MONTHYEARML24016A0052024-01-23023 January 2024 Summary of Meeting with Holtec Decommissioning International, LLC, Regarding Power Operations Technical Specifications ML23303A2132023-11-0101 November 2023 Summary of Meeting with Holtec Decommissioning International, LLC Regarding Plan to Submit a License Transfer Request as Part of a Regulatory Path for Potentially Requesting Reauthorization of Power Operations at Palisades Nuclear Plant ML23263A0012023-09-27027 September 2023 Summary of August 29, 2023, Meeting with Holtec Decommissioning International, LLC Regarding Plan to Submit an Exemption Request as Part of a Regulatory Path for Potentially Requesting Reauthorization of Power Operations at Palisades Nuclea ML23171B1222023-06-22022 June 2023 Summary of Meeting with Holtec Decommissioning International, LLC Regarding Regulatory Path for Potentially Requesting Reauthorization of Power Operations at Palisades Nuclear Plant ML23107A1212023-04-20020 April 2023 Summary of Meeting with Holtec Decommissioning International, Llc Regarding Regulatory Path for Potentially Requesting Reauthorization of Power Operations at Palisades Nuclear Plant ML22292A2612022-10-31031 October 2022 PSDAR Meeting Summary ML22132A0892022-05-12012 May 2022 Summary of the April 26, 2022, Public Outreach to Discuss the NRC 2021 End-of-Cycle Plant Performance Assessment of Palisades Nuclear Plant ML21200A2262021-07-19019 July 2021 Summary of the July 1, 2021, Public Outreach to Discuss the NRC 2020 End-of-Cycle Plant Performance Assessment of Palisades Nuclear Plant ML21145A0482021-06-0202 June 2021 Summary of May 12, 2021, Teleconference with Entergy Nuclear Operations, Inc. to Discuss Potential License Amendment Request Related to Permanently Defueled Technical Specifications for Palisades Nuclear Plant ML21012A0382021-01-14014 January 2021 December 8, 2020, Summary of Public Teleconference with Entergy Nuclear Operations Inc. Regarding Pre-submittal of a License Transfer Application to Holtec International for Palisades Nuclear Plant ML20309A2372020-11-0606 November 2020 Summary of Public Teleconference with Entergy Nuclear Operations, Inc. to Discuss Future Request for One-Time Exemption from Certain Requirements of 10 CFR 50, Appendix E, Section Iv.F. at Palisades Nuclear Plant (EPID L-2020-LRM-0091 ML20304A1442020-11-0202 November 2020 Summary of September 21, 2020, Public Teleconference with Entergy Nuclear Operations Inc. Regarding a Proposed Alternative for Repair of Reactor Vessel Head Penetrations for Palisades Nuclear Plant ML20280A6972020-10-13013 October 2020 20200910 NRC Mid Outage Q and a for Phone Call for Palisades 1R27-Entergy Responses ML20280A6962020-10-13013 October 2020 20200912 NRC Mid Outage Q and a for Phone Call for Palisades 1R27 (Revised) ML20280A6952020-10-13013 October 2020 Letter - Palisades Nuclear Plant- Summary of September 11, 2020, Conference Call with Entergy Nuclear Operations Inc. Regarding the Fall 2020 Steam Generator Tube Inspections at Palisades Nuclear Plant EPID L-2020-LRO-0051 ML20231A2202020-08-17017 August 2020 Summary of Public Webinar to Discuss the NRC 2019 End-Of-Cycle Plant Performance Assessment of the Palisades Nuclear Plant ML19296D0632019-11-0101 November 2019 August 2019 Palisades NEIMA 108 Public Meeting Summary ML19136A2552019-05-16016 May 2019 Summary of the Public Outreach/Open House to Discuss the NRC 2018 End-of-Cycle Plant Performance Assessment of the Palisades Nuclear Plant ML18351A2382018-12-18018 December 2018 Summary of Public Teleconference Call with Entergy Nuclear Operations. Inc., Regarding Emergent Alternative Request for Repair of Central Rod Drive Nozzles at Palisades Nuclear Plant ML18340A0072018-12-0606 December 2018 Summary of Call with Entergy Nuclear Operations, Inc. - Verbal Authorization of Request for Alternative for the Repair of Reactor Vessel Closure Head Penetrations ML18268A2802018-09-26026 September 2018 Summary of Public Teleconference Call with Entergy Nuclear Operations, Inc. Regarding Upcoming License Amendment Request to Relocate Surveillance Frequencies to Licensee Control ML18107A4972018-04-27027 April 2018 April 10, 2017, Summary of Public Meeting with Entergy Nuclear Operations, Inc. Regarding Upcoming License Amendment Request to Add Setpoint Verification Requirement to Technical Specification Surveillance Requirements ML18113A6592018-04-23023 April 2018 Summary of Open House to Discuss the 2017 End-of-Cycle Plant Performance Assessment of Palisades Nuclear Plant ML18099A0712018-04-16016 April 2018 March 20, 2018, Summary of Meeting with the Nuclear Energy Institute and Other Industry Representatives Regarding the Surveillance Frequency Control Program ML18008A2302018-01-10010 January 2018 Summary of Public Teleconference Meeting with Entergy Nuclear Operations, Inc., Regarding Request to Extend Enforcement Discretion for Tornado-Generated Missile Non-Conformances at Palisades Nuclear Plant ML17338B0502017-12-0505 December 2017 Summary of November 28, 2017, Public Meeting with Entergy Nuclear Operations, Inc. Regarding a Potential Request Associated with an Alternative to the Reexamination Frequency for a Relevant Condition ML17335A0262017-12-0505 December 2017 Summary of November 27, 2017 Public Meeting with Entergy Nuclear Operations, Inc. Regarding Request to Extend Enforcement Discretion for Tornado Missle Non-Confomances ML17227A2742017-08-14014 August 2017 Summary of the July 26, 2017, Public Meeting Regarding Palisades Nuclear Plant ML17173A7672017-07-28028 July 2017 Summary of 6/20/2017 Meeting with Entergy to Discuss Plan for Decommissioning Licensing Actions of Palisades, Pilgrim, Indian Point, Units 2 and 3, and Vermont Yankee ML17164A3112017-06-27027 June 2017 Summary of 06/12/2017, Pre-Submittal Meeting with Entergy Nuclear Operations, Inc. to Discuss Palisades Nuclear Plant Post Shutdown Emergency Plan and Administrative Technical Specification License Amendment Request ML17160A1812017-06-14014 June 2017 Summary of Conference Call with Palisades Nuclear Plant Regarding the Spring 2017 Steam Generator Inspections ML17080A1492017-03-23023 March 2017 Summary of March 20, 2017, Public Meeting with Entergy Nuclear Operations, Inc. Regarding the Cyber Security Plan Implementation Schedule ML16344A0862016-12-20020 December 2016 Summary of Public Meeting with Entergy Nuclear Operations, Inc. Regarding National Fire Protection Association Standard 805 ML16277A6772016-10-11011 October 2016 Summary of Public Meeting with Entergy Nuclear Operations, Inc. Regarding the Proposed Closure Plant for Generic Safety Issue 191, Assessment of Debris Accumulation on Pressurized Water Reactor (PWR) Sump Performance ML16182A5142016-06-30030 June 2016 Summary of the June 23, 2016, Public Meeting Regarding Palisades Nuclear Plant ML16127A1722016-05-0505 May 2016 6/23/16 Notice of Significant Public Meeting to Discuss Nrc'S End-of-Cycle Assessment of the Palisades Nuclear Plant Performance for the 2015 Calendar Year ML16035A4252016-03-0101 March 2016 Summary of January 25, 2016, Pre-Application Teleconference Meeting with Entergy Nuclear Operations to Discuss a Forthcoming License Amendment Request Regarding Steam Generator Cold Leg Alternate Repair Criteria at Palisades Nuclear Plant ( ML15294A2972015-10-27027 October 2015 Steam Generator Tube Inspection Discussion During Palisades 2015 (RF24) Outage (Preliminary Information) ML15294A2922015-10-27027 October 2015 Summary of Conference Call with Palisades Nuclear Plant Regarding the Fall 2015 Steam Generator Inspections ML15272A0652015-09-30030 September 2015 Summary of Telephone Conference on September 28, 2015, Verbal Authorization of Relief Request for Palisades Nuclear Plant ML15261A0392015-09-21021 September 2015 September 17, 2015, Summary of Telephone Conference Verbal Authorization of Relief Request for Palisades Nuclear Plant ML15119A0442015-05-0606 May 2015 Summary of April 14, 2015, Meeting with Entergy Nuclear Operations, Inc. on Plans for Volumetric Examinations of Primary Coolant System Alloy 600 Welds ML15118A0352015-04-27027 April 2015 Meeting Summary with Public to Discuss the 2014 Annual Assessment Results for Palisades Nuclear Plant ML15026A5202015-01-29029 January 2015 Summary of Palisades Nuclear Plant, June 24 - 28, 2013, Audit Associated with License Amendment Request to Transition to National Fire Protection Association 805 Standards (Tac No. MF0382) ML14192B3842014-07-11011 July 2014 Summary of Public Meeting Regarding Palisades Nuclear Plant to Discuss 2013 Annual Assessment ML14093A2432014-04-30030 April 2014 Summary of Conference Call with Palisades Nuclear Plant Regarding the Fall 2014 Steam Generator Inspections ML13347B2862013-12-13013 December 2013 Summary of Public Meeting Webinar Regarding Independent Spent Fuel Storage Installation (ISFSI) Basics ML13296A5402013-10-28028 October 2013 Summary of Pre-Application Teleconference Meeting with Entergy Nuclear Operations, Inc., to Discuss a Forthcoming Palisades Equivalent Margin Analysis Submittal ML13221A5962013-08-0909 August 2013 7/16/2013 - Summary of Public Internet Event Briefing Regarding Palisades Safety Injection Refueling Water Tank (SIRWT) Leak ML13165A2422013-06-13013 June 2013 Summary of Public Meeting Webinar to Discuss Nrc'S Perspectives on Palisades Nuclear Power Plant Effluents 2024-01-23
[Table view] |
Text
U.S. Nuclear Regulatory Commission Public Meeting Summary October 31, 2022
Title:
Palisades Nuclear Plant Post-Shutdown Decommissioning Activities Report Public Meeting (EPID L-2022-LRO-0073)
Meeting Identifier: 20220887 Dates and Time of Meeting: September 22, 2022, from 6 p.m. to 8 p.m. EDT (hybrid)
Location: Lake Michigan College, South Haven Campus, 125 Veterans Boulevard, South Haven, Michigan, and via Microsoft Teams Type of Meeting: Comment-Gathering Purpose of the Meeting:
The purpose of this meeting was to discuss and receive public comments on the Palisades Nuclear Plant (Palisades) post-shutdown decommissioning activities report (PSDAR), which includes the site-specific decommissioning cost estimate (DCE). The Palisades PSDAR was submitted by Holtec Decommissioning International, LLC (HDI, the licensee) and is available in the U.S. Nuclear Regulatory Commission's (NRCs) Agencywide Documents Access and Management System (ADAMS) under Accession No. ML20358A232.
General Details:
A notice of receipt, availability, the purpose of the public meeting, and request for comments on the Palisades PSDAR was published in the Federal Register on August 26, 2022 (87 FR 52598), which requested that all comments on the Palisades PSDAR and DCE be submitted by December 27, 2022 (see the docket for the Palisades PSDAR at Docket ID NRC-2022-0158).
On August 26, 2022 (ML22242A279), the hybrid meeting notice and meeting agenda were posted on the NRC public web page. A press release was issued on September 9, 2022 (NRC News Release No.22-037). The meeting was also transcribed (ML22292A263).
Summary of Meeting:
The NRC Headquarters staff opened the meeting with a presentation that discussed the reactor decommissioning program, provided a brief decommissioning status for Palisades, and gave an overview of the PSDAR requirements and content of the HDI PSDAR for the Palisades plant.
NRC staff from the Region III office in Lisle, Illinois, then discussed the inspection program for decommissioning reactors, and NRC Headquarters staff explained the NRCs PSDAR review process and relayed details for providing public comment on the Palisades PSDAR and DCE
outside the public meeting. A copy of the presentation slides used for the meeting can be found in ADAMS at Accession No. ML22262A303; these slides were made available to the public in ADAMS and on the NRCs public meeting webpage prior to the meeting.
Following the presentations, the meeting was dedicated to answering questions on the decommissioning program and the NRC staff review process for the Palisades PSDAR and DCE, as well as receiving comments from members of the public. Approximately 120 attendees participated in-person or virtually via Teams. Of the comments related to the Palisades decommissioning plans, many focused on decommissioning funding adequacy, spent fuel storage, inspection, maintenance, and security considerations, groundwater monitoring and effluent release concerns, and the impacts of waste removal from the site via barge. However, numerous comments were also received opposed to, or supportive of, the potential for the Palisades plant to continue operation by taking advantage of the U.S. Department of Energys Civil Nuclear Credit program to pursue restart. While these comments were out of scope for the Palisades PSDAR meeting, they are captured in the meeting transcript.
Action Items/Next Steps:
The NRC staff will consider the comments provided during this meeting as part of its review of the Palisades PSDAR and DCE, as appropriate. Please contact me with any inquiries at 301-415-3178 or via e-mail at marlayna.doell@nrc.gov.
Sincerely, Signed by Doell, Marlayna on 10/31/22 Marlayna V. Doell, Project Manager Reactor Decommissioning Branch Division of Decommissioning, Uranium Recovery and Waste Programs Office of Nuclear Material Safety and Safeguards Docket No. 50-255 License No. DPR-20 cc: Palisades ListServ
ML22292A260; ML22292A261 OFFICE NMSS/DUWP/RDB R-III/DNMS/MCID NMSS/DUWP/RDB NMSS/DUWP/RDB NAME MDoell MD REdwards RE BWatson BW SAnderson SA DATE Oct 19, 2022 Oct 21, 2022 Oct 28, 2022 Oct 31, 2022 OFFICE NMSS/DUWP/RDB NAME MDoell MD DATE Oct 31, 2022