| title = Triennial Fire Protection Inspection Report 05000247/2016007
| title = Triennial Fire Protection Inspection Report 05000247/2016007
| author name = Dentel G T
| author name = Dentel G
| author affiliation = NRC/RGN-I/DRS/EB2
| author affiliation = NRC/RGN-I/DRS/EB2
| addressee name = Vitale A J
| addressee name = Vitale A
| addressee affiliation = Entergy Nuclear Operations, Inc
| addressee affiliation = Entergy Nuclear Operations, Inc
| docket = 05000247
| docket = 05000247
| license number = DPR-026
| license number = DPR-026
| contact person = Dentel G T
| contact person = Dentel G
| document report number = IR 2016007
| document report number = IR 2016007
| document type = Inspection Report, Letter
| document type = Inspection Report, Letter
Line 18: Line 18:


=Text=
=Text=
{{#Wiki_filter:
{{#Wiki_filter:ary 6, 2017
[[Issue date::January 6, 2017]]


Mr. Anthony J. Vitale, Site Vice President Entergy Nuclear Operations, Inc.
==SUBJECT:==
 
INDIAN POINT NUCLEAR GENERATING UNIT 2 - TRIENNIAL FIRE PROTECTION INSPECTION REPORT 05000247/2016007
Indian Point Energy Center
 
450 Broadway, GSB
 
P.O. Box 249
 
Buchanan, NY 10511-0249
 
SUBJECT: INDIAN POINT NUCLEAR GENERATING UNIT 2 - TRIENNIAL FIRE PROTECTION INSPECTION REPORT 05000247/2016007


==Dear Mr. Vitale:==
==Dear Mr. Vitale:==
On December 16, 2016, the U.S. Nuclear Regulatory Commission (NRC) completed a triennial  
On December 16, 2016, the U.S. Nuclear Regulatory Commission (NRC) completed a triennial fire protection inspection at your Indian Point Nuclear Generating Unit 2 and discussed the results of this inspection with you and other members of your staff. The results of this inspection are documented in the enclosed report.


fire protection inspection at your Indian Point Nuclear Generating Unit 2 and discussed the  
The inspection examined activities conducted under your license as they relate to safety and compliance with the Commission's rules and regulations, and with the conditions of your license. The inspectors reviewed selected procedures and records, observed activities, and interviewed station personnel. The inspectors also reviewed mitigation strategies for addressing large fires and explosions.


results of this inspection with you and other members of your staff. The results of this
Based on the results of this inspection, no findings were identified. This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with 10 CFR 2.390, Public Inspections, Exemptions, Requests for Withholding.
 
inspection are documented in the enclosed report.
 
The inspection examined activities conducted under your license as they relate to safety and compliance with the Commission's rules and regulations, and with the conditions of your license. The inspectors reviewed selected procedures and records, observed activities, and interviewed station personnel. The inspectors also reviewed mitigation strategies for addressing
 
large fires and explosions.
 
Based on the results of this inspection, no findings were identified. This letter, its enclosure, and your response (if any) will be made available for public inspection  
 
and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with 10 CFR 2.390, "Public Inspections, Exemptions, Requests for Withholding."


Sincerely,
Sincerely,
/RA/ Glenn T. Dentel, Chief Engineering Branch 2 Division of Reactor Safety  
/RA/
 
Glenn T. Dentel, Chief Engineering Branch 2 Division of Reactor Safety Docket No. 50-247 License No. DPR-26 Enclosure:
Docket No. 50-247 License No. DPR-26  
Inspection Report 05000247/2016007 w/Attachment: Supplementary Information cc w/encl: Distribution via ListServ
 
Enclosure:  
 
Inspection Report 05000247/2016007  
 
w/Attachment: Supplementary Information  
 
cc w/encl: Distribution via ListServ


=SUMMARY=
=SUMMARY=
IR 05000247/2016007; 11/28/2016 - 12/16/2016; Indian Point Nuclear Generating Unit 2;  
IR 05000247/2016007; 11/28/2016 - 12/16/2016; Indian Point Nuclear Generating Unit 2;


Triennial Fire Protection Inspection.
Triennial Fire Protection Inspection.


This report covered a two week on-site triennial fire protection team inspection by specialist inspectors. The NRC's program for overseeing the safe operation of commercial nuclear power reactors is described in NUREG-1649, "Reactor Oversight Process," Revision 6, dated July 2016.
This report covered a two week on-site triennial fire protection team inspection by specialist inspectors. The NRCs program for overseeing the safe operation of commercial nuclear power reactors is described in NUREG-1649, Reactor Oversight Process, Revision 6, dated July 2016.


No findings were identified.
No findings were identified.
3


=REPORT DETAILS=
=REPORT DETAILS=


Background  
Background This report presents the results of a triennial fire protection inspection conducted in accordance with NRC Inspection Procedure (IP) 71111.05T, Fire Protection. An objective of the inspection was to assess whether Entergy Nuclear Operations, Inc. (Entergy) has implemented an adequate fire protection program and that post-fire safe shutdown capabilities have been established and are being properly maintained at the Indian Point Nuclear Generating Unit 2 (IP2). The following fire areas (FA) and associated fire zones (FZ) were selected for detailed review based on prior inspection results and risk insights from the IP2 Individual Plant Examination of External Events:
 
Fire Area / Fire Zone FZ 15      Main Control Room FZ 10      Diesel Generator Building FA F      PAB Corridor 80 & 98 and Fan House 89 Inspection of these FAs/FZs fulfilled the IP requirement to inspect a minimum of three samples.
This report presents the results of a triennial fire protection inspection conducted in accordance  
 
with NRC Inspection Procedure (IP) 71111.05T, "Fire Protection.An objective of the inspection  


was to assess whether Entergy Nuclear Operations, Inc. (Entergy) has implemented an
The inspectors evaluated Entergys fire protection program (FPP) against applicable requirements which included Unit 2 Operating License Conditions 2.K. and 2.N., Unit 3 Operating License Condition 2.AC., NRC Safety Evaluations, Title 10 of the Code of Federal Regulations (10 CFR) 50.48, and 10 CFR 50, Appendix R. The inspectors also reviewed related documents that included the Updated Final Safety Analysis Report (UFSAR), the Fire Protection Program Plan, the Fire Hazards Analysis (FHA), and the Safe Shutdown Analysis Report.


adequate fire protection program and that post-fire safe shutdown capabilities have been
The team evaluated aspects of three mitigating strategies for responding to large fires and explosions, which are required by Operating License Condition 2.N for Unit 2, Operating License Condition 2.AC for Unit 3, and 10 CFR 50.54(hh)(2). The team also reviewed related documents that included Nuclear Energy Institute 06-12, "B.5.b Phases 2 & 3 Submittal Guidance," Revision 2 (ML070090060). Inspection of these strategies fulfills the IP requirement to inspect a minimum of one sample.
 
established and are being properly maintained at the Indian Point Nuclear Generating Unit 2 (IP2). The following fire areas (FA) and associated fire zones (FZ) were selected for detailed
 
review based on prior inspection results and risk insights from the IP2 Individual Plant
 
Examination of External Events:
 
Fire Area / Fire Zone FZ 15 Main Control Room  FZ 10 Diesel Generator Building  FA F PAB Corridor 80' & 98' and Fan House 89' Inspection of these FAs/FZs fulfilled the IP requirement to inspect a minimum of three samples.
 
The inspectors evaluated Entergy's fire protection program (FPP) against applicable
 
requirements which included Unit 2 Operating License Conditions 2.K. and 2.N., Unit 3
 
Operating License Condition 2.AC., NRC Safety Evaluations, Title 10 of the Code of Federal Regulations (10 CFR) 50.48, and 10 CFR 50, Appendix R. The inspectors also reviewed related documents that included the Updated Final Safety Analysis Report (UFSAR), the Fire
 
Protection Program Plan, the Fire Hazards Analysis (FHA), and the Safe Shutdown Analysis
 
Report.
 
The team evaluated aspects of three mitigating strategies for responding to large fires and  
 
explosions, which are required by Operating License Condition 2.N for Unit 2, Operating  
 
License Condition 2.AC for Unit 3, and 10 CFR 50.54(hh)(2). The team also reviewed related  
 
documents that included Nuclear Energy Institute 06-12, "B.5.b Phases 2 & 3 Submittal  
 
Guidance," Revision 2 (ML070090060). Inspection of these strategies fulfills the IP requirement  
 
to inspect a minimum of one sample.


Documents reviewed for each section of this report are listed in the Attachment.
Documents reviewed for each section of this report are listed in the Attachment.


==REACTOR SAFETY==
==REACTOR SAFETY==
Cornerstones: Initiating Events, Mitigating Systems, and Barrier Integrity 1R05 Fire Protection (IP 71111.05T)
Cornerstones: Initiating Events, Mitigating Systems, and Barrier Integrity
{{a|1R05}}
==1R05 Fire Protection (IP 71111.05T)==


===.01 Protection of Safe Shutdown Capabilities===
===.01 Protection of Safe Shutdown Capabilities===


====a. Inspection Scope====
====a. Inspection Scope====
The team reviewed the FHA, post-fire safe shutdown analyses, and supporting drawings  
The team reviewed the FHA, post-fire safe shutdown analyses, and supporting drawings and documents to verify whether the safe shutdown capabilities were properly protected from fire damage. The team evaluated equipment and cable separation to determine whether the applicable separation requirements of Appendix R, Section III.G, and the IP2 design and licensing bases were maintained for the credited safe shutdown equipment and their supporting power, control, and instrumentation cables. The team's review included an assessment of the adequacy of the selected systems for reactor pressure control, reactivity control, reactor coolant makeup, decay heat removal, process monitoring, and associated support system functions.
 
and documents to verify whether the safe shutdown capabilities were properly protected from fire damage. The team evaluated equipment and cable separation to determine whether the applicable separation requirements of Appendix R, Section III.G, and the  
 
IP2 design and licensing bases were maintained for the credited safe shutdown  
 
equipment and their supporting power, control, and instrumentation cables. The team's  
 
review included an assessment of the adequacy of the selected systems for reactor  
 
pressure control, reactivity control, reactor coolant makeup, decay heat removal, process monitoring, and associated support system functions.


====b. Findings====
====b. Findings====
Line 142: Line 71:


====a. Inspection Scope====
====a. Inspection Scope====
The team walked down accessible portions of the selected FAs to evaluate whether the  
The team walked down accessible portions of the selected FAs to evaluate whether the material conditions of the FA boundaries were adequate for the fire hazards in the area.


material conditions of the FA boundaries were adequate for the fire hazards in the area.
The team compared the FA boundaries, including walls, ceilings, floors, fire doors, fire dampers, penetration seals, electrical raceway and conduit fire barriers, and redundant equipment fire barriers to design and licensing basis requirements, industry standards, and the IP2 FPP, as approved by the NRC, to identify any potential degradation or non-conformances.


The team compared the FA boundaries, including walls, ceilings, floors, fire doors, fire  
The team reviewed selected engineering evaluations, installation and repair work orders, and qualification records for a sample of penetration seals to determine whether the fill material was properly installed and whether the as-left configuration satisfied design requirements for the intended fire rating. The team also reviewed similar records for selected fire protection wraps and an encapsulation system to verify whether the material and configuration was appropriate for the required fire rating and conformed to the engineering design.


dampers, penetration seals, electrical raceway and conduit fire barriers, and redundant
The team also reviewed recent inspection records and functional test procedures for fire dampers, and the inspection records for penetration seals and fire barriers, to verify whether the inspection was adequately conducted, the acceptance criteria were met, and any potential performance degradation was identified.
 
equipment fire barriers to design and licensing basis requirements, industry standards, and the IP2 FPP, as approved by the NRC, to identify any potential degradation or non-
 
conformances.
 
The team reviewed selected engineering evaluations, installation and repair work 
 
orders, and qualification records for a sample of penetration seals to determine whether
 
the fill material was properly installed and whether the as-left configuration satisfied
 
design requirements for the intended fire rating. The team also reviewed similar records
 
for selected fire protection wraps and an encapsulation system to verify whether the
 
material and configuration was appropriate for the required fire rating and conformed to
 
the engineering design.
 
The team also reviewed recent inspection records and functional test procedures for fire  
 
dampers, and the inspection records for penetration seals and fire barriers, to verify  
 
whether the inspection was adequately conducted, the acceptance criteria were met, and any potential performance degradation was identified.


====b. Findings====
====b. Findings====
Line 180: Line 85:


====a. Inspection Scope====
====a. Inspection Scope====
The team evaluated manual and automatic fire suppression and detection systems in the selected FAs to determine whether they were installed, tested, maintained, and  
The team evaluated manual and automatic fire suppression and detection systems in the selected FAs to determine whether they were installed, tested, maintained, and operated in accordance with NRC requirements, National Fire Protection Association (NFPA) codes of record, and the IP2 FPP, as approved by the NRC. The team also assessed whether the suppression systems capabilities were adequate to control and/or extinguish fires associated with the hazards in the selected areas.
 
operated in accordance with NRC requirements, National Fire Protection Association (NFPA) codes of record, and the IP2 FPP, as approved by the NRC. The team also
 
assessed whether the suppression systems capabilities were adequate to control and/or  


extinguish fires associated with the hazards in the selected areas.
The team reviewed the as-built capability of the fire water supply system to verify the design and licensing basis and NFPA code of record requirements were satisfied, and to assess whether those capabilities were adequate for the hazards involved. The team reviewed the fire water system hydraulic analyses to assess the adequacy of a single fire water pump to supply the largest single hydraulic load on the fire water system plus concurrent fire hose usage. The team evaluated the fire pump performance tests to assess the adequacy of the test acceptance criteria for pump minimum discharge pressure at the required flow rate, to verify the criteria was adequate to ensure that the design basis and hydraulic analysis requirements were satisfied. The team also evaluated the underground fire loop flow tests to verify the tests adequately demonstrated that the flow distribution circuits were able to meet design basis requirements. In addition, the team reviewed recent pump and loop flow test results to verify the testing was adequately conducted, the acceptance criteria were met, and any potential performance degradation was identified.


The team reviewed the as-built capability of the fire water supply system to verify the design and licensing basis and NFPA code of record requirements were satisfied, and to
The team walked down accessible portions of the detection and water suppression systems in the selected areas and major portions of the fire water supply system, including motor and diesel driven fire pumps, interviewed system and program engineers, and reviewed condition reports to independently assess the material condition of the systems and components. In addition, the team reviewed recent test results for the fire detection and suppression systems for the selected FAs to verify the testing was adequately conducted, the acceptance criteria were met, and any performance degradation was identified.


assess whether those capabilities were adequate for the hazards involved. The team
The team assessed the fire brigade capabilities by reviewing training, qualification, and drill critique records. The team also reviewed Entergy's fire-fighting strategies (i.e., pre-fire plans) and smoke removal plans for the selected FAs to determine if appropriate information was provided to fire brigade members and plant operators to identify safe shutdown equipment and instrumentation, and to facilitate suppression of a fire that could impact post-fire safe shutdown capability. The team independently inspected the fire brigade equipment, including personnel protective gear (e.g., turnout gear) and smoke removal equipment, to determine operational readiness for fire-fighting. In addition, the team reviewed Entergy's fire brigade equipment inventory and recent inspection and inventory results to verify adequate equipment was available, and any potential material deficiencies were identified.
 
reviewed the fire water system hydraulic analyses to assess the adequacy of a single
 
fire water pump to supply the largest single hydraulic load on the fire water system plus
 
concurrent fire hose usage. The team evaluated the fire pump performance tests to
 
assess the adequacy of the test acceptance criteria for pump minimum discharge
 
pressure at the required flow rate, to verify the criteria was adequate to ensure that the
 
design basis and hydraulic analysis requirements were satisfied. The team also
 
evaluated the underground fire loop flow tests to verify the tests adequately
 
demonstrated that the flow distribution circuits were able to meet design basis
 
requirements. In addition, the team reviewed recent pump and loop flow test results to
 
verify the testing was adequately conducted, the acceptance criteria were met, and any
 
potential performance degradation was identified.
 
The team walked down accessible portions of the detection and water suppression
 
systems in the selected areas and major portions of the fire water supply system, including motor and diesel driven fire pumps, interviewed system and program engineers, and reviewed condition reports to independently assess the material
 
condition of the systems and components. In addition, the team reviewed recent test
 
results for the fire detection and suppression systems for the selected FAs to verify the
 
testing was adequately conducted, the acceptance criteria were met, and any
 
performance degradation was identified.
 
The team assessed the fire brigade capabilities by reviewing training, qualification, and  
 
drill critique records. The team also reviewed Entergy's fire-fighting strategies (i.e., pre-
 
fire plans) and smoke removal plans for the selected FAs to determine if appropriate  
 
information was provided to fire brigade members and plant operators to identify safe  
 
shutdown equipment and instrumentation, and to facilitate suppression of a fire that  
 
could impact post-fire safe shutdown capability. The team independently inspected the  
 
fire brigade equipment, including personnel protective gear (e.g., turnout gear) and  
 
smoke removal equipment, to determine operational readiness for fire-fighting. In  
 
addition, the team reviewed Entergy's fire brigade equipment inventory and recent  
 
inspection and inventory results to verify adequate equipment was available, and any  
 
potential material deficiencies were identified.


====b. Findings====
====b. Findings====
Line 254: Line 99:


====a. Inspection Scope====
====a. Inspection Scope====
The team performed document reviews and plant walkdowns to verify that redundant  
The team performed document reviews and plant walkdowns to verify that redundant trains of systems required for hot shutdown, which are located in the same FA, are not subject to damage from fire suppression activities or from the rupture or inadvertent operation of fire suppression systems. Specifically, the team verified that:
 
A fire in one of the selected FAs would not indirectly, through production of smoke, heat or hot gases, cause activation of suppression systems that could potentially damage all redundant safe shutdown trains; A fire in one of the selected FAs (or the inadvertent actuation or rupture of a fire suppression system) would not indirectly cause damage to all redundant trains (e.g. sprinkler caused flooding of other than the locally affected train); and, Adequate drainage is provided in areas protected by water suppression systems.
trains of systems required for hot shutdown, which are located in the same FA, are
 
not subject to damage from fire suppression activities or from the rupture or inadvertent  
 
operation of fire suppression systems. Specifically, the team verified that:
A fire in one of the selected FAs would not indirectly, through production of smoke, heat or hot gases, cause activation of suppression systems that could  
 
potentially damage all redundant safe shutdown trains; A fire in one of the selected FAs (or the inadvertent actuation or rupture of a fire suppression system) would not indirectly cause damage to all redundant trains (e.g. sprinkler caused flooding of other than the locally affected train); and, Adequate drainage is provided in areas pr otected by water suppression systems.


====b. Findings====
====b. Findings====
Line 271: Line 108:


====a. Inspection Scope====
====a. Inspection Scope====
The team reviewed the safe shutdown analysis, operating procedures, piping and instrumentation drawings, electrical drawings, the UFSAR, and other supporting documents for the selected FAs to determine whether Entergy had properly identified the systems and components necessary to achieve and maintain post-fire safe shutdown conditions. The team evaluated selected systems and components credited by the safe shutdown analysis for reactor pressure control, reactivity control, reactor coolant  
The team reviewed the safe shutdown analysis, operating procedures, piping and instrumentation drawings, electrical drawings, the UFSAR, and other supporting documents for the selected FAs to determine whether Entergy had properly identified the systems and components necessary to achieve and maintain post-fire safe shutdown conditions. The team evaluated selected systems and components credited by the safe shutdown analysis for reactor pressure control, reactivity control, reactor coolant makeup, decay heat removal, process monitoring, and support system functions to assess the adequacy of Entergy's alternative shutdown methodology. The team also assessed whether alternative post-fire shutdown could be performed both with and without the availability of off-site power. The team walked down selected plant configurations to verify whether they were consistent with the assumptions and descriptions in the safe shutdown and the FHA. In addition, the team evaluated whether the systems and components credited for use during post-fire safe shutdown would remain free from fire damage.
 
makeup, decay heat removal, process monitoring, and support system functions to assess the adequacy of Entergy's alternative shutdown methodology. The team also assessed whether alternative post-fire shutdown could be performed both with and without the availability of off-site power. The team walked down selected plant  
 
configurations to verify whether they were consistent with the assumptions and descriptions in the safe shutdown and the FHA. In addition, the team evaluated whether the systems and components credited for use during post-fire safe shutdown would  


remain free from fire damage.
The team reviewed the training program for licensed and non-licensed operators to verify whether it included alternative shutdown capability. The team also verified whether personnel, required for post-fire safe shutdown, using either the normal or alternative shutdown methods, were trained and available on-site at all times, exclusive of those assigned as fire brigade members.
 
The team reviewed the training program for licensed and non-licensed operators to verify whether it included alternative shutdown capability. The team also verified whether personnel, required for post-fire safe shutdown, using either the normal or alternative shutdown methods, were trained and available on-site at all times, exclusive  
 
of those assigned as fire brigade members.


The team reviewed the adequacy of procedures utilized for post-fire shutdown and performed an independent walk through of procedure steps (i.e., a procedure tabletop)to assess the adequacy of implementation and human factors within the procedures.
The team reviewed the adequacy of procedures utilized for post-fire shutdown and performed an independent walk through of procedure steps (i.e., a procedure tabletop)to assess the adequacy of implementation and human factors within the procedures.
Line 287: Line 116:
The team also evaluated the time required to perform specific actions to verify whether operators could reasonably be expected to perform those actions within sufficient time to maintain plant parameters within specified limits.
The team also evaluated the time required to perform specific actions to verify whether operators could reasonably be expected to perform those actions within sufficient time to maintain plant parameters within specified limits.


Specific procedures reviewed for normal and alternative post-fire shutdown included:  
Specific procedures reviewed for normal and alternative post-fire shutdown included:
2-AOP-SSD-1, Control Room Inaccessibility Safe Shutdown Control, Revision 23; 2-ONOP-FP-001, Plant Fires, Revision 17; and, 2-SOP-ESP-001, Local Equipment Operation and Contingency Actions, Revision 12.


2-AOP-SSD-1, Control Room Inaccessibility Safe Shutdown Control, Revision 23;  2-ONOP-FP-001, Plant Fires, Revision 17; and, 2-SOP-ESP-001, Local Equipment Operation and Contingency Actions, Revision 12.
The team reviewed selected operator manual actions to verify whether they had been properly reviewed and approved and whether the actions could be implemented in accordance with plant procedures in the time necessary to support the safe shutdown method for each FA. The team also reviewed the periodic testing of the alternative shutdown transfer and isolation capability, and instrumentation and control functions, to evaluate whether the tests were adequate to ensure the functionality of the alternative shutdown capability.
 
The team reviewed selected operator manual actions to verify whether they had been  
 
properly reviewed and approved and whether the actions could be implemented in accordance with plant procedures in the time necessary to support the safe shutdown method for each FA. The team also reviewed the periodic testing of the alternative shutdown transfer and isolation capability, and instrumentation and control functions, to evaluate whether the tests were adequate to ensure the functionality of the alternative shutdown capability.


====b. Findings====
====b. Findings====
Line 308: Line 134:
In addition, the team reviewed cable raceway drawings and cable routing databases for a sample of components required for post-fire safe shutdown to determine whether those cables were routed as described in the safe shutdown analysis. The team also reviewed equipment important to safe shutdown, but not part of the success path, to assess whether Entergy's safe shutdown methodologies were appropriate, conformed to design and licensing basis requirements, and appropriately considered the guidance in NRC Regulatory Guide 1.189, "Fire Protection for Nuclear Power Plants," Revision 2.
In addition, the team reviewed cable raceway drawings and cable routing databases for a sample of components required for post-fire safe shutdown to determine whether those cables were routed as described in the safe shutdown analysis. The team also reviewed equipment important to safe shutdown, but not part of the success path, to assess whether Entergy's safe shutdown methodologies were appropriate, conformed to design and licensing basis requirements, and appropriately considered the guidance in NRC Regulatory Guide 1.189, "Fire Protection for Nuclear Power Plants," Revision 2.


Cable failure modes were reviewed for the following components:
Cable failure modes were reviewed for the following components:
 
21CHP, 21 Charging Pump 21CCP, 21 Component Cooling Pump 250A and 4925, 21 Reactor Coolant Pump Seal Water Injection Line Isolation Valves LCV-112C, Volume Control Tank Outlet Isolation Valve LT-417D(427D), Steam Generator 21(22) Level Indicators The team reviewed a sample of circuit breaker and fuse over-current protection coordination studies to determine whether equipment needed for post-fire safe shutdown activities could be adversely affected due to a lack of coordination that could result in a common power supply or common electrical bus concern. The team also evaluated whether coordination studies appropriately considered multiple faults due to fire. In addition, the team reviewed a sample of circuit breaker maintenance records, for components required for safe shutdown, to determine whether the breakers were properly maintained.
21CHP , 21 Charging Pump 21CCP, 21 Component Cooling Pump 250A and 4925, 21 Reactor Coolant Pump Seal Water Injection Line Isolation Valves LCV-112C, Volume Control Tank Outlet Isolation Valve LT-417D(427D), Steam Generator 21(22) Level Indicators The team reviewed a sample of circuit breaker and fuse over-current protection coordination studies to determine whether equipment needed for post-fire safe shutdown activities could be adversely affected due to a lack of coordination that could result in a common power supply or common electrical bus concern. The team also evaluated whether coordination studies appropriately considered multiple faults due to fire. In  
 
addition, the team reviewed a sample of circuit breaker maintenance records, for components required for safe shutdown, to determine whether the breakers were properly maintained.


The team assessed the transfer of control from the main control room to the alternative shutdown location to determine whether it would be adversely affected by fire-induced circuit faults (e.g., by the provision of separate fuses and power supplies for alternative shutdown control circuits).
The team assessed the transfer of control from the main control room to the alternative shutdown location to determine whether it would be adversely affected by fire-induced circuit faults (e.g., by the provision of separate fuses and power supplies for alternative shutdown control circuits).
Line 322: Line 145:


====a. Inspection Scope====
====a. Inspection Scope====
The team reviewed safe shutdown procedures, the safe shutdown analysis, and  
The team reviewed safe shutdown procedures, the safe shutdown analysis, and associated documents to verify an adequate method of communications would be available to plant operators following a fire. During this review, the team considered the effects of ambient noise levels, clarity of reception, reliability, and coverage patterns.
 
associated documents to verify an adequate method of communications would be  


available to plant operators following a fire. During this review, the team considered the
The team also inspected the designated emergency storage lockers to verify the availability of portable radios for the fire brigade and for plant operators. The team also verified that communications equipment such as repeaters and transmitters would not be affected by a fire.
 
effects of ambient noise levels, clarity of reception, reliability, and coverage patterns.
 
The team also inspected the designated emergency storage lockers to verify the  
 
availability of portable radios for the fire brigade and for plant operators. The team also  
 
verified that communications equipment such as repeaters and transmitters would not be  
 
affected by a fire.


====b. Findings====
====b. Findings====
Line 344: Line 155:


====a. Inspection Scope====
====a. Inspection Scope====
The team observed the placement and coverage area of eight-hour emergency lights  
The team observed the placement and coverage area of eight-hour emergency lights throughout the selected FAs to evaluate their adequacy for illuminating access and egress pathways and any equipment requiring local operation or instrumentation monitoring for post-fire safe shutdown. The team also verified that the battery power supplies were rated for at least an eight-hour capacity. Preventive maintenance procedures, the vendor manual, completed surveillance tests, and battery replacement practices were also reviewed to verify that the emergency lighting was being maintained consistent with the manufacturers recommendations and in a manner that would ensure reliable operation.
 
throughout the selected FAs to evaluate their adequacy for illuminating access and  
 
egress pathways and any equipment requiring local operation or instrumentation monitoring for post-fire safe shutdown. The team also verified that the battery power  
 
supplies were rated for at least an eight-hour capacity. Preventive maintenance  
 
procedures, the vendor manual, completed surv eillance tests, and battery replacement practices were also reviewed to verify that the emergency lighting was being maintained  
 
consistent with the manufacturer's recommendations and in a manner that would ensure  
 
reliable operation.


====b. Findings====
====b. Findings====
Line 364: Line 163:


====a. Inspection Scope====
====a. Inspection Scope====
The team reviewed Entergy's dedicated repair procedures for components which might be damaged by fire and were required to achieve post-fire cold shutdown. The team evaluated selected cold shutdown repairs to determine whether they could be achieved  
The team reviewed Entergy's dedicated repair procedures for components which might be damaged by fire and were required to achieve post-fire cold shutdown. The team evaluated selected cold shutdown repairs to determine whether they could be achieved within the time frames assumed in the design and licensing bases. In addition, the team verified whether the necessary repair equipment, tools, and materials (e.g., pre-cut cables with prepared attachment lugs) were available and accessible on site.
 
within the time frames assumed in the design and licensing bases. In addition, the team verified whether the necessary repair equipment, tools, and materials (e.g., pre-cut cables with prepared attachment lugs) were available and accessible on site.


====b. Findings====
====b. Findings====
Line 374: Line 171:


====a. Inspection Scope====
====a. Inspection Scope====
The team verified that compensatory measures were in place for out-of-service, degraded, or inoperable fire protection and post-fire safe shutdown equipment, systems, or features (e.g. detection and suppression systems and equipment; passive fire  
The team verified that compensatory measures were in place for out-of-service, degraded, or inoperable fire protection and post-fire safe shutdown equipment, systems, or features (e.g. detection and suppression systems and equipment; passive fire barriers; or pumps, valves, or electrical devices providing safe shutdown functions or capabilities). The team also verified that the short term compensatory measures compensated for the degraded function or feature until appropriate corrective action could be taken and that Entergy was effective in returning the equipment to service in a reasonable period of time.
 
barriers; or pumps, valves, or electrical dev ices providing safe shutdown functions or capabilities). The team also verified that the short term compensatory measures  
 
compensated for the degraded function or feature until appropriate corrective action  
 
could be taken and that Entergy was effective in returning the equipment to service in a  
 
reasonable period of time.


====b. Findings====
====b. Findings====
Line 390: Line 179:


====a. Inspection Scope====
====a. Inspection Scope====
The team reviewed recent changes to the approved FPP to verify that the changes did  
The team reviewed recent changes to the approved FPP to verify that the changes did     not constitute an adverse effect on the ability to safely shutdown.
 
not constitute an adverse effect on the ability to safely shutdown.


====b. Findings====
====b. Findings====
Line 400: Line 187:


====a. Inspection Scope====
====a. Inspection Scope====
The team reviewed Entergy's procedures and programs for the control of ignition  
The team reviewed Entergys procedures and programs for the control of ignition sources and transient combustibles to assess their effectiveness in preventing fires and in controlling combustible loading within limits established in the FHA. A sample of hot work and transient combustible control permits were also reviewed. The team performed plant walkdowns to verify that transient combustibles and ignition sources were being implemented in accordance with the administrative controls.
 
sources and transient combustibles to assess their effectiveness in preventing fires and  
 
in controlling combustible loading within limits established in the FHA. A sample of hot  
 
work and transient combustible control permits were also reviewed. The team  
 
performed plant walkdowns to verify that transient combustibles and ignition sources  
 
were being implemented in accordance with the administrative controls.


====b. Findings====
====b. Findings====
Line 418: Line 195:


====a. Inspection Scope====
====a. Inspection Scope====
The team conducted a review of selected mitigation strategies intended to maintain or  
The team conducted a review of selected mitigation strategies intended to maintain or restore core decay heat removal and spent fuel pool cooling capabilities under the circumstances associated with the loss of large areas of the plant due to explosions and/or fires. The team assessed whether Entergy continued to meet the requirements of the Indian Point Nuclear Power Station Units 2 and 3 Operating Licenses and 10 CFR 50.54(hh)(2).
 
restore core decay heat removal and spent fuel pool cooling capabilities under the  
 
circumstances associated with the loss of large areas of the plant due to explosions  
 
and/or fires. The team assessed whether Entergy continued to meet the requirements  


of the Indian Point Nuclear Power Station Units 2 and 3 Operating Licenses and 10 CFR
The team reviewed the following mitigation strategies:
 
Unit 3 Makeup to the Spent Fuel Pool with Permanently Installed and Portable Equipment; Unit 3 External Spray; Unit 2 Manual Operation of Steam Generator Atmospheric Dump Valves; and, Unit 2 Makeup to the Steam Generators with the Portable Pump The team's review included: a detailed assessment of the procedural guidance; a tabletop discussion with licensed operators; and a walk down of four mitigation strategies with operators to assess the feasibility of the strategies and operator familiarity, maintenance and surveillance testing of selected strategy equipment, and an inventory check of the B.5.b pump and equipment trailers to ensure the appropriateness of equipment storage and availability.
50.54(hh)(2).
 
The team reviewed the following mitigation strategies:  
 
Unit 3 Makeup to the Spent Fuel Pool with Permanently Installed and Portable Equipment;                                                 Unit 3 External Spray; Unit 2 Manual Operation of Steam Generator Atmospheric Dump Valves; and, Unit 2 Makeup to the Steam Generators with the Portable Pump  
 
The team's review included: a detailed assessment of the procedural guidance; a  
 
tabletop discussion with licensed operators; and a walk down of four mitigation  
 
strategies with operators to assess the feasibility of the strategies and operator  
 
familiarity, maintenance and surveillance testing of selected strategy equipment, and an  
 
inventory check of the B.5.b pump and equipment trailers to ensure the appropriateness  
 
of equipment storage and availability.


====b. Findings====
====b. Findings====
Line 454: Line 208:


====a. Inspection Scope====
====a. Inspection Scope====
The team reviewed a sample of condition reports associated with the FPP, post-fire safe  
The team reviewed a sample of condition reports associated with the FPP, post-fire safe shutdown issues, and mitigation strategy issues to determine whether Entergy was appropriately identifying, characterizing, and correcting problems associated with these areas and whether the planned or completed corrective actions were appropriate.
 
shutdown issues, and mitigation strategy issues to determine whether Entergy was  
 
appropriately identifying, characterizing, and correcting problems associated with these  
 
areas and whether the planned or completed corrective actions were appropriate.


====b. Findings====
====b. Findings====
No findings were identified.
No findings were identified.
 
{{a|4OA6}}
{{a|4OA6}}
==4OA6 Meetings, Including Exit==
==4OA6 Meetings, Including Exit==


The team presented the inspection results to Mr. Anthony J. Vitale, Site Vice President, and other members of the site staff at an exit meeting on December 16, 2016. The team  
The team presented the inspection results to Mr. Anthony J. Vitale, Site Vice President, and other members of the site staff at an exit meeting on December 16, 2016. The team verified that this report does not contain proprietary information.
 
verified that this report does not contain proprietary information.


ATTACHMENT:
ATTACHMENT:  


=SUPPLEMENTARY INFORMATION=
=SUPPLEMENTARY INFORMATION=
Line 479: Line 224:


===Licensee Personnel===
===Licensee Personnel===
J. Balletta Senior Reactor Operator
J. Balletta           Senior Reactor Operator
S. Bianco Fire Brigade Training
S. Bianco             Fire Brigade Training
T. Chan Design Engineer
T. Chan               Design Engineer
G. Dahl Licensing Engineer
G. Dahl               Licensing Engineer
K. Elliot Appendix R Engineer
K. Elliot             Appendix R Engineer
D. Powell Senior Reactor Operator
D. Powell             Senior Reactor Operator
C. Wilson Fire Protection Engineer  
C. Wilson             Fire Protection Engineer
 
NRC
NRC
: [[contact::B. Haagensen           Senior Resident Inspector]], Indian Point
: [[contact::B. Haagensen Senior Resident Inspector]], Indian Point  
: [[contact::S. Rich               Resident Inspector]], Indian Point
: [[contact::S. Rich   Resident Inspector]], Indian Point
: [[contact::C. Safouri             Acting Resident Inspector]], Indian
: [[contact::C. Safouri Acting Resident Inspector]], Indian  


==LIST OF ITEMS OPENED, CLOSED, AND DISCUSSED==
==LIST OF ITEMS OPENED, CLOSED, AND DISCUSSED==
Line 496: Line 240:
===Opened===
===Opened===


NONE
NONE


===Opened and Closed===
===Opened and Closed===


NONE
NONE


===Closed===
===Closed===
: NONE  
 
NONE


===Discussed===
===Discussed===


NONE  
NONE


==LIST OF DOCUMENTS REVIEWED==
==LIST OF DOCUMENTS REVIEWED==
Fire Protection Licensing Documents Indian Point Nuclear Generating Unit No. 2, Amended Facility Operating License, 9/28/73
: IP2
: EN-DC-330, Indian Point Nuclear Generating Unit No. 2, Fire Protection Program, Revision 4
: IP2 UFSAR, Revision 26
: IP2-RPT-03-00015, IP2 Fire Hazards Analysis, Revision 7
: IP-RPT-04-00224, NFPA Code of Record Determination for Indian Point Unit 2 Fire Protection
: Design Basis Documents and Specifications
: IP2-DBD-221, IP2 Design Basis Document for Fire Protection System, Revision 3
: Calculations/Engineering Evaluation Reports
: 247-09-0013.024, IP2 Nuclear Power Plant Fire Probabilistic Risk Assessment, Multiple Spurious Operations Report, Revision 0
: CE-PS 100-79, Fireproofing of Diesel Generator Bldg., Revision 0
: FEX-00246-00, Evaluation of PAB Fire Protection Line at EL. 80' Due to Potential Flooding of
: RHR Pump Cells at
: EL 15', Revision 0
: IP2-RPT-03-00010, 3M INTERAM Fire-Resistant Enclosure at Electrical Penetration H20 &
: Response to NRC Information Notice 95-52, Supplement 1, Revision 1
: IP3-CALC-CVCS-393, Calculation of Allowable Time for Operating Charging Pumps Without Cooling Water, Revision 1
: IP-CALC-04-01171, the Hydraulic Analysis of Indian Point Unit 1 and Unit 2 Fire Protection Water
: Supply Systems and Several Unit 2 Suppression Systems, Revision 0
: IP-CALC-08-00024, Sizing Calculation for RHR Pump Flooding Line, Revision 0
: IP-RPT-04-00188, Evaluation of Hemyc Wrap Fire Protective Systems, Revision 1
: IP-RPT-05-00071, IP2 10
: CFR 50, Appendix R Safe-Shutdown Separation Analysis, Revision 2
: IP-RPT-09-00012, Validation of Operator Manual Actions Credited for Appendix R, Section
: III.G
: Fire Areas: IP2 and IP3, Revision 0
: IP-RPT-12-00022, Inaccessible Fire Barrier Penetration Seals, Revision 0
: PGI-00355, NRC Information Notice 92-18 MOV Control Hot Short Issue, Revision 4
: PGI-00581-00, Fire Protection 86-10 Evaluation for EDG Structural Steel Fire Resistant Coating, Revision 0
: SGX-00048-01, 480V Switchgear Coordination Calculation for Switchgears 21 and 22, Revision 1
: Engineering Change Requests (ECR)
: EC-40404, Relocate 21 Charging Pump Control Switch from 480V switchgear to the CCR and Install Solenoid and its control in CCR to Resolve U2-OMA-20 and 21, 3/24/14
: EC-41582, OMA Resolution:
: OMA-6, 4/07/14
: EC-42090, Resolve OMA 9 and 10, Support Safe Shutdown Instrument Indication in IP2 CCR,
: 3/24/14
: EC-45124, Update EP & Operations Communication to Address Fukushima FLEX
: Requirements in
: NEI 12-01, Revision 0
: EC-50149, FLEX Electrical EC for Phase 2, Revision 0
: FPX-93-09146-F, Removal of Thermal Lag Fire Barrier from RHR Pump 22 Feeder, dated
: 5/9/94 
: Fire Barrier Tests
: CTP 1001A, Three Hour Fire Qualification Test, 7/25/80
: CTP 1076, Three Hour Fire Qualification Test, 3/28/85
: CTP 1098A, Three Hour Fire Qualification Test, 8/11/86
: CTP 2005/CTP 2008, Fire Endurance Test of 3M INTERAM Mat Fire Protective Envelopes, 11/12/98 
: Piping and Instrumentation Diagrams
: 21-F-2018, Flow Diagram Condensate & Boiler Feed Pump Suction, Revision 148
: 21-F-2019, Boiler Feedwater Flow Diagram, Revision 118
: 21-F-2036, Flow Diagram Instrument Air Control Bldg. Conventional Plant, Etc., Revision 101
: 21-F-2720, Auxiliary Coolant Syst em Flow Diagram, Revision 92
: 21-F-2722, Service Water System Flow Diagram, Revision 128 
: 9321-F-2736, CVCS Flow Diagram, Revision 130
: 21-F-2738, Reactor Coolant System Flow Diagram, Revision 122 
===Drawings===
and Wiring Diagrams
: 25151, Elementary Wiring Diagram of Component Cooling Pump 23, Revision 15
: 260430, Loop Diagram Reactor Coolant System, Pressurizer Level Control, Revision 3
: 260510, Loop Diagram Feedwater
: SG 21 Wide Range Level, Revision 6
: 260511, Loop Diagram Feedwater
: SG 22 Wide Range Level, Revision 6
: 400400-05, Fire Area/Zone Arrangement Site Plan, Revision 2
: 400402, Fire Area/Zone Arrangement at EL. 36', Revision 3
: 400403-05, Fire Area/Zone Arrangement at EL. 53', Revision 5
: 400404-04, Fire Area/ Zone arrangement at
: EL 80', Revision 4
: 400405-02, Fire Area/Zone Arrangement at EL. 98', Revision 2
: 503797, Elementary Wiring Diagram for Charging Pump 21, Revision 0
: 503802, IP2 PAB, EL. 98' Valve
: LCV-112C Fire Enclosure Plan & Sections, Civil, Revision 0
: 21-F-3008, Single Line Diagram DC Power Panels, Revision 92
: 21-F-4006-78, Yard Fire Protection Piping, Revision 78
: A208088, One Line Diagram of 480Vac Switchgear 21 and 22, Revision 44
: A208377, Main One Line Diagram, Revision 17
: A208831, Schematic Diagram for Post-Accident
: MOV 250A, Revision 4
: A208832, Schematic Diagram for Post-Accident
: MOV 4925, Revision 7
: A227551-66, Sht. 1, Fire Protection System Diagram Details, Revision 66
: A227552-47, Sht. 2, Fire Protection System Diagram Details, Revision 47
: A227553-51, Sht. 3, Fire Protection System Diagram Detail, Revision 51
: A227554-27, Sht. 4, Fire Protection System Diagram Detail, Revision 27
: A231592, 6900Vac One Line Diagram, Revision 19
: A240128, Boiler Feedwater Level and Flow Instrumentation SG's 21 thru 24, Revision 5
: B192477-3, Flow Diagram Piping & Instrumentation Symbols, Revision 0
: B225115, Sht. 9, Elementary Wiring Diagram Switch Development, Revision 3
: B225133, Elementary Wiring Diagram on Component Cooling Pump 21, Revision 14
: B228010-04, Fire Barrier Penetrations Diesel Generator Building, Wall 1032A-W, 12/17/03
: B228016-05, Fire Barrier Penetrations Charging Pump Rooms, PAB Wells 7A/5-N, 7A/6-N,
: 7A/7-N, 12/17/03
: B228050-06, Fire Barrier Penetration Schedule Walls 7A/5-N, 7A/6-N, 7A/7-N, 12/17/03
: B228053-05, Fire Barrier Penetration Schedule Walls 14/ST3-S, 14/43A-W, 10/32A-W,
: 2/17/03
: IP2-S-000255, Elementary Wiring Diagram VCT Drain MOV
: LCV-112C, Revision 3 
===Procedures===
: 0-PT-M002, Alternate Safe Shutdown Equipment Inventory and Inspection, Revision 16
: 0-PT-Q001, Alternate Safe Shutdown Equipment Inventory and Inspection, Revision 13
: 2-AOP-SSD-1, Control Room Inaccessibility Safe Shutdown Control, Revision 23
: 2BRK-021-CUB, Westinghouse 480V DB Series Breaker Cubicle Inspection and Cleaning, Revision 5
: 2-BRK-023-ELC, DB Breaker Amptector Overcurrent Test, Revision 6
: 2-BRK-024-ELC, DB Breaker Amptector Calibration Test, Revision 3
: 2-COL-3.1, Chemical and Volume Control System, Revision 43
: 2-ELC-004-FIR, IP2 Repairs for Safe Shutdown in the Event of an Appendix R Fire, Revision 2
: 2-IC-PC-I-L-417, 21 SG Wide Range Level Calibration, Revision 2
: 2-IC-PC-I-L-417, 21 SG Wide Range Level Calibration, Revision 3
: 2-IC-PC-I-L-427, 22 SG Wide Range Level Calibration, Revision 2
: 2-PC-R3-1, Pressurizer Level Transmitters, Revision 8 
: 2-PC-R37, Alternate Safe Shutdown and Remote Shutdown Instruments, Revision 13
: 2-PT-2Y042, 21 CHP Central Control Room Station Switches, Revision 1
: 2-PT-Q017A, Alternate Safe Shutdown Supply Verification to 21 AFP, Revision 13
: 2-PT-Q017B, Alternate Safe Shutdown Supply Verification to 23 CHP, Revision 11
: 2-PT-Q017C, Alternate Safe Shutdown Supply Verification to 23 CCP, Revision 17
: 2-PT-Q017D, Alternate Safe Shutdown Supply Verification to 23 SWP, Revision 11
: 2-PT-Q017E, Alternate Safe Shutdown Supply Verification to 24 SWP, Revision 11
: 2-PT-Q017F, Alternate Safe Shutdown Supply Verification to 21 Safety Injection and Residual Heat Removal Pumps, Revision 9
: EN-DC-127, Control of Hot Work and Ignition Sources, Revision 15
: EN-DC-128, Fire Protection Impact Reviews, Revision 10
: EN-DC-161, Control of Combustibles, Revision 13
: EN-DC-186, Fuse Control, Revision 2
: EN-DC-330, Fire Protection Program, Revision 4
: SAO-703, Fire Protection Impairment Criteria and Surveillance, Revision 35
: SEP-FPP-IP-001, IPEG Fire Protection Program, Revision 4
: SEP-FPP-IP-002, IPEG Fire Watch Program, Revision 2
: Operations Procedures
: 2-AOP-SSD-1, Control Room Inaccessibility Safe Shutdown Control, Revision 23
: 2-ONOP-FP-001, Plant Fires, Revision 17
: 2-SOP-ESP-001, Local Equipment Operation and Contingency Actions, Revision 12
: Operator Safe Shutdown Training
: IOLP-LOR-AOP010, 2/3-AOP-SSD-1, Control Room Inaccessibility Safe Shutdown Control, Revision 1
: OPEX Reviews
: OE-NOE-2015-30
: CA-14,
: IN 2015-02, Antifreeze Agents in Fire Water Sprinkler Systems
: Quality Assurance Audits and Self Assessments
: QA-9-2016-IP-1, Fire Protection, Revision 6
: System Health Reports
: 480Vac Systems, 1
st and 3 rd Qtr. 2016
: IPEG Fire Protection, 2
nd Quarter 2016
: IPEG Fire Protection, 3
rd Quarter 2016
: Completed Tests, Surveillances, and Preventive Maintenance
: 0-ELC-420-FIR, Appendix R Emergency Light Unit Inspection, Battery Replacement, and test, Completed on 2/15/16 and 11/3/16
: 0-PT-M001, Fire Brigade Equipment Inventory and Inspection, Completed11/6/16 and 12/3/16
: 2-PT-2Y017, Penetration Fire Barrier Seal Inspection, Completed 10/12/12 and 12/14/14
: 2-PT-2Y041, Fire Damper Functionality, Completed 6/12/12 and 4/6/15
: 2-PT-3Y015A, Underground Fire Loop Flow, Completed 10/24/11 and 7/12/15
: 2-PT-3Y015B, Turbine Building Fire Loop Flow, 5/17/11 and 7/27/14
: 2-PT-A023, Fire Main Booster Pump capacity Test, Completed 4/08/14 and 8/13/15
: 2-PT-A040, Diesel Driven Fire Pump Capacity, Completed on 2/15/15 and 2/14/16
: 2-PT-A048, Rollup Fire Doors, Completed 9/8/15 and 10/17/16
: 2-PT-A057, U1 Smoke Detector Test, Completed 9/30/14 and 9/28/15
: 2-PT-M034A, 11 Fire Main Booster Pump, Completed on 7/28/16 and 8/24/16
: 2-PT-M034B, 12 Fire Main Booster Pump, Completed on 7/28/16, 8/24/16, and 9/22/16 
: 2-PT-M040, Diesel Fire Pump, Completed on 9/11/16 and 10/17/16
: 2-PT-M049B, Appendix R Emergency Lighting (Nuclear), Completed on 9/23/16 and 10/15/16
: 2-PT-SA012D, Ionization Type Smoke Detector (PAB-Specific), Completed 4/18/16 and 9/26/16
: 2-PT-SA012D, Ionization Type Smoke Detectors (PAB), Completed 11/19/15
: 2-PT-SA020, Swing Fire Doors, Completed 4/18/16 and 9/26/16
: PT-EM9, Fire Dampers Operability, Completed 5/1/14 and 1/6/16
: PT-SA11, Diesel Generator Building Fire Detection System, Completed 1/15/16 and 8/16/16
: PT-SA12A, Ionization Type Smoke Detector (Conventional), Completed 2/9/16 and 7/19/16
: PT-SA12B, Ionization Type Smoke Detector (PAB), Completed 2/11/16 and 9/22/16
: PT-SA17, CCR Intake Smoke Detectors and Ventilation Control, Completed 1/15/16 and
: 8/26/16
: Transient Combustible Evaluations
: 16-046, SFP Equipment Area, 10/3/16
: 16-044, AFW Pump Room, 10/8/16
: 16-045, AFW Building 2
nd Elevation, 10/9/16
: 16-047, U2 AFW Pump Room, 10/17/16
: 16-048, Fan House/PAB Annex, 10/19/16
: Hot Work Permits
: 279749, U2, Turbine Bldg. 15' Col. 9 Line B-7, 9/15/16
: 297947, U2, Turbine Bldg. 33' Col. 3 Line B, 9/15/16
: 2864, U2, Telecom Room 15', 9/26/16
: 309854, U1,
: FP-1 Elbow (Tool Room) EL. 15', 10/26/16
: Fire Fighting Strategies (i.e., Pre-Fire Plans)
: PFP-211, General Floor Plan - Primary Auxiliary Building 80'EL., Revision 14
: PFP-212, General Floor Plan - Primary Auxiliary Building 98' EL., Revision 14
: PFP-253, Control Room - Control Building, Revision 13
: PFP-258, EDG #21-#22-#23-Diesel Generator Building/Electrical Tunnel Exhaust Fans, Revision 5
: Fire Brigade Training
: I0LP-OPS-FBT003, Fire Brigade Leadership (Initial/Retraining), 9/9/16
: Initial Fire Brigade Training Manual, 2016
: I0LP-OPS-FBT003, Fire Brigade Annual Retraining, 8/16
: I0LP-OPS-FBT003, Fire Brigade Annual Retraining, 12/16
: Fire Brigade Drills and Critiques
: U1 TB Appendix R EDG, 9/17/16
: U2 Dock Diesel Storage Tank, 9/14/16
: U2 Dryden Diving Trailers, 9/14/16
: U3 NLW Chem. App., 9/18/16
: U3 MBFPL0 Purifier, 9/25/16
: U3 Area 15' Water Factory, 11/1/16
: Large Fires and Explosions Mitigation Strategies Documents
: 0-AOP-SEC-3, Event Contingency Actions, Revision 3
: 0-SOP-ESP-002, Emergency Contingency Plan, Revision 12
: 0-SOP-ESP-003, Emergency Contingency Plant Strategy Attachments, Revision 1
: 2-SOP-ESP-001, Local Equipment Operations and Contingency Actions, Revision 4
: 3-SOP-ESP-001, Local Equipment Operations and Contingency Actions, Revision 9 
: Corrective Action Program [Condition Reports (CR)]
: CR-IP2-2004-00609
: CR-IP2-2007-00719
: CR-IP2-2010-03184
: CR-IP2-2014-00128
: CR-IP2-2014-00528
: CR-IP2-2014-00904
: CR-IP2-2014-01970
: CR-IP2-2015-00483
: CR-IP2-2015-01702
: CR-IP2-2015-03333
: CR-IP2-2015-04087
: CR-IP2-2016-00458
: CR-IP2-2016-00517
: CR-IP2-2016-00699
: CR-IP2-2016-01146
: CR-IP2-2016-02710
: CR-IP2-2016-03052
: CR-IP2-2016-03209
: CR-IP2-2016-03554
: CR-IP2-2016-05139
: CR-IP2-2016-05584
: CR-IP2-2016-06527
: CR-IP2-2016-06584
: CR-IP2-2016-06637
: CR-IP2-2016-06650
: CR-IP2-2016-06674
: CR-IP2-2016-06737
: CR-IP2-2016-06828
: CR-IP2-2016-06977
: CR-IP2-2016-06593*
: CR-IP2-2016-06844*
: CR-IP2-2016-07028*
: CR-IP2-2016-07048*
: CR-IP2-2016-07049*
: CR-IP2-2016-07050*
: CR-IP2-2016-07074*
: CR-IP2-2016-07077*
: CR-IP2-2016-07078*
: CR-IP2-2016-07082*
: CR-IP2-2016-07092*
: CR-IP2-2016-07094*
: CR-IP2-2016-07105*
: CR-IP2-2016-07233*
: CR-IP2-2016-07310*
: CR-IP2-2016-07316*
: CR-IP2-2016-07317*
: CR-IP2-2016-07320*
: CR-IP2-2016-07322*
: CR-IP2-2016-07323*
: CR-IP2-2016-07340*
*NRC identified during this inspection.
===Work Orders===
: 00224629
: 00339098
: 00340641
: 00340644
: 00340653
: 50065602
: 51498409
: 51503416
: 2309599
: 52309622
: 52310161
: 52429908
: 2448198
: 52458897
: 52474186
: 52477866
: 2501024
: 52527196
: 52537922
: 52541985
: 2556636
: 52560550
: 52582200
: 52587735
: 2624553
: 52638317
: 52638848
: 52639020
: 2640117
: 52643882
: 52644044
: 52649255
: 2654544
: 52663061
: 52672476
: 52672477
: 2677506
: 52677933
: 52677934
: 52690147
: 2695005
: 52696115
: 52697773
: 52699588
: 2704374
: 52706670
: 52706673
: 52713556
: 2721451
: 52727166 
===Miscellaneous Documents===
: 10/32A-W001, IP2 Type 1, Fire Barrier Penetration Seal Index 9 PAB)
: 10/32A-W002, IP2 Type 1 Fire Barrier Penetration Seal Index (Diesel Generator Building)
: CE-PS 100-79, Fireproofing of Diesel Generator Bldg., 6/21/79
: Daily Plant status report, 11/29/16
: Fire Protection System Impairment Summary Unit 2, Dated 11/01/16
: Indian Point Unit 2 Fire Impairment Log, 11/1/16
: IP2 Post-Fire Safe Shutdown OMA Timeline Validations on 12/18/12, 5/14/13, and 5/16/13
: IPEG Radio System Summary Description, 2016
: OAP, Operations Commitments and Policy Details, Revision 26
==LIST OF ACRONYMS==


CFR Title 10 of the
Code of Federal Regulations
: [[DRS]] [[Division of Reactor Safety]]
: [[FA]] [[Fire Area]]
: [[FHA]] [[Fire Hazards Analysis]]
: [[FPP]] [[Fire Protection Program]]
: [[FZ]] [[Fire Zone]]
: [[IP]] [[Inspection Procedure]]
: [[NFPA]] [[National Fire Protection Association]]
: [[NRC]] [[Nuclear Regulatory Commission,]]
: [[U.S.]] [[]]
: [[UFSAR]] [[Updated Final Safety Analysis Report]]
}}
}}

Latest revision as of 18:32, 19 December 2019

Triennial Fire Protection Inspection Report 05000247/2016007
ML17006A254
Person / Time
Site: Indian Point Entergy icon.png
Issue date: 01/06/2017
From: Glenn Dentel
Engineering Region 1 Branch 2
To: Vitale A
Entergy Nuclear Operations
Dentel G
References
IR 2016007
Download: ML17006A254 (21)


Text

ary 6, 2017

SUBJECT:

INDIAN POINT NUCLEAR GENERATING UNIT 2 - TRIENNIAL FIRE PROTECTION INSPECTION REPORT 05000247/2016007

Dear Mr. Vitale:

On December 16, 2016, the U.S. Nuclear Regulatory Commission (NRC) completed a triennial fire protection inspection at your Indian Point Nuclear Generating Unit 2 and discussed the results of this inspection with you and other members of your staff. The results of this inspection are documented in the enclosed report.

The inspection examined activities conducted under your license as they relate to safety and compliance with the Commission's rules and regulations, and with the conditions of your license. The inspectors reviewed selected procedures and records, observed activities, and interviewed station personnel. The inspectors also reviewed mitigation strategies for addressing large fires and explosions.

Based on the results of this inspection, no findings were identified. This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with 10 CFR 2.390, Public Inspections, Exemptions, Requests for Withholding.

Sincerely,

/RA/

Glenn T. Dentel, Chief Engineering Branch 2 Division of Reactor Safety Docket No. 50-247 License No. DPR-26 Enclosure:

Inspection Report 05000247/2016007 w/Attachment: Supplementary Information cc w/encl: Distribution via ListServ

SUMMARY

IR 05000247/2016007; 11/28/2016 - 12/16/2016; Indian Point Nuclear Generating Unit 2;

Triennial Fire Protection Inspection.

This report covered a two week on-site triennial fire protection team inspection by specialist inspectors. The NRCs program for overseeing the safe operation of commercial nuclear power reactors is described in NUREG-1649, Reactor Oversight Process, Revision 6, dated July 2016.

No findings were identified.

REPORT DETAILS

Background This report presents the results of a triennial fire protection inspection conducted in accordance with NRC Inspection Procedure (IP) 71111.05T, Fire Protection. An objective of the inspection was to assess whether Entergy Nuclear Operations, Inc. (Entergy) has implemented an adequate fire protection program and that post-fire safe shutdown capabilities have been established and are being properly maintained at the Indian Point Nuclear Generating Unit 2 (IP2). The following fire areas (FA) and associated fire zones (FZ) were selected for detailed review based on prior inspection results and risk insights from the IP2 Individual Plant Examination of External Events:

Fire Area / Fire Zone FZ 15 Main Control Room FZ 10 Diesel Generator Building FA F PAB Corridor 80 & 98 and Fan House 89 Inspection of these FAs/FZs fulfilled the IP requirement to inspect a minimum of three samples.

The inspectors evaluated Entergys fire protection program (FPP) against applicable requirements which included Unit 2 Operating License Conditions 2.K. and 2.N., Unit 3 Operating License Condition 2.AC., NRC Safety Evaluations, Title 10 of the Code of Federal Regulations (10 CFR) 50.48, and 10 CFR 50, Appendix R. The inspectors also reviewed related documents that included the Updated Final Safety Analysis Report (UFSAR), the Fire Protection Program Plan, the Fire Hazards Analysis (FHA), and the Safe Shutdown Analysis Report.

The team evaluated aspects of three mitigating strategies for responding to large fires and explosions, which are required by Operating License Condition 2.N for Unit 2, Operating License Condition 2.AC for Unit 3, and 10 CFR 50.54(hh)(2). The team also reviewed related documents that included Nuclear Energy Institute 06-12, "B.5.b Phases 2 & 3 Submittal Guidance," Revision 2 (ML070090060). Inspection of these strategies fulfills the IP requirement to inspect a minimum of one sample.

Documents reviewed for each section of this report are listed in the Attachment.

REACTOR SAFETY

Cornerstones: Initiating Events, Mitigating Systems, and Barrier Integrity

1R05 Fire Protection (IP 71111.05T)

.01 Protection of Safe Shutdown Capabilities

a. Inspection Scope

The team reviewed the FHA, post-fire safe shutdown analyses, and supporting drawings and documents to verify whether the safe shutdown capabilities were properly protected from fire damage. The team evaluated equipment and cable separation to determine whether the applicable separation requirements of Appendix R,Section III.G, and the IP2 design and licensing bases were maintained for the credited safe shutdown equipment and their supporting power, control, and instrumentation cables. The team's review included an assessment of the adequacy of the selected systems for reactor pressure control, reactivity control, reactor coolant makeup, decay heat removal, process monitoring, and associated support system functions.

b. Findings

No findings were identified.

.02 Passive Fire Protection

a. Inspection Scope

The team walked down accessible portions of the selected FAs to evaluate whether the material conditions of the FA boundaries were adequate for the fire hazards in the area.

The team compared the FA boundaries, including walls, ceilings, floors, fire doors, fire dampers, penetration seals, electrical raceway and conduit fire barriers, and redundant equipment fire barriers to design and licensing basis requirements, industry standards, and the IP2 FPP, as approved by the NRC, to identify any potential degradation or non-conformances.

The team reviewed selected engineering evaluations, installation and repair work orders, and qualification records for a sample of penetration seals to determine whether the fill material was properly installed and whether the as-left configuration satisfied design requirements for the intended fire rating. The team also reviewed similar records for selected fire protection wraps and an encapsulation system to verify whether the material and configuration was appropriate for the required fire rating and conformed to the engineering design.

The team also reviewed recent inspection records and functional test procedures for fire dampers, and the inspection records for penetration seals and fire barriers, to verify whether the inspection was adequately conducted, the acceptance criteria were met, and any potential performance degradation was identified.

b. Findings

No findings were identified.

.03 Active Fire Protection

a. Inspection Scope

The team evaluated manual and automatic fire suppression and detection systems in the selected FAs to determine whether they were installed, tested, maintained, and operated in accordance with NRC requirements, National Fire Protection Association (NFPA) codes of record, and the IP2 FPP, as approved by the NRC. The team also assessed whether the suppression systems capabilities were adequate to control and/or extinguish fires associated with the hazards in the selected areas.

The team reviewed the as-built capability of the fire water supply system to verify the design and licensing basis and NFPA code of record requirements were satisfied, and to assess whether those capabilities were adequate for the hazards involved. The team reviewed the fire water system hydraulic analyses to assess the adequacy of a single fire water pump to supply the largest single hydraulic load on the fire water system plus concurrent fire hose usage. The team evaluated the fire pump performance tests to assess the adequacy of the test acceptance criteria for pump minimum discharge pressure at the required flow rate, to verify the criteria was adequate to ensure that the design basis and hydraulic analysis requirements were satisfied. The team also evaluated the underground fire loop flow tests to verify the tests adequately demonstrated that the flow distribution circuits were able to meet design basis requirements. In addition, the team reviewed recent pump and loop flow test results to verify the testing was adequately conducted, the acceptance criteria were met, and any potential performance degradation was identified.

The team walked down accessible portions of the detection and water suppression systems in the selected areas and major portions of the fire water supply system, including motor and diesel driven fire pumps, interviewed system and program engineers, and reviewed condition reports to independently assess the material condition of the systems and components. In addition, the team reviewed recent test results for the fire detection and suppression systems for the selected FAs to verify the testing was adequately conducted, the acceptance criteria were met, and any performance degradation was identified.

The team assessed the fire brigade capabilities by reviewing training, qualification, and drill critique records. The team also reviewed Entergy's fire-fighting strategies (i.e., pre-fire plans) and smoke removal plans for the selected FAs to determine if appropriate information was provided to fire brigade members and plant operators to identify safe shutdown equipment and instrumentation, and to facilitate suppression of a fire that could impact post-fire safe shutdown capability. The team independently inspected the fire brigade equipment, including personnel protective gear (e.g., turnout gear) and smoke removal equipment, to determine operational readiness for fire-fighting. In addition, the team reviewed Entergy's fire brigade equipment inventory and recent inspection and inventory results to verify adequate equipment was available, and any potential material deficiencies were identified.

b. Findings

No findings were identified.

.04 Protection from Damage from Fire Suppression Activities

a. Inspection Scope

The team performed document reviews and plant walkdowns to verify that redundant trains of systems required for hot shutdown, which are located in the same FA, are not subject to damage from fire suppression activities or from the rupture or inadvertent operation of fire suppression systems. Specifically, the team verified that:

A fire in one of the selected FAs would not indirectly, through production of smoke, heat or hot gases, cause activation of suppression systems that could potentially damage all redundant safe shutdown trains; A fire in one of the selected FAs (or the inadvertent actuation or rupture of a fire suppression system) would not indirectly cause damage to all redundant trains (e.g. sprinkler caused flooding of other than the locally affected train); and, Adequate drainage is provided in areas protected by water suppression systems.

b. Findings

No findings were identified.

.05 Alternative Shutdown Capability

a. Inspection Scope

The team reviewed the safe shutdown analysis, operating procedures, piping and instrumentation drawings, electrical drawings, the UFSAR, and other supporting documents for the selected FAs to determine whether Entergy had properly identified the systems and components necessary to achieve and maintain post-fire safe shutdown conditions. The team evaluated selected systems and components credited by the safe shutdown analysis for reactor pressure control, reactivity control, reactor coolant makeup, decay heat removal, process monitoring, and support system functions to assess the adequacy of Entergy's alternative shutdown methodology. The team also assessed whether alternative post-fire shutdown could be performed both with and without the availability of off-site power. The team walked down selected plant configurations to verify whether they were consistent with the assumptions and descriptions in the safe shutdown and the FHA. In addition, the team evaluated whether the systems and components credited for use during post-fire safe shutdown would remain free from fire damage.

The team reviewed the training program for licensed and non-licensed operators to verify whether it included alternative shutdown capability. The team also verified whether personnel, required for post-fire safe shutdown, using either the normal or alternative shutdown methods, were trained and available on-site at all times, exclusive of those assigned as fire brigade members.

The team reviewed the adequacy of procedures utilized for post-fire shutdown and performed an independent walk through of procedure steps (i.e., a procedure tabletop)to assess the adequacy of implementation and human factors within the procedures.

The team also evaluated the time required to perform specific actions to verify whether operators could reasonably be expected to perform those actions within sufficient time to maintain plant parameters within specified limits.

Specific procedures reviewed for normal and alternative post-fire shutdown included:

2-AOP-SSD-1, Control Room Inaccessibility Safe Shutdown Control, Revision 23; 2-ONOP-FP-001, Plant Fires, Revision 17; and, 2-SOP-ESP-001, Local Equipment Operation and Contingency Actions, Revision 12.

The team reviewed selected operator manual actions to verify whether they had been properly reviewed and approved and whether the actions could be implemented in accordance with plant procedures in the time necessary to support the safe shutdown method for each FA. The team also reviewed the periodic testing of the alternative shutdown transfer and isolation capability, and instrumentation and control functions, to evaluate whether the tests were adequate to ensure the functionality of the alternative shutdown capability.

b. Findings

No findings were identified.

.06 Circuit Analysis

a. Inspection Scope

The team reviewed Entergy's post-fire safe shutdown analysis for the selected FAs to determine whether the analysis identified both required and associated electrical circuits and cables for the systems and components necessary to achieve and maintain safe shutdown. The team reviewed electrical schematics and cable routing data for power, control, and instrumentation associated with selected components. Specifically, the team evaluated the selected circuits and cables to determine whether they were

(a) adequately protected from potential fire damage, or
(b) analyzed to show that fire-induced faults (e.g., hot shorts, open circuits, and shorts to ground) would not prevent safe shutdown, or
(c) analyzed to show that potential damage could be mitigated with approved operator manual actions, in order to determine whether fire-induced faults could adversely impact safe shutdown capabilities. The team's evaluations considered credible fire scenarios, cable insulation attributes, cable failure modes, cable routing, and common power supply or electrical bus configurations.

In addition, the team reviewed cable raceway drawings and cable routing databases for a sample of components required for post-fire safe shutdown to determine whether those cables were routed as described in the safe shutdown analysis. The team also reviewed equipment important to safe shutdown, but not part of the success path, to assess whether Entergy's safe shutdown methodologies were appropriate, conformed to design and licensing basis requirements, and appropriately considered the guidance in NRC Regulatory Guide 1.189, "Fire Protection for Nuclear Power Plants," Revision 2.

Cable failure modes were reviewed for the following components:

21CHP, 21 Charging Pump 21CCP, 21 Component Cooling Pump 250A and 4925, 21 Reactor Coolant Pump Seal Water Injection Line Isolation Valves LCV-112C, Volume Control Tank Outlet Isolation Valve LT-417D(427D), Steam Generator 21(22) Level Indicators The team reviewed a sample of circuit breaker and fuse over-current protection coordination studies to determine whether equipment needed for post-fire safe shutdown activities could be adversely affected due to a lack of coordination that could result in a common power supply or common electrical bus concern. The team also evaluated whether coordination studies appropriately considered multiple faults due to fire. In addition, the team reviewed a sample of circuit breaker maintenance records, for components required for safe shutdown, to determine whether the breakers were properly maintained.

The team assessed the transfer of control from the main control room to the alternative shutdown location to determine whether it would be adversely affected by fire-induced circuit faults (e.g., by the provision of separate fuses and power supplies for alternative shutdown control circuits).

b. Findings

No findings were identified.

.07 Communications

a. Inspection Scope

The team reviewed safe shutdown procedures, the safe shutdown analysis, and associated documents to verify an adequate method of communications would be available to plant operators following a fire. During this review, the team considered the effects of ambient noise levels, clarity of reception, reliability, and coverage patterns.

The team also inspected the designated emergency storage lockers to verify the availability of portable radios for the fire brigade and for plant operators. The team also verified that communications equipment such as repeaters and transmitters would not be affected by a fire.

b. Findings

No findings were identified.

.08 Emergency Lighting

a. Inspection Scope

The team observed the placement and coverage area of eight-hour emergency lights throughout the selected FAs to evaluate their adequacy for illuminating access and egress pathways and any equipment requiring local operation or instrumentation monitoring for post-fire safe shutdown. The team also verified that the battery power supplies were rated for at least an eight-hour capacity. Preventive maintenance procedures, the vendor manual, completed surveillance tests, and battery replacement practices were also reviewed to verify that the emergency lighting was being maintained consistent with the manufacturers recommendations and in a manner that would ensure reliable operation.

b. Findings

No findings were identified.

.09 Cold Shutdown Repairs

a. Inspection Scope

The team reviewed Entergy's dedicated repair procedures for components which might be damaged by fire and were required to achieve post-fire cold shutdown. The team evaluated selected cold shutdown repairs to determine whether they could be achieved within the time frames assumed in the design and licensing bases. In addition, the team verified whether the necessary repair equipment, tools, and materials (e.g., pre-cut cables with prepared attachment lugs) were available and accessible on site.

b. Findings

No findings were identified.

.10 Compensatory Measures

a. Inspection Scope

The team verified that compensatory measures were in place for out-of-service, degraded, or inoperable fire protection and post-fire safe shutdown equipment, systems, or features (e.g. detection and suppression systems and equipment; passive fire barriers; or pumps, valves, or electrical devices providing safe shutdown functions or capabilities). The team also verified that the short term compensatory measures compensated for the degraded function or feature until appropriate corrective action could be taken and that Entergy was effective in returning the equipment to service in a reasonable period of time.

b. Findings

No findings were identified.

.11 Review and Documentation of FPP Changes

a. Inspection Scope

The team reviewed recent changes to the approved FPP to verify that the changes did not constitute an adverse effect on the ability to safely shutdown.

b. Findings

No findings were identified.

.12 Control of Transient Combustibles and Ignition Sources

a. Inspection Scope

The team reviewed Entergys procedures and programs for the control of ignition sources and transient combustibles to assess their effectiveness in preventing fires and in controlling combustible loading within limits established in the FHA. A sample of hot work and transient combustible control permits were also reviewed. The team performed plant walkdowns to verify that transient combustibles and ignition sources were being implemented in accordance with the administrative controls.

b. Findings

No findings were identified.

.13 Large Fires and Explosions Mitigation Strategies

a. Inspection Scope

The team conducted a review of selected mitigation strategies intended to maintain or restore core decay heat removal and spent fuel pool cooling capabilities under the circumstances associated with the loss of large areas of the plant due to explosions and/or fires. The team assessed whether Entergy continued to meet the requirements of the Indian Point Nuclear Power Station Units 2 and 3 Operating Licenses and 10 CFR 50.54(hh)(2).

The team reviewed the following mitigation strategies:

Unit 3 Makeup to the Spent Fuel Pool with Permanently Installed and Portable Equipment; Unit 3 External Spray; Unit 2 Manual Operation of Steam Generator Atmospheric Dump Valves; and, Unit 2 Makeup to the Steam Generators with the Portable Pump The team's review included: a detailed assessment of the procedural guidance; a tabletop discussion with licensed operators; and a walk down of four mitigation strategies with operators to assess the feasibility of the strategies and operator familiarity, maintenance and surveillance testing of selected strategy equipment, and an inventory check of the B.5.b pump and equipment trailers to ensure the appropriateness of equipment storage and availability.

b. Findings

No findings were identified.

OTHER ACTIVITIES

4OA2 Identification and Resolution of Problems (IP 71152)

a. Inspection Scope

The team reviewed a sample of condition reports associated with the FPP, post-fire safe shutdown issues, and mitigation strategy issues to determine whether Entergy was appropriately identifying, characterizing, and correcting problems associated with these areas and whether the planned or completed corrective actions were appropriate.

b. Findings

No findings were identified.

4OA6 Meetings, Including Exit

The team presented the inspection results to Mr. Anthony J. Vitale, Site Vice President, and other members of the site staff at an exit meeting on December 16, 2016. The team verified that this report does not contain proprietary information.

ATTACHMENT:

SUPPLEMENTARY INFORMATION

KEY POINTS OF CONTACT

Licensee Personnel

J. Balletta Senior Reactor Operator

S. Bianco Fire Brigade Training

T. Chan Design Engineer

G. Dahl Licensing Engineer

K. Elliot Appendix R Engineer

D. Powell Senior Reactor Operator

C. Wilson Fire Protection Engineer

NRC

B. Haagensen Senior Resident Inspector, Indian Point
S. Rich Resident Inspector, Indian Point
C. Safouri Acting Resident Inspector, Indian

LIST OF ITEMS OPENED, CLOSED, AND DISCUSSED

Opened

NONE

Opened and Closed

NONE

Closed

NONE

Discussed

NONE

LIST OF DOCUMENTS REVIEWED