Letter Sequence Other |
---|
|
|
MONTHYEARRS-20-139, Response to Request for Additional Information Regarding License Amendment Requests to Adopt TSTF-505, Revision 2, and 10 CFR 50.692020-11-24024 November 2020 Response to Request for Additional Information Regarding License Amendment Requests to Adopt TSTF-505, Revision 2, and 10 CFR 50.69 Project stage: Response to RAI JAFP-21-0069, Application to Adopt 10 CFR 50.69, Risk-informed Categorization and Treatment of Structures, Systems and Components for Nuclear Power Reactors2021-07-30030 July 2021 Application to Adopt 10 CFR 50.69, Risk-informed Categorization and Treatment of Structures, Systems and Components for Nuclear Power Reactors Project stage: Request JAFP-21-0070, License Amendment Request to Revise Technical Specifications to Adopt Risk Informed Completion Times TSTF-505, Revision 2, Provide Risk- Informed Extended Completion Times - RITSTF Initiative 4b2021-07-30030 July 2021 License Amendment Request to Revise Technical Specifications to Adopt Risk Informed Completion Times TSTF-505, Revision 2, Provide Risk- Informed Extended Completion Times - RITSTF Initiative 4b Project stage: Request ML21246A2112021-09-0303 September 2021 Acceptance of Requested Licensing Action License Amendment Request to Adopt TSTF-505 Project stage: Acceptance Review ML21246A2072021-09-0303 September 2021 Acceptance of Requested Licensing Action License Amendment Request to Adopt 10 CFR 50.69 Project stage: Acceptance Review ML21285A1492021-10-22022 October 2021 Audit Plan in Support of Review of License Amendment Requests Regarding 50.69/TSFT-505 Project stage: Other JAFP-22-2020, Supplemental Information No. 1 for James A. FitzPatrick Nuclear Power Plant to Adopt Risk Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b. and 10CFR 50.69, Risk-Info2022-03-0404 March 2022 Supplemental Information No. 1 for James A. FitzPatrick Nuclear Power Plant to Adopt Risk Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b. and 10CFR 50.69, Risk-Informed Project stage: Supplement ML22124A2672022-05-0404 May 2022 Request for Additional Information for James A. FitzPatrick Nuclear Power Plant TSTF-505 Project stage: RAI JAFP-22-0032, Response to Request for Additional Information for James A. FitzPatrick Nuclear Power Plant to Adopt Risk Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b..2022-06-16016 June 2022 Response to Request for Additional Information for James A. FitzPatrick Nuclear Power Plant to Adopt Risk Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b.. Project stage: Response to RAI ML22196A0612022-08-23023 August 2022 Issuance of Amendment No. 352 Adoption of 10 CFR 50.69 Risk-Informed Categorization and Treatment of Structures, Systems and Components for Nuclear Power Reactors Project stage: Approval ML22238A1202022-08-31031 August 2022 Regulatory Audit Summary Regarding License Amendment Requests to Adopt 10 CFR 50.69 and to Permit the Use of Risk-Informed Completion Times in Accordance with TSTF-505, Rev. 2 (EPIDs L-2021-LLA 0142 and L-2021-LLA-0143) Project stage: Other ML22223A1412022-09-0101 September 2022 Issuance of Amendment No. 353 Adoption of TSTF - 505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4B Project stage: Approval 2022-03-04
[Table View] |
|
---|
Category:Audit Report
MONTHYEARML22238A1202022-08-31031 August 2022 Regulatory Audit Summary Regarding License Amendment Requests to Adopt 10 CFR 50.69 and to Permit the Use of Risk-Informed Completion Times in Accordance with TSTF-505, Rev. 2 (EPIDs L-2021-LLA 0142 and L-2021-LLA-0143) ML18166A2542018-06-21021 June 2018 Report for the Audit of Licensee Responses to Interim Staff Evaluations Open Items Related to NRC Order EA-13-109 to Modify Licenses with Regard to Reliable Hardened Containment Vents Capable of Operation ... ML16343A0112016-12-14014 December 2016 Report for the Audit Regarding Implementation of Mitigating Strategies and Reliable Spent Fuel Pool Instrumentation Related to Orders EA-12-049 and EA-12-051 ML16072A0352016-04-12012 April 2016 Nrc'S Report for the Audit of Entergy Nuclear Operations, Inc'S. Flood Hazard Reevaluation Report Submittal Relating to the Near-Term Task Force Recommendation 2.1-Flooding for James A. Fitzpatrick Nuclear Power Plant ML15313A1082015-12-0101 December 2015 Audit of Entergy'S Management of Regulatory Commitments ML14007A6812014-02-21021 February 2014 Interim Staff Evaluation Relating to Overall Integrated Plan in Response to Order EA-12-049 (Mitigation Strategies) ML0923904602009-09-0101 September 2009 ME1717 - Letter Audit of Entergy'S Management of Regulatory Commitments ML0705804642007-05-25025 May 2007 Audit Summary for the JAFNPP LRA Safety Site Audits ML0703803892007-02-0606 February 2007 JAFNPP AMP and AMR Database ML0634004152006-12-0404 December 2006 (PA-LR) AMP Audit Request and Response Items 50 - 417 ML0616000582006-06-13013 June 2006 Audit of Entergy'S Management of Regulatory Commitments 2022-08-31
[Table view] Category:Letter
MONTHYEARIR 05000333/20230042024-02-0707 February 2024 Integrated Inspection Report 05000333/2023004 and Independent Spent Fuel Storage Installation Inspection Report 07200012/2023001 ML24037A0102024-02-0606 February 2024 Requalification Program Inspection ML24018A0012024-01-18018 January 2024 Notification of Commercial Grade Dedication Inspection (05000333/2024010) and Request for Information ML24004A2302024-01-0808 January 2024 Project Manager Reassignment ML23356A0832024-01-0404 January 2024 Exemption from Select Requirements of 10 CFR Part 73 (EPID L-2023-LLE-0058 (Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting)) ML23278A1292023-12-14014 December 2023 Units 1 & 2; Limerick, Units 1 & 2; Nine Mile Point, Units 1 & 2; and Peach Bottom, Units 2 & 3 -Revision to Approved Alternatives to Use Boiling Water Reactor Vessel and Internals Project Guidelines JAFP-23-0065, License Amendment Request to Revise Technical Specifications to Adopt TSTF-529, Clarify Use and Application Rules, Revision 4, and Administrative Changes to the Technical Specifications2023-12-14014 December 2023 License Amendment Request to Revise Technical Specifications to Adopt TSTF-529, Clarify Use and Application Rules, Revision 4, and Administrative Changes to the Technical Specifications IR 05000333/20234012023-12-0808 December 2023 Cybersecurity Inspection Report 05000333/2023401 (Cover Letter Only) RS-23-126, Request for Exemption from 10 CFR 2.109(b)2023-12-0707 December 2023 Request for Exemption from 10 CFR 2.109(b) JAFP-23-0069, Supplemental Response to Part 73 Exemption Request Withdrawal of Request for Exemption from 10 CFR 73, Subpart B, Preemption Authority Requirements2023-12-0707 December 2023 Supplemental Response to Part 73 Exemption Request Withdrawal of Request for Exemption from 10 CFR 73, Subpart B, Preemption Authority Requirements JAFP-23-0057, and Independent Spent Fuel Storage Installation - Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation2023-11-22022 November 2023 and Independent Spent Fuel Storage Installation - Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation JAFP-23-0064, Emergency Plan Document Revision2023-11-15015 November 2023 Emergency Plan Document Revision JAFP-23-0063, Registration of Spent Fuel Cask Use2023-11-13013 November 2023 Registration of Spent Fuel Cask Use IR 05000333/20230032023-11-13013 November 2023 Integrated Inspection Report 05000333/2023003 ML23317A1192023-11-10010 November 2023 Constellation Energy Generation, LLC - 2023 Annual Report - Guarantees of Payment of Deferred Premiums IR 05000333/20230102023-10-26026 October 2023 Biennial Problem Identification and Resolution Inspection Report 05000333/2023010 JAFP-23-0059, Registration of Spent Fuel Cask Use2023-10-24024 October 2023 Registration of Spent Fuel Cask Use IR 05000333/20233012023-10-19019 October 2023 Initial Operator Licensing Examination Report 05000333/2023301 RS-23-097, Constellation Energy Generation, LLC, Advisement of Leadership Changes and Submittal of Updated Standard Practice Procedures Plans2023-10-12012 October 2023 Constellation Energy Generation, LLC, Advisement of Leadership Changes and Submittal of Updated Standard Practice Procedures Plans JAFP-23-0050, Physical Security Plan, Revision 242023-08-31031 August 2023 Physical Security Plan, Revision 24 JAFP-23-0048, Supplemental Information for License Amendment Request to Update the Technical Specification Bases to Change the Fuel Handling Accident Analysis2023-08-31031 August 2023 Supplemental Information for License Amendment Request to Update the Technical Specification Bases to Change the Fuel Handling Accident Analysis IR 05000333/20230052023-08-31031 August 2023 Updated Inspection Plan for James A. FitzPatrick Nuclear Power Plant (Report 05000333/2023005) JAFP-23-0047, Correction to the 2022 Annual Radioactive Effluent Release Report2023-08-30030 August 2023 Correction to the 2022 Annual Radioactive Effluent Release Report ML23228A1342023-08-16016 August 2023 Licensed Operator Positive Fitness-For-Duty Test IR 05000333/20230022023-08-0707 August 2023 Integrated Inspection Report 05000333/2023002 RS-23-087, Revision to Approved Alternatives Associated with the Use of the BWRVIP Guidelines in Lieu of Specific ASME Code Requirements on Reactor2023-08-0404 August 2023 Revision to Approved Alternatives Associated with the Use of the BWRVIP Guidelines in Lieu of Specific ASME Code Requirements on Reactor JAFP-23-0040, License Amendment Request to Update the Technical Specification Bases to Change the Fuel Handling Accident Analysis2023-08-0303 August 2023 License Amendment Request to Update the Technical Specification Bases to Change the Fuel Handling Accident Analysis JAFP-23-0043, 10 CFR 50.46 Annual Report2023-07-31031 July 2023 10 CFR 50.46 Annual Report JAFP-23-0038, License Amendment Request to Modify Technical Specification Surveillance Requirement (SR) 3.4.3.1 Safety Relief Valves (S/Rvs) Setpoint Lower Tolerance2023-07-28028 July 2023 License Amendment Request to Modify Technical Specification Surveillance Requirement (SR) 3.4.3.1 Safety Relief Valves (S/Rvs) Setpoint Lower Tolerance ML23208A1622023-07-27027 July 2023 Operator Licensing Examination Approval IR 05000333/20234022023-07-26026 July 2023 Security Baseline Inspection Report 05000333/2023402 IR 05000333/20230112023-07-25025 July 2023 Post-Approval Site Inspection for License Renewal - Phase 4 Inspection Report 05000333/2023011 IR 05000333/20235012023-07-20020 July 2023 Emergency Preparedness Biennial Exercise Inspection Report 05000333/2023501 JAFP-23-0033, License Amendment Request - Technical Specifications (TS) Section 3.3.1.2, Source Range Monitors (SRM) Instrumentation2023-06-28028 June 2023 License Amendment Request - Technical Specifications (TS) Section 3.3.1.2, Source Range Monitors (SRM) Instrumentation IR 05000333/20234202023-06-26026 June 2023 Security Baseline Inspection Report 05000333 2023420 RS-23-077, Response to NRC Regulatory Issue Summary 2023-01, Preparation and Scheduling of Operator Licensing Examinations2023-06-16016 June 2023 Response to NRC Regulatory Issue Summary 2023-01, Preparation and Scheduling of Operator Licensing Examinations ML23164A0322023-06-13013 June 2023 Request for Information for a Biennial Problem Identification and Resolution Inspection; Inspection Report 05000333/2023010 ML23152A0042023-06-0101 June 2023 Information Request for the Cyber Security Baseline Inspection, Notification to Perform Inspection 05000333/2023401 RS-23-042, Application to Revise Technical Specifications to Adopt TSTF-580, Provide Exception from Entering Mode 4 with No Operable RHR Shutdown Cooling2023-05-25025 May 2023 Application to Revise Technical Specifications to Adopt TSTF-580, Provide Exception from Entering Mode 4 with No Operable RHR Shutdown Cooling JAFP-23-0025, 2022 Annual Radiological Environmental Operating Report2023-05-10010 May 2023 2022 Annual Radiological Environmental Operating Report IR 05000333/20230012023-05-0303 May 2023 Integrated Inspection Report 05000333/2023001 ML23117A2172023-05-0101 May 2023 Safety Evaluation for Quality Assurance Program Manual Reduction in Commitment ML23114A2522023-04-28028 April 2023 Request to Use a Provision of a Later Edition of the ASME Boiler & Pressure Vessel Code, Section XI JAFP-23-0023, 2022 Annual Radioactive Effluent Release Report2023-04-27027 April 2023 2022 Annual Radioactive Effluent Release Report IR 05000333/20230122023-04-13013 April 2023 Quadrennial Fire Protection Inspection Report 05000333/2023012 ML23095A3722023-04-0505 April 2023 2023 Updated Final Safety Analysis Report, Technical Specification Bases and Technical Requirements Manual Changes Transmittal RS-23-049, Constellation Energy Generation, LLC, Report on Status of Decommissioning Funding for Reactors and Independent Spent Fuel Storage Installations2023-03-23023 March 2023 Constellation Energy Generation, LLC, Report on Status of Decommissioning Funding for Reactors and Independent Spent Fuel Storage Installations IR 05000333/20220042023-03-20020 March 2023 Integrated Inspection Report 05000333/2022004 JAFP-23-0010, 2022 REIRS Transmittal of NRC Form 52023-03-20020 March 2023 2022 REIRS Transmittal of NRC Form 5 ML23061A1632023-03-0303 March 2023 Reassignment of the U.S. Nuclear Regulatory Commission Branch Chief in the Division of Operating Reactor Licensing for Plant Licensing Branch 3 2024-02-07
[Table view] |
Text
August 31, 2022 Mr. David P. Rhoades Senior Vice President Constellation Energy Generation, LLC President and Chief Nuclear Officer Constellation Nuclear 4300 Winfield Road Warrenville, IL 60555
SUBJECT:
JAMES A. FITZPATRICK NUCLEAR POWER PLANT - REGULATORY AUDIT
SUMMARY
REGARDING LICENSE AMENDMENT REQUESTS TO ADOPT 10 CFR 50.69, RISK-INFORMED CATEGORIZATION AND TREATMENT OF STRUCTURES, SYSTEMS, AND COMPONENTS FOR NUCLEAR POWER PLANTS AND TO PERMIT THE USE OF RISK-INFORMED COMPLETION TIMES IN ACCORDANCE WITH TSTF-505, REVISION 2, PROVIDE RISK-INFORMED EXTENDED COMPLETION TIMES - RITSTF INITIATIVE 4B (EPID L-2021-LLA-0142 AND L-2021-LLA-0143)
Dear Mr. Rhoades:
By letters dated July 30, 2021 (Agencywide Documents Access and Management System (ADAMS) Accession Nos. ML21211A053 and ML21211A078), Exelon Generation Company, LLC (Exelon) submitted two license amendment requests (LARs) for James A. FitzPatrick Nuclear Power Plant. On February 1, 2022 (ML22032A333), Exelon Generation Company, LLC was renamed Constellation Energy Generation, LLC (the licensee). In its LARs, the licensee requested to amend license DPR-59 to adopt Technical Specifications Task Force (TSTF)
Traveler 505 (TSTF-505), Provide Risk-informed Extended Completion Times, RITSTF Initiative 4b, and the provisions of Title 10 of the Code of Federal Regulations (10 CFR),
Section 50.69, Risk-informed categorization and treatment of structures, systems and components for nuclear power reactors.
The U.S. Nuclear Regulatory Commission (NRC) staff reviewed the licensees LARs and determined that a regulatory audit would assist in the timely completion of the LAR review. By letter dated October 22, 2021 (ML21285A149), the NRC staff issued its audit plan. The plan consisted of an in-office audit and a remote audit, which occurred during the week of January 18, 2022.
As a result of the audit, on March 4, 2022 (ML22063A135), the licensee submitted a supplement to the LARs to respond to most of the audit questions posed by the NRC staff during the virtual audit. To address the remaining questions, the NRC issued a request for additional information, which the licensee responded to on June 16, 2022 (ML22167A071).
The audit summary for the combined remote audit is enclosed.
D. Rhoades If you have any questions, please contact me by telephone at 301-415-2048 or by e-mail to Justin.Poole@nrc.gov.
Sincerely,
/RA/
Justin C. Poole, Project Manager Plant Licensing Branch I Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-333
Enclosure:
Regulatory Audit Summary cc: Listserv
COMBINED REGULATORY AUDIT
SUMMARY
LICENSE AMENDMENT REQUESTS REGARDING RISK-INFORMED COMPLETION TIMES AND ADOPTION OF 10 CFR 50.69, RISK-INFORMED CATEGORIZATION AND TREATMENT OF STRUCTURES, SYSTEMS, AND COMPONENTS FOR NUCLEAR POWER PLANTS CONSTELLATION FITZPATRICK, LLC DOCKET NO. 50-333
1.0 BACKGROUND
A regulatory audit is a planned license or regulation-related activity that includes the examination and evaluation of primarily non-docketed information. The audit is conducted with the intent to gain understanding, to verify information, and to identify information that will require docketing to support the basis of a licensing or regulatory decision.
By letters dated July 30, 2021 (Agencywide Documents Access and Management System (ADAMS) Accession Nos. ML21211A053 and ML21211A078), Exelon Generation Company, LLC (Exelon) submitted two license amendment requests (LARs) for James A. FitzPatrick Nuclear Power Plant. On February 1, 2022 (ML22032A333), Exelon Generation Company, LLC was renamed Constellation Energy Generation, LLC (the licensee). In its LARs, the licensee requested to amend license DPR-59 to adopt Technical Specifications Task Force (TSTF)
Traveler 505 (TSTF-505), Provide Risk-informed Extended Completion Times, RITSTF Initiative 4b, and the provisions of Title 10 of the Code of Federal Regulations (10 CFR),
Section 50.69, Risk-informed categorization and treatment of structures, systems and components for nuclear power reactors.
The NRC staff performed a preliminary review of the licensees LARs and determined that a regulatory audit would assist in the timely completion of the reviews. The regulatory audit was performed consistent with NRC Office of Nuclear Reactor Regulation (NRR) Office Instruction LIC-111, Regulatory Audits, dated December 29, 2008 (ML082900195). The NRC staff conducted a combined regulatory audit that consisted of an electronic and remote audit, which occurred during the week of January 18, 2022. The initial audit plans consisting of In-office Audit and Site Audit were provided to the licensee on October 22, 2021 (ML21285A149), and included a list of information that the licensee needed to upload on to the ePortals with access control, to the audit team members.
The NRC staff reviewed documents and held discussions with members of the licensee regarding the LARs under staff review. As a result of the audit, on March 4, 2022 (ML22063A135), the licensee submitted a supplement to the LARs to respond to most of the audit questions posed by the NRC staff during the virtual audit. To address the remaining questions, the NRC issued a request for additional information, which the licensee responded to on June 16, 2022 (ML22167A071).
Enclosure
2.0 AUDIT ACTIVITIES AND OBSERVATIONS 2.1 In-Office and Remote Audits The remote audit was conducted using video and teleconferencing capabilities. The purpose of the audit was to (1) gain a better understanding of the information in the LARs to support the staffs review, and (2) identify any information that would be required from the licensee to be provided on-the-docket for the NRC staff to render a staff finding to support the safety evaluation.
The NRC staff reviewed documents identified as audit information needs in the audit plan.
These documents were accessed through the electronic reading room established by the licensee. They were used to prepare for the virtual meeting phase of the audit and to develop specific questions to be addressed.
During the virtual meeting, the licensee presented prepared material to address questions the NRC staff had transmitted in advance. After each presentation, the audit team held detailed discussions with the licensee and in some cases, reviewed additional documentation in the electronic reading room. The NRC staff assesses the information gathered in this way to determine whether it should be submitted on the docket (either in a supplement to the amendment request or in response to a request for additional information that the staff would issue after the exit interview). Supplemental submittals and staff requests for additional information are outside the scope of the audit.
During the virtual meeting, there was an entrance interview, presentations prepared by the licensee on technical topics associated with the § 50.69 and TSTF-505 LARs, discussions of the audit questions prepared by the auditors, written and verbal responses by the licensee; ad hoc sessions on technical issues of interest to the NRC staff, and the inspection of additional records (e.g., probable risk assessment-related reports). At the end of the virtual meeting, the NRC staff conducted a brief exit interview reporting preliminary observations.
AUDIT
SUMMARY
From discussions, the NRC staff gathered information on various elements of the technical adequacy of the probable risk assessments (PRAs) and the programmatic elements of the risk-informed applications that are important in the staffs review. The staff also observed a demonstration of the tool the licensee plans to use in its configuration risk management program.
On January 20, 2022, the NRC staff and the licensee concluded the virtual audit meeting. The NRC staff summarized the information identified during the audit that would need to be docketed and discussed near-term milestones in the review of the LARs.
3.0 RESULTS OF THE AUDIT During the in-office and remote audits, the NRC staff did not make any regulatory decisions regarding the LARs under staff review. The audits identified information that the licensee needed to provide to the NRC on-the-docket and identified information that was not needed to render a staff finding, thus obviating the need for some RAIs.
4.0 AUDIT PARTICIPANTS Licensee and their Contractors:
Vince Anderson Eric Deeken Caitlin Gainey Bob Graham Jessie Hodge Bob Kirchner James Landale Larry Lee Suzanne Lloyd Andy Miller Ed Parsley David Passehl Timothy Peter Chris Pupek Darani Reddick Ronnie Reynolds Mike Saunders Jeff Schappaugh Leo Shanley Nick Sternowski Jeff Stone Richard Sullivan Phil Tarpinian Evan Thompson Don Vanover Alaina Vivanco Steve Wyman Tony Yost NRC and their Contractors:
Steven Alferink Adrienne Brown Jeff Circle James Danna Fred Forsaty Chuck Moulton Malcolm Patterson Justin Poole Bob Pascarelli Andrea Russell Steven Short Mark Wilk Wesley Wu Steve Wyman Bob Vettori
5.0 LIST OF DOCUMENTS REVIEWED The following documents were reviewed during the audit:
- 1. James A. FitzPatrick Nuclear Power Plant PRA Peer Review Report, April 2010.
- 2. James A. FitzPatrick Nuclear Power Plant F&O Report, April 2020.
- 3. James A. FitzPatrick Nuclear Power Plant Focused Peer Review Report, April 2020.
- 4. James A. FitzPatrick Nuclear Power Plant Fire PRA Peer Review Report, April 2020.
- 5. James A. FitzPatrick Nuclear Power Plant FPIE & Fire PRA F&O Independent Assessment, August 2020.
- 6. James A. FitzPatrick Nuclear Power Plant PRA F&O Independent Assessment, April 2021.
- 7. James A. FitzPatrick Nuclear Power Plant Fire PRA Summary & Quantification Notebook, JF-PRA-021.11, Revision 3, March 2021.
- 8. ER-AA-600-1015, FPIE PRA MODEL UPDATE, Revision 20.
- 9. ER-AA-600-1061 Fire PRA Model Update and Control, Revision 7.
- 10. James A. FitzPatrick Nuclear Power Plant Fire PRA Uncertainty and Sensitivity Notebook, JF-PRA-021.12, Revision 2.
- 11. JF-PRA-013, James A. FitzPatrick Nuclear Power Plant PRA Summary Document Notebook, Revision 0.
- 12. JF-PRA-014, James A. FitzPatrick Nuclear Power Plant Quantification Notebook, Revision 2.
- 13. JF-PRA-015, James A. FitzPatrick Nuclear Power Plant Level 2 Analysis, Revision 0.
- 14. JF-MISC-021, James A. FitzPatrick Nuclear Power Plant Assessment of Key Assumptions and Source of Uncertainty, Revision 0.
- 15. JAF-RPT-MISC-02211, James A. FitzPatrick Nuclear Power Plant Individual Plant Examination of External Events, Revision 0.
- 16. NRC Letter, James A. FitzPatrick Nuclear Power Plant Individual Plant Examination of External Events Safety Evaluation. September 21, 2000.
- 17. James A. FitzPatrick Nuclear Power Plant AOP-13, Severe Weather, Revision 38.
- 18. JF-ASM-002, JAF TMRE Model Development and Quantification, Revision 0.
- 19. JF-PRA-005.33, James A. FitzPatrick Nuclear Power Plant Portable Equipment System Notebook, Revision 0.
- 20. JAFP-15-0036, Flooding Hazard Reevaluation Report.
- 21. Exelon Fleet Procedure OP-AA-201-012-1001, Operations On-Line Fire Risk Management.
- 22. Exelon Fleet Procedure OP-AA-108-118, Risk Informed Completion Time.
- 23. Exelon Fleet Procedure WC-AA-101-1006, On-Line Risk Management and Assessment.
ML22238A120 OFFICE NRR/DORL/LPL1/PM NRR/DORL/LPL1/LA NRR/DRA/APLA/BC NAME JPoole KZeleznock RPascarelli DATE 8/25/2022 08/30/2022 08/30/2022 OFFICE NRR/DORL/LPL1/BC NRR/DORL/LPL1/PM NAME HGonzalez JPoole DATE 08/31/2022 08/31/2022