum wind setup of 4.1 feet, the maximum rainfall of 0.35 feet and a maximum wave run-up height of 7.5 feet; this results in a maximum probable flood lake level of just under 262'. The grade elevation at JAF is 272ft (JAF FSAR 2011, Section 2.4.3.7).
the plant is built above the design basis flood level (DBFL). For sites that are not "dry", water intrusion is prevented by barriers and there could be a potential for those barriers to be exceeded or compromised. Such sites would include those that are kept "dry" by permanently installed barriers, e.g., seawall, levees, etc.,
Therefore, JAF is built above the design basis flood level and is considered a "dry" site by the NEI guidance (NEI 12-06, Section 6.2.1) and "dry" sites are not Revision 1 Page 10 of 60 2014-02-15 required to evaluate flood-induced challenges.
and those that install temporary barriers or rely on watertight doors to keep the design basis flood from impacting safe shutdown equipment.
The licensee stated that the external flood hazard screens out as not applicable to JAF. On page 3, in the section of the Integrated Plan discussing key assumptions to implement NEI 12-06 strategies, the licensee stated that the flooding re-evaluations pursuant to the 10 CFR 50.54(f) letter of March 12, 2012 had not been completed and therefore were not assumed in the Integrated Plan. As the re-evaluations are completed, appropriate issues will be entered into the corrective action system and addressed.
On page 1, in the section of the Integrated Plan discussing the external flood hazard assessment, Entergy stated that JAF is built above the design basis flood level. Per JAF FSAR (JAF Final Safety Analysis Report, updated 2011, Sections 2.4.3.2 and 2.4.3.7), the Probable Maximum Flood (PMF) elevation at the screenwell is 255 ft. This is based on a maximum lake level of Elevation 250 feet, and considers the setup (4.1 feet) and maximum precipitation (0.35 feet).
In this section of the Integrated Plan, the licensee stated that the maximum probable flood lake level is determined considering the maximum lake level, a maximum wind setup of 4.1 feet, the maximum rainfall of 0.35 feet and a maximum wave run-up height of 7.5 feet; this results in a maximum probable flood lake level of just under 262'. The grade elevation at JAF is 272ft (JAF FSAR 2011, Section 2.4.3.7). Therefore, JAF is built above the design basis flood level and is considered a "dry" site by the NEI guidance (NEI 12-06, Section 6.2.1) and "dry" sites are not Revision 1                                     Page 10 of 60                                 2014-02-15
 
required to evaluate flood-induced challenges.
The licensee stated that the external flood hazard screens out as not applicable to JAF.
On page 3, in the section of the Integrated Plan discussing key assumptions to implement NEI 12-06 strategies, the licensee stated that the flooding re-evaluations pursuant to the 10 CFR 50.54(f) letter of March 12, 2012 had not been completed and therefore were not assumed in the Integrated Plan. As the re-evaluations are completed, appropriate issues will be entered into the corrective action system and addressed.
The licensee's approach described above, as currently understood, is consistent with the guidance found in NEI 12-06, as endorsed by JLD-ISG-2012-01, and provides reasonable assurance that the requirements of Order EA-12-049 will be met with respect to screening and characterization of the flooding hazard if these requirements are implemented as described.
The licensee's approach described above, as currently understood, is consistent with the guidance found in NEI 12-06, as endorsed by JLD-ISG-2012-01, and provides reasonable assurance that the requirements of Order EA-12-049 will be met with respect to screening and characterization of the flooding hazard if these requirements are implemented as described.
3.1.2.1 Protection of FLEX Equipment  
3.1.2.1 Protection of FLEX Equipment - Flooding Hazard NEI 12-06, Section 6.2.3.1 states:
-Flooding Hazard NEI 12-06, Section 6.2.3.1 states: These considerations apply to the protection of FLEX equipment from external flood hazards:  
These considerations apply to the protection of FLEX equipment from external flood hazards:
: 1. The equipment should be stored in one or more of the following configurations:  
: 1. The equipment should be stored in one or more of the following configurations:
: a. Stored above the flood elevation from the most recent site flood analysis.
: a. Stored above the flood elevation from the most recent site flood analysis.
The evaluation to determine the elevation for storage should be informed by flood analysis applicable to the site from early site permits, combined license applications, and/or contiguous licensed sites. b. Stored in a structure designed to protect the equipment from the flood. c. FLEX equipment can be stored below flood level if time is available and plant procedures/guidance address the needed actions to relocate the equipment.
The evaluation to determine the elevation for storage should be informed by flood analysis applicable to the site from early site permits, combined license applications, and/or contiguous licensed sites.
Based on the timing of the limiting flood scenario(s),
: b. Stored in a structure designed to protect the equipment from the flood.
the FLEX equipment can be relocated  
: c. FLEX equipment can be stored below flood level if time is available and plant procedures/guidance address the needed actions to relocate the equipment. Based on the timing of the limiting flood scenario(s), the FLEX equipment can be relocated [footnote 2 omitted] to a position that is protected from the flood, either by barriers or by elevation, prior to the arrival of the potentially damaging flood levels. This should also consider the conditions on-site during the increasing flood levels and whether movement of the FLEX equipment will be possible before potential inundation occurs, not just the ultimate flood height.
[footnote 2 omitted]
: 2. Storage areas that are potentially impacted by a rapid rise of water should be avoided.
to a position that is protected from the flood, either by barriers or by elevation, prior to the arrival of the potentially damaging flood levels. This should also consider the conditions on-site during the increasing flood levels and whether movement of the FLEX equipment will be possible before potential inundation occurs, not just the ultimate flood height. 2. Storage areas that are potentially impacted by a rapid rise of water should be avoided.
On pages 19, 26, 34, and 41 in the sections of the Integrated Plan regarding the strategies for maintaining core cooling, containment, spent fuel cooling and for safety systems support, respectively, the licensee stated that protection of associated portable equipment from flooding hazards is not applicable since the flooding hazard has been screened out as discussed in Section 3.1.2.1 above. During the audit process, the licensee restated that because JAF is a "dry" site per NEI guidance, no further evaluation of the flood hazard is required.
On pages 19, 26, 34, and 41 in the sections of the Integrated Plan regarding the strategies for maintaining core cooling, containment, spent fuel cooling and for safety systems  
Revision 1                                   Page 11 of 60                                 2014-02-15
: support, respectively, the licensee stated that protection of associated portable equipment from flooding hazards is not applicable since the flooding hazard has been screened out as discussed in Section 3.1.2.1 above. During the audit process, the licensee restated that because JAF is a "dry" site per NEI guidance, no further evaluation of the flood hazard is required.
 
Revision 1 Page 11 of 60 2014-02-15 The licensee's approach described above, as currently understood, is consistent with the guidance found in NEI 12-06, as endorsed by JLD-ISG-2012-01, and provides reasonable assurance that the requirements of Order EA-12-049 will be met with respect to protection of FLEX equipment considering the flooding hazard if these requirements are implemented as described.
The licensee's approach described above, as currently understood, is consistent with the guidance found in NEI 12-06, as endorsed by JLD-ISG-2012-01, and provides reasonable assurance that the requirements of Order EA-12-049 will be met with respect to protection of FLEX equipment considering the flooding hazard if these requirements are implemented as described.
3.1.2.2 Deployment of FLEX Equipment-Flooding Hazard NEI 12-06, Section 6.2.3.2 states: There are a number of considerations which apply to the deployment of FLEX equipment for external flood hazards:  
3.1.2.2 Deployment of FLEX Equipment- Flooding Hazard NEI 12-06, Section 6.2.3.2 states:
: 1. For external floods with warning time, the plant may not be at power. In fact, the plant may have been shut down for a considerable time and the plant configuration could be established to optimize FLEX deployment.
There are a number of considerations which apply to the deployment of FLEX equipment for external flood hazards:
For example, the portable pump could be connected, tested, and readied for use prior to the arrival of the critical flood level. Further, protective actions can be taken to reduce the potential for flooding  
: 1. For external floods with warning time, the plant may not be at power. In fact, the plant may have been shut down for a considerable time and the plant configuration could be established to optimize FLEX deployment. For example, the portable pump could be connected, tested, and readied for use prior to the arrival of the critical flood level. Further, protective actions can be taken to reduce the potential for flooding impacts, including cooldown, berating the RCS [reactor coolant system], isolating accumulators, isolating RCP [reactor coolant pump] seal leak off, obtaining dewatering pumps, creating temporary flood barriers, etc. These factors can be credited in considering how the baseline capability is deployed.
: impacts, including  
: 2. The ability to move equipment and restock supplies may be hampered during a flood, especially a flood with long persistence. Accommodations along these lines may be necessary to support successful long-term FLEX deployment.
: cooldown, berating the RCS [reactor coolant system],
: 3. Depending on plant layout, the ultimate heat sink may be one of the first functions affected by a flooding condition. Consequently, the deployment of the FLEX equipment should address the effects of LUHS [loss of ultimate heat sink], as well as ELAP.
isolating accumulators, isolating RCP [reactor coolant pump] seal leak off, obtaining dewatering pumps, creating temporary flood barriers, etc. These factors can be credited in considering how the baseline capability is deployed.  
: 4. Portable pumps and power supplies will require fuel that would normally be obtained from fuel oil storage tanks that could be inundated by the flood or above ground tanks that could be damaged by the flood. Steps should be considered to protect or provide alternate sources of fuel oil for flood conditions. Potential flooding impacts on access and egress should also be considered.
: 2. The ability to move equipment and restock supplies may be hampered during a flood, especially a flood with long persistence.
: 5. Connection points for portable equipment should be reviewed to ensure that they remain viable for the flooded condition.
Accommodations along these lines may be necessary to support successful long-term FLEX deployment.  
: 6. For plants that are limited by storm-driven flooding, such as Probable Maximum Surge or Probable Maximum Hurricane (PMH), expected storm conditions should be considered in evaluating the adequacy of the baseline deployment strategies.
: 3. Depending on plant layout, the ultimate heat sink may be one of the first functions affected by a flooding condition.
Revision 1                                   Page 12 of 60                                 2014-02-15
Consequently, the deployment of the FLEX equipment should address the effects of LUHS [loss of ultimate heat sink], as well as ELAP. 4. Portable pumps and power supplies will require fuel that would normally be obtained from fuel oil storage tanks that could be inundated by the flood or above ground tanks that could be damaged by the flood. Steps should be considered to protect or provide alternate sources of fuel oil for flood conditions.
: 7. Since installed sump pumps will not be available for dewatering due to the ELAP, plants should consider the need to provide water extraction pumps capable of operating in an ELAP and hoses for rejecting accumulated water for structures required for deployment of FLEX strategies.
Potential flooding impacts on access and egress should also be considered.  
: 8. Plants relying on temporary flood barriers should assure that the storage location for barriers and related material provides reasonable assurance that the barriers could be deployed to provide the required protection.
: 5. Connection points for portable equipment should be reviewed to ensure that they remain viable for the flooded condition.  
: 9. A means to move FLEX equipment should be provided that is also reasonably protected from the event.
: 6. For plants that are limited by storm-driven  
As discussed in Section 3.1.2.1, the JAF site is designated a "dry site." During the audit process, the licensee restated that because JAF is a "dry" site per NEI guidance, no further evaluation of the flood hazard is required. Therefore, considerations 1 through 9 related to deployment during a flood are not applicable to JAF.
: flooding, such as Probable Maximum Surge or Probable Maximum Hurricane (PMH), expected storm conditions should be considered in evaluating the adequacy of the baseline deployment strategies.
The licensee's approach described above, as currently understood, is consistent with the guidance found in NEI 12-06, as endorsed by JLD-ISG-2012-01, provides reasonable assurance that the requirements of Order EA-12-049 will be met with respect to deployment of FLEX equipment considering the flooding hazard if these requirements are implemented as described.
Revision 1 Page 12 of 60 2014-02-15
3.1.2.3 Procedural Interfaces -Flooding Hazard NEI 12-06, Section 6.2.3.3 states:
: 7. Since installed sump pumps will not be available for dewatering due to the ELAP, plants should consider the need to provide water extraction pumps capable of operating in an ELAP and hoses for rejecting accumulated water for structures required for deployment of FLEX strategies.  
The following procedural interface considerations should be addressed.
: 8. Plants relying on temporary flood barriers should assure that the storage location for barriers and related material provides reasonable assurance that the barriers could be deployed to provide the required protection.  
: 1. Many sites have external flooding procedures. The actions necessary to support the deployment considerations identified above should be incorporated into those procedures.
: 9. A means to move FLEX equipment should be provided that is also reasonably protected from the event. As discussed in Section 3.1.2.1, the JAF site is designated a "dry site." During the audit process, the licensee restated that because JAF is a "dry" site per NEI guidance, no further evaluation of the flood hazard is required.
: 2. Additional guidance may be required to address the deployment of FLEX for flooded conditions (i.e., connection points may be different for flooded vs.
Therefore, considerations 1 through 9 related to deployment during a flood are not applicable to JAF. The licensee's approach described above, as currently understood, is consistent with the guidance found in NEI 12-06, as endorsed by JLD-ISG-2012-01, provides reasonable assurance that the requirements of Order EA-12-049 will be met with respect to deployment of FLEX equipment considering the flooding hazard if these requirements are implemented as described.
non-flooded conditions).
3.1.2.3 Procedural Interfaces  
-Flooding Hazard NEI 12-06, Section 6.2.3.3 states: The following procedural interface considerations should be addressed.  
: 1. Many sites have external flooding procedures.
The actions necessary to support the deployment considerations identified above should be incorporated into those procedures.  
: 2. Additional guidance may be required to address the deployment of FLEX for flooded conditions (i.e., connection points may be different for flooded vs. non-flooded conditions).  
: 3. FLEX guidance should describe the deployment of temporary flood barriers and extraction pumps necessary to support FLEX deployment.
: 3. FLEX guidance should describe the deployment of temporary flood barriers and extraction pumps necessary to support FLEX deployment.
As discussed in section 3.1.2.1 above, the licensee screens as a dry site and as such, no evaluation of the above considerations is required.
As discussed in section 3.1.2.1 above, the licensee screens as a dry site and as such, no evaluation of the above considerations is required.
The licensee's approach described above, as currently understood, is consistent with the guidance found in NEI 12-06, as endorsed by JLD-ISG-2012-01, and provides reasonable assurance that the requirements of Order EA-12-049 will be met with respect to procedural interfaces considering the flood hazard if these requirements are implemented as described.
The licensee's approach described above, as currently understood, is consistent with the guidance found in NEI 12-06, as endorsed by JLD-ISG-2012-01, and provides reasonable assurance that the requirements of Order EA-12-049 will be met with respect to procedural interfaces considering the flood hazard if these requirements are implemented as described.
3.1.2.4 Considerations in Using Offsite Resources  
3.1.2.4 Considerations in Using Offsite Resources - Flooding Hazard NEI 12-06, Section 6.2.3.4 states:
-Flooding Hazard NEI 12-06, Section 6.2.3.4 states: Revision 1 Page 13 of 60 2014-02-15 Extreme external floods can have regional impacts that could have a significant impact on the transportation of off-site resources.  
Revision 1                                   Page 13 of 60                               2014-02-15
: 1. Sites should review site access routes to determine the best means to obtain resources from off-site following a flood. 2. Sites impacted by persistent floods should consider where equipment delivered from off-site could be staged for use on-site.
 
On page 10, in the section of the Integrated Plan discussing the RRCs, Entergy stated that the industry has selected a vendor to manage two RRCs to provide large equipment in support of the response to BDBEEs. Each RRC will store and maintain five sets of equipment, four of which are expected to be fully deployable upon request.
Extreme external floods can have regional impacts that could have a significant impact on the transportation of off-site resources.
The fifth set is provided to account for equipment that may be unavailable due to its maintenance and testing cycle. JAF will utilize the industry RRCs for Phase 3 equipment.
: 1. Sites should review site access routes to determine the best means to obtain resources from off-site following a flood.
In an ELAP event, communications would be established between JAF and the SAFER team and required equipment mobilized as needed. JAF will enter into a contractual agreement with the SAFER team. Equipment will initially be moved from an RRC to a local staging area, established by the SAFER team and JAF. The equipment will be prepared at the staging area prior to transport to the site. First arriving equipment, as established during development of the RRC playbook, will be delivered to the site within 24 hours from the initial request.
: 2. Sites impacted by persistent floods should consider where equipment delivered from off-site could be staged for use on-site.
On page 10, in the section of the Integrated Plan discussing the RRCs, Entergy stated that the industry has selected a vendor to manage two RRCs to provide large equipment in support of the response to BDBEEs. Each RRC will store and maintain five sets of equipment, four of which are expected to be fully deployable upon request. The fifth set is provided to account for equipment that may be unavailable due to its maintenance and testing cycle.
JAF will utilize the industry RRCs for Phase 3 equipment. In an ELAP event, communications would be established between JAF and the SAFER team and required equipment mobilized as needed. JAF will enter into a contractual agreement with the SAFER team. Equipment will initially be moved from an RRC to a local staging area, established by the SAFER team and JAF. The equipment will be prepared at the staging area prior to transport to the site. First arriving equipment, as established during development of the RRC playbook, will be delivered to the site within [[estimated NRC review hours::24 hours]] from the initial request.
On page 22, in the section of the Integrated Plan discussing coping strategies to maintain core cooling during Phase 3, the licensee stated that equipment transported to the site will be either immediately staged at the point of use or temporarily stored at the lay down area. The lay down area is located outside the protected area on the south side of the plant near the main entrance.
On page 22, in the section of the Integrated Plan discussing coping strategies to maintain core cooling during Phase 3, the licensee stated that equipment transported to the site will be either immediately staged at the point of use or temporarily stored at the lay down area. The lay down area is located outside the protected area on the south side of the plant near the main entrance.
Entergy has not yet identified the local offsite staging area(s) for the RRC FLEX equipment nor evaluated the methods for delivery of equipment from the offsite staging area to the site under various conditions such as seismic,  
Entergy has not yet identified the local offsite staging area(s) for the RRC FLEX equipment nor evaluated the methods for delivery of equipment from the offsite staging area to the site under various conditions such as seismic, flooding, high winds, and snow, ice and extreme cold. The identification of local offsite staging areas and evaluation of delivery methods during a flooding event has been combined with Confirmatory Item 3.1.1.4.A in Section 4.2.
: flooding, high winds, and snow, ice and extreme cold. The identification of local offsite staging areas and evaluation of delivery methods during a flooding event has been combined with Confirmatory Item 3.1.1.4.A in Section 4.2. The licensee's approach described above, as currently understood, is consistent with the guidance found in NEI 12-06, as endorsed by JLD-ISG-2012-01, and subject to the successful closure of issues related to the Confirmatory Item, provides reasonable assurance that the requirements of Order EA-12-049 will be met with respect to offsite resources if these requirements are implemented as described.
The licensee's approach described above, as currently understood, is consistent with the guidance found in NEI 12-06, as endorsed by JLD-ISG-2012-01, and subject to the successful closure of issues related to the Confirmatory Item, provides reasonable assurance that the requirements of Order EA-12-049 will be met with respect to offsite resources if these requirements are implemented as described.
3.1.3 High Winds NEI 12-06, Section 7, provides the NRC-endorsed screening process for evaluation of high wind hazards.
3.1.3 High Winds NEI 12-06, Section 7, provides the NRC-endorsed screening process for evaluation of high wind hazards. This screening process considers the hazard due to hurricanes and tornadoes. The first part of the evaluation of high wind challenges is determining whether the site is potentially susceptible to different high wind conditions to allow characterization of the applicable high wind hazard.
This screening process considers the hazard due to hurricanes and tornadoes.
The screening for high wind hazards associated with hurricanes should be accomplished by comparing the site location to NEI 12-06, Figure 7-1 (Figure 3-1 of U.S. NRC, "Technical Basis Revision 1                                   Page 14 of 60                             2014-02-15
The first part of the evaluation of high wind challenges is determining whether the site is potentially susceptible to different high wind conditions to allow characterization of the applicable high wind hazard. The screening for high wind hazards associated with hurricanes should be accomplished by comparing the site location to NEI 12-06, Figure 7-1 (Figure 3-1 of U.S. NRC, "Technical Basis Revision 1 Page 14 of 60 2014-02-15 for Regulatory Guidance on Design Basis Hurricane Wind Speeds for Nuclear Power Plants,"
 
NUREG/CR-7005,  
for Regulatory Guidance on Design Basis Hurricane Wind Speeds for Nuclear Power Plants,"
: December, 2009); if the resulting frequency of recurrence of hurricanes with wind speeds in excess of 130 mph exceeds 1 o-6 per year, the site should address hazards due to extreme high winds associated with hurricanes.
NUREG/CR-7005, December, 2009); if the resulting frequency of recurrence of hurricanes with wind speeds in excess of 130 mph exceeds 1o-6 per year, the site should address hazards due to extreme high winds associated with hurricanes.
The screening for high wind hazard associated with tornadoes should be accomplished by comparing the site location to NEI 12-06, Figure 7-2, from U.S. NRC, "Tornado Climatology of the Contiguous United States,"
The screening for high wind hazard associated with tornadoes should be accomplished by comparing the site location to NEI 12-06, Figure 7-2, from U.S. NRC, "Tornado Climatology of the Contiguous United States," NUREG/CR-4461, Rev. 2, February 2007; if the recommended o-tornado design wind speed for a 1 6 /year probability exceeds 130 mph, the site should address hazards due to extreme high winds associated with tornadoes.
NUREG/CR-4461, Rev. 2, February 2007; if the recommended tornado design wind speed for a 1 o-6/year probability exceeds 130 mph, the site should address hazards due to extreme high winds associated with tornadoes.
On page 2, in the section of the Integrated Plan discussing severe storms with high wind assessment, the licensee stated that as indicated in NEI 12-06 Figure 7-1, hurricane winds in excess of 130 mph are not expected to occur at JAF. However, per the NEI 12-06 Figure 7-2, a recommended design tornado wind speed of 169 mph is identified. The licensee stated that the high wind hazard (169 mph tornado winds) is applicable to JAF.
On page 2, in the section of the Integrated Plan discussing severe storms with high wind assessment, the licensee stated that as indicated in NEI 12-06 Figure 7-1, hurricane winds in excess of 130 mph are not expected to occur at JAF. However, per the NEI 12-06 Figure 7-2, a recommended design tornado wind speed of 169 mph is identified.
The licensee's approach described above, as currently understood, is consistent with the guidance found in NEI 12-06, as endorsed by JLD-ISG-2012-01, and provides reasonable assurance that the requirements of Order EA-12-049 will be met with respect to high wind screening if these requirements are implemented as described.
The licensee stated that the high wind hazard (169 mph tornado winds) is applicable to JAF. The licensee's approach described above, as currently understood, is consistent with the guidance found in NEI 12-06, as endorsed by JLD-ISG-2012-01, and provides reasonable assurance that the requirements of Order EA-12-049 will be met with respect to high wind screening if these requirements are implemented as described.
3.1.3.1   Protection of FLEX Equipment- High Winds Hazard NEI 12-06, Section 7.3.1 states:
3.1.3.1 Protection of FLEX Equipment-High Winds Hazard NEI 12-06, Section 7.3.1 states: These considerations apply to the protection of FLEX equipment from high wind hazards:  
These considerations apply to the protection of FLEX equipment from high wind hazards:
: 1. For plants exposed to high wind hazards, FLEX equipment should be stored in one of the following configurations:
: 1. For plants exposed to high wind hazards, FLEX equipment should be stored in one of the following configurations:
Revision 1 a. In a structure that meets the plant's design basis for high wind hazards (e.g., existing safety-related structure).  
: a. In a structure that meets the plant's design basis for high wind hazards (e.g., existing safety-related structure).
: b. In storage locations designed to or evaluated equivalent to ASCE 7-1 0, Minimum Design Loads for Buildings and Other Structures given the limiting tornado wind speeds from Regulatory Guide 1. 76 or design basis hurricane wind speeds for the site.
: b. In storage locations designed to or evaluated equivalent to ASCE 7-1 0, Minimum Design Loads for Buildings and Other Structures given the limiting tornado wind speeds from Regulatory Guide 1. 76 or design basis hurricane wind speeds for the site.
* Given the FLEX basis limiting tornado or hurricane wind speeds, building loads would be computed in accordance with requirements of ASCE 7-10. Acceptance criteria would be based on building serviceability requirements not strict compliance with stress or capacity limits. This would allow for some minor plastic deformation, yet assure that the building would remain functional.
* Given the FLEX basis limiting tornado or hurricane wind speeds, building loads would be computed in accordance with requirements of ASCE 7-10. Acceptance criteria would be based on building serviceability requirements not strict compliance with stress or capacity limits. This would allow for some minor plastic deformation, yet assure that the building would remain functional.
* Tornado missiles and hurricane missiles will be accounted for in that the FLEX equipment will be stored in diverse locations to provide reasonable assurance that N sets of FLEX equipment will remain deployable following the high wind event. This will Page 15 of 60 2014-02-15 consider locations adjacent to existing robust structures or in lower sections of buildings that minimizes the probability that missiles will damage all mitigation equipment required from a single event by protection from adjacent buildings and limiting pathways for missiles to damage equipment.
* Tornado missiles and hurricane missiles will be accounted for in that the FLEX equipment will be stored in diverse locations to provide reasonable assurance that N sets of FLEX equipment will remain deployable following the high wind event. This will Revision 1                                    Page 15 of 60                               2014-02-15
* The axis of separation should consider the predominant path of tornados in the geographical location.
 
In general, tornadoes travel from the West or West Southwesterly direction, diverse locations should be aligned in the North-South arrangement, where possible.
consider locations adjacent to existing robust structures or in lower sections of buildings that minimizes the probability that missiles will damage all mitigation equipment required from a single event by protection from adjacent buildings and limiting pathways for missiles to damage equipment.
Additionally, in selecting diverse FLEX storage locations, consideration should be given to the location of the diesel generators and switchyard such that the path of a single tornado would not impact all locations.
* The axis of separation should consider the predominant path of tornados in the geographical location. In general, tornadoes travel from the West or West Southwesterly direction, diverse locations should be aligned in the North-South arrangement, where possible. Additionally, in selecting diverse FLEX storage locations, consideration should be given to the location of the diesel generators and switchyard such that the path of a single tornado would not impact all locations.
* Stored mitigation equipment exposed to the wind should be adequately tied down. Loose equipment should be in protective boxes that are adequately tied down to foundations or slabs to prevent protected equipment from being damaged or becoming airborne.  
* Stored mitigation equipment exposed to the wind should be adequately tied down. Loose equipment should be in protective boxes that are adequately tied down to foundations or slabs to prevent protected equipment from being damaged or becoming airborne. (During a tornado, high winds may blow away metal siding and metal deck roof, subjecting the equipment to high wind forces.)
(During a tornado, high winds may blow away metal siding and metal deck roof, subjecting the equipment to high wind forces.)  
: c. In evaluated storage locations separated by a sufficient distance that minimizes the probability that a single event would damage all FLEX mitigation equipment such that at least N sets of FLEX equipment would remain deployable following the high wind event. (This option is not applicable for hurricane conditions).
: c. In evaluated storage locations separated by a sufficient distance that minimizes the probability that a single event would damage all FLEX mitigation equipment such that at least N sets of FLEX equipment would remain deployable following the high wind event. (This option is not applicable for hurricane conditions).
* Consistent with configuration b., the axis of separation should consider the predominant path of tornados in the geographical location.
* Consistent with configuration b., the axis of separation should consider the predominant path of tornados in the geographical location.
* Consistent with configuration b., stored mitigation equipment should be adequately tied down. On pages 20, 27, 34, and 41 in the sections of the Integrated Plan regarding the strategies for maintaining core cooling, containment, spent fuel cooling and for safety systems support, respectively, the licensee stated that protection of associated portable equipment from the high wind hazards would be provided by constructing structures that meet the guidelines of NEI 12-06, Section 11, which references Sections 5 through 9 for more detailed guidance for protection of FLEX equipment during specific external events. During the audit process, the licensee stated that the two storage facilities in geographically separate locations with the selected locations in the northeast area of the protected area just east of the radwaste building and outside the protected area to the south and east of the protected area near the off-site well ness center. However, the licensee did not provide the separation distance of the storage buildings or the relation of the axis of separation to the predominant path of tornados in the geographic area to demonstrate that at least N sets of FLEX equipment would remain deployable following the high wind event. This is identified as Open Item 3.1.3.1.A in Section 4.1. The licensee's approach described above, as currently understood, has raised concerns which must be addressed before confirmation can be provided that the approach is consistent with the Revision 1 Page 16 of 60 2014-02-15 guidance found in NEI 12-06, as endorsed by JLD-ISG-2012-01, such that there would be reasonable assurance that the requirements of Order EA-12-049 will be met with respect to protection of FLEX equipment considering the high wind hazard. This concern is identified as Open Item 3.1.3.1.A above and in Section 4.1. 3.1.3.2 Deployment of FLEX Equipment-High Wind Hazard NEI 12-06, Section 7.3.2 states: There are a number of considerations which apply to the deployment of FLEX equipment for high wind hazards:  
* Consistent with configuration b., stored mitigation equipment should be adequately tied down.
: 1. For hurricane plants, the plant may not be at power prior to the simultaneous ELAP and LUHS condition.
On pages 20, 27, 34, and 41 in the sections of the Integrated Plan regarding the strategies for maintaining core cooling, containment, spent fuel cooling and for safety systems support, respectively, the licensee stated that protection of associated portable equipment from the high wind hazards would be provided by constructing structures that meet the guidelines of NEI 12-06, Section 11, which references Sections 5 through 9 for more detailed guidance for protection of FLEX equipment during specific external events. During the audit process, the licensee stated that the two storage facilities in geographically separate locations with the selected locations in the northeast area of the protected area just east of the radwaste building and outside the protected area to the south and east of the protected area near the off-site well ness center. However, the licensee did not provide the separation distance of the storage buildings or the relation of the axis of separation to the predominant path of tornados in the geographic area to demonstrate that at least N sets of FLEX equipment would remain deployable following the high wind event. This is identified as Open Item 3.1.3.1.A in Section 4.1.
In fact, the plant may have been shut down and the plant configuration could be established to optimize FLEX deployment.
The licensee's approach described above, as currently understood, has raised concerns which must be addressed before confirmation can be provided that the approach is consistent with the Revision 1                                   Page 16 of 60                                 2014-02-15
For example, the portable pumps could be connected, tested, and readied for use prior to the arrival of the hurricane.  
 
: Further, protective actions can be taken to reduce the potential for wind impacts.
guidance found in NEI 12-06, as endorsed by JLD-ISG-2012-01, such that there would be reasonable assurance that the requirements of Order EA-12-049 will be met with respect to protection of FLEX equipment considering the high wind hazard. This concern is identified as Open Item 3.1.3.1.A above and in Section 4.1.
These factors can be credited in considering how the baseline capability is deployed.  
3.1.3.2 Deployment of FLEX Equipment- High Wind Hazard NEI 12-06, Section 7.3.2 states:
: 2. The ultimate heat sink may be one of the first functions affected by a hurricane due to debris and storm surge considerations.
There are a number of considerations which apply to the deployment of FLEX equipment for high wind hazards:
Consequently, the evaluation should address the effects of ELAP/LUHS, along with any other equipment that would be damaged by the postulated storm. 3. Deployment of FLEX following a hurricane or tornado may involve the need to remove debris. Consequently, the capability to remove debris caused by these extreme wind storms should be included.  
: 1. For hurricane plants, the plant may not be at power prior to the simultaneous ELAP and LUHS condition. In fact, the plant may have been shut down and the plant configuration could be established to optimize FLEX deployment.
: 4. A means to move FLEX equipment should be provided that is also reasonably protected from the event. 5. The ability to move equipment and restock supplies may be hampered during a hurricane and should be considered in plans for deployment of FLEX equipment.
For example, the portable pumps could be connected, tested, and readied for use prior to the arrival of the hurricane. Further, protective actions can be taken to reduce the potential for wind impacts. These factors can be credited in considering how the baseline capability is deployed.
Consideration 1, 2 and 5 are not applicable to JAF since the plant is not susceptible to the hurricane hazard as noted in Section 3.1.3 of this technical evaluation report. The Integrated Plan did not address potential impacts from wind generated debris nor identify any debris removal equipment to be available on site to facilitate deployment of FLEX equipment in Phase 2. This is identified as Confirmatory Item 3.1.3.2.A in Section 4.2. The protection of the means to move FLEX equipment from the high wind hazard has not been addressed in the Integrated Plan. This is identified as Confirmatory Item 3.1.3.2.8 in Section 4.2. The licensee's approach described above, as currently understood, is consistent with the guidance found in NEI 12-06, as endorsed by JLD-ISG-2012-01, and subject to the successful closure of issues related to the Confirmatory Items, provides reasonable assurance that the requirements of Order EA-12-049 will be met with respect to deployment of FLEX equipment Revision 1 Page 17 of 60 2014-02-15 considering the high wind hazard if these requirements are implemented as described.
: 2. The ultimate heat sink may be one of the first functions affected by a hurricane due to debris and storm surge considerations. Consequently, the evaluation should address the effects of ELAP/LUHS, along with any other equipment that would be damaged by the postulated storm.
3.1.3.3 Procedural Interfaces-High Wind Hazard NEI 12-06, Section 7.3.3, states: The overall plant response strategy should be enveloped by the baseline capabilities, but procedural interfaces may need to be considered.
: 3. Deployment of FLEX following a hurricane or tornado may involve the need to remove debris. Consequently, the capability to remove debris caused by these extreme wind storms should be included.
For example, many sites have hurricane procedures.
: 4. A means to move FLEX equipment should be provided that is also reasonably protected from the event.
The actions necessary to support the deployment considerations identified above should be incorporated into those procedures.
: 5. The ability to move equipment and restock supplies may be hampered during a hurricane and should be considered in plans for deployment of FLEX equipment.
On page 8, in the section of the Integrated Plan discussing how strategies will be deployed in all modes, the licensee stated that the identified paths and deployment areas will be accessible during all modes of operation.
Consideration 1, 2 and 5 are not applicable to JAF since the plant is not susceptible to the hurricane hazard as noted in Section 3.1.3 of this technical evaluation report.
In addition the clearing of these paths following any significant external event or hazard will be handled on a priority basis. This deployment strategy will be included within an administrative program in order to keep pathways clear or implement actions to clear the pathways.
The Integrated Plan did not address potential impacts from wind generated debris nor identify any debris removal equipment to be available on site to facilitate deployment of FLEX equipment in Phase 2. This is identified as Confirmatory Item 3.1.3.2.A in Section 4.2.
On page 15, in the section of the Integrated Plan discussing procedures, strategies and guidelines for maintaining core cooling during the initial phases, the licensee stated that JAF will utilize the industry-developed guidance from the Owners Groups, the Electric Power Research Institute (EPRI), and NEI Task team to develop site-specific procedures or guidelines to address the criteria in NEI 12-06. These procedures and/or guidelines will support the existing symptom based command and control strategies in the current emergency operating procedures (EOPs). The licensee's approach described above, as currently understood, is consistent with the guidance found in NEI 12-06, as endorsed by JLD-ISG-2012-01, and provides reasonable assurance that the requirements of Order EA-12-049 will be met with respect to procedural interfaces if these requirements are implemented as described.
The protection of the means to move FLEX equipment from the high wind hazard has not been addressed in the Integrated Plan. This is identified as Confirmatory Item 3.1.3.2.8 in Section 4.2.
3.1.3.4 Considerations in Using Offsite Resources-High Wind Hazard NEI 12-06, Section 7.3.4 states: Extreme storms with high winds can have regional impacts that could have a significant impact on the transportation of off-site resources.  
The licensee's approach described above, as currently understood, is consistent with the guidance found in NEI 12-06, as endorsed by JLD-ISG-2012-01, and subject to the successful closure of issues related to the Confirmatory Items, provides reasonable assurance that the requirements of Order EA-12-049 will be met with respect to deployment of FLEX equipment Revision 1                                   Page 17 of 60                               2014-02-15
: 1. Sites should review site access routes to determine the best means to obtain resources from off-site following a hurricane.  
 
considering the high wind hazard if these requirements are implemented as described.
3.1.3.3 Procedural Interfaces- High Wind Hazard NEI 12-06, Section 7.3.3, states:
The overall plant response strategy should be enveloped by the baseline capabilities, but procedural interfaces may need to be considered. For example, many sites have hurricane procedures. The actions necessary to support the deployment considerations identified above should be incorporated into those procedures.
On page 8, in the section of the Integrated Plan discussing how strategies will be deployed in all modes, the licensee stated that the identified paths and deployment areas will be accessible during all modes of operation. In addition the clearing of these paths following any significant external event or hazard will be handled on a priority basis. This deployment strategy will be included within an administrative program in order to keep pathways clear or implement actions to clear the pathways.
On page 15, in the section of the Integrated Plan discussing procedures, strategies and guidelines for maintaining core cooling during the initial phases, the licensee stated that JAF will utilize the industry-developed guidance from the Owners Groups, the Electric Power Research Institute (EPRI), and NEI Task team to develop site-specific procedures or guidelines to address the criteria in NEI 12-06. These procedures and/or guidelines will support the existing symptom based command and control strategies in the current emergency operating procedures (EOPs).
The licensee's approach described above, as currently understood, is consistent with the guidance found in NEI 12-06, as endorsed by JLD-ISG-2012-01, and provides reasonable assurance that the requirements of Order EA-12-049 will be met with respect to procedural interfaces if these requirements are implemented as described.
3.1.3.4 Considerations in Using Offsite Resources- High Wind Hazard NEI 12-06, Section 7.3.4 states:
Extreme storms with high winds can have regional impacts that could have a significant impact on the transportation of off-site resources.
: 1. Sites should review site access routes to determine the best means to obtain resources from off-site following a hurricane.
: 2. Sites impacted by storms with high winds should consider where equipment delivered from off-site could be staged for use on-site.
: 2. Sites impacted by storms with high winds should consider where equipment delivered from off-site could be staged for use on-site.
On page 10, in the section of the Integrated Plan discussing the RRCs, Entergy stated that the industry has selected a vendor to manage two RRCs to provide large equipment in support of the response to BDBEEs. Each RRC will store and maintain five sets of equipment, four of which are expected to be fully deployable upon request.
On page 10, in the section of the Integrated Plan discussing the RRCs, Entergy stated that the industry has selected a vendor to manage two RRCs to provide large equipment in support of the response to BDBEEs. Each RRC will store and maintain five sets of equipment, four of which are expected to be fully deployable upon request. The fifth set is provided to account for equipment that may be unavailable due to its maintenance and testing cycle.
The fifth set is provided to account for equipment that may be unavailable due to its maintenance and testing cycle. JAF will utilize the industry RRCs for Phase 3 equipment.
JAF will utilize the industry RRCs for Phase 3 equipment. In an ELAP event, communications Revision 1                                   Page 18 of 60                             2014-02-15
In an ELAP event, communications Revision 1 Page 18 of 60 2014-02-15 would be established between JAF and the industry SAFER team and required equipment mobilized as needed. JAF will enter into a contractual agreement with the SAFER team. Equipment will initially be moved from an RRC to a local staging area, established by the SAFER team and JAF. The equipment will be prepared at the staging area prior to transport to the site. First arriving equipment, as established during development of the RRC playbook, will be delivered to the site within 24 hours from the initial request.
 
would be established between JAF and the industry SAFER team and required equipment mobilized as needed. JAF will enter into a contractual agreement with the SAFER team.
Equipment will initially be moved from an RRC to a local staging area, established by the SAFER team and JAF. The equipment will be prepared at the staging area prior to transport to the site. First arriving equipment, as established during development of the RRC playbook, will be delivered to the site within [[estimated NRC review hours::24 hours]] from the initial request.
On page 22, in the section of the Integrated Plan discussing coping strategies to maintain core cooling during Phase 3, the licensee stated that equipment transported to the site will be either immediately staged at the point of use or temporarily stored at the lay down area. The lay down area is located outside the protected area on the south side of the plant near the main entrance.
On page 22, in the section of the Integrated Plan discussing coping strategies to maintain core cooling during Phase 3, the licensee stated that equipment transported to the site will be either immediately staged at the point of use or temporarily stored at the lay down area. The lay down area is located outside the protected area on the south side of the plant near the main entrance.
Entergy has not yet identified the local offsite staging area(s) for the RRC FLEX equipment nor evaluated the methods for delivery of equipment from the offsite staging area to the site under various conditions such as seismic,  
Entergy has not yet identified the local offsite staging area(s) for the RRC FLEX equipment nor evaluated the methods for delivery of equipment from the offsite staging area to the site under various conditions such as seismic, flooding, high winds, and snow, ice and extreme cold. The identification of local offsite staging areas and evaluation of delivery methods following high wind events has been combined with Confirmatory Item 3.1.1.4.A in Section 4.2.
: flooding, high winds, and snow, ice and extreme cold. The identification of local offsite staging areas and evaluation of delivery methods following high wind events has been combined with Confirmatory Item 3.1.1.4.A in Section 4.2. The licensee's approach described above, as currently understood, is consistent with the guidance found in NEI 12-06, as endorsed by JLD-ISG-2012-01, and subject to the successful closure of issues related to the Confirmatory Item, provides reasonable assurance that the requirements of Order EA-12-049 will be met with respect to offsite resources if these requirements are implemented as described.
The licensee's approach described above, as currently understood, is consistent with the guidance found in NEI 12-06, as endorsed by JLD-ISG-2012-01, and subject to the successful closure of issues related to the Confirmatory Item, provides reasonable assurance that the requirements of Order EA-12-049 will be met with respect to offsite resources if these requirements are implemented as described.
3.1.4 Snow, Ice and Extreme Cold As discussed in NEI 12-06, Section 8.2.1: All sites should consider the temperature ranges and weather conditions for their site in storing and deploying their FLEX equipment consistent with normal design practices.
3.1.4 Snow, Ice and Extreme Cold As discussed in NEI 12-06, Section 8.2.1:
All sites outside of Southern California,  
All sites should consider the temperature ranges and weather conditions for their site in storing and deploying their FLEX equipment consistent with normal design practices. All sites outside of Southern California, Arizona, the Gulf Coast and Florida are expected to address deployment for conditions of snow, ice, and extreme cold. All sites located North of the 351h Parallel should provide the capability to address extreme snowfall with snow removal equipment. Finally, all sites except for those within Level 1 and 2 of the maximum ice storm severity map contained in Figure 8-2 should address the impact of ice storms.
: Arizona, the Gulf Coast and Florida are expected to address deployment for conditions of snow, ice, and extreme cold. All sites located North of the 351h Parallel should provide the capability to address extreme snowfall with snow removal equipment.  
On page 1 of the Integrated Plan, in the section regarding the determination of applicable extreme external hazards, the licensee stated that the JAF site is located above the 35th parallel and is subject to the extreme cold hazards, including snow and ice. The site is located within the region characterized by NOAA as subject to significant accumulations during three-day snowfalls. The site is located within the region characterized by EPRI as ice severity level 5.
: Finally, all sites except for those within Level 1 and 2 of the maximum ice storm severity map contained in Figure 8-2 should address the impact of ice storms. On page 1 of the Integrated Plan, in the section regarding the determination of applicable extreme external  
As such, the JAF site is subject to severe icing conditions that could also cause catastrophic destruction to electrical transmission lines.
: hazards, the licensee stated that the JAF site is located above the 35th parallel and is subject to the extreme cold hazards, including snow and ice. The site is located within the region characterized by NOAA as subject to significant accumulations during day snowfalls.
The licensee stated that the extreme cold hazard, including snow and ice, is applicable to JAF.
The site is located within the region characterized by EPRI as ice severity level 5. As such, the JAF site is subject to severe icing conditions that could also cause catastrophic destruction to electrical transmission lines. The licensee stated that the extreme cold hazard, including snow and ice, is applicable to JAF. The licensee's approach described above, as currently understood, is consistent with the guidance found in NEI 12-06, as endorsed by JLD-ISG-2012-01, and provides reasonable assurance that the requirements of Order EA-12-049 will be met with respect to screening for snow, ice, and extreme cold if these requirements are implemented as described.
The licensee's approach described above, as currently understood, is consistent with the guidance found in NEI 12-06, as endorsed by JLD-ISG-2012-01, and provides reasonable assurance that the requirements of Order EA-12-049 will be met with respect to screening for snow, ice, and extreme cold if these requirements are implemented as described.
Revision 1 Page 19 of 60 2014-02-15 3.1.4.1 Protection of FLEX Equipment  
Revision 1                                   Page 19 of 60                               2014-02-15
-Snow, Ice and Extreme Cold Hazard NEI 12-06, Section 8.3.1 states: These considerations apply to the protection of FLEX equipment from snow, ice, and extreme cold hazards:  
 
: 1. For sites subject to significant snowfall and ice storms, portable FLEX equipment should be stored in one of the two configurations.  
3.1.4.1 Protection of FLEX Equipment - Snow, Ice and Extreme Cold Hazard NEI 12-06, Section 8.3.1 states:
: a. In a structure that meets the plant's design basis for the snow, ice and cold conditions (e.g., existing safety-related structure).  
These considerations apply to the protection of FLEX equipment from snow, ice, and extreme cold hazards:
: b. In a structure designed to or evaluated equivalent to ASCE 7-10, Minimum Design Loads for Buildings and Other Structures for the snow, ice, and cold conditions from the site's design basis. c. Provided the N sets of equipment are located as described in a or b above, the N+1 equipment may be stored in an evaluated storage location capable of withstanding historical extreme weather conditions such that the equipment is deployable.  
: 1. For sites subject to significant snowfall and ice storms, portable FLEX equipment should be stored in one of the two configurations.
: 2. Storage of FLEX equipment should account for the fact that the equipment will need to function in a timely manner. The equipment should be maintained at a temperature within a range to ensure its likely function when called upon. For example, by storage in a heated enclosure or by direct heating (e.g., jacket water, battery, engine block heater, etc.). On page 3, in the section of the Integrated Plan discussing the key assumptions that were considered in the development and implementation of FLEX strategies, the licensee stated that Phase 2 FLEX components stored at the site will be protected against the applicable hazards in accordance with NEI 12-06. On pages 20, 27, 34, and 41 in the sections of the Integrated Plan regarding the strategies for maintaining core cooling, containment, spent fuel cooling and for safety systems support, respectively, the licensee stated that protection of associated FLEX portable equipment from snow, ice and extreme cold hazards would be provided by constructing structures that meet the guidelines of NEI 12-06, Section 11, which references Sections 5 through 9 for more detailed guidance for protection of FLEX equipment during specific external events. During the audit process, the licensee provided additional information stating that the storage facilities will be heated as necessary in accordance with manufacturer recommendations and that the FLEX storage structures have to meet ASCE 7-10 for snow and ice loading and cold conditions or otherwise meet the site design basis snow and ice loading.
: a. In a structure that meets the plant's design basis for the snow, ice and cold conditions (e.g., existing safety-related structure).
: b. In a structure designed to or evaluated equivalent to ASCE 7-10, Minimum Design Loads for Buildings and Other Structures for the snow, ice, and cold conditions from the site's design basis.
: c. Provided the N sets of equipment are located as described in a or b above, the N+1 equipment may be stored in an evaluated storage location capable of withstanding historical extreme weather conditions such that the equipment is deployable.
: 2. Storage of FLEX equipment should account for the fact that the equipment will need to function in a timely manner. The equipment should be maintained at a temperature within a range to ensure its likely function when called upon.
For example, by storage in a heated enclosure or by direct heating (e.g.,
jacket water, battery, engine block heater, etc.).
On page 3, in the section of the Integrated Plan discussing the key assumptions that were considered in the development and implementation of FLEX strategies, the licensee stated that Phase 2 FLEX components stored at the site will be protected against the applicable hazards in accordance with NEI 12-06.
On pages 20, 27, 34, and 41 in the sections of the Integrated Plan regarding the strategies for maintaining core cooling, containment, spent fuel cooling and for safety systems support, respectively, the licensee stated that protection of associated FLEX portable equipment from snow, ice and extreme cold hazards would be provided by constructing structures that meet the guidelines of NEI 12-06, Section 11, which references Sections 5 through 9 for more detailed guidance for protection of FLEX equipment during specific external events. During the audit process, the licensee provided additional information stating that the storage facilities will be heated as necessary in accordance with manufacturer recommendations and that the FLEX storage structures have to meet ASCE 7-10 for snow and ice loading and cold conditions or otherwise meet the site design basis snow and ice loading.
The licensee's approach described above, as currently understood, is consistent with the guidance found in NEI 12-06, as endorsed by JLD-ISG-2012-01, and provides reasonable assurance that the requirements of Order EA-12-049 will be met with respect to protection of FLEX equipment considering the snow, ice and extreme cold hazard if these requirements are implemented as described.
The licensee's approach described above, as currently understood, is consistent with the guidance found in NEI 12-06, as endorsed by JLD-ISG-2012-01, and provides reasonable assurance that the requirements of Order EA-12-049 will be met with respect to protection of FLEX equipment considering the snow, ice and extreme cold hazard if these requirements are implemented as described.
3.1.4.2 Deployment of FLEX Equipment-Snow, Ice and Extreme Cold Hazard Revision 1 Page 20 of 60 2014-02-15 NEI 12-06, Section 8.3.2 states: There are a number of considerations that apply to the deployment of FLEX equipment for snow, ice, and extreme cold hazards:  
3.1.4.2 Deployment of FLEX Equipment- Snow, Ice and Extreme Cold Hazard Revision 1                                   Page 20 of 60                               2014-02-15
: 1. The FLEX equipment should be procured to function in the extreme conditions applicable to the site. Normal safety-related design limits for outside conditions may be used, but consideration should also be made for any manual operations required by plant personnel in such conditions.  
 
: 2. For sites exposed to extreme snowfall and ice storms, provisions should be made for snow/ice  
NEI 12-06, Section 8.3.2 states:
: removal, as needed to obtain and transport FLEX equipment from storage to its location for deployment.  
There are a number of considerations that apply to the deployment of FLEX equipment for snow, ice, and extreme cold hazards:
: 3. For some sites, the ultimate heat sink and flow path may be affected by extreme low temperatures due to ice blockage or formation of frazil ice. Consequently, the evaluation should address the effects of such a loss of UHS on the deployment of FLEX equipment.
: 1. The FLEX equipment should be procured to function in the extreme conditions applicable to the site. Normal safety-related design limits for outside conditions may be used, but consideration should also be made for any manual operations required by plant personnel in such conditions.
For example, if UHS water is to be used as a makeup source, some additional measures may need to be taken to assure that the FLEX equipment can utilize the water. On page 8, in the section of the Integrated Plan discussing how strategies will be deployed in all modes, the licensee stated that the identified paths and deployment areas will be accessible during all modes of operation.
: 2. For sites exposed to extreme snowfall and ice storms, provisions should be made for snow/ice removal, as needed to obtain and transport FLEX equipment from storage to its location for deployment.
In addition, the clearing of these paths following any significant external event or hazard will be handled on a priority basis. This deployment strategy will be included within an administrative program in order to keep pathways clear or actions to clear the pathways.  
: 3. For some sites, the ultimate heat sink and flow path may be affected by extreme low temperatures due to ice blockage or formation of frazil ice.
: However, the Integrated Plan did not address the means for snow removal and does not list snow removal equipment in the table on page 45 which shows the portable FLEX equipment for Phase 2. This is identified as Confirmatory Item 3.1.4.2.A in Section 4.2. The licensee had not addressed the potential impact on the UHS due to ice blockage or formation of frazil ice as a result of extreme cold. This is identified as Open Item 3.1.4.2.8 in Section 4.1. The licensee's approach described above, as currently understood, is consistent with the guidance found in NEI 12-06, as endorsed by JLD-ISG-2012-01, and subject to the successful closure of issues related to the Confirmatory and Open Items, provides reasonable assurance that the requirements of Order EA-12-049 will be met with respect to deployment of FLEX equipment considering the snow, ice and extreme cold hazard if these requirements are implemented as described.
Consequently, the evaluation should address the effects of such a loss of UHS on the deployment of FLEX equipment. For example, if UHS water is to be used as a makeup source, some additional measures may need to be taken to assure that the FLEX equipment can utilize the water.
3.1.4.3 Procedural Interfaces-Snow, Ice, and Extreme Cold Hazard NEI 12-06, Section 8.3.3, states: The only procedural enhancements that would be expected to apply involve addressing the effects of snow and ice on transporting the FLEX equipment.
On page 8, in the section of the Integrated Plan discussing how strategies will be deployed in all modes, the licensee stated that the identified paths and deployment areas will be accessible during all modes of operation. In addition, the clearing of these paths following any significant external event or hazard will be handled on a priority basis. This deployment strategy will be included within an administrative program in order to keep pathways clear or actions to clear the pathways. However, the Integrated Plan did not address the means for snow removal and does not list snow removal equipment in the table on page 45 which shows the portable FLEX equipment for Phase 2. This is identified as Confirmatory Item 3.1.4.2.A in Section 4.2.
The licensee had not addressed the potential impact on the UHS due to ice blockage or formation of frazil ice as a result of extreme cold. This is identified as Open Item 3.1.4.2.8 in Section 4.1.
The licensee's approach described above, as currently understood, is consistent with the guidance found in NEI 12-06, as endorsed by JLD-ISG-2012-01, and subject to the successful closure of issues related to the Confirmatory and Open Items, provides reasonable assurance that the requirements of Order EA-12-049 will be met with respect to deployment of FLEX equipment considering the snow, ice and extreme cold hazard if these requirements are implemented as described.
3.1.4.3 Procedural Interfaces- Snow, Ice, and Extreme Cold Hazard NEI 12-06, Section 8.3.3, states:
The only procedural enhancements that would be expected to apply involve addressing the effects of snow and ice on transporting the FLEX equipment.
This includes both access to the transport path, e.g., snow removal, and appropriately equipped vehicles for moving the equipment.
This includes both access to the transport path, e.g., snow removal, and appropriately equipped vehicles for moving the equipment.
Revision 1 Page 21 of 60 2014-02-15 As discussed in Section 3.1.4.2 of this report, the licensee has committed to develop an administrative program to ensure pathways remain clear or compensatory actions will be implemented to ensure all strategies can be deployed during all modes of operation.
Revision 1                                 Page 21 of 60                               2014-02-15
 
As discussed in Section 3.1.4.2 of this report, the licensee has committed to develop an administrative program to ensure pathways remain clear or compensatory actions will be implemented to ensure all strategies can be deployed during all modes of operation.
Entergy has not discussed changes to station procedures relative to an ELAP during a snow, ice and extreme cold hazard. However, the licensee has stated that they have not yet completed plans for storage buildings and deployment paths for portable/FLEX equipment, but will use industry developed guidance to develop specific site procedures.
Entergy has not discussed changes to station procedures relative to an ELAP during a snow, ice and extreme cold hazard. However, the licensee has stated that they have not yet completed plans for storage buildings and deployment paths for portable/FLEX equipment, but will use industry developed guidance to develop specific site procedures.
On page 15, in the section of the Integrated Plan discussing procedures, strategies and guidelines for maintaining core cooling during the initial phases, the licensee stated that JAF will utilize the industry-developed guidance from the Owners Groups, EPRI and NEI Task team to develop site-specific procedures or guidelines to address the criteria in NEI 12-06. These procedures and/or guidelines will support the existing symptom based command and control strategies in the current EOPs. The licensee's approach described above, as currently understood, is consistent with the guidance found in NEI 12-06, as endorsed by JLD-ISG-2012-01, and provides reasonable assurance that the requirements of Order EA-12-049 will be met with respect to procedural interfaces if these requirements are implemented as described.
On page 15, in the section of the Integrated Plan discussing procedures, strategies and guidelines for maintaining core cooling during the initial phases, the licensee stated that JAF will utilize the industry-developed guidance from the Owners Groups, EPRI and NEI Task team to develop site-specific procedures or guidelines to address the criteria in NEI 12-06. These procedures and/or guidelines will support the existing symptom based command and control strategies in the current EOPs.
3.1.4.4 Considerations in Using Offsite Resources  
The licensee's approach described above, as currently understood, is consistent with the guidance found in NEI 12-06, as endorsed by JLD-ISG-2012-01, and provides reasonable assurance that the requirements of Order EA-12-049 will be met with respect to procedural interfaces if these requirements are implemented as described.
-Snow, Ice and Extreme Cold Hazard NEI 12-06, Section 8.3.4, states: Severe snow and ice storms can affect site access and can impact staging areas for receipt of off-site material and equipment.
3.1.4.4 Considerations in Using Offsite Resources - Snow, Ice and Extreme Cold Hazard NEI 12-06, Section 8.3.4, states:
On page 10, in the section of the Integrated Plan discussing the RRCs, Entergy stated that the industry has selected a vendor to manage two RRCs to provide large equipment in support of the response to BDBEEs. Each RRC will store and maintain five sets of equipment, four of which are expected to be fully deployable upon request.
Severe snow and ice storms can affect site access and can impact staging areas for receipt of off-site material and equipment.
The fifth set is provided to account for equipment that may be unavailable due to its maintenance and testing cycle. JAF will utilize the industry RRCs for Phase 3 equipment.
On page 10, in the section of the Integrated Plan discussing the RRCs, Entergy stated that the industry has selected a vendor to manage two RRCs to provide large equipment in support of the response to BDBEEs. Each RRC will store and maintain five sets of equipment, four of which are expected to be fully deployable upon request. The fifth set is provided to account for equipment that may be unavailable due to its maintenance and testing cycle.
In an ELAP event, communications would be established between JAF and the industry SAFER team and required equipment mobilized as needed. JAF will enter into a contractual agreement with the SAFER team. Equipment will initially be moved from an RRC to a local staging area, established by the SAFER team and JAF. The equipment will be prepared at the staging area prior to transport to the site. First arriving equipment, as established during development of the RRC playbook, will be delivered to the site within 24 hours from the initial request.
JAF will utilize the industry RRCs for Phase 3 equipment. In an ELAP event, communications would be established between JAF and the industry SAFER team and required equipment mobilized as needed. JAF will enter into a contractual agreement with the SAFER team.
Equipment will initially be moved from an RRC to a local staging area, established by the SAFER team and JAF. The equipment will be prepared at the staging area prior to transport to the site. First arriving equipment, as established during development of the RRC playbook, will be delivered to the site within [[estimated NRC review hours::24 hours]] from the initial request.
On page 22, in the section of the Integrated Plan discussing coping strategies to maintain core cooling during Phase 3, the licensee stated that equipment transported to the site will be either immediately staged at the point of use or temporarily stored at the lay down area. The lay down area is located outside the protected area on the south side of the plant near the main entrance.
On page 22, in the section of the Integrated Plan discussing coping strategies to maintain core cooling during Phase 3, the licensee stated that equipment transported to the site will be either immediately staged at the point of use or temporarily stored at the lay down area. The lay down area is located outside the protected area on the south side of the plant near the main entrance.
Entergy has not yet identified the local offsite staging area(s) for the RRC FLEX equipment nor evaluated the methods for delivery of equipment from the offsite staging area to the site under various conditions such as seismic,  
Entergy has not yet identified the local offsite staging area(s) for the RRC FLEX equipment nor evaluated the methods for delivery of equipment from the offsite staging area to the site under various conditions such as seismic, flooding, high winds, and snow, ice and extreme cold. The identification of local offsite staging areas and evaluation of delivery methods following a snow, Revision 1                                     Page 22 of 60                             2014-02-15
: flooding, high winds, and snow, ice and extreme cold. The identification of local offsite staging areas and evaluation of delivery methods following a snow, Revision 1 Page 22 of 60 2014-02-15 ice and extreme cold event has been combined with Confirmatory Item 3.1.1.4.A in Section 4.2. The licensee's approach described above, as currently understood, is consistent with the guidance found in NEI 12-06, as endorsed by JLD-ISG-2012-01, and subject to the successful closure of issues related to the Confirmatory Item, provides reasonable assurance that the requirements of Order EA-12-049 will be met with respect to offsite resources if these requirements are implemented as described.
 
3.1.5 High Temperatures NEI 12-06, Section 9 states: All sites will address high temperatures.
ice and extreme cold event has been combined with Confirmatory Item 3.1.1.4.A in Section 4.2.
Virtually every state in the lower 48 contiguous United States has experienced temperatures in excess of 110°F. Many states have experienced temperatures in excess of 120°F. In this case, sites should consider the impacts of these conditions on deployment of the FLEX equipment.
The licensee's approach described above, as currently understood, is consistent with the guidance found in NEI 12-06, as endorsed by JLD-ISG-2012-01, and subject to the successful closure of issues related to the Confirmatory Item, provides reasonable assurance that the requirements of Order EA-12-049 will be met with respect to offsite resources if these requirements are implemented as described.
On page 2, in the section of the Integrated Plan discussing the determination of applicable extreme external  
3.1.5 High Temperatures NEI 12-06, Section 9 states:
: hazards, the licensee noted that per NEI 12-06 Section 9.2, all sites will address high temperatures.
All sites will address high temperatures. Virtually every state in the lower 48 contiguous United States has experienced temperatures in excess of 110°F.
Extreme high temperatures are not expected to impact the utilization of off-site resources or the ability of personnel to implement the required FLEX strategies.
Many states have experienced temperatures in excess of 120°F.
Site industrial safety procedures currently address activities with a potential for heat stress to prevent adverse impacts on personnel.
In this case, sites should consider the impacts of these conditions on deployment of the FLEX equipment.
The licensee stated that the high temperature hazard is applicable to JAF. The licensee's approach described above, as currently understood, is consistent with the guidance found in NEI 12-06, as endorsed by JLD-ISG-2012-01, and provides reasonable assurance that the requirements of Order EA-12-049 will be met with respect to screening for high temperature hazards if these requirements are implemented as described.
On page 2, in the section of the Integrated Plan discussing the determination of applicable extreme external hazards, the licensee noted that per NEI 12-06 Section 9.2, all sites will address high temperatures. Extreme high temperatures are not expected to impact the utilization of off-site resources or the ability of personnel to implement the required FLEX strategies. Site industrial safety procedures currently address activities with a potential for heat stress to prevent adverse impacts on personnel. The licensee stated that the high temperature hazard is applicable to JAF.
3.1.5.1 Protection of FLEX Equipment-High Temperature Hazard NEI 12-06, Section 9.3.1, states: The equipment should be maintained at a temperature within a range to ensure its likely function when called upon. On pages 20, 27, 34, and 41 in the sections of the Integ rated Plan regarding the strategies for maintaining core cooling, containment, spent fuel cooling and for safety systems support, respectively, the licensee stated that protection of associated portable equipment from high temperature hazards would be provided in structures constructed to meet the guidelines of NEI 12-06, Section 11, which references Sections 5 through 9 for more detailed guidance for protection of FLEX equipment during specific external events. During the audit process, the licensee stated that due to the plant's location on the southern shore of Lake Ontario, extreme high temperatures are not expected.
The licensee's approach described above, as currently understood, is consistent with the guidance found in NEI 12-06, as endorsed by JLD-ISG-2012-01, and provides reasonable assurance that the requirements of Order EA-12-049 will be met with respect to screening for high temperature hazards if these requirements are implemented as described.
FLEX equipment maintained in the FLEX storage structures will be provided with adequate ventilation.
3.1.5.1 Protection of FLEX Equipment- High Temperature Hazard NEI 12-06, Section 9.3.1, states:
The licensee's approach described above, as currently understood, is consistent with the guidance found in NEI 12-06, as endorsed by JLD-ISG-2012-01, and provides reasonable Revision 1 Page 23 of 60 2014-02-15 assurance that the requirements of Order EA-12-049 will be met with respect to protection of FLEX equipment considering the high temperature hazard if these requirements are implemented as described.
The equipment should be maintained at a temperature within a range to ensure its likely function when called upon.
3.1.5.2 Deployment of FLEX Equipment-High Temperature Hazard NEI 12-06, Section 9.3.2 states: The FLEX equipment should be procured to function, including the need to move the equipment, in the extreme conditions applicable to the site. The potential impact of high temperatures on the storage of equipment should also be considered, e.g., expansion of sheet metal, swollen door seals, etc. Normal safety-related design limits for outside conditions may be used, but consideration should also be made for any manual operations required by plant personnel in such conditions.
On pages 20, 27, 34, and 41 in the sections of the Integ rated Plan regarding the strategies for maintaining core cooling, containment, spent fuel cooling and for safety systems support, respectively, the licensee stated that protection of associated portable equipment from high temperature hazards would be provided in structures constructed to meet the guidelines of NEI 12-06, Section 11, which references Sections 5 through 9 for more detailed guidance for protection of FLEX equipment during specific external events. During the audit process, the licensee stated that due to the plant's location on the southern shore of Lake Ontario, extreme high temperatures are not expected. FLEX equipment maintained in the FLEX storage structures will be provided with adequate ventilation.
There was insufficient information provided in the Integrated Plan to demonstrate that the impact of high temperature has been addressed for the deployment of equipment per the guidance of NEI 12-06. The licensee addressed this issue during the audit process by stating that temperatures will be determined in the areas where portable equipment is stored and at points of deployment where the equipment will operate (and therefore the temperature for which the equipment needs to be procured).
The licensee's approach described above, as currently understood, is consistent with the guidance found in NEI 12-06, as endorsed by JLD-ISG-2012-01, and provides reasonable Revision 1                                   Page 23 of 60                             2014-02-15
Heat and exhaust dissipated from the FLEX equipment during operation will be accounted for in the location where the FLEX equipment will be operated and on the requirements for the equipment.
 
assurance that the requirements of Order EA-12-049 will be met with respect to protection of FLEX equipment considering the high temperature hazard if these requirements are implemented as described.
3.1.5.2 Deployment of FLEX Equipment- High Temperature Hazard NEI 12-06, Section 9.3.2 states:
The FLEX equipment should be procured to function, including the need to move the equipment, in the extreme conditions applicable to the site. The potential impact of high temperatures on the storage of equipment should also be considered, e.g., expansion of sheet metal, swollen door seals, etc. Normal safety-related design limits for outside conditions may be used, but consideration should also be made for any manual operations required by plant personnel in such conditions.
There was insufficient information provided in the Integrated Plan to demonstrate that the impact of high temperature has been addressed for the deployment of equipment per the guidance of NEI 12-06. The licensee addressed this issue during the audit process by stating that temperatures will be determined in the areas where portable equipment is stored and at points of deployment where the equipment will operate (and therefore the temperature for which the equipment needs to be procured). Heat and exhaust dissipated from the FLEX equipment during operation will be accounted for in the location where the FLEX equipment will be operated and on the requirements for the equipment.
The licensee's approach described above, as currently understood, is consistent with the guidance found in NEI 12-06, as endorsed by JLD-ISG-2012-01, and provides reasonable assurance that the requirements of Order EA-12-049 will be met with respect to deployment of FLEX equipment considering the high temperature hazard if these requirements are implemented as described.
The licensee's approach described above, as currently understood, is consistent with the guidance found in NEI 12-06, as endorsed by JLD-ISG-2012-01, and provides reasonable assurance that the requirements of Order EA-12-049 will be met with respect to deployment of FLEX equipment considering the high temperature hazard if these requirements are implemented as described.
3.1.5.3 Procedural Interfaces  
3.1.5.3 Procedural Interfaces - High Temperature Hazard NEI 12-06, Section 9.3.3 states:
-High Temperature Hazard NEI 12-06, Section 9.3.3 states: The only procedural enhancements that would be expected to apply involve addressing the effects of high temperatures on the FLEX equipment.
The only procedural enhancements that would be expected to apply involve addressing the effects of high temperatures on the FLEX equipment.
In the Integrated Plan, the licensee has discussed the effect of high area temperatures resulting from an ELAP on accessibility to several rooms and facility locations.  
In the Integrated Plan, the licensee has discussed the effect of high area temperatures resulting from an ELAP on accessibility to several rooms and facility locations. However, there is no discussion of the potential effects of high temperatures at the location where the portable/FLEX equipment would be stored or operated in the event of high temperatures. During the audit process, the licensee stated that the new storage buildings housing the FLEX equipment will be provided with ventilation to cope with the high ambient temperatures.
: However, there is no discussion of the potential effects of high temperatures at the location where the portable/FLEX equipment would be stored or operated in the event of high temperatures.
During the audit process, the licensee stated that the new storage buildings housing the FLEX equipment will be provided with ventilation to cope with the high ambient temperatures.
The licensee's approach described above, as currently understood, is consistent with the guidance found in NEI 12-06, as endorsed by JLD-ISG-2012-01, and provides reasonable assurance that the requirements of Order EA-12-049 will be met with respect to procedural interfaces if these requirements are implemented as described.
The licensee's approach described above, as currently understood, is consistent with the guidance found in NEI 12-06, as endorsed by JLD-ISG-2012-01, and provides reasonable assurance that the requirements of Order EA-12-049 will be met with respect to procedural interfaces if these requirements are implemented as described.
3.2 PHASED APPROACH Revision 1 Page 24 of 60 2014-02-15 Attachment (2) to Order EA-12-049 describes the three-phase approach required for mitigating BDBEEs in order to maintain or restore core cooling, containment and SFP cooling capabilities.
3.2     PHASED APPROACH Revision 1                                 Page 24 of 60                               2014-02-15
 
Attachment (2) to Order EA-12-049 describes the three-phase approach required for mitigating BDBEEs in order to maintain or restore core cooling, containment and SFP cooling capabilities.
The phases consist of an initial phase using installed equipment and resources, followed by a transition phase using portable onsite equipment and consumables and a final phase using offsite resources.
The phases consist of an initial phase using installed equipment and resources, followed by a transition phase using portable onsite equipment and consumables and a final phase using offsite resources.
To meet these EA-12-049 requirements, Licensees will establish a baseline coping capability to prevent fuel damage in the reactor core or SFP and to maintain containment capabilities in the context of a BDBEE that results in the loss of all ac power, with the exception of buses supplied by safety-related batteries through inverters, and loss of normal access to the UHS. As described in NEI 12-06, Section 1.3, "[p]lant-specific analyses will determine the duration of each phase." This baseline coping capability is supplemented by the ability to use portable pumps to provide reactor pressure vessel (RPV)/reactor makeup in order to restore core or SFP capabilities as described in NEI 12-06, Section 3.2.2, Guideline (13). The NRC endorsed this approach with JLD-ISG-2012-01.
To meet these EA-12-049 requirements, Licensees will establish a baseline coping capability to prevent fuel damage in the reactor core or SFP and to maintain containment capabilities in the context of a BDBEE that results in the loss of all ac power, with the exception of buses supplied by safety-related batteries through inverters, and loss of normal access to the UHS. As described in NEI 12-06, Section 1.3, "[p]lant-specific analyses will determine the duration of each phase." This baseline coping capability is supplemented by the ability to use portable pumps to provide reactor pressure vessel (RPV)/reactor makeup in order to restore core or SFP capabilities as described in NEI 12-06, Section 3.2.2, Guideline (13). The NRC endorsed this approach with JLD-ISG-2012-01.
3.2.1 Reactor Core Cooling, Heat Removal, and Inventory Control Strategies NEI 12-06, Table 3-1 and Appendix C summarize one acceptable approach for the reactor core cooling strategies.
3.2.1   Reactor Core Cooling, Heat Removal, and Inventory Control Strategies NEI 12-06, Table 3-1 and Appendix C summarize one acceptable approach for the reactor core cooling strategies. This approach uses the installed reactor core isolation cooling (RCIC) system, or the high pressure coolant injection (HPCI) system to provide core cooling with installed equipment for the initial phase. This approach relies on depressurization of the RPV for injection with a portable injection source with diverse injection points established to inject through separate divisions/trains for the transition and final phases. This approach also provides for manual initiation of RCIC/HPCI as a contingency for further degradation of installed structures, systems, and components as a result of the beyond-design-basis initiating event.
This approach uses the installed reactor core isolation cooling (RCIC) system, or the high pressure coolant injection (HPCI) system to provide core cooling with installed equipment for the initial phase. This approach relies on depressurization of the RPV for injection with a portable injection source with diverse injection points established to inject through separate divisions/trains for the transition and final phases. This approach also provides for manual initiation of RCIC/HPCI as a contingency for further degradation of installed structures,  
As described in NEI 12-06, Section 3.2.1. 7, and JLD-ISG-2012-01, Section 2.1, strategies that have a time constraint to be successful should be identified and a basis provided that the time can be reasonably met. NEI 12-06, Section 3, provides the performance attributes, general criteria, and baseline assumptions to be used in developing the technical basis for the time constraints. Since the event is a beyond-design-basis event, the analysis used to provide the technical basis for time constraints for the mitigation strategies may use nominal initial values (without uncertainties) for plant parameters, and best-estimate physics data. All equipment used for consequence mitigation may be assumed to operate at nominal setpoints and capacities. NEI 12-06, Section 3.2.1.2, describes the initial plant conditions for the at-power mode of operation; Section 3.2.1.3 describes the initial conditions; and Section 3.2.1.4 describes boundary conditions for the reactor transient.
: systems, and components as a result of the beyond-design-basis initiating event. As described in NEI 12-06, Section 3.2.1. 7, and JLD-ISG-2012-01, Section 2.1, strategies that have a time constraint to be successful should be identified and a basis provided that the time can be reasonably met. NEI 12-06, Section 3, provides the performance attributes, general criteria, and baseline assumptions to be used in developing the technical basis for the time constraints.
Acceptance criteria for the analyses serving as the technical basis for establishing the time constraints for the baseline coping capabilities described in NEI 12-06, which provide an acceptable approach, as endorsed by JLD-ISG-2012-01, to meeting the requirements of EA 049 for maintaining core cooling are 1) the preclusion of core damage as discussed in NEI 12-06, Section 1.3 as the purpose of FLEX; and 2) the performance attributes as discussed in Appendix C.
Since the event is a beyond-design-basis event, the analysis used to provide the technical basis for time constraints for the mitigation strategies may use nominal initial values (without uncertainties) for plant parameters, and best-estimate physics data. All equipment used for consequence mitigation may be assumed to operate at nominal setpoints and capacities.
As described in NEI12-06, Section 1.3, plant-specific analyses determine the duration of the phases for the mitigation strategies. In support of its mitigation strategies, the licensee should perform a thermal-hydraulic analysis for an event with a simultaneous loss of all ac power and loss of normal access to the ultimate heat sink for an extended period (the ELAP event).
NEI 12-06, Section 3.2.1.2, describes the initial plant conditions for the at-power mode of operation; Section 3.2.1.3 describes the initial conditions; and Section 3.2.1.4 describes boundary conditions for the reactor transient.
Revision 1                                   Page 25 of 60                               2014-02-15
Acceptance criteria for the analyses serving as the technical basis for establishing the time constraints for the baseline coping capabilities described in NEI 12-06, which provide an acceptable  
 
: approach, as endorsed by JLD-ISG-2012-01, to meeting the requirements of EA-12-049 for maintaining core cooling are 1) the preclusion of core damage as discussed in NEI 12-06, Section 1.3 as the purpose of FLEX; and 2) the performance attributes as discussed in Appendix C. As described in NEI12-06, Section 1.3, plant-specific analyses determine the duration of the phases for the mitigation strategies.
3.2.1.1. Computer Code Used for ELAP Analysis.
In support of its mitigation strategies, the licensee should perform a thermal-hydraulic analysis for an event with a simultaneous loss of all ac power and loss of normal access to the ultimate heat sink for an extended period (the ELAP event). Revision 1 Page 25 of 60 2014-02-15 3.2.1.1.
NEI 12-06, Section 1.3 states in part:
Computer Code Used for ELAP Analysis.
To the extent practical, generic thermal hydraulic analyses will be developed to support plant specific decision-making. Justification for the duration of each phase will address the on-site availability of equipment, the resources necessary to deploy the equipment consistent with the required timeline, anticipated site conditions following the beyond-design-basis external event, and the ability of the local infrastructure to enable delivery of equipment and resources from offsite.
NEI 12-06, Section 1.3 states in part: To the extent practical, generic thermal hydraulic analyses will be developed to support plant specific decision-making.
On pages 7, 12, 14, and 24 of the Integrated Plan, the licensee identified the industry-developed Modular Accident Analysis Program (MAAP) code as the analysis method for determining plant response to the ELAP event. The plant response and FLEX implementation strategies are shown in the Integrated Plan in Attachment 1A "Sequence of Events (SOE)
Justification for the duration of each phase will address the on-site availability of equipment, the resources necessary to deploy the equipment consistent with the required  
Timeline" which includes the time constraints and the technical basis for the site. During the audit the licensee stated that MAAP version 4.0.5 was used, using site-specific inputs; and the site-specific analysis followed as a guide the generic analysis done by GE Hitachi Nuclear Energy (GEH) in NEDC-33771 P/NED0-33771 "GEH Evaluation of FLEX Implementation Guidelines," Revision 0 (hereinafter referred to as NEDC-33771 P). (Revision 1 of this document was submitted to the NRC for information and has a publicly available version at ADAMS Accession No. ML130370742.)
: timeline, anticipated site conditions following the beyond-design-basis external event, and the ability of the local infrastructure to enable delivery of equipment and resources from offsite.
MAAP was written to simulate the response of both current and advanced light water reactors to loss of coolant accident (LOCA) and non-LOCA transients for probabilistic risk analyses as well as severe accident sequences. The code has been used to evaluate a wide range of severe accident phenomena, such as hydrogen generation and combustion, steam formation, and containment heating and pressurization.
On pages 7, 12, 14, and 24 of the Integrated Plan, the licensee identified the developed Modular Accident Analysis Program (MAAP) code as the analysis method for determining plant response to the ELAP event. The plant response and FLEX implementation strategies are shown in the Integrated Plan in Attachment 1A "Sequence of Events (SOE) Timeline" which includes the time constraints and the technical basis for the site. During the audit the licensee stated that MAAP version 4.0.5 was used, using site-specific inputs; and the site-specific analysis followed as a guide the generic analysis done by GE Hitachi Nuclear Energy (GEH) in NEDC-33771 P/NED0-33771 "GEH Evaluation of FLEX Implementation Guidelines,"
While the NRC staff acknowledges that MAAP4 has been used many times over the years and in a variety of forums for severe and beyond design basis analysis, MAAP4 is not an NRC-approved code, and the NRC staff has not examined its technical adequacy for performing thermal hydraulic analyses. Therefore, during the review of licensees' Integrated Plan, the issue of using MAAP4 was raised as a Generic Concern and was addressed by NEI in their position paper dated June 2013, entitled "Use of Modular Accident Analysis Program (MAAP4) in Support of Post-Fukushima Applications" (ADAMS Accession No. ML13190A201 ). After review of this position paper, the NRC staff endorsed a resolution through letter dated October 3, 2013 (ADAMS Accession No. ML13275A318). This endorsement contained five limitations on the MAAP4 computer code's use for simulating the ELAP event for Boiling Water Reactors (BWRs). Those limitations and their corresponding Confirmatory Item numbers for this report are provided as follows:
Revision 0 (hereinafter referred to as NEDC-33771 P). (Revision 1 of this document was submitted to the NRC for information and has a publicly available version at ADAMS Accession No. ML 130370742.)
(1) From the June 2013 position paper, benchmarks must be identified and discussed which demonstrate that MAAP is an appropriate code for the simulation of an ELAP event at your facility. This is Confirmatory Item 3.2.1.1.A in Section 4.2.
MAAP was written to simulate the response of both current and advanced light water reactors to loss of coolant accident (LOCA) and non-LOCA transients for probabilistic risk analyses as well as severe accident sequences.
(2) The collapsed level must remain above Top of Active Fuel (TAF) and the cool down rate must be within technical specifications limits. This is Confirmatory Item 3.2.1.1. 8 in Section 4.2.
The code has been used to evaluate a wide range of severe accident phenomena, such as hydrogen generation and combustion, steam formation, and containment heating and pressurization.
Revision 1                                   Page 26 of 60                               2014-02-15
While the NRC staff acknowledges that MAAP4 has been used many times over the years and in a variety of forums for severe and beyond design basis analysis, MAAP4 is not an approved code, and the NRC staff has not examined its technical adequacy for performing thermal hydraulic analyses.
 
Therefore, during the review of licensees' Integrated Plan, the issue of using MAAP4 was raised as a Generic Concern and was addressed by NEI in their position paper dated June 2013, entitled "Use of Modular Accident Analysis Program (MAAP4) in Support of Post-Fukushima Applications" (ADAMS Accession No. ML 13190A201
(3) MAAP must be used in accordance with Sections 4.1, 4.2, 4.3, 4.4, and 4.5 of the June 2013 position paper. This is Confirmatory Item 3.2.1.1.C in Section 4.2.
). After review of this position paper, the NRC staff endorsed a resolution through letter dated October 3, 2013 (ADAMS Accession No. ML 13275A318).
(4) In using MAAP, the licensee must identify and justify the subset of key modeling parameters cited from Tables 4-1 through 4-6 of the "MAAP Application Guidance, Desktop Reference for Using MAAP Software, Revision 2" (Electric Power Research Institute Report 1020236). This should include response at a plant-specific level regarding specific modeling options and parameter choices for key models that would be expected to substantially affect the ELAP analysis performed for that licensee's plant.
This endorsement contained five limitations on the MAAP4 computer code's use for simulating the ELAP event for Boiling Water Reactors (BWRs). Those limitations and their corresponding Confirmatory Item numbers for this report are provided as follows:  
Although some suggested key phenomena are identified below, other parameters considered important in the simulation of the ELAP event by the vendor /licensee should also be included.
(1) From the June 2013 position paper, benchmarks must be identified and discussed which demonstrate that MAAP is an appropriate code for the simulation of an ELAP event at your facility.
: a. Nodalization
This is Confirmatory Item 3.2.1.1.A in Section 4.2. (2) The collapsed level must remain above Top of Active Fuel (TAF) and the cool down rate must be within technical specifications limits. This is Confirmatory Item 3.2.1.1.
: b. General two-phase flow modeling
8 in Section 4.2. Revision 1 Page 26 of 60 2014-02-15 (3) MAAP must be used in accordance with Sections 4.1, 4.2, 4.3, 4.4, and 4.5 of the June 2013 position paper. This is Confirmatory Item 3.2.1.1.C in Section 4.2. (4) In using MAAP, the licensee must identify and justify the subset of key modeling parameters cited from Tables 4-1 through 4-6 of the "MAAP Application  
: c. Modeling of heat transfer and losses
: Guidance, Desktop Reference for Using MAAP Software, Revision 2" (Electric Power Research Institute Report 1 020236).
: d. Choked flow
This should include response at a plant-specific level regarding specific modeling options and parameter choices for key models that would be expected to substantially affect the ELAP analysis performed for that licensee's plant. Although some suggested key phenomena are identified below, other parameters considered important in the simulation of the ELAP event by the vendor /licensee should also be included.  
: e. Vent line pressure losses
: a. Nodalization  
: f. Decay heat (fission products I actinides I etc.)
: b. General two-phase flow modeling  
This is Confirmatory Item 3.2.1.1.D in Section 4.2.
: c. Modeling of heat transfer and losses d. Choked flow e. Vent line pressure losses f. Decay heat (fission products I actinides I etc.) This is Confirmatory Item 3.2.1.1.D in Section 4.2. (5) The specific MAAP analysis case that was used to validate the timing of mitigating strategies in the Integrated Plan must be identified and should be available on the ePortal for NRC staff to view. Alternately, a comparable level of information may be included in the supplemental response.
(5) The specific MAAP analysis case that was used to validate the timing of mitigating strategies in the Integrated Plan must be identified and should be available on the ePortal for NRC staff to view. Alternately, a comparable level of information may be included in the supplemental response. In either case, the analysis should include a plot of the collapsed vessel level to confirm that TAF is not reached (the elevation of the TAF should be provided) and a plot of the temperature cool down to confirm that the cool down is within technical specifications limits. This is Confirmatory Item 3.2.1.1. E in Section 4.2.
In either case, the analysis should include a plot of the collapsed vessel level to confirm that TAF is not reached (the elevation of the T AF should be provided) and a plot of the temperature cool down to confirm that the cool down is within technical specifications limits. This is Confirmatory Item 3.2.1.1.
The concern regarding the MAAP limitations was addressed during the audit process. The licensee stated that JAF will provide an updated MAAP analysis which will conform to the limitations identified in the NRC staff's endorsement letter.
E in Section 4.2. The concern regarding the MAAP limitations was addressed during the audit process.
The licensee's approach described above, as currently understood, is consistent with the guidance found in NEI 12-06, as endorsed by JLD-ISG-2012-01, and subject to the successful closure of issues related to the Confirmatory Items, provides reasonable assurance that the requirements of Order EA-12-049 will be met with respect to the use of computer codes if these requirements are implemented as described.
The licensee stated that JAF will provide an updated MAAP analysis which will conform to the limitations identified in the NRC staff's endorsement letter. The licensee's approach described above, as currently understood, is consistent with the guidance found in NEI 12-06, as endorsed by JLD-ISG-2012-01, and subject to the successful closure of issues related to the Confirmatory Items, provides reasonable assurance that the requirements of Order EA-12-049 will be met with respect to the use of computer codes if these requirements are implemented as described.
3.2.1.2. Recirculation Pump Seal Leakage Models.
3.2.1.2.
Conformance with the guidance of NEI 12-06, Section 3.2.1.5, Paragraph (4) includes consideration of recirculation pump seal leakage. When determining time constraints and the ability to maintain core cooling, it is important to consider losses to the RCS inventory as this can have a significant impact on the SOE. Special attention is paid to the recirculation pump seals because these can fail in a station blackout (SBO) event and contribute to beyond normal system leakage.
Recirculation Pump Seal Leakage Models. Conformance with the guidance of NEI 12-06, Section 3.2.1.5, Paragraph (4) includes consideration of recirculation pump seal leakage.
Revision 1                                   Page 27 of 60                               2014-02-15
When determining time constraints and the ability to maintain core cooling, it is important to consider losses to the RCS inventory as this can have a significant impact on the SOE. Special attention is paid to the recirculation pump seals because these can fail in a station blackout (SBO) event and contribute to beyond normal system leakage.
 
Revision 1 Page 27 of 60 2014-02-15 Entergy has not discussed reactor coolant inventory loss including normal system leakage and losses due to BWR recirculation pump seal leakage that is included in the ELAP analysis.
Entergy has not discussed reactor coolant inventory loss including normal system leakage and losses due to BWR recirculation pump seal leakage that is included in the ELAP analysis.
There is no discussion of the details of seal leakage rates, the details of the seal qualification tests, the seal leakage rate models and supporting test data, and leakage rate dependence.
There is no discussion of the details of seal leakage rates, the details of the seal qualification tests, the seal leakage rate models and supporting test data, and leakage rate pressure-dependence.
During the audit process, the licensee stated that the current MAAP analysis will be updated to address the code limitations as indicated in Section 3.2.1.1 of this technical evaluation report. Information regarding the seal leakage rates will also be provided when the reanalysis is completed.
During the audit process, the licensee stated that the current MAAP analysis will be updated to address the code limitations as indicated in Section 3.2.1.1 of this technical evaluation report.
This is identified as Confirmatory Item 3.2.1.2.A in Section 4.2. The licensee's approach described above, as currently understood, is consistent with the guidance found in NEI 12-06, as endorsed by JLD-ISG-2012-01, and subject to the successful closure of issues related to the Confirmatory Items, provides reasonable assurance that the requirements of Order EA-12-049 will be met with respect to the recirculation pump seal leakage model if these requirements are implemented as described.
Information regarding the seal leakage rates will also be provided when the reanalysis is completed. This is identified as Confirmatory Item 3.2.1.2.A in Section 4.2.
3.2.1.3 Sequence of Events NEI 12-06 discusses an event timeline and time constraints in several sections of the document, for example Section 1.3, Section 3.2.1.7 principle (4) and (6), Section 3.2.2 Guideline (1) and Section 12.1. NEI 12-06, Section 3.2.2 addresses the minimum baseline capabilities:
The licensee's approach described above, as currently understood, is consistent with the guidance found in NEI 12-06, as endorsed by JLD-ISG-2012-01, and subject to the successful closure of issues related to the Confirmatory Items, provides reasonable assurance that the requirements of Order EA-12-049 will be met with respect to the recirculation pump seal leakage model if these requirements are implemented as described.
Each site should establish the minimum coping capabilities consistent with specific evaluation of the potential impacts and responses to an ELAP and LUHS. In general, this coping can be thought of as occurring in three phases:
3.2.1.3 Sequence of Events NEI 12-06 discusses an event timeline and time constraints in several sections of the document, for example Section 1.3, Section 3.2.1.7 principle (4) and (6), Section 3.2.2 Guideline (1) and Section 12.1.
NEI 12-06, Section 3.2.2 addresses the minimum baseline capabilities:
Each site should establish the minimum coping capabilities consistent with unit-specific evaluation of the potential impacts and responses to an ELAP and LUHS. In general, this coping can be thought of as occurring in three phases:
* Phase 1: Cope relying on installed plant equipment.
* Phase 1: Cope relying on installed plant equipment.
* Phase 2: Transition from installed plant equipment to on-site FLEX equipment.
* Phase 2: Transition from installed plant equipment to on-site FLEX equipment.
* Phase 3: Obtain additional capability and redundancy from off-site equipment until power, water, and coolant injection systems are restored or commissioned.
* Phase 3: Obtain additional capability and redundancy from off-site equipment until power, water, and coolant injection systems are restored or commissioned.
In order to support the objective of an indefinite coping capability, each plant will be expected to establish capabilities consistent with Table 3-1 (BWRs). Additional explanation of these functions and capabilities are provided in NEI 12-06 Appendix C, "Approach to BWR Functions."
In order to support the objective of an indefinite coping capability, each plant will be expected to establish capabilities consistent with Table 3-1 (BWRs). Additional explanation of these functions and capabilities are provided in NEI 12-06 Appendix C, "Approach to BWR Functions."
The Integrated Plan includes a discussion of time constraints on pages 5 and 6 and in the "Sequence of Events Timeline",
The Integrated Plan includes a discussion of time constraints on pages 5 and 6 and in the "Sequence of Events Timeline", Attachment 1A, on pages 48 and 49.
Attachment 1A, on pages 48 and 49. In describing the technical basis for the SOE timeline, on page 6 of the Integrated Plan the licensee stated that GEH, on behalf of the Boiling Water Reactor Owners Group (BWROG),
In describing the technical basis for the SOE timeline, on page 6 of the Integrated Plan the licensee stated that GEH, on behalf of the Boiling Water Reactor Owners Group (BWROG),
developed document NEDC-33771 P to supplement the guidance in NEI 12-06 by providing additional BWR-specific information regarding the individual plant response to an ELAP event. The document includes the identification of the generic event scenario and expected plant response, the associated analytical bases and recommended actions for performance of a site-Revision 1 Page 28 of 60 2014-02-15 specific gap analysis.
developed document NEDC-33771 P to supplement the guidance in NEI 12-06 by providing additional BWR-specific information regarding the individual plant response to an ELAP event.
In the document, GEH utilized the NRC-accepted SUPERHEX (SHEX) computer code methodology for the BWR long-term containment analysis for the ELAP analysis.
The document includes the identification of the generic event scenario and expected plant response, the associated analytical bases and recommended actions for performance of a site-Revision 1                                   Page 28 of 60                               2014-02-15
As part of this document, a generic BWR 4/Mark I containment nuclear steam supply system (NSSS) evaluation was performed.
 
The generic BWR 4/Mark I containment analysis is generally applicable to the JAF (a BWR 4/Mark I plant) coping strategy because it supplements the guidance in NEI 12-06 by providing BWR-specific information regarding plant response for core cooling and containment integrity.
specific gap analysis. In the document, GEH utilized the NRC-accepted SUPERHEX (SHEX) computer code methodology for the BWR long-term containment analysis for the ELAP analysis. As part of this document, a generic BWR 4/Mark I containment nuclear steam supply system (NSSS) evaluation was performed. The generic BWR 4/Mark I containment analysis is generally applicable to the JAF (a BWR 4/Mark I plant) coping strategy because it supplements the guidance in NEI 12-06 by providing BWR-specific information regarding plant response for core cooling and containment integrity. The Integrated Plan states that the guidance provided in the BWROG report was utilized as appropriate to develop coping strategies and for prediction of the plant's response.
The Integrated Plan states that the guidance provided in the BWROG report was utilized as appropriate to develop coping strategies and for prediction of the plant's response.
During the audit process, the licensee stated that site-specific analyses were performed to develop the SOE timeline for the JAF plant. NEDC-33771 P was not used to develop the JAF site-specific coping strategies for maintaining core and containment cooling but used as a guide.
During the audit process, the licensee stated that site-specific analyses were performed to develop the SOE timeline for the JAF plant. NEDC-33771 P was not used to develop the JAF site-specific coping strategies for maintaining core and containment cooling but used as a guide. The SOE timeline presented in the Integrated Plan is based on analyses using the MAAP code as discussed in Section 3.2.1.1 of this report. The licensee stated that the site-specific reanalysis will be performed considering the code limitations identified in Section 3.2.1.1.
The SOE timeline presented in the Integrated Plan is based on analyses using the MAAP code as discussed in Section 3.2.1.1 of this report. The licensee stated that the site-specific reanalysis will be performed considering the code limitations identified in Section 3.2.1.1. This reanalysis may affect the time constraints identified in the SOE. This is identified as Confirmatory Item 3.2.1.3.A in Section 4.2.
This reanalysis may affect the time constraints identified in the SOE. This is identified as Confirmatory Item 3.2.1.3.A in Section 4.2. The licensee's approach described above, as currently understood, is consistent with the guidance found in NEI 12-06, as endorsed by JLD-ISG-2012-01, and, subject to the successful closure of issues related to the Confirmatory Item, provides reasonable assurance that the requirements of Order EA-12-049 will be met with respect to the sequence of events timeline if these requirements are implemented as described.
The licensee's approach described above, as currently understood, is consistent with the guidance found in NEI 12-06, as endorsed by JLD-ISG-2012-01, and, subject to the successful closure of issues related to the Confirmatory Item, provides reasonable assurance that the requirements of Order EA-12-049 will be met with respect to the sequence of events timeline if these requirements are implemented as described.
3.2.1.4 Systems and Components for Consequence Mitigation NEI 12-06, Section 11 provides details on the equipment quality attributes and design for the implementation of FLEX strategies.
3.2.1.4 Systems and Components for Consequence Mitigation NEI 12-06, Section 11 provides details on the equipment quality attributes and design for the implementation of FLEX strategies. It states:
It states: And, Equipment associated with these strategies will be procured as commercial equipment with design, storage, maintenance,  
Equipment associated with these strategies will be procured as commercial equipment with design, storage, maintenance, testing, and configuration control as outlined in this section [Section 11 ]. If the equipment is credited for other functions (e.g., fire protection), then the quality attributes of the other functions apply.
: testing, and configuration control as outlined in this section [Section 11 ]. If the equipment is credited for other functions (e.g., fire protection),
: And, Design requirements and supporting analysis should be developed for portable equipment that directly performs a FLEX mitigation strategy for core, containment, and SFP that provides the inputs, assumptions, and documented analysis that the mitigation strategy and support equipment will perform as intended.
then the quality attributes of the other functions apply. Design requirements and supporting analysis should be developed for portable equipment that directly performs a FLEX mitigation strategy for core, containment, and SFP that provides the inputs, assumptions, and documented analysis that the mitigation strategy and support equipment will perform as intended.
NEI 12-06, Section 3.2.1.12 states:
NEI 12-06, Section 3.2.1.12 states: Equipment relied upon to support FLEX implementation does not need to be qualified to all extreme environments that may be posed, but some basis should be provided for the capability of the equipment to continue to function.
Equipment relied upon to support FLEX implementation does not need to be qualified to all extreme environments that may be posed, but some basis should be provided for the capability of the equipment to continue to function.
Revision 1 Page 29 of60 2014-02-15 On page 3 of the Integrated Plan, the licensee stated that the portable FLEX components will be procured commercially and will be designed to be capable of performing in response to the screened in hazards in accordance with NEI 12-06. On pages 9 and 10, in the section of the Integrated Plan discussing program controls, the licensee stated that JAF will utilize the standard EPRI industry preventive maintenance (PM) process for establishing the maintenance actions for FLEX components.
Revision 1                                   Page 29 of60                                   2014-02-15
PM procedures will be established for portable components that directly perform in the mitigation strategy for the key FLEX safety functions (i.e., core cooling, containment integrity, and spent fuel cooling).
 
These procedures will consider NEI 12-06 guidance, vendor recommendations, and applicable industry standards.
On page 3 of the Integrated Plan, the licensee stated that the portable FLEX components will be procured commercially and will be designed to be capable of performing in response to the screened in hazards in accordance with NEI 12-06.
Testing procedures will be developed and performed at frequencies established based on type of equipment and considerations made within EPRI guidelines.
On pages 9 and 10, in the section of the Integrated Plan discussing program controls, the licensee stated that JAF will utilize the standard EPRI industry preventive maintenance (PM) process for establishing the maintenance actions for FLEX components. PM procedures will be established for portable components that directly perform in the mitigation strategy for the key FLEX safety functions (i.e., core cooling, containment integrity, and spent fuel cooling). These procedures will consider NEI 12-06 guidance, vendor recommendations, and applicable industry standards. Testing procedures will be developed and performed at frequencies established based on type of equipment and considerations made within EPRI guidelines.
On page 45 of the Integrated Plan, the design requirements for the FLEX equipment are shown in the table listing required equipment for Phase 2 mitigation strategies.
On page 45 of the Integrated Plan, the design requirements for the FLEX equipment are shown in the table listing required equipment for Phase 2 mitigation strategies. During the audit process, the licensee stated that the sizing of the pumps are bounding values based on conceptual design calculations and may change slightly when the detailed design is completed.
During the audit process, the licensee stated that the sizing of the pumps are bounding values based on conceptual design calculations and may change slightly when the detailed design is completed.
The licensee further stated that the loading calculations for the 600 Vac generators for Phase 2 and the 4160 Vac generator(s) for Phase 3 have not been completed. This is identified as Confirmatory Item 3.2.1.4.A in Section 4.2.
The licensee further stated that the loading calculations for the 600 Vac generators for Phase 2 and the 4160 Vac generator(s) for Phase 3 have not been completed.
The licensee's approach described above, as currently understood, is consistent with the guidance found in NEI 12-06, as endorsed by JLD-ISG-2012-01, and subject to the successful closure of issues related to the Confirmatory Item, provides reasonable assurance that the requirements of Order EA-12-049 will be met with respect to systems and components for consequence mitigation if these requirements are implemented as described.
This is identified as Confirmatory Item 3.2.1.4.A in Section 4.2. The licensee's approach described above, as currently understood, is consistent with the guidance found in NEI 12-06, as endorsed by JLD-ISG-2012-01, and subject to the successful closure of issues related to the Confirmatory Item, provides reasonable assurance that the requirements of Order EA-12-049 will be met with respect to systems and components for consequence mitigation if these requirements are implemented as described. 3.2.1.5 Monitoring Instrumentation and Controls NEI 12-06, Section 3.2.1.1 0 provides information regarding instrumentation and controls necessary for the success of the coping strategies.
3.2.1.5 Monitoring Instrumentation and Controls NEI 12-06, Section 3.2.1.1 0 provides information regarding instrumentation and controls necessary for the success of the coping strategies. NEI 12-06 provides the following guidance:
NEI 12-06 provides the following guidance:
The parameters selected must be able to demonstrate the success of the strategies at maintaining the key safety functions as well as indicate imminent or actual core damage to facilitate a decision to manage the response to the event within the Emergency Operating Procedures and FLEX Support Guidelines or within the SAMGs [Severe Accident Management Guidelines]. Typically these parameters would include the following:
The parameters selected must be able to demonstrate the success of the strategies at maintaining the key safety functions as well as indicate imminent or actual core damage to facilitate a decision to manage the response to the event within the Emergency Operating Procedures and FLEX Support Guidelines or within the SAMGs [Severe Accident Management Guidelines].
Typically these parameters would include the following:
* RPV Level RPV Pressure
* RPV Level RPV Pressure
* Containment Pressure Suppression Pool Level Suppression Pool Temperature
* Containment Pressure Suppression Pool Level Suppression Pool Temperature
* SFP Level The plant-specific evaluation may identify additional parameters that are needed in order to support key actions identified in the plant procedures/guidance, or to indicate imminent or actual core damage. On pages 15 and 16, in the section of the Integrated Plan discussing instrumentation credited Revision 1 Page 30 of 60 2014-02-15 for supporting the coping strategy to maintain core cooling during the initial phase, the licensee listed the following instruments:
* SFP Level The plant-specific evaluation may identify additional parameters that are needed in order to support key actions identified in the plant procedures/guidance, or to indicate imminent or actual core damage.
On pages 15 and 16, in the section of the Integrated Plan discussing instrumentation credited Revision 1                                 Page 30 of 60                             2014-02-15
 
for supporting the coping strategy to maintain core cooling during the initial phase, the licensee listed the following instruments:
Reactor Vessel Essential Instrumentation:
Reactor Vessel Essential Instrumentation:
* RPV Level
* RPV Level
Line 533: Line 572:
* Torus Temperature
* Torus Temperature
* Drywell Water Level
* Drywell Water Level
* Torus Water Level Spent Fuel Pool Essential Instrumentation:
* Torus Water Level Spent Fuel Pool Essential Instrumentation: SFP Level In addition, the licensee stated that JAF will have the following key instrument remain available following load stripping due to its power source: Condensate Storage Tank (CST) Level.
SFP Level In addition, the licensee stated that JAF will have the following key instrument remain available following load stripping due to its power source: Condensate Storage Tank (CST) Level. On page 25, in the section of the Integrated Plan discussing instrumentation credited for supporting the coping strategy to maintain containment during the initial phase, the licensee listed additional instrumentation as follows:
On page 25, in the section of the Integrated Plan discussing instrumentation credited for supporting the coping strategy to maintain containment during the initial phase, the licensee listed additional instrumentation as follows:
* RHV (Reliable Hardened Vent) System Radiation Monitor
* RHV (Reliable Hardened Vent) System Radiation Monitor
* RHV Valve Position Indication
* RHV Valve Position Indication
* RHV System Pressure
* RHV System Pressure
* RHV Effluent Temperature On page 15, in the section of the Integrated Plan discussing modifications to support coping strategies to maintain core cooling during the initial phase, the licensee stated that a modification will be implemented to change the power supply of ac-powered critical instrumentation (e.g., torus temperature, pressure and level, drywell temperature and pressure) to move it from the ac instrument bus to a station battery-backed source. This will provide continuous power to critical instruments so that critical containment parameters can be monitored throughout the event. During the audit process, the licensee further clarified that the power will be from the 125 volt de power system and the instrumentation will be available to the operators from time of ELAP initiation.
* RHV Effluent Temperature On page 15, in the section of the Integrated Plan discussing modifications to support coping strategies to maintain core cooling during the initial phase, the licensee stated that a modification will be implemented to change the power supply of ac-powered critical instrumentation (e.g., torus temperature, pressure and level, drywell temperature and pressure) to move it from the ac instrument bus to a station battery-backed source. This will provide continuous power to critical instruments so that critical containment parameters can be monitored throughout the event. During the audit process, the licensee further clarified that the power will be from the 125 volt de power system and the instrumentation will be available to the operators from time of ELAP initiation. Other critical instrumentation is powered from the 125 volt de power system and will be available without the need for a modification. Completion of the modification is identified as Confirmatory Item 3.2.1.5.A in Section 4.2.
Other critical instrumentation is powered from the 125 volt de power system and will be available without the need for a modification.
The licensee's approach described above, as currently understood, is consistent with the guidance found in NEI 12-06, as endorsed by JLD-ISG-2012-01, and subject to the successful closure of issues related to the Confirmatory Item, provides reasonable assurance that the requirements of Order EA-12-049 will be met with respect to monitoring instrumentation and controls if these requirements are implemented as described.
Completion of the modification is identified as Confirmatory Item 3.2.1.5.A in Section 4.2. The licensee's approach described above, as currently understood, is consistent with the guidance found in NEI 12-06, as endorsed by JLD-ISG-2012-01, and subject to the successful closure of issues related to the Confirmatory Item, provides reasonable assurance that the requirements of Order EA-12-049 will be met with respect to monitoring instrumentation and controls if these requirements are implemented as described.
3.2.1.6 Motive Power, Valve Controls and Motive Air System NEI 12-06, Section 12.1 provides guidance regarding the scope of equipment that will be Revision 1                                 Page 31 of 60                               2014-02-15
3.2.1.6 Motive Power, Valve Controls and Motive Air System NEI 12-06, Section 12.1 provides guidance regarding the scope of equipment that will be Revision 1 Page 31 of 60 2014-02-15 needed from off-site resources to support coping strategies.
 
NEI 12-06, Section 12.1 states that: And, Arrangements will need to be established by each site addressing the scope of equipment that will be required for the off-site phase, as well as the maintenance and delivery provisions for such equipment.
needed from off-site resources to support coping strategies. NEI 12-06, Section 12.1 states that:
Table 12-1 provides a sample list of the equipment expected to be provided to each site from off-site within 24 hours. The actual list will be specified by each site as part of the site-specific analysis.
Arrangements will need to be established by each site addressing the scope of equipment that will be required for the off-site phase, as well as the maintenance and delivery provisions for such equipment.
And, Table 12-1 provides a sample list of the equipment expected to be provided to each site from off-site within [[estimated NRC review hours::24 hours]]. The actual list will be specified by each site as part of the site-specific analysis.
Table 12-1 includes "Portable air compressor or nitrogen bottles & regulators (if required by plant strategy).
Table 12-1 includes "Portable air compressor or nitrogen bottles & regulators (if required by plant strategy).
On page 13, in the section of the Integrated Plan discussing coping strategies for maintaining core cooling during the initial phase, the licensee stated that the primary method of reactor pressure control is by operation of the safety/relief valves (SRVs). The licensee stated that all SRVs can be either automatically actuated by excess steam pressure or the valves can also be opened manually through remote switches and that the SRVs are equipped with nitrogen accumulators.
On page 13, in the section of the Integrated Plan discussing coping strategies for maintaining core cooling during the initial phase, the licensee stated that the primary method of reactor pressure control is by operation of the safety/relief valves (SRVs). The licensee stated that all SRVs can be either automatically actuated by excess steam pressure or the valves can also be opened manually through remote switches and that the SRVs are equipped with nitrogen accumulators. The licensee stated that in addition to the accumulators, a pneumatic supply system for the SRVs that are part of the automatic depressurization system (ADS) provides a reliable, safety-related, seismically qualified, 100-day supply following a design basis accident to enable long-term cooling. A FLEX air compressor is listed in the table on page 45 as equipment available for coping in Phase 2.
The licensee stated that in addition to the accumulators, a pneumatic supply system for the SRVs that are part of the automatic depressurization system (ADS) provides a reliable, safety-related, seismically qualified, 1 00-day supply following a design basis accident to enable long-term cooling.
On page 21 of the Integrated Plan, discussing coping strategies for maintaining core cooling during the Phase 3, the licensee stated that the reactor core cooling strategy is to place one loop of the residual heat removal (RHR) system into the shutdown cooling mode. This will be accomplished by powering up a Division I or II RHR pump from the Class 1E emergency bus utilizing a 4160 Vac FLEX portable diesel generator supplied by the RRC. Re-powering either bus can power an RHR pump that can provide flow to either RHR heat exchanger (HX). A modification will be implemented to provide a cross-connection between the fire protection system and one train of the residual heat removal service water (RHRSW) system. The seismically qualified diesel-driven fire pump will be used to provide lake water to the tube side of the appropriate RHR heat exchangers. The diesel-driven fire pump provides 2500 gallons per minute at a nominal discharge pressure of 125 psig. The licensee stated that the 4160 Vac RRC FLEX diesel generator will be capable of carrying approximately 2000 kW load which is sufficient to carry all of the loads on either of the two Class 1E 4160 Vac buses necessary to support the Phase 3 FLEX strategies which includes an RHR pump and its support equipment.
A FLEX air compressor is listed in the table on page 45 as equipment available for coping in Phase 2. On page 21 of the Integrated Plan, discussing coping strategies for maintaining core cooling during the Phase 3, the licensee stated that the reactor core cooling strategy is to place one loop of the residual heat removal (RHR) system into the shutdown cooling mode. This will be accomplished by powering up a Division I or II RHR pump from the Class 1 E emergency bus utilizing a 4160 Vac FLEX portable diesel generator supplied by the RRC. Re-powering either bus can power an RHR pump that can provide flow to either RHR heat exchanger (HX). A modification will be implemented to provide a cross-connection between the fire protection system and one train of the residual heat removal service water (RHRSW) system. The seismically qualified diesel-driven fire pump will be used to provide lake water to the tube side of the appropriate RHR heat exchangers.
On pages 26 and 28 of the Integrated Plan, discussing maintaining containment during Phases 2 and 3, the licensee stated that the primary strategy to maintain containment integrity utilizes the reliable hardened vent system (RHVS), which is permanently installed plant equipment. The RHVS is expected to rely on de power, which may require implementation of the FLEX strategies during Phase 2 to re-power a battery charger. The battery charger can be repowered by the 600 Vac FLEX diesel generator stored on site or during Phase 3 by the 4160 Vac diesel generator (DG) supplied by the RRC.
The diesel-driven fire pump provides 2500 gallons per minute at a nominal discharge pressure of 125 psig. The licensee stated that the 4160 Vac RRC FLEX diesel generator will be capable of carrying approximately 2000 kW load which is sufficient to carry all of the loads on either of the two Class 1 E 4160 Vac buses necessary to support the Phase 3 FLEX strategies which includes an RHR pump and its support equipment.
Revision 1                                   Page 32 of 60                               2014-02-15
On pages 26 and 28 of the Integrated Plan, discussing maintaining containment during Phases 2 and 3, the licensee stated that the primary strategy to maintain containment integrity utilizes the reliable hardened vent system (RHVS), which is permanently installed plant equipment.
 
The RHVS is expected to rely on de power, which may require implementation of the FLEX strategies during Phase 2 to re-power a battery charger.
On page 32 of the Integrated Plan, discussing maintaining SFP cooling during Phase 2, the licensee stated that the portable FLEX diesel driven pump taking suction from Lake Ontario will supply makeup water to the SFP. On page 36, the licensee stated that for Phase 3 the strategy for maintaining SFP cooling will be the same as in Phase 2.
The battery charger can be repowered by the 600 Vac FLEX diesel generator stored on site or during Phase 3 by the 4160 Vac diesel generator (DG) supplied by the RRC. Revision 1 Page 32 of 60 2014-02-15 On page 32 of the Integrated Plan, discussing maintaining SFP cooling during Phase 2, the licensee stated that the portable FLEX diesel driven pump taking suction from Lake Ontario will supply makeup water to the SFP. On page 36, the licensee stated that for Phase 3 the strategy for maintaining SFP cooling will be the same as in Phase 2. On page 45 of the Integrated Plan the licensee listed portable equipment required to provide motive power to support the coping strategies during Phase 2. The equipment includes diesel driven portable air compressors and diesel driven electric generators.
On page 45 of the Integrated Plan the licensee listed portable equipment required to provide motive power to support the coping strategies during Phase 2. The equipment includes diesel driven portable air compressors and diesel driven electric generators. On page 46 the licensee listed a diesel driven generator, supplied by the RRC, to provide motive power during Phase 3.
On page 46 the licensee listed a diesel driven generator, supplied by the RRC, to provide motive power during Phase 3. The licensee's approach described above, as currently understood, is consistent with the guidance found in NEI 12-06, as endorsed by JLD-ISG-2012-01, and provides reasonable assurance that the requirements of Order EA-12-049 will be met with respect to motive power, valve controls and motive air if these requirements are implemented as described.
The licensee's approach described above, as currently understood, is consistent with the guidance found in NEI 12-06, as endorsed by JLD-ISG-2012-01, and provides reasonable assurance that the requirements of Order EA-12-049 will be met with respect to motive power, valve controls and motive air if these requirements are implemented as described.
3.2.1. 7 Cold Shutdown and Refueling NEI12-06, Table 1-1, lists the coping strategy requirements as presented in Order EA-12-049. Item (4) of that list states: Licensee or CP holders must be capable of implementing the strategies in all modes. The NRC staff reviewed the licensee's Integrated Plan and determined that the Generic Concern related to shutdown and refueling guidelines is applicable to the plant. This Generic Concern has been resolved generically through the NRC's endorsement of NEI position paper entitled "Shutdown/Refueling Modes" (ADAMS Accession No. ML 13273A514);
3.2.1. 7   Cold Shutdown and Refueling NEI12-06, Table 1-1, lists the coping strategy requirements as presented in Order EA 049. Item (4) of that list states:
and has been endorsed by the NRC in a letter dated September 30, 2013 (ADAMS Accession No. ML 13267 A382). The position paper describes how licensees will, by procedure, maintain equipment available for deployment in shutdown and refueling modes. The NRC staff concluded that the position paper provides an acceptable approach for demonstrating that the licensees are capable of implementing mitigating strategies in all modes of operation.
Licensee or CP holders must be capable of implementing the strategies in all modes.
During the audit process, the licensee informed the NRC staff of its plans to abide by this generic resolution.
The NRC staff reviewed the licensee's Integrated Plan and determined that the Generic Concern related to shutdown and refueling guidelines is applicable to the plant. This Generic Concern has been resolved generically through the NRC's endorsement of NEI position paper entitled "Shutdown/Refueling Modes" (ADAMS Accession No. ML13273A514); and has been endorsed by the NRC in a letter dated September 30, 2013 (ADAMS Accession No. ML13267A382).
The NRC staff will evaluate the licensee's resulting program through the audit and inspection processes.
The position paper describes how licensees will, by procedure, maintain equipment available for deployment in shutdown and refueling modes. The NRC staff concluded that the position paper provides an acceptable approach for demonstrating that the licensees are capable of implementing mitigating strategies in all modes of operation. During the audit process, the licensee informed the NRC staff of its plans to abide by this generic resolution. The NRC staff will evaluate the licensee's resulting program through the audit and inspection processes.
The licensee's approach described above, as currently understood, is consistent with the guidance found in NEI 12-06, as endorsed by JLD-ISG-2012-01, and provides reasonable assurance that the requirements of Order EA-12-049 will be met with respect to the shutdown and refueling modes if these requirements are implemented as described.
The licensee's approach described above, as currently understood, is consistent with the guidance found in NEI 12-06, as endorsed by JLD-ISG-2012-01, and provides reasonable assurance that the requirements of Order EA-12-049 will be met with respect to the shutdown and refueling modes if these requirements are implemented as described.
3.2.1.8 Use of Portable Pumps NEI 12-06, Section 3.2.2, Guideline (13), states in part: Regardless of installed coping capability, all plants will include the ability to use portable pumps to provide RPV/RCS/SG makeup as a means to provide diverse capability beyond installed equipment.
3.2.1.8 Use of Portable Pumps NEI 12-06, Section 3.2.2, Guideline (13), states in part:
The use of portable pumps to provide RPV/RCS/SG makeup requires a transition and interaction with installed systems.
Regardless of installed coping capability, all plants will include the ability to use portable pumps to provide RPV/RCS/SG makeup as a means to provide diverse capability beyond installed equipment. The use of portable pumps to provide RPV/RCS/SG makeup requires a transition and interaction with installed systems. For example, transitioning from RCIC to a portable FLEX pump as the Revision 1                                 Page 33 of 60                                     2014-02-15
For example, transitioning from RCIC to a portable FLEX pump as the Revision 1 Page 33 of 60 2014-02-15 source for RPV makeup requires appropriate controls on the depressurization of the RPV and injection rates to avoid extended core uncovery.
 
Similarly, transition to a portable pump for SG makeup may require cooldown and depressurization of the SGs in advance of using the portable pump connections.
source for RPV makeup requires appropriate controls on the depressurization of the RPV and injection rates to avoid extended core uncovery. Similarly, transition to a portable pump for SG makeup may require cooldown and depressurization of the SGs in advance of using the portable pump connections.
Guidance should address both the proactive transition from installed equipment to portable and reactive transitions in the event installed equipment degrades or fails. Preparations for reactive use of portable equipment should not distract site resources from establishing the primary coping strategy.
Guidance should address both the proactive transition from installed equipment to portable and reactive transitions in the event installed equipment degrades or fails. Preparations for reactive use of portable equipment should not distract site resources from establishing the primary coping strategy. In some cases, in order to meet the time-sensitive required actions of the site-specific strategies, the FLEX equipment may need to be stored in its deployed position.
In some cases, in order to meet the time-sensitive required actions of the site-specific strategies, the FLEX equipment may need to be stored in its deployed position.
The fuel necessary to operate the FLEX equipment needs to be assessed in the plant specific analysis to ensure sufficient quantities are available as well as to address delivery capabilities.
The fuel necessary to operate the FLEX equipment needs to be assessed in the plant specific analysis to ensure sufficient quantities are available as well as to address delivery capabilities.
NEI 12-06 Section 11.2 states in part: Design requirements and supporting analysis should be developed for portable equipment that directly performs a FLEX mitigation strategy for core, containment, and SFP that provides the inputs, assumptions, and documented analysis that the mitigation strategy and support equipment will perform as intended.
NEI 12-06 Section 11.2 states in part:
On page 12 of the Integrated Plan in the section describing core cooling in Phase 1, the licensee stated that the existing installed RCIC pump will draw water from either the suppression pool or the CST and inject water into the reactor pressure vessel. Based on the initial volume in the CSTs (200,000 gallons),
Design requirements and supporting analysis should be developed for portable equipment that directly performs a FLEX mitigation strategy for core, containment, and SFP that provides the inputs, assumptions, and documented analysis that the mitigation strategy and support equipment will perform as intended.
in conjunction with the volume of water in the torus used during hours 1 through 5 of the event, this will enable RCIC to provide make-up for at least 35 hours without replenishment of the CSTs. On page 17 of the Integrated Plan in the section describing core cooling in Phase 2, the licensee stated that prior to the depletion of the CST, the flow path will be established from the existing seismically-qualified, diesel-driven fire pump to provide make up to the reactor pressure vessel. A pre-staged hose will be used to connect the fire protection system to the RHR service water (RHRSW) system. RHRSW system is then cross connected to the RHR system allowing makeup flow into the reactor pressure vessel. Also on page 1 of the Integrated Plan in the section describing core cooling in Phase 2, the licensee stated that a portable FLEX pump can be used to draw water from the intake bay and pump it through a temporary hose connected to the RHRSW system. The FLEX pump would be lowered through a hatch at El 255' of the screenwell and pump into a temporary hose to the RHRSW connection to provide make up to the reactor pressure vessel by cross connecting to the RHR system as described above. This portable FLEX pump can also be used to provide makeup water to the CST. Replenishment of the CST will be accomplished either through a new underground pipe or above ground through approximately 600' of hose. This same pump is also used to provide the make up to the spent fuel pool, which will be discussed below in the Maintain Spent Fuel Pool Cooling function.
On page 12 of the Integrated Plan in the section describing core cooling in Phase 1, the licensee stated that the existing installed RCIC pump will draw water from either the suppression pool or the CST and inject water into the reactor pressure vessel. Based on the initial volume in the CSTs (200,000 gallons), in conjunction with the volume of water in the torus used during hours 1 through 5 of the event, this will enable RCIC to provide make-up for at least [[estimated NRC review hours::35 hours]] without replenishment of the CSTs.
Four FLEX diesel driven pumps will be stored on site. Each pump is rated at 450 gpm at 400ft. head. The Integrated Plan described the use of FLEX pumps taking suction from the Lake Ontario, but did not address the impact of water quality on entrained debris potentially resulting in a Revision 1 Page 34 of 60 2014-02-15 restriction of coolant flow across the fuel assemblies to an extent that would inhibit adequate flow to the core. During the audit process, the licensee stated that FLEX support guidelines will contain guidance on prioritizing water sources from the most to least pure. The current strategy, as presented in the Integrated Plan, includes transitioning to shutdown cooling in Phase 3 for long term cooling thus reducing the need to supply water for RCS makeup. Long term cooling strategies, including the evaluation of raw water, will be finalized during the detailed design process.
On page 17 of the Integrated Plan in the section describing core cooling in Phase 2, the licensee stated that prior to the depletion of the CST, the flow path will be established from the existing seismically-qualified, diesel-driven fire pump to provide make up to the reactor pressure vessel. A pre-staged hose will be used to connect the fire protection system to the RHR service water (RHRSW) system. RHRSW system is then cross connected to the RHR system allowing makeup flow into the reactor pressure vessel.
This is identified as Confirmatory Item 3.2.1.8.A in Section 4.2. Fuel for the portable FLEX equipment is discussed in Section 3.2.4.9 of this report. The licensee's approach described above, as currently understood, is consistent with the guidance found in NEI 12-06, as endorsed by JLD-ISG-2012-01, and subject to the successful closure of issues related to the Confirmatory Item, provides reasonable assurance that the requirements of Order EA-12-049 will be met with respect to use of portable pumps if these requirements are implemented as described.
Also on page 1 of the Integrated Plan in the section describing core cooling in Phase 2, the licensee stated that a portable FLEX pump can be used to draw water from the intake bay and pump it through a temporary hose connected to the RHRSW system. The FLEX pump would be lowered through a hatch at El 255' of the screenwell and pump into a temporary hose to the RHRSW connection to provide make up to the reactor pressure vessel by cross connecting to the RHR system as described above. This portable FLEX pump can also be used to provide makeup water to the CST. Replenishment of the CST will be accomplished either through a new underground pipe or above ground through approximately 600' of hose. This same pump is also used to provide the make up to the spent fuel pool, which will be discussed below in the Maintain Spent Fuel Pool Cooling function. Four FLEX diesel driven pumps will be stored on site. Each pump is rated at 450 gpm at 400ft. head.
3.2.2 Spent Fuel Pool Cooling Strategies NEI 12-06, Table 3-1 and Appendix C summarize one acceptable approach for the SFP cooling strategies for BWRs. This approach uses a portable injection source to provide 1) makeup via hoses on the refuel deck/floor capable of exceeding the boil-off rate for the design basis heat load; 2) makeup via connection to SFP cooling piping or other alternate location capable of exceeding the boil-off rate for the design basis heat load; and alternatively  
The Integrated Plan described the use of FLEX pumps taking suction from the Lake Ontario, but did not address the impact of water quality on entrained debris potentially resulting in a Revision 1                                   Page 34 of 60                                 2014-02-15
: 3) spray via portable monitor nozzles from the refueling deck/floor capable of providing a minimum of 200 gallons per minute (gpm) per unit (250 gpm to account for overspray).
 
This approach will also provide a vent pathway for steam and condensate from the SFP. As described in NEI 12-06, Section 3.2.1. 7 and JLD-ISG-2012-01, Section 2.1, strategies that have a time constraint to be successful should be identified and a basis provided that the time can be reasonably met. NEI 12-06, Section 3 provides the performance attributes, general criteria, and baseline assumptions to be used in developing the technical basis for the time constraints.
restriction of coolant flow across the fuel assemblies to an extent that would inhibit adequate flow to the core. During the audit process, the licensee stated that FLEX support guidelines will contain guidance on prioritizing water sources from the most to least pure. The current strategy, as presented in the Integrated Plan, includes transitioning to shutdown cooling in Phase 3 for long term cooling thus reducing the need to supply water for RCS makeup. Long term cooling strategies, including the evaluation of raw water, will be finalized during the detailed design process. This is identified as Confirmatory Item 3.2.1.8.A in Section 4.2.
Since the event is a beyond-design-basis event, the analysis used to provide the technical basis for time constraints for the mitigation strategies may use nominal initial values (without uncertainties) for plant parameters, and best-estimate physics data. All equipment used for consequence mitigation may assume to operate at nominal setpoints and capacities.
Fuel for the portable FLEX equipment is discussed in Section 3.2.4.9 of this report.
The licensee's approach described above, as currently understood, is consistent with the guidance found in NEI 12-06, as endorsed by JLD-ISG-2012-01, and subject to the successful closure of issues related to the Confirmatory Item, provides reasonable assurance that the requirements of Order EA-12-049 will be met with respect to use of portable pumps if these requirements are implemented as described.
3.2.2   Spent Fuel Pool Cooling Strategies NEI 12-06, Table 3-1 and Appendix C summarize one acceptable approach for the SFP cooling strategies for BWRs. This approach uses a portable injection source to provide 1) makeup via hoses on the refuel deck/floor capable of exceeding the boil-off rate for the design basis heat load; 2) makeup via connection to SFP cooling piping or other alternate location capable of exceeding the boil-off rate for the design basis heat load; and alternatively 3) spray via portable monitor nozzles from the refueling deck/floor capable of providing a minimum of 200 gallons per minute (gpm) per unit (250 gpm to account for overspray). This approach will also provide a vent pathway for steam and condensate from the SFP.
As described in NEI 12-06, Section 3.2.1. 7 and JLD-ISG-2012-01, Section 2.1, strategies that have a time constraint to be successful should be identified and a basis provided that the time can be reasonably met. NEI 12-06, Section 3 provides the performance attributes, general criteria, and baseline assumptions to be used in developing the technical basis for the time constraints. Since the event is a beyond-design-basis event, the analysis used to provide the technical basis for time constraints for the mitigation strategies may use nominal initial values (without uncertainties) for plant parameters, and best-estimate physics data. All equipment used for consequence mitigation may assume to operate at nominal setpoints and capacities.
NEI 12-06, Section 3.2.1.2 describes the initial plant conditions for the at-power mode of operation; Section 3.2.1.3 describes the initial conditions; and Section 3.2.1.6 describes SFP conditions.
NEI 12-06, Section 3.2.1.2 describes the initial plant conditions for the at-power mode of operation; Section 3.2.1.3 describes the initial conditions; and Section 3.2.1.6 describes SFP conditions.
NEI 12-06, Section 3.2.1.1 provides the acceptance criterion for the analyses serving as the technical basis for establishing the time constraints for the baseline coping capabilities described in NEI 12-06, which provide an acceptable approach to meeting the requirements of EA-12-049 for maintaining SFP cooling.
NEI 12-06, Section 3.2.1.1 provides the acceptance criterion for the analyses serving as the technical basis for establishing the time constraints for the baseline coping capabilities described in NEI 12-06, which provide an acceptable approach to meeting the requirements of EA-12-049 for maintaining SFP cooling. This criterion is keeping the fuel in the SFP covered.
This criterion is keeping the fuel in the SFP covered.
NEI 12-06, Section 3.2.1.6 provides the initial boundary conditions for SFP cooling.
NEI 12-06, Section 3.2.1.6 provides the initial boundary conditions for SFP cooling.  
: 1. All boundaries of the SFP are intact, including the liner, gates, transfer canals, etc.
: 1. All boundaries of the SFP are intact, including the liner, gates, transfer canals, etc. 2. Although sloshing may occur during a seismic event, the initial loss of SFP inventory does not preclude access to the refueling deck around the pool. Revision 1 Page 35 of 60 2014-02-15
: 2. Although sloshing may occur during a seismic event, the initial loss of SFP inventory does not preclude access to the refueling deck around the pool.
: 3. SFP cooling system is intact, including attached piping. 4. SFP heat load assumes the maximum design basis heat load for the site. On page 30, in the section of the Integrated Plan discussing maintaining SFP cooling during the initial phase, the licensee stated that there are no Phase 1 actions required for more than 35 hours. Fuel in the SFP is cooled by the existing water inventory requirements of at least 21 feet-7 inches of water normally maintained over the top of the fuel. Using the design basis heat load, the SFP water inventory will heat up from an initial114 degrees Fahrenheit to 212 degrees Fahrenheit during the first 37.9 hours and there would be approximately 305 hours before any uncovering of the fuel would occur. These values consider the decay heat from a fresh reload batch in the pool upon startup from a 30-day refueling outage. SFP level monitoring is accomplished using the instrumentation installed per NRC Order EA-12-051. The licensee also stated that the maximum heat load situation in the pool could occur if a core was off-loaded into the pool. The time to boil in this scenario could be as little as 8.1 hours. Even with this time to boil the fuel is expected to be protected for a substantial amount of time: the time to uncover the fuel is 65 hours and the peak required make up rate is approximately 60 gpm. The licensee stated that this indicates there is time to deploy the planned FLEX equipment.
Revision 1                                   Page 35 of 60                               2014-02-15
The licensee stated that this scenario occurs during an outage at the plant and that more staffing resources would be available to implement the mitigation strategy (i.e., increased staffing is planned during outages to support the outage initiatives).
: 3. SFP cooling system is intact, including attached piping.
On pages 32 and 33, in the section of the Integrated Plan discussing maintaining SFP cooling during the transition phase, the licensee stated that the transition from Phase 1 to Phase 2 for SFP cooling function will occur at approximately 37 hours in the normal condition in which fuel has been transferred to the pool after a refueling.
: 4. SFP heat load assumes the maximum design basis heat load for the site.
SFP makeup connections can be established using portable FLEX equipment.
On page 30, in the section of the Integrated Plan discussing maintaining SFP cooling during the initial phase, the licensee stated that there are no Phase 1 actions required for more than [[estimated NRC review hours::35 hours]]. Fuel in the SFP is cooled by the existing water inventory requirements of at least 21 feet-7 inches of water normally maintained over the top of the fuel. Using the design basis heat load, the SFP water inventory will heat up from an initial114 degrees Fahrenheit to 212 degrees Fahrenheit during the first 37.[[estimated NRC review hours::9 hours]] and there would be approximately [[estimated NRC review hours::305 hours]] before any uncovering of the fuel would occur. These values consider the decay heat from a fresh reload batch in the pool upon startup from a 30-day refueling outage.
The FLEX pump used to provide the SFP makeup function is the same FLEX pump described in Section 3.2.1.8 in this report which provides make up to the reactor pressure vessel and the CST. Portable equipment (i.e., provisions for makeup to the SFP) is expected to be in place for utilization at approximately 24 hours. Makeup to the SFP will be provided by one of three baseline capabilities.
SFP level monitoring is accomplished using the instrumentation installed per NRC Order EA 051.
Method 1 -Makeup via permanent piping The first method uses an existing diesel driven fire pump taking suction from Lake Ontario aligned to the fire protection system header. A staged hose will be connected between the fire protection system and the RHRSW system. Flow can then be directed to the fuel pool cooling assist piping to the spent fuel pool cooling system. This provides make up flow to the SFP through seismically qualified piping to spargers located near the floor of the pool. The fire pump is capable of pumping 2500 gpm at 125 psig discharge pressure; the required flow rate for pool make up is less than 35 gpm. Method 2 -Makeup via hose The second method to provide water to the SFP utilizes the portable diesel driven FLEX pump. This pump will discharge into piping or hose and flow from the screen house around to near the truck bay of the reactor building, and up to the operating floor of the reactor building.
The licensee also stated that the maximum heat load situation in the pool could occur if a full-core was off- loaded into the pool. The time to boil in this scenario could be as little as 8.[[estimated NRC review hours::1 hours]]. Even with this time to boil the fuel is expected to be protected for a substantial amount of time: the time to uncover the fuel is [[estimated NRC review hours::65 hours]] and the peak required make up rate is approximately 60 gpm. The licensee stated that this indicates there is time to deploy the planned FLEX equipment. The licensee stated that this scenario occurs during an outage at the plant and that more staffing resources would be available to implement the mitigation strategy (i.e., increased staffing is planned during outages to support the outage initiatives).
At that point, a hose long enough to reach the SFP is connected to allow filling of the SFP utilizing lake water. Revision 1 Page 36 of 60 2014-02-15 Method 3 -Makeup via spray The third method is a flow path ending in spray nozzles at the pool. The third method of providing water to the SFP utilizes the diesel driven FLEX pump and flow path described in Method 2. The hose connection at the operating floor, however, is connected to two monitor spray nozzles rather than supplying make up directly into the pool. Two 100 gpm nozzles, which satisfy the JAF 10 CFR 50.54(hh)(2) commitment, are currently stored in the reactor building.
On pages 32 and 33, in the section of the Integrated Plan discussing maintaining SFP cooling during the transition phase, the licensee stated that the transition from Phase 1 to Phase 2 for SFP cooling function will occur at approximately [[estimated NRC review hours::37 hours]] in the normal condition in which fuel has been transferred to the pool after a refueling. SFP makeup connections can be established using portable FLEX equipment. The FLEX pump used to provide the SFP makeup function is the same FLEX pump described in Section 3.2.1.8 in this report which provides make up to the reactor pressure vessel and the CST. Portable equipment (i.e., provisions for makeup to the SFP) is expected to be in place for utilization at approximately [[estimated NRC review hours::24 hours]]. Makeup to the SFP will be provided by one of three baseline capabilities.
The FLEX pump will be capable of supplying 200 gpm to the refuel floor at a pressure sufficient for the spray nozzles.
Method 1 - Makeup via permanent piping The first method uses an existing diesel driven fire pump taking suction from Lake Ontario aligned to the fire protection system header. A staged hose will be connected between the fire protection system and the RHRSW system. Flow can then be directed to the fuel pool cooling assist piping to the spent fuel pool cooling system. This provides make up flow to the SFP through seismically qualified piping to spargers located near the floor of the pool. The fire pump is capable of pumping 2500 gpm at 125 psig discharge pressure; the required flow rate for pool make up is less than 35 gpm.
Method 2 - Makeup via hose The second method to provide water to the SFP utilizes the portable diesel driven FLEX pump.
This pump will discharge into piping or hose and flow from the screen house around to near the truck bay of the reactor building, and up to the operating floor of the reactor building. At that point, a hose long enough to reach the SFP is connected to allow filling of the SFP utilizing lake water.
Revision 1                                   Page 36 of 60                                 2014-02-15
 
Method 3 - Makeup via spray The third method is a flow path ending in spray nozzles at the pool. The third method of providing water to the SFP utilizes the diesel driven FLEX pump and flow path described in Method 2. The hose connection at the operating floor, however, is connected to two monitor spray nozzles rather than supplying make up directly into the pool. Two 100 gpm nozzles, which satisfy the JAF 10 CFR 50.54(hh)(2) commitment, are currently stored in the reactor building. The FLEX pump will be capable of supplying 200 gpm to the refuel floor at a pressure sufficient for the spray nozzles.
During the audit process, the licensee clarified that the method of cooling the spent fuel during Phase 3 will be to use the same means as in Phase 2 and that water to the SFP can be added indefinitely using the portable diesel driven FLEX pump. The licensee also clarified conformance to the NEI guidance that the spray flow rate be 250 gpm to account for overspray.
During the audit process, the licensee clarified that the method of cooling the spent fuel during Phase 3 will be to use the same means as in Phase 2 and that water to the SFP can be added indefinitely using the portable diesel driven FLEX pump. The licensee also clarified conformance to the NEI guidance that the spray flow rate be 250 gpm to account for overspray.
The licensee stated that during the detailed design, considerations will include nozzle locations, the spray angle, and pattern selected and the required flow rate to ensure that with any anticipated overshoot or undershoot of the SFP the required minimum of 200 gpm to the SFP is provided.
The licensee stated that during the detailed design, considerations will include nozzle locations, the spray angle, and pattern selected and the required flow rate to ensure that with any anticipated overshoot or undershoot of the SFP the required minimum of 200 gpm to the SFP is provided.
On page 40, in the section of the Integrated Plan discussing the SFP area ventilation during the transition phase, the licensee stated that a vent pathway for steam and condensate from the SFP can be established by opening the truck bay doors (at grade elevation) and opening the airlock on El. 369'-6" to the outside of the reactor building.
On page 40, in the section of the Integrated Plan discussing the SFP area ventilation during the transition phase, the licensee stated that a vent pathway for steam and condensate from the SFP can be established by opening the truck bay doors (at grade elevation) and opening the airlock on El. 369'-6" to the outside of the reactor building. The SBO/FLEX strategy is to establish this ventilation flow path early in the event response period, e.g., before the pool begins to boil, or prior to about [[estimated NRC review hours::37 hours]]. Ventilation can be enhanced by re-powering a standby gas treatment system (SGTS) fan. A modification to provide new connection points for a portable diesel generator unit to re-power a SGTS fan will be considered. A FLEX 600 Vac, 200 kW DG will be connected as conditions warrant. A 200 kW, 600Vac FLEX DG can power a SGTS fan and its valve.
The SBO/FLEX strategy is to establish this ventilation flow path early in the event response period, e.g., before the pool begins to boil, or prior to about 37 hours. Ventilation can be enhanced by re-powering a standby gas treatment system (SGTS) fan. A modification to provide new connection points for a portable diesel generator unit to re-power a SGTS fan will be considered.
During the audit process, the licensee clarified that there are several potential locations to establish a vent path to accommodate boiling in the SFP. The method of ventilation, including any power requirements, for the SFP will be addressed in the detailed design phase. This is identified as Confirmatory Item 3.2.2.A in Section 4.2.
A FLEX 600 Vac, 200 kW DG will be connected as conditions warrant.
The licensee's approach described above, as currently understood, is consistent with the guidance found in NEI 12-06, as endorsed by JLD-ISG-2012-01, and subject to the successful closure of issues related to the Confirmatory Item, provides reasonable assurance that the requirements of Order EA-12-049 will be met with respect to SFP cooling if these requirements are implemented as described.
A 200 kW, 600Vac FLEX DG can power a SGTS fan and its valve. During the audit process, the licensee clarified that there are several potential locations to establish a vent path to accommodate boiling in the SFP. The method of ventilation, including any power requirements, for the SFP will be addressed in the detailed design phase. This is identified as Confirmatory Item 3.2.2.A in Section 4.2. The licensee's approach described above, as currently understood, is consistent with the guidance found in NEI 12-06, as endorsed by JLD-ISG-2012-01, and subject to the successful closure of issues related to the Confirmatory Item, provides reasonable assurance that the requirements of Order EA-12-049 will be met with respect to SFP cooling if these requirements are implemented as described.
3.2.3   Containment Functions Strategies NE112-06, Table 3-1 and Appendix C provide a description of the safety functions and performance attributes for BWR containments which are to be maintained during an ELAP as defined by Order EA-12-049. The safety function applicable to a BWR with a Mark I containment listed in Table 3-1 is Containment Pressure Control/Heat Removal, and the method cited for accomplishing this safety function is Containment Venting or Alternative Containment Heat Removal. Furthermore, the performance attributes listed in Table C-2 denote the containment's function is to provide a reliable means to assure containment heat removal. JLD-ISG-2012-01, Section 5.1 is aligned with this position stating, in part, that the goal of this Revision 1                                   Page 37 of 60                               2014-02-15
3.2.3 Containment Functions Strategies NE112-06, Table 3-1 and Appendix C provide a description of the safety functions and performance attributes for BWR containments which are to be maintained during an ELAP as defined by Order EA-12-049.
 
The safety function applicable to a BWR with a Mark I containment listed in Table 3-1 is Containment Pressure Control/Heat  
strategy is to relieve pressure from the containment.
: Removal, and the method cited for accomplishing this safety function is Containment Venting or Alternative Containment Heat Removal.
On page 24, in the section of the Integrated Plan discussing maintaining containment integrity during the initial phase, the licensee stated that during Phase 1, containment integrity is maintained using the normal installed design features of the containment such as the containment isolation valves and the RHVS. In accordance with NEI 12-06, the containment is assumed to be isolated following the event. As the torus heats up and the water begins to boil, the containment will begin to heat up and pressurize. Additionally, the water level in the torus rises due to the transfer of inventory from the CST to the torus (via RCIC and SRVs). According to the JAF site specific event response analysis, the limiting containment parameter will be the torus design pressure. The licensee stated that the rise in drywell pressure can be reversed before the design pressure limit is reached. This is accomplished by venting the containment.
Furthermore, the performance attributes listed in Table C-2 denote the containment's function is to provide a reliable means to assure containment heat removal. ISG-2012-01, Section 5.1 is aligned with this position  
The licensee further stated that the containment design pressure is 56 psig. The event response analysis assumed that the containment is vented at about [[estimated NRC review hours::23 hours]] into the event.
: stating, in part, that the goal of this Revision 1 Page 37 of 60 2014-02-15 strategy is to relieve pressure from the containment.
This timing was derived from the timing of the containment response of the drywell pressure approaching the design pressure; this venting assumption was made to ensure that the containment pressure limit is not challenged. During the audit process, the licensee stated that the decision to vent will be based on the installed torus pressure instrumentation. The torus pressure instrumentation, as discussed in section 3.2.1.5 of this report, is identified as containment essential instrumentation and will be available throughout the ELAP event.
On page 24, in the section of the Integrated Plan discussing maintaining containment integrity during the initial phase, the licensee stated that during Phase 1, containment integrity is maintained using the normal installed design features of the containment such as the containment isolation valves and the RHVS. In accordance with NEI 12-06, the containment is assumed to be isolated following the event. As the torus heats up and the water begins to boil, the containment will begin to heat up and pressurize.
On page 6 of the Integrated Plan, the licensee stated that the venting action will be accomplished in accordance with EOPs to maintain containment parameters within acceptable limits and within the limits that support continued use of the RCIC system. The operators will open the wetwell vent and the RHVS to relieve pressure conditions in the wetwell/drywell.
Additionally, the water level in the torus rises due to the transfer of inventory from the CST to the torus (via RCIC and SRVs). According to the JAF site specific event response  
Operation of RHVS is performed from the relay room and can be accomplished because the RHVS is seismically rugged, de-powered (backed by batteries), and provided with adequate nitrogen from the containment atmospheric dilution (CAD) system, backed up by portable gas bottles for the ELAP event. Critical instruments associated with containment and the RHVS are de-powered and can be read in the relay room.
: analysis, the limiting containment parameter will be the torus design pressure.
After opening the containment vent system, the non-condensable atmosphere will be removed which makes the containment considerably more vulnerable to overcooling/negative pressure transients and vacuum breaker actuation. This may ultimately result in the loss of inert conditions when air enters the containment to replace the volume vacated by steam condensing out of drywall atmosphere. During the audit process, the licensee addressed the effects of overcooling/negative pressure transients by stating that it is not a concern early in the event.
The licensee stated that the rise in drywell pressure can be reversed before the design pressure limit is reached.
The licensee additionally stated that the strategy does not utilize drywell or torus sprays; it utilizes containment venting. The evaluation of the effect of overcooling/negative pressure transients during the later stages of the event will be performed during the final design I procedure development process. The licensee stated that Entergy will be following the industry's early venting position paper.
This is accomplished by venting the containment.
On pages 26 and 28, in the section of the Integrated Plan discussing maintaining containment integrity during the transition and the final phases, the licensee stated that the primary strategy to maintain containment integrity utilizes only permanently installed plant equipment (i.e.,
The licensee further stated that the containment design pressure is 56 psig. The event response analysis assumed that the containment is vented at about 23 hours into the event. This timing was derived from the timing of the containment response of the drywell pressure approaching the design pressure; this venting assumption was made to ensure that the containment pressure limit is not challenged.
RHVS) as described for Phase 1. The RHVS is expected to rely on de power, which may require implementation of the FLEX strategies to re-power a battery charger.
During the audit process, the licensee stated that the decision to vent will be based on the installed torus pressure instrumentation.
In an endorsement letter dated January 9, 2014 (ADAMS Accession No. ML13358A206), the NRC staff concluded that the changes to the BWR venting strategy, as described in the Revision 1                                   Page 38 of 60                               2014-02-15
The torus pressure instrumentation, as discussed in section 3.2.1.5 of this report, is identified as containment essential instrumentation and will be available throughout the ELAP event. On page 6 of the Integrated Plan, the licensee stated that the venting action will be accomplished in accordance with EOPs to maintain containment parameters within acceptable limits and within the limits that support continued use of the RCIC system. The operators will open the wetwell vent and the RHVS to relieve pressure conditions in the wetwell/drywell.
 
Operation of RHVS is performed from the relay room and can be accomplished because the RHVS is seismically rugged, de-powered (backed by batteries),
November 21, 2013, position paper submitted by NEI on behalf of the Boiling Water Reactor Owners Group (BWROG), are acceptable, subject to each licensee addressing the plant-specific implementation of the guidance. The letter stated, The NRC staff agrees that the changes to the containment venting strategies as described in the BWROG information report are acceptable for use as part of strategies proposed in response to Order EA-12-049, provided that licensee implementation is in compliance with normal change processes for plant emergency procedures and provided that plant-specific evaluations support the use of the revised strategies. The BWROG paper addresses the venting strategy on a generic basis, but plant-specific implementation relies on such items as the capabilities of the installed vent path, net positive suction head for the reactor coolant system injection pumps, and guidance to prevent negative pressure in containment. The NRC staff will evaluate a licensee's application of containment venting strategies in its development of the final Safety Evaluation documenting compliance with NRC Order EA-12-049.
and provided with adequate nitrogen from the containment atmospheric dilution (CAD) system, backed up by portable gas bottles for the ELAP event. Critical instruments associated with containment and the RHVS are de-powered and can be read in the relay room. After opening the containment vent system, the non-condensable atmosphere will be removed which makes the containment considerably more vulnerable to overcooling/negative pressure transients and vacuum breaker actuation.
With regard to maintaining containment, the implementation of Boiling Water Reactor Owners Group (BWROG) Emergency Procedure Guideline (EPG)/Severe Accident Guideline (SAG),
This may ultimately result in the loss of inert conditions when air enters the containment to replace the volume vacated by steam condensing out of drywall atmosphere.
Revision 3, including any associated plant-specific evaluations, must be completed in accordance with the provisions of NRC letter dated January 9, 2014. This is identified as Open Item 3.2.3.A in Section 4.1.
During the audit process, the licensee addressed the effects of overcooling/negative pressure transients by stating that it is not a concern early in the event. The licensee additionally stated that the strategy does not utilize drywell or torus sprays; it utilizes containment venting.
A hardened containment vent system is currently installed at JAF but will be enhanced in accordance with NRC Order EA-13-109 on BWR containment vents. In the first six-month status report updating JAF's Integrated Plan, the licensee stated that JAF will implement requirements of Phase 1 of Order EA-13-109 and that Phase 1 of Order EA-13-109 currently requires implementation in 2016 at JAF.
The evaluation of the effect of overcooling/negative pressure transients during the later stages of the event will be performed during the final design I procedure development process.
The licensee's approach described above, as currently understood, is consistent with the guidance found in NEI 12-06, as endorsed by JLD-ISG-2012-01, and subject to the successful closure of issues related to the Open Item, provides reasonable assurance that the requirements of Order EA-12-049 will be met with respect to containment function strategies if these requirements are implemented as described.
The licensee stated that Entergy will be following the industry's early venting position paper. On pages 26 and 28, in the section of the Integrated Plan discussing maintaining containment integrity during the transition and the final phases, the licensee stated that the primary strategy to maintain containment integrity utilizes only permanently installed plant equipment (i.e., RHVS) as described for Phase 1. The RHVS is expected to rely on de power, which may require implementation of the FLEX strategies to re-power a battery charger.
3.2.4   Support Functions 3.2.4.1 Equipment Cooling - Cooling Water NEI 12-06, Section 3.2.2, Guideline (3) states:
In an endorsement letter dated January 9, 2014 (ADAMS Accession No. ML 13358A206),
Plant procedures/guidance should specify actions necessary to assure that equipment functionality can be maintained (including support systems or alternate method) in an ELAPILUHS or can perform without ac power or normal access to the UHS.
the NRC staff concluded that the changes to the BWR venting strategy, as described in the Revision 1 Page 38 of 60 2014-02-15 November 21, 2013, position paper submitted by NEI on behalf of the Boiling Water Reactor Owners Group (BWROG),
Cooling functions provided by such systems as auxiliary building cooling water, service water, or component cooling water may normally be used in order for equipment to perform their function. It may be necessary to provide an alternate means for support systems that require ac power or normal access to the UHS, Revision 1                                 Page 39 of 60                               2014-02-15
are acceptable, subject to each licensee addressing the specific implementation of the guidance.
 
The letter stated, The NRC staff agrees that the changes to the containment venting strategies as described in the BWROG information report are acceptable for use as part of strategies proposed in response to Order EA-12-049, provided that licensee implementation is in compliance with normal change processes for plant emergency procedures and provided that plant-specific evaluations support the use of the revised strategies.
or provide a technical justification for continued functionality without the support system.
The BWROG paper addresses the venting strategy on a generic basis, but plant-specific implementation relies on such items as the capabilities of the installed vent path, net positive suction head for the reactor coolant system injection pumps, and guidance to prevent negative pressure in containment.
The licensee made no reference in the Integrated Plan regarding the need for, or use of, additional cooling systems necessary to assure that coping strategy functionality can be maintained. Nonetheless, the only coping strategy equipment identified in the Integrated Plan that would require some form of cooling are portable diesel powered pumps and generators.
The NRC staff will evaluate a licensee's application of containment venting strategies in its development of the final Safety Evaluation documenting compliance with NRC Order EA-12-049. With regard to maintaining containment, the implementation of Boiling Water Reactor Owners Group (BWROG) Emergency Procedure Guideline (EPG)/Severe Accident Guideline (SAG), Revision 3, including any associated plant-specific evaluations, must be completed in accordance with the provisions of NRC letter dated January 9, 2014. This is identified as Open Item 3.2.3.A in Section 4.1. A hardened containment vent system is currently installed at JAF but will be enhanced in accordance with NRC Order EA-13-109 on BWR containment vents. In the first six-month status report updating JAF's Integrated Plan, the licensee stated that JAF will implement requirements of Phase 1 of Order EA-13-109 and that Phase 1 of Order EA-13-109 currently requires implementation in 2016 at JAF. The licensee's approach described above, as currently understood, is consistent with the guidance found in NEI 12-06, as endorsed by JLD-ISG-2012-01, and subject to the successful closure of issues related to the Open Item, provides reasonable assurance that the requirements of Order EA-12-049 will be met with respect to containment function strategies if these requirements are implemented as described.
These self-contained commercially available units would not be expected to require an external cooling system nor would they require ac power or normal access to the UHS.
3.2.4 Support Functions 3.2.4.1 Equipment Cooling -Cooling Water NEI 12-06, Section 3.2.2, Guideline (3) states: Plant procedures/guidance should specify actions necessary to assure that equipment functionality can be maintained (including support systems or alternate method) in an ELAPILUHS or can perform without ac power or normal access to the UHS. Cooling functions provided by such systems as auxiliary building cooling water, service water, or component cooling water may normally be used in order for equipment to perform their function.
The licensee's approach described above, as currently understood, is consistent with the guidance found in NEI 12-06, as endorsed by JLD-ISG-2012-01, and provides reasonable assurance that the requirements of Order EA-12-049 will be met with respect to equipment cooling if these requirements are implemented as described.
It may be necessary to provide an alternate means for support systems that require ac power or normal access to the UHS, Revision 1 Page 39 of 60 2014-02-15 or provide a technical justification for continued functionality without the support system. The licensee made no reference in the Integrated Plan regarding the need for, or use of, additional cooling systems necessary to assure that coping strategy functionality can be maintained.
3.2.4.2 Ventilation - Equipment Cooling NEI 12-06, Section 3.2.2, Guideline (1 0) states:
Nonetheless, the only coping strategy equipment identified in the Integrated Plan that would require some form of cooling are portable diesel powered pumps and generators.
Plant procedures/guidance should consider Joss of ventilation effects on specific energized equipment necessary for shutdown (e.g., those containing internal electrical power supplies or other local heat sources that may be energized or present in an ELAP.
These self-contained commercially available units would not be expected to require an external cooling system nor would they require ac power or normal access to the UHS. The licensee's approach described above, as currently understood, is consistent with the guidance found in NEI 12-06, as endorsed by JLD-ISG-2012-01, and provides reasonable assurance that the requirements of Order EA-12-049 will be met with respect to equipment cooling if these requirements are implemented as described.
ELAP procedures/guidance should identify specific actions to be taken to ensure that equipment failure does not occur as a result of a loss of forced ventilation/cooling. Actions should be tied to either the ELAP/LUHS or upon reaching certain temperatures in the plant. Plant areas requiring additional air flow are likely to be locations containing shutdown instrumentation and power supplies, turbine-driven decay heat removal equipment, and in the vicinity of the inverters. These areas include: steam driven [auxiliary feedwater] AFW pump room, HPCI and RCIC pump rooms, the control room, and logic cabinets. Air flow may be accomplished by opening doors to rooms and electronic and relay cabinets, and/or providing supplemental air flow.
3.2.4.2 Ventilation  
Air temperatures may be monitored during an ELAP/LUHS event through operator observation, portable instrumentation, or the use of locally mounted thermometers inside cabinets and in plant areas where cooling may be needed.
-Equipment Cooling NEI 12-06, Section 3.2.2, Guideline (1 0) states: Plant procedures/guidance should consider Joss of ventilation effects on specific energized equipment necessary for shutdown (e.g., those containing internal electrical power supplies or other local heat sources that may be energized or present in an ELAP. ELAP procedures/guidance should identify specific actions to be taken to ensure that equipment failure does not occur as a result of a loss of forced ventilation/cooling.
Alternatively, procedures/guidance may direct the operator to take action to provide for alternate air flow in the event normal cooling is lost. Upon loss of these systems, or indication of temperatures outside the maximum normal range of values, the procedures/guidance should direct supplemental air flow be provided to the affected cabinet or area, and/or designate alternate means for monitoring system functions.
Actions should be tied to either the ELAP/LUHS or upon reaching certain temperatures in the plant. Plant areas requiring additional air flow are likely to be locations containing shutdown instrumentation and power supplies, turbine-driven decay heat removal equipment, and in the vicinity of the inverters.
For the limited cooling requirements of a cabinet containing power supplies for instrumentation, simply opening the back doors is effective. For larger cooling loads, such as HPCI, RCIC, and AFW pump rooms, portable engine-driven blowers may be considered during the transient to augment the natural circulation provided by opening doors. The necessary rate of air supply to these rooms may be estimated on the basis of rapidly turning over the room's air Revision 1                                   Page 40 of 60                               2014-02-15
These areas include:
 
steam driven [auxiliary feedwater]
volume.
AFW pump room, HPCI and RCIC pump rooms, the control room, and logic cabinets.
Temperatures in the HPCI pump room and/or steam tunnel for a BWR may reach levels which isolate HPCI or RCIC steam lines. Supplemental air flow or the capability to override the isolation feature may be necessary at some plants. The procedures/guidance should identify the corrective action required, if necessary.
Air flow may be accomplished by opening doors to rooms and electronic and relay cabinets, and/or providing supplemental air flow. Air temperatures may be monitored during an ELAP/LUHS event through operator observation, portable instrumentation, or the use of locally mounted thermometers inside cabinets and in plant areas where cooling may be needed. Alternatively, procedures/guidance may direct the operator to take action to provide for alternate air flow in the event normal cooling is lost. Upon loss of these systems, or indication of temperatures outside the maximum normal range of values, the procedures/guidance should direct supplemental air flow be provided to the affected cabinet or area, and/or designate alternate means for monitoring system functions.
Actuation set points for fire protection systems are typically at 165-180°F. It is expected that temperature rises due to loss of ventilation/cooling during an ELAP/LUHS will not be sufficiently high to initiate actuation of fire protection systems. If lower fire protection system setpoints are used or temperatures are expected to exceed these temperatures during an ELAP/LUHS, procedures/guidance should identify actions to avoid such inadvertent actuations or the plant should ensure that actuation does not impact long term operation of the equipment.
For the limited cooling requirements of a cabinet containing power supplies for instrumentation, simply opening the back doors is effective.
In the Integrated Plan the licensee discussed the ventilation and cooling requirements for plant areas during the ELAP event. The applicable areas of interest are discussed below.
For larger cooling loads, such as HPCI, RCIC, and AFW pump rooms, portable engine-driven blowers may be considered during the transient to augment the natural circulation provided by opening doors. The necessary rate of air supply to these rooms may be estimated on the basis of rapidly turning over the room's air Revision 1 Page 40 of 60 2014-02-15 volume. Temperatures in the HPCI pump room and/or steam tunnel for a BWR may reach levels which isolate HPCI or RCIC steam lines. Supplemental air flow or the capability to override the isolation feature may be necessary at some plants. The procedures/guidance should identify the corrective action required, if necessary.
Main Control Room (MCR)
Actuation set points for fire protection systems are typically at 165-180°F.
On page 37, in the section of the Integrated Plan discussing main control room habitability during the initial phase, the licensee stated that under ELAP conditions with only simple mitigating actions taken, an analysis projects the temperature in the control room will not exceed 105 degrees Fahrenheit considering a loss of ventilation for three days. This is below the assumed maximum temperature for efficient human performance (11 0 degrees Fahrenheit) as described in NUMARC 87-00, "Guidelines and Technical Bases for NUMARC Initiatives Addressing Station Blackout at Light Water Reactors," Revision 1. The calculation credited heat escaping through a damper in the floor of the kitchen. The Phase 1 FLEX strategy is to confirm the damper is open as well as to block open the entrance air lock when the MCR temperature reaches about 90 degrees Fahrenheit. Additionally, plant procedures require opening all MCR panel doors in the control room within 30 minutes of the beginning of an SBO to minimize heatup of the components contained in the MCR panels. The licensee stated that during Phase 2, portable fans powered from portable FLEX diesel generators will be provided to improve the heat removal from the MCR and maintain temperatures below 104 degrees Fahrenheit for personnel accessibility and equipment availability. The licensee stated that during the final phase, the strategies for cooling the MCR are the same as for Phase 2. However, the power for the MCR chillers and air-handling units may be powered from the 4160 Vac emergency bus if the bus is re-energized by the RRC FLEX 4160 Vac DG.
It is expected that temperature rises due to loss of ventilation/cooling during an ELAP/LUHS will not be sufficiently high to initiate actuation of fire protection systems.
RCIC Room On pages 37, in the section of the Integrated Plan discussing RCIC room accessibility during the initial phase, the licensee stated that the RCIC room will have a large heat load under ELAP conditions, as the steam-driven RCIC pump is utilized during the event as the primary source of core cooling. Current analysis demonstrates that the RCIC room remains at acceptable levels for the four-hour SBO scenario. A preliminary evaluation of the room temperature response for the FLEX scenario indicates the room temperature will be elevated. The strategy for the RCIC room is to ensure room doors are open or utilize portable fans to ventilate the area. The licensee stated that JAF does not anticipate that continuous accessibility would be required in the RCIC room. If personnel entry is required into the RCIC room, then supplemental ventilation Revision 1                                   Page 41 of 60                               2014-02-15
If lower fire protection system setpoints are used or temperatures are expected to exceed these temperatures during an ELAP/LUHS, procedures/guidance should identify actions to avoid such inadvertent actuations or the plant should ensure that actuation does not impact long term operation of the equipment.
 
In the Integrated Plan the licensee discussed the ventilation and cooling requirements for plant areas during the ELAP event. The applicable areas of interest are discussed below. Main Control Room (MCR) On page 37, in the section of the Integrated Plan discussing main control room habitability during the initial phase, the licensee stated that under ELAP conditions with only simple mitigating actions taken, an analysis projects the temperature in the control room will not exceed 105 degrees Fahrenheit considering a loss of ventilation for three days. This is below the assumed maximum temperature for efficient human performance (11 0 degrees Fahrenheit) as described in NUMARC 87-00, "Guidelines and Technical Bases for NUMARC Initiatives Addressing Station Blackout at Light Water Reactors,"
and personnel protective measures (such as ice vests) will be taken. The licensee stated that during the transition phase, the primary strategy for maintaining the environment of the RCIC room will use the same strategy as in the Phase 1. Further evaluation of RCIC room temperature will be performed to confirm an acceptable environment is maintained. This is identified as Confirmatory Item 3.2.4.2.A in Section 4.2.
Revision  
Battery Room On page 39 in the section of the Integrated Plan discussing battery room ventilation during the transition phase, the licensee stated that hydrogen generation rate during charging is such that the hydrogen concentration in the room does not reach 2% for more than 5 days and that this is well into the Phase 3 deployment period. The licensee stated that battery room ventilation is not a concern for the general Phase 2 strategy period of from [[estimated NRC review hours::8 hours]] to [[estimated NRC review hours::72 hours]].
: 1. The calculation credited heat escaping through a damper in the floor of the kitchen.
On page 43, in the section of the Integrated Plan discussing battery room ventilation during the final phase, the licensee stated that while the rate of hydrogen generation at JAF does not result in hydrogen concentrations of greater 2% for more than five days, the rooms will have to be ventilated during Phase 3. There are two strategies for venting the battery rooms. The primary strategy is to repower the existing battery room exhaust fans. The licensee stated that this could occur after the FLEX DG has been connected to power the Class 1E 600 volt bus, but will more likely not be performed until the larger portable diesel generators are delivered from the RRC. The licensee stated that the second option is to prop open doors and set up portable fans that will exhaust into an adjacent corridor that communicates with a roll up door to the outside.
The Phase 1 FLEX strategy is to confirm the damper is open as well as to block open the entrance air lock when the MCR temperature reaches about 90 degrees Fahrenheit.
Additionally, plant procedures require opening all MCR panel doors in the control room within 30 minutes of the beginning of an SBO to minimize heatup of the components contained in the MCR panels. The licensee stated that during Phase 2, portable fans powered from portable FLEX diesel generators will be provided to improve the heat removal from the MCR and maintain temperatures below 104 degrees Fahrenheit for personnel accessibility and equipment availability.
The licensee stated that during the final phase, the strategies for cooling the MCR are the same as for Phase 2. However, the power for the MCR chillers and air-handling units may be powered from the 4160 Vac emergency bus if the bus is re-energized by the RRC FLEX 4160 Vac DG. RCIC Room On pages 37, in the section of the Integrated Plan discussing RCIC room accessibility during the initial phase, the licensee stated that the RCIC room will have a large heat load under ELAP conditions, as the steam-driven RCIC pump is utilized during the event as the primary source of core cooling.
Current analysis demonstrates that the RCIC room remains at acceptable levels for the four-hour SBO scenario.
A preliminary evaluation of the room temperature response for the FLEX scenario indicates the room temperature will be elevated.
The strategy for the RCIC room is to ensure room doors are open or utilize portable fans to ventilate the area. The licensee stated that JAF does not anticipate that continuous accessibility would be required in the RCIC room. If personnel entry is required into the RCIC room, then supplemental ventilation Revision 1 Page 41 of 60 2014-02-15 and personnel protective measures (such as ice vests) will be taken. The licensee stated that during the transition phase, the primary strategy for maintaining the environment of the RCIC room will use the same strategy as in the Phase 1. Further evaluation of RCIC room temperature will be performed to confirm an acceptable environment is maintained.
This is identified as Confirmatory Item 3.2.4.2.A in Section 4.2. Battery Room On page 39 in the section of the Integrated Plan discussing battery room ventilation during the transition phase, the licensee stated that hydrogen generation rate during charging is such that the hydrogen concentration in the room does not reach 2% for more than 5 days and that this is well into the Phase 3 deployment period. The licensee stated that battery room ventilation is not a concern for the general Phase 2 strategy period of from 8 hours to 72 hours. On page 43, in the section of the Integrated Plan discussing battery room ventilation during the final phase, the licensee stated that while the rate of hydrogen generation at JAF does not result in hydrogen concentrations of greater 2% for more than five days, the rooms will have to be ventilated during Phase 3. There are two strategies for venting the battery rooms. The primary strategy is to repower the existing battery room exhaust fans. The licensee stated that this could occur after the FLEX DG has been connected to power the Class 1 E 600 volt bus, but will more likely not be performed until the larger portable diesel generators are delivered from the RRC. The licensee stated that the second option is to prop open doors and set up portable fans that will exhaust into an adjacent corridor that communicates with a roll up door to the outside.
The Integrated Plan did not address the room temperature effects on battery performance.
The Integrated Plan did not address the room temperature effects on battery performance.
During the audit process the licensee stated that charging batteries during high room temperatures may require additional forced air flow during Phase 2 and 3. The licensee stated that additional calculations will be developed.
During the audit process the licensee stated that charging batteries during high room temperatures may require additional forced air flow during Phase 2 and 3. The licensee stated that additional calculations will be developed. This is identified as Confirmatory Item 3.2.4.2.8 in Section 4.2.
This is identified as Confirmatory Item 3.2.4.2.8 in Section 4.2. During the audit process, the licensee further stated that during cold weather the electrolyte in the cells is not expected to drop to a limiting temperature due to the battery room's interior location within the plant. The licensee stated that it is reasonable to assume that the room will remain near its pre-event temperature during the relatively short period of time until the FLEX generators are deployed and have energized the battery chargers.
During the audit process, the licensee further stated that during cold weather the electrolyte in the cells is not expected to drop to a limiting temperature due to the battery room's interior location within the plant. The licensee stated that it is reasonable to assume that the room will remain near its pre-event temperature during the relatively short period of time until the FLEX generators are deployed and have energized the battery chargers. Additional details on adequacy of battery room ventilation for extreme temperature protection will be available later in the design/procedure development process. This is combined with Confirmatory Item 3.2.4.2.8 above.
Additional details on adequacy of battery room ventilation for extreme temperature protection will be available later in the design/procedure development process.
DC Equipment Room On page 39, in the section of the Integrated Plan discussing de equipment room ventilation during the transition phase, the licensee stated that the de equipment rooms contain the battery chargers which are energized in Phase 2 to recharge the batteries. The method to ventilate the de equipment rooms is to prop open doors and set up portable fans that will exhaust into an adjacent corridor that communicates with a roll up door to the outside. During the audit process, the licensee stated that detail design to determine the required ventilation flow or the size of the portable fans has not been determined. This is identified as Confirmatory Item 3.2.4.2.C in Section 4.2.
This is combined with Confirmatory Item 3.2.4.2.8 above. DC Equipment Room On page 39, in the section of the Integrated Plan discussing de equipment room ventilation during the transition phase, the licensee stated that the de equipment rooms contain the battery chargers which are energized in Phase 2 to recharge the batteries.
RHR Room Revision 1                                 Page 42 of 60                               2014-02-15
The method to ventilate the de equipment rooms is to prop open doors and set up portable fans that will exhaust into an adjacent corridor that communicates with a roll up door to the outside.
 
During the audit process, the licensee stated that detail design to determine the required ventilation flow or the size of the portable fans has not been determined.
On page 43, in the section of the Integrated Plan discussing RHR room accessibility during the final phase, the licensee stated that as part of Phase 3 strategies, an RHR pump is placed into service in order to perform shutdown cooling. This results in heat addition to the RHR pump area due to heat generated by the RHR pump motor as well as heat dissipated from the associated piping. For long term RHR pump operation, the RHR pump area must be cooled to maintain area temperatures within acceptable ranges (limited by maximum allowable RHR pump motor requirements). The licensee stated that mitigating actions can be accomplished by ensuring that cooling support is also powered when the RRC 4160 Vac FLEX DG is connected to the Class 1E 4160 Vac bus to power the RHR pump and that the room cooler can be energized and cooling water supplied via the connections provided between the fire protection system piping and ESW cooling water supply piping. The licensee stated that an alternate means of cooling the RHR rooms if the RHR pump room coolers are not available is to use portable exhaust fans and hose trunks to exhaust hot RHR room air to outside the reactor building.
This is identified as Confirmatory Item 3.2.4.2.C in Section 4.2. RHR Room Revision 1 Page 42 of 60 2014-02-15 On page 43, in the section of the Integrated Plan discussing RHR room accessibility during the final phase, the licensee stated that as part of Phase 3 strategies, an RHR pump is placed into service in order to perform shutdown cooling.
This results in heat addition to the RHR pump area due to heat generated by the RHR pump motor as well as heat dissipated from the associated piping. For long term RHR pump operation, the RHR pump area must be cooled to maintain area temperatures within acceptable ranges (limited by maximum allowable RHR pump motor requirements).
The licensee stated that mitigating actions can be accomplished by ensuring that cooling support is also powered when the RRC 4160 Vac FLEX DG is connected to the Class 1 E 4160 Vac bus to power the RHR pump and that the room cooler can be energized and cooling water supplied via the connections provided between the fire protection system piping and ESW cooling water supply piping. The licensee stated that an alternate means of cooling the RHR rooms if the RHR pump room coolers are not available is to use portable exhaust fans and hose trunks to exhaust hot RHR room air to outside the reactor building.
The licensee's approach described above, as currently understood, is consistent with the guidance found in NEI 12-06, as endorsed by JLD-ISG-2012-01, and subject to the successful closure of issues related to the Confirmatory Items, provides reasonable assurance that the requirements of Order EA-12-049 will be met with respect to ventilation for equipment cooling if these requirements are implemented as described.
The licensee's approach described above, as currently understood, is consistent with the guidance found in NEI 12-06, as endorsed by JLD-ISG-2012-01, and subject to the successful closure of issues related to the Confirmatory Items, provides reasonable assurance that the requirements of Order EA-12-049 will be met with respect to ventilation for equipment cooling if these requirements are implemented as described.
3.2.4.3 Heat Tracing.
3.2.4.3 Heat Tracing.
NEI 12-06, Section 3.2.2, Guideline (12) states: Plant procedures/guidance should consider loss of heat tracing effects for equipment required to cope with an ELAP. Alternate steps, if needed, should be identified to supplement planned action. Heat tracing is used at some plants to ensure cold weather conditions do not result in freezing important piping and instrumentation systems with small diameter piping. Procedures/guidance should be reviewed to identify if any heat traced systems are relied upon to cope with an ELAP. For example, additional condensate makeup may be supplied from a system exposed to cold weather where heat tracing is needed to ensure control systems are available.
NEI 12-06, Section 3.2.2, Guideline (12) states:
If any such systems are identified, additional backup sources of water not dependent on heat tracing should be identified.
Plant procedures/guidance should consider loss of heat tracing effects for equipment required to cope with an ELAP. Alternate steps, if needed, should be identified to supplement planned action.
The Integrated Plan does not address heat tracing for freeze protection of piping, instrument lines and equipment.
Heat tracing is used at some plants to ensure cold weather conditions do not result in freezing important piping and instrumentation systems with small diameter piping. Procedures/guidance should be reviewed to identify if any heat traced systems are relied upon to cope with an ELAP. For example, additional condensate makeup may be supplied from a system exposed to cold weather where heat tracing is needed to ensure control systems are available. If any such systems are identified, additional backup sources of water not dependent on heat tracing should be identified.
The need for heat tracing and freeze protection during an ELAP may include permanent plant equipment and also portable/FLEX equipment that is deployed outdoors during periods of cold weather.
The Integrated Plan does not address heat tracing for freeze protection of piping, instrument lines and equipment. The need for heat tracing and freeze protection during an ELAP may include permanent plant equipment and also portable/FLEX equipment that is deployed outdoors during periods of cold weather. During the audit process, the licensee stated that the need for heat tracing will be addressed later in the design/procedure development phase and that walkdowns will be conducted to identify areas where heat tracing for freeze protection may be required. This is identified as Confirmatory Item 3.2.4.3.A in Section 4.2 The licensee's approach described above, as currently understood, is consistent with the guidance found in NEI 12-06, as endorsed by JLD-ISG-2012-01, and subject to the successful closure of issues related to the Confirmatory Item, provides reasonable assurance that the requirements of Order EA-12-049 will be met with respect to heat tracing if these requirements Revision 1                                 Page 43 of 60                             2014-02-15
During the audit process, the licensee stated that the need for heat tracing will be addressed later in the design/procedure development phase and that walkdowns will be conducted to identify areas where heat tracing for freeze protection may be required.
 
This is identified as Confirmatory Item 3.2.4.3.A in Section 4.2 The licensee's approach described above, as currently understood, is consistent with the guidance found in NEI 12-06, as endorsed by JLD-ISG-2012-01, and subject to the successful closure of issues related to the Confirmatory Item, provides reasonable assurance that the requirements of Order EA-12-049 will be met with respect to heat tracing if these requirements Revision 1 Page 43 of 60 2014-02-15 are implemented as described.
are implemented as described.
3.2.4.4 Accessibility-Lighting and Communication NEI 12-06, Section 3.2.2, Guideline (8) states: Plant procedures/guidance should identify the portable lighting (e.g., flashlights or head/amps) and communications systems necessary for ingress and egress to plant areas required for deployment of FLEX strategies.
3.2.4.4 Accessibility- Lighting and Communication NEI 12-06, Section 3.2.2, Guideline (8) states:
Plant procedures/guidance should identify the portable lighting (e.g., flashlights or head/amps) and communications systems necessary for ingress and egress to plant areas required for deployment of FLEX strategies.
Areas requiring access for instrumentation monitoring or equipment operation may require portable lighting as necessary to perform essential functions.
Areas requiring access for instrumentation monitoring or equipment operation may require portable lighting as necessary to perform essential functions.
Normal communications may be lost or hampered during an ELAP. Consequently, in some cases, portable communication devices may be required to support interaction between personnel in the plant and those providing overall command and control.
Normal communications may be lost or hampered during an ELAP.
The Integrated Plan does not discuss portable, emergency and hand held lighting available to operators for implementing mitigation strategies during an ELAP. The licensee addressed this concern during the audit process by stating that current plant procedures define flashlights as standard gear/equipment of operators with duties in the plant. The de portion of the lighting system receives power from the 125 volt de power system. Also, light towers are available for exterior lighting.
Consequently, in some cases, portable communication devices may be required to support interaction between personnel in the plant and those providing overall command and control.
The licensee stated that need for additional portable  
The Integrated Plan does not discuss portable, emergency and hand held lighting available to operators for implementing mitigation strategies during an ELAP. The licensee addressed this concern during the audit process by stating that current plant procedures define flashlights as standard gear/equipment of operators with duties in the plant. The de portion of the lighting system receives power from the 125 volt de power system. Also, light towers are available for exterior lighting. The licensee stated that need for additional portable lighting, such as portable de powered lights, is still being evaluated. This is identified as Confirmatory Item 3.2.4.4.A in Section 4.2.
: lighting, such as portable de powered lights, is still being evaluated.
During the audit process the licensee stated that although not credited, in addition, self-contained emergency lighting units with an 8-hour power supply are located in many areas.
This is identified as Confirmatory Item 3.2.4.4.A in Section 4.2. During the audit process the licensee stated that although not credited, in addition, contained emergency lighting units with an 8-hour power supply are located in many areas. These lights were installed per 10 CFR 50, Appendix R to provide adequate lighting for operators to access, operate, and then egress from safe shutdown equipment.
These lights were installed per 10 CFR 50, Appendix R to provide adequate lighting for operators to access, operate, and then egress from safe shutdown equipment.
The NRC staff has reviewed the licensee communications assessment (ADAMS Accession Nos. ML 12306A244 and ML 13063A048) in response to the March 12, 2012 50.54(f) request for information letter for JAF and, as documented in the staff analysis (ADAMS Accession No. ML 13123A203),
The NRC staff has reviewed the licensee communications assessment (ADAMS Accession Nos. ML12306A244 and ML13063A048) in response to the March 12, 2012 50.54(f) request for information letter for JAF and, as documented in the staff analysis (ADAMS Accession No. ML13123A203), has determined that the assessment for communications is reasonable, and the analyzed existing systems, proposed enhancements, and interim measures will help to ensure that communications are maintained. Therefore, there is reasonable assurance that the guidance and strategies developed by the licensee will conform to the guidance of NEI 12-06 Section 3.2.2, Guideline (8) regarding communications capabilities during an ELAP.
has determined that the assessment for communications is reasonable, and the analyzed existing  
Confirmation will be required that upgrades to the site's communications systems have been completed. This has been identified as Confirmatory Item 3.2.4.4.8 in Section 4.2.
: systems, proposed enhancements, and interim measures will help to ensure that communications are maintained.
The licensee's approach described above, as currently understood, is consistent with the guidance found in NEI 12-06, as endorsed by JLD-ISG-2012-01, and subject to the successful closure of issues related to the Confirmatory Items, provides reasonable assurance that the requirements of Order EA-12-049 will be met with respect to availability of lighting and communication if these requirements are implemented as described.
Therefore, there is reasonable assurance that the guidance and strategies developed by the licensee will conform to the guidance of NEI 12-06 Section 3.2.2, Guideline (8) regarding communications capabilities during an ELAP. Confirmation will be required that upgrades to the site's communications systems have been completed.
Revision 1                                 Page 44 of 60                                 2014-02-15
This has been identified as Confirmatory Item 3.2.4.4.8 in Section 4.2. The licensee's approach described above, as currently understood, is consistent with the guidance found in NEI 12-06, as endorsed by JLD-ISG-2012-01, and subject to the successful closure of issues related to the Confirmatory Items, provides reasonable assurance that the requirements of Order EA-12-049 will be met with respect to availability of lighting and communication if these requirements are implemented as described.
 
Revision 1 Page 44 of 60 2014-02-15 3.2.4.5 Protected and Internal Locked Area Access NEI 12-06, Section 3.2.2, Guideline (9) states: Plant procedures/guidance should consider the effects of ac power loss on area access, as well as the need to gain entry to the Protected Area and internal locked areas where remote equipment operation is necessary.
3.2.4.5 Protected and Internal Locked Area Access NEI 12-06, Section 3.2.2, Guideline (9) states:
At some plants, the security system may be adversely affected by the loss of the preferred or Class 1 E power supplies in an ELAP. In such cases, manual actions specified in ELAP response procedures/guidance may require additional actions to obtain access. There is no discussion in the Integrated Plan of the guidance and strategies with regard to the effects of ac power loss on area access to the protected area and internal locked areas to demonstrate conformance with NEI 12-06. During the audit process, the licensee stated that procedures exist and FSGs will be developed to ensure that operators can access required areas in the event of loss of power. The licensee stated that additional details on controls for access to security controlled or internal locked areas where extended loss of all power would disable normal controlled access will be contained in the FSGs or associated procedures.
Plant procedures/guidance should consider the effects of ac power loss on area access, as well as the need to gain entry to the Protected Area and internal locked areas where remote equipment operation is necessary.
At some plants, the security system may be adversely affected by the loss of the preferred or Class 1E power supplies in an ELAP. In such cases, manual actions specified in ELAP response procedures/guidance may require additional actions to obtain access.
There is no discussion in the Integrated Plan of the guidance and strategies with regard to the effects of ac power loss on area access to the protected area and internal locked areas to demonstrate conformance with NEI 12-06. During the audit process, the licensee stated that procedures exist and FSGs will be developed to ensure that operators can access required areas in the event of loss of power. The licensee stated that additional details on controls for access to security controlled or internal locked areas where extended loss of all power would disable normal controlled access will be contained in the FSGs or associated procedures.
The licensee's approach described above, as currently understood, is consistent with the guidance found in NEI 12-06, as endorsed by JLD-ISG-2012-01, and provides reasonable assurance that the requirements of Order EA-12-049 will be met with respect to access to protected and locked areas if these requirements are implemented as described.
The licensee's approach described above, as currently understood, is consistent with the guidance found in NEI 12-06, as endorsed by JLD-ISG-2012-01, and provides reasonable assurance that the requirements of Order EA-12-049 will be met with respect to access to protected and locked areas if these requirements are implemented as described.
3.2.4.6 Personnel Habitability-Elevated Temperature NEI 12-06, Section 3.2.2, Paragraph (11) provides that: Plant procedures/guidance should consider accessibility guidelines at locations where operators will be required to perform local manual operations.
3.2.4.6 Personnel Habitability- Elevated Temperature NEI 12-06, Section 3.2.2, Paragraph (11) provides that:
Plant procedures/guidance should consider accessibility guidelines at locations where operators will be required to perform local manual operations.
Due to elevated temperatures and humidity in some locations where local operator actions are required (e.g., manual valve manipulations, equipment connections, etc.), procedures/guidance should identify the protective clothing or other equipment or actions necessary to protect the operator, as appropriate.
Due to elevated temperatures and humidity in some locations where local operator actions are required (e.g., manual valve manipulations, equipment connections, etc.), procedures/guidance should identify the protective clothing or other equipment or actions necessary to protect the operator, as appropriate.
FLEX strategies must be capable of execution under the adverse conditions (unavailability of installed plant lighting, ventilation, etc.) expected following a BDBE resulting in an ELAP/LUHS.
FLEX strategies must be capable of execution under the adverse conditions (unavailability of installed plant lighting, ventilation, etc.) expected following a BDBE resulting in an ELAP/LUHS. Accessibility of equipment, tooling, connection points, and plant components shall be accounted for in the development of the FLEX strategies. The use of appropriate human performance aids (e.g., component marking, connection schematics, installation sketches, photographs, etc.) shall be included in the FLEX guidance implementing the FLEX strategies.
Accessibility of equipment,  
During the audit process, the licensee stated that long term habitability of the main control room will be assured by monitoring control room conditions, heat stress countermeasures, and rotation of personnel to the extent feasible. The licensee stated that impact to habitability would be primarily from elevated temperatures and that FSGs will provide guidance for control room Revision 1                                     Page 45 of 60                                 2014-02-15
: tooling, connection points, and plant components shall be accounted for in the development of the FLEX strategies.
 
The use of appropriate human performance aids (e.g., component  
staff to evaluate the control room temperature and take actions as necessary. The licensee stated that Entergy already uses passive cooling technologies for response personnel in high temperature environments. The maximum expected temperature in the control room and planned measures for providing ventilation cooling is discussed in section 3.2.4.2 of this report.
: marking, connection schematics, installation  
During the audit process, the licensee also stated that it's not anticipated that accessibility of the RCIC room will be required; however if personnel access is necessary to implement the FLEX strategy the method of assuring RCIC habitability will be addressed in the detailed design phase. This is combined with Confirmatory Item 3.2.4.2.A in Section 4.2.
: sketches, photographs, etc.) shall be included in the FLEX guidance implementing the FLEX strategies.
During the audit process, the licensee stated that operators are trained on working in high temperature areas of the plant and that entry into high temperature environments is governed by Entergy's industrial safety procedures with controls for heat stress situations. The licensee stated that continuous standby in the RCIC room is not required and operators can cycle in and out of the room as necessary to adjust flow and maintain operation of the RCIC pump. Also, as stated on page 37 of the Integrated Plan, if personnel entry is required into the RCIC room, then supplemental ventilation and personnel protective measures (such as ice vests) will be taken.
During the audit process, the licensee stated that long term habitability of the main control room will be assured by monitoring control room conditions, heat stress countermeasures, and rotation of personnel to the extent feasible.
The licensee's approach described above, as currently understood, is consistent with the guidance found in NEI 12-06, as endorsed by JLD-ISG-2012-01, and subject to the successful closure of issues related to the Confirmatory Item, provides reasonable assurance that the requirements of Order EA-12-049 will be met with respect to personnel habitability if these requirements are implemented as described.
The licensee stated that impact to habitability would be primarily from elevated temperatures and that FSGs will provide guidance for control room Revision 1 Page 45 of 60 2014-02-15 staff to evaluate the control room temperature and take actions as necessary.
The licensee stated that Entergy already uses passive cooling technologies for response personnel in high temperature environments.
The maximum expected temperature in the control room and planned measures for providing ventilation cooling is discussed in section 3.2.4.2 of this report. During the audit process, the licensee also stated that it's not anticipated that accessibility of the RCIC room will be required; however if personnel access is necessary to implement the FLEX strategy the method of assuring RCIC habitability will be addressed in the detailed design phase. This is combined with Confirmatory Item 3.2.4.2.A in Section 4.2. During the audit process, the licensee stated that operators are trained on working in high temperature areas of the plant and that entry into high temperature environments is governed by Entergy's industrial safety procedures with controls for heat stress situations.
The licensee stated that continuous standby in the RCIC room is not required and operators can cycle in and out of the room as necessary to adjust flow and maintain operation of the RCIC pump. Also, as stated on page 37 of the Integrated Plan, if personnel entry is required into the RCIC room, then supplemental ventilation and personnel protective measures (such as ice vests) will be taken. The licensee's approach described above, as currently understood, is consistent with the guidance found in NEI 12-06, as endorsed by JLD-ISG-2012-01, and subject to the successful closure of issues related to the Confirmatory Item, provides reasonable assurance that the requirements of Order EA-12-049 will be met with respect to personnel habitability if these requirements are implemented as described.
3.2.4.7 Water Sources.
3.2.4.7 Water Sources.
NEI 12-06, Section 3.2.2, Guideline (5) states: Plant procedures/guidance should ensure that a flow path is promptly established for makeup flow to the steam generator/nuclear boiler and identify backup water sources in order of intended use. Additionally, plant procedures/guidance should specify clear criteria for transferring to the next preferred source of water. Under certain beyond-design-basis conditions, the integrity of some water sources may be challenged.
NEI 12-06, Section 3.2.2, Guideline (5) states:
Coping with an ELAP/LUHS may require water supplies for multiple days. Guidance should address alternate water sources and water delivery systems to support the extended coping duration.
Plant procedures/guidance should ensure that a flow path is promptly established for makeup flow to the steam generator/nuclear boiler and identify backup water sources in order of intended use. Additionally, plant procedures/guidance should specify clear criteria for transferring to the next preferred source of water.
Cooling and makeup water inventories contained in systems or structures with designs that are robust with respect to seismic events, floods, and high winds, and associated missiles are assumed to be available in an ELAP/LUHS at their nominal capacities.
Under certain beyond-design-basis conditions, the integrity of some water sources may be challenged. Coping with an ELAP/LUHS may require water supplies for multiple days. Guidance should address alternate water sources and water delivery systems to support the extended coping duration. Cooling and makeup water inventories contained in systems or structures with designs that are robust with respect to seismic events, floods, and high winds, and associated missiles are assumed to be available in an ELAP/LUHS at their nominal capacities. Water in robust UHS piping may also be available for use but would need to be evaluated to ensure adequate NPSH can be demonstrated and, for example, that the water does not gravity drain back to the UHS.
Water in robust UHS piping may also be available for use but would need to be evaluated to ensure adequate NPSH can be demonstrated and, for example, that the water does not gravity drain back to the UHS. Alternate water delivery systems can be considered available on a case-by-case basis. In general, all CSTs should be used first if available.
Alternate water delivery systems can be considered available on a case-by-case basis. In general, all CSTs should be used first if available. If the normal source of makeup water (e.g., CST) fails or becomes exhausted as a result of the hazard, then robust demineralized, raw, or borated water tanks may be used as appropriate.
If the normal source of makeup water (e.g., CST) fails or becomes exhausted as a result of the hazard, then robust demineralized, raw, or borated water tanks may be used as appropriate.
Heated torus water can be relied upon if sufficient [net positive suction head]
Heated torus water can be relied upon if sufficient  
NPSH can be established. Finally, when all other preferred water sources have Revision 1                                   Page 46 of 60                             2014-02-15
[net positive suction head] NPSH can be established.  
 
: Finally, when all other preferred water sources have Revision 1 Page 46 of 60 2014-02-15 been depleted, lower water quality sources may be pumped as makeup flow using available equipment (e.g., a diesel driven fire pump or a portable pump drawing from a raw water source).
been depleted, lower water quality sources may be pumped as makeup flow using available equipment (e.g., a diesel driven fire pump or a portable pump drawing from a raw water source). Procedures/guidance should clearly specify the conditions when the operator is expected to resort to increasingly impure water sources.
Procedures/guidance should clearly specify the conditions when the operator is expected to resort to increasingly impure water sources.
The licensee has identified three water sources for use in the FLEX strategies. These are the suppression pool, the CST and the ultimate heat sink, Lake Ontario. As described on page 12 of the Integrated Plan, JAF's primary coping strategy to prevent core damage during an ELAP is through the use of the RCIC pump. The licensee stated that the CSTs, with a minimum capacity of 200,000 gallons, are the normal pump suction supply to RCIC. The suction supply for the RCIC pump will automatically transfer from the CSTs to the suppression pool (SP) on low CSTs level. The licensee stated that during an ELAP, at approximately 1 hour event time, operators will manually transfer RCIC suction to the SP. The RCIC suction path will remain aligned to the SP until the SP temperature reaches about 170 degrees Fahrenheit. This is expected to occur at approximately [[estimated NRC review hours::5 hours]] event time. Operators will then shift the RCIC suction path back to the CSTs. The licensee stated that the combined water volumes of the SP and the CSTs are expected to provide core cooling for approximately [[estimated NRC review hours::35 hours]] without refilling the CSTs.
The licensee has identified three water sources for use in the FLEX strategies.
During the audit process, the licensee stated that the lower half of each CST is below ground level for tornado and seismic protection of the tank's 100,000 gallons storage capacity. The licensee stated that the CSTs are considered robust and available following the BDBEEs.
These are the suppression pool, the CST and the ultimate heat sink, Lake Ontario.
During the audit process, the licensee further stated that switchover between the suppression pool and the CSTs is done manually by the operators from the control room and that automatic controls are not relied upon to align water sources to the RCIC pump for core cooling.
As described on page 12 of the Integrated Plan, JAF's primary coping strategy to prevent core damage during an ELAP is through the use of the RCIC pump. The licensee stated that the CSTs, with a minimum capacity of 200,000 gallons, are the normal pump suction supply to RCIC. The suction supply for the RCIC pump will automatically transfer from the CSTs to the suppression pool (SP) on low CSTs level. The licensee stated that during an ELAP, at approximately 1 hour event time, operators will manually transfer RCIC suction to the SP. The RCIC suction path will remain aligned to the SP until the SP temperature reaches about 170 degrees Fahrenheit.
As described on page 17 of the Integrated Plan, prior to depletion of the CSTs, the licensee plans to transition from the steam driven RCIC pump to using the installed seismically qualified diesel driven fire pump to supply makeup water from Lake Ontario to the RPV. This is accomplished by connecting a temporary hose from the fire protection header to the RHRSW system. RHRSW can be cross tied to the RHR system allowing water injection into the RPV. In the event that the station diesel firewater pump is not available, the licensee has established an alternate strategy to lower a portable diesel-driven FLEX pump into the screenwell area and makeup to the RPV by the same flow path. The portable diesel driven FLEX pump can also supply water to the SFP and refill the CSTs.
This is expected to occur at approximately 5 hours event time. Operators will then shift the RCIC suction path back to the CSTs. The licensee stated that the combined water volumes of the SP and the CSTs are expected to provide core cooling for approximately 35 hours without refilling the CSTs. During the audit process, the licensee stated that the lower half of each CST is below ground level for tornado and seismic protection of the tank's 100,000 gallons storage capacity.
The licensee's approach described above, as currently understood, is consistent with the guidance found in NEI 12-06, as endorsed by JLD-ISG-2012-01, and provides reasonable assurance that the requirements of Order EA-12-049 will be met with respect to water sources if these requirements are implemented as described.
The licensee stated that the CSTs are considered robust and available following the BDBEEs. During the audit process, the licensee further stated that switchover between the suppression pool and the CSTs is done manually by the operators from the control room and that automatic controls are not relied upon to align water sources to the RCIC pump for core cooling.
3.2.4.8 Electrical Power Sources/Isolations and Interactions NEI 12-06, Section 3.2.2, Guideline (13) states in part:
As described on page 17 of the Integrated Plan, prior to depletion of the CSTs, the licensee plans to transition from the steam driven RCIC pump to using the installed seismically qualified diesel driven fire pump to supply makeup water from Lake Ontario to the RPV. This is accomplished by connecting a temporary hose from the fire protection header to the RHRSW system. RHRSW can be cross tied to the RHR system allowing water injection into the RPV. In the event that the station diesel firewater pump is not available, the licensee has established an alternate strategy to lower a portable diesel-driven FLEX pump into the screenwell area and makeup to the RPV by the same flow path. The portable diesel driven FLEX pump can also supply water to the SFP and refill the CSTs. The licensee's approach described above, as currently understood, is consistent with the guidance found in NEI 12-06, as endorsed by JLD-ISG-2012-01, and provides reasonable assurance that the requirements of Order EA-12-049 will be met with respect to water sources if these requirements are implemented as described.
The use of portable equipment to charge batteries or locally energize equipment may be needed under ELAP/LUHS conditions. Appropriate electrical isolations and interactions should be addressed in procedures/guidance.
3.2.4.8 Electrical Power Sources/Isolations and Interactions NEI 12-06, Section 3.2.2, Guideline (13) states in part: The use of portable equipment to charge batteries or locally energize equipment may be needed under ELAP/LUHS conditions.
Revision 1                                 Page 47 of 60                               2014-02-15
Appropriate electrical isolations and interactions should be addressed in procedures/guidance.
 
Revision 1 Page 47 of 60 2014-02-15 On pages 17 and 18 of the Integrated Plan the licensee provided a description of the electrical support strategy during Phase 2. The 125 Vdc batteries are available for up to 10 hours without recharging.
On pages 17 and 18 of the Integrated Plan the licensee provided a description of the electrical support strategy during Phase 2. The 125 Vdc batteries are available for up to [[estimated NRC review hours::10 hours]] without recharging. A modification will provide new connection points for a portable diesel generator unit to re-power the battery chargers which charge the batteries and supply de loads. The FLEX 600 Vac, 200 kW DG will be connected at approximately [[estimated NRC review hours::6 hours]] and is sized to power the battery charger and fans (about 90 kW). As an alternate strategy to that of powering the battery chargers from their Class 1E 600 volt electrical buses, connections will be provided to enable power to be provided directly to the battery chargers. This will enable the use of a 90 kW FLEX 600 Vac DG to power the battery charger. Permanently installed cables will be run to facilitate the use of this alternative power arrangement.
A modification will provide new connection points for a portable diesel generator unit to re-power the battery chargers which charge the batteries and supply de loads. The FLEX 600 Vac, 200 kW DG will be connected at approximately 6 hours and is sized to power the battery charger and fans (about 90 kW). As an alternate strategy to that of powering the battery chargers from their Class 1 E 600 volt electrical buses, connections will be provided to enable power to be provided directly to the battery chargers.
On page 21 of the Integrated Plan, the licensee provided a description of the electrical support strategy to be used during Phase 3. For Phase 3, the reactor core cooling strategy is to place one loop of RHR into the shutdown cooling mode. This will be accomplished by powering up a Division I or II RHR pump from the respective Class 1E emergency bus, utilizing a 4160 Vac FLEX portable diesel generator supplied by the RRC. The licensee stated that the 4160 Vac RRC FLEX diesel generator will be capable of carrying approximately 2000 kW load which is sufficient to carry all of the loads necessary to support the Phase 3 FLEX strategies which includes an RHR pump and its support equipment. The licensee stated that an alternate means of providing power to the RHR pumps for SOC operation is to run cable from the 4160 Vac RRC FLEX DG directly to the component by connecting either at the switchgear end of the component's power cable or locally at the pump end of the power cable.
This will enable the use of a 90 kW FLEX 600 Vac DG to power the battery charger.
During the audit process, the licensee addressed the issues associated with electrical isolations and interactions. The licensee stated that connection points and other permanent modifications will be designed in accordance with approved design practices to assure no adverse effects during normal operation. The licensee stated that at the onset of the ELAP, Class 1E emergency diesel generators are assumed unavailable to supply the Class 1E busses. Portable generators are used in response to an ELAP in FLEX strategies for Phases 2 and 3. The licensee stated that at the point when ELAP mitigation activities require tie-in of FLEX generators, in addition to existing electrical interlocks, procedural controls such as inhibiting EDG start circuits and breaker rack-outs (e.g., EDG breakers, offsite feeder breakers, etc) will be employed to prevent simultaneous connection of both the FLEX generators and Class 1E EDG to the same ac distribution system or component. Additionally, repowering the Class 1E electrical busses from either the FLEX generators or subsequently the Class 1E EDGs (should they become available) will be accomplished manually and controlled by procedure; no automatic sequencing or automatic repowering of the busses will be utilized.
Permanently installed cables will be run to facilitate the use of this alternative power arrangement.
The Integrated Plan did not provide information regarding the technical basis for the selection and size of the FLEX generators to be used in support of the coping strategies. Supporting information should be provided to address both Phase 2 and 3 power requirements. The licensee addressed the topic of generator sizing during the audit process by stating that the information would be provided in a future 6-month update. This is identified as Confirmatory Item 3.2.4.8.A in Section 4.2.
On page 21 of the Integrated Plan, the licensee provided a description of the electrical support strategy to be used during Phase 3. For Phase 3, the reactor core cooling strategy is to place one loop of RHR into the shutdown cooling mode. This will be accomplished by powering up a Division I or II RHR pump from the respective Class 1 E emergency bus, utilizing a 4160 Vac FLEX portable diesel generator supplied by the RRC. The licensee stated that the 4160 Vac RRC FLEX diesel generator will be capable of carrying approximately 2000 kW load which is sufficient to carry all of the loads necessary to support the Phase 3 FLEX strategies which includes an RHR pump and its support equipment.
The licensee's approach described above, as currently understood, is consistent with the guidance found in NEI 12-06, as endorsed by JLD-ISG-2012-01, and subject to the successful closure of issues related to the Confirmatory Item, provides reasonable assurance that the requirements of Order EA-12-049 will be met with respect to electrical power sources, isolations and interactions if these requirements are implemented as described.
The licensee stated that an alternate means of providing power to the RHR pumps for SOC operation is to run cable from the 4160 Vac RRC FLEX DG directly to the component by connecting either at the switchgear end of the component's power cable or locally at the pump end of the power cable. During the audit process, the licensee addressed the issues associated with electrical isolations and interactions.
Revision 1                                 Page 48 of 60                               2014-02-15
The licensee stated that connection points and other permanent modifications will be designed in accordance with approved design practices to assure no adverse effects during normal operation.
 
The licensee stated that at the onset of the ELAP, Class 1 E emergency diesel generators are assumed unavailable to supply the Class 1 E busses. Portable generators are used in response to an ELAP in FLEX strategies for Phases 2 and 3. The licensee stated that at the point when ELAP mitigation activities require tie-in of FLEX generators, in addition to existing electrical interlocks, procedural controls such as inhibiting EDG start circuits and breaker rack-outs (e.g., EDG breakers, offsite feeder breakers, etc) will be employed to prevent simultaneous connection of both the FLEX generators and Class 1 E EDG to the same ac distribution system or component.
3.2.4.9 Portable Equipment Fuel NEI 12-06, Section 3.2.2, Guideline (13) states in part:
Additionally, repowering the Class 1 E electrical busses from either the FLEX generators or subsequently the Class 1 E EDGs (should they become available) will be accomplished manually and controlled by procedure; no automatic sequencing or automatic repowering of the busses will be utilized.
The fuel necessary to operate the FLEX equipment needs to be assessed in the plant specific analysis to ensure sufficient quantities are available as well as to address delivery capabilities.
The Integrated Plan did not provide information regarding the technical basis for the selection and size of the FLEX generators to be used in support of the coping strategies.
NEI 12-06, Section 3.2.1.3, initial condition (5) states:
Supporting information should be provided to address both Phase 2 and 3 power requirements.
Fuel for FLEX equipment stored in structures with designs which are robust with respect to seismic events, floods and high winds and associated missiles, remains available.
The licensee addressed the topic of generator sizing during the audit process by stating that the information would be provided in a future 6-month update. This is identified as Confirmatory Item 3.2.4.8.A in Section 4.2. The licensee's approach described above, as currently understood, is consistent with the guidance found in NEI 12-06, as endorsed by JLD-ISG-2012-01, and subject to the successful closure of issues related to the Confirmatory Item, provides reasonable assurance that the requirements of Order EA-12-049 will be met with respect to electrical power sources, isolations and interactions if these requirements are implemented as described.
On page 18, in the section of the Integrated Plan discussing coping strategies for maintaining core cooling during the transition phase, the licensee stated that diesel fuel to support operation of the portable Phase 2 FLEX equipment for at least [[estimated NRC review hours::15 hours]] will be stored with the FLEX equipment. The licensee stated that additional diesel fuel is available in the underground emergency diesel generator (EDG) fuel storage tanks and that the Division I & II EDG fuel oil storage tanks contain more than 128,000 gallons of fuel oil. The licensee stated that underground EDG fuel oil storage tanks contain sufficient fuel oil to support all Phase 2 strategies. The licensee stated that if the normal procedure for transferring fuel from the underground storage tanks is not possible, the fuel oil can be obtained from the underground storage tanks using a manual, air, or battery operated pump to pump the fuel into a transfer tank. Two trailers with fuel tank and portable containers are provided as part of the Phase 2 FLEX equipment as indicated in the table on page 45 of the Integrated Plan.
Revision 1 Page 48 of 60 2014-02-15 3.2.4.9 Portable Equipment Fuel NEI 12-06, Section 3.2.2, Guideline (13) states in part: The fuel necessary to operate the FLEX equipment needs to be assessed in the plant specific analysis to ensure sufficient quantities are available as well as to address delivery capabilities.
During the audit process, the licensee stated that the quality of the fuel in the EDG fuel oil storage tanks is maintained in accordance with JAF's diesel fuel oil testing program and that fuel oil in the fuel tanks of the portable diesel driven FLEX equipment will be maintained in the preventative maintenance program in accordance with the EPRI maintenance template.
NEI 12-06, Section 3.2.1.3, initial condition (5) states: Fuel for FLEX equipment stored in structures with designs which are robust with respect to seismic events, floods and high winds and associated  
: missiles, remains available.
On page 18, in the section of the Integrated Plan discussing coping strategies for maintaining core cooling during the transition phase, the licensee stated that diesel fuel to support operation of the portable Phase 2 FLEX equipment for at least 15 hours will be stored with the FLEX equipment.
The licensee stated that additional diesel fuel is available in the underground emergency diesel generator (EDG) fuel storage tanks and that the Division I & II EDG fuel oil storage tanks contain more than 128,000 gallons of fuel oil. The licensee stated that underground EDG fuel oil storage tanks contain sufficient fuel oil to support all Phase 2 strategies.
The licensee stated that if the normal procedure for transferring fuel from the underground storage tanks is not possible, the fuel oil can be obtained from the underground storage tanks using a manual, air, or battery operated pump to pump the fuel into a transfer tank. Two trailers with fuel tank and portable containers are provided as part of the Phase 2 FLEX equipment as indicated in the table on page 45 of the Integrated Plan. During the audit process, the licensee stated that the quality of the fuel in the EDG fuel oil storage tanks is maintained in accordance with JAF's diesel fuel oil testing program and that fuel oil in the fuel tanks of the portable diesel driven FLEX equipment will be maintained in the preventative maintenance program in accordance with the EPRI maintenance template.
The licensee's approach described above, as currently understood, is consistent with the guidance found in NEI 12-06, as endorsed by JLD-ISG-2012-01, and provides reasonable assurance that the requirements of Order EA-12-049 will be met with respect to fuel oil supplies if these requirements are implemented as described.
The licensee's approach described above, as currently understood, is consistent with the guidance found in NEI 12-06, as endorsed by JLD-ISG-2012-01, and provides reasonable assurance that the requirements of Order EA-12-049 will be met with respect to fuel oil supplies if these requirements are implemented as described.
3.2.4.1 0 Load Reduction to Conserve DC Power NEI 12-06, Section 3.2.2, Guideline (6) states: Plant procedures/guidance should identify loads that need to be stripped from the plant de buses (both Class 1 E and non-Class 1 E) for the purpose of conserving de power. DC power is needed in an ELAP for such loads as shutdown system instrumentation, control systems, and de backed AOVs and MOVs. Emergency lighting may also be powered by safety-related batteries.  
3.2.4.1 0 Load Reduction to Conserve DC Power NEI 12-06, Section 3.2.2, Guideline (6) states:
: However, for many plants, this lighting may have been supplemented by Appendix R and security lights, thereby allowing the emergency lighting load to be eliminated.
Plant procedures/guidance should identify loads that need to be stripped from the plant de buses (both Class 1E and non-Class 1E) for the purpose of conserving de power.
ELAP procedures/guidance should direct operators to conserve de power during the Revision 1 Page 49 of 60 2014-02-15 event by stripping nonessential loads as soon as practical.
DC power is needed in an ELAP for such loads as shutdown system instrumentation, control systems, and de backed AOVs and MOVs. Emergency lighting may also be powered by safety-related batteries. However, for many plants, this lighting may have been supplemented by Appendix R and security lights, thereby allowing the emergency lighting load to be eliminated. ELAP procedures/guidance should direct operators to conserve de power during the Revision 1                                   Page 49 of 60                                 2014-02-15
Early load stripping can significantly extend the availability of the unit's Class 1 E batteries.
 
In certain circumstances, AFW/HPCI/RCIC operation may be extended by throttling flow to a constant rate, rather than by stroking valves in open-shut cycles. Given the beyond-design-basis nature of these conditions, it is acceptable to strip loads down to the minimum equipment necessary and one set of instrument channels for required indications.
event by stripping nonessential loads as soon as practical. Early load stripping can significantly extend the availability of the unit's Class 1E batteries. In certain circumstances, AFW/HPCI/RCIC operation may be extended by throttling flow to a constant rate, rather than by stroking valves in open-shut cycles.
Credit for load-shedding actions should consider the other concurrent actions that may be required in such a condition.
Given the beyond-design-basis nature of these conditions, it is acceptable to strip loads down to the minimum equipment necessary and one set of instrument channels for required indications. Credit for load-shedding actions should consider the other concurrent actions that may be required in such a condition.
On page 5, in the section of the Integrated Plan discussing time constraints identified in the sequence of events time line, the licensee stated that at 90 minutes after an ELAP, de load shed is completed and that FLEX response procedures will detail the actions necessary.
On page 5, in the section of the Integrated Plan discussing time constraints identified in the sequence of events time line, the licensee stated that at 90 minutes after an ELAP, de load shed is completed and that FLEX response procedures will detail the actions necessary. The licensee stated that the de buses are readily available for operator access and breakers will be appropriately identified (labeled) to show which are required to be opened to implement a deep load shed. The Integrated Plan states that that based on engineering judgment, it is reasonable to expect that operators can complete the shedding of loads from the de bus in approximately 30 minutes. The licensee noted that existing station blackout procedure (AOP-49) includes direction to depressurize and vent the main generator within 30 minutes of a station blackout.
The licensee stated that the de buses are readily available for operator access and breakers will be appropriately identified (labeled) to show which are required to be opened to implement a deep load shed. The Integrated Plan states that that based on engineering  
During the audit the licensee stated that the load shed list will be refined during the design process and that the potential adverse impacts of shedding these additional loads will be evaluated. This is identified as Confirmatory Item 3.2.4.1 O.A in Section 4.2.
: judgment, it is reasonable to expect that operators can complete the shedding of loads from the de bus in approximately 30 minutes.
On page 5 of the Integrated Plan, the licensee stated that at [[estimated NRC review hours::10 hours]] a battery charger is re-powered to maintain the de power system. Deployment of the FLEX DG will be initiated shortly after the BDBEE is declared in recognition of the potential for battery depletion. The licensee stated that the event is time critical at battery depletion and that both the A and the B batteries have been calculated to last more than [[estimated NRC review hours::10 hours]] in the FLEX scenario. During the audit process, the licensee stated that the 10 hour runtime is based on the minimum battery voltage (111.6 volts for battery A and 110.26 volts for battery B) and expected electrical loading. The minimum voltage is the acceptance criteria for the SBO minimum battery voltage as stated in existing battery calculations. The de load profile with the required loads for the mitigating strategies to maintain core cooling, containment, and spent fuel cooling is still in the design/development phase. The licensee stated that the finalized minimum battery voltages will be available later in the design phase. This is identified as Confirmatory Item 3.2.4.1 0. B in Section 4.2.
The licensee noted that existing station blackout procedure (AOP-49) includes direction to depressurize and vent the main generator within 30 minutes of a station blackout.
During the audit process, the licensee stated that the FLEX 600 Vac DGs will be connected within [[estimated NRC review hours::6 hours]] after the ELAP, whereas on page 48 of the Integrated Plan, the sequence of events table indicates that the station battery chargers will be re-powered at [[estimated NRC review hours::10 hours]]. The sequence of events timeline needs to be reconfirmed or updated to address this apparent change in strategy. This is identified as Confirmatory Item 3.2.4.1 O.C in Section 4.2.
During the audit the licensee stated that the load shed list will be refined during the design process and that the potential adverse impacts of shedding these additional loads will be evaluated.
The NRC staff reviewed the licensee's Integrated Plan and determined that the Generic Concern related to battery duty cycles beyond [[estimated NRC review hours::8 hours]] is applicable to the plant. This Generic Concern has been resolved generically through the NRC endorsement of NEI position paper entitled "Battery Life Issue" (ADAMS Accession Nos. ML13241A186 (position paper) and ML13241A188 (NRC endorsement letter)).
This is identified as Confirmatory Item 3.2.4.1 O.A in Section 4.2. On page 5 of the Integrated Plan, the licensee stated that at 10 hours a battery charger is powered to maintain the de power system. Deployment of the FLEX DG will be initiated shortly after the BDBEE is declared in recognition of the potential for battery depletion.
The purpose of the Generic Concern and associated endorsement of the position paper was to resolve concerns associated with Integrated Plan submittals in a timely manner and on a Revision 1                                   Page 50 of 60                                 2014-02-15
The licensee stated that the event is time critical at battery depletion and that both the A and the B batteries have been calculated to last more than 10 hours in the FLEX scenario.
 
During the audit process, the licensee stated that the 10 hour runtime is based on the minimum battery voltage (111.6 volts for battery A and 110.26 volts for battery B) and expected electrical loading.
generic basis, to the extent possible, and provide a consistent review by the NRC staff. Position papers provided to the NRC by industry further develop and clarify the guidance provided in NEI 12-06 related to industry's ability to meet the requirements of Order EA-12-049.
The minimum voltage is the acceptance criteria for the SBO minimum battery voltage as stated in existing battery calculations.
The Generic Concern related to extended battery duty cycles required clarification of the capability of the existing vented lead-acid station batteries to perform their expected function for durations greater than [[estimated NRC review hours::8 hours]] throughout the expected service life of the battery. The position paper provided sufficient basis to resolve this concern by developing an acceptable method for demonstrating that batteries will perform as specified in a plant's Integrated Plan. The methodology relies on the licensee's battery sizing calculations developed in accordance with the Institute of Electrical and Electronics Engineers Standard 485, "Recommended Practice for Sizing Large Lead Storage Batteries for Generating Stations and Substations," load shedding schemes, and manufacturer data to demonstrate that the existing vented lead-acid station batteries can perform their intended function for extended duty cycles (i.e., beyond [[estimated NRC review hours::8 hours]]).
The de load profile with the required loads for the mitigating strategies to maintain core cooling, containment, and spent fuel cooling is still in the design/development phase. The licensee stated that the finalized minimum battery voltages will be available later in the design phase. This is identified as Confirmatory Item 3.2.4.1 0. B in Section 4.2. During the audit process, the licensee stated that the FLEX 600 Vac DGs will be connected within 6 hours after the ELAP, whereas on page 48 of the Integrated Plan, the sequence of events table indicates that the station battery chargers will be re-powered at 10 hours. The sequence of events timeline needs to be reconfirmed or updated to address this apparent change in strategy.
The NRC staff concluded that the position paper provides an acceptable approach for licensees to use in demonstrating that vented lead-acid batteries can be credited for durations longer than [[estimated NRC review hours::8 hours]]. The NRC staff will evaluate a licensee's application of the guidance (calculations and supporting data) in its development of the final Safety Evaluation documenting review of the licensee's Integrated Plan.
This is identified as Confirmatory Item 3.2.4.1 O.C in Section 4.2. The NRC staff reviewed the licensee's Integrated Plan and determined that the Generic Concern related to battery duty cycles beyond 8 hours is applicable to the plant. This Generic Concern has been resolved generically through the NRC endorsement of NEI position paper entitled "Battery Life Issue" (ADAMS Accession Nos. ML 13241 A 186 (position paper) and ML 13241A188 (NRC endorsement letter)).
During the audit process, the licensee stated that the FLEX strategy battery run time was determined in accordance with the IEEE 485 methodology.
The purpose of the Generic Concern and associated endorsement of the position paper was to resolve concerns associated with Integrated Plan submittals in a timely manner and on a Revision 1 Page 50 of 60 2014-02-15 generic basis, to the extent possible, and provide a consistent review by the NRC staff. Position papers provided to the NRC by industry further develop and clarify the guidance provided in NEI 12-06 related to industry's ability to meet the requirements of Order EA-12-049.
The Generic Concern related to extended battery duty cycles required clarification of the capability of the existing vented lead-acid station batteries to perform their expected function for durations greater than 8 hours throughout the expected service life of the battery.
The position paper provided sufficient basis to resolve this concern by developing an acceptable method for demonstrating that batteries will perform as specified in a plant's Integrated Plan. The methodology relies on the licensee's battery sizing calculations developed in accordance with the Institute of Electrical and Electronics Engineers Standard 485, "Recommended Practice for Sizing Large Lead Storage Batteries for Generating Stations and Substations,"
load shedding  
: schemes, and manufacturer data to demonstrate that the existing vented lead-acid station batteries can perform their intended function for extended duty cycles (i.e., beyond 8 hours). The NRC staff concluded that the position paper provides an acceptable approach for licensees to use in demonstrating that vented lead-acid batteries can be credited for durations longer than 8 hours. The NRC staff will evaluate a licensee's application of the guidance (calculations and supporting data) in its development of the final Safety Evaluation documenting review of the licensee's Integrated Plan. During the audit process, the licensee stated that the FLEX strategy battery run time was determined in accordance with the IEEE 485 methodology.
The licensee's approach described above, as currently understood, is consistent with the guidance found in NEI 12-06, as endorsed by JLD-ISG-2012-01, and subject to the successful closure of issues related to the Confirmatory Items, provides reasonable assurance that the requirements of Order EA-12-049 will be met with respect to load reduction if these requirements are implemented as described.
The licensee's approach described above, as currently understood, is consistent with the guidance found in NEI 12-06, as endorsed by JLD-ISG-2012-01, and subject to the successful closure of issues related to the Confirmatory Items, provides reasonable assurance that the requirements of Order EA-12-049 will be met with respect to load reduction if these requirements are implemented as described.
3.3 PROGRAMMATIC CONTROLS 3.3.1 Equipment Maintenance and Testing.
3.3     PROGRAMMATIC CONTROLS 3.3.1 Equipment Maintenance and Testing.
NEI 12-06, Section 3.2.2, the paragraph following Guideline (15) states in part: In order to assure reliability and availability of the FLEX equipment required to meet these capabilities, the site should have sufficient equipment to address all functions at all units on-site, plus one additional spare, i.e., an N+1 capability, where "N" is the number of units on-site.
NEI 12-06, Section 3.2.2, the paragraph following Guideline (15) states in part:
Thus, a two-unit site would nominally have at least three portable pumps, three sets of portable ac/dc power supplies, three sets of hoses & cables, etc. It is also acceptable to have a single resource that is sized to support the required functions for multiple units at a site (e.g., a single pump capable of all water supply functions for a dual unit site). In this case, the N+1 could simply involve a second pump of equivalent capability.
In order to assure reliability and availability of the FLEX equipment required to meet these capabilities, the site should have sufficient equipment to address all functions at all units on-site, plus one additional spare, i.e., an N+1 capability, where "N" is the number of units on-site. Thus, a two-unit site would nominally have at least three portable pumps, three sets of portable ac/dc power supplies, three sets of hoses & cables, etc. It is also acceptable to have a single resource that is sized to support the required functions for multiple units at a site (e.g., a single pump capable of all water supply functions for a dual unit site). In this case, the N+1 could simply involve a second pump of equivalent capability. In addition, it is also acceptable to have multiple strategies to accomplish a function (e.g., two separate means to repower instrumentation). In this case the equipment associated with each strategy does not require N+1. The existing 50.54(hh)(2) pump and supplies can be counted toward the N+1, provided it meets the functional and storage requirements outlined in this guide. The N+1 capability applies to the portable FLEX equipment described in Tables 3-1 Revision 1                                   Page 51 of 60                                 2014-02-15
In addition, it is also acceptable to have multiple strategies to accomplish a function (e.g., two separate means to repower instrumentation).
 
In this case the equipment associated with each strategy does not require N+1. The existing 50.54(hh)(2) pump and supplies can be counted toward the N+1, provided it meets the functional and storage requirements outlined in this guide. The N+1 capability applies to the portable FLEX equipment described in Tables 3-1 Revision 1 Page 51 of 60 2014-02-15 and 3-2 (i.e., that equipment that directly supports maintenance of the key safety functions).
and 3-2 (i.e., that equipment that directly supports maintenance of the key safety functions). Other FLEX support equipment only requires an N capability.
Other FLEX support equipment only requires an N capability.
NEI 12-06, Section 11.5 states:
NEI 12-06, Section 11.5 states: 1. FLEX mitigation equipment should be initially tested or other reasonable means used to verify performance conforms to the limiting FLEX requirements.
: 1. FLEX mitigation equipment should be initially tested or other reasonable means used to verify performance conforms to the limiting FLEX requirements. Validation of source manufacturer quality is not required.
Validation of source manufacturer quality is not required.  
: 2. Portable equipment that directly performs a FLEX mitigation strategy for the core, containment, or SFP should be subject to maintenance and testing 1 guidance provided in INPO AP 913, Equipment Reliability Process, to verify proper function. The maintenance program should ensure that the FLEX equipment reliability is being achieved. Standard industry templates (e.g.,
: 2. Portable equipment that directly performs a FLEX mitigation strategy for the core, containment, or SFP should be subject to maintenance and testing 1 guidance provided in INPO AP 913, Equipment Reliability  
EPRI [Electric Power Research Institute]) and associated bases will be developed to define specific maintenance and testing including the following:
: Process, to verify proper function.
: a. Periodic testing and frequency should be determined based on equipment type and expected use. Testing should be done to verify design requirements and/or basis. The basis should be documented and deviations from vendor recommendations and applicable standards should be justified.
The maintenance program should ensure that the FLEX equipment reliability is being achieved.
: b. Preventive maintenance should be determined based on equipment type and expected use. The basis should be documented and deviations from vendor recommendations and applicable standards should be justified.
Standard industry templates (e.g., EPRI [Electric Power Research Institute])
: c. Existing work control processes may be used to control maintenance and testing. (e.g., PM Program, Surveillance Program, Vendor Contracts, and work orders).
and associated bases will be developed to define specific maintenance and testing including the following:  
: 3. The unavailability of equipment and applicable connections that directly performs a FLEX mitigation strategy for core, containment, and SFP should be managed such that risk to mitigating strategy capability is minimized.
: a. Periodic testing and frequency should be determined based on equipment type and expected use. Testing should be done to verify design requirements and/or basis. The basis should be documented and deviations from vendor recommendations and applicable standards should be justified.  
: a. The unavailability of installed plant equipment is controlled by existing plant processes such as the Technical Specifications. When installed plant equipment which supports FLEX strategies becomes unavailable, then the FLEX strategy affected by this unavailability does not need to be maintained during the unavailability.
: b. Preventive maintenance should be determined based on equipment type and expected use. The basis should be documented and deviations from vendor recommendations and applicable standards should be justified.  
: b. Portable equipment may be unavailable for 90 days provided that the site FLEX capability (N) is available.
: c. Existing work control processes may be used to control maintenance and testing.  
(e.g., PM Program, Surveillance  
: Program, Vendor Contracts, and work orders).  
: 3. The unavailability of equipment and applicable connections that directly performs a FLEX mitigation strategy for core, containment, and SFP should be managed such that risk to mitigating strategy capability is minimized.  
: a. The unavailability of installed plant equipment is controlled by existing plant processes such as the Technical Specifications.
When installed plant equipment which supports FLEX strategies becomes unavailable, then the FLEX strategy affected by this unavailability does not need to be maintained during the unavailability.  
: b. Portable equipment may be unavailable for 90 days provided that the site FLEX capability (N) is available.  
: c. Connections to permanent equipment required for FLEX strategies can be unavailable for 90 days provided alternate capabilities remain functional.
: c. Connections to permanent equipment required for FLEX strategies can be unavailable for 90 days provided alternate capabilities remain functional.
1 Testing includes surveillances, inspections, etc. Revision 1 Page 52 of 60 2014-02-15
1 Testing includes surveillances, inspections, etc.
: d. Portable equipment that is expected to be unavailable for more than 90 days or expected to be unavailable during forecast site specific external events (e.g., hurricane) should be supplemented with alternate suitable equipment.  
Revision 1                                     Page 52 of 60                             2014-02-15
: e. The short duration of equipment unavailability, discussed above, does not constitute a loss of reasonable protection from a diverse storage location protection strategy perspective.  
: d. Portable equipment that is expected to be unavailable for more than 90 days or expected to be unavailable during forecast site specific external events (e.g., hurricane) should be supplemented with alternate suitable equipment.
: f. If portable equipment becomes unavailable such that the site FLEX capability (N) is not maintained, initiate actions within 24 hours to restore the site FLEX capability (N) and implement compensatory measures (e.g., use of alternate suitable equipment or supplemental personnel) within 72 hours. On pages 9 and 10, in the section of the Integrated Plan discussing programmatic  
: e. The short duration of equipment unavailability, discussed above, does not constitute a loss of reasonable protection from a diverse storage location protection strategy perspective.
: controls, the licensee stated that JAF will implement an administrative program for implementation and maintenance of the FLEX strategies in accordance with NEI 12-06 guidance.
: f. If portable equipment becomes unavailable such that the site FLEX capability (N) is not maintained, initiate actions within [[estimated NRC review hours::24 hours]] to restore the site FLEX capability (N) and implement compensatory measures (e.g., use of alternate suitable equipment or supplemental personnel) within [[estimated NRC review hours::72 hours]].
* Installed structures, systems and components currently designed and installed meet augmented quality guidelines (e.g., equipment installed to address 1 OCFR50.48, Fire Protection, or 1 OCFR50.63, Station Blackout) will continue to meet the augmented quality guidelines.
On pages 9 and 10, in the section of the Integrated Plan discussing programmatic controls, the licensee stated that JAF will implement an administrative program for implementation and maintenance of the FLEX strategies in accordance with NEI 12-06 guidance.
* JAF will utilize the standard EPRI industry PM process for establishing the maintenance actions for FLEX components.
* Installed structures, systems and components currently designed and installed meet augmented quality guidelines (e.g., equipment installed to address 10CFR50.48, Fire Protection, or 10CFR50.63, Station Blackout) will continue to meet the augmented quality guidelines.
Preventive maintenance procedures will be established for portable components that directly perform in the mitigating strategy for the key FLEX safety functions (i.e., core cooling, containment integrity, and spent fuel cooling.)
* JAF will utilize the standard EPRI industry PM process for establishing the maintenance actions for FLEX components. Preventive maintenance procedures will be established for portable components that directly perform in the mitigating strategy for the key FLEX safety functions (i.e., core cooling, containment integrity, and spent fuel cooling.) These procedures will consider NEI 12-06 guidance, vendor recommendations, and applicable industry standards.
These procedures will consider NEI 12-06 guidance, vendor recommendations, and applicable industry standards.
* Testing procedures will be developed and performed at frequencies established based on type of equipment and considerations made within EPRI guidelines.
* Testing procedures will be developed and performed at frequencies established based on type of equipment and considerations made within EPRI guidelines.
The NRC staff reviewed the Integrated Plan for JAF and determined that the Generic Concern related to maintenance and testing of FLEX equipment is applicable to the plant. This Generic Concern has been resolved generically through the NRC endorsement of the EPRI technical report on preventive maintenance of FLEX equipment, submitted by NEI by letter dated October 3, 2013 (ADAMS Accession No. ML 13276A573).
The NRC staff reviewed the Integrated Plan for JAF and determined that the Generic Concern related to maintenance and testing of FLEX equipment is applicable to the plant. This Generic Concern has been resolved generically through the NRC endorsement of the EPRI technical report on preventive maintenance of FLEX equipment, submitted by NEI by letter dated October 3, 2013 (ADAMS Accession No. ML13276A573). The NRC staff's endorsement letter is dated October 7, 2013 (ADAMS Accession No. ML13276A224).
The NRC staff's endorsement letter is dated October 7, 2013 (ADAMS Accession No. ML 13276A224).
This Generic Concern involves clarification of how licensees would maintain FLEX equipment such that it would be readily available for use. The technical report provided sufficient basis to resolve this concern by describing a database that licensees could use to develop preventative maintenance programs for FLEX equipment. The database describes maintenance tasks and maintenance intervals that have been evaluated as sufficient to provide for the readiness of the FLEX equipment. The NRC staff has determined that the technical report provides an acceptable approach for developing a program for maintaining FLEX equipment in a ready-to-use status.
This Generic Concern involves clarification of how licensees would maintain FLEX equipment such that it would be readily available for use. The technical report provided sufficient basis to resolve this concern by describing a database that licensees could use to develop preventative maintenance programs for FLEX equipment.
Revision 1                                     Page 53 of 60                                 2014-02-15
The database describes maintenance tasks and maintenance intervals that have been evaluated as sufficient to provide for the readiness of the FLEX equipment.
 
The NRC staff has determined that the technical report provides an acceptable approach for developing a program for maintaining FLEX equipment in a use status. Revision 1 Page 53 of 60 2014-02-15 During the audit process, the licensee informed the NRC of JAF's plans to abide by this generic resolution.
During the audit process, the licensee informed the NRC of JAF's plans to abide by this generic resolution. The NRC staff will evaluate the resulting program through the audit and inspection processes.
The NRC staff will evaluate the resulting program through the audit and inspection processes.
The licensee's approach described above, as currently understood, is consistent with the guidance found in NEI 12-06, as endorsed by JLD-ISG-2012-01 and provides reasonable assurance that the requirements of Order EA-12-049 will be met with respect to maintenance and testing if these requirements are implemented as described.
The licensee's approach described above, as currently understood, is consistent with the guidance found in NEI 12-06, as endorsed by JLD-ISG-2012-01 and provides reasonable assurance that the requirements of Order EA-12-049 will be met with respect to maintenance and testing if these requirements are implemented as described.
3.3.2 Configuration Control.
3.3.2 Configuration Control.
NEI 12-06, Section 11.8 states: 1. The FLEX strategies and basis will be maintained in an overall program document.
NEI 12-06, Section 11.8 states:
This program document will also contain a historical record of previous strategies and the basis for changes.
: 1. The FLEX strategies and basis will be maintained in an overall program document. This program document will also contain a historical record of previous strategies and the basis for changes. The document will also contain the basis for the ongoing maintenance and testing programs chosen for the FLEX equipment.
The document will also contain the basis for the ongoing maintenance and testing programs chosen for the FLEX equipment.  
: 2. Existing plant configuration control procedures will be modified to ensure that changes to the plant design, physical plant layout, roads, buildings, and miscellaneous structures will not adversely impact the approved FLEX strategies.
: 2. Existing plant configuration control procedures will be modified to ensure that changes to the plant design, physical plant layout, roads, buildings, and miscellaneous structures will not adversely impact the approved FLEX strategies.  
: 3. Changes to FLEX strategies may be made without prior NRC approval provided:
: 3. Changes to FLEX strategies may be made without prior NRC approval provided:
a) The revised FLEX strategy meets the requirements of this guideline.
a) The revised FLEX strategy meets the requirements of this guideline.
b) An engineering basis is documented that ensures that the change in FLEX strategy continues to ensure the key safety functions (core and SFP cooling, containment integrity) are met. On pages 9, in the section of the Integrated Plan discussing programmatic  
b) An engineering basis is documented that ensures that the change in FLEX strategy continues to ensure the key safety functions (core and SFP cooling, containment integrity) are met.
: controls, the licensee stated that JAF will implement an administrative program for implementation and maintenance of the FLEX strategies in accordance with NEI 12-06 guidance.
On pages 9, in the section of the Integrated Plan discussing programmatic controls, the licensee stated that JAF will implement an administrative program for implementation and maintenance of the FLEX strategies in accordance with NEI 12-06 guidance.
On page 15, in the section of the Integrated Plan discussing procedures and guidance, the licensee stated that JAF will utilize the industry-developed guidance from the Owners Groups, EPRI and NEI Task team to develop site-specific procedures and guidelines to address the criteria in NEI 12-06. These procedures and/or guidelines will support the existing symptom based command and control strategies in the current EOPs. On page 19, in the section of the Integrated Plan discussing storage and protection of equipment, the licensee stated that locations I structures to provide protection of the FLEX equipment will be fabricated I constructed to meet the requirements identified in NEI 12-06, Section 11. JAF procedures and programs are being developed to address storage structure requirements, haul path requirements, and FLEX equipment requirements relative to the hazards applicable to JAF. The licensee's approach described above, as currently understood, is consistent with the guidance found in NEI 12-06, as endorsed by JLD-ISG-2012-01, and provides reasonable Revision 1 Page 54 of 60 2014-02-15 assurance that the requirements of Order EA-12-049 will be met with respect to configuration control if these requirements are implemented as described.
On page 15, in the section of the Integrated Plan discussing procedures and guidance, the licensee stated that JAF will utilize the industry-developed guidance from the Owners Groups, EPRI and NEI Task team to develop site-specific procedures and guidelines to address the criteria in NEI 12-06. These procedures and/or guidelines will support the existing symptom based command and control strategies in the current EOPs.
On page 19, in the section of the Integrated Plan discussing storage and protection of equipment, the licensee stated that locations I structures to provide protection of the FLEX equipment will be fabricated I constructed to meet the requirements identified in NEI 12-06, Section 11. JAF procedures and programs are being developed to address storage structure requirements, haul path requirements, and FLEX equipment requirements relative to the hazards applicable to JAF.
The licensee's approach described above, as currently understood, is consistent with the guidance found in NEI 12-06, as endorsed by JLD-ISG-2012-01, and provides reasonable Revision 1                                 Page 54 of 60                               2014-02-15
 
assurance that the requirements of Order EA-12-049 will be met with respect to configuration control if these requirements are implemented as described.
3.3.3 Training.
3.3.3 Training.
NEI 12-06, Section 11.6 states: 1. Programs and controls should be established to assure personnel proficiency in the mitigation of beyond-design-basis events is developed and maintained.
NEI 12-06, Section 11.6 states:
These programs and controls should be implemented in accordance with an accepted training process.2 2. Periodic training should be provided to site emergency response leaders3 on beyond design-basis emergency response strategies and implementing guidelines.
: 1. Programs and controls should be established to assure personnel proficiency in the mitigation of beyond-design-basis events is developed and maintained.
Operator training for beyond-design-basis event accident mitigation should not be given undue weight in comparison with other training requirements.
These programs and controls should be implemented in accordance with an accepted training process. 2
The testing/evaluation of Operator knowledge and skills in this area should be similarly weighted.  
: 2. Periodic training should be provided to site emergency response leaders 3 on beyond design-basis emergency response strategies and implementing guidelines. Operator training for beyond-design-basis event accident mitigation should not be given undue weight in comparison with other training requirements. The testing/evaluation of Operator knowledge and skills in this area should be similarly weighted.
: 3. Personnel assigned to direct the execution of mitigation strategies for beyond-design basis events will receive necessary training to ensure familiarity with the associated tasks, considering available job aids, instructions, and mitigating strategy time constraints.  
: 3. Personnel assigned to direct the execution of mitigation strategies for beyond-design basis events will receive necessary training to ensure familiarity with the associated tasks, considering available job aids, instructions, and mitigating strategy time constraints.
: 4. "ANSI/ANS 3.5, Nuclear Power Plant Simulators for use in Operator Training" certification of simulator fidelity (if used) is considered to be sufficient for the initial stages of the beyond-design-basis external event scenario until the current capability of the simulator model is exceeded.
: 4. "ANSI/ANS 3.5, Nuclear Power Plant Simulators for use in Operator Training" certification of simulator fidelity (if used) is considered to be sufficient for the initial stages of the beyond-design-basis external event scenario until the current capability of the simulator model is exceeded. Full scope simulator models will not be upgraded to accommodate FLEX training or drills.
Full scope simulator models will not be upgraded to accommodate FLEX training or drills. 5. Where appropriate, the integrated FLEX drills should be organized on a team or crew basis and conducted periodically; with all time-sensitive actions to be evaluated over a period of not more than eight years. It is not the intent to connect to or operate permanently installed equipment during these drills and demonstrations.
: 5. Where appropriate, the integrated FLEX drills should be organized on a team or crew basis and conducted periodically; with all time-sensitive actions to be evaluated over a period of not more than eight years. It is not the intent to connect to or operate permanently installed equipment during these drills and demonstrations.
On page 10, in the section of the Integrated Plan discussing the general plan elements and the training plan, the licensee stated the new training of general station staff and the Emergency Response Organization will be performed prior to design implementation.
On page 10, in the section of the Integrated Plan discussing the general plan elements and the training plan, the licensee stated the new training of general station staff and the Emergency Response Organization will be performed prior to design implementation. The licensee stated that these programs and controls will be implemented in accordance with the Systematic Approach to Training and NEI 12-06 guidance.
The licensee stated that these programs and controls will be implemented in accordance with the Systematic Approach to Training and NEI 12-06 guidance.
The licensee's approach described above, as currently understood, is consistent with the guidance found in NEI 12-06, as endorsed by JLD-ISG-2012-01, and provides reasonable assurance that the requirements of Order EA-12-049 will be met with respect to training if these requirements are implemented as described.
The licensee's approach described above, as currently understood, is consistent with the guidance found in NEI 12-06, as endorsed by JLD-ISG-2012-01, and provides reasonable assurance that the requirements of Order EA-12-049 will be met with respect to training if these requirements are implemented as described.
2 The Systematic Approach to Training (SAT) is recommended.
2 The Systematic Approach to Training (SAT) is recommended.
3 Emergency response leaders are those utility emergency roles, as defined by the Emergency Plan, for managing emergency response to design basis and beyond-design-basis plant emergencies.
3 Emergency response leaders are those utility emergency roles, as defined by the Emergency Plan, for managing emergency response to design basis and beyond-design-basis plant emergencies.
Revision 1 Page 55 of 60 2014-02-15 3.4 OFF SITE RESOURCES NEI 12-06, Section 12.2 lists the following minimum capabilities for offsite resources for which each licensee should establish the availability of: 1) A capability to obtain equipment and commodities to sustain and backup the site's coping strategies.  
Revision 1                                     Page 55 of 60                                   2014-02-15
: 2) Off-site equipment procurement, maintenance,  
 
: testing, calibration,  
3.4 OFF SITE RESOURCES NEI 12-06, Section 12.2 lists the following minimum capabilities for offsite resources for which each licensee should establish the availability of:
: storage, and control.  
: 1) A capability to obtain equipment and commodities to sustain and backup the site's coping strategies.
: 3) A provision to inspect and audit the contractual agreements to reasonably assure the capabilities to deploy the FLEX strategies including unannounced random inspections by the Nuclear Regulatory Commission.  
: 2) Off-site equipment procurement, maintenance, testing, calibration, storage, and control.
: 4) Provisions to ensure that no single external event will preclude the capability to supply the needed resources to the plant site. 5) Provisions to ensure that the off-site capability can be maintained for the life of the plant. 6) Provisions to revise the required supplied equipment due to changes in the FLEX strategies or plant equipment or equipment obsolescence.  
: 3) A provision to inspect and audit the contractual agreements to reasonably assure the capabilities to deploy the FLEX strategies including unannounced random inspections by the Nuclear Regulatory Commission.
: 7) The appropriate standard mechanical and electrical connections need to be specified.  
: 4) Provisions to ensure that no single external event will preclude the capability to supply the needed resources to the plant site.
: 8) Provisions to ensure that the periodic maintenance, periodic maintenance  
: 5) Provisions to ensure that the off-site capability can be maintained for the life of the plant.
: schedule, testing, and calibration of off-site equipment are comparable/consistent with that of similar on-site FLEX equipment.  
: 6) Provisions to revise the required supplied equipment due to changes in the FLEX strategies or plant equipment or equipment obsolescence.
: 9) Provisions to ensure that equipment determined to be operational during maintenance or testing is either restored to operational status or replaced with appropriate alternative equipment within 90 days. 1 0) Provision to ensure that reasonable supplies of spare parts for the off-site equipment are readily available if needed. The intent of this provision is to reduce the likelihood of extended equipment maintenance (requiring in excess of 90 days for returning the equipment to operational status).
: 7) The appropriate standard mechanical and electrical connections need to be specified.
: 8) Provisions to ensure that the periodic maintenance, periodic maintenance schedule, testing, and calibration of off-site equipment are comparable/consistent with that of similar on-site FLEX equipment.
: 9) Provisions to ensure that equipment determined to be unavailable/non-operational during maintenance or testing is either restored to operational status or replaced with appropriate alternative equipment within 90 days.
: 10) Provision to ensure that reasonable supplies of spare parts for the off-site equipment are readily available if needed. The intent of this provision is to reduce the likelihood of extended equipment maintenance (requiring in excess of 90 days for returning the equipment to operational status).
On page 10, in the section of the Integrated Plan discussing the RRC in the general Integrated Plan elements, the licensee stated that the industry has selected a vendor to manage two RRC to provide large equipment in support of the response to BDBEE. Each RRC will store and maintain five sets of equipment, four of which are expected to be fully deployable upon request.
On page 10, in the section of the Integrated Plan discussing the RRC in the general Integrated Plan elements, the licensee stated that the industry has selected a vendor to manage two RRC to provide large equipment in support of the response to BDBEE. Each RRC will store and maintain five sets of equipment, four of which are expected to be fully deployable upon request.
The fifth set is provided to account for equipment that may be unavailable due to its maintenance and testing cycle. As currently envisioned, the two RRC facilities will be located in Memphis, TN and Phoenix, AZ. JAF will utilize the industry RRC for Phase 3 equipment.
The fifth set is provided to account for equipment that may be unavailable due to its maintenance and testing cycle. As currently envisioned, the two RRC facilities will be located in Memphis, TN and Phoenix, AZ.
In an ELAP event, communications would be established between JAF and the industry SAFER team and required equipment mobilized as needed. JAF will enter into a contractual agreement with the SAFER team. Equipment will initially be moved from an RRC to a local staging Revision 1 Page 56 of 60 2014-02-15 area, established by the SAFER team and JAF. The equipment will be prepared at the staging area prior to transportation to the site. The licensee stated that first arriving equipment, as established during development of the RRC playbook, will be delivered to the site within 24 hours from the initial request.
JAF will utilize the industry RRC for Phase 3 equipment. In an ELAP event, communications would be established between JAF and the industry SAFER team and required equipment mobilized as needed. JAF will enter into a contractual agreement with the SAFER team. Equipment will initially be moved from an RRC to a local staging Revision 1                                 Page 56 of 60                                 2014-02-15
The licensee's use of off-site resources, as described above, conforms to the guidance found in NEI 12-06, Section 12.2, with regard to the capability to obtain equipment and commodities to sustain and backup the site's coping strategies (Guideline 1 ). However, insufficient information has been included to provide reasonable assurance that guidance will be established to conform to the remaining items of NEI 12-06, Section 12.2 (Guidelines 2 through 1 0). This has been identified as Open Item 3.4.A, in Section 4.1. The licensee's approach described above, as currently understood, is consistent with the guidance found in NEI 12-06, as endorsed by JLD-ISG-2012-01, and subject to the successful closure of issues related to the Open Item, provides reasonable assurance that the requirements of Order EA-12-049 will be met with respect to offsite resources if these requirements are implemented as described.
 
4.0 OPEN ITEMS AND CONFIRMATORY ITEMS 4.1 OPEN ITEMS Item Number Description Notes 3.1.1.3.A Procedural Interface (Seismic Hazard) -Evaluate the impacts from large internal flooding sources.
area, established by the SAFER team and JAF. The equipment will be prepared at the staging area prior to transportation to the site. The licensee stated that first arriving equipment, as established during development of the RRC playbook, will be delivered to the site within [[estimated NRC review hours::24 hours]] from the initial request.
3.1.3.1.A Protection of FLEX Equipment (High Wind Hazard) -Evaluate Significant the separation distance and the axis of separation considering the predominant path of tornados in the geographic area to demonstrate that at least N sets of FLEX equipment would remain deployable in the context of a tornado missile hazard. 3.1.4.2.8 Deployment of FLEX Equipment (Snow, Ice and Extreme Cold) -Evaluate the potential impact on the UHS due to ice blockage or formation of frazil ice as a result of extreme cold. 3.2.3.A Containment-Confirm that the implementation of Boiling Water Reactor Owners Group (BWROG) Emergency Procedure Guideline (EPG)/Severe Accident Guideline (SAG), Revision 3, including any associated plant-specific evaluations, will be completed in accordance with the provisions of NRC letter dated January 9, 2014 3.4.A Off-site Resources-Review how conformance with NEI 12-06, Section 12.2 guidelines 2 through 10 is being met. Revision 1 Page 57 of 60 2014-02-15 4.2 CONFIRMATORY ITEMS Item Number Description Notes 3.1.1.2.A Deployment of FLEX Equipment  
The licensee's use of off-site resources, as described above, conforms to the guidance found in NEI 12-06, Section 12.2, with regard to the capability to obtain equipment and commodities to sustain and backup the site's coping strategies (Guideline 1). However, insufficient information has been included to provide reasonable assurance that guidance will be established to conform to the remaining items of NEI 12-06, Section 12.2 (Guidelines 2 through 10). This has been identified as Open Item 3.4.A, in Section 4.1.
-Review the potential for soil liquefaction that might impede vehicle movement following a seismic event. 3.1.1.2.8 Deployment of FLEX Equipment  
The licensee's approach described above, as currently understood, is consistent with the guidance found in NEI 12-06, as endorsed by JLD-ISG-2012-01, and subject to the successful closure of issues related to the Open Item, provides reasonable assurance that the requirements of Order EA-12-049 will be met with respect to offsite resources if these requirements are implemented as described.
-Confirm final design features of the new storage building including the susceptibility to the loss of ac power. Reliance on ac power, if any, to deploy eg_uipment is to be evaluated.
4.0     OPEN ITEMS AND CONFIRMATORY ITEMS 4.1     OPEN ITEMS Item Number       Description                                                           Notes 3.1.1.3.A         Procedural Interface (Seismic Hazard) -Evaluate the impacts from large internal flooding sources.
3.1.1.2.C Deployment of FLEX Equipment-Verify the storage locations and means of protection against the seismic hazard of the super duty pickup trucks and the two flatbed trailers used for deployment of FLEX equipment.
3.1.3.1.A         Protection of FLEX Equipment (High Wind Hazard) - Evaluate             Significant the separation distance and the axis of separation considering the predominant path of tornados in the geographic area to demonstrate that at least N sets of FLEX equipment would remain deployable in the context of a tornado missile hazard.
3.1.1.4.A Offsite Resources-Confirm location of offsite staging area(s),
3.1.4.2.8         Deployment of FLEX Equipment (Snow, Ice and Extreme Cold)
                    - Evaluate the potential impact on the UHS due to ice blockage or formation of frazil ice as a result of extreme cold.
3.2.3.A           Containment- Confirm that the implementation of Boiling Water Reactor Owners Group (BWROG) Emergency Procedure Guideline (EPG)/Severe Accident Guideline (SAG), Revision 3, including any associated plant-specific evaluations, will be completed in accordance with the provisions of NRC letter dated January 9, 2014 3.4.A             Off-site Resources- Review how conformance with NEI 12-06, Section 12.2 guidelines 2 through 10 is being met.
Revision 1                                   Page 57 of 60                               2014-02-15
 
4.2     CONFIRMATORY ITEMS Item Number     Description                                                       Notes 3.1.1.2.A       Deployment of FLEX Equipment -Review the potential for soil liquefaction that might impede vehicle movement following a seismic event.
3.1.1.2.8       Deployment of FLEX Equipment -Confirm final design features of the new storage building including the susceptibility to the loss of ac power. Reliance on ac power, if any, to deploy eg_uipment is to be evaluated.
3.1.1.2.C       Deployment of FLEX Equipment- Verify the storage locations and means of protection against the seismic hazard of the super duty pickup trucks and the two flatbed trailers used for deployment of FLEX equipment.
3.1.1.4.A       Offsite Resources- Confirm location of offsite staging area(s),
access routes and methods of delivery of equipment to the site considering the seismic, flood, high wind, snow, ice and extreme cold hazards.
access routes and methods of delivery of equipment to the site considering the seismic, flood, high wind, snow, ice and extreme cold hazards.
3.1.3.2.A Deployment of FLEX Equipment (High Wind Hazard) -Confirm availability of debris removal equipment to facilitate deployment of FLEX equipment.
3.1.3.2.A       Deployment of FLEX Equipment (High Wind Hazard) - Confirm availability of debris removal equipment to facilitate deployment of FLEX equipment.
3.1.3.2.8 Deployment of FLEX Equipment (High Wind Hazard) -Confirm protection of the means to move FLEX equipment.
3.1.3.2.8       Deployment of FLEX Equipment (High Wind Hazard) - Confirm protection of the means to move FLEX equipment.
3.1.4.2.A Deployment of FLEX Equipment (Snow, Ice and Extreme Cold) -Confirm availability of snow removal equipment to facilitate deQioyment of FLEX e_guipment.
3.1.4.2.A     Deployment of FLEX Equipment (Snow, Ice and Extreme Cold)
3.2.1.1.A Computer Code Used for ELAP Analysis-Benchmarks need to be identified and discussed which demonstrate that MAAP is an appropriate code for the simulation of an ELAP event at JAF. 3.2.1.1.8 Computer Code Used for ELAP Analysis  
              - Confirm availability of snow removal equipment to facilitate deQioyment of FLEX e_guipment.
-Confirm that the collapsed level remains above Top of Active Fuel (TAF) and the cool down rate is within technical specifications limits. 3.2.1.1.C Computer Code Used for ELAP Analysis-Confirm that MAAP was used in accordance with Sections 4.1, 4.2, 4.3, 4.4, and 4.5 of the June 2013 position paper (ADAMS Accession No. ML 13190A201
3.2.1.1.A     Computer Code Used for ELAP Analysis-Benchmarks need to be identified and discussed which demonstrate that MAAP is an appropriate code for the simulation of an ELAP event at JAF.
). 3.2.1.1.D Computer Code Used for ELAP Analysis-Confirm that the licensee, in using MAAP, identified and justified the subset of key modeling parameters cited from Tables 4-1 through 4-6 of the "MAAP Application  
3.2.1.1.8     Computer Code Used for ELAP Analysis -Confirm that the collapsed level remains above Top of Active Fuel (TAF) and the cool down rate is within technical specifications limits.
: Guidance, Desktop Reference for Using MAAP Software, Revision 2" (Electric Power Research Institute Report 1 020236).
3.2.1.1.C     Computer Code Used for ELAP Analysis- Confirm that MAAP was used in accordance with Sections 4.1, 4.2, 4.3, 4.4, and 4.5 of the June 2013 position paper (ADAMS Accession No. ML13190A201 ).
Revision 1 Page 58 of 60 2014-02-15 3.2.1.1.E Computer Code Used for ELAP Analysis-Confirm that the specific MAAP analysis case that was used to validate the timing of mitigating strategies in the Integrated Plan has been identified and is available for NRC staff to review. Alternately, a comparable level of information has been included in the supplemental response.
3.2.1.1.D     Computer Code Used for ELAP Analysis- Confirm that the licensee, in using MAAP, identified and justified the subset of key modeling parameters cited from Tables 4-1 through 4-6 of the "MAAP Application Guidance, Desktop Reference for Using MAAP Software, Revision 2" (Electric Power Research Institute Report 1020236).
In either case, the analysis should include a plot of the collapsed vessel level to confirm that T AF is not reached (the elevation of the T AF should be provided) and a plot of the temperature cool down to confirm that the cool down is within technical limits. 3.2.1.2.A Recirculation Pump Seal Leakage Models-Confirm the seal leakage model used in the updated MAAP analysis (which will address the MAAP code limitations when used for ELAP analysis).
Revision 1                               Page 58 of 60                           2014-02-15
Evaluate the seal leakage rate model used, the details of the seal qualification tests and supporting test data, and leakage rate pressure-dependence.
 
3.2.1.3.A Sequence of Events-Confirm the sequence of events timeline after reanalysis using the MAAP code which will address the limitations when used for the ELAP analysis.
3.2.1.1.E   Computer Code Used for ELAP Analysis- Confirm that the specific MAAP analysis case that was used to validate the timing of mitigating strategies in the Integrated Plan has been identified and is available for NRC staff to review. Alternately, a comparable level of information has been included in the supplemental response. In either case, the analysis should include a plot of the collapsed vessel level to confirm that TAF is not reached (the elevation of the TAF should be provided) and a plot of the temperature cool down to confirm that the cool down is within technical s~ecifications limits.
3.2.1.4.A Systems and Components for Consequence Mitigation  
3.2.1.2.A Recirculation Pump Seal Leakage Models-Confirm the seal leakage model used in the updated MAAP analysis (which will address the MAAP code limitations when used for ELAP analysis). Evaluate the seal leakage rate model used, the details of the seal qualification tests and supporting test data, and leakage rate pressure-dependence.
-Confirm sizing of the FLEX pumps and 600 Vac FLEX DG and the 4160 Vac generator to be obtained from the RRC. 3.2.1.5.A Monitoring Instrumentation and Controls  
3.2.1.3.A Sequence of Events- Confirm the sequence of events timeline after reanalysis using the MAAP code which will address the limitations when used for the ELAP analysis.
-Confirm ac powered torus temperature, pressure and level and drywell temperature and pressure instrumentation is modified to remain powered during an ELAP. 3.2.1.8.A Use of Portable Pumps-Evaluate impacts of using raw water from Lake Ontario for long term core and spent fuel pool cooling strategies.
3.2.1.4.A Systems and Components for Consequence Mitigation -
3.2.2.A Spent Fuel Pool Cooling-Confirm the method of ventilation and power requirements, if any, of the spent fuel pool area. 3.2.4.2.A Ventilation (Equipment Cooling)  
Confirm sizing of the FLEX pumps and 600 Vac FLEX DG and the 4160 Vac generator to be obtained from the RRC.
-Confirm that additional evaluations of the RCIC room temperature demonstrate that an acceptable environment is maintained during the transition phase both for equipment in the room and habitability for operators who may need to enter the room. 3.2.4.2.8 Ventilation (Equipment Cooling)  
3.2.1.5.A Monitoring Instrumentation and Controls -Confirm ac powered torus temperature, pressure and level and drywell temperature and pressure instrumentation is modified to remain powered during an ELAP.
-Confirm that evaluations of the battery room temperature demonstrate that an acceptable environment, during both high ambient temperature and during extreme cold ambient temperature, is maintained during Phases 2 and 3. 3.2.4.2.C Ventilation (Equipment Cooling)  
3.2.1.8.A Use of Portable Pumps- Evaluate impacts of using raw water from Lake Ontario for long term core and spent fuel pool cooling strategies.
-Confirm the required ventilation flow or the size of the portable fans to maintain acceptable environmental conditions in the DC equipment room. 3.2.4.3.A Heat Tracing-Confirm completion of walkdowns and evaluation of where heat tracing may be needed for freeze protection of equipment or instruments used in the ELAP mitigation strategies.
3.2.2.A   Spent Fuel Pool Cooling-Confirm the method of ventilation and power requirements, if any, of the spent fuel pool area.
Revision 1 Page 59 of 60 2014-02-15 3.2.4.4.A Lighting-Confirm need for additional portable  
3.2.4.2.A Ventilation (Equipment Cooling) - Confirm that additional evaluations of the RCIC room temperature demonstrate that an acceptable environment is maintained during the transition phase both for equipment in the room and habitability for operators who may need to enter the room.
: lighting, such as de powered lights. 3.2.4.4.8 Communications  
3.2.4.2.8 Ventilation (Equipment Cooling) - Confirm that evaluations of the battery room temperature demonstrate that an acceptable environment, during both high ambient temperature and during extreme cold ambient temperature, is maintained during Phases 2 and 3.
-Confirm that upgrades to the site's communication system have been completed.
3.2.4.2.C Ventilation (Equipment Cooling) -Confirm the required ventilation flow or the size of the portable fans to maintain acceptable environmental conditions in the DC equipment room.
3.2.4.8.A Electrical Power Sources-Confirm the technical basis for the selection and size of the FLEX generators to be used in support of the coping strategies.
3.2.4.3.A Heat Tracing- Confirm completion of walkdowns and evaluation of where heat tracing may be needed for freeze protection of equipment or instruments used in the ELAP mitigation strategies.
3.2.4.10.A Load Reduction to Conserve DC Power-Confirm final load shed list and the evaluation of any potential adverse effects of shedding those loads. 3.2.4.10.8 Load Reduction to Conserve DC Power-Confirm the final de load profile with the required loads and the finalized minimum battery voltage.
Revision 1                           Page 59 of 60                             2014-02-15
3.2.4.10.C Load Reduction to Conserve DC Power-Confirm time after the ELAP for connecting the FLEX DG to the battery chargers.
 
Revision 1 Page 60 of 60 2014-02-15   If you have any questions, please contact John Boska at 301-415-2901.
3.2.4.4.A Lighting- Confirm need for additional portable lighting, such as de powered lights.
Docket No. 50-333  
3.2.4.4.8 Communications - Confirm that upgrades to the site's communication system have been completed.
3.2.4.8.A Electrical Power Sources- Confirm the technical basis for the selection and size of the FLEX generators to be used in support of the coping strategies.
3.2.4.10.A Load Reduction to Conserve DC Power- Confirm final load shed list and the evaluation of any potential adverse effects of shedding those loads.
3.2.4.10.8 Load Reduction to Conserve DC Power- Confirm the final de load profile with the required loads and the finalized minimum battery voltage.
3.2.4.10.C Load Reduction to Conserve DC Power- Confirm time after the ELAP for connecting the FLEX DG to the battery chargers.
Revision 1                         Page 60 of 60                           2014-02-15
 
If you have any questions, please contact John Boska at 301-415-2901.
Sincerely, IRA/
Jeremy S. Bowen, Chief Mitigating Strategies Projects Branch Mitigating Strategies Directorate Office of Nuclear Reactor Regulation Docket No. 50-333


==Enclosures:==
==Enclosures:==
: 1. Interim Staff Evaluation  
: 1. Interim Staff Evaluation
: 2. Technical Evaluation Report Sincerely, IRA/ Jeremy S. Bowen, Chief Mitigating Strategies Projects Branch Mitigating Strategies Directorate Office of Nuclear Reactor Regulation cc w/encl: Distribution via Listserv DISTRIBUTION PUBLIC LPL 1-1 R/F RidsNrrDorllpl1-1 Resource RidsNrrPMFitzPatrick Resource RidsNrrLASLent Resource RidsAcrsAcnw_MaiiCTR Resource RidsRgn1 MaiiCenter Resource JBoska, NRRIMSD JBowen, NRRIMSD ADAMS A ccess1on N Pk ML14007A679 L tt /ISE ML14007A681 TER ML14043A428 OS. (Q , e er ' *V" "I 1aema1 OFFICE NRRIMSD/MSPB/PM NRRIMSD/LA NRRIMSD/SA*
: 2. Technical Evaluation Report cc w/encl: Distribution via Listserv DISTRIBUTION PUBLIC                                               RidsRgn1 MaiiCenter Resource LPL 1-1 R/F                                           JBoska, NRRIMSD RidsNrrDorllpl1-1 Resource                           JBowen, NRRIMSD RidsNrrPMFitzPatrick Resource RidsNrrLASLent Resource RidsAcrsAcnw_MaiiCTR Resource ADAMS A ccess1on NOS. Pk(Q ML14007A679 , Le tter/ISE ML14007A681 TER ML14043A428         *V"1aema1"I OFFICE       NRRIMSD/MSPB/PM     NRRIMSD/LA               NRRIMSD/SA*           NRR/MSD/MSPB/BC*
NRR/MSD/MSPB/BC*
NAME         JBoska             Slent                     EBowman               JBowen DATE         02/19/14           02/19/14                 02/19/14               02/19/14 OFFICE       NRRIMSD/MESB/BC*   NRRIMSD/MRSB/BC*         NRRIMSD/D             NRRIMSD/MSPB/BC NAME         SBailey             SWhaley                 JDavis (JBowen for)   JBowen DATE         02/19/14           02/19/14                 02/21/14               02/21/14 OFFICIAL RECORD COPY}}
NAME JBoska Slent EBowman JBowen DATE 02/19/14 02/19/14 02/19/14 02/19/14 OFFICE NRRIMSD/MESB/BC*
NRRIMSD/MRSB/BC*
NRRIMSD/D NRRIMSD/MSPB/BC NAME SBailey SWhaley JDavis (JBowen for) JBowen DATE 02/19/14 02/19/14 02/21/14 02/21/14 OFFICIAL RECORD COPY}}

Latest revision as of 00:06, 6 February 2020

Interim Staff Evaluation Relating to Overall Integrated Plan in Response to Order EA-12-049 (Mitigation Strategies)
ML14007A681
Person / Time
Site: FitzPatrick Constellation icon.png
Issue date: 02/21/2014
From: Jeremy Bowen
NRC/NRR/DPR/MSD/MSPB
To:
Entergy Nuclear Operations
Lent S, NRR/DPR, 415-1365
Shared Package
ML14007A679 List:
References
EA-12-049, Job Code J4672, NRC-HQ-13-C-03-0039, TAC MF1077
Download: ML14007A681 (76)


Text

UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 February 21, 2014 Vice President, Operations Entergy Nuclear Operations, Inc.

James A. FitzPatrick Nuclear Power Plant P.O. Box 110 Lycoming, NY 13093

SUBJECT:

JAMES A. FITZPATRICK NUCLEAR POWER PLANT- INTERIM STAFF EVALUATION RELATING TO OVERALL INTEGRATED PLAN IN RESPONSE TO ORDER EA-12-049 (MITIGATION STRATEGIES) (TAC NO. MF1077)

Dear Sir or Madam:

On March 12, 2012, the U.S. Nuclear Regulatory Commission (NRC) issued Order EA-12-049, "Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events" (Agencywide Documents Access and Management System (ADAMS) Accession No. ML12054A736). By letter dated February 28, 2013 (ADAMS Accession No. ML13063A262), Entergy Nuclear Operations, Inc. (Entergy, the licensee) submitted its Overall Integrated Plan for James A. FitzPatrick Nuclear Power Plant in response to Order EA-12-049. By letter dated August 28, 2013 (ADAMS Accession No. ML13241A204),

Entergy submitted a six-month update to the Overall Integrated Plan.

Based on a review of Entergy's plan, including the six-month update dated August 28, 2013, and information obtained through the mitigation strategies audit process, 1 the NRC concludes that the licensee has provided sufficient information to determine that there is reasonable assurance that the plan, when properly implemented, will meet the requirements of Order EA-12-049 at James A. FitzPatrick Nuclear Power Plant. This conclusion is based on the assumption that the licensee will implement the plan as described, including the satisfactory resolution of the open and confirmatory items detailed in the enclosed Interim Staff Evaluation and Audit Report. As identified in Section 4.0 of the enclosed report, the open item warranting the greatest attention to ensure successful implementation is to demonstrate adequate protection of FLEX equipment from a potential tornado hazard.

1 A description of the mitigation strategies audit process may be found at ADAMS Accession No. ML13234A503.

If you have any questions, please contact John Boska at 301-415-2901.

Sincerely, Jeremy S. Bowen, Chief Mitigating Strategies Projects Branch Mitigating Strategies Directorate Office of Nuclear Reactor Regulation Docket No. 50-333

Enclosures:

1. Interim Staff Evaluation
2. Technical Evaluation Report cc w/encl: Distribution via Listserv

UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 INTERIM STAFF EVALUATION AND AUDIT REPORT BY THE OFFICE OF NUCLEAR REACTOR REGULATION RELATED TO ORDER EA-12-049 MODIFYING LICENSES WITH REGARD TO REQUIREMENTS FOR MITIGATION STRATEGIES FOR BEYOND-DESIGN-BASIS EXTERNAL EVENTS ENTERGY NUCLEAR OPERATIONS. INC.

JAMES A FITZPATRICK NUCLEAR POWER PLANT DOCKET NO. 50-333

1.0 INTRODUCTION

The earthquake and tsunami at the Fukushima Dai-ichi nuc:ear power plant in March 2011, highlighted the possibility that extreme natural phenomena could challenge the prevention, mitigation and emergency preparedness defense-in-de;Jth layers. At Fukushima, limitations in time and unpredictable conditions associated with the accident significantly challenged attempts by the responders to preclude core damage and containment failure. During the events in Fukushima, the challenges faced by the operators were beyond any faced previously at a commercial nuclear reactor. The Nuclear Regulato1y Commission (NRC) determined that additional requirements needed to be imposed to mitigate beyond-design-basis external events (BDBEEs). Accordingly, by letter dated March 12. 2012, the NRC issued Order EA-12-049, "Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events" [Reference 1]. The order directed licensees to develop, implement, and maintain guidance and strategies to maintain or restore core cooling, containment, and spent fuel pool (SFP) cooling capabilities in the event of a BDBEE.

By letter dated February 28, 2013 [Reference 2], Entergy Nuclear Operations, Inc. (Entergy or the licensee) submitted its Overall Integrated Plan (hereafter referred to as the Integrated Plan) for James A FitzPatrick Nuclear Power P!ant (JAF) in response to Order EA-12-049. By letter dated August 28, 2013 [Reference 3], F.ntergy submitted a six-month update to the Integrated Plan.

Enclosure 1

2.0 REGULATORY EVALUATION

Following the events at the Fukushima Dai-ichi nuclear power plant on March 11, 2011, the NRC established a senior-level agency task force referred to as the Near-Term Task Force (NTTF). The NTTF was tasked with conducting a systematic and methodical review of the NRC's regulations and processes, and with determining whether the agency should make improvements to these programs in light of the events at Fukushima Dai-ichi. As a result of this review, the NTTF developed a comprehensive set of recommendations, documented in SECY-11-0093, "Near-Term Report and Recommendations for Agency Actions Following the Events in Japan," dated July 12, 2011 [Reference 4]. These recommendations were enhanced by the NRC staff following interactions with stakeholders. Documentation of the NRC staff's efforts is contained in SECY-11-0124, "Recommended Actions to be Taken without Delay from the Near-Term Task Force Report," dated September 9, 2011 [Reference 5] and SECY-11-0137, "Prioritization of Recommended Actions to be Taken in Response to Fukushima Lessons Learned," dated October 3, 2011 [Reference 6].

As directed by the Commission's Staff Requirement Memorandum (SRM) for SECY-11-0093

[Reference 7], the NRC staff reviewed the NTTF recommendations within the context of the NRC's existing regulatory framework and considered the various regulatory vehicles available to the NRC to implement the recommendations. SECY-11-0124 and SECY-11-0137 established the NRC staff's prioritization of the recommendations based upon the potential safety enhancements.

After receiving the Commission's direction in SRM-SECY-11-0124 [Reference 8] and SRM-SECY-11-0137 [Reference 9], the NRC staff conducted public meetings to discuss enhanced mitigation strategies intended to maintain or restore core cooling, containment, and SFP cooling capabilities following beyond-design-basis external events. At these meetings, the industry described its proposal for a Diverse and Flexible Mitigation Capability (FLEX), as documented in the Nuclear Energy Institute's (NEI's) letter dated December 16, 2011

[Reference 10]. FLEX was proposed as a strategy to fulfill the key safety functions of core cooling, containment integrity, and spent fuel cooling. Stakeholder input influenced the NRC staff to pursue a more performance-based approach to improve the safety of operating power reactors than envisioned in NTTF Recommendation 4.2, SECY-11-0124, and SECY-11-0137.

On February 17, 2012, the NRC staff provided SECY-12-0025, "Proposed Orders and Requests for Information in Response to Lessons Learned from Japan's March 11, 2011, Great Tohoku Earthquake and Tsunami," [Reference 11] to the Commission, including the proposed order to implement the enhanced mitigation strategies. As directed by SRM-SECY-12-0025

[Reference 12], the NRC staff issued Order EA-12-049, "Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events"

[Reference 1].

Order EA-12-049, Attachment 2, 1 requires that operating power reactor licensees and construction permit holders use a three-phase approach for mitigating BDBEEs. The initial phase requires the use of installed equipment and resources to maintain or restore core cooling, 1

Attachment 3 provides requirements for Combined License holders.

containment and SFP cooling capabilities. The transition phase requires providing sufficient, portable, onsite equipment and consumables to maintain or restore these functions until they can be accomplished with resources brought from off site. The final phase requires obtaining sufficient offsite resources to sustain those functions indefinitely. Specific operational requirements of the order are listed below:

1) Licensees or construction permit (CP) holders shall develop, implement, and maintain guidance and strategies to maintain or restore core cooling, containment, and SFP cooling capabilities following a beyond-design-basis external event.
2) These strategies must be capable of mitigating a simultaneous loss of all alternating current (ac) power and loss of normal access to the ultimate heat sink and have adequate capacity to address challenges to core cooling, containment, and SFP cooling capabilities at all units on a site subject to the order.
3) Licensees or CP holders must provide reasonable protection for the associated equipment from external events. Such protection must demonstrate that there is adequate capacity to address challenges to core cooling, containment, and SFP cooling capabilities at all units on a site subject to the order.
4) Licensees or CP holders must be capable of implementing the strategies in all modes.
5) Full compliance shall include procedures, guidance, training, and acquisition, staging, or installing of equipment needed for the strategies.

On May 4, 2012, NEI submitted document 12-06, "Diverse and Flexible Coping Strategies (FLEX) Implementation Guide," Revision B [Reference 13] to provide specifications for an industry developed methodology for the development, implementation, and maintenance of guidance and strategies in response to the Mitigating Strategies order. On May 13, 2012, NEI submitted NEI 12-06, Revision B 1 [Reference 14]. The guidance and strategies described in NEI 12-06 expand on those that industry developed and implemented to address the limited set of BDBEE that involve the loss of a large area of the plant due to explosions and fire required pursuant to paragraph (hh)(2) in Section 50.54, "Conditions of licenses" of Title 10 of the Code of Federal Regulations.

On May 31, 2012, the NRC staff issued a draft version of the interim staff guidance (ISG) document JLD-ISG-2012-01, "Compliance with Order EA-12-049, Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events," [Reference 15] and published a notice of its availability for public comment in the Federal Register(?? FR 33779), with the comment period running through July 7, 2012.

JLD-ISG-2012-01 proposed endorsing NEI 12-06, Revision B1, as providing an acceptable method of meeting the requirements of Order EA-12-049. The NRC staff received seven comments during this time. The NRC staff documented its analysis of these comments in "NRC Response to Public Comments, JLD-ISG-2012-01 (Docket ID NRC-2012-0068)" [Reference 16].

On July 3, 2012, NEI submitted comments on JLD-ISG-2012-01, including Revision C to NEI 12-06 [Reference 17], incorporating many of the exceptions and clarifications included in the draft version of the ISG. Following a public meeting held July 26, 2012, to discuss the remaining exceptions and clarifications, on August 21, 2012, NEI submitted Revision 0 to NEI 12-06 [Reference 18].

On August 29, 2012, the NRC staff issued the final version of JLD-ISG-2012-01, "Compliance with Order EA-12-049, Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events" [Reference 19], endorsing NEI 12-06, Revision 0, as an acceptable means of meeting the requirements of Order EA-12-049, and published a notice of its availability in the Federal Register (77 FR 55230).

The NRC staff determined that the overall integrated plans submitted by licensees in response to Order EA-12-049,Section IV.C.1.a should follow the guidance in NEI 12-06, Section 13, which states that:

The Overall Integrated Plan should include a complete description of the FLEX strategies, including important operational characteristics. The level of detail generally considered adequate is consistent to the level of detail contained in the Licensee's Final Safety Analysis Report (FSAR). The plan should provide the following information:

1. Extent to which this guidance, NEI 12-06, is being followed including a description of any alternatives to the guidance, and provide a milestone schedule of planned actions.
2. Description of the strategies and guidance to be developed to meet the requirements contained in Attachment 2 or Attachment 3 of the order.
3. Description of major installed and portable FLEX components used in the strategies, the applicable reasonable protection for the FLEX portable equipment, and the applicable maintenance requirements for the portable equipment.
4. Description of the steps for the development of the necessary procedures, guidance, and training for the strategies; FLEX equipment acquisition, staging or installation, including necessary modifications.
5. Conceptual sketches, as necessary to indicate equipment which is installed or equipment hookups necessary for the strategies. (As-built piping and instrumentation diagrams (P&ID) will be available upon completion of plant modifications.)
6. Description of how the portable FLEX equipment will be available to be deployed in all modes.

By letter dated August 28, 2013 [Reference 20], the NRC notified all licensees and construction permit holders that the staff is conducting audits of their responses to Order EA-12-049. That

letter described the process to be used by the staff in its reviews, leading to the issuance of this interim staff evaluation and audit report for each site. The purpose of the staff's audits is to determine the extent to which licensees are proceeding on a path towards successful implementation of the actions needed to achieve full compliance with the order. Additional NRC staff review and inspection may be necessary following full implementation of those actions to verify licensees' compliance with the order.

3.0 TECHNICAL EVALUATION

The NRC staff contracted with Mega Tech Services, LLC (MTS) for technical support in the evaluation of the Integrated Plan for JAF, submitted by Entergy's letter dated February 28, 2013, as supplemented. NRC and MTS staff have reviewed the submitted information and held clarifying discussions with Entergy in evaluating the licensee's plans for addressing BDBEEs and its progress towards implementing those plans.

JAF is a boiling water reactor with a Mark I containment. A simplified description of the JAF Integrated Plan to mitigate the postulated extended loss of ac power (ELAP) event is that the licensee will initially remove the core decay heat by using the Reactor Core Isolation Cooling (RCIC) system and the High Pressure Coolant Injection (HPCI) system. The steam-driven RCIC pump and HPCI pump will initially supply water to the reactor pressure vessel (RPV) from the condensate storage tank (CST). The licensee noted that the CST has a robust design for the lower half and that most of the water volume should survive the BDBEE. The larger HPCI pump will be stopped by the operators about 20 minutes into the event, as RPV level is restored to its normal level. Steam from the RPV will be vented through the safety/relief valves (SRVs) to the suppression pool (SP) in the torus in order to control the pressure in the RPV. Once it has been determined to be an ELAP event (about the 60 minute point), operators will shift the RCIC suction to the SP in order to utilize the SP water before it becomes too hot for the RCIC pump. When the SP temperature reaches about 170 degrees Fahrenheit (°F), operators will shift the RCIC suction back to the CST. Steam from the RPV will then be vented through the SRVs to the SP to cool down the RPV. RPV depressurization will be stopped at a pressure between 200 to 400 pounds per square inch gauge (psig) to ensure sufficient steam pressure for continued RCIC operation. Before the containment reaches its design pressure, the SP (torus) will be vented to atmosphere using the hardened vents to release steam and stop the pressure increase. The licensee estimates that this will occur at about 23 hours0.958 days <br />0.137 weeks <br />0.0315 months <br /> into the event.

When RCIC can no longer be operated reliably, operators will depressurize the RPV below 50 psig and use either the diesel-driven fire pump or FLEX pumps to inject water into the RPV from the ultimate heat sink (UHS), Lake Ontario.

FLEX generators will be used to reenergize the installed battery chargers to keep the necessary direct current (de) buses energized, which will then keep the 120 volt ac instrument buses energized. The licensee's long term plan is that they will utilize the industry Regional Response Centers (RRCs) for additional Phase 3 equipment. The Phase 3 generators from the RRC will be used to energize a plant residual heat removal (RHR) pump, and the plant systems needed for support, and reactor coolant system shutdown cooling will be established.

In the postulated ELAP event, the SFP will initially heat up due to the unavailability of the normal cooling system. A FLEX pump will be aligned and used to add water to the SFP to maintain

level as the pool boils. This will maintain a sufficient amount of water above the top of the fuel assemblies for cooling and shielding purposes.

To control containment parameters, Entergy plans to use containment (torus) venting to maintain containment pressure and temperature within acceptable values.

By letter dated February 6, 2014 [Reference 21], MTS documented the interim results of the Integrated Plan review in the attached technical evaluation report (TER). The NRC staff has reviewed this TER for consistency with NRC policy and technical accuracy and finds that it accurately reflects the state of completeness of the Integrated Plan. The NRC staff therefore adopts the findings of the TER with respect to individual aspects of the requirements of Order EA-12-049.

4.0 OPEN AND CONFIRMATORY ITEMS This section contains a summary of the open and confirmatory items identified as part of the technical evaluation. The NRC and MTS have assigned each review item to one of the following categories:

Confirmatory Item - an item that is considered conceptually acceptable, but for which resolution may be incomplete. These items are expected to be acceptable, but are expected to require some minimal follow up review or audit prior to the licensee's compliance with Order EA-12-049.

Open Item - an item for which the licensee has not presented a sufficient basis to determine that the issue is on a path to resolution. The intent behind designating an issue as an Open Item is to document items that need resolution during the review process, rather than being verified after the compliance date through the inspection process.

As discussed in Section 3.0, above, the NRC staff has reviewed MTS' TER for consistency with NRC policy and technical accuracy and finds that it accurately reflects the state of completeness of the licensee's Integrated Plan. The NRC staff therefore adopts the open and confirmatory items identified in the TER and listed in the tables below. Minor editorial changes were made by the NRC staff to some items. These summary tables provide a brief description of the issue of concern. Further details for each open and confirmatory item are provided in the corresponding sections of the TER, identified by the item number.

In the tables below, the NRC staff made the following change compared to the original summary tables in the TER, due to a determination that since the licensee has expertise in modifications, a detailed review is unnecessary:

1. Open Item 3.4.A was moved to be Confirmatory Item 3.4.A to conform to previous NRC staff treatment of similar items.

4.1 OPEN ITEMS Item Number Description Notes 3.1.1.3.A Procedural Interface (Seismic Hazard) - Evaluate the impacts from large internal flooding sources.

3.1.3.1.A Protection of FLEX Equipment (High Wind Hazard) - Evaluate Significant the separation distance and the axis of separation considering the predominant path of tornados in the geographic area to demonstrate that at least N sets of FLEX equipment would remain deployable in the context of a tornado missile hazard.

3.1.4.2.8 Deployment of FLEX Equipment (Snow, Ice and Extreme Cold)

- Evaluate the potential impact on the UHS due to ice blockage or formation of frazil ice as a result of extreme cold.

3.2.3.A Containment- Verify that the implementation of Boiling Water Reactor Owners Group (BWROG) Emergency Procedure Guideline (EPG)/Severe Accident Guideline (SAG), Revision 3, including any associated plant-specific evaluations, has been completed in accordance with the provisions of NRC letter dated January 9, 2014 [Reference 23].

4.2 CONFIRMATORY ITEMS Item Number Description Notes 3.1.1.2.A Deployment of FLEX Equipment- Confirm that soil liquefaction will not impede vehicle movement following a seismic event.

3.1.1.2.8 Deployment of FLEX Equipment- Confirm final design features of the new storage building including the susceptibility to the loss of ac power to deploy equipment.

3.1.1.2.C Deployment of FLEX Equipment - Confirm the storage locations and means of protection against the seismic hazard of the super duty pickup trucks and the two flatbed trailers used for deployment of FLEX equipment.

3.1.1.4.A Offsite Resources- Confirm location of offsite staging area(s),

access routes and methods of delivery of equipment to the site considering the seismic, flood, high wind, snow, ice and extreme cold hazards.

3.1.3.2.A Deployment of FLEX Equipment (High Wind Hazard)- Confirm availability of debris removal equipment to facilitate deployment of FLEX equipment.

3.1.3.2.8 Deployment of FLEX Equipment (High Wind Hazard)- Confirm protection of the means to move FLEX equipment.

3.1.4.2.A Deployment of FLEX Equipment (Snow, Ice and Extreme Cold)

- Confirm availability of snow removal equipment to facilitate

deployment of FLEX equipment.

3.2.1.1.A Computer Code Used for ELAP Analysis - Benchmarks need to be identified and discussed which demonstrate that Modular Accident Analysis Program (MAAP) is an appropriate code for the simulation of an ELAP event at JAF.

3.2.1.1.8 Computer Code Used for ELAP Analysis -Confirm that the collapsed level remains above Top of Active Fuel (TAF) and the cool down rate is within technical specifications limits.

3.2.1.1.C Computer Code Used for ELAP Analysis - Confirm that MAAP was used in accordance with Sections 4.1, 4.2, 4.3, 4.4, and 4.5 of the June 2013 position paper (ADAMS Accession No. ML13190A201 ).

3.2.1.1.D Computer Code Used for ELAP Analysis - Confirm that the licensee, in using MAAP, identified and justified the subset of key modeling parameters cited from Tables 4-1 through 4-6 of the "MAAP Application Guidance, Desktop Reference for Using MAAP Software, Revision 2" (Electric Power Research Institute Report 1020236).

3.2.1.1.E Computer Code Used for ELAP Analysis - Confirm that the specific MAAP analysis case that was used to validate the timing of mitigating strategies in the Integrated Plan has been identified and is available for NRC staff to review. Alternately, a comparable level of information has been included in the supplemental response. In either case, the analysis should include a plot of the collapsed vessel level to confirm that TAF is not reached {the elevation of the TAF should be provided) and a plot of the temperature cool down to confirm that the cool down is within technical specifications limits.

3.2.1.2.A Recirculation Pump Seal Leakage Models - Confirm the seal leakage model used in the updated MAAP analysis (which will address the MAAP code limitations when used for ELAP analysis). Evaluate the seal leakage rate model used, the details of the seal qualification tests and supporting test data, and leakage rate pressure-dependence.

3.2.1.3.A Sequence of Events (SOE)- Confirm the SOE timeline after reanalysis using the MAAP code which will address the limitations when used for the ELAP analysis.

3.2.1.4.A Systems and Components for Consequence Mitigation -

Confirm sizing of the FLEX pumps and 600 Vac FLEX diesel generator (DG) and the 4160 Vac generator to be obtained from the RRC.

3.2.1.5.A Monitoring Instrumentation and Controls- Confirm ac powered torus temperature, pressure and level and drywell temperature and pressure instrumentation is modified to remain powered during an ELAP.

3.2.1.8.A Use of Portable Pumps - Confirm that the use of raw water from

Lake Ontario for long term core and spent fuel pool cooling strategies is acceptable.

3.2.2.A Spent Fuel Pool Cooling - Confirm the method of ventilation and power requirements, if any, of the spent fuel pool area.

3.2.4.2.A Ventilation (Equipment Cooling)- Confirm that additional evaluations of the RCIC room temperature demonstrate that an acceptable environment is maintained during the transition phase both for equipment in the room and habitability for operators who may need to enter the room.

3.2.4.2.8 Ventilation (Equipment Cooling)- Confirm that evaluations of the battery room temperature demonstrate that an acceptable environment, during both high ambient temperature and during extreme cold ambient temperature, is maintained during Phases 2 and 3.

3.2.4.2.C Ventilation (Equipment Cooling)- Confirm the required ventilation flow or the size of the portable fans to maintain acceptable environmental conditions in the DC equipment room.

3.2.4.3.A Heat Tracing - Confirm completion of walkdowns and evaluation of where heat tracing may be needed for freeze protection of equipment or instruments used in the ELAP mitigation strategies.

3.2.4.4.A Lighting - Confirm need for additional portable lighting, such as de powered lights.

3.2.4.4.8 Communications - Confirm that upgrades to the site's communication system have been completed.

3.2.4.8.A Electrical Power Sources - Confirm the technical basis for the selection and size of the FLEX generators to be used in support of the coping strategies.

3.2.4.10.A Load Reduction to Conserve DC Power - Confirm final load shed list and the evaluation of any potential adverse effects of shedding those loads.

3.2.4.10.8 Load Reduction to Conserve DC Power - Confirm the final de load profile with the required loads and the finalized minimum battery voltage.

3.2.4.10.C Load Reduction to Conserve DC Power- Confirm time after the ELAP for connecting the FLEX DG to the battery chargers.

3.4.A Off-site Resources- Confirm that NEI 12-06, Section 12.2 guidelines 2 through 10 are addressed, or that an appropriate alternative is justified.

Based on a review of Entergy's plan, including the six-month update dated August 28, 2013, and information obtained through the mitigation strategies audit process, the NRC concludes that the licensee has provided sufficient information to determine that there is reasonable assurance that the plan, when properly implemented, will meet the requirements of Order EA-12-049 at JAF. This conclusion is based on the assumption that the licensee will implement the plan as described, including the satisfactory resolution of the open and confirmatory items.

5.0

SUMMARY

As required by Order EA-12-049, the licensee is developing, and will implement and maintain, guidance and strategies to restore or maintain core cooling, containment, and SFP cooling capabilities in the event of a BDBEE. These new requirements provide a greater mitigation capability consistent with the overall defense-in-depth philosophy, and, therefore, greater assurance that the challenges posed by BDBEEs to power reactors do not pose an undue risk to public health and safety.

The NRC's objective in preparing this interim staff evaluation and audit report is to provide a finding to the licensee on whether or not their integrated plan, if implemented as described, provides a reasonable path for compliance with the order. For areas where the NRC staff has insufficient information to make this finding (identified above in Section 4.0), the staff will review these areas as they become available or address them as part of the inspection process. The staff notes that the licensee has the ability to modify their plans as stated in NEI 12-06, Section 11.8. However, additional NRC review and/or inspection may be necessary to verify compliance.

The NRC staff has reviewed the licensee's plans for additional defense-in-depth measures.

With the exception of the items noted in Section 4.0 above, the staff finds that the proposed measures, properly implemented, will meet the intent of Order EA-12-049, thereby enhancing the licensee's capability to mitigate the consequences of a BDBEE that impacts the availability of ac power and the UHS. Full compliance with the order will enable the NRC to continue to have reasonable assurance of adequate protection of public health and safety. The staff will issue a safety evaluation confirming compliance with the order and may conduct inspections to verify proper implementation of the licensee's proposed measures.

6.0 REFERENCES

1. Order EA-12-049, "Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events," March 12, 2012 (ADAMS Accession No. ML12054A736)
2. Letter from Entergy to NRC, "Overall Integrated Plan in Response to March 12, 2012 Commission Order to Modify Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049)," dated February 28, 2013 (ADAMS Accession No. ML13063A287)
3. Letter from Entergy to NRC, "First Six-Month Status Report In Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond Design Basis External Events (Order Number EA-12-049)," dated August 28, 2013 (ADAMS Accession No. ML13241A204)
4. SECY-11-0093, "Near-Term Report and Recommendations for Agency Actions Following the Events in Japan," July 12, 2011 (ADAMS Accession No. ML11186A950)
5. SECY-11-0124, "Recommended Actions to be Taken without Delay from the Near-Term Task Force Report," September 9, 2011 (ADAMS Accession No. ML11245A158)
6. SECY-11-0137, "Prioritization of Recommended Actions to be Taken in Response to Fukushima Lessons Learned," October 3, 2011 (ADAMS Accession No. ML11272A111)
7. SRM-SECY-11-0093, "Staff Requirements- SECY-11-0093- Near-Term Report and Recommendations for Agency Actions following the Events in Japan," August 19, 2011 (ADAMS Accession No. ML112310021)
8. SRM-SECY-11-0124, "Staff Requirements- SECY-11-0124- Recommended Actions to be Take without Delay from the Near-Term Task Force Report," October 18, 2011 (ADAMS Accession No. ML112911571)
9. SRM-SECY-11-0137, "Staff Requirements- SECY-11-0137- Prioritization of Recommended Actions to be Taken in Response to Fukushima Lessons Learned,"

December 15, 2011 (ADAMS Accession No. ML113490055)

10. Letter from Adrian Heymer (NEI) to David L. Skeen (NRC), "An Integrated, Safety-Focused Approach to Expediting Implementation of Fukushima Dai-ichi Lessons Learned," December 16, 2011 (ADAMS Accession No. ML11353A008)
11. SECY-12-0025, "Proposed Orders and Requests for Information in Response to Lessons Learned from Japan's March 11, 2011, Great Tohoku Earthquake and Tsunami," February 17, 2012 (ADAMS Accession No. ML12039A103)
12. SRM-SECY-12-0025, "Staff Requirements- SECY-12-0025- Proposed Orders and Requests for Information in Response to Lessons Learned from Japan's March 11, 2011, Great Tohoku Earthquake and Tsunami," March 9, 2012 (ADAMS Accession No. ML120690347)
13. Nuclear Energy Institute (NEI) document 12-06, "Diverse and Flexible Coping Strategies (FLEX) Implementation Guide," Revision B, May 4, 2012 (ADAMS Accession No. ML12144A419)
14. NEI document NEI 12-06, "Diverse and Flexible Coping Strategies (FLEX)

Implementation Guide," Revision B1, May 13, 2012 (ADAMS Accession No. ML12143A232)

15. Draft JLD-ISG-2012-01, "Compliance with Order EA-12-049, Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events," May 31, 2012 (ADAMS Accession No. ML12146A014)
16. NRC Response to Public Comments, JLD-ISG-2012-01 (Docket ID NRC-2012-0068),

August 29, 2012 (ADAMS Accession No. ML12229A253)

17. NEI comments to draft JLD-ISG-2012-01 and document 12-06, "Diverse and Flexible Coping Strategies (FLEX) Implementation Guide," Revision C, July 3, 2012 (ADAMS Accession No. ML121910390)
18. NEI document 12-06, "Diverse and Flexible Coping Strategies (FLEX) Implementation Guide," Revision 0, August 21, 2012 (ADAMS Accession No. ML12242A378)
19. Final Interim Staff Guidance JLD-ISG-2012-01, "Compliance with Order EA-12-049, Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events," August 29, 2012 (ADAMS Accession No. ML12229A174)
20. Letter from Jack R. Davis (NRC) to All Operating Reactor Licensees and Holders of Construction Permits, "Nuclear Regulatory Commission Audits of Licensee Responses to Mitigation Strategies Order EA-12-049," August 28, 2013 (ADAMS Accession No. ML13234A503)
21. Letter from John Bowen, MegaTech Services, LLC, to Eric Bowman, NRC, submitting "Technical Evaluation Reports Related to Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events, EA 12-049," dated February 15, 2014 (ADAMS Accession No. ML14049A207)
22. Order EA-13-1 09, "Order to Modify Licenses with Regard to Reliable Hardened Containment Vents Capable of Operation Under Severe Accident Conditions," June 6, 2013 (ADAMS Accession No. ML13143A321)
23. Letter from Jack R. Davis (NRC) to Joseph E. Pollock (NEI) dated January 9, 2014, regarding Boiling Water Reactor Containment Venting (ADAMS Accession No. ML13358A206)

Principal Contributors: E. Bowman B. Lee R. Fitzpatrick G. Armstrong K. Heller J. Boska Date: February 21, 2014

Enclosure 2 Technical Evaluation Report

Mega-Tech Services, LLC Technical Evaluation Report Related to Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events, EA-12-049 Revision 1 February 15, 2014 Entergy Nuclear Northeast Entergy Nuclear Operations, Inc.

James A. FitzPatrick Nuclear Power Plant Docket No. 50-333 Prepared for:

U.S. Nuclear Regulatory Commission Washington, D.C. 20555 Contract N RC-HQ-13-C-03-0039 Task Order No. NRC-HQ-13-T-03-0001 Job Code: J4672 TAC No. MF1077 Prepared by:

Mega-Tech Services, LLC 11118 Manor View Drive Mechanicsville, Virginia 23116 11118 Manor View Drive

  • Mechanicsville, Virginia 23116 804.789.1577
  • Fax: 804.789.1578 www.mega-techservices.biz

Technical Evaluation Report James A FitzPatrick Nuclear Power Plant Order EA-12-049 Evaluation

1.0 BACKGROUND

Following the events at the Fukushima Dai-ichi nuclear power plant on March 11, 2011, the U.S. Nuclear Regulatory Commission (NRC) established a senior-level agency task force referred to as the Near-Term Task Force (NTTF). The NTTF was tasked with conducting a systematic, methodical review of NRC regulations and processes to determine if the agency should make additional improvements to these programs in light of the events at Fukushima Dai-ichi. As a result of this review, the NTTF developed a comprehensive set of recommendations, documented in SECY-11-0093, "Near-Term Report and Recommendations for Agency Actions Following the Events in Japan," dated July 12, 2011. These recommendations were enhanced by the NRC staff following interactions with stakeholders.

Documentation of the staff's efforts is contained in SECY-11-0124, "Recommended Actions to be Taken without Delay from the Near-Term Task Force Report," dated September 9, 2011, and SECY-11-0137, "Prioritization of Recommended Actions to be Taken in Response to Fukushima Lessons Learned," dated October 3, 2011.

As directed by the Commission's staff requirement memorandum (SRM) for SECY-11-0093, the NRC staff reviewed the NTTF recommendations within the context of the NRC's existing regulatory framework and considered the various regulatory vehicles available to the NRC to implement the recommendations. SECY-11-0124 and SECY-11-0137 established the staff's prioritization of the recommendations.

After receiving the Commission's direction in SRM-SECY-11-0124 and SRM-SECY-11-0137, the NRC staff conducted public meetings to discuss enhanced mitigation strategies intended to maintain or restore core cooling, containment, and spent fuel pool (SFP) cooling capabilities following beyond-design-basis external events (BDBEEs). At these meetings, the industry described its proposal for a Diverse and Flexible Mitigation Capability (FLEX), as documented in Nuclear Energy Institute's (NEI) letter, dated December 16, 2011 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML11353A008). FLEX was proposed as a strategy to fulfill the key safety functions of core cooling, containment integrity, and spent fuel cooling. Stakeholder input influenced the NRC staff to pursue a more performance-based approach to improve the safety of operating power reactors relative to the approach that was envisioned in NTTF Recommendation 4.2, SECY-11-0124, and SECY 0137.

On February 17, 2012, the NRC staff provided SECY-12-0025, "Proposed Orders and Requests for Information in Response to Lessons Learned from Japan's March 11, 2011, Great Tohoku Earthquake and Tsunami," to the Commission, including the proposed order to implement the enhanced mitigation strategies. As directed by SRM-SECY-12-0025, the NRC staff issued Order EA-12-049, "Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events."

Guidance and strategies required by the Order would be available if a loss of power, motive force and normal access to the ultimate heat sink needed to prevent fuel damage in the reactor and SFP affected all units at a site simultaneously. The Order requires a three-phase approach for mitigating BDBEEs. The initial phase requires the use of installed equipment and resources Revision 1 Page 2 of 60 2014-02-15

to maintain or restore key safety functions including core cooling, containment, and SFP cooling. The transition phase requires providing sufficient portable onsite equipment and consumables to maintain or restore these functions until they can be accomplished with resources brought from offsite. The final phase requires obtaining sufficient offsite resources to sustain those functions indefinitely.

NEI submitted its document NEI 12-06, "Diverse and Flexible Coping Strategies (FLEX)

Implementation Guide" in August 2012 (ADAMS Accession No. ML12242A378) to provide specifications for an industry-developed methodology for the development, implementation, and maintenance of guidance and strategies in response to Order EA-12-049. The guidance and strategies described in NEI 12-06 expand on those that industry developed and implemented to address the limited set of BDBEEs that involve the loss of a large area of the plant due to explosions and fire required pursuant to paragraph (hh)(2) of 10 CFR 50.54, "Conditions of licenses."

As described in Interim Staff Guidance (ISG), JLD-ISG-2012-01, "Compliance with Order EA-12-049, Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events," the NRC staff considers that the development, implementation, and maintenance of guidance and strategies in conformance with the guidelines provided in NEI 12-06, Revision 0, subject to the clarifications in Attachment 1 of the ISG are an acceptable means of meeting the requirements of Order EA-12-049.

In response to Order EA-12-049, licensees submitted Overall Integrated Plans (hereafter, the Integrated Plan) describing their course of action for mitigation strategies that are to conform with the guidance of NEI 12-06, or provide an acceptable alternative to demonstrate compliance with the requirements of Order EA-12-049.

2.0 EVALUATION PROCESS In accordance with the provisions of Contract NRC-HQ-13-C-03-0039, Task Order No.

NRC-HQ-13-T-03-0001, Mega-Tech Services, LLC (MTS) performed an evaluation of each licensee's Integrated Plan. As part of the evaluation, MTS, in parallel with the NRC staff, reviewed the original Integrated Plan and the first 6-month status update, and conducted an audit of the licensee documents. The staff and MTS also reviewed the licensee's answers to the NRC staff's and MTS's questions as part of the audit process. The objective of the evaluation was to assess whether the proposed mitigation strategies conformed to the guidance in NEI 12-06, as endorsed by the positions stated in JLD-ISG-2012-01, or an acceptable alternative had been proposed that would satisfy the requirements of Order EA-12-049. The audit plan that describes the audit process was provided to all licensees in a letter dated August 28, 2013 from Jack R. Davis, Director, Mitigation Strategies Directorate (ADAMS Accession No. ML13234A503).

The review and evaluation of the licensee's Integrated Plan was performed in the following areas consistent with NEI 12-06 and the regulatory guidance of JLD-ISG-2012-01:

  • Evaluation of External Hazards
  • Phased Approach

~ Initial Response Phase

~ Transition Phase

~ Final Phase

  • Core Cooling Strategies Revision 1 Page 3 of 60 2014-02-15
  • SFP Cooling Strategies
  • Containment Function Strategies
  • Programmatic Controls

~ Equipment Protection, Storage, and Deployment

~ Equipment Quality The technical evaluation in Section 3.0 documents the results of the MTS evaluation and audit results. Section 4.0 summarizes Confirmatory Items and Open Items that require further evaluation before a conclusion can be reached that the Integrated Plan is consistent with the guidance in NEI 12-06 or an acceptable alternative has been proposed that would satisfy the requirements of Order EA-12-049. For the purpose of this evaluation, the following definitions are used for Confirmatory Item and Open Item.

Confirmatory Item - an item that is considered conceptually acceptable, but for which resolution may be incomplete. These items are expected to be acceptable, but are expected to require some minimal follow up review or audit prior to the licensee's compliance with Order EA-12-049.

Open Item - an item for which the licensee has not presented a sufficient basis to determine that the issue is on a path to resolution. The intent behind designating an issue as an Open Item is to document items that need resolution during the review process, rather than being verified after the compliance date through the inspection process.

Additionally, for the purpose of this evaluation and the NRC staff's interim staff evaluation (ISE),

licensee statements, commitments, and references to existing programs that are subject to routine NRC oversight (Updated Final Safety Analysis Report (UFSAR) program, procedure program, quality assurance program, modification configuration control program, etc.) will generally be accepted. For example, references to existing UFSAR information that supports the licensee's overall mitigating strategies plan, will be assumed to be correct, unless there is a specific reason to question its accuracy. Likewise, if a licensee states that they will generate a procedure to implement a specific mitigating strategy, assuming that the procedure would otherwise support the licensee's plan, this evaluation accepts that a proper procedure will be prepared. This philosophy for this evaluation and the ISE does not imply that there are any limits in this area to future NRC inspection activities.

3.0 TECHNICAL EVALUATION

By letter dated February 28, 2013, (ADAMS Accession No. ML13063A287), and as supplemented by the first six-month status report in a letter dated August 28, 2013 (ADAMS Accession No. ML13241A204), Entergy Nuclear Northeast, Entergy Nuclear Operations, Inc.

(the licensee or Entergy) provided the James A. FitzPatrick Nuclear Power Plant (JAF)

Integrated Plan for Compliance with Order EA-12-049. The Integrated Plan describes the strategies and guidance under development for implementation by the licensee for the maintenance or restoration of core cooling, containment, and SFP cooling capabilities following a BDBEE, including modifications necessary to support this implementation, pursuant to Order EA-12-049. By letter dated August 28, 2013 (ADAMS Accession No. ML13234A503), the NRC notified all licensees and construction permit holders that the staff is conducting audits of their responses to Order EA-12-049. That letter described the process used by the NRC staff in its review, leading to the issuance of an interim staff evaluation and audit report. The purpose of the staff's audit is to determine the extent to which the licensees are proceeding on a path Revision 1 Page 4 of 60 2014-02-15

towards successful implementation of the actions needed to achieve full compliance with the Order.

3.1 EVALUATION OF EXTERNAL HAZARDS Sections 4 through 9 of NEI 12-06 provide the NRC-endorsed methodology for the determination of applicable extreme external hazards in order to identify potential complicating factors for the protection and deployment of equipment needed for mitigation of BDBEEs leading to an extended loss of all alternating current (ac) power (ELAP) and loss of normal access to the ultimate heat sink (UHS). These hazards are broadly grouped into the categories discussed below in Sections 3.1.1 through 3.1.5 of this evaluation. Characterization of the applicable hazards for a specific site includes the identification of realistic timelines for the hazard; characterization of the functional threats due to the hazard; development of a strategy for responding to events with warning; and development of a strategy for responding to events without warning.

3.1.1 Seismic Events.

NEI 12-06, Section 5.2 states:

All sites will address BOB [beyond-design-basis] seismic considerations in the implementation of FLEX strategies, as described below. The basis for this is that, while some sites are in areas with lower seismic activity, their design basis generally reflects that lower activity. There are large, and unavoidable, uncertainties in the seismic hazard for all U.S. plants. In order to provide an increased level of safety, the FLEX deployment strategy will address seismic hazards at all sites.

These considerations will be treated in four primary areas: protection of FLEX equipment, deployment of FLEX equipment, procedural interfaces, and considerations in utilizing off-site resources.

On page 1 of the Integrated Plan, in the section regarding determination of applicable extreme external hazards, the licensee stated that the seismic design for Class I structures and equipment is based on dynamic analysis using acceleration response spectrum curves normalized to a ground motion of 0.08g for the Operating Basis Earthquake and 0.15g for the Design Basis Earthquake. The NRC also refers to the Design Basis Earthquake as the Safe Shutdown Earthquake (SSE). The basis for these criteria is presented in the JAF Final Safety Analysis Report [JAF Final Safety Analysis Report, updated 2011] Section 2.6.

The licensee stated that in accordance with NEI 12-06, all sites will consider the seismic hazard and that the seismic hazard is applicable to JAF.

The licensee also stated on page 3 that the seismic re-evaluations pursuant to the 10 CFR 50.54(f) letter of March 12, 2012 had not been completed and therefore were not assumed in their Integrated Plan. As the re-evaluations are completed, appropriate issues will be entered into the corrective action system and addressed.

The licensee's approach described above, as currently understood, is consistent with the guidance found in NEI 12-06, as endorsed by JLD-ISG-2012-01, and provides reasonable assurance that the requirements of Order EA-12-049 will be met with respect to seismic Revision 1 Page 5 of 60 2014-02-15

screening if these requirements are implemented as described.

3.1.1.1 Protection of FLEX Equipment - Seismic Hazard NEI 12-06, Section 5.3.1 states:

1. FLEX equipment should be stored in one or more of following three configurations:
a. In a structure that meets the plant's design basis for the Safe Shutdown Earthquake (SSE) (e.g., existing safety-related structure).
b. In a structure designed to or evaluated equivalent to [American Society of Civil Engineers] ASCE 7-10, Minimum Design Loads for Buildings and Other Structures.
c. Outside a structure and evaluated for seismic interactions to ensure equipment is not damaged by non-seismically robust components or structures.
2. Large portable FLEX equipment such as pumps and power supplies should be secured as appropriate to protect them during a seismic event (i.e., Safe Shutdown Earthquake (SSE) level).
3. Stored equipment and structures should be evaluated and protected from seismic interactions to ensure that unsecured and/or non-seismic components do not damage the equipment.

On pages 19, 26, 34, and 41 in the sections of the Integrated Plan regarding the strategies for maintaining core cooling, containment, spent fuel cooling and for safety systems support, respectively, the licensee stated that protection of associated portable equipment from seismic hazards will be provided by constructing structures that meet the guidelines of NEI 12-06 Section 11 which references Sections 5 through 9 for more detailed guidance for protection of FLEX equipment during specific external events. With respect to consideration (1), during the audit process, the licensee stated that two storage facilities are planned. The selected locations are in the northeast area of the protected area just east of the radwaste building and outside the protected area to the south and east of the protected area near the off-site wellness center. The storage buildings will be designed for seismic criteria equivalent to ASCE 7-10, and local building codes.

With respect to considerations 2 and 3, the licensee stated during the audit process that storage of large FLEX equipment will take into consideration protection of the equipment by location or securing the equipment to ensure that there are no seismic interactions between the FLEX equipment during a seismic event.

The licensee's approach described above, as currently understood, is consistent with the guidance found in NEI 12-06, as endorsed by JLD-ISG-2012-01, and provides reasonable assurance that the requirements of Order EA-12-049 will be met with respect to protection of FLEX equipment considering the seismic hazard if these requirements are implemented as described.

Revision 1 Page 6 of 60 2014-02-15

3.1.1.2 Deployment of FLEX Equipment - Seismic Hazard NEI 12-06, Section 5.3.2 states:

The baseline capability requirements already address loss of non-seismically robust equipment and tanks as well as loss of all AC. So, these seismic considerations are implicitly addressed.

There are five considerations for the deployment of FLEX equipment following a seismic event:

1. If the equipment needs to be moved from a storage location to a different point for deployment, the route to be traveled should be reviewed for potential soil liquefaction that could impede movement following a severe seismic event.
2. At least one connection point for the FLEX equipment will only require access through seismically robust structures. This includes both the connection point and any areas that plant operators will have to access to deploy or control the capability.
3. If the plant FLEX strategy relies on a water source that is not seismically robust, e.g., a downstream dam, the deployment of FLEX coping capabilities should address how water will be accessed. Most sites with this configuration have an underwater berm that retains a needed volume of water. However, accessing this water may require new or different equipment.
4. If power is required to move or deploy the equipment (e.g., to open the door from a storage location), then power supplies should be provided as part of the FLEX deployment.
5. A means to move FLEX equipment should be provided that is also reasonably protected from the event.

Two locations for storage of the FLEX equipment have been selected and haul routes of the FLEX equipment to the staging areas have been identified as shown in Figure 3, page 55, in the Integrated Plan. During the audit process, the licensee stated that potential for soil liquefaction along the deployment routes has not yet been evaluated. This is identified as Confirmatory Item 3.1.1.2.A in Section 4.2.

On page 3, in the section of the Integrated Plan discussing key site assumptions to implement NEI 12-06 strategies, Entergy stated that the designed hardened connections are protected against external events or are established at multiple and diverse locations. On pages 19, 22, 23, 33, and 40 in the Integrated Plan, Entergy provided details on the new connections required to support the FLEX strategies. Furthermore during the audit the licensee stated that FLEX equipment connection points will be located in seismically qualified or seismically robust structures. At least one connection point will only require access through seismic structures. If located outside a structure, connection points will be evaluated for seismic interactions, extreme cold, high wind and high temperature.

With regard to consideration 4 above, the Integrated Plan did not address whether power would Revision 1 Page 7 of 60 2014-02-15

be required to move or deploy equipment. During the audit process, the licensee stated that design details of the structures have not been completed. This is identified as Confirmatory Item 3.1.1.2.B in Section 4.2.

On page 45 of the Integrated Plan, the licensee identified four super duty pickup trucks and two flatbed trailers as portable FLEX equipment. However, it is not clear where this equipment is stored and how it is protected from the seismic event. This is identified as Confirmatory Item 3.1.1.2.C in Section 4.2.

The licensee's approach described above, as currently understood, is consistent with the guidance found in NEI 12-06, as endorsed by JLD-ISG-2012-01, and subject to the successful closure of issues related to the Confirmatory Items provides reasonable assurance that the requirements of Order EA-12-049 will be met with respect to deployment of FLEX equipment considering the seismic hazard if these requirements are implemented as described.

3.1.1.3 Procedural Interfaces- Seismic Hazard NEI 12-06, Section 5.3.3 states:

There are four procedural interface considerations that should be addressed.

1. Seismic studies have shown that even seismically qualified electrical equipment can be affected by BOB seismic events. In order to address these considerations, each plant should compile a reference source for the plant operators that provides approaches to obtaining necessary instrument readings to support the implementation of the coping strategy (see Section 3.2.1.1 0). This reference source should include control room and non-control room readouts and should also provide guidance on how and where to measure key instrument readings at containment penetrations, where applicable, using a portable instrument (e.g., a Fluke meter). Such a resource could be provided as an attachment to the plant procedures/guidance. Guidance should include critical actions to perform until alternate indications can be connected and on how to control critical equipment without associated control power.
2. Consideration should be given to the impacts from large internal flooding sources that are not seismically robust and do not require ac [alternating current] power (e.g., gravity drainage from lake or cooling basins for non-safety-related cooling water systems).
3. For sites that use ac power to mitigate ground water in critical locations, a strategy to remove this water will be required.
4. Additional guidance may be required to address the deployment of FLEX for those plants that could be impacted by failure of a not seismically robust downstream dam.

On pages 15, 16 and 25 of the Integrated Plan, the licensee listed the installed instrumentation credited for monitoring the effectiveness of the FLEX coping strategies. These instruments are discussed in more detail in Section 3.2.1.5. The licensee's Integrated Plan with regard to procedural interface (seismic) did not address 1) reference sources for the plant operators that Revision 1 Page 8 of 60 2014-02-15

provide approaches to obtaining necessary instrument readings using a portable instrument and

2) guidance for critical actions to perform until alternate indications can be connected and on how to control critical equipment without associated control power. During the audit process, the licensee stated that the FLEX support guidelines (FSGs) and supporting procedures will be developed addressing the guidance in NEI 12-06 Section 5.3.3.

The licensee's Integrated Plan does not address large internal flooding sources. During the audit process, the licensee addressed this consideration by stating that the evaluation has not yet been performed. This is identified as Open Item 3.1.1. 3.A in Section 4.1.

The licensee's Integrated Plan does not address the use of alternating current (ac) power to mitigate ground water in critical locations. During the audit process, the licensee addressed this consideration by stating that the levels in the perimeter pits will be monitored and temporary power will be provided to the perimeter drain pumps as needed.

The licensee's approach described above, as currently understood, is consistent with the guidance found in NEI 12-06, as endorsed by JLD-ISG-2012-01, and subject to the successful closure of issues related to the Open Item, provides reasonable assurance that the requirements of Order EA-12-049 will be met with respect to procedural interfaces if these requirements are implemented as described.

3.1.1.4 Considerations in Using Offsite Resources - Seismic Hazard NEI 12-06, Section 5.3.4 states:

Severe seismic events can have far-reaching effects on the infrastructure in and around a plant. While nuclear power plants are designed for large seismic events, many parts of the Owner Controlled Area and surrounding infrastructure (e.g., roads, bridges, dams, etc.) may be designed to lesser standards.

Obtaining off-site resources may require use of alternative transportation (such as air-lift capability) that can overcome or circumvent damage to the existing local infrastructure.

1. The FLEX strategies will need to assess the best means to obtain resources from off-site following a seismic event.

On page 10, in the section of the Integrated Plan discussing the Regional Response Center (RRC), Entergy stated that the industry has selected a vendor to manage two RRCs to provide large equipment in support of the response to BDBEEs. Each RRC will store and maintain five sets of equipment, four of which are expected to be fully deployable upon request. The fifth set is provided to account for equipment that may be unavailable due to its maintenance and testing cycle.

The licensee stated that JAF will utilize the industry RRCs for Phase 3 equipment. In an ELAP event, communications would be established between JAF and the industry Strategic Alliance for FLEX Emergency Response (SAFER) team and required equipment mobilized as needed.

JAF will enter into a contractual agreement with the SAFER team. Equipment will initially be moved from an RRC to a local staging area, established by the SAFER team and JAF. The equipment will be prepared at the staging area prior to transport to the site. First arriving equipment, as established during development of the SAFER Response Plan (RRC playbook),

will be delivered to the site within 24 hours1 days <br />0.143 weeks <br />0.0329 months <br /> from the initial request.

Revision 1 Page 9 of 60 2014-02-15

On page 22, in the section of the Integrated Plan discussing coping strategies to maintain core cooling during Phase 3, Entergy stated that equipment transported to the site will be either immediately staged at the point of use or temporarily stored at the lay down area. The lay down area is located outside the protected area on the south side of the plant near the main entrance.

Entergy has not yet identified the local offsite staging area(s) for the RRC FLEX equipment nor evaluated the methods for delivery of equipment from the offsite staging area to the site under various conditions such as seismic, flooding, high winds, and snow, ice and extreme cold. The identification of local offsite staging areas and evaluation of delivery methods following a seismic event has been identified as Confirmatory Item 3.1.1.4.A in Section 4.2.

The licensee's approach described above, as currently understood, is consistent with the guidance found in NEI 12-06, as endorsed by JLD-ISG-2012-01, and subject to the successful closure of issues related to the Confirmatory Item, provides reasonable assurance that the requirements of Order EA-12-049 will be met with respect to offsite resources if these requirements are implemented as described.

3.1.2 Flooding NEI 12-06, Section 6.2 states:

The evaluation of external flood-induced challenges has three parts. The first part is determining whether the site is susceptible to external flooding. The second part is the characterization of the applicable external flooding threat. The third part is the application of the flooding characterization to the protection and deployment of FLEX strategies.

NEI 12-06, Section 6.2.1 states in part:

Susceptibility to external flooding is based on whether the site is a "dry" site, i.e.,

the plant is built above the design basis flood level (DBFL). For sites that are not "dry", water intrusion is prevented by barriers and there could be a potential for those barriers to be exceeded or compromised. Such sites would include those that are kept "dry" by permanently installed barriers, e.g., seawall, levees, etc.,

and those that install temporary barriers or rely on watertight doors to keep the design basis flood from impacting safe shutdown equipment.

On page 1, in the section of the Integrated Plan discussing the external flood hazard assessment, Entergy stated that JAF is built above the design basis flood level. Per JAF FSAR (JAF Final Safety Analysis Report, updated 2011, Sections 2.4.3.2 and 2.4.3.7), the Probable Maximum Flood (PMF) elevation at the screenwell is 255 ft. This is based on a maximum lake level of Elevation 250 feet, and considers the setup (4.1 feet) and maximum precipitation (0.35 feet).

In this section of the Integrated Plan, the licensee stated that the maximum probable flood lake level is determined considering the maximum lake level, a maximum wind setup of 4.1 feet, the maximum rainfall of 0.35 feet and a maximum wave run-up height of 7.5 feet; this results in a maximum probable flood lake level of just under 262'. The grade elevation at JAF is 272ft (JAF FSAR 2011, Section 2.4.3.7). Therefore, JAF is built above the design basis flood level and is considered a "dry" site by the NEI guidance (NEI 12-06, Section 6.2.1) and "dry" sites are not Revision 1 Page 10 of 60 2014-02-15

required to evaluate flood-induced challenges.

The licensee stated that the external flood hazard screens out as not applicable to JAF.

On page 3, in the section of the Integrated Plan discussing key assumptions to implement NEI 12-06 strategies, the licensee stated that the flooding re-evaluations pursuant to the 10 CFR 50.54(f) letter of March 12, 2012 had not been completed and therefore were not assumed in the Integrated Plan. As the re-evaluations are completed, appropriate issues will be entered into the corrective action system and addressed.

The licensee's approach described above, as currently understood, is consistent with the guidance found in NEI 12-06, as endorsed by JLD-ISG-2012-01, and provides reasonable assurance that the requirements of Order EA-12-049 will be met with respect to screening and characterization of the flooding hazard if these requirements are implemented as described.

3.1.2.1 Protection of FLEX Equipment - Flooding Hazard NEI 12-06, Section 6.2.3.1 states:

These considerations apply to the protection of FLEX equipment from external flood hazards:

1. The equipment should be stored in one or more of the following configurations:
a. Stored above the flood elevation from the most recent site flood analysis.

The evaluation to determine the elevation for storage should be informed by flood analysis applicable to the site from early site permits, combined license applications, and/or contiguous licensed sites.

b. Stored in a structure designed to protect the equipment from the flood.
c. FLEX equipment can be stored below flood level if time is available and plant procedures/guidance address the needed actions to relocate the equipment. Based on the timing of the limiting flood scenario(s), the FLEX equipment can be relocated [footnote 2 omitted] to a position that is protected from the flood, either by barriers or by elevation, prior to the arrival of the potentially damaging flood levels. This should also consider the conditions on-site during the increasing flood levels and whether movement of the FLEX equipment will be possible before potential inundation occurs, not just the ultimate flood height.
2. Storage areas that are potentially impacted by a rapid rise of water should be avoided.

On pages 19, 26, 34, and 41 in the sections of the Integrated Plan regarding the strategies for maintaining core cooling, containment, spent fuel cooling and for safety systems support, respectively, the licensee stated that protection of associated portable equipment from flooding hazards is not applicable since the flooding hazard has been screened out as discussed in Section 3.1.2.1 above. During the audit process, the licensee restated that because JAF is a "dry" site per NEI guidance, no further evaluation of the flood hazard is required.

Revision 1 Page 11 of 60 2014-02-15

The licensee's approach described above, as currently understood, is consistent with the guidance found in NEI 12-06, as endorsed by JLD-ISG-2012-01, and provides reasonable assurance that the requirements of Order EA-12-049 will be met with respect to protection of FLEX equipment considering the flooding hazard if these requirements are implemented as described.

3.1.2.2 Deployment of FLEX Equipment- Flooding Hazard NEI 12-06, Section 6.2.3.2 states:

There are a number of considerations which apply to the deployment of FLEX equipment for external flood hazards:

1. For external floods with warning time, the plant may not be at power. In fact, the plant may have been shut down for a considerable time and the plant configuration could be established to optimize FLEX deployment. For example, the portable pump could be connected, tested, and readied for use prior to the arrival of the critical flood level. Further, protective actions can be taken to reduce the potential for flooding impacts, including cooldown, berating the RCS [reactor coolant system], isolating accumulators, isolating RCP [reactor coolant pump] seal leak off, obtaining dewatering pumps, creating temporary flood barriers, etc. These factors can be credited in considering how the baseline capability is deployed.
2. The ability to move equipment and restock supplies may be hampered during a flood, especially a flood with long persistence. Accommodations along these lines may be necessary to support successful long-term FLEX deployment.
3. Depending on plant layout, the ultimate heat sink may be one of the first functions affected by a flooding condition. Consequently, the deployment of the FLEX equipment should address the effects of LUHS [loss of ultimate heat sink], as well as ELAP.
4. Portable pumps and power supplies will require fuel that would normally be obtained from fuel oil storage tanks that could be inundated by the flood or above ground tanks that could be damaged by the flood. Steps should be considered to protect or provide alternate sources of fuel oil for flood conditions. Potential flooding impacts on access and egress should also be considered.
5. Connection points for portable equipment should be reviewed to ensure that they remain viable for the flooded condition.
6. For plants that are limited by storm-driven flooding, such as Probable Maximum Surge or Probable Maximum Hurricane (PMH), expected storm conditions should be considered in evaluating the adequacy of the baseline deployment strategies.

Revision 1 Page 12 of 60 2014-02-15

7. Since installed sump pumps will not be available for dewatering due to the ELAP, plants should consider the need to provide water extraction pumps capable of operating in an ELAP and hoses for rejecting accumulated water for structures required for deployment of FLEX strategies.
8. Plants relying on temporary flood barriers should assure that the storage location for barriers and related material provides reasonable assurance that the barriers could be deployed to provide the required protection.
9. A means to move FLEX equipment should be provided that is also reasonably protected from the event.

As discussed in Section 3.1.2.1, the JAF site is designated a "dry site." During the audit process, the licensee restated that because JAF is a "dry" site per NEI guidance, no further evaluation of the flood hazard is required. Therefore, considerations 1 through 9 related to deployment during a flood are not applicable to JAF.

The licensee's approach described above, as currently understood, is consistent with the guidance found in NEI 12-06, as endorsed by JLD-ISG-2012-01, provides reasonable assurance that the requirements of Order EA-12-049 will be met with respect to deployment of FLEX equipment considering the flooding hazard if these requirements are implemented as described.

3.1.2.3 Procedural Interfaces -Flooding Hazard NEI 12-06, Section 6.2.3.3 states:

The following procedural interface considerations should be addressed.

1. Many sites have external flooding procedures. The actions necessary to support the deployment considerations identified above should be incorporated into those procedures.
2. Additional guidance may be required to address the deployment of FLEX for flooded conditions (i.e., connection points may be different for flooded vs.

non-flooded conditions).

3. FLEX guidance should describe the deployment of temporary flood barriers and extraction pumps necessary to support FLEX deployment.

As discussed in section 3.1.2.1 above, the licensee screens as a dry site and as such, no evaluation of the above considerations is required.

The licensee's approach described above, as currently understood, is consistent with the guidance found in NEI 12-06, as endorsed by JLD-ISG-2012-01, and provides reasonable assurance that the requirements of Order EA-12-049 will be met with respect to procedural interfaces considering the flood hazard if these requirements are implemented as described.

3.1.2.4 Considerations in Using Offsite Resources - Flooding Hazard NEI 12-06, Section 6.2.3.4 states:

Revision 1 Page 13 of 60 2014-02-15

Extreme external floods can have regional impacts that could have a significant impact on the transportation of off-site resources.

1. Sites should review site access routes to determine the best means to obtain resources from off-site following a flood.
2. Sites impacted by persistent floods should consider where equipment delivered from off-site could be staged for use on-site.

On page 10, in the section of the Integrated Plan discussing the RRCs, Entergy stated that the industry has selected a vendor to manage two RRCs to provide large equipment in support of the response to BDBEEs. Each RRC will store and maintain five sets of equipment, four of which are expected to be fully deployable upon request. The fifth set is provided to account for equipment that may be unavailable due to its maintenance and testing cycle.

JAF will utilize the industry RRCs for Phase 3 equipment. In an ELAP event, communications would be established between JAF and the SAFER team and required equipment mobilized as needed. JAF will enter into a contractual agreement with the SAFER team. Equipment will initially be moved from an RRC to a local staging area, established by the SAFER team and JAF. The equipment will be prepared at the staging area prior to transport to the site. First arriving equipment, as established during development of the RRC playbook, will be delivered to the site within 24 hours1 days <br />0.143 weeks <br />0.0329 months <br /> from the initial request.

On page 22, in the section of the Integrated Plan discussing coping strategies to maintain core cooling during Phase 3, the licensee stated that equipment transported to the site will be either immediately staged at the point of use or temporarily stored at the lay down area. The lay down area is located outside the protected area on the south side of the plant near the main entrance.

Entergy has not yet identified the local offsite staging area(s) for the RRC FLEX equipment nor evaluated the methods for delivery of equipment from the offsite staging area to the site under various conditions such as seismic, flooding, high winds, and snow, ice and extreme cold. The identification of local offsite staging areas and evaluation of delivery methods during a flooding event has been combined with Confirmatory Item 3.1.1.4.A in Section 4.2.

The licensee's approach described above, as currently understood, is consistent with the guidance found in NEI 12-06, as endorsed by JLD-ISG-2012-01, and subject to the successful closure of issues related to the Confirmatory Item, provides reasonable assurance that the requirements of Order EA-12-049 will be met with respect to offsite resources if these requirements are implemented as described.

3.1.3 High Winds NEI 12-06, Section 7, provides the NRC-endorsed screening process for evaluation of high wind hazards. This screening process considers the hazard due to hurricanes and tornadoes. The first part of the evaluation of high wind challenges is determining whether the site is potentially susceptible to different high wind conditions to allow characterization of the applicable high wind hazard.

The screening for high wind hazards associated with hurricanes should be accomplished by comparing the site location to NEI 12-06, Figure 7-1 (Figure 3-1 of U.S. NRC, "Technical Basis Revision 1 Page 14 of 60 2014-02-15

for Regulatory Guidance on Design Basis Hurricane Wind Speeds for Nuclear Power Plants,"

NUREG/CR-7005, December, 2009); if the resulting frequency of recurrence of hurricanes with wind speeds in excess of 130 mph exceeds 1o-6 per year, the site should address hazards due to extreme high winds associated with hurricanes.

The screening for high wind hazard associated with tornadoes should be accomplished by comparing the site location to NEI 12-06, Figure 7-2, from U.S. NRC, "Tornado Climatology of the Contiguous United States," NUREG/CR-4461, Rev. 2, February 2007; if the recommended o-tornado design wind speed for a 1 6 /year probability exceeds 130 mph, the site should address hazards due to extreme high winds associated with tornadoes.

On page 2, in the section of the Integrated Plan discussing severe storms with high wind assessment, the licensee stated that as indicated in NEI 12-06 Figure 7-1, hurricane winds in excess of 130 mph are not expected to occur at JAF. However, per the NEI 12-06 Figure 7-2, a recommended design tornado wind speed of 169 mph is identified. The licensee stated that the high wind hazard (169 mph tornado winds) is applicable to JAF.

The licensee's approach described above, as currently understood, is consistent with the guidance found in NEI 12-06, as endorsed by JLD-ISG-2012-01, and provides reasonable assurance that the requirements of Order EA-12-049 will be met with respect to high wind screening if these requirements are implemented as described.

3.1.3.1 Protection of FLEX Equipment- High Winds Hazard NEI 12-06, Section 7.3.1 states:

These considerations apply to the protection of FLEX equipment from high wind hazards:

1. For plants exposed to high wind hazards, FLEX equipment should be stored in one of the following configurations:
a. In a structure that meets the plant's design basis for high wind hazards (e.g., existing safety-related structure).
b. In storage locations designed to or evaluated equivalent to ASCE 7-1 0, Minimum Design Loads for Buildings and Other Structures given the limiting tornado wind speeds from Regulatory Guide 1. 76 or design basis hurricane wind speeds for the site.
  • Given the FLEX basis limiting tornado or hurricane wind speeds, building loads would be computed in accordance with requirements of ASCE 7-10. Acceptance criteria would be based on building serviceability requirements not strict compliance with stress or capacity limits. This would allow for some minor plastic deformation, yet assure that the building would remain functional.
  • Tornado missiles and hurricane missiles will be accounted for in that the FLEX equipment will be stored in diverse locations to provide reasonable assurance that N sets of FLEX equipment will remain deployable following the high wind event. This will Revision 1 Page 15 of 60 2014-02-15

consider locations adjacent to existing robust structures or in lower sections of buildings that minimizes the probability that missiles will damage all mitigation equipment required from a single event by protection from adjacent buildings and limiting pathways for missiles to damage equipment.

  • The axis of separation should consider the predominant path of tornados in the geographical location. In general, tornadoes travel from the West or West Southwesterly direction, diverse locations should be aligned in the North-South arrangement, where possible. Additionally, in selecting diverse FLEX storage locations, consideration should be given to the location of the diesel generators and switchyard such that the path of a single tornado would not impact all locations.
  • Stored mitigation equipment exposed to the wind should be adequately tied down. Loose equipment should be in protective boxes that are adequately tied down to foundations or slabs to prevent protected equipment from being damaged or becoming airborne. (During a tornado, high winds may blow away metal siding and metal deck roof, subjecting the equipment to high wind forces.)
c. In evaluated storage locations separated by a sufficient distance that minimizes the probability that a single event would damage all FLEX mitigation equipment such that at least N sets of FLEX equipment would remain deployable following the high wind event. (This option is not applicable for hurricane conditions).
  • Consistent with configuration b., the axis of separation should consider the predominant path of tornados in the geographical location.
  • Consistent with configuration b., stored mitigation equipment should be adequately tied down.

On pages 20, 27, 34, and 41 in the sections of the Integrated Plan regarding the strategies for maintaining core cooling, containment, spent fuel cooling and for safety systems support, respectively, the licensee stated that protection of associated portable equipment from the high wind hazards would be provided by constructing structures that meet the guidelines of NEI 12-06, Section 11, which references Sections 5 through 9 for more detailed guidance for protection of FLEX equipment during specific external events. During the audit process, the licensee stated that the two storage facilities in geographically separate locations with the selected locations in the northeast area of the protected area just east of the radwaste building and outside the protected area to the south and east of the protected area near the off-site well ness center. However, the licensee did not provide the separation distance of the storage buildings or the relation of the axis of separation to the predominant path of tornados in the geographic area to demonstrate that at least N sets of FLEX equipment would remain deployable following the high wind event. This is identified as Open Item 3.1.3.1.A in Section 4.1.

The licensee's approach described above, as currently understood, has raised concerns which must be addressed before confirmation can be provided that the approach is consistent with the Revision 1 Page 16 of 60 2014-02-15

guidance found in NEI 12-06, as endorsed by JLD-ISG-2012-01, such that there would be reasonable assurance that the requirements of Order EA-12-049 will be met with respect to protection of FLEX equipment considering the high wind hazard. This concern is identified as Open Item 3.1.3.1.A above and in Section 4.1.

3.1.3.2 Deployment of FLEX Equipment- High Wind Hazard NEI 12-06, Section 7.3.2 states:

There are a number of considerations which apply to the deployment of FLEX equipment for high wind hazards:

1. For hurricane plants, the plant may not be at power prior to the simultaneous ELAP and LUHS condition. In fact, the plant may have been shut down and the plant configuration could be established to optimize FLEX deployment.

For example, the portable pumps could be connected, tested, and readied for use prior to the arrival of the hurricane. Further, protective actions can be taken to reduce the potential for wind impacts. These factors can be credited in considering how the baseline capability is deployed.

2. The ultimate heat sink may be one of the first functions affected by a hurricane due to debris and storm surge considerations. Consequently, the evaluation should address the effects of ELAP/LUHS, along with any other equipment that would be damaged by the postulated storm.
3. Deployment of FLEX following a hurricane or tornado may involve the need to remove debris. Consequently, the capability to remove debris caused by these extreme wind storms should be included.
4. A means to move FLEX equipment should be provided that is also reasonably protected from the event.
5. The ability to move equipment and restock supplies may be hampered during a hurricane and should be considered in plans for deployment of FLEX equipment.

Consideration 1, 2 and 5 are not applicable to JAF since the plant is not susceptible to the hurricane hazard as noted in Section 3.1.3 of this technical evaluation report.

The Integrated Plan did not address potential impacts from wind generated debris nor identify any debris removal equipment to be available on site to facilitate deployment of FLEX equipment in Phase 2. This is identified as Confirmatory Item 3.1.3.2.A in Section 4.2.

The protection of the means to move FLEX equipment from the high wind hazard has not been addressed in the Integrated Plan. This is identified as Confirmatory Item 3.1.3.2.8 in Section 4.2.

The licensee's approach described above, as currently understood, is consistent with the guidance found in NEI 12-06, as endorsed by JLD-ISG-2012-01, and subject to the successful closure of issues related to the Confirmatory Items, provides reasonable assurance that the requirements of Order EA-12-049 will be met with respect to deployment of FLEX equipment Revision 1 Page 17 of 60 2014-02-15

considering the high wind hazard if these requirements are implemented as described.

3.1.3.3 Procedural Interfaces- High Wind Hazard NEI 12-06, Section 7.3.3, states:

The overall plant response strategy should be enveloped by the baseline capabilities, but procedural interfaces may need to be considered. For example, many sites have hurricane procedures. The actions necessary to support the deployment considerations identified above should be incorporated into those procedures.

On page 8, in the section of the Integrated Plan discussing how strategies will be deployed in all modes, the licensee stated that the identified paths and deployment areas will be accessible during all modes of operation. In addition the clearing of these paths following any significant external event or hazard will be handled on a priority basis. This deployment strategy will be included within an administrative program in order to keep pathways clear or implement actions to clear the pathways.

On page 15, in the section of the Integrated Plan discussing procedures, strategies and guidelines for maintaining core cooling during the initial phases, the licensee stated that JAF will utilize the industry-developed guidance from the Owners Groups, the Electric Power Research Institute (EPRI), and NEI Task team to develop site-specific procedures or guidelines to address the criteria in NEI 12-06. These procedures and/or guidelines will support the existing symptom based command and control strategies in the current emergency operating procedures (EOPs).

The licensee's approach described above, as currently understood, is consistent with the guidance found in NEI 12-06, as endorsed by JLD-ISG-2012-01, and provides reasonable assurance that the requirements of Order EA-12-049 will be met with respect to procedural interfaces if these requirements are implemented as described.

3.1.3.4 Considerations in Using Offsite Resources- High Wind Hazard NEI 12-06, Section 7.3.4 states:

Extreme storms with high winds can have regional impacts that could have a significant impact on the transportation of off-site resources.

1. Sites should review site access routes to determine the best means to obtain resources from off-site following a hurricane.
2. Sites impacted by storms with high winds should consider where equipment delivered from off-site could be staged for use on-site.

On page 10, in the section of the Integrated Plan discussing the RRCs, Entergy stated that the industry has selected a vendor to manage two RRCs to provide large equipment in support of the response to BDBEEs. Each RRC will store and maintain five sets of equipment, four of which are expected to be fully deployable upon request. The fifth set is provided to account for equipment that may be unavailable due to its maintenance and testing cycle.

JAF will utilize the industry RRCs for Phase 3 equipment. In an ELAP event, communications Revision 1 Page 18 of 60 2014-02-15

would be established between JAF and the industry SAFER team and required equipment mobilized as needed. JAF will enter into a contractual agreement with the SAFER team.

Equipment will initially be moved from an RRC to a local staging area, established by the SAFER team and JAF. The equipment will be prepared at the staging area prior to transport to the site. First arriving equipment, as established during development of the RRC playbook, will be delivered to the site within 24 hours1 days <br />0.143 weeks <br />0.0329 months <br /> from the initial request.

On page 22, in the section of the Integrated Plan discussing coping strategies to maintain core cooling during Phase 3, the licensee stated that equipment transported to the site will be either immediately staged at the point of use or temporarily stored at the lay down area. The lay down area is located outside the protected area on the south side of the plant near the main entrance.

Entergy has not yet identified the local offsite staging area(s) for the RRC FLEX equipment nor evaluated the methods for delivery of equipment from the offsite staging area to the site under various conditions such as seismic, flooding, high winds, and snow, ice and extreme cold. The identification of local offsite staging areas and evaluation of delivery methods following high wind events has been combined with Confirmatory Item 3.1.1.4.A in Section 4.2.

The licensee's approach described above, as currently understood, is consistent with the guidance found in NEI 12-06, as endorsed by JLD-ISG-2012-01, and subject to the successful closure of issues related to the Confirmatory Item, provides reasonable assurance that the requirements of Order EA-12-049 will be met with respect to offsite resources if these requirements are implemented as described.

3.1.4 Snow, Ice and Extreme Cold As discussed in NEI 12-06, Section 8.2.1:

All sites should consider the temperature ranges and weather conditions for their site in storing and deploying their FLEX equipment consistent with normal design practices. All sites outside of Southern California, Arizona, the Gulf Coast and Florida are expected to address deployment for conditions of snow, ice, and extreme cold. All sites located North of the 351h Parallel should provide the capability to address extreme snowfall with snow removal equipment. Finally, all sites except for those within Level 1 and 2 of the maximum ice storm severity map contained in Figure 8-2 should address the impact of ice storms.

On page 1 of the Integrated Plan, in the section regarding the determination of applicable extreme external hazards, the licensee stated that the JAF site is located above the 35th parallel and is subject to the extreme cold hazards, including snow and ice. The site is located within the region characterized by NOAA as subject to significant accumulations during three-day snowfalls. The site is located within the region characterized by EPRI as ice severity level 5.

As such, the JAF site is subject to severe icing conditions that could also cause catastrophic destruction to electrical transmission lines.

The licensee stated that the extreme cold hazard, including snow and ice, is applicable to JAF.

The licensee's approach described above, as currently understood, is consistent with the guidance found in NEI 12-06, as endorsed by JLD-ISG-2012-01, and provides reasonable assurance that the requirements of Order EA-12-049 will be met with respect to screening for snow, ice, and extreme cold if these requirements are implemented as described.

Revision 1 Page 19 of 60 2014-02-15

3.1.4.1 Protection of FLEX Equipment - Snow, Ice and Extreme Cold Hazard NEI 12-06, Section 8.3.1 states:

These considerations apply to the protection of FLEX equipment from snow, ice, and extreme cold hazards:

1. For sites subject to significant snowfall and ice storms, portable FLEX equipment should be stored in one of the two configurations.
a. In a structure that meets the plant's design basis for the snow, ice and cold conditions (e.g., existing safety-related structure).
b. In a structure designed to or evaluated equivalent to ASCE 7-10, Minimum Design Loads for Buildings and Other Structures for the snow, ice, and cold conditions from the site's design basis.
c. Provided the N sets of equipment are located as described in a or b above, the N+1 equipment may be stored in an evaluated storage location capable of withstanding historical extreme weather conditions such that the equipment is deployable.
2. Storage of FLEX equipment should account for the fact that the equipment will need to function in a timely manner. The equipment should be maintained at a temperature within a range to ensure its likely function when called upon.

For example, by storage in a heated enclosure or by direct heating (e.g.,

jacket water, battery, engine block heater, etc.).

On page 3, in the section of the Integrated Plan discussing the key assumptions that were considered in the development and implementation of FLEX strategies, the licensee stated that Phase 2 FLEX components stored at the site will be protected against the applicable hazards in accordance with NEI 12-06.

On pages 20, 27, 34, and 41 in the sections of the Integrated Plan regarding the strategies for maintaining core cooling, containment, spent fuel cooling and for safety systems support, respectively, the licensee stated that protection of associated FLEX portable equipment from snow, ice and extreme cold hazards would be provided by constructing structures that meet the guidelines of NEI 12-06, Section 11, which references Sections 5 through 9 for more detailed guidance for protection of FLEX equipment during specific external events. During the audit process, the licensee provided additional information stating that the storage facilities will be heated as necessary in accordance with manufacturer recommendations and that the FLEX storage structures have to meet ASCE 7-10 for snow and ice loading and cold conditions or otherwise meet the site design basis snow and ice loading.

The licensee's approach described above, as currently understood, is consistent with the guidance found in NEI 12-06, as endorsed by JLD-ISG-2012-01, and provides reasonable assurance that the requirements of Order EA-12-049 will be met with respect to protection of FLEX equipment considering the snow, ice and extreme cold hazard if these requirements are implemented as described.

3.1.4.2 Deployment of FLEX Equipment- Snow, Ice and Extreme Cold Hazard Revision 1 Page 20 of 60 2014-02-15

NEI 12-06, Section 8.3.2 states:

There are a number of considerations that apply to the deployment of FLEX equipment for snow, ice, and extreme cold hazards:

1. The FLEX equipment should be procured to function in the extreme conditions applicable to the site. Normal safety-related design limits for outside conditions may be used, but consideration should also be made for any manual operations required by plant personnel in such conditions.
2. For sites exposed to extreme snowfall and ice storms, provisions should be made for snow/ice removal, as needed to obtain and transport FLEX equipment from storage to its location for deployment.
3. For some sites, the ultimate heat sink and flow path may be affected by extreme low temperatures due to ice blockage or formation of frazil ice.

Consequently, the evaluation should address the effects of such a loss of UHS on the deployment of FLEX equipment. For example, if UHS water is to be used as a makeup source, some additional measures may need to be taken to assure that the FLEX equipment can utilize the water.

On page 8, in the section of the Integrated Plan discussing how strategies will be deployed in all modes, the licensee stated that the identified paths and deployment areas will be accessible during all modes of operation. In addition, the clearing of these paths following any significant external event or hazard will be handled on a priority basis. This deployment strategy will be included within an administrative program in order to keep pathways clear or actions to clear the pathways. However, the Integrated Plan did not address the means for snow removal and does not list snow removal equipment in the table on page 45 which shows the portable FLEX equipment for Phase 2. This is identified as Confirmatory Item 3.1.4.2.A in Section 4.2.

The licensee had not addressed the potential impact on the UHS due to ice blockage or formation of frazil ice as a result of extreme cold. This is identified as Open Item 3.1.4.2.8 in Section 4.1.

The licensee's approach described above, as currently understood, is consistent with the guidance found in NEI 12-06, as endorsed by JLD-ISG-2012-01, and subject to the successful closure of issues related to the Confirmatory and Open Items, provides reasonable assurance that the requirements of Order EA-12-049 will be met with respect to deployment of FLEX equipment considering the snow, ice and extreme cold hazard if these requirements are implemented as described.

3.1.4.3 Procedural Interfaces- Snow, Ice, and Extreme Cold Hazard NEI 12-06, Section 8.3.3, states:

The only procedural enhancements that would be expected to apply involve addressing the effects of snow and ice on transporting the FLEX equipment.

This includes both access to the transport path, e.g., snow removal, and appropriately equipped vehicles for moving the equipment.

Revision 1 Page 21 of 60 2014-02-15

As discussed in Section 3.1.4.2 of this report, the licensee has committed to develop an administrative program to ensure pathways remain clear or compensatory actions will be implemented to ensure all strategies can be deployed during all modes of operation.

Entergy has not discussed changes to station procedures relative to an ELAP during a snow, ice and extreme cold hazard. However, the licensee has stated that they have not yet completed plans for storage buildings and deployment paths for portable/FLEX equipment, but will use industry developed guidance to develop specific site procedures.

On page 15, in the section of the Integrated Plan discussing procedures, strategies and guidelines for maintaining core cooling during the initial phases, the licensee stated that JAF will utilize the industry-developed guidance from the Owners Groups, EPRI and NEI Task team to develop site-specific procedures or guidelines to address the criteria in NEI 12-06. These procedures and/or guidelines will support the existing symptom based command and control strategies in the current EOPs.

The licensee's approach described above, as currently understood, is consistent with the guidance found in NEI 12-06, as endorsed by JLD-ISG-2012-01, and provides reasonable assurance that the requirements of Order EA-12-049 will be met with respect to procedural interfaces if these requirements are implemented as described.

3.1.4.4 Considerations in Using Offsite Resources - Snow, Ice and Extreme Cold Hazard NEI 12-06, Section 8.3.4, states:

Severe snow and ice storms can affect site access and can impact staging areas for receipt of off-site material and equipment.

On page 10, in the section of the Integrated Plan discussing the RRCs, Entergy stated that the industry has selected a vendor to manage two RRCs to provide large equipment in support of the response to BDBEEs. Each RRC will store and maintain five sets of equipment, four of which are expected to be fully deployable upon request. The fifth set is provided to account for equipment that may be unavailable due to its maintenance and testing cycle.

JAF will utilize the industry RRCs for Phase 3 equipment. In an ELAP event, communications would be established between JAF and the industry SAFER team and required equipment mobilized as needed. JAF will enter into a contractual agreement with the SAFER team.

Equipment will initially be moved from an RRC to a local staging area, established by the SAFER team and JAF. The equipment will be prepared at the staging area prior to transport to the site. First arriving equipment, as established during development of the RRC playbook, will be delivered to the site within 24 hours1 days <br />0.143 weeks <br />0.0329 months <br /> from the initial request.

On page 22, in the section of the Integrated Plan discussing coping strategies to maintain core cooling during Phase 3, the licensee stated that equipment transported to the site will be either immediately staged at the point of use or temporarily stored at the lay down area. The lay down area is located outside the protected area on the south side of the plant near the main entrance.

Entergy has not yet identified the local offsite staging area(s) for the RRC FLEX equipment nor evaluated the methods for delivery of equipment from the offsite staging area to the site under various conditions such as seismic, flooding, high winds, and snow, ice and extreme cold. The identification of local offsite staging areas and evaluation of delivery methods following a snow, Revision 1 Page 22 of 60 2014-02-15

ice and extreme cold event has been combined with Confirmatory Item 3.1.1.4.A in Section 4.2.

The licensee's approach described above, as currently understood, is consistent with the guidance found in NEI 12-06, as endorsed by JLD-ISG-2012-01, and subject to the successful closure of issues related to the Confirmatory Item, provides reasonable assurance that the requirements of Order EA-12-049 will be met with respect to offsite resources if these requirements are implemented as described.

3.1.5 High Temperatures NEI 12-06, Section 9 states:

All sites will address high temperatures. Virtually every state in the lower 48 contiguous United States has experienced temperatures in excess of 110°F.

Many states have experienced temperatures in excess of 120°F.

In this case, sites should consider the impacts of these conditions on deployment of the FLEX equipment.

On page 2, in the section of the Integrated Plan discussing the determination of applicable extreme external hazards, the licensee noted that per NEI 12-06 Section 9.2, all sites will address high temperatures. Extreme high temperatures are not expected to impact the utilization of off-site resources or the ability of personnel to implement the required FLEX strategies. Site industrial safety procedures currently address activities with a potential for heat stress to prevent adverse impacts on personnel. The licensee stated that the high temperature hazard is applicable to JAF.

The licensee's approach described above, as currently understood, is consistent with the guidance found in NEI 12-06, as endorsed by JLD-ISG-2012-01, and provides reasonable assurance that the requirements of Order EA-12-049 will be met with respect to screening for high temperature hazards if these requirements are implemented as described.

3.1.5.1 Protection of FLEX Equipment- High Temperature Hazard NEI 12-06, Section 9.3.1, states:

The equipment should be maintained at a temperature within a range to ensure its likely function when called upon.

On pages 20, 27, 34, and 41 in the sections of the Integ rated Plan regarding the strategies for maintaining core cooling, containment, spent fuel cooling and for safety systems support, respectively, the licensee stated that protection of associated portable equipment from high temperature hazards would be provided in structures constructed to meet the guidelines of NEI 12-06, Section 11, which references Sections 5 through 9 for more detailed guidance for protection of FLEX equipment during specific external events. During the audit process, the licensee stated that due to the plant's location on the southern shore of Lake Ontario, extreme high temperatures are not expected. FLEX equipment maintained in the FLEX storage structures will be provided with adequate ventilation.

The licensee's approach described above, as currently understood, is consistent with the guidance found in NEI 12-06, as endorsed by JLD-ISG-2012-01, and provides reasonable Revision 1 Page 23 of 60 2014-02-15

assurance that the requirements of Order EA-12-049 will be met with respect to protection of FLEX equipment considering the high temperature hazard if these requirements are implemented as described.

3.1.5.2 Deployment of FLEX Equipment- High Temperature Hazard NEI 12-06, Section 9.3.2 states:

The FLEX equipment should be procured to function, including the need to move the equipment, in the extreme conditions applicable to the site. The potential impact of high temperatures on the storage of equipment should also be considered, e.g., expansion of sheet metal, swollen door seals, etc. Normal safety-related design limits for outside conditions may be used, but consideration should also be made for any manual operations required by plant personnel in such conditions.

There was insufficient information provided in the Integrated Plan to demonstrate that the impact of high temperature has been addressed for the deployment of equipment per the guidance of NEI 12-06. The licensee addressed this issue during the audit process by stating that temperatures will be determined in the areas where portable equipment is stored and at points of deployment where the equipment will operate (and therefore the temperature for which the equipment needs to be procured). Heat and exhaust dissipated from the FLEX equipment during operation will be accounted for in the location where the FLEX equipment will be operated and on the requirements for the equipment.

The licensee's approach described above, as currently understood, is consistent with the guidance found in NEI 12-06, as endorsed by JLD-ISG-2012-01, and provides reasonable assurance that the requirements of Order EA-12-049 will be met with respect to deployment of FLEX equipment considering the high temperature hazard if these requirements are implemented as described.

3.1.5.3 Procedural Interfaces - High Temperature Hazard NEI 12-06, Section 9.3.3 states:

The only procedural enhancements that would be expected to apply involve addressing the effects of high temperatures on the FLEX equipment.

In the Integrated Plan, the licensee has discussed the effect of high area temperatures resulting from an ELAP on accessibility to several rooms and facility locations. However, there is no discussion of the potential effects of high temperatures at the location where the portable/FLEX equipment would be stored or operated in the event of high temperatures. During the audit process, the licensee stated that the new storage buildings housing the FLEX equipment will be provided with ventilation to cope with the high ambient temperatures.

The licensee's approach described above, as currently understood, is consistent with the guidance found in NEI 12-06, as endorsed by JLD-ISG-2012-01, and provides reasonable assurance that the requirements of Order EA-12-049 will be met with respect to procedural interfaces if these requirements are implemented as described.

3.2 PHASED APPROACH Revision 1 Page 24 of 60 2014-02-15

Attachment (2) to Order EA-12-049 describes the three-phase approach required for mitigating BDBEEs in order to maintain or restore core cooling, containment and SFP cooling capabilities.

The phases consist of an initial phase using installed equipment and resources, followed by a transition phase using portable onsite equipment and consumables and a final phase using offsite resources.

To meet these EA-12-049 requirements, Licensees will establish a baseline coping capability to prevent fuel damage in the reactor core or SFP and to maintain containment capabilities in the context of a BDBEE that results in the loss of all ac power, with the exception of buses supplied by safety-related batteries through inverters, and loss of normal access to the UHS. As described in NEI 12-06, Section 1.3, "[p]lant-specific analyses will determine the duration of each phase." This baseline coping capability is supplemented by the ability to use portable pumps to provide reactor pressure vessel (RPV)/reactor makeup in order to restore core or SFP capabilities as described in NEI 12-06, Section 3.2.2, Guideline (13). The NRC endorsed this approach with JLD-ISG-2012-01.

3.2.1 Reactor Core Cooling, Heat Removal, and Inventory Control Strategies NEI 12-06, Table 3-1 and Appendix C summarize one acceptable approach for the reactor core cooling strategies. This approach uses the installed reactor core isolation cooling (RCIC) system, or the high pressure coolant injection (HPCI) system to provide core cooling with installed equipment for the initial phase. This approach relies on depressurization of the RPV for injection with a portable injection source with diverse injection points established to inject through separate divisions/trains for the transition and final phases. This approach also provides for manual initiation of RCIC/HPCI as a contingency for further degradation of installed structures, systems, and components as a result of the beyond-design-basis initiating event.

As described in NEI 12-06, Section 3.2.1. 7, and JLD-ISG-2012-01, Section 2.1, strategies that have a time constraint to be successful should be identified and a basis provided that the time can be reasonably met. NEI 12-06, Section 3, provides the performance attributes, general criteria, and baseline assumptions to be used in developing the technical basis for the time constraints. Since the event is a beyond-design-basis event, the analysis used to provide the technical basis for time constraints for the mitigation strategies may use nominal initial values (without uncertainties) for plant parameters, and best-estimate physics data. All equipment used for consequence mitigation may be assumed to operate at nominal setpoints and capacities. NEI 12-06, Section 3.2.1.2, describes the initial plant conditions for the at-power mode of operation; Section 3.2.1.3 describes the initial conditions; and Section 3.2.1.4 describes boundary conditions for the reactor transient.

Acceptance criteria for the analyses serving as the technical basis for establishing the time constraints for the baseline coping capabilities described in NEI 12-06, which provide an acceptable approach, as endorsed by JLD-ISG-2012-01, to meeting the requirements of EA 049 for maintaining core cooling are 1) the preclusion of core damage as discussed in NEI 12-06, Section 1.3 as the purpose of FLEX; and 2) the performance attributes as discussed in Appendix C.

As described in NEI12-06, Section 1.3, plant-specific analyses determine the duration of the phases for the mitigation strategies. In support of its mitigation strategies, the licensee should perform a thermal-hydraulic analysis for an event with a simultaneous loss of all ac power and loss of normal access to the ultimate heat sink for an extended period (the ELAP event).

Revision 1 Page 25 of 60 2014-02-15

3.2.1.1. Computer Code Used for ELAP Analysis.

NEI 12-06, Section 1.3 states in part:

To the extent practical, generic thermal hydraulic analyses will be developed to support plant specific decision-making. Justification for the duration of each phase will address the on-site availability of equipment, the resources necessary to deploy the equipment consistent with the required timeline, anticipated site conditions following the beyond-design-basis external event, and the ability of the local infrastructure to enable delivery of equipment and resources from offsite.

On pages 7, 12, 14, and 24 of the Integrated Plan, the licensee identified the industry-developed Modular Accident Analysis Program (MAAP) code as the analysis method for determining plant response to the ELAP event. The plant response and FLEX implementation strategies are shown in the Integrated Plan in Attachment 1A "Sequence of Events (SOE)

Timeline" which includes the time constraints and the technical basis for the site. During the audit the licensee stated that MAAP version 4.0.5 was used, using site-specific inputs; and the site-specific analysis followed as a guide the generic analysis done by GE Hitachi Nuclear Energy (GEH) in NEDC-33771 P/NED0-33771 "GEH Evaluation of FLEX Implementation Guidelines," Revision 0 (hereinafter referred to as NEDC-33771 P). (Revision 1 of this document was submitted to the NRC for information and has a publicly available version at ADAMS Accession No. ML130370742.)

MAAP was written to simulate the response of both current and advanced light water reactors to loss of coolant accident (LOCA) and non-LOCA transients for probabilistic risk analyses as well as severe accident sequences. The code has been used to evaluate a wide range of severe accident phenomena, such as hydrogen generation and combustion, steam formation, and containment heating and pressurization.

While the NRC staff acknowledges that MAAP4 has been used many times over the years and in a variety of forums for severe and beyond design basis analysis, MAAP4 is not an NRC-approved code, and the NRC staff has not examined its technical adequacy for performing thermal hydraulic analyses. Therefore, during the review of licensees' Integrated Plan, the issue of using MAAP4 was raised as a Generic Concern and was addressed by NEI in their position paper dated June 2013, entitled "Use of Modular Accident Analysis Program (MAAP4) in Support of Post-Fukushima Applications" (ADAMS Accession No. ML13190A201 ). After review of this position paper, the NRC staff endorsed a resolution through letter dated October 3, 2013 (ADAMS Accession No. ML13275A318). This endorsement contained five limitations on the MAAP4 computer code's use for simulating the ELAP event for Boiling Water Reactors (BWRs). Those limitations and their corresponding Confirmatory Item numbers for this report are provided as follows:

(1) From the June 2013 position paper, benchmarks must be identified and discussed which demonstrate that MAAP is an appropriate code for the simulation of an ELAP event at your facility. This is Confirmatory Item 3.2.1.1.A in Section 4.2.

(2) The collapsed level must remain above Top of Active Fuel (TAF) and the cool down rate must be within technical specifications limits. This is Confirmatory Item 3.2.1.1. 8 in Section 4.2.

Revision 1 Page 26 of 60 2014-02-15

(3) MAAP must be used in accordance with Sections 4.1, 4.2, 4.3, 4.4, and 4.5 of the June 2013 position paper. This is Confirmatory Item 3.2.1.1.C in Section 4.2.

(4) In using MAAP, the licensee must identify and justify the subset of key modeling parameters cited from Tables 4-1 through 4-6 of the "MAAP Application Guidance, Desktop Reference for Using MAAP Software, Revision 2" (Electric Power Research Institute Report 1020236). This should include response at a plant-specific level regarding specific modeling options and parameter choices for key models that would be expected to substantially affect the ELAP analysis performed for that licensee's plant.

Although some suggested key phenomena are identified below, other parameters considered important in the simulation of the ELAP event by the vendor /licensee should also be included.

a. Nodalization
b. General two-phase flow modeling
c. Modeling of heat transfer and losses
d. Choked flow
e. Vent line pressure losses
f. Decay heat (fission products I actinides I etc.)

This is Confirmatory Item 3.2.1.1.D in Section 4.2.

(5) The specific MAAP analysis case that was used to validate the timing of mitigating strategies in the Integrated Plan must be identified and should be available on the ePortal for NRC staff to view. Alternately, a comparable level of information may be included in the supplemental response. In either case, the analysis should include a plot of the collapsed vessel level to confirm that TAF is not reached (the elevation of the TAF should be provided) and a plot of the temperature cool down to confirm that the cool down is within technical specifications limits. This is Confirmatory Item 3.2.1.1. E in Section 4.2.

The concern regarding the MAAP limitations was addressed during the audit process. The licensee stated that JAF will provide an updated MAAP analysis which will conform to the limitations identified in the NRC staff's endorsement letter.

The licensee's approach described above, as currently understood, is consistent with the guidance found in NEI 12-06, as endorsed by JLD-ISG-2012-01, and subject to the successful closure of issues related to the Confirmatory Items, provides reasonable assurance that the requirements of Order EA-12-049 will be met with respect to the use of computer codes if these requirements are implemented as described.

3.2.1.2. Recirculation Pump Seal Leakage Models.

Conformance with the guidance of NEI 12-06, Section 3.2.1.5, Paragraph (4) includes consideration of recirculation pump seal leakage. When determining time constraints and the ability to maintain core cooling, it is important to consider losses to the RCS inventory as this can have a significant impact on the SOE. Special attention is paid to the recirculation pump seals because these can fail in a station blackout (SBO) event and contribute to beyond normal system leakage.

Revision 1 Page 27 of 60 2014-02-15

Entergy has not discussed reactor coolant inventory loss including normal system leakage and losses due to BWR recirculation pump seal leakage that is included in the ELAP analysis.

There is no discussion of the details of seal leakage rates, the details of the seal qualification tests, the seal leakage rate models and supporting test data, and leakage rate pressure-dependence.

During the audit process, the licensee stated that the current MAAP analysis will be updated to address the code limitations as indicated in Section 3.2.1.1 of this technical evaluation report.

Information regarding the seal leakage rates will also be provided when the reanalysis is completed. This is identified as Confirmatory Item 3.2.1.2.A in Section 4.2.

The licensee's approach described above, as currently understood, is consistent with the guidance found in NEI 12-06, as endorsed by JLD-ISG-2012-01, and subject to the successful closure of issues related to the Confirmatory Items, provides reasonable assurance that the requirements of Order EA-12-049 will be met with respect to the recirculation pump seal leakage model if these requirements are implemented as described.

3.2.1.3 Sequence of Events NEI 12-06 discusses an event timeline and time constraints in several sections of the document, for example Section 1.3, Section 3.2.1.7 principle (4) and (6), Section 3.2.2 Guideline (1) and Section 12.1.

NEI 12-06, Section 3.2.2 addresses the minimum baseline capabilities:

Each site should establish the minimum coping capabilities consistent with unit-specific evaluation of the potential impacts and responses to an ELAP and LUHS. In general, this coping can be thought of as occurring in three phases:

  • Phase 1: Cope relying on installed plant equipment.
  • Phase 2: Transition from installed plant equipment to on-site FLEX equipment.
  • Phase 3: Obtain additional capability and redundancy from off-site equipment until power, water, and coolant injection systems are restored or commissioned.

In order to support the objective of an indefinite coping capability, each plant will be expected to establish capabilities consistent with Table 3-1 (BWRs). Additional explanation of these functions and capabilities are provided in NEI 12-06 Appendix C, "Approach to BWR Functions."

The Integrated Plan includes a discussion of time constraints on pages 5 and 6 and in the "Sequence of Events Timeline", Attachment 1A, on pages 48 and 49.

In describing the technical basis for the SOE timeline, on page 6 of the Integrated Plan the licensee stated that GEH, on behalf of the Boiling Water Reactor Owners Group (BWROG),

developed document NEDC-33771 P to supplement the guidance in NEI 12-06 by providing additional BWR-specific information regarding the individual plant response to an ELAP event.

The document includes the identification of the generic event scenario and expected plant response, the associated analytical bases and recommended actions for performance of a site-Revision 1 Page 28 of 60 2014-02-15

specific gap analysis. In the document, GEH utilized the NRC-accepted SUPERHEX (SHEX) computer code methodology for the BWR long-term containment analysis for the ELAP analysis. As part of this document, a generic BWR 4/Mark I containment nuclear steam supply system (NSSS) evaluation was performed. The generic BWR 4/Mark I containment analysis is generally applicable to the JAF (a BWR 4/Mark I plant) coping strategy because it supplements the guidance in NEI 12-06 by providing BWR-specific information regarding plant response for core cooling and containment integrity. The Integrated Plan states that the guidance provided in the BWROG report was utilized as appropriate to develop coping strategies and for prediction of the plant's response.

During the audit process, the licensee stated that site-specific analyses were performed to develop the SOE timeline for the JAF plant. NEDC-33771 P was not used to develop the JAF site-specific coping strategies for maintaining core and containment cooling but used as a guide.

The SOE timeline presented in the Integrated Plan is based on analyses using the MAAP code as discussed in Section 3.2.1.1 of this report. The licensee stated that the site-specific reanalysis will be performed considering the code limitations identified in Section 3.2.1.1. This reanalysis may affect the time constraints identified in the SOE. This is identified as Confirmatory Item 3.2.1.3.A in Section 4.2.

The licensee's approach described above, as currently understood, is consistent with the guidance found in NEI 12-06, as endorsed by JLD-ISG-2012-01, and, subject to the successful closure of issues related to the Confirmatory Item, provides reasonable assurance that the requirements of Order EA-12-049 will be met with respect to the sequence of events timeline if these requirements are implemented as described.

3.2.1.4 Systems and Components for Consequence Mitigation NEI 12-06, Section 11 provides details on the equipment quality attributes and design for the implementation of FLEX strategies. It states:

Equipment associated with these strategies will be procured as commercial equipment with design, storage, maintenance, testing, and configuration control as outlined in this section [Section 11 ]. If the equipment is credited for other functions (e.g., fire protection), then the quality attributes of the other functions apply.

And, Design requirements and supporting analysis should be developed for portable equipment that directly performs a FLEX mitigation strategy for core, containment, and SFP that provides the inputs, assumptions, and documented analysis that the mitigation strategy and support equipment will perform as intended.

NEI 12-06, Section 3.2.1.12 states:

Equipment relied upon to support FLEX implementation does not need to be qualified to all extreme environments that may be posed, but some basis should be provided for the capability of the equipment to continue to function.

Revision 1 Page 29 of60 2014-02-15

On page 3 of the Integrated Plan, the licensee stated that the portable FLEX components will be procured commercially and will be designed to be capable of performing in response to the screened in hazards in accordance with NEI 12-06.

On pages 9 and 10, in the section of the Integrated Plan discussing program controls, the licensee stated that JAF will utilize the standard EPRI industry preventive maintenance (PM) process for establishing the maintenance actions for FLEX components. PM procedures will be established for portable components that directly perform in the mitigation strategy for the key FLEX safety functions (i.e., core cooling, containment integrity, and spent fuel cooling). These procedures will consider NEI 12-06 guidance, vendor recommendations, and applicable industry standards. Testing procedures will be developed and performed at frequencies established based on type of equipment and considerations made within EPRI guidelines.

On page 45 of the Integrated Plan, the design requirements for the FLEX equipment are shown in the table listing required equipment for Phase 2 mitigation strategies. During the audit process, the licensee stated that the sizing of the pumps are bounding values based on conceptual design calculations and may change slightly when the detailed design is completed.

The licensee further stated that the loading calculations for the 600 Vac generators for Phase 2 and the 4160 Vac generator(s) for Phase 3 have not been completed. This is identified as Confirmatory Item 3.2.1.4.A in Section 4.2.

The licensee's approach described above, as currently understood, is consistent with the guidance found in NEI 12-06, as endorsed by JLD-ISG-2012-01, and subject to the successful closure of issues related to the Confirmatory Item, provides reasonable assurance that the requirements of Order EA-12-049 will be met with respect to systems and components for consequence mitigation if these requirements are implemented as described.

3.2.1.5 Monitoring Instrumentation and Controls NEI 12-06, Section 3.2.1.1 0 provides information regarding instrumentation and controls necessary for the success of the coping strategies. NEI 12-06 provides the following guidance:

The parameters selected must be able to demonstrate the success of the strategies at maintaining the key safety functions as well as indicate imminent or actual core damage to facilitate a decision to manage the response to the event within the Emergency Operating Procedures and FLEX Support Guidelines or within the SAMGs [Severe Accident Management Guidelines]. Typically these parameters would include the following:

  • Containment Pressure Suppression Pool Level Suppression Pool Temperature
  • SFP Level The plant-specific evaluation may identify additional parameters that are needed in order to support key actions identified in the plant procedures/guidance, or to indicate imminent or actual core damage.

On pages 15 and 16, in the section of the Integrated Plan discussing instrumentation credited Revision 1 Page 30 of 60 2014-02-15

for supporting the coping strategy to maintain core cooling during the initial phase, the licensee listed the following instruments:

Reactor Vessel Essential Instrumentation:

  • RPV Pressure Containment Essential Instrumentation:
  • Drywell Pressure
  • Torus Pressure
  • Drywell Temperature
  • Torus Temperature
  • Drywell Water Level
  • Torus Water Level Spent Fuel Pool Essential Instrumentation: SFP Level In addition, the licensee stated that JAF will have the following key instrument remain available following load stripping due to its power source: Condensate Storage Tank (CST) Level.

On page 25, in the section of the Integrated Plan discussing instrumentation credited for supporting the coping strategy to maintain containment during the initial phase, the licensee listed additional instrumentation as follows:

  • RHV Valve Position Indication
  • RHV System Pressure
  • RHV Effluent Temperature On page 15, in the section of the Integrated Plan discussing modifications to support coping strategies to maintain core cooling during the initial phase, the licensee stated that a modification will be implemented to change the power supply of ac-powered critical instrumentation (e.g., torus temperature, pressure and level, drywell temperature and pressure) to move it from the ac instrument bus to a station battery-backed source. This will provide continuous power to critical instruments so that critical containment parameters can be monitored throughout the event. During the audit process, the licensee further clarified that the power will be from the 125 volt de power system and the instrumentation will be available to the operators from time of ELAP initiation. Other critical instrumentation is powered from the 125 volt de power system and will be available without the need for a modification. Completion of the modification is identified as Confirmatory Item 3.2.1.5.A in Section 4.2.

The licensee's approach described above, as currently understood, is consistent with the guidance found in NEI 12-06, as endorsed by JLD-ISG-2012-01, and subject to the successful closure of issues related to the Confirmatory Item, provides reasonable assurance that the requirements of Order EA-12-049 will be met with respect to monitoring instrumentation and controls if these requirements are implemented as described.

3.2.1.6 Motive Power, Valve Controls and Motive Air System NEI 12-06, Section 12.1 provides guidance regarding the scope of equipment that will be Revision 1 Page 31 of 60 2014-02-15

needed from off-site resources to support coping strategies. NEI 12-06, Section 12.1 states that:

Arrangements will need to be established by each site addressing the scope of equipment that will be required for the off-site phase, as well as the maintenance and delivery provisions for such equipment.

And, Table 12-1 provides a sample list of the equipment expected to be provided to each site from off-site within 24 hours1 days <br />0.143 weeks <br />0.0329 months <br />. The actual list will be specified by each site as part of the site-specific analysis.

Table 12-1 includes "Portable air compressor or nitrogen bottles & regulators (if required by plant strategy).

On page 13, in the section of the Integrated Plan discussing coping strategies for maintaining core cooling during the initial phase, the licensee stated that the primary method of reactor pressure control is by operation of the safety/relief valves (SRVs). The licensee stated that all SRVs can be either automatically actuated by excess steam pressure or the valves can also be opened manually through remote switches and that the SRVs are equipped with nitrogen accumulators. The licensee stated that in addition to the accumulators, a pneumatic supply system for the SRVs that are part of the automatic depressurization system (ADS) provides a reliable, safety-related, seismically qualified, 100-day supply following a design basis accident to enable long-term cooling. A FLEX air compressor is listed in the table on page 45 as equipment available for coping in Phase 2.

On page 21 of the Integrated Plan, discussing coping strategies for maintaining core cooling during the Phase 3, the licensee stated that the reactor core cooling strategy is to place one loop of the residual heat removal (RHR) system into the shutdown cooling mode. This will be accomplished by powering up a Division I or II RHR pump from the Class 1E emergency bus utilizing a 4160 Vac FLEX portable diesel generator supplied by the RRC. Re-powering either bus can power an RHR pump that can provide flow to either RHR heat exchanger (HX). A modification will be implemented to provide a cross-connection between the fire protection system and one train of the residual heat removal service water (RHRSW) system. The seismically qualified diesel-driven fire pump will be used to provide lake water to the tube side of the appropriate RHR heat exchangers. The diesel-driven fire pump provides 2500 gallons per minute at a nominal discharge pressure of 125 psig. The licensee stated that the 4160 Vac RRC FLEX diesel generator will be capable of carrying approximately 2000 kW load which is sufficient to carry all of the loads on either of the two Class 1E 4160 Vac buses necessary to support the Phase 3 FLEX strategies which includes an RHR pump and its support equipment.

On pages 26 and 28 of the Integrated Plan, discussing maintaining containment during Phases 2 and 3, the licensee stated that the primary strategy to maintain containment integrity utilizes the reliable hardened vent system (RHVS), which is permanently installed plant equipment. The RHVS is expected to rely on de power, which may require implementation of the FLEX strategies during Phase 2 to re-power a battery charger. The battery charger can be repowered by the 600 Vac FLEX diesel generator stored on site or during Phase 3 by the 4160 Vac diesel generator (DG) supplied by the RRC.

Revision 1 Page 32 of 60 2014-02-15

On page 32 of the Integrated Plan, discussing maintaining SFP cooling during Phase 2, the licensee stated that the portable FLEX diesel driven pump taking suction from Lake Ontario will supply makeup water to the SFP. On page 36, the licensee stated that for Phase 3 the strategy for maintaining SFP cooling will be the same as in Phase 2.

On page 45 of the Integrated Plan the licensee listed portable equipment required to provide motive power to support the coping strategies during Phase 2. The equipment includes diesel driven portable air compressors and diesel driven electric generators. On page 46 the licensee listed a diesel driven generator, supplied by the RRC, to provide motive power during Phase 3.

The licensee's approach described above, as currently understood, is consistent with the guidance found in NEI 12-06, as endorsed by JLD-ISG-2012-01, and provides reasonable assurance that the requirements of Order EA-12-049 will be met with respect to motive power, valve controls and motive air if these requirements are implemented as described.

3.2.1. 7 Cold Shutdown and Refueling NEI12-06, Table 1-1, lists the coping strategy requirements as presented in Order EA 049. Item (4) of that list states:

Licensee or CP holders must be capable of implementing the strategies in all modes.

The NRC staff reviewed the licensee's Integrated Plan and determined that the Generic Concern related to shutdown and refueling guidelines is applicable to the plant. This Generic Concern has been resolved generically through the NRC's endorsement of NEI position paper entitled "Shutdown/Refueling Modes" (ADAMS Accession No. ML13273A514); and has been endorsed by the NRC in a letter dated September 30, 2013 (ADAMS Accession No. ML13267A382).

The position paper describes how licensees will, by procedure, maintain equipment available for deployment in shutdown and refueling modes. The NRC staff concluded that the position paper provides an acceptable approach for demonstrating that the licensees are capable of implementing mitigating strategies in all modes of operation. During the audit process, the licensee informed the NRC staff of its plans to abide by this generic resolution. The NRC staff will evaluate the licensee's resulting program through the audit and inspection processes.

The licensee's approach described above, as currently understood, is consistent with the guidance found in NEI 12-06, as endorsed by JLD-ISG-2012-01, and provides reasonable assurance that the requirements of Order EA-12-049 will be met with respect to the shutdown and refueling modes if these requirements are implemented as described.

3.2.1.8 Use of Portable Pumps NEI 12-06, Section 3.2.2, Guideline (13), states in part:

Regardless of installed coping capability, all plants will include the ability to use portable pumps to provide RPV/RCS/SG makeup as a means to provide diverse capability beyond installed equipment. The use of portable pumps to provide RPV/RCS/SG makeup requires a transition and interaction with installed systems. For example, transitioning from RCIC to a portable FLEX pump as the Revision 1 Page 33 of 60 2014-02-15

source for RPV makeup requires appropriate controls on the depressurization of the RPV and injection rates to avoid extended core uncovery. Similarly, transition to a portable pump for SG makeup may require cooldown and depressurization of the SGs in advance of using the portable pump connections.

Guidance should address both the proactive transition from installed equipment to portable and reactive transitions in the event installed equipment degrades or fails. Preparations for reactive use of portable equipment should not distract site resources from establishing the primary coping strategy. In some cases, in order to meet the time-sensitive required actions of the site-specific strategies, the FLEX equipment may need to be stored in its deployed position.

The fuel necessary to operate the FLEX equipment needs to be assessed in the plant specific analysis to ensure sufficient quantities are available as well as to address delivery capabilities.

NEI 12-06 Section 11.2 states in part:

Design requirements and supporting analysis should be developed for portable equipment that directly performs a FLEX mitigation strategy for core, containment, and SFP that provides the inputs, assumptions, and documented analysis that the mitigation strategy and support equipment will perform as intended.

On page 12 of the Integrated Plan in the section describing core cooling in Phase 1, the licensee stated that the existing installed RCIC pump will draw water from either the suppression pool or the CST and inject water into the reactor pressure vessel. Based on the initial volume in the CSTs (200,000 gallons), in conjunction with the volume of water in the torus used during hours 1 through 5 of the event, this will enable RCIC to provide make-up for at least 35 hours1.458 days <br />0.208 weeks <br />0.0479 months <br /> without replenishment of the CSTs.

On page 17 of the Integrated Plan in the section describing core cooling in Phase 2, the licensee stated that prior to the depletion of the CST, the flow path will be established from the existing seismically-qualified, diesel-driven fire pump to provide make up to the reactor pressure vessel. A pre-staged hose will be used to connect the fire protection system to the RHR service water (RHRSW) system. RHRSW system is then cross connected to the RHR system allowing makeup flow into the reactor pressure vessel.

Also on page 1 of the Integrated Plan in the section describing core cooling in Phase 2, the licensee stated that a portable FLEX pump can be used to draw water from the intake bay and pump it through a temporary hose connected to the RHRSW system. The FLEX pump would be lowered through a hatch at El 255' of the screenwell and pump into a temporary hose to the RHRSW connection to provide make up to the reactor pressure vessel by cross connecting to the RHR system as described above. This portable FLEX pump can also be used to provide makeup water to the CST. Replenishment of the CST will be accomplished either through a new underground pipe or above ground through approximately 600' of hose. This same pump is also used to provide the make up to the spent fuel pool, which will be discussed below in the Maintain Spent Fuel Pool Cooling function. Four FLEX diesel driven pumps will be stored on site. Each pump is rated at 450 gpm at 400ft. head.

The Integrated Plan described the use of FLEX pumps taking suction from the Lake Ontario, but did not address the impact of water quality on entrained debris potentially resulting in a Revision 1 Page 34 of 60 2014-02-15

restriction of coolant flow across the fuel assemblies to an extent that would inhibit adequate flow to the core. During the audit process, the licensee stated that FLEX support guidelines will contain guidance on prioritizing water sources from the most to least pure. The current strategy, as presented in the Integrated Plan, includes transitioning to shutdown cooling in Phase 3 for long term cooling thus reducing the need to supply water for RCS makeup. Long term cooling strategies, including the evaluation of raw water, will be finalized during the detailed design process. This is identified as Confirmatory Item 3.2.1.8.A in Section 4.2.

Fuel for the portable FLEX equipment is discussed in Section 3.2.4.9 of this report.

The licensee's approach described above, as currently understood, is consistent with the guidance found in NEI 12-06, as endorsed by JLD-ISG-2012-01, and subject to the successful closure of issues related to the Confirmatory Item, provides reasonable assurance that the requirements of Order EA-12-049 will be met with respect to use of portable pumps if these requirements are implemented as described.

3.2.2 Spent Fuel Pool Cooling Strategies NEI 12-06, Table 3-1 and Appendix C summarize one acceptable approach for the SFP cooling strategies for BWRs. This approach uses a portable injection source to provide 1) makeup via hoses on the refuel deck/floor capable of exceeding the boil-off rate for the design basis heat load; 2) makeup via connection to SFP cooling piping or other alternate location capable of exceeding the boil-off rate for the design basis heat load; and alternatively 3) spray via portable monitor nozzles from the refueling deck/floor capable of providing a minimum of 200 gallons per minute (gpm) per unit (250 gpm to account for overspray). This approach will also provide a vent pathway for steam and condensate from the SFP.

As described in NEI 12-06, Section 3.2.1. 7 and JLD-ISG-2012-01, Section 2.1, strategies that have a time constraint to be successful should be identified and a basis provided that the time can be reasonably met. NEI 12-06, Section 3 provides the performance attributes, general criteria, and baseline assumptions to be used in developing the technical basis for the time constraints. Since the event is a beyond-design-basis event, the analysis used to provide the technical basis for time constraints for the mitigation strategies may use nominal initial values (without uncertainties) for plant parameters, and best-estimate physics data. All equipment used for consequence mitigation may assume to operate at nominal setpoints and capacities.

NEI 12-06, Section 3.2.1.2 describes the initial plant conditions for the at-power mode of operation; Section 3.2.1.3 describes the initial conditions; and Section 3.2.1.6 describes SFP conditions.

NEI 12-06, Section 3.2.1.1 provides the acceptance criterion for the analyses serving as the technical basis for establishing the time constraints for the baseline coping capabilities described in NEI 12-06, which provide an acceptable approach to meeting the requirements of EA-12-049 for maintaining SFP cooling. This criterion is keeping the fuel in the SFP covered.

NEI 12-06, Section 3.2.1.6 provides the initial boundary conditions for SFP cooling.

1. All boundaries of the SFP are intact, including the liner, gates, transfer canals, etc.
2. Although sloshing may occur during a seismic event, the initial loss of SFP inventory does not preclude access to the refueling deck around the pool.

Revision 1 Page 35 of 60 2014-02-15

3. SFP cooling system is intact, including attached piping.
4. SFP heat load assumes the maximum design basis heat load for the site.

On page 30, in the section of the Integrated Plan discussing maintaining SFP cooling during the initial phase, the licensee stated that there are no Phase 1 actions required for more than 35 hours1.458 days <br />0.208 weeks <br />0.0479 months <br />. Fuel in the SFP is cooled by the existing water inventory requirements of at least 21 feet-7 inches of water normally maintained over the top of the fuel. Using the design basis heat load, the SFP water inventory will heat up from an initial114 degrees Fahrenheit to 212 degrees Fahrenheit during the first 37.9 hours0.375 days <br />0.0536 weeks <br />0.0123 months <br /> and there would be approximately 305 hours12.708 days <br />1.815 weeks <br />0.418 months <br /> before any uncovering of the fuel would occur. These values consider the decay heat from a fresh reload batch in the pool upon startup from a 30-day refueling outage.

SFP level monitoring is accomplished using the instrumentation installed per NRC Order EA 051.

The licensee also stated that the maximum heat load situation in the pool could occur if a full-core was off- loaded into the pool. The time to boil in this scenario could be as little as 8.1 hours0.0417 days <br />0.00595 weeks <br />0.00137 months <br />. Even with this time to boil the fuel is expected to be protected for a substantial amount of time: the time to uncover the fuel is 65 hours2.708 days <br />0.387 weeks <br />0.089 months <br /> and the peak required make up rate is approximately 60 gpm. The licensee stated that this indicates there is time to deploy the planned FLEX equipment. The licensee stated that this scenario occurs during an outage at the plant and that more staffing resources would be available to implement the mitigation strategy (i.e., increased staffing is planned during outages to support the outage initiatives).

On pages 32 and 33, in the section of the Integrated Plan discussing maintaining SFP cooling during the transition phase, the licensee stated that the transition from Phase 1 to Phase 2 for SFP cooling function will occur at approximately 37 hours1.542 days <br />0.22 weeks <br />0.0507 months <br /> in the normal condition in which fuel has been transferred to the pool after a refueling. SFP makeup connections can be established using portable FLEX equipment. The FLEX pump used to provide the SFP makeup function is the same FLEX pump described in Section 3.2.1.8 in this report which provides make up to the reactor pressure vessel and the CST. Portable equipment (i.e., provisions for makeup to the SFP) is expected to be in place for utilization at approximately 24 hours1 days <br />0.143 weeks <br />0.0329 months <br />. Makeup to the SFP will be provided by one of three baseline capabilities.

Method 1 - Makeup via permanent piping The first method uses an existing diesel driven fire pump taking suction from Lake Ontario aligned to the fire protection system header. A staged hose will be connected between the fire protection system and the RHRSW system. Flow can then be directed to the fuel pool cooling assist piping to the spent fuel pool cooling system. This provides make up flow to the SFP through seismically qualified piping to spargers located near the floor of the pool. The fire pump is capable of pumping 2500 gpm at 125 psig discharge pressure; the required flow rate for pool make up is less than 35 gpm.

Method 2 - Makeup via hose The second method to provide water to the SFP utilizes the portable diesel driven FLEX pump.

This pump will discharge into piping or hose and flow from the screen house around to near the truck bay of the reactor building, and up to the operating floor of the reactor building. At that point, a hose long enough to reach the SFP is connected to allow filling of the SFP utilizing lake water.

Revision 1 Page 36 of 60 2014-02-15

Method 3 - Makeup via spray The third method is a flow path ending in spray nozzles at the pool. The third method of providing water to the SFP utilizes the diesel driven FLEX pump and flow path described in Method 2. The hose connection at the operating floor, however, is connected to two monitor spray nozzles rather than supplying make up directly into the pool. Two 100 gpm nozzles, which satisfy the JAF 10 CFR 50.54(hh)(2) commitment, are currently stored in the reactor building. The FLEX pump will be capable of supplying 200 gpm to the refuel floor at a pressure sufficient for the spray nozzles.

During the audit process, the licensee clarified that the method of cooling the spent fuel during Phase 3 will be to use the same means as in Phase 2 and that water to the SFP can be added indefinitely using the portable diesel driven FLEX pump. The licensee also clarified conformance to the NEI guidance that the spray flow rate be 250 gpm to account for overspray.

The licensee stated that during the detailed design, considerations will include nozzle locations, the spray angle, and pattern selected and the required flow rate to ensure that with any anticipated overshoot or undershoot of the SFP the required minimum of 200 gpm to the SFP is provided.

On page 40, in the section of the Integrated Plan discussing the SFP area ventilation during the transition phase, the licensee stated that a vent pathway for steam and condensate from the SFP can be established by opening the truck bay doors (at grade elevation) and opening the airlock on El. 369'-6" to the outside of the reactor building. The SBO/FLEX strategy is to establish this ventilation flow path early in the event response period, e.g., before the pool begins to boil, or prior to about 37 hours1.542 days <br />0.22 weeks <br />0.0507 months <br />. Ventilation can be enhanced by re-powering a standby gas treatment system (SGTS) fan. A modification to provide new connection points for a portable diesel generator unit to re-power a SGTS fan will be considered. A FLEX 600 Vac, 200 kW DG will be connected as conditions warrant. A 200 kW, 600Vac FLEX DG can power a SGTS fan and its valve.

During the audit process, the licensee clarified that there are several potential locations to establish a vent path to accommodate boiling in the SFP. The method of ventilation, including any power requirements, for the SFP will be addressed in the detailed design phase. This is identified as Confirmatory Item 3.2.2.A in Section 4.2.

The licensee's approach described above, as currently understood, is consistent with the guidance found in NEI 12-06, as endorsed by JLD-ISG-2012-01, and subject to the successful closure of issues related to the Confirmatory Item, provides reasonable assurance that the requirements of Order EA-12-049 will be met with respect to SFP cooling if these requirements are implemented as described.

3.2.3 Containment Functions Strategies NE112-06, Table 3-1 and Appendix C provide a description of the safety functions and performance attributes for BWR containments which are to be maintained during an ELAP as defined by Order EA-12-049. The safety function applicable to a BWR with a Mark I containment listed in Table 3-1 is Containment Pressure Control/Heat Removal, and the method cited for accomplishing this safety function is Containment Venting or Alternative Containment Heat Removal. Furthermore, the performance attributes listed in Table C-2 denote the containment's function is to provide a reliable means to assure containment heat removal. JLD-ISG-2012-01, Section 5.1 is aligned with this position stating, in part, that the goal of this Revision 1 Page 37 of 60 2014-02-15

strategy is to relieve pressure from the containment.

On page 24, in the section of the Integrated Plan discussing maintaining containment integrity during the initial phase, the licensee stated that during Phase 1, containment integrity is maintained using the normal installed design features of the containment such as the containment isolation valves and the RHVS. In accordance with NEI 12-06, the containment is assumed to be isolated following the event. As the torus heats up and the water begins to boil, the containment will begin to heat up and pressurize. Additionally, the water level in the torus rises due to the transfer of inventory from the CST to the torus (via RCIC and SRVs). According to the JAF site specific event response analysis, the limiting containment parameter will be the torus design pressure. The licensee stated that the rise in drywell pressure can be reversed before the design pressure limit is reached. This is accomplished by venting the containment.

The licensee further stated that the containment design pressure is 56 psig. The event response analysis assumed that the containment is vented at about 23 hours0.958 days <br />0.137 weeks <br />0.0315 months <br /> into the event.

This timing was derived from the timing of the containment response of the drywell pressure approaching the design pressure; this venting assumption was made to ensure that the containment pressure limit is not challenged. During the audit process, the licensee stated that the decision to vent will be based on the installed torus pressure instrumentation. The torus pressure instrumentation, as discussed in section 3.2.1.5 of this report, is identified as containment essential instrumentation and will be available throughout the ELAP event.

On page 6 of the Integrated Plan, the licensee stated that the venting action will be accomplished in accordance with EOPs to maintain containment parameters within acceptable limits and within the limits that support continued use of the RCIC system. The operators will open the wetwell vent and the RHVS to relieve pressure conditions in the wetwell/drywell.

Operation of RHVS is performed from the relay room and can be accomplished because the RHVS is seismically rugged, de-powered (backed by batteries), and provided with adequate nitrogen from the containment atmospheric dilution (CAD) system, backed up by portable gas bottles for the ELAP event. Critical instruments associated with containment and the RHVS are de-powered and can be read in the relay room.

After opening the containment vent system, the non-condensable atmosphere will be removed which makes the containment considerably more vulnerable to overcooling/negative pressure transients and vacuum breaker actuation. This may ultimately result in the loss of inert conditions when air enters the containment to replace the volume vacated by steam condensing out of drywall atmosphere. During the audit process, the licensee addressed the effects of overcooling/negative pressure transients by stating that it is not a concern early in the event.

The licensee additionally stated that the strategy does not utilize drywell or torus sprays; it utilizes containment venting. The evaluation of the effect of overcooling/negative pressure transients during the later stages of the event will be performed during the final design I procedure development process. The licensee stated that Entergy will be following the industry's early venting position paper.

On pages 26 and 28, in the section of the Integrated Plan discussing maintaining containment integrity during the transition and the final phases, the licensee stated that the primary strategy to maintain containment integrity utilizes only permanently installed plant equipment (i.e.,

RHVS) as described for Phase 1. The RHVS is expected to rely on de power, which may require implementation of the FLEX strategies to re-power a battery charger.

In an endorsement letter dated January 9, 2014 (ADAMS Accession No. ML13358A206), the NRC staff concluded that the changes to the BWR venting strategy, as described in the Revision 1 Page 38 of 60 2014-02-15

November 21, 2013, position paper submitted by NEI on behalf of the Boiling Water Reactor Owners Group (BWROG), are acceptable, subject to each licensee addressing the plant-specific implementation of the guidance. The letter stated, The NRC staff agrees that the changes to the containment venting strategies as described in the BWROG information report are acceptable for use as part of strategies proposed in response to Order EA-12-049, provided that licensee implementation is in compliance with normal change processes for plant emergency procedures and provided that plant-specific evaluations support the use of the revised strategies. The BWROG paper addresses the venting strategy on a generic basis, but plant-specific implementation relies on such items as the capabilities of the installed vent path, net positive suction head for the reactor coolant system injection pumps, and guidance to prevent negative pressure in containment. The NRC staff will evaluate a licensee's application of containment venting strategies in its development of the final Safety Evaluation documenting compliance with NRC Order EA-12-049.

With regard to maintaining containment, the implementation of Boiling Water Reactor Owners Group (BWROG) Emergency Procedure Guideline (EPG)/Severe Accident Guideline (SAG),

Revision 3, including any associated plant-specific evaluations, must be completed in accordance with the provisions of NRC letter dated January 9, 2014. This is identified as Open Item 3.2.3.A in Section 4.1.

A hardened containment vent system is currently installed at JAF but will be enhanced in accordance with NRC Order EA-13-109 on BWR containment vents. In the first six-month status report updating JAF's Integrated Plan, the licensee stated that JAF will implement requirements of Phase 1 of Order EA-13-109 and that Phase 1 of Order EA-13-109 currently requires implementation in 2016 at JAF.

The licensee's approach described above, as currently understood, is consistent with the guidance found in NEI 12-06, as endorsed by JLD-ISG-2012-01, and subject to the successful closure of issues related to the Open Item, provides reasonable assurance that the requirements of Order EA-12-049 will be met with respect to containment function strategies if these requirements are implemented as described.

3.2.4 Support Functions 3.2.4.1 Equipment Cooling - Cooling Water NEI 12-06, Section 3.2.2, Guideline (3) states:

Plant procedures/guidance should specify actions necessary to assure that equipment functionality can be maintained (including support systems or alternate method) in an ELAPILUHS or can perform without ac power or normal access to the UHS.

Cooling functions provided by such systems as auxiliary building cooling water, service water, or component cooling water may normally be used in order for equipment to perform their function. It may be necessary to provide an alternate means for support systems that require ac power or normal access to the UHS, Revision 1 Page 39 of 60 2014-02-15

or provide a technical justification for continued functionality without the support system.

The licensee made no reference in the Integrated Plan regarding the need for, or use of, additional cooling systems necessary to assure that coping strategy functionality can be maintained. Nonetheless, the only coping strategy equipment identified in the Integrated Plan that would require some form of cooling are portable diesel powered pumps and generators.

These self-contained commercially available units would not be expected to require an external cooling system nor would they require ac power or normal access to the UHS.

The licensee's approach described above, as currently understood, is consistent with the guidance found in NEI 12-06, as endorsed by JLD-ISG-2012-01, and provides reasonable assurance that the requirements of Order EA-12-049 will be met with respect to equipment cooling if these requirements are implemented as described.

3.2.4.2 Ventilation - Equipment Cooling NEI 12-06, Section 3.2.2, Guideline (1 0) states:

Plant procedures/guidance should consider Joss of ventilation effects on specific energized equipment necessary for shutdown (e.g., those containing internal electrical power supplies or other local heat sources that may be energized or present in an ELAP.

ELAP procedures/guidance should identify specific actions to be taken to ensure that equipment failure does not occur as a result of a loss of forced ventilation/cooling. Actions should be tied to either the ELAP/LUHS or upon reaching certain temperatures in the plant. Plant areas requiring additional air flow are likely to be locations containing shutdown instrumentation and power supplies, turbine-driven decay heat removal equipment, and in the vicinity of the inverters. These areas include: steam driven [auxiliary feedwater] AFW pump room, HPCI and RCIC pump rooms, the control room, and logic cabinets. Air flow may be accomplished by opening doors to rooms and electronic and relay cabinets, and/or providing supplemental air flow.

Air temperatures may be monitored during an ELAP/LUHS event through operator observation, portable instrumentation, or the use of locally mounted thermometers inside cabinets and in plant areas where cooling may be needed.

Alternatively, procedures/guidance may direct the operator to take action to provide for alternate air flow in the event normal cooling is lost. Upon loss of these systems, or indication of temperatures outside the maximum normal range of values, the procedures/guidance should direct supplemental air flow be provided to the affected cabinet or area, and/or designate alternate means for monitoring system functions.

For the limited cooling requirements of a cabinet containing power supplies for instrumentation, simply opening the back doors is effective. For larger cooling loads, such as HPCI, RCIC, and AFW pump rooms, portable engine-driven blowers may be considered during the transient to augment the natural circulation provided by opening doors. The necessary rate of air supply to these rooms may be estimated on the basis of rapidly turning over the room's air Revision 1 Page 40 of 60 2014-02-15

volume.

Temperatures in the HPCI pump room and/or steam tunnel for a BWR may reach levels which isolate HPCI or RCIC steam lines. Supplemental air flow or the capability to override the isolation feature may be necessary at some plants. The procedures/guidance should identify the corrective action required, if necessary.

Actuation set points for fire protection systems are typically at 165-180°F. It is expected that temperature rises due to loss of ventilation/cooling during an ELAP/LUHS will not be sufficiently high to initiate actuation of fire protection systems. If lower fire protection system setpoints are used or temperatures are expected to exceed these temperatures during an ELAP/LUHS, procedures/guidance should identify actions to avoid such inadvertent actuations or the plant should ensure that actuation does not impact long term operation of the equipment.

In the Integrated Plan the licensee discussed the ventilation and cooling requirements for plant areas during the ELAP event. The applicable areas of interest are discussed below.

Main Control Room (MCR)

On page 37, in the section of the Integrated Plan discussing main control room habitability during the initial phase, the licensee stated that under ELAP conditions with only simple mitigating actions taken, an analysis projects the temperature in the control room will not exceed 105 degrees Fahrenheit considering a loss of ventilation for three days. This is below the assumed maximum temperature for efficient human performance (11 0 degrees Fahrenheit) as described in NUMARC 87-00, "Guidelines and Technical Bases for NUMARC Initiatives Addressing Station Blackout at Light Water Reactors," Revision 1. The calculation credited heat escaping through a damper in the floor of the kitchen. The Phase 1 FLEX strategy is to confirm the damper is open as well as to block open the entrance air lock when the MCR temperature reaches about 90 degrees Fahrenheit. Additionally, plant procedures require opening all MCR panel doors in the control room within 30 minutes of the beginning of an SBO to minimize heatup of the components contained in the MCR panels. The licensee stated that during Phase 2, portable fans powered from portable FLEX diesel generators will be provided to improve the heat removal from the MCR and maintain temperatures below 104 degrees Fahrenheit for personnel accessibility and equipment availability. The licensee stated that during the final phase, the strategies for cooling the MCR are the same as for Phase 2. However, the power for the MCR chillers and air-handling units may be powered from the 4160 Vac emergency bus if the bus is re-energized by the RRC FLEX 4160 Vac DG.

RCIC Room On pages 37, in the section of the Integrated Plan discussing RCIC room accessibility during the initial phase, the licensee stated that the RCIC room will have a large heat load under ELAP conditions, as the steam-driven RCIC pump is utilized during the event as the primary source of core cooling. Current analysis demonstrates that the RCIC room remains at acceptable levels for the four-hour SBO scenario. A preliminary evaluation of the room temperature response for the FLEX scenario indicates the room temperature will be elevated. The strategy for the RCIC room is to ensure room doors are open or utilize portable fans to ventilate the area. The licensee stated that JAF does not anticipate that continuous accessibility would be required in the RCIC room. If personnel entry is required into the RCIC room, then supplemental ventilation Revision 1 Page 41 of 60 2014-02-15

and personnel protective measures (such as ice vests) will be taken. The licensee stated that during the transition phase, the primary strategy for maintaining the environment of the RCIC room will use the same strategy as in the Phase 1. Further evaluation of RCIC room temperature will be performed to confirm an acceptable environment is maintained. This is identified as Confirmatory Item 3.2.4.2.A in Section 4.2.

Battery Room On page 39 in the section of the Integrated Plan discussing battery room ventilation during the transition phase, the licensee stated that hydrogen generation rate during charging is such that the hydrogen concentration in the room does not reach 2% for more than 5 days and that this is well into the Phase 3 deployment period. The licensee stated that battery room ventilation is not a concern for the general Phase 2 strategy period of from 8 hours0.333 days <br />0.0476 weeks <br />0.011 months <br /> to 72 hours3 days <br />0.429 weeks <br />0.0986 months <br />.

On page 43, in the section of the Integrated Plan discussing battery room ventilation during the final phase, the licensee stated that while the rate of hydrogen generation at JAF does not result in hydrogen concentrations of greater 2% for more than five days, the rooms will have to be ventilated during Phase 3. There are two strategies for venting the battery rooms. The primary strategy is to repower the existing battery room exhaust fans. The licensee stated that this could occur after the FLEX DG has been connected to power the Class 1E 600 volt bus, but will more likely not be performed until the larger portable diesel generators are delivered from the RRC. The licensee stated that the second option is to prop open doors and set up portable fans that will exhaust into an adjacent corridor that communicates with a roll up door to the outside.

The Integrated Plan did not address the room temperature effects on battery performance.

During the audit process the licensee stated that charging batteries during high room temperatures may require additional forced air flow during Phase 2 and 3. The licensee stated that additional calculations will be developed. This is identified as Confirmatory Item 3.2.4.2.8 in Section 4.2.

During the audit process, the licensee further stated that during cold weather the electrolyte in the cells is not expected to drop to a limiting temperature due to the battery room's interior location within the plant. The licensee stated that it is reasonable to assume that the room will remain near its pre-event temperature during the relatively short period of time until the FLEX generators are deployed and have energized the battery chargers. Additional details on adequacy of battery room ventilation for extreme temperature protection will be available later in the design/procedure development process. This is combined with Confirmatory Item 3.2.4.2.8 above.

DC Equipment Room On page 39, in the section of the Integrated Plan discussing de equipment room ventilation during the transition phase, the licensee stated that the de equipment rooms contain the battery chargers which are energized in Phase 2 to recharge the batteries. The method to ventilate the de equipment rooms is to prop open doors and set up portable fans that will exhaust into an adjacent corridor that communicates with a roll up door to the outside. During the audit process, the licensee stated that detail design to determine the required ventilation flow or the size of the portable fans has not been determined. This is identified as Confirmatory Item 3.2.4.2.C in Section 4.2.

RHR Room Revision 1 Page 42 of 60 2014-02-15

On page 43, in the section of the Integrated Plan discussing RHR room accessibility during the final phase, the licensee stated that as part of Phase 3 strategies, an RHR pump is placed into service in order to perform shutdown cooling. This results in heat addition to the RHR pump area due to heat generated by the RHR pump motor as well as heat dissipated from the associated piping. For long term RHR pump operation, the RHR pump area must be cooled to maintain area temperatures within acceptable ranges (limited by maximum allowable RHR pump motor requirements). The licensee stated that mitigating actions can be accomplished by ensuring that cooling support is also powered when the RRC 4160 Vac FLEX DG is connected to the Class 1E 4160 Vac bus to power the RHR pump and that the room cooler can be energized and cooling water supplied via the connections provided between the fire protection system piping and ESW cooling water supply piping. The licensee stated that an alternate means of cooling the RHR rooms if the RHR pump room coolers are not available is to use portable exhaust fans and hose trunks to exhaust hot RHR room air to outside the reactor building.

The licensee's approach described above, as currently understood, is consistent with the guidance found in NEI 12-06, as endorsed by JLD-ISG-2012-01, and subject to the successful closure of issues related to the Confirmatory Items, provides reasonable assurance that the requirements of Order EA-12-049 will be met with respect to ventilation for equipment cooling if these requirements are implemented as described.

3.2.4.3 Heat Tracing.

NEI 12-06, Section 3.2.2, Guideline (12) states:

Plant procedures/guidance should consider loss of heat tracing effects for equipment required to cope with an ELAP. Alternate steps, if needed, should be identified to supplement planned action.

Heat tracing is used at some plants to ensure cold weather conditions do not result in freezing important piping and instrumentation systems with small diameter piping. Procedures/guidance should be reviewed to identify if any heat traced systems are relied upon to cope with an ELAP. For example, additional condensate makeup may be supplied from a system exposed to cold weather where heat tracing is needed to ensure control systems are available. If any such systems are identified, additional backup sources of water not dependent on heat tracing should be identified.

The Integrated Plan does not address heat tracing for freeze protection of piping, instrument lines and equipment. The need for heat tracing and freeze protection during an ELAP may include permanent plant equipment and also portable/FLEX equipment that is deployed outdoors during periods of cold weather. During the audit process, the licensee stated that the need for heat tracing will be addressed later in the design/procedure development phase and that walkdowns will be conducted to identify areas where heat tracing for freeze protection may be required. This is identified as Confirmatory Item 3.2.4.3.A in Section 4.2 The licensee's approach described above, as currently understood, is consistent with the guidance found in NEI 12-06, as endorsed by JLD-ISG-2012-01, and subject to the successful closure of issues related to the Confirmatory Item, provides reasonable assurance that the requirements of Order EA-12-049 will be met with respect to heat tracing if these requirements Revision 1 Page 43 of 60 2014-02-15

are implemented as described.

3.2.4.4 Accessibility- Lighting and Communication NEI 12-06, Section 3.2.2, Guideline (8) states:

Plant procedures/guidance should identify the portable lighting (e.g., flashlights or head/amps) and communications systems necessary for ingress and egress to plant areas required for deployment of FLEX strategies.

Areas requiring access for instrumentation monitoring or equipment operation may require portable lighting as necessary to perform essential functions.

Normal communications may be lost or hampered during an ELAP.

Consequently, in some cases, portable communication devices may be required to support interaction between personnel in the plant and those providing overall command and control.

The Integrated Plan does not discuss portable, emergency and hand held lighting available to operators for implementing mitigation strategies during an ELAP. The licensee addressed this concern during the audit process by stating that current plant procedures define flashlights as standard gear/equipment of operators with duties in the plant. The de portion of the lighting system receives power from the 125 volt de power system. Also, light towers are available for exterior lighting. The licensee stated that need for additional portable lighting, such as portable de powered lights, is still being evaluated. This is identified as Confirmatory Item 3.2.4.4.A in Section 4.2.

During the audit process the licensee stated that although not credited, in addition, self-contained emergency lighting units with an 8-hour power supply are located in many areas.

These lights were installed per 10 CFR 50, Appendix R to provide adequate lighting for operators to access, operate, and then egress from safe shutdown equipment.

The NRC staff has reviewed the licensee communications assessment (ADAMS Accession Nos. ML12306A244 and ML13063A048) in response to the March 12, 2012 50.54(f) request for information letter for JAF and, as documented in the staff analysis (ADAMS Accession No. ML13123A203), has determined that the assessment for communications is reasonable, and the analyzed existing systems, proposed enhancements, and interim measures will help to ensure that communications are maintained. Therefore, there is reasonable assurance that the guidance and strategies developed by the licensee will conform to the guidance of NEI 12-06 Section 3.2.2, Guideline (8) regarding communications capabilities during an ELAP.

Confirmation will be required that upgrades to the site's communications systems have been completed. This has been identified as Confirmatory Item 3.2.4.4.8 in Section 4.2.

The licensee's approach described above, as currently understood, is consistent with the guidance found in NEI 12-06, as endorsed by JLD-ISG-2012-01, and subject to the successful closure of issues related to the Confirmatory Items, provides reasonable assurance that the requirements of Order EA-12-049 will be met with respect to availability of lighting and communication if these requirements are implemented as described.

Revision 1 Page 44 of 60 2014-02-15

3.2.4.5 Protected and Internal Locked Area Access NEI 12-06, Section 3.2.2, Guideline (9) states:

Plant procedures/guidance should consider the effects of ac power loss on area access, as well as the need to gain entry to the Protected Area and internal locked areas where remote equipment operation is necessary.

At some plants, the security system may be adversely affected by the loss of the preferred or Class 1E power supplies in an ELAP. In such cases, manual actions specified in ELAP response procedures/guidance may require additional actions to obtain access.

There is no discussion in the Integrated Plan of the guidance and strategies with regard to the effects of ac power loss on area access to the protected area and internal locked areas to demonstrate conformance with NEI 12-06. During the audit process, the licensee stated that procedures exist and FSGs will be developed to ensure that operators can access required areas in the event of loss of power. The licensee stated that additional details on controls for access to security controlled or internal locked areas where extended loss of all power would disable normal controlled access will be contained in the FSGs or associated procedures.

The licensee's approach described above, as currently understood, is consistent with the guidance found in NEI 12-06, as endorsed by JLD-ISG-2012-01, and provides reasonable assurance that the requirements of Order EA-12-049 will be met with respect to access to protected and locked areas if these requirements are implemented as described.

3.2.4.6 Personnel Habitability- Elevated Temperature NEI 12-06, Section 3.2.2, Paragraph (11) provides that:

Plant procedures/guidance should consider accessibility guidelines at locations where operators will be required to perform local manual operations.

Due to elevated temperatures and humidity in some locations where local operator actions are required (e.g., manual valve manipulations, equipment connections, etc.), procedures/guidance should identify the protective clothing or other equipment or actions necessary to protect the operator, as appropriate.

FLEX strategies must be capable of execution under the adverse conditions (unavailability of installed plant lighting, ventilation, etc.) expected following a BDBE resulting in an ELAP/LUHS. Accessibility of equipment, tooling, connection points, and plant components shall be accounted for in the development of the FLEX strategies. The use of appropriate human performance aids (e.g., component marking, connection schematics, installation sketches, photographs, etc.) shall be included in the FLEX guidance implementing the FLEX strategies.

During the audit process, the licensee stated that long term habitability of the main control room will be assured by monitoring control room conditions, heat stress countermeasures, and rotation of personnel to the extent feasible. The licensee stated that impact to habitability would be primarily from elevated temperatures and that FSGs will provide guidance for control room Revision 1 Page 45 of 60 2014-02-15

staff to evaluate the control room temperature and take actions as necessary. The licensee stated that Entergy already uses passive cooling technologies for response personnel in high temperature environments. The maximum expected temperature in the control room and planned measures for providing ventilation cooling is discussed in section 3.2.4.2 of this report.

During the audit process, the licensee also stated that it's not anticipated that accessibility of the RCIC room will be required; however if personnel access is necessary to implement the FLEX strategy the method of assuring RCIC habitability will be addressed in the detailed design phase. This is combined with Confirmatory Item 3.2.4.2.A in Section 4.2.

During the audit process, the licensee stated that operators are trained on working in high temperature areas of the plant and that entry into high temperature environments is governed by Entergy's industrial safety procedures with controls for heat stress situations. The licensee stated that continuous standby in the RCIC room is not required and operators can cycle in and out of the room as necessary to adjust flow and maintain operation of the RCIC pump. Also, as stated on page 37 of the Integrated Plan, if personnel entry is required into the RCIC room, then supplemental ventilation and personnel protective measures (such as ice vests) will be taken.

The licensee's approach described above, as currently understood, is consistent with the guidance found in NEI 12-06, as endorsed by JLD-ISG-2012-01, and subject to the successful closure of issues related to the Confirmatory Item, provides reasonable assurance that the requirements of Order EA-12-049 will be met with respect to personnel habitability if these requirements are implemented as described.

3.2.4.7 Water Sources.

NEI 12-06, Section 3.2.2, Guideline (5) states:

Plant procedures/guidance should ensure that a flow path is promptly established for makeup flow to the steam generator/nuclear boiler and identify backup water sources in order of intended use. Additionally, plant procedures/guidance should specify clear criteria for transferring to the next preferred source of water.

Under certain beyond-design-basis conditions, the integrity of some water sources may be challenged. Coping with an ELAP/LUHS may require water supplies for multiple days. Guidance should address alternate water sources and water delivery systems to support the extended coping duration. Cooling and makeup water inventories contained in systems or structures with designs that are robust with respect to seismic events, floods, and high winds, and associated missiles are assumed to be available in an ELAP/LUHS at their nominal capacities. Water in robust UHS piping may also be available for use but would need to be evaluated to ensure adequate NPSH can be demonstrated and, for example, that the water does not gravity drain back to the UHS.

Alternate water delivery systems can be considered available on a case-by-case basis. In general, all CSTs should be used first if available. If the normal source of makeup water (e.g., CST) fails or becomes exhausted as a result of the hazard, then robust demineralized, raw, or borated water tanks may be used as appropriate.

Heated torus water can be relied upon if sufficient [net positive suction head]

NPSH can be established. Finally, when all other preferred water sources have Revision 1 Page 46 of 60 2014-02-15

been depleted, lower water quality sources may be pumped as makeup flow using available equipment (e.g., a diesel driven fire pump or a portable pump drawing from a raw water source). Procedures/guidance should clearly specify the conditions when the operator is expected to resort to increasingly impure water sources.

The licensee has identified three water sources for use in the FLEX strategies. These are the suppression pool, the CST and the ultimate heat sink, Lake Ontario. As described on page 12 of the Integrated Plan, JAF's primary coping strategy to prevent core damage during an ELAP is through the use of the RCIC pump. The licensee stated that the CSTs, with a minimum capacity of 200,000 gallons, are the normal pump suction supply to RCIC. The suction supply for the RCIC pump will automatically transfer from the CSTs to the suppression pool (SP) on low CSTs level. The licensee stated that during an ELAP, at approximately 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br /> event time, operators will manually transfer RCIC suction to the SP. The RCIC suction path will remain aligned to the SP until the SP temperature reaches about 170 degrees Fahrenheit. This is expected to occur at approximately 5 hours0.208 days <br />0.0298 weeks <br />0.00685 months <br /> event time. Operators will then shift the RCIC suction path back to the CSTs. The licensee stated that the combined water volumes of the SP and the CSTs are expected to provide core cooling for approximately 35 hours1.458 days <br />0.208 weeks <br />0.0479 months <br /> without refilling the CSTs.

During the audit process, the licensee stated that the lower half of each CST is below ground level for tornado and seismic protection of the tank's 100,000 gallons storage capacity. The licensee stated that the CSTs are considered robust and available following the BDBEEs.

During the audit process, the licensee further stated that switchover between the suppression pool and the CSTs is done manually by the operators from the control room and that automatic controls are not relied upon to align water sources to the RCIC pump for core cooling.

As described on page 17 of the Integrated Plan, prior to depletion of the CSTs, the licensee plans to transition from the steam driven RCIC pump to using the installed seismically qualified diesel driven fire pump to supply makeup water from Lake Ontario to the RPV. This is accomplished by connecting a temporary hose from the fire protection header to the RHRSW system. RHRSW can be cross tied to the RHR system allowing water injection into the RPV. In the event that the station diesel firewater pump is not available, the licensee has established an alternate strategy to lower a portable diesel-driven FLEX pump into the screenwell area and makeup to the RPV by the same flow path. The portable diesel driven FLEX pump can also supply water to the SFP and refill the CSTs.

The licensee's approach described above, as currently understood, is consistent with the guidance found in NEI 12-06, as endorsed by JLD-ISG-2012-01, and provides reasonable assurance that the requirements of Order EA-12-049 will be met with respect to water sources if these requirements are implemented as described.

3.2.4.8 Electrical Power Sources/Isolations and Interactions NEI 12-06, Section 3.2.2, Guideline (13) states in part:

The use of portable equipment to charge batteries or locally energize equipment may be needed under ELAP/LUHS conditions. Appropriate electrical isolations and interactions should be addressed in procedures/guidance.

Revision 1 Page 47 of 60 2014-02-15

On pages 17 and 18 of the Integrated Plan the licensee provided a description of the electrical support strategy during Phase 2. The 125 Vdc batteries are available for up to 10 hours0.417 days <br />0.0595 weeks <br />0.0137 months <br /> without recharging. A modification will provide new connection points for a portable diesel generator unit to re-power the battery chargers which charge the batteries and supply de loads. The FLEX 600 Vac, 200 kW DG will be connected at approximately 6 hours0.25 days <br />0.0357 weeks <br />0.00822 months <br /> and is sized to power the battery charger and fans (about 90 kW). As an alternate strategy to that of powering the battery chargers from their Class 1E 600 volt electrical buses, connections will be provided to enable power to be provided directly to the battery chargers. This will enable the use of a 90 kW FLEX 600 Vac DG to power the battery charger. Permanently installed cables will be run to facilitate the use of this alternative power arrangement.

On page 21 of the Integrated Plan, the licensee provided a description of the electrical support strategy to be used during Phase 3. For Phase 3, the reactor core cooling strategy is to place one loop of RHR into the shutdown cooling mode. This will be accomplished by powering up a Division I or II RHR pump from the respective Class 1E emergency bus, utilizing a 4160 Vac FLEX portable diesel generator supplied by the RRC. The licensee stated that the 4160 Vac RRC FLEX diesel generator will be capable of carrying approximately 2000 kW load which is sufficient to carry all of the loads necessary to support the Phase 3 FLEX strategies which includes an RHR pump and its support equipment. The licensee stated that an alternate means of providing power to the RHR pumps for SOC operation is to run cable from the 4160 Vac RRC FLEX DG directly to the component by connecting either at the switchgear end of the component's power cable or locally at the pump end of the power cable.

During the audit process, the licensee addressed the issues associated with electrical isolations and interactions. The licensee stated that connection points and other permanent modifications will be designed in accordance with approved design practices to assure no adverse effects during normal operation. The licensee stated that at the onset of the ELAP, Class 1E emergency diesel generators are assumed unavailable to supply the Class 1E busses. Portable generators are used in response to an ELAP in FLEX strategies for Phases 2 and 3. The licensee stated that at the point when ELAP mitigation activities require tie-in of FLEX generators, in addition to existing electrical interlocks, procedural controls such as inhibiting EDG start circuits and breaker rack-outs (e.g., EDG breakers, offsite feeder breakers, etc) will be employed to prevent simultaneous connection of both the FLEX generators and Class 1E EDG to the same ac distribution system or component. Additionally, repowering the Class 1E electrical busses from either the FLEX generators or subsequently the Class 1E EDGs (should they become available) will be accomplished manually and controlled by procedure; no automatic sequencing or automatic repowering of the busses will be utilized.

The Integrated Plan did not provide information regarding the technical basis for the selection and size of the FLEX generators to be used in support of the coping strategies. Supporting information should be provided to address both Phase 2 and 3 power requirements. The licensee addressed the topic of generator sizing during the audit process by stating that the information would be provided in a future 6-month update. This is identified as Confirmatory Item 3.2.4.8.A in Section 4.2.

The licensee's approach described above, as currently understood, is consistent with the guidance found in NEI 12-06, as endorsed by JLD-ISG-2012-01, and subject to the successful closure of issues related to the Confirmatory Item, provides reasonable assurance that the requirements of Order EA-12-049 will be met with respect to electrical power sources, isolations and interactions if these requirements are implemented as described.

Revision 1 Page 48 of 60 2014-02-15

3.2.4.9 Portable Equipment Fuel NEI 12-06, Section 3.2.2, Guideline (13) states in part:

The fuel necessary to operate the FLEX equipment needs to be assessed in the plant specific analysis to ensure sufficient quantities are available as well as to address delivery capabilities.

NEI 12-06, Section 3.2.1.3, initial condition (5) states:

Fuel for FLEX equipment stored in structures with designs which are robust with respect to seismic events, floods and high winds and associated missiles, remains available.

On page 18, in the section of the Integrated Plan discussing coping strategies for maintaining core cooling during the transition phase, the licensee stated that diesel fuel to support operation of the portable Phase 2 FLEX equipment for at least 15 hours0.625 days <br />0.0893 weeks <br />0.0205 months <br /> will be stored with the FLEX equipment. The licensee stated that additional diesel fuel is available in the underground emergency diesel generator (EDG) fuel storage tanks and that the Division I & II EDG fuel oil storage tanks contain more than 128,000 gallons of fuel oil. The licensee stated that underground EDG fuel oil storage tanks contain sufficient fuel oil to support all Phase 2 strategies. The licensee stated that if the normal procedure for transferring fuel from the underground storage tanks is not possible, the fuel oil can be obtained from the underground storage tanks using a manual, air, or battery operated pump to pump the fuel into a transfer tank. Two trailers with fuel tank and portable containers are provided as part of the Phase 2 FLEX equipment as indicated in the table on page 45 of the Integrated Plan.

During the audit process, the licensee stated that the quality of the fuel in the EDG fuel oil storage tanks is maintained in accordance with JAF's diesel fuel oil testing program and that fuel oil in the fuel tanks of the portable diesel driven FLEX equipment will be maintained in the preventative maintenance program in accordance with the EPRI maintenance template.

The licensee's approach described above, as currently understood, is consistent with the guidance found in NEI 12-06, as endorsed by JLD-ISG-2012-01, and provides reasonable assurance that the requirements of Order EA-12-049 will be met with respect to fuel oil supplies if these requirements are implemented as described.

3.2.4.1 0 Load Reduction to Conserve DC Power NEI 12-06, Section 3.2.2, Guideline (6) states:

Plant procedures/guidance should identify loads that need to be stripped from the plant de buses (both Class 1E and non-Class 1E) for the purpose of conserving de power.

DC power is needed in an ELAP for such loads as shutdown system instrumentation, control systems, and de backed AOVs and MOVs. Emergency lighting may also be powered by safety-related batteries. However, for many plants, this lighting may have been supplemented by Appendix R and security lights, thereby allowing the emergency lighting load to be eliminated. ELAP procedures/guidance should direct operators to conserve de power during the Revision 1 Page 49 of 60 2014-02-15

event by stripping nonessential loads as soon as practical. Early load stripping can significantly extend the availability of the unit's Class 1E batteries. In certain circumstances, AFW/HPCI/RCIC operation may be extended by throttling flow to a constant rate, rather than by stroking valves in open-shut cycles.

Given the beyond-design-basis nature of these conditions, it is acceptable to strip loads down to the minimum equipment necessary and one set of instrument channels for required indications. Credit for load-shedding actions should consider the other concurrent actions that may be required in such a condition.

On page 5, in the section of the Integrated Plan discussing time constraints identified in the sequence of events time line, the licensee stated that at 90 minutes after an ELAP, de load shed is completed and that FLEX response procedures will detail the actions necessary. The licensee stated that the de buses are readily available for operator access and breakers will be appropriately identified (labeled) to show which are required to be opened to implement a deep load shed. The Integrated Plan states that that based on engineering judgment, it is reasonable to expect that operators can complete the shedding of loads from the de bus in approximately 30 minutes. The licensee noted that existing station blackout procedure (AOP-49) includes direction to depressurize and vent the main generator within 30 minutes of a station blackout.

During the audit the licensee stated that the load shed list will be refined during the design process and that the potential adverse impacts of shedding these additional loads will be evaluated. This is identified as Confirmatory Item 3.2.4.1 O.A in Section 4.2.

On page 5 of the Integrated Plan, the licensee stated that at 10 hours0.417 days <br />0.0595 weeks <br />0.0137 months <br /> a battery charger is re-powered to maintain the de power system. Deployment of the FLEX DG will be initiated shortly after the BDBEE is declared in recognition of the potential for battery depletion. The licensee stated that the event is time critical at battery depletion and that both the A and the B batteries have been calculated to last more than 10 hours0.417 days <br />0.0595 weeks <br />0.0137 months <br /> in the FLEX scenario. During the audit process, the licensee stated that the 10 hour1.157407e-4 days <br />0.00278 hours <br />1.653439e-5 weeks <br />3.805e-6 months <br /> runtime is based on the minimum battery voltage (111.6 volts for battery A and 110.26 volts for battery B) and expected electrical loading. The minimum voltage is the acceptance criteria for the SBO minimum battery voltage as stated in existing battery calculations. The de load profile with the required loads for the mitigating strategies to maintain core cooling, containment, and spent fuel cooling is still in the design/development phase. The licensee stated that the finalized minimum battery voltages will be available later in the design phase. This is identified as Confirmatory Item 3.2.4.1 0. B in Section 4.2.

During the audit process, the licensee stated that the FLEX 600 Vac DGs will be connected within 6 hours0.25 days <br />0.0357 weeks <br />0.00822 months <br /> after the ELAP, whereas on page 48 of the Integrated Plan, the sequence of events table indicates that the station battery chargers will be re-powered at 10 hours0.417 days <br />0.0595 weeks <br />0.0137 months <br />. The sequence of events timeline needs to be reconfirmed or updated to address this apparent change in strategy. This is identified as Confirmatory Item 3.2.4.1 O.C in Section 4.2.

The NRC staff reviewed the licensee's Integrated Plan and determined that the Generic Concern related to battery duty cycles beyond 8 hours0.333 days <br />0.0476 weeks <br />0.011 months <br /> is applicable to the plant. This Generic Concern has been resolved generically through the NRC endorsement of NEI position paper entitled "Battery Life Issue" (ADAMS Accession Nos. ML13241A186 (position paper) and ML13241A188 (NRC endorsement letter)).

The purpose of the Generic Concern and associated endorsement of the position paper was to resolve concerns associated with Integrated Plan submittals in a timely manner and on a Revision 1 Page 50 of 60 2014-02-15

generic basis, to the extent possible, and provide a consistent review by the NRC staff. Position papers provided to the NRC by industry further develop and clarify the guidance provided in NEI 12-06 related to industry's ability to meet the requirements of Order EA-12-049.

The Generic Concern related to extended battery duty cycles required clarification of the capability of the existing vented lead-acid station batteries to perform their expected function for durations greater than 8 hours0.333 days <br />0.0476 weeks <br />0.011 months <br /> throughout the expected service life of the battery. The position paper provided sufficient basis to resolve this concern by developing an acceptable method for demonstrating that batteries will perform as specified in a plant's Integrated Plan. The methodology relies on the licensee's battery sizing calculations developed in accordance with the Institute of Electrical and Electronics Engineers Standard 485, "Recommended Practice for Sizing Large Lead Storage Batteries for Generating Stations and Substations," load shedding schemes, and manufacturer data to demonstrate that the existing vented lead-acid station batteries can perform their intended function for extended duty cycles (i.e., beyond 8 hours0.333 days <br />0.0476 weeks <br />0.011 months <br />).

The NRC staff concluded that the position paper provides an acceptable approach for licensees to use in demonstrating that vented lead-acid batteries can be credited for durations longer than 8 hours0.333 days <br />0.0476 weeks <br />0.011 months <br />. The NRC staff will evaluate a licensee's application of the guidance (calculations and supporting data) in its development of the final Safety Evaluation documenting review of the licensee's Integrated Plan.

During the audit process, the licensee stated that the FLEX strategy battery run time was determined in accordance with the IEEE 485 methodology.

The licensee's approach described above, as currently understood, is consistent with the guidance found in NEI 12-06, as endorsed by JLD-ISG-2012-01, and subject to the successful closure of issues related to the Confirmatory Items, provides reasonable assurance that the requirements of Order EA-12-049 will be met with respect to load reduction if these requirements are implemented as described.

3.3 PROGRAMMATIC CONTROLS 3.3.1 Equipment Maintenance and Testing.

NEI 12-06, Section 3.2.2, the paragraph following Guideline (15) states in part:

In order to assure reliability and availability of the FLEX equipment required to meet these capabilities, the site should have sufficient equipment to address all functions at all units on-site, plus one additional spare, i.e., an N+1 capability, where "N" is the number of units on-site. Thus, a two-unit site would nominally have at least three portable pumps, three sets of portable ac/dc power supplies, three sets of hoses & cables, etc. It is also acceptable to have a single resource that is sized to support the required functions for multiple units at a site (e.g., a single pump capable of all water supply functions for a dual unit site). In this case, the N+1 could simply involve a second pump of equivalent capability. In addition, it is also acceptable to have multiple strategies to accomplish a function (e.g., two separate means to repower instrumentation). In this case the equipment associated with each strategy does not require N+1. The existing 50.54(hh)(2) pump and supplies can be counted toward the N+1, provided it meets the functional and storage requirements outlined in this guide. The N+1 capability applies to the portable FLEX equipment described in Tables 3-1 Revision 1 Page 51 of 60 2014-02-15

and 3-2 (i.e., that equipment that directly supports maintenance of the key safety functions). Other FLEX support equipment only requires an N capability.

NEI 12-06, Section 11.5 states:

1. FLEX mitigation equipment should be initially tested or other reasonable means used to verify performance conforms to the limiting FLEX requirements. Validation of source manufacturer quality is not required.
2. Portable equipment that directly performs a FLEX mitigation strategy for the core, containment, or SFP should be subject to maintenance and testing 1 guidance provided in INPO AP 913, Equipment Reliability Process, to verify proper function. The maintenance program should ensure that the FLEX equipment reliability is being achieved. Standard industry templates (e.g.,

EPRI [Electric Power Research Institute]) and associated bases will be developed to define specific maintenance and testing including the following:

a. Periodic testing and frequency should be determined based on equipment type and expected use. Testing should be done to verify design requirements and/or basis. The basis should be documented and deviations from vendor recommendations and applicable standards should be justified.
b. Preventive maintenance should be determined based on equipment type and expected use. The basis should be documented and deviations from vendor recommendations and applicable standards should be justified.
c. Existing work control processes may be used to control maintenance and testing. (e.g., PM Program, Surveillance Program, Vendor Contracts, and work orders).
3. The unavailability of equipment and applicable connections that directly performs a FLEX mitigation strategy for core, containment, and SFP should be managed such that risk to mitigating strategy capability is minimized.
a. The unavailability of installed plant equipment is controlled by existing plant processes such as the Technical Specifications. When installed plant equipment which supports FLEX strategies becomes unavailable, then the FLEX strategy affected by this unavailability does not need to be maintained during the unavailability.
b. Portable equipment may be unavailable for 90 days provided that the site FLEX capability (N) is available.
c. Connections to permanent equipment required for FLEX strategies can be unavailable for 90 days provided alternate capabilities remain functional.

1 Testing includes surveillances, inspections, etc.

Revision 1 Page 52 of 60 2014-02-15

d. Portable equipment that is expected to be unavailable for more than 90 days or expected to be unavailable during forecast site specific external events (e.g., hurricane) should be supplemented with alternate suitable equipment.
e. The short duration of equipment unavailability, discussed above, does not constitute a loss of reasonable protection from a diverse storage location protection strategy perspective.
f. If portable equipment becomes unavailable such that the site FLEX capability (N) is not maintained, initiate actions within 24 hours1 days <br />0.143 weeks <br />0.0329 months <br /> to restore the site FLEX capability (N) and implement compensatory measures (e.g., use of alternate suitable equipment or supplemental personnel) within 72 hours3 days <br />0.429 weeks <br />0.0986 months <br />.

On pages 9 and 10, in the section of the Integrated Plan discussing programmatic controls, the licensee stated that JAF will implement an administrative program for implementation and maintenance of the FLEX strategies in accordance with NEI 12-06 guidance.

  • Installed structures, systems and components currently designed and installed meet augmented quality guidelines (e.g., equipment installed to address 10CFR50.48, Fire Protection, or 10CFR50.63, Station Blackout) will continue to meet the augmented quality guidelines.
  • JAF will utilize the standard EPRI industry PM process for establishing the maintenance actions for FLEX components. Preventive maintenance procedures will be established for portable components that directly perform in the mitigating strategy for the key FLEX safety functions (i.e., core cooling, containment integrity, and spent fuel cooling.) These procedures will consider NEI 12-06 guidance, vendor recommendations, and applicable industry standards.
  • Testing procedures will be developed and performed at frequencies established based on type of equipment and considerations made within EPRI guidelines.

The NRC staff reviewed the Integrated Plan for JAF and determined that the Generic Concern related to maintenance and testing of FLEX equipment is applicable to the plant. This Generic Concern has been resolved generically through the NRC endorsement of the EPRI technical report on preventive maintenance of FLEX equipment, submitted by NEI by letter dated October 3, 2013 (ADAMS Accession No. ML13276A573). The NRC staff's endorsement letter is dated October 7, 2013 (ADAMS Accession No. ML13276A224).

This Generic Concern involves clarification of how licensees would maintain FLEX equipment such that it would be readily available for use. The technical report provided sufficient basis to resolve this concern by describing a database that licensees could use to develop preventative maintenance programs for FLEX equipment. The database describes maintenance tasks and maintenance intervals that have been evaluated as sufficient to provide for the readiness of the FLEX equipment. The NRC staff has determined that the technical report provides an acceptable approach for developing a program for maintaining FLEX equipment in a ready-to-use status.

Revision 1 Page 53 of 60 2014-02-15

During the audit process, the licensee informed the NRC of JAF's plans to abide by this generic resolution. The NRC staff will evaluate the resulting program through the audit and inspection processes.

The licensee's approach described above, as currently understood, is consistent with the guidance found in NEI 12-06, as endorsed by JLD-ISG-2012-01 and provides reasonable assurance that the requirements of Order EA-12-049 will be met with respect to maintenance and testing if these requirements are implemented as described.

3.3.2 Configuration Control.

NEI 12-06, Section 11.8 states:

1. The FLEX strategies and basis will be maintained in an overall program document. This program document will also contain a historical record of previous strategies and the basis for changes. The document will also contain the basis for the ongoing maintenance and testing programs chosen for the FLEX equipment.
2. Existing plant configuration control procedures will be modified to ensure that changes to the plant design, physical plant layout, roads, buildings, and miscellaneous structures will not adversely impact the approved FLEX strategies.
3. Changes to FLEX strategies may be made without prior NRC approval provided:

a) The revised FLEX strategy meets the requirements of this guideline.

b) An engineering basis is documented that ensures that the change in FLEX strategy continues to ensure the key safety functions (core and SFP cooling, containment integrity) are met.

On pages 9, in the section of the Integrated Plan discussing programmatic controls, the licensee stated that JAF will implement an administrative program for implementation and maintenance of the FLEX strategies in accordance with NEI 12-06 guidance.

On page 15, in the section of the Integrated Plan discussing procedures and guidance, the licensee stated that JAF will utilize the industry-developed guidance from the Owners Groups, EPRI and NEI Task team to develop site-specific procedures and guidelines to address the criteria in NEI 12-06. These procedures and/or guidelines will support the existing symptom based command and control strategies in the current EOPs.

On page 19, in the section of the Integrated Plan discussing storage and protection of equipment, the licensee stated that locations I structures to provide protection of the FLEX equipment will be fabricated I constructed to meet the requirements identified in NEI 12-06, Section 11. JAF procedures and programs are being developed to address storage structure requirements, haul path requirements, and FLEX equipment requirements relative to the hazards applicable to JAF.

The licensee's approach described above, as currently understood, is consistent with the guidance found in NEI 12-06, as endorsed by JLD-ISG-2012-01, and provides reasonable Revision 1 Page 54 of 60 2014-02-15

assurance that the requirements of Order EA-12-049 will be met with respect to configuration control if these requirements are implemented as described.

3.3.3 Training.

NEI 12-06, Section 11.6 states:

1. Programs and controls should be established to assure personnel proficiency in the mitigation of beyond-design-basis events is developed and maintained.

These programs and controls should be implemented in accordance with an accepted training process. 2

2. Periodic training should be provided to site emergency response leaders 3 on beyond design-basis emergency response strategies and implementing guidelines. Operator training for beyond-design-basis event accident mitigation should not be given undue weight in comparison with other training requirements. The testing/evaluation of Operator knowledge and skills in this area should be similarly weighted.
3. Personnel assigned to direct the execution of mitigation strategies for beyond-design basis events will receive necessary training to ensure familiarity with the associated tasks, considering available job aids, instructions, and mitigating strategy time constraints.
4. "ANSI/ANS 3.5, Nuclear Power Plant Simulators for use in Operator Training" certification of simulator fidelity (if used) is considered to be sufficient for the initial stages of the beyond-design-basis external event scenario until the current capability of the simulator model is exceeded. Full scope simulator models will not be upgraded to accommodate FLEX training or drills.
5. Where appropriate, the integrated FLEX drills should be organized on a team or crew basis and conducted periodically; with all time-sensitive actions to be evaluated over a period of not more than eight years. It is not the intent to connect to or operate permanently installed equipment during these drills and demonstrations.

On page 10, in the section of the Integrated Plan discussing the general plan elements and the training plan, the licensee stated the new training of general station staff and the Emergency Response Organization will be performed prior to design implementation. The licensee stated that these programs and controls will be implemented in accordance with the Systematic Approach to Training and NEI 12-06 guidance.

The licensee's approach described above, as currently understood, is consistent with the guidance found in NEI 12-06, as endorsed by JLD-ISG-2012-01, and provides reasonable assurance that the requirements of Order EA-12-049 will be met with respect to training if these requirements are implemented as described.

2 The Systematic Approach to Training (SAT) is recommended.

3 Emergency response leaders are those utility emergency roles, as defined by the Emergency Plan, for managing emergency response to design basis and beyond-design-basis plant emergencies.

Revision 1 Page 55 of 60 2014-02-15

3.4 OFF SITE RESOURCES NEI 12-06, Section 12.2 lists the following minimum capabilities for offsite resources for which each licensee should establish the availability of:

1) A capability to obtain equipment and commodities to sustain and backup the site's coping strategies.
2) Off-site equipment procurement, maintenance, testing, calibration, storage, and control.
3) A provision to inspect and audit the contractual agreements to reasonably assure the capabilities to deploy the FLEX strategies including unannounced random inspections by the Nuclear Regulatory Commission.
4) Provisions to ensure that no single external event will preclude the capability to supply the needed resources to the plant site.
5) Provisions to ensure that the off-site capability can be maintained for the life of the plant.
6) Provisions to revise the required supplied equipment due to changes in the FLEX strategies or plant equipment or equipment obsolescence.
7) The appropriate standard mechanical and electrical connections need to be specified.
8) Provisions to ensure that the periodic maintenance, periodic maintenance schedule, testing, and calibration of off-site equipment are comparable/consistent with that of similar on-site FLEX equipment.
9) Provisions to ensure that equipment determined to be unavailable/non-operational during maintenance or testing is either restored to operational status or replaced with appropriate alternative equipment within 90 days.
10) Provision to ensure that reasonable supplies of spare parts for the off-site equipment are readily available if needed. The intent of this provision is to reduce the likelihood of extended equipment maintenance (requiring in excess of 90 days for returning the equipment to operational status).

On page 10, in the section of the Integrated Plan discussing the RRC in the general Integrated Plan elements, the licensee stated that the industry has selected a vendor to manage two RRC to provide large equipment in support of the response to BDBEE. Each RRC will store and maintain five sets of equipment, four of which are expected to be fully deployable upon request.

The fifth set is provided to account for equipment that may be unavailable due to its maintenance and testing cycle. As currently envisioned, the two RRC facilities will be located in Memphis, TN and Phoenix, AZ.

JAF will utilize the industry RRC for Phase 3 equipment. In an ELAP event, communications would be established between JAF and the industry SAFER team and required equipment mobilized as needed. JAF will enter into a contractual agreement with the SAFER team. Equipment will initially be moved from an RRC to a local staging Revision 1 Page 56 of 60 2014-02-15

area, established by the SAFER team and JAF. The equipment will be prepared at the staging area prior to transportation to the site. The licensee stated that first arriving equipment, as established during development of the RRC playbook, will be delivered to the site within 24 hours1 days <br />0.143 weeks <br />0.0329 months <br /> from the initial request.

The licensee's use of off-site resources, as described above, conforms to the guidance found in NEI 12-06, Section 12.2, with regard to the capability to obtain equipment and commodities to sustain and backup the site's coping strategies (Guideline 1). However, insufficient information has been included to provide reasonable assurance that guidance will be established to conform to the remaining items of NEI 12-06, Section 12.2 (Guidelines 2 through 10). This has been identified as Open Item 3.4.A, in Section 4.1.

The licensee's approach described above, as currently understood, is consistent with the guidance found in NEI 12-06, as endorsed by JLD-ISG-2012-01, and subject to the successful closure of issues related to the Open Item, provides reasonable assurance that the requirements of Order EA-12-049 will be met with respect to offsite resources if these requirements are implemented as described.

4.0 OPEN ITEMS AND CONFIRMATORY ITEMS 4.1 OPEN ITEMS Item Number Description Notes 3.1.1.3.A Procedural Interface (Seismic Hazard) -Evaluate the impacts from large internal flooding sources.

3.1.3.1.A Protection of FLEX Equipment (High Wind Hazard) - Evaluate Significant the separation distance and the axis of separation considering the predominant path of tornados in the geographic area to demonstrate that at least N sets of FLEX equipment would remain deployable in the context of a tornado missile hazard.

3.1.4.2.8 Deployment of FLEX Equipment (Snow, Ice and Extreme Cold)

- Evaluate the potential impact on the UHS due to ice blockage or formation of frazil ice as a result of extreme cold.

3.2.3.A Containment- Confirm that the implementation of Boiling Water Reactor Owners Group (BWROG) Emergency Procedure Guideline (EPG)/Severe Accident Guideline (SAG), Revision 3, including any associated plant-specific evaluations, will be completed in accordance with the provisions of NRC letter dated January 9, 2014 3.4.A Off-site Resources- Review how conformance with NEI 12-06, Section 12.2 guidelines 2 through 10 is being met.

Revision 1 Page 57 of 60 2014-02-15

4.2 CONFIRMATORY ITEMS Item Number Description Notes 3.1.1.2.A Deployment of FLEX Equipment -Review the potential for soil liquefaction that might impede vehicle movement following a seismic event.

3.1.1.2.8 Deployment of FLEX Equipment -Confirm final design features of the new storage building including the susceptibility to the loss of ac power. Reliance on ac power, if any, to deploy eg_uipment is to be evaluated.

3.1.1.2.C Deployment of FLEX Equipment- Verify the storage locations and means of protection against the seismic hazard of the super duty pickup trucks and the two flatbed trailers used for deployment of FLEX equipment.

3.1.1.4.A Offsite Resources- Confirm location of offsite staging area(s),

access routes and methods of delivery of equipment to the site considering the seismic, flood, high wind, snow, ice and extreme cold hazards.

3.1.3.2.A Deployment of FLEX Equipment (High Wind Hazard) - Confirm availability of debris removal equipment to facilitate deployment of FLEX equipment.

3.1.3.2.8 Deployment of FLEX Equipment (High Wind Hazard) - Confirm protection of the means to move FLEX equipment.

3.1.4.2.A Deployment of FLEX Equipment (Snow, Ice and Extreme Cold)

- Confirm availability of snow removal equipment to facilitate deQioyment of FLEX e_guipment.

3.2.1.1.A Computer Code Used for ELAP Analysis-Benchmarks need to be identified and discussed which demonstrate that MAAP is an appropriate code for the simulation of an ELAP event at JAF.

3.2.1.1.8 Computer Code Used for ELAP Analysis -Confirm that the collapsed level remains above Top of Active Fuel (TAF) and the cool down rate is within technical specifications limits.

3.2.1.1.C Computer Code Used for ELAP Analysis- Confirm that MAAP was used in accordance with Sections 4.1, 4.2, 4.3, 4.4, and 4.5 of the June 2013 position paper (ADAMS Accession No. ML13190A201 ).

3.2.1.1.D Computer Code Used for ELAP Analysis- Confirm that the licensee, in using MAAP, identified and justified the subset of key modeling parameters cited from Tables 4-1 through 4-6 of the "MAAP Application Guidance, Desktop Reference for Using MAAP Software, Revision 2" (Electric Power Research Institute Report 1020236).

Revision 1 Page 58 of 60 2014-02-15

3.2.1.1.E Computer Code Used for ELAP Analysis- Confirm that the specific MAAP analysis case that was used to validate the timing of mitigating strategies in the Integrated Plan has been identified and is available for NRC staff to review. Alternately, a comparable level of information has been included in the supplemental response. In either case, the analysis should include a plot of the collapsed vessel level to confirm that TAF is not reached (the elevation of the TAF should be provided) and a plot of the temperature cool down to confirm that the cool down is within technical s~ecifications limits.

3.2.1.2.A Recirculation Pump Seal Leakage Models-Confirm the seal leakage model used in the updated MAAP analysis (which will address the MAAP code limitations when used for ELAP analysis). Evaluate the seal leakage rate model used, the details of the seal qualification tests and supporting test data, and leakage rate pressure-dependence.

3.2.1.3.A Sequence of Events- Confirm the sequence of events timeline after reanalysis using the MAAP code which will address the limitations when used for the ELAP analysis.

3.2.1.4.A Systems and Components for Consequence Mitigation -

Confirm sizing of the FLEX pumps and 600 Vac FLEX DG and the 4160 Vac generator to be obtained from the RRC.

3.2.1.5.A Monitoring Instrumentation and Controls -Confirm ac powered torus temperature, pressure and level and drywell temperature and pressure instrumentation is modified to remain powered during an ELAP.

3.2.1.8.A Use of Portable Pumps- Evaluate impacts of using raw water from Lake Ontario for long term core and spent fuel pool cooling strategies.

3.2.2.A Spent Fuel Pool Cooling-Confirm the method of ventilation and power requirements, if any, of the spent fuel pool area.

3.2.4.2.A Ventilation (Equipment Cooling) - Confirm that additional evaluations of the RCIC room temperature demonstrate that an acceptable environment is maintained during the transition phase both for equipment in the room and habitability for operators who may need to enter the room.

3.2.4.2.8 Ventilation (Equipment Cooling) - Confirm that evaluations of the battery room temperature demonstrate that an acceptable environment, during both high ambient temperature and during extreme cold ambient temperature, is maintained during Phases 2 and 3.

3.2.4.2.C Ventilation (Equipment Cooling) -Confirm the required ventilation flow or the size of the portable fans to maintain acceptable environmental conditions in the DC equipment room.

3.2.4.3.A Heat Tracing- Confirm completion of walkdowns and evaluation of where heat tracing may be needed for freeze protection of equipment or instruments used in the ELAP mitigation strategies.

Revision 1 Page 59 of 60 2014-02-15

3.2.4.4.A Lighting- Confirm need for additional portable lighting, such as de powered lights.

3.2.4.4.8 Communications - Confirm that upgrades to the site's communication system have been completed.

3.2.4.8.A Electrical Power Sources- Confirm the technical basis for the selection and size of the FLEX generators to be used in support of the coping strategies.

3.2.4.10.A Load Reduction to Conserve DC Power- Confirm final load shed list and the evaluation of any potential adverse effects of shedding those loads.

3.2.4.10.8 Load Reduction to Conserve DC Power- Confirm the final de load profile with the required loads and the finalized minimum battery voltage.

3.2.4.10.C Load Reduction to Conserve DC Power- Confirm time after the ELAP for connecting the FLEX DG to the battery chargers.

Revision 1 Page 60 of 60 2014-02-15

If you have any questions, please contact John Boska at 301-415-2901.

Sincerely, IRA/

Jeremy S. Bowen, Chief Mitigating Strategies Projects Branch Mitigating Strategies Directorate Office of Nuclear Reactor Regulation Docket No. 50-333

Enclosures:

1. Interim Staff Evaluation
2. Technical Evaluation Report cc w/encl: Distribution via Listserv DISTRIBUTION PUBLIC RidsRgn1 MaiiCenter Resource LPL 1-1 R/F JBoska, NRRIMSD RidsNrrDorllpl1-1 Resource JBowen, NRRIMSD RidsNrrPMFitzPatrick Resource RidsNrrLASLent Resource RidsAcrsAcnw_MaiiCTR Resource ADAMS A ccess1on NOS. Pk(Q ML14007A679 , Le tter/ISE ML14007A681 TER ML14043A428 *V"1aema1"I OFFICE NRRIMSD/MSPB/PM NRRIMSD/LA NRRIMSD/SA* NRR/MSD/MSPB/BC*