Summary of the July 1, 2021, Public Outreach to Discuss the NRC 2020 End-of-Cycle Plant Performance Assessment of Palisades Nuclear Plant
ML21200A226
Person / Time
Site: Palisades Entergy icon.png
Issue date: 07/19/2021
From: Billy Dickson
NRC/RGN-III/DRP/RPB2
To:
Entergy Nuclear Operations
Shared Package
ML21050A355 List:
References
Download: ML21200A226 (4)


Text

July 19, 2021 LICENSEE: ENTERGY NUCLEAR OPERATIONS, INC.

FACILITY: PALISADES NUCLEAR PLANT

SUBJECT:

SUMMARY

OF THE JULY 1, 2021, PUBLIC OUTREACH TO DISCUSS THE NRC 2020 END-OF-CYCLE PLANT PERFORMANCE ASSESSMENT OF PALISADES NUCLEAR PLANT On July 1, 2021, from 6:00 p.m. to 7:00 p.m. (EDT), representatives of the U.S. Nuclear Regulatory Commission (NRC) held a public webinar to provide the public with information on the 2020 End-of-Cycle plant performance assessment of the Palisades Nuclear Plant, and general information on the NRC. The NRC representatives discussed plant performance with members of the public and state and local government officials listed in the attached enclosure.

The NRC discussed their assessment of the Palisades Nuclear Plant, as documented in the March 4, 2021, End-of-Cycle Assessment Letter (ADAMS Accession Number ML21060B528).

Representatives from the NRC made links to that letter, inspection reports, fact sheets and brochures, and other public documents available to those in attendance. During the Question and Answer session of the webinar, representatives from the NRC discussed various topics of public interest. The presentation for this webinar is available in ADAMS, Accession Number ML21196A087.

___/RA/_________________

B. Dickson, Chief Branch 2 Division of Reactor Projects Docket Nos. 50-255 License No. DPR-20 cc: Distribution via LISTSERV

SUBJECT:

SUMMARY

OF THE JULY 1, 2021, PUBLIC OUTREACH TO DISCUSS THE NRC 2020 END-OF-CYCLE PLANT PERFORMANCE ASSESSMENT OF PALISADES NUCLEAR PLANT DISTRIBUTION:

Jessie Quichocho Aaron McCraw RidsNrrPMPalisades Resource RidsNrrDorlLpl3 RidsNrrDroIrib Resource John Giessner Mohammed Shuaibi Jamnes Cameron Allan Barker DRPIII DRSIII ROPassessment.Resource@nrc.gov ADAMS Accession Number: ML21200A226 OFFICE RIII RIII NAME RRuiz:ve via email BDickson via email DATE 7/16/2021 7/19/2021 OFFICIAL RECORD COPY

PUBLIC WEBINAR ATTENDEES July 1, 2021 U.S. Nuclear Regulatory Commission B. Dickson, Chief, Branch 2, Division of Reactor Projects R. Ruiz, Senior Project Engineer P. LaFlamme, Senior Resident Inspector, Palisades Nuclear Plant C. St. Peters, Resident Inspector, Palisades Nuclear Plant S. Wall, Senior Project Manager, Office of Nuclear Reactor Regulation V. Mitlyng, Senior Public Affairs Officer P. Chandrathil, Public Affairs Officer D. Hills, Chief, Materials Control, ISFSI, and Decommissioning, Division of Nuclear Materials Safety J. Dalzell, Reactor Inspector (Decommissioning)

R. Edwards, Senior Health Physicist V. Myers, Senior Health Physicist H. Logaras, Regional Government Liaison Specialist S. Orth, Chief, Plant Support Branch, Division of Reactor Safety C. Wolf, Congressional Affairs Officer C. Hernandez, Resident Office Assistant, Palisades Nuclear Plant Entergy Nuclear Operations, Inc.

D. Corbin N. Culp B. Dotson O. Gustafson J. Giddens T. Mulford State of Michigan/Berrien County R. Adams, Berrien County J. Faul, Berrien County G. Gothard, Environment, Great Lakes, and Energy, State of Michigan J. Zordan, Michigan Public Health Members of the Public M. Chappell P. Couture S. DeSantis E. Everett, American Nuclear Insurers R. Gaston J. Gordon K. Kamps, Beyond Nuclear, Dont Waste Michigan M. Kirk D.L.

R. Massa M. Middaugh 1 Enclosure

Members of the Public (continued)

J. Pfabe J. Quinn K. Schultz, Michigan Safe Energy Future R. VanGilder, WOOD-TV, Grand Rapids 2 Enclosure