| | number = ML081420218 | | | number = ML081420218 |
| | issue date = 05/21/2008 | | | issue date = 05/21/2008 |
| | title = 05/12/2008 Summary of Palisades EOC Public Meeting with Entergy to Discuss the Nrc'S 2007 End-of-Cycle Assessment of the Palisades Nuclear Plant Safety Performance | | | title = Summary of Palisades EOC Public Meeting with Entergy to Discuss the Nrc'S 2007 End-of-Cycle Assessment of the Palisades Nuclear Plant Safety Performance |
| | author name = Lipa C | | | author name = Lipa C |
| | author affiliation = NRC/RGN-III/DRP/B4 | | | author affiliation = NRC/RGN-III/DRP/B4 |
Line 15: |
Line 15: |
|
| |
|
| =Text= | | =Text= |
| {{#Wiki_filter:UNITED STATES NUCLEAR REGULATORY COMMISSION REGION III 2443 WARRENVILLE ROAD, SUITE 210 LISLE, IL 60532-4352 May 21, 2008 LICENSEE: Entergy Nuclear Operations, Inc. | | {{#Wiki_filter:UNITED STATES NUCLEAR REGULATORY COMMISSION REGION III 2443 WARRENVILLE ROAD, SUITE 210 LISLE, IL 60532-4352 May 21, 2008 LICENSEE: Entergy Nuclear Operations, Inc. |
| | | FACILITY: Palisades Nuclear Plant |
| FACILITY: Palisades Nuclear Plant | |
|
| |
|
| ==SUBJECT:== | | ==SUBJECT:== |
|
| |
|
| ==SUMMARY== | | ==SUMMARY== |
| OF THE MAY 12, 2008, PUBLIC MEETING TO DISCUSS THE 2007 PALISADES END-OF-CYCLE PERFORMANCE ASSESSMENT On May 12, 2008, the Nuclear Regulatory Commission (NRC) held a public meeting at Lake Michigan College in South Haven, Michigan. The meeting was between NRC Region III management and Entergy representatives to discuss the NRC's 2007 End-of-Cycle Assessment of the Palisades Nuclear Plant safety performance. The results of that assessment were discussed in a letter to the licensee dated March 3, 2008 (ADAMS ML080600494). | | OF THE MAY 12, 2008, PUBLIC MEETING TO DISCUSS THE 2007 PALISADES END-OF-CYCLE PERFORMANCE ASSESSMENT On May 12, 2008, the Nuclear Regulatory Commission (NRC) held a public meeting at Lake Michigan College in South Haven, Michigan. The meeting was between NRC Region III management and Entergy representatives to discuss the NRCs 2007 End-of-Cycle Assessment of the Palisades Nuclear Plant safety performance. The results of that assessment were discussed in a letter to the licensee dated March 3, 2008 (ADAMS ML080600494). |
| The NRC began the meeting with an overview of the NRC and the nuclear industry, the NRC's Reactor Oversight Process (ROP), and national ROP results. This was followed by a summary of the NRC's assessment of Palisades' performance in 2007. The NRC's meeting presentation slides can be found in ADAMS at ML081280796. | | The NRC began the meeting with an overview of the NRC and the nuclear industry, the NRCs Reactor Oversight Process (ROP), and national ROP results. This was followed by a summary of the NRCs assessment of Palisades performance in 2007. The NRCs meeting presentation slides can be found in ADAMS at ML081280796. |
| The licensee then provided a response to the NRC's assessment and discussed its plan to address the newly opened substantive cross-cutting issue in human performance. In summary, the licensee concurred with the NRC assessment that Palisades was operated in a manner that preserved the safety of the public and the environment. A list of principal meeting attendees can be found in the attached enclosure. | | The licensee then provided a response to the NRCs assessment and discussed its plan to address the newly opened substantive cross-cutting issue in human performance. In summary, the licensee concurred with the NRC assessment that Palisades was operated in a manner that preserved the safety of the public and the environment. A list of principal meeting attendees can be found in the attached enclosure. |
| At the end of the meeting, members of the public were given the opportunity to ask questions of NRC officials. Numerous members of the public asked questions that covered a wide variety of topics including: head replacement, emergency diesel generators, plant response to an earthquake, spent fuel storage and nuclear waste solutions, impact on the Great Lakes, tritium, vessel embrittlement, relicensing, and suggestions to improve communications. | | At the end of the meeting, members of the public were given the opportunity to ask questions of NRC officials. Numerous members of the public asked questions that covered a wide variety of topics including: head replacement, emergency diesel generators, plant response to an earthquake, spent fuel storage and nuclear waste solutions, impact on the Great Lakes, tritium, vessel embrittlement, relicensing, and suggestions to improve communications. |
| /RA by Robert M. Lerch for/ Christine A. Lipa, Chief Branch 4 Division of Reactor Projects Docket No. 50-255, 72-007 License No. DPR-20
| | /RA by Robert M. Lerch for/ |
| | Christine A. Lipa, Chief Branch 4 Division of Reactor Projects Docket No. 50-255, 72-007 License No. DPR-20 |
|
| |
|
| ==Enclosure:== | | ==Enclosure:== |
| As stated | | As stated Distribution: |
| | See next page |
|
| |
|
| Distribution:
| | Letter to Entergy Nuclear Operations, Inc. from C. Lipa dated May 21, 2008 |
| See next page Letter to Entergy Nuclear Operations, Inc. from C. Lipa dated May 21, 2008
| |
|
| |
|
| ==SUBJECT:== | | ==SUBJECT:== |
|
| |
|
| ==SUMMARY== | | ==SUMMARY== |
| OF THE MAY 12, 2008, PUBLIC MEETING TO DISCUSS THE 2007 PALISADES END-OF-CYCLE PERFORMANCE ASSESSMENT | | OF THE MAY 12, 2008, PUBLIC MEETING TO DISCUSS THE 2007 PALISADES END-OF-CYCLE PERFORMANCE ASSESSMENT cc w/encl: C. Schwarz, Vice President, Operations Senior Vice President Vice President Oversight Senior Manager, Nuclear Safety & Licensing Senior Vice President and COO Assistant General Counsel Manager, Licensing W. DiProfio W. Russell G. Randolph Supervisor, Covert Township Office of the Governor T. Strong, Chief, State Liaison Office, State of Michigan Michigan Department of Environmental Quality - |
| | Waste and Hazardous Materials Division Michigan Office of the Attorney General Mayor of Bangor City Manager of Bangor Mayor of Hartford City Manager of Hartford Mayor of South Haven City Manager of South Haven Administrator, Allegan County Allegan County Sheriff Allegan County Emergency Management Coordinator County Coordinator Berrien County Sheriff Director, Berrien County Emergency Management Agency Chairman, Van Buren County Board Van Buren County Sheriff Director, Van Buren County Emergency Management Agency Mayor of Watervliet Mayor of Coloma G. Mortensen, INPO |
|
| |
|
| cc w/encl: C. Schwarz, Vice President, Operations Senior Vice President Vice President Oversight Senior Manager, Nuclear Safety & Licensing Senior Vice President and COO Assistant General Counsel Manager, Licensing W. DiProfio W. Russell G. Randolph Supervisor, Covert Township Office of the Governor T. Strong, Chief, State Liaison Office, State of Michigan Michigan Department of Environmental Quality - Waste and Hazardous Materials Division Michigan Office of the Attorney General Mayor of Bangor City Manager of Bangor Mayor of Hartford City Manager of Hartford Mayor of South Haven City Manager of South Haven Administrator, Allegan County Allegan County Sheriff Allegan County Emergency Management Coordinator County Coordinator Berrien County Sheriff Director, Berrien County Emergency Management Agency Chairman, Van Buren County Board Van Buren County Sheriff Director, Van Buren County Emergency Management Agency Mayor of Watervliet Mayor of Coloma G. Mortensen, INPO
| | LICENSEE: Entergy Nuclear Operations, Inc. |
| | | FACILITY: Palisades Nuclear Plant |
| LICENSEE: Entergy Nuclear Operations, Inc. | |
| FACILITY: Palisades Nuclear Plant | |
|
| |
|
| ==SUBJECT:== | | ==SUBJECT:== |
|
| |
|
| ==SUMMARY== | | ==SUMMARY== |
| OF THE MAY 12, 2008, PUBLIC MEETING TO DISCUSS THE 2007 PALISADES END-OF-CYCLE PERFORMANCE ASSESSMENT On May 12, 2008, the Nuclear Regulatory Commission (NRC) held a public meeting at Lake Michigan College in South Haven, Michigan. The meeting was between NRC Region III management and Entergy representatives to discuss the NRC's 2007 End-of-Cycle Assessment of the Palisades Nuclear Plant safety performance. The results of that assessment were discussed in a letter to the licensee dated March 3, 2008 (ADAMS ML080600494). | | OF THE MAY 12, 2008, PUBLIC MEETING TO DISCUSS THE 2007 PALISADES END-OF-CYCLE PERFORMANCE ASSESSMENT On May 12, 2008, the Nuclear Regulatory Commission (NRC) held a public meeting at Lake Michigan College in South Haven, Michigan. The meeting was between NRC Region III management and Entergy representatives to discuss the NRCs 2007 End-of-Cycle Assessment of the Palisades Nuclear Plant safety performance. The results of that assessment were discussed in a letter to the licensee dated March 3, 2008 (ADAMS ML080600494). |
| The NRC began the meeting with an overview of the NRC and the nuclear industry, the NRC's Reactor Oversight Process (ROP), and national ROP results. This was followed by a summary of the NRC's assessment of Palisades' performance in 2007. The NRC's meeting presentation slides can be found in ADAMS at ML081280796. | | The NRC began the meeting with an overview of the NRC and the nuclear industry, the NRCs Reactor Oversight Process (ROP), and national ROP results. This was followed by a summary of the NRCs assessment of Palisades performance in 2007. The NRCs meeting presentation slides can be found in ADAMS at ML081280796. |
| | | The licensee then provided a response to the NRCs assessment and discussed its plan to address the newly opened substantive cross-cutting issue in human performance. In summary, the licensee concurred with the NRC assessment that Palisades was operated in a manner that preserved the safety of the public and the environment. A list of principal meeting attendees can be found in the attached enclosure. |
| The licensee then provided a response to the NRC's assessment and discussed its plan to address the newly opened substantive cross-cutting issue in human performance. In summary, the licensee concurred with the NRC assessment that Palisades was operated in a manner that preserved the safety of the public and the environment. A list of principal meeting attendees can be found in the attached enclosure. | |
| At the end of the meeting, members of the public were given the opportunity to ask questions of NRC officials. Numerous members of the public asked questions that covered a wide variety of topics including: head replacement, emergency diesel generators, plant response to an earthquake, spent fuel storage and nuclear waste solutions, impact on the Great Lakes, tritium, vessel embrittlement, relicensing, and suggestions to improve communications. | | At the end of the meeting, members of the public were given the opportunity to ask questions of NRC officials. Numerous members of the public asked questions that covered a wide variety of topics including: head replacement, emergency diesel generators, plant response to an earthquake, spent fuel storage and nuclear waste solutions, impact on the Great Lakes, tritium, vessel embrittlement, relicensing, and suggestions to improve communications. |
| Christine A. Lipa, Chief Branch 4 Division of Reactor Projects Docket No. 50-255, 72-007 License No. DPR-20 | | Christine A. Lipa, Chief Branch 4 Division of Reactor Projects Docket No. 50-255, 72-007 License No. DPR-20 |
|
| |
|
| ==Enclosure:== | | ==Enclosure:== |
| As stated Distribution: | | As stated Distribution: |
| See next page DOCUMENT NAME: G:\Branch TSS\ALL EOC\EOC CY 2007\Meeting Notices-Letters\Palisades EOC Meeting Summary 051208.doc G Publicly Available G Non-Publicly Available G Sensitive G Non-Sensitive To receive a copy of this document, indicate in the concurrence box "C" = Copy without attach/encl "E" = Copy with attach/encl "N" = No copy OFFICE RIII RIII NAME AGarmoe:dtp CLipa DATE 05/20/08 05/21/08 OFFICIAL RECORD COPY Letter to Entergy Nuclear Operations, Inc. from C. Lipa dated May 21, 2008 | | See next page DOCUMENT NAME: G:\Branch TSS\ALL EOC\EOC CY 2007\Meeting Notices-Letters\Palisades EOC Meeting Summary 051208.doc G Publicly Available G Non-Publicly Available G Sensitive G Non-Sensitive To receive a copy of this document, indicate in the concurrence box "C" = Copy without attach/encl "E" = Copy with attach/encl "N" = No copy OFFICE RIII RIII NAME AGarmoe:dtp CLipa DATE 05/20/08 05/21/08 OFFICIAL RECORD COPY |
| | |
| | Letter to Entergy Nuclear Operations, Inc. from C. Lipa dated May 21, 2008 |
|
| |
|
| ==SUBJECT:== | | ==SUBJECT:== |
|
| |
|
| ==SUMMARY== | | ==SUMMARY== |
| OF THE MAY 12, 2008, PUBLIC MEETING TO DISCUSS THE 2007 PALISADES END-OF-CYCLE PERFORMANCE ASSESSMENT | | OF THE MAY 12, 2008, PUBLIC MEETING TO DISCUSS THE 2007 PALISADES END-OF-CYCLE PERFORMANCE ASSESSMENT DISTRIBUTION: |
| | | M. Chawla T. Bloomer RidsNrrDirslpab J. Caldwell M. Satorius K. OBrien J. Heck R. Lickus Palisades SRI Palisades RI C. Ariano L. Linn (electronic IRs only) |
| DISTRIBUTION: | | C. Pederson, DRP (hard copy - IRs only) |
| M. Chawla T. Bloomer RidsNrrDirslpab J. Caldwell M. Satorius K. OBrien J. Heck R. Lickus Palisades SRI Palisades RI C. Ariano L. Linn (electronic IR's only) C. Pederson, DRP (hard copy - IR's only) DRPIII DRSIII P. Buckley T. Tomczak | | DRPIII DRSIII P. Buckley T. Tomczak |
|
| |
|
| Enclosure PUBLIC MEETING PRINCIPAL ATTENDEES May 12, 2008 Entergy Nuclear Operations, Inc.
| | PUBLIC MEETING PRINCIPAL ATTENDEES May 12, 2008 Entergy Nuclear Operations, Inc. |
| C. Schwarz, Site Vice President T. Kirwin, Plant Manager, Fermi J. Broschak, Engineering Director C. Arnone, Nuclear Safety Assurance Director Nuclear Regulatory Commission C. Lipa, Branch Chief, Division of Reactor Projects, Region III J. Ellegood, Senior Resident Inspector, Palisades J. Giessner, Resident Inspector, Palisades S. Bakhsh, Inspector, Decommissioning Branch, Region III V. Mitlyng, Public Affairs Officer, Region III}} | | C. Schwarz, Site Vice President T. Kirwin, Plant Manager, Fermi J. Broschak, Engineering Director C. Arnone, Nuclear Safety Assurance Director Nuclear Regulatory Commission C. Lipa, Branch Chief, Division of Reactor Projects, Region III J. Ellegood, Senior Resident Inspector, Palisades J. Giessner, Resident Inspector, Palisades S. Bakhsh, Inspector, Decommissioning Branch, Region III V. Mitlyng, Public Affairs Officer, Region III Enclosure}} |
|
---|
Category:Letter
MONTHYEARPNP 2024-014, Request for USNRC to Rescind Approved Exemption Requests for 140.11(a)(4) and 50.54(w)(1), Reduction of Insurances2024-10-0909 October 2024 Request for USNRC to Rescind Approved Exemption Requests for 140.11(a)(4) and 50.54(w)(1), Reduction of Insurances PNP 2024-037, Response to Requests for Additional Information Regarding the Proposed Reauthorization of Power Operations Under Renewed Facility Operating License Number DPR-0202024-10-0404 October 2024 Response to Requests for Additional Information Regarding the Proposed Reauthorization of Power Operations Under Renewed Facility Operating License Number DPR-020 ML24267A2962024-10-0101 October 2024 Summary of Conference Call Regarding Steam Generator Tube Inspections ML24263A1712024-09-20020 September 2024 Environmental Request for Additional Information ML24240A1692024-09-18018 September 2024 Cy 2023 Summary of Decommissioning Trust Fund Status ML24219A4202024-09-12012 September 2024 Change in Estimated Hours and Review Schedule for Licensing Actions Submitted to Support Resumption of Power Operations (Epids L-2023-LLE-0025, L-2023-LLM-0005, L-2023-LLA-0174, L-2024-LLA-0013, L-2024-LLA-0060, L-2024-LLA-0071) IR 05000255/20244022024-09-0606 September 2024 Public: Palisades Nuclear Plant - Decommissioning Security Inspection Report 05000255/2024402 PNP 2024-029, Notice of Payroll Transition at Palisades Nuclear Plant2024-08-15015 August 2024 Notice of Payroll Transition at Palisades Nuclear Plant IR 05000255/20240022024-08-0909 August 2024 NRC Inspection Report No. 05000255/2024002 PNP 2024-030, Update Report for Holtec Decommissioning International Fleet Decommissioning Quality Assurance Program Rev. 3 and Palisades Transitioning Quality Assurance Plan, Rev 02024-08-0202 August 2024 Update Report for Holtec Decommissioning International Fleet Decommissioning Quality Assurance Program Rev. 3 and Palisades Transitioning Quality Assurance Plan, Rev 0 PNP 2024-032, Supplement to License Amendment Request to Revise Selected Permanently Defueled Technical Specifications Administrative Controls to Support Resumption of Power Operations2024-07-31031 July 2024 Supplement to License Amendment Request to Revise Selected Permanently Defueled Technical Specifications Administrative Controls to Support Resumption of Power Operations ML24206A0572024-07-25025 July 2024 PRM-50-125 - Letter to Alan Blind; Docketing of Petition for Rulemaking and Sufficiency Review Status (10 CFR Part 50) PNP 2024-033, Response to Request for Additional Information - License Amendment Request to Revise the Palisades Nuclear Plant Site Emergency Plan to Support Resumption of Power Operations2024-07-24024 July 2024 Response to Request for Additional Information - License Amendment Request to Revise the Palisades Nuclear Plant Site Emergency Plan to Support Resumption of Power Operations PNP 2024-031, Response to RIS 2024-01, Preparation and Scheduling of Operator Licensing Examinations2024-07-18018 July 2024 Response to RIS 2024-01, Preparation and Scheduling of Operator Licensing Examinations IR 05000255/20240112024-07-15015 July 2024 Nuclear Plant - Restart Inspection Report 05000255/2024011 PNP 2024-027, Supplement to License Amendment Request to Revise Renewed Facility Operating License and Permanently Defueled Technical Specifications to Support Resumption of Power Operations2024-07-0909 July 2024 Supplement to License Amendment Request to Revise Renewed Facility Operating License and Permanently Defueled Technical Specifications to Support Resumption of Power Operations ML24183A1382024-07-0202 July 2024 Tribal Letter - Lac Du Flambeau Band of Lake Superior Chippewa Indians ML24137A0142024-07-0202 July 2024 OEDO-24-00011 - 2.206 Petition for Misuse of Palisades Decommissioning Trust Fund (EPID L-2023-CRS-0008) - Letter ML24183A1492024-07-0101 July 2024 Tribal Letter - Pokagon Band of Potawatomi Indians ML24156A0222024-07-0101 July 2024 Initiation of Scoping Process to Prepare an Environmental Assessment for the Environmental Review of Holtec Decommissioning International, Llc’S Licensing and Regulatory Requests for Reauthorization of Power Operations at Palisades EPID L-2 ML24183A1552024-07-0101 July 2024 Tribal Letter - Red Lake Band of Chippewa Indians ML24183A1542024-07-0101 July 2024 Tribal Letter Red Cliff Band of Lake Superior Chippewa Indians ML24172A0032024-07-0101 July 2024 Letter to L. Powers, Mackinac Bands of Chippewa and Ottawa Indians Re Initiation of Scoping Process for Environ Review Holtec Decommissioning Intl, LLC Request for Reauthorization of Power Ops-Palisades ML24183A1332024-07-0101 July 2024 Tribal Letter-Forest County Potawatomi Community ML24183A1582024-07-0101 July 2024 Tribal Letter Sault Ste. Marie Tribe of Chippewa Indians ML24183A1302024-07-0101 July 2024 Tribal Letter-Chippewa Cree Indians of the Rocky Boys Reservation ML24183A1282024-07-0101 July 2024 Tribal letter-Bay Mills Indian Community ML24183A1532024-07-0101 July 2024 Tribal Letter Quechan Tribe of the Fort Yuma Indian Reservation ML24183A1572024-07-0101 July 2024 Tribal Letter - Saint Croix Chippewa Indians of Wisconsin ML24183A1462024-07-0101 July 2024 Tribal letter-Mille Lacs Band of Ojibwe ML24183A1422024-07-0101 July 2024 Tribal Letter-Little Traverse Bay Bands of Odawa Indians ML24183A1312024-07-0101 July 2024 Tribal Letter-Citizen Potawatomi Nation ML24163A0552024-07-0101 July 2024 Rebecca Held Knoche NOAA-Palisades-NOI to Conduct Scoping Process and Prepare an EA - EPID No. L-2024-LNE-0003-Docket No. 50-0255 ML24163A2392024-07-0101 July 2024 Sara Thompson, Michigan DNR-Palisades-NOI to Conduct Scoping Process and Prepare an EPID No. L-2024-LNE-0003-Docket No. 50-0255 ML24155A0102024-07-0101 July 2024 Quentin L. Messer Jr., Michigan Econ-Palisades-NOI to Conduct Scoping Process and Prep an EA-EPID No. L-2024-LNE-0003 Docket No.50-0255P ML24155A0032024-07-0101 July 2024 Kathy Kowal, Us EPA Region 5-Palisades-NOI to Cibdyct Scoping Process and Prepare an EA EPID L-2024-LNE-0003 ML24163A0832024-07-0101 July 2024 Ltr to R Schumaker SHPO Re Initiation of Scoping Process, Section 106 Consult for Env Rev of HDI, LLC Request for Reauth of Power Operations at Palisades Nuclear Plant ML24183A1342024-07-0101 July 2024 Tribal Letter-Grand Portage Band of Lake Superior Chippewa ML24183A1392024-07-0101 July 2024 Tribal Letter-Lac Vieux Desert Band of Lake Superior Chippewa Indians ML24183A1272024-07-0101 July 2024 Tribal Letter-Bad River Band of the Lake Superior Tribe of Chippewa ML24183A1412024-07-0101 July 2024 Tribal Letter-Little River Band of Ottawa Indians ML24163A1922024-07-0101 July 2024 Jeremy Rubio, Dept of Env, Great Lakes and Energy, Kalamazoo District-Palisades-NOI to Conduct Scoping Process and Prepare an EA EPID No. L-2024-LNE-0003 Docket No.50-0255 ML24183A1322024-07-0101 July 2024 Tribal Letter-Fond Du Lac Band of Lake Superior Chippewa ML24183A1592024-07-0101 July 2024 Tribal letter-Sokaogon Chippewa Community ML24163A0822024-07-0101 July 2024 Ltr to J Loichinger Achp Re Initiation of Scoping Process, Section 106 Consult for Env Rev of HDI, LLC Request for Reauth of Power Operations at Palisades Nuclear Plant ML24183A1252024-07-0101 July 2024 Letter to G. Gould, Swan Creek Black River Confederated Ojibwa-Init of Scoping Process for the Env Rev of Holtec Decommissioning Intl, LLC Request for Reauth of Power Ops at Palisades ML24183A1352024-07-0101 July 2024 Tribal Letter-Hannahville Indian Community ML24183A1442024-07-0101 July 2024 Tribal Letter - Menominee Indian Tribe of Wisconsin ML24183A1502024-07-0101 July 2024 Tribal Letter - Prarie Band Potawatomi Nation ML24183A1452024-07-0101 July 2024 Tribal Letter - Miami Tribe of Oklahoma 2024-09-06
[Table view] Category:Meeting Summary
MONTHYEARML24267A2962024-10-0101 October 2024 Summary of Conference Call Regarding Steam Generator Tube Inspections ML24257A0582024-09-26026 September 2024 Summary of August 1, 2024, Hybrid Public Meeting on the Potential Palisades Nuclear Plant Restart ML24212A0592024-08-0606 August 2024 May 15, 2024, Summary of Meeting with Holtec Decommissioning International,Llc Regarding LAR to Approve Biasi Critical Heat Flux Correlation for Use with Main Steam Line Break Analysis to Support Potential Reauthorization of Power Operation ML24166A2912024-06-25025 June 2024 April 29, 2024, Summary of Meeting with Holtec Decommissioning International, LLC Regarding Plan to Submit a Quality Assurance Program Manual to Support Potential Reauthorization of Power Operations at Palisades Nuclear Plant ML24141A0632024-05-23023 May 2024 Summary of April 17, 2024, Hybrid Public Outreach Meeting ML24089A2472024-04-0808 April 2024 March 18, 2024, Summary of Pre-Submittal Meeting with Holtec Decommissioning International, LLC Regarding Proposed Emergency Plan for Resumption of Power Operations at the Palisades Nuclear Plant ML24051A0942024-02-27027 February 2024 Summary of February 6, 2024, Pre-Submittal Meeting with Holtec Decommissioning International, LLC Regarding Technical Specifications Administrative Controls and Quality Assurance Program ML24016A0052024-01-23023 January 2024 Summary of Meeting with Holtec Decommissioning International, LLC, Regarding Power Operations Technical Specifications ML23303A2132023-11-0101 November 2023 Summary of Meeting with Holtec Decommissioning International, LLC Regarding Plan to Submit a License Transfer Request as Part of a Regulatory Path for Potentially Requesting Reauthorization of Power Operations at Palisades Nuclear Plant ML23263A0012023-09-27027 September 2023 Summary of August 29, 2023, Meeting with Holtec Decommissioning International, LLC Regarding Plan to Submit an Exemption Request as Part of a Regulatory Path for Potentially Requesting Reauthorization of Power Operations at Palisades Nuclea ML23171B1222023-06-22022 June 2023 Summary of Meeting with Holtec Decommissioning International, LLC Regarding Regulatory Path for Potentially Requesting Reauthorization of Power Operations at Palisades Nuclear Plant ML23107A1212023-04-20020 April 2023 Summary of Meeting with Holtec Decommissioning International, Llc Regarding Regulatory Path for Potentially Requesting Reauthorization of Power Operations at Palisades Nuclear Plant ML22292A2612022-10-31031 October 2022 PSDAR Meeting Summary ML22132A0892022-05-12012 May 2022 Summary of the April 26, 2022, Public Outreach to Discuss the NRC 2021 End-of-Cycle Plant Performance Assessment of Palisades Nuclear Plant ML21200A2262021-07-19019 July 2021 Summary of the July 1, 2021, Public Outreach to Discuss the NRC 2020 End-of-Cycle Plant Performance Assessment of Palisades Nuclear Plant ML21145A0482021-06-0202 June 2021 Summary of May 12, 2021, Teleconference with Entergy Nuclear Operations, Inc. to Discuss Potential License Amendment Request Related to Permanently Defueled Technical Specifications for Palisades Nuclear Plant ML21012A0382021-01-14014 January 2021 December 8, 2020, Summary of Public Teleconference with Entergy Nuclear Operations Inc. Regarding Pre-submittal of a License Transfer Application to Holtec International for Palisades Nuclear Plant ML20309A2372020-11-0606 November 2020 Summary of Public Teleconference with Entergy Nuclear Operations, Inc. to Discuss Future Request for One-Time Exemption from Certain Requirements of 10 CFR 50, Appendix E, Section Iv.F. at Palisades Nuclear Plant (EPID L-2020-LRM-0091 ML20304A1442020-11-0202 November 2020 Summary of September 21, 2020, Public Teleconference with Entergy Nuclear Operations Inc. Regarding a Proposed Alternative for Repair of Reactor Vessel Head Penetrations for Palisades Nuclear Plant ML20280A6952020-10-13013 October 2020 Letter - Palisades Nuclear Plant- Summary of September 11, 2020, Conference Call with Entergy Nuclear Operations Inc. Regarding the Fall 2020 Steam Generator Tube Inspections at Palisades Nuclear Plant EPID L-2020-LRO-0051 ML20280A6962020-10-13013 October 2020 20200912 NRC Mid Outage Q and a for Phone Call for Palisades 1R27 (Revised) ML20280A6972020-10-13013 October 2020 20200910 NRC Mid Outage Q and a for Phone Call for Palisades 1R27-Entergy Responses ML20231A2202020-08-17017 August 2020 Summary of Public Webinar to Discuss the NRC 2019 End-Of-Cycle Plant Performance Assessment of the Palisades Nuclear Plant ML19296D0632019-11-0101 November 2019 August 2019 Palisades NEIMA 108 Public Meeting Summary ML19136A2552019-05-16016 May 2019 Summary of the Public Outreach/Open House to Discuss the NRC 2018 End-of-Cycle Plant Performance Assessment of the Palisades Nuclear Plant ML18351A2382018-12-18018 December 2018 Summary of Public Teleconference Call with Entergy Nuclear Operations. Inc., Regarding Emergent Alternative Request for Repair of Central Rod Drive Nozzles at Palisades Nuclear Plant ML18340A0072018-12-0606 December 2018 Summary of Call with Entergy Nuclear Operations, Inc. - Verbal Authorization of Request for Alternative for the Repair of Reactor Vessel Closure Head Penetrations ML18268A2802018-09-26026 September 2018 Summary of Public Teleconference Call with Entergy Nuclear Operations, Inc. Regarding Upcoming License Amendment Request to Relocate Surveillance Frequencies to Licensee Control ML18107A4972018-04-27027 April 2018 April 10, 2017, Summary of Public Meeting with Entergy Nuclear Operations, Inc. Regarding Upcoming License Amendment Request to Add Setpoint Verification Requirement to Technical Specification Surveillance Requirements ML18113A6592018-04-23023 April 2018 Summary of Open House to Discuss the 2017 End-of-Cycle Plant Performance Assessment of Palisades Nuclear Plant ML18099A0712018-04-16016 April 2018 March 20, 2018, Summary of Meeting with the Nuclear Energy Institute and Other Industry Representatives Regarding the Surveillance Frequency Control Program ML18008A2302018-01-10010 January 2018 Summary of Public Teleconference Meeting with Entergy Nuclear Operations, Inc., Regarding Request to Extend Enforcement Discretion for Tornado-Generated Missile Non-Conformances at Palisades Nuclear Plant ML17335A0262017-12-0505 December 2017 Summary of November 27, 2017 Public Meeting with Entergy Nuclear Operations, Inc. Regarding Request to Extend Enforcement Discretion for Tornado Missle Non-Confomances ML17338B0502017-12-0505 December 2017 Summary of November 28, 2017, Public Meeting with Entergy Nuclear Operations, Inc. Regarding a Potential Request Associated with an Alternative to the Reexamination Frequency for a Relevant Condition ML17227A2742017-08-14014 August 2017 Summary of the July 26, 2017, Public Meeting Regarding Palisades Nuclear Plant ML17173A7672017-07-28028 July 2017 Summary of 6/20/2017 Meeting with Entergy to Discuss Plan for Decommissioning Licensing Actions of Palisades, Pilgrim, Indian Point, Units 2 and 3, and Vermont Yankee ML17164A3112017-06-27027 June 2017 Summary of 06/12/2017, Pre-Submittal Meeting with Entergy Nuclear Operations, Inc. to Discuss Palisades Nuclear Plant Post Shutdown Emergency Plan and Administrative Technical Specification License Amendment Request ML17160A1812017-06-14014 June 2017 Summary of Conference Call with Palisades Nuclear Plant Regarding the Spring 2017 Steam Generator Inspections ML17080A1492017-03-23023 March 2017 Summary of March 20, 2017, Public Meeting with Entergy Nuclear Operations, Inc. Regarding the Cyber Security Plan Implementation Schedule ML16344A0862016-12-20020 December 2016 Summary of Public Meeting with Entergy Nuclear Operations, Inc. Regarding National Fire Protection Association Standard 805 ML16277A6772016-10-11011 October 2016 Summary of Public Meeting with Entergy Nuclear Operations, Inc. Regarding the Proposed Closure Plant for Generic Safety Issue 191, Assessment of Debris Accumulation on Pressurized Water Reactor (PWR) Sump Performance ML16182A5142016-06-30030 June 2016 Summary of the June 23, 2016, Public Meeting Regarding Palisades Nuclear Plant ML16127A1722016-05-0505 May 2016 6/23/16 Notice of Significant Public Meeting to Discuss Nrc'S End-of-Cycle Assessment of the Palisades Nuclear Plant Performance for the 2015 Calendar Year ML16035A4252016-03-0101 March 2016 Summary of January 25, 2016, Pre-Application Teleconference Meeting with Entergy Nuclear Operations to Discuss a Forthcoming License Amendment Request Regarding Steam Generator Cold Leg Alternate Repair Criteria at Palisades Nuclear Plant ( ML15294A2972015-10-27027 October 2015 Steam Generator Tube Inspection Discussion During Palisades 2015 (RF24) Outage (Preliminary Information) ML15294A2922015-10-27027 October 2015 Summary of Conference Call with Palisades Nuclear Plant Regarding the Fall 2015 Steam Generator Inspections ML15272A0652015-09-30030 September 2015 Summary of Telephone Conference on September 28, 2015, Verbal Authorization of Relief Request for Palisades Nuclear Plant ML15261A0392015-09-21021 September 2015 September 17, 2015, Summary of Telephone Conference Verbal Authorization of Relief Request for Palisades Nuclear Plant ML15119A0442015-05-0606 May 2015 Summary of April 14, 2015, Meeting with Entergy Nuclear Operations, Inc. on Plans for Volumetric Examinations of Primary Coolant System Alloy 600 Welds ML15118A0352015-04-27027 April 2015 Meeting Summary with Public to Discuss the 2014 Annual Assessment Results for Palisades Nuclear Plant 2024-09-26
[Table view] |
Text
UNITED STATES NUCLEAR REGULATORY COMMISSION REGION III 2443 WARRENVILLE ROAD, SUITE 210 LISLE, IL 60532-4352 May 21, 2008 LICENSEE: Entergy Nuclear Operations, Inc.
FACILITY: Palisades Nuclear Plant
SUBJECT:
SUMMARY
OF THE MAY 12, 2008, PUBLIC MEETING TO DISCUSS THE 2007 PALISADES END-OF-CYCLE PERFORMANCE ASSESSMENT On May 12, 2008, the Nuclear Regulatory Commission (NRC) held a public meeting at Lake Michigan College in South Haven, Michigan. The meeting was between NRC Region III management and Entergy representatives to discuss the NRCs 2007 End-of-Cycle Assessment of the Palisades Nuclear Plant safety performance. The results of that assessment were discussed in a letter to the licensee dated March 3, 2008 (ADAMS ML080600494).
The NRC began the meeting with an overview of the NRC and the nuclear industry, the NRCs Reactor Oversight Process (ROP), and national ROP results. This was followed by a summary of the NRCs assessment of Palisades performance in 2007. The NRCs meeting presentation slides can be found in ADAMS at ML081280796.
The licensee then provided a response to the NRCs assessment and discussed its plan to address the newly opened substantive cross-cutting issue in human performance. In summary, the licensee concurred with the NRC assessment that Palisades was operated in a manner that preserved the safety of the public and the environment. A list of principal meeting attendees can be found in the attached enclosure.
At the end of the meeting, members of the public were given the opportunity to ask questions of NRC officials. Numerous members of the public asked questions that covered a wide variety of topics including: head replacement, emergency diesel generators, plant response to an earthquake, spent fuel storage and nuclear waste solutions, impact on the Great Lakes, tritium, vessel embrittlement, relicensing, and suggestions to improve communications.
/RA by Robert M. Lerch for/
Christine A. Lipa, Chief Branch 4 Division of Reactor Projects Docket No. 50-255,72-007 License No. DPR-20
Enclosure:
As stated Distribution:
See next page
Letter to Entergy Nuclear Operations, Inc. from C. Lipa dated May 21, 2008
SUBJECT:
SUMMARY
OF THE MAY 12, 2008, PUBLIC MEETING TO DISCUSS THE 2007 PALISADES END-OF-CYCLE PERFORMANCE ASSESSMENT cc w/encl: C. Schwarz, Vice President, Operations Senior Vice President Vice President Oversight Senior Manager, Nuclear Safety & Licensing Senior Vice President and COO Assistant General Counsel Manager, Licensing W. DiProfio W. Russell G. Randolph Supervisor, Covert Township Office of the Governor T. Strong, Chief, State Liaison Office, State of Michigan Michigan Department of Environmental Quality -
Waste and Hazardous Materials Division Michigan Office of the Attorney General Mayor of Bangor City Manager of Bangor Mayor of Hartford City Manager of Hartford Mayor of South Haven City Manager of South Haven Administrator, Allegan County Allegan County Sheriff Allegan County Emergency Management Coordinator County Coordinator Berrien County Sheriff Director, Berrien County Emergency Management Agency Chairman, Van Buren County Board Van Buren County Sheriff Director, Van Buren County Emergency Management Agency Mayor of Watervliet Mayor of Coloma G. Mortensen, INPO
LICENSEE: Entergy Nuclear Operations, Inc.
FACILITY: Palisades Nuclear Plant
SUBJECT:
SUMMARY
OF THE MAY 12, 2008, PUBLIC MEETING TO DISCUSS THE 2007 PALISADES END-OF-CYCLE PERFORMANCE ASSESSMENT On May 12, 2008, the Nuclear Regulatory Commission (NRC) held a public meeting at Lake Michigan College in South Haven, Michigan. The meeting was between NRC Region III management and Entergy representatives to discuss the NRCs 2007 End-of-Cycle Assessment of the Palisades Nuclear Plant safety performance. The results of that assessment were discussed in a letter to the licensee dated March 3, 2008 (ADAMS ML080600494).
The NRC began the meeting with an overview of the NRC and the nuclear industry, the NRCs Reactor Oversight Process (ROP), and national ROP results. This was followed by a summary of the NRCs assessment of Palisades performance in 2007. The NRCs meeting presentation slides can be found in ADAMS at ML081280796.
The licensee then provided a response to the NRCs assessment and discussed its plan to address the newly opened substantive cross-cutting issue in human performance. In summary, the licensee concurred with the NRC assessment that Palisades was operated in a manner that preserved the safety of the public and the environment. A list of principal meeting attendees can be found in the attached enclosure.
At the end of the meeting, members of the public were given the opportunity to ask questions of NRC officials. Numerous members of the public asked questions that covered a wide variety of topics including: head replacement, emergency diesel generators, plant response to an earthquake, spent fuel storage and nuclear waste solutions, impact on the Great Lakes, tritium, vessel embrittlement, relicensing, and suggestions to improve communications.
Christine A. Lipa, Chief Branch 4 Division of Reactor Projects Docket No. 50-255,72-007 License No. DPR-20
Enclosure:
As stated Distribution:
See next page DOCUMENT NAME: G:\Branch TSS\ALL EOC\EOC CY 2007\Meeting Notices-Letters\Palisades EOC Meeting Summary 051208.doc G Publicly Available G Non-Publicly Available G Sensitive G Non-Sensitive To receive a copy of this document, indicate in the concurrence box "C" = Copy without attach/encl "E" = Copy with attach/encl "N" = No copy OFFICE RIII RIII NAME AGarmoe:dtp CLipa DATE 05/20/08 05/21/08 OFFICIAL RECORD COPY
Letter to Entergy Nuclear Operations, Inc. from C. Lipa dated May 21, 2008
SUBJECT:
SUMMARY
OF THE MAY 12, 2008, PUBLIC MEETING TO DISCUSS THE 2007 PALISADES END-OF-CYCLE PERFORMANCE ASSESSMENT DISTRIBUTION:
M. Chawla T. Bloomer RidsNrrDirslpab J. Caldwell M. Satorius K. OBrien J. Heck R. Lickus Palisades SRI Palisades RI C. Ariano L. Linn (electronic IRs only)
C. Pederson, DRP (hard copy - IRs only)
DRPIII DRSIII P. Buckley T. Tomczak
PUBLIC MEETING PRINCIPAL ATTENDEES May 12, 2008 Entergy Nuclear Operations, Inc.
C. Schwarz, Site Vice President T. Kirwin, Plant Manager, Fermi J. Broschak, Engineering Director C. Arnone, Nuclear Safety Assurance Director Nuclear Regulatory Commission C. Lipa, Branch Chief, Division of Reactor Projects, Region III J. Ellegood, Senior Resident Inspector, Palisades J. Giessner, Resident Inspector, Palisades S. Bakhsh, Inspector, Decommissioning Branch, Region III V. Mitlyng, Public Affairs Officer, Region III Enclosure