| {{#Wiki_filter:NRC MeetingRevise Footnote in TS 3.8.1March 3, 2011 Xcel Energy ParticipantsJon Anderson Regulatory Affairs ManagerCorey Hessen General Manager -EngineeringThomas Roddey Prairie Island Site Engineering DirectorMarcia Thompson Project SponsorBob Flaaen Plant Engineering Interface Dale Vincent Licensing Engineer AgendaIntroductions-Jon AndersonMeeting purpose-Jon AndersonScope of LAR-Jon AndersonLAR Background-Dale VincentProposed TS and Bases changes -Dale VincentBattery Charger Modification -Marcia ThompsonBasis for Alternative Modification-Marcia ThompsonRequested Schedule Basis-Thomas RoddeyRAI discussion-Dale VincentSummary -Thomas Roddey Meeting GoalsDiscuss LAR to revise SR 3.8.1.10.c footnoteProvide technical basis for battery charger modificationSchedule basis Scope of LARRevise footnoteBattery charger modification under 10 CFR 50.59 LAR Background -112 Battery Charger manual actions identifiedD2 operability question Exigent LAR October 14, 2010SR 3.8.1.10.c footnote added LAR Background -2October 2010 LAR stated:NSPM is planning a modification to the 12 Battery Charger that will automatically shed the battery charger during an undervoltage event (e.g. LOOP, SI with LOOP or other undervoltage condition) and then repower the battery charger back on the bus within the 60 seconds required by the current TS. | | {{#Wiki_filter:NRC Meeting Revise Footnote in TS 3.8.1 March 3, 2011 |
| LAR Background -3Current SR 3.8.1.10.c footnote:A modification will be installed during or prior to the Unit 1 2011 refueling outage to automatically shed the 12 Battery Charger from its normal bus and then automatically repower the charger from the bus within 60 seconds. Compliance with this SR will be demonstrated after implementation of the modification. | | |
| Proposed TS and Bases Changes -1Revise SR 3.8.1.10.c footnote to read:A modification will be installed during or prior to the Unit 1 2011 refueling outage to assure the 12 Battery Charger is automatically powered from its normal bus within 60 seconds. Compliance with this SR will be demonstrated after implementation of the modification. | | Xcel Energy Participants Jon Anderson - Regulatory Affairs Manager Corey Hessen - General Manager - Engineering Thomas Roddey - Prairie Island Site Engineering Director Marcia Thompson - Project Sponsor Bob Flaaen - Plant Engineering Interface Dale Vincent - Licensing Engineer |
| Proposed TS and Bases Changes -2Revise SR 3.8.1.10 Bases:Note 3 is provided to allow D2 DG to be OPERABLE without requiring the 12 Battery Charger to be energized until completion of the Unit 1 2011 refueling outage. | | |
| Battery Charger Modification -1 Battery Charger Study options (October 2010):1.SI contact2.New chargers3.C&D Technologies, Inc. battery charger control modification4.Low voltage relay control modification5.Charger output based control modification Battery Charger Modification -2 Selected modifications 1 and 4Most viable Equipment external to chargersOpening/closing power supply breaker to charger based on charger input voltageAutomatic shedding and repowering of the chargers NSPM approved modification concept Early December 2010 Battery Charger Modification -3 PBNP Ametek SCI chargerNot susceptible to the C&D charger lockupIdentified late December 2010Could meet PINGP performance requirements Would not meet PINGP seismic and physical dimension requirements Battery Charger Modification -4 VEGP Ametek SCI chargerIdentified during reviews with AmetekMeets PINGP design and performance requirementsProcure on expedited schedule Battery Charger Modification -5 Internal control features of the Ametek SCI chargers Not susceptible to conditions which cause PINGP charger lockupInternal control relay Prevent back feeding control circuit board Relay senses incoming AC line voltageShut off charger -AC voltage below relay dropout setpointRestart charger -voltage returns above pickup setpointInstantaneous shutoff Time delay on reset -a few seconds Battery Charger Modification -6 PBNP prototype Ametek battery charger testingPINGP has known voltage variations outside nameplate ratingInformational testing January 2011Confirm engineering design review of the control circuit operationEquipped with internal control function Demonstrate charger capabilities, operation, shutdown, and automatic restart during anticipated voltage transients outside the nameplate rating of the chargers. | | Agenda |
| Battery Charger Modification -7 Factory Acceptance Testing (April 2011)Per Ametek quality assurance program Specified in NSPM purchase orderFormal documentation of charger capabilitiesshut off and reset setpointstime delaysother operating requirements Battery Charger Modification -8 Ametek SCI battery charger controls accommodate AC input voltage variations SR 3.8.1.10 footnote specifically statesmodification will be installed to automatically its busSR 3.8.1.10 footnote requires revision to allow installation of the Ametek SCI battery charger Battery Charger Modification -9 Schedule MilestonesIssue Ametek contract for Unit 1 chargers Unit 1 30% EC Design Review meetingUnit 1 90% EC Design Review meetingBattery charger shipped to PINGP Start Unit 1 2011 outageUnit 1 outage installation and post-modification testingUnit 1 integrated SI test Basis for Alternative Modification -1Battery charger considerations:Required logic internal to chargerModification performed in controlled shop environment Testing performed in advance of installation Basis for Alternative Modification -2Plant design considerations:Simpler design Spare breaker on Bus 16 preservedMaintenance sources at the 480V level preservedRelay setting or logic design coordination not required Basis for Alternative Modification -3Plant modification considerations:Simpler installationFocus Engineering and procurement resourcesReduces procurement riskAvoid: new power cable installationfire penetration work when routing new cablesadditions to the load sequencer cabinets Reduces outage work time and outage testing time Requested Schedule Basis -1Refueling outage scheduleRequest review and approval by May 6, 2011 Current footnote specifies resolution by end of Unit 1 2011 refueling outageTesting performed after modification Requested Schedule Basis -2Battery charger replacement decision January 2011 LAR submitted approximately one week after decision RAI discussion -11.Provide a comparison of the major electrical parameters including the minimum voltage requirement of the alternating current (AC) input breaker, drop out, reset for the existing and proposed new battery chargers. Discuss in detail the electrical parameters for the proposed new charger that are different than the existing 12 charger and how these parameters were determined to be acceptable. 2.Discuss whether the description of existing and new battery chargers will be provided in a future revision of the PINGP Updated Final Safety Analysis Report (UFSAR). 3.Confirm that the proposed new battery charger can recharge its associated battery to the fully charged state within 24 hours while supplying its normal loads after a battery discharge to the bounding design basis event discharge state in accordance with PINGP UFSAR Section 8.5.3 and Technical Specification Surveillance Requirement 3.8.4.2. | | * Introductions -Jon Anderson |
| RAI discussion -24.Industry operating experience has shown that momentary overvoltage or undervoltage transients experienced during switching, fault or lightning-related perturbations can trigger a self-protecting lockout feature in battery chargers resulting in disabling the chargers. Provide details on the magnitude and duration of transient and sustained overvoltage/undervoltage conditions resulting from grid perturbations (or the emergency diesel generator system) that have been evaluated for operation of the proposed battery charger. 5.Technical Specification SR 3.8.1.10 NOTE 3 states that the 12 Battery Charger is not required to be energized during performance of SR 3.8.1.10(c) until the completion of Unit 1 2011 refueling outage. The license amendment request proposes a footnote stating that the battery charger equipment will be modified during or prior to the Unit 1 2011 refueling outage. State why NOTE 3 was not modified to apply only until the new equipment has been installed and tested. | | * Meeting purpose -Jon Anderson |
| RAI discussion -3Proposed response scheduleTwo weeks from receipt of letter SummaryTS require 12 Battery Charger modification during Unit 1 2011 refueling outage Battery charger replacement modification assures battery charger function performed This LAR proposes to revise footnote to allow battery charger replacement modificationExpedited review and approval requested}} | | * Scope of LAR -Jon Anderson |
| | * LAR Background -Dale Vincent |
| | * Proposed TS and Bases changes -Dale Vincent |
| | * Battery Charger Modification -Marcia Thompson |
| | * Basis for Alternative Modification -Marcia Thompson |
| | * Requested Schedule Basis -Thomas Roddey |
| | * RAI discussion -Dale Vincent |
| | * Summary -Thomas Roddey |
| | |
| | Meeting Goals |
| | * Discuss LAR to revise SR 3.8.1.10.c footnote |
| | * Provide technical basis for battery charger modification |
| | * Schedule basis |
| | |
| | Scope of LAR |
| | * Revise footnote |
| | * Battery charger modification under 10 CFR 50.59 |
| | |
| | LAR Background -1 |
| | * 12 Battery Charger manual actions identified |
| | * D2 operability question |
| | * Exigent LAR October 14, 2010 |
| | * SR 3.8.1.10.c footnote added |
| | |
| | LAR Background - 2 |
| | * October 2010 LAR stated: |
| | NSPM is planning a modification to the 12 Battery Charger that will automatically shed the battery charger during an undervoltage event (e.g. |
| | LOOP, SI with LOOP or other undervoltage condition) and then repower the battery charger back on the bus within the 60 seconds required by the current TS. |
| | |
| | LAR Background - 3 |
| | * Current SR 3.8.1.10.c footnote: |
| | A modification will be installed during or prior to the Unit 1 2011 refueling outage to automatically shed the 12 Battery Charger from its normal bus and then automatically repower the charger from the bus within 60 seconds. Compliance with this SR will be demonstrated after implementation of the modification. |
| | |
| | Proposed TS and Bases Changes - 1 |
| | * Revise SR 3.8.1.10.c footnote to read: |
| | A modification will be installed during or prior to the Unit 1 2011 refueling outage to assure the 12 Battery Charger is automatically powered from its normal bus within 60 seconds. Compliance with this SR will be demonstrated after implementation of the modification. |
| | |
| | Proposed TS and Bases Changes - 2 |
| | * Revise SR 3.8.1.10 Bases: |
| | Note 3 is provided to allow D2 DG to be OPERABLE without requiring the 12 Battery Charger to be energized until completion of the Unit 1 2011 refueling outage. |
| | |
| | Battery Charger Modification - 1 |
| | * Battery Charger Study options (October 2010): |
| | : 1. SI contact |
| | : 2. New chargers |
| | : 3. C&D Technologies, Inc. battery charger control modification |
| | : 4. Low voltage relay control modification |
| | : 5. Charger output based control modification |
| | |
| | Battery Charger Modification - 2 |
| | * Selected modifications 1 and 4 |
| | - Most viable |
| | - Equipment external to chargers |
| | - Opening/closing power supply breaker to charger based on charger input voltage |
| | - Automatic shedding and repowering of the chargers |
| | * NSPM approved modification concept |
| | - Early December 2010 |
| | |
| | Battery Charger Modification - 3 |
| | * PBNP Ametek SCI charger |
| | - Not susceptible to the C&D charger lockup |
| | - Identified late December 2010 |
| | - Could meet PINGP performance requirements |
| | - Would not meet PINGP seismic and physical dimension requirements |
| | |
| | Battery Charger Modification - 4 |
| | * VEGP Ametek SCI charger |
| | - Identified during reviews with Ametek |
| | - Meets PINGP design and performance requirements |
| | - Procure on expedited schedule |
| | |
| | Battery Charger Modification - 5 |
| | * Internal control features of the Ametek SCI chargers |
| | - Not susceptible to conditions which cause PINGP charger lockup |
| | - Internal control relay |
| | - Prevent back feeding control circuit board |
| | - Relay senses incoming AC line voltage |
| | * Shut off charger - AC voltage below relay dropout setpoint |
| | * Restart charger - voltage returns above pickup setpoint |
| | - Instantaneous shutoff |
| | - Time delay on reset - a few seconds |
| | |
| | Battery Charger Modification - 6 |
| | * PBNP prototype Ametek battery charger testing |
| | - PINGP has known voltage variations outside nameplate rating |
| | - Informational testing January 2011 |
| | - Confirm engineering design review of the control circuit operation |
| | - Equipped with internal control function |
| | - Demonstrate charger capabilities, operation, shutdown, and automatic restart during anticipated voltage transients outside the nameplate rating of the chargers. |
| | |
| | Battery Charger Modification - 7 |
| | * Factory Acceptance Testing (April 2011) |
| | - Per Ametek quality assurance program |
| | - Specified in NSPM purchase order |
| | - Formal documentation of charger capabilities |
| | * shut off and reset setpoints |
| | * time delays |
| | * other operating requirements |
| | |
| | Battery Charger Modification - 8 |
| | * Ametek SCI battery charger controls accommodate AC input voltage variations |
| | * SR 3.8.1.10 footnote specifically states |
| | - modification will be installed to automatically shed and repower the 12 Battery Charger from its bus |
| | * SR 3.8.1.10 footnote requires revision to allow installation of the Ametek SCI battery charger |
| | |
| | Battery Charger Modification - 9 |
| | * Schedule Milestones |
| | - Issue Ametek contract for Unit 1 chargers |
| | - Unit 1 30% EC Design Review meeting |
| | - Unit 1 90% EC Design Review meeting |
| | - Battery charger shipped to PINGP |
| | - Start Unit 1 2011 outage |
| | - Unit 1 outage installation and post-modification testing |
| | - Unit 1 integrated SI test |
| | |
| | Basis for Alternative Modification - 1 |
| | * Battery charger considerations: |
| | - Required logic internal to charger |
| | - Modification performed in controlled shop environment |
| | - Testing performed in advance of installation |
| | |
| | Basis for Alternative Modification - 2 |
| | * Plant design considerations: |
| | - Simpler design |
| | - Spare breaker on Bus 16 preserved |
| | - Maintenance sources at the 480V level preserved |
| | - Relay setting or logic design coordination not required |
| | |
| | Basis for Alternative Modification - 3 |
| | * Plant modification considerations: |
| | - Simpler installation |
| | - Focus Engineering and procurement resources |
| | - Reduces procurement risk |
| | - Avoid: |
| | * new power cable installation |
| | * fire penetration work when routing new cables |
| | * additions to the load sequencer cabinets |
| | - Reduces outage work time and outage testing time |
| | |
| | Requested Schedule Basis - 1 |
| | * Refueling outage schedule |
| | * Request review and approval by May 6, 2011 |
| | * Current footnote specifies resolution by end of Unit 1 2011 refueling outage |
| | - Testing performed after modification |
| | |
| | Requested Schedule Basis - 2 |
| | * Battery charger replacement decision January 2011 |
| | * LAR submitted approximately one week after decision |
| | |
| | RAI discussion - 1 |
| | : 1. Provide a comparison of the major electrical parameters including the minimum voltage requirement of the alternating current (AC) input breaker, drop out, reset for the existing and proposed new battery chargers. Discuss in detail the electrical parameters for the proposed new charger that are different than the existing 12 charger and how these parameters were determined to be acceptable. |
| | : 2. Discuss whether the description of existing and new battery chargers will be provided in a future revision of the PINGP Updated Final Safety Analysis Report (UFSAR). |
| | : 3. Confirm that the proposed new battery charger can recharge its associated battery to the fully charged state within 24 hours while supplying its normal loads after a battery discharge to the bounding design basis event discharge state in accordance with PINGP UFSAR Section 8.5.3 and Technical Specification Surveillance Requirement 3.8.4.2. |
| | |
| | RAI discussion - 2 |
| | : 4. Industry operating experience has shown that momentary overvoltage or undervoltage transients experienced during switching, fault or lightning-related perturbations can trigger a self-protecting lockout feature in battery chargers resulting in disabling the chargers. Provide details on the magnitude and duration of transient and sustained overvoltage/undervoltage conditions resulting from grid perturbations (or the emergency diesel generator system) that have been evaluated for operation of the proposed battery charger. |
| | : 5. Technical Specification SR 3.8.1.10 NOTE 3 states that the 12 Battery Charger is not required to be energized during performance of SR 3.8.1.10(c) until the completion of Unit 1 2011 refueling outage. The license amendment request proposes a footnote stating that the battery charger equipment will be modified during or prior to the Unit 1 2011 refueling outage. State why NOTE 3 was not modified to apply only until the new equipment has been installed and tested. |
| | |
| | RAI discussion - 3 |
| | * Proposed response schedule |
| | - Two weeks from receipt of letter |
| | |
| | Summary |
| | * TS require 12 Battery Charger modification during Unit 1 2011 refueling outage |
| | * Battery charger replacement modification assures battery charger function performed |
| | - does not involve shedding per TS footnote |
| | * This LAR proposes to revise footnote to allow battery charger replacement modification |
| | * Expedited review and approval requested}} |
Letter Sequence Meeting |
---|
|
|
MONTHYEARL-PI-10-098, Exigent License Amendment Request to Modify Technical Specifications Surveillance Requirement 3.8.1.102010-10-14014 October 2010 Exigent License Amendment Request to Modify Technical Specifications Surveillance Requirement 3.8.1.10 Project stage: Request L-PI-11-016, License Amendment Request (LAR) to Revise Surveillance Requirement (SR) Footnote in Technical Specification (TS) 3.8.1, AC Sources - Operating.2011-02-0303 February 2011 License Amendment Request (LAR) to Revise Surveillance Requirement (SR) Footnote in Technical Specification (TS) 3.8.1, AC Sources - Operating. Project stage: Request ML1104702792011-02-16016 February 2011 Notice of Forthcoming Meeting with Licensee for Prairie Island Nuclear Generating Plant, Unit 1 to Discuss License Amendment Request to Revise Surveillance Requirement Footnote in Technical Specification 3.8.1, AC Sources - Operating. Project stage: Meeting ML1104904292011-02-16016 February 2011 Acceptance Review of LAR to Revise Surveillance Requirement (SR) Footnote in Technical Specification (TS) 3.8.1, AC Sources - Operating Project stage: Acceptance Review ML1106600792011-03-0303 March 2011 March 3, 2011 Meeting Handouts - Revise Footnote in TS 3.8.1, Prairie Island Nuclear Generating Plant Project stage: Meeting ML1106104752011-03-0404 March 2011 Request for Additional Information Related to Request to Revise the Technical Specification 3.8.1, AC Sources - Operating, Footnote Requiring Battery Charger Modifications Project stage: RAI L-PI-11-024, Supplement to License Amendment Request (LAR) to Revise Surveillance Requirement (SR) Footnote in Technical Specification (TS) 3.8.1, AC Sources - Operating.2011-03-15015 March 2011 Supplement to License Amendment Request (LAR) to Revise Surveillance Requirement (SR) Footnote in Technical Specification (TS) 3.8.1, AC Sources - Operating. Project stage: Supplement ML1107401932011-03-22022 March 2011 Summary of March 3, 2011, Meeting to Discuss the Licensee'S February 3, 2011, License Amendment Request to Revise Surveillance Requirement Footnote in Technical Specification 3.8.1, AC Sources - Operating. Project stage: Meeting ML1110205512011-04-29029 April 2011 Issuance of Amendment Revision to Surveillance Requirements Footnote in Technical Specification 3.8.1, AC Sources - Operating Project stage: Approval 2011-03-15
[Table View] |
|
---|
Category:Meeting Briefing Package/Handouts
MONTHYEARML24127A2402024-05-0707 May 2024 Presentation Slides for Prairie Island 2023 End-of-Cycle Meeting ML24029A0382024-01-31031 January 2024 January 31, 2024, Pre-application Meeting Presentation - Prairie Island ISFSI License Amendment Request to Add Grace to License Conditions ML23168A0032023-06-20020 June 2023 Handout for 6/23/2023 Pre-Application Public Meeting with Prairie Island Nuclear Generating Plant to Revise ISFSI TS 4.4 for TN-40HT Casks ML23156A2602023-06-0505 June 2023 2022 Prairie Island End-of-Cycle Meeting Presentation ML23102A1752023-04-14014 April 2023 April 14, 2023 TS 3.7.8 LAR Pre-Submittal Meeting Slides ML22130A5852022-05-10010 May 2022 2021 Monticello and Prairie Island Nuclear Generating Plant End-of-Cycle Meeting Presentation ML22048B1812022-02-18018 February 2022 Pre-Application Meeting for Prairie Island TS 5.6.6, PTLR, LAR ML21221A0202021-08-11011 August 2021 Nis Pr Bypass Test Panel License Amendment Request ML21166A3792021-06-15015 June 2021 Units 1 and 2 2020 End-of-Cycle Meeting Presentation ML21032A2632021-02-0303 February 2021 Slides for Public Meeting with Xcel Energy to Discuss a Planned Amendment to Combine the Emergency Plans and Create a Common Emergency Offsite Facility for Monticello and Prairie Island ML19347B0722019-12-12012 December 2019 TVA and Xcel Energy Slides for Joint Presubmittal Meeting to License Amendment Requests to Adopt WCAP-17661, Revision 1 ML19268A0422019-09-26026 September 2019 Pre-Application Meeting License Amendment Request Revise Technical Specifications to Adopt Risk Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b ML19210D4512019-07-22022 July 2019 Abeyance Seal Preapplication Meeting Slides ML18051A1752018-02-20020 February 2018 Pre-Application Meeting License Amendment for TSTF-425 Relocation of Specific Surveillance Frequency Requirements to a Licensee Controlled Program Xcel Energy 2/20/2018 ML17240A3382017-08-30030 August 2017 Non-Safety Related Digital Feedwater and Amsac/Dss Control Systems Replacement Project Presentation ML17198A2632017-07-17017 July 2017 Pre-Application Meeting ML17066A3732017-03-0909 March 2017 Spent Fuel Pool Criticality Technical Specification Changes Round 2 Request for Additional Information Public Meeting: March 9, 2017 ML17037D1172017-02-0707 February 2017 License Amendment Requests for Change in Emergency Plan Staff Augmentation Response Times Pre-Submittal Meeting for Prairie Island Nuclear Generating Plant Monticello Nuclear Generating Plant: February 7, 2017 ML17023A0652017-01-24024 January 2017 Pre-Submittal Call Regarding License Amendment Requests for Prairie Island Nuclear Generating Plant, Units 1 and 2 and Monticello Nuclear Generating Plant Emergency Action Level Scheme Changes ML15140A3342015-05-13013 May 2015 Public Meeting 05132015 Licensee Slides Only ML15105A0372015-04-14014 April 2015 Xcel Energy Slide Presentation to Support Pre-Application Meeting on April 14, 2015, to Discuss Nuclear Fuel Design Transition to Include Integral Fuel Burnable Absorber (Ifba) at the Prairie Island Nuclear Generating Plant ML14323B0222014-11-19019 November 2014 Regcon, November 19-20, 2014: 03-Info-Session-2 Ronald Johnson - Tribal Perspective on Continued Storage ML14153A0242014-05-16016 May 2014 Xcel Energy'S Presentation Slides Supporting a May 16, 2014, Public Meeting to Discuss the Flood Hazard Reevaluation Schedule for the Monticello and Prairie Island Nuclear Generating Plants ML14058A1732014-02-19019 February 2014 Diesel Generator Steady State Voltage and Frequency Limits - Prairie Island Nuclear Generating Plant Meeting February 19, 2014 ML13210A2012013-07-29029 July 2013 2012 End-of-Cycle Slides - Licensee ML13210A2002013-07-11011 July 2013 2012 End-of-Cycle Slides ML13056A0262013-02-25025 February 2013 Regulatory Conference Slide Presentation ML12340A5402012-12-0606 December 2012 Reactor Core Cooling & Heat Removal FLEX Strategy - Phase 1 ML12326A9712012-11-21021 November 2012 Encl 3 (Handouts - Public) to Summary of October 24, 2012, Meeting with the Northern States Power Company, D/B/A Excel Energy Regarding Security Requirements and Changes Pertaining to Prairie Island TAC L24689 ML12277A1762012-10-0404 October 2012 Steam Generator Replacement Presentation ML12275A4652012-09-27027 September 2012 Meeting September 27, 2012 - Handouts ML12275A3782012-09-27027 September 2012 Xcel Energy Prairie Island Nuclear Generating Plant Meeting Presentation, Diesel Generator Voltage and Frequency Limits. ML12205A2172012-07-23023 July 2012 NRC 2011 End-of-Cycle Slides ML12205A2202012-07-17017 July 2012 Licensee 2012 End-of-Cycle Slides ML12115A3112012-04-24024 April 2012 Meeting Slides: 04/24/2012 Meeting with Xcel Energy NFPA 805 Presubmittal - Prairie Island Nuclear Generating Plant ML1207904792012-03-14014 March 2012 March 14, 2012 Telecon Slides ML1122803892011-08-18018 August 2011 Pre-Application Meeting for Prairie Island Nuclear Generating Plant (Ping) Extended Power Uprate (EPU) ML1119903462011-07-28028 July 2011 Meeting Presentation, Prairie Island Nuclear Generating Plant - Failure to Maintain the Train a and B Direct Current Electrical Power Subsystems Operable ML1117804242011-06-22022 June 2011 June 22, 2011, Meeting Handout #1 - NRC Meeting Diesel Fuel Oil LAR for Prairie Island Ngp ML1120701572011-06-22022 June 2011 June 22, 2011, Meeting Handout #2 - Proposed Technical Specification Changes for Prairie Island Ngp Diesel Fuel Oil LAR ML1106600792011-03-0303 March 2011 March 3, 2011 Meeting Handouts - Revise Footnote in TS 3.8.1, Prairie Island Nuclear Generating Plant ML1034701142010-12-14014 December 2010 Excel Energy Slides for Public Meeting 12/14/2010 to Discuss Human Performance Issues ML1027802642010-10-0404 October 2010 Session 4 - Heather Westra Presentation at October 4, 2010, Public Meeting on Groundwater Protection ML1023805712010-08-25025 August 2010 Meeting Presentation Alternative Source Term Steam Generator Tube Rupture Margin to Overfill Evaluation - Prairie Island Nuclear Generating Plant ML1014502432010-05-26026 May 2010 Responses to Questions from the Prairie Island Indian Community Concerning Issues Related to Prairie Island Nuclear Generating Plant ML1012604192010-05-20020 May 2010 Meeting Presentation Prairie Island Annual Assessment Meeting - Reactor Oversight Program - 2009 ML1012503422010-05-0505 May 2010 Regulatory Conference Slides ML1015801072010-04-28028 April 2010 2R26 Outage, SG Tube Inspection Telecon Slides ML1010604782010-04-15015 April 2010 April 15, 2010, Meeting Slides - Pre-Application Meeting for Prairie Island Ngp Extended Power Uprate ML0932901282009-12-0101 December 2009 Licensee Slides for Public Meeting 2024-05-07
[Table view] Category:Slides and Viewgraphs
MONTHYEARML24127A2402024-05-0707 May 2024 Presentation Slides for Prairie Island 2023 End-of-Cycle Meeting ML24059A4042024-03-0606 March 2024 March 6, 2023, Presubmittal Meeting for License Amendment Request to Modify Technical Specifications Definitions & Approve Plant-Specific Methods for Response Time Testing (EPID L-2024-LRM-0034) - Slides ML24029A0382024-01-31031 January 2024 January 31, 2024, Pre-application Meeting Presentation - Prairie Island ISFSI License Amendment Request to Add Grace to License Conditions ML23168A0032023-06-20020 June 2023 Handout for 6/23/2023 Pre-Application Public Meeting with Prairie Island Nuclear Generating Plant to Revise ISFSI TS 4.4 for TN-40HT Casks ML23156A2602023-06-0505 June 2023 2022 Prairie Island End-of-Cycle Meeting Presentation ML23102A1752023-04-14014 April 2023 April 14, 2023 TS 3.7.8 LAR Pre-Submittal Meeting Slides ML22130A5852022-05-10010 May 2022 2021 Monticello and Prairie Island Nuclear Generating Plant End-of-Cycle Meeting Presentation ML22048B1812022-02-18018 February 2022 Pre-Application Meeting for Prairie Island TS 5.6.6, PTLR, LAR ML21166A3792021-06-15015 June 2021 Units 1 and 2 2020 End-of-Cycle Meeting Presentation ML21124A0652021-05-0606 May 2021 Xcel Energy Presentation for May 6, 2021 Public Meeting to Discuss 24-Month Cycles at Prairie Island Nuclear Generating Plant, Units 1 and 2 ML21032A2632021-02-0303 February 2021 Slides for Public Meeting with Xcel Energy to Discuss a Planned Amendment to Combine the Emergency Plans and Create a Common Emergency Offsite Facility for Monticello and Prairie Island ML20266F1052020-09-23023 September 2020 (PINGP) COVID-19 Exemption Request for the 2020 Biennial Emergency Preparedness Exercise ML20212L8622020-07-29029 July 2020 2019 Monticello and Prairie Island EOC Presentation from Webinar ML20098F0682020-04-0909 April 2020 Preapplication Teleconference Presentation: License Amendment Request to Adopt TSTF-569 ML20057D3082020-02-18018 February 2020 Slides Potential License Amendment to Remove Note from LCO 3.4.12 and LCO 3.4.13 ML19268A0422019-09-26026 September 2019 Pre-Application Meeting License Amendment Request Revise Technical Specifications to Adopt Risk Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b ML19210D4512019-07-22022 July 2019 Abeyance Seal Preapplication Meeting Slides ML19071A2782019-03-0707 March 2019 Enclosure 3: Meeting Slides (Summary of February 28, 2019, Public Meeting with Xcel Energy to Discuss Increasing the Amount of Special Nuclear Material Authorized for Storage at the Prairie Island ISFSI (W/Enclosures 1 and 2)) ML18162A0262018-06-12012 June 2018 License Amendment Request to Reclassify Certain Fuel Handling Equipment ML18051A1752018-02-20020 February 2018 Pre-Application Meeting License Amendment for TSTF-425 Relocation of Specific Surveillance Frequency Requirements to a Licensee Controlled Program Xcel Energy 2/20/2018 ML17240A3382017-08-30030 August 2017 Non-Safety Related Digital Feedwater and Amsac/Dss Control Systems Replacement Project Presentation ML17209A1192017-07-17017 July 2017 Summary of July 17, 2017, Meeting with Northern States Power Company, Doing Business as Xcel Energy, on Potential License Amendment Request Related to Heavy Lifting Devices ML17198A2632017-07-17017 July 2017 Pre-Application Meeting ML17066A3732017-03-0909 March 2017 Spent Fuel Pool Criticality Technical Specification Changes Round 2 Request for Additional Information Public Meeting: March 9, 2017 ML17037D1172017-02-0707 February 2017 License Amendment Requests for Change in Emergency Plan Staff Augmentation Response Times Pre-Submittal Meeting for Prairie Island Nuclear Generating Plant Monticello Nuclear Generating Plant: February 7, 2017 ML17023A0652017-01-24024 January 2017 Pre-Submittal Call Regarding License Amendment Requests for Prairie Island Nuclear Generating Plant, Units 1 and 2 and Monticello Nuclear Generating Plant Emergency Action Level Scheme Changes ML16280A0372016-09-29029 September 2016 Flood Hazard Reevaluation Report - Response to Requested Information (CAC Nos. MF7710 and MF7711) - Figure 2 of 3 ML16280A0422016-09-29029 September 2016 Flood Hazard Reevaluation Report - Response to Requested Information (CAC Nos. MF7710 and MF7711) - Figure 3 of 3 ML16280A0352016-09-29029 September 2016 Flood Hazard Reevaluation Report - Response to Requested Information (CAC Nos. MF7710 and MF7711) - Figure 1 of 3 ML15140A3342015-05-13013 May 2015 Public Meeting 05132015 Licensee Slides Only ML15127A6562015-05-0707 May 2015 PI EOC Mtg NRC Slides ML15105A0372015-04-14014 April 2015 Xcel Energy Slide Presentation to Support Pre-Application Meeting on April 14, 2015, to Discuss Nuclear Fuel Design Transition to Include Integral Fuel Burnable Absorber (Ifba) at the Prairie Island Nuclear Generating Plant ML14323B0222014-11-19019 November 2014 Regcon, November 19-20, 2014: 03-Info-Session-2 Ronald Johnson - Tribal Perspective on Continued Storage ML14162A5202014-06-11011 June 2014 Slides: Prairie Island Independent Spent Fuel Storage Installation - License Renewal Application - Discussion of Requests for Additional Information, for June 16, 2014, Public Meeting ML14153A0242014-05-16016 May 2014 Xcel Energy'S Presentation Slides Supporting a May 16, 2014, Public Meeting to Discuss the Flood Hazard Reevaluation Schedule for the Monticello and Prairie Island Nuclear Generating Plants ML14084A3242014-03-21021 March 2014 M140321: Slides - Presented by Multiple Participants at Commission Briefing on Waste Confidence Rulemaking ML13210A2012013-07-29029 July 2013 2012 End-of-Cycle Slides - Licensee ML13210A2002013-07-11011 July 2013 2012 End-of-Cycle Slides ML13056A0262013-02-25025 February 2013 Regulatory Conference Slide Presentation ML12340A5402012-12-0606 December 2012 Reactor Core Cooling & Heat Removal FLEX Strategy - Phase 1 ML12326A9712012-11-21021 November 2012 Encl 3 (Handouts - Public) to Summary of October 24, 2012, Meeting with the Northern States Power Company, D/B/A Excel Energy Regarding Security Requirements and Changes Pertaining to Prairie Island TAC L24689 ML12277A1762012-10-0404 October 2012 Steam Generator Replacement Presentation ML12275A3782012-09-27027 September 2012 Xcel Energy Prairie Island Nuclear Generating Plant Meeting Presentation, Diesel Generator Voltage and Frequency Limits. ML12205A2172012-07-23023 July 2012 NRC 2011 End-of-Cycle Slides ML12205A2202012-07-17017 July 2012 Licensee 2012 End-of-Cycle Slides ML12115A3112012-04-24024 April 2012 Meeting Slides: 04/24/2012 Meeting with Xcel Energy NFPA 805 Presubmittal - Prairie Island Nuclear Generating Plant ML1207904792012-03-14014 March 2012 March 14, 2012 Telecon Slides ML1122803892011-08-18018 August 2011 Pre-Application Meeting for Prairie Island Nuclear Generating Plant (Ping) Extended Power Uprate (EPU) ML1119903462011-07-28028 July 2011 Meeting Presentation, Prairie Island Nuclear Generating Plant - Failure to Maintain the Train a and B Direct Current Electrical Power Subsystems Operable ML1117804242011-06-22022 June 2011 June 22, 2011, Meeting Handout #1 - NRC Meeting Diesel Fuel Oil LAR for Prairie Island Ngp 2024-05-07
[Table view] |
Text
NRC Meeting Revise Footnote in TS 3.8.1 March 3, 2011
Xcel Energy Participants Jon Anderson - Regulatory Affairs Manager Corey Hessen - General Manager - Engineering Thomas Roddey - Prairie Island Site Engineering Director Marcia Thompson - Project Sponsor Bob Flaaen - Plant Engineering Interface Dale Vincent - Licensing Engineer
Agenda
- Introductions -Jon Anderson
- Meeting purpose -Jon Anderson
- Scope of LAR -Jon Anderson
- LAR Background -Dale Vincent
- Proposed TS and Bases changes -Dale Vincent
- Battery Charger Modification -Marcia Thompson
- Basis for Alternative Modification -Marcia Thompson
- Requested Schedule Basis -Thomas Roddey
- RAI discussion -Dale Vincent
Meeting Goals
- Provide technical basis for battery charger modification
Scope of LAR
LAR Background -1
- 12 Battery Charger manual actions identified
- Exigent LAR October 14, 2010
LAR Background - 2
NSPM is planning a modification to the 12 Battery Charger that will automatically shed the battery charger during an undervoltage event (e.g.
LOOP, SI with LOOP or other undervoltage condition) and then repower the battery charger back on the bus within the 60 seconds required by the current TS.
LAR Background - 3
A modification will be installed during or prior to the Unit 1 2011 refueling outage to automatically shed the 12 Battery Charger from its normal bus and then automatically repower the charger from the bus within 60 seconds. Compliance with this SR will be demonstrated after implementation of the modification.
Proposed TS and Bases Changes - 1
A modification will be installed during or prior to the Unit 1 2011 refueling outage to assure the 12 Battery Charger is automatically powered from its normal bus within 60 seconds. Compliance with this SR will be demonstrated after implementation of the modification.
Proposed TS and Bases Changes - 2
Note 3 is provided to allow D2 DG to be OPERABLE without requiring the 12 Battery Charger to be energized until completion of the Unit 1 2011 refueling outage.
Battery Charger Modification - 1
- Battery Charger Study options (October 2010):
- 1. SI contact
- 2. New chargers
- 3. C&D Technologies, Inc. battery charger control modification
- 4. Low voltage relay control modification
- 5. Charger output based control modification
Battery Charger Modification - 2
- Selected modifications 1 and 4
- Most viable
- Equipment external to chargers
- Opening/closing power supply breaker to charger based on charger input voltage
- Automatic shedding and repowering of the chargers
- NSPM approved modification concept
- Early December 2010
Battery Charger Modification - 3
- Not susceptible to the C&D charger lockup
- Identified late December 2010
- Could meet PINGP performance requirements
- Would not meet PINGP seismic and physical dimension requirements
Battery Charger Modification - 4
- Identified during reviews with Ametek
- Meets PINGP design and performance requirements
- Procure on expedited schedule
Battery Charger Modification - 5
- Internal control features of the Ametek SCI chargers
- Not susceptible to conditions which cause PINGP charger lockup
- Internal control relay
- Prevent back feeding control circuit board
- Relay senses incoming AC line voltage
- Shut off charger - AC voltage below relay dropout setpoint
- Restart charger - voltage returns above pickup setpoint
- Instantaneous shutoff
- Time delay on reset - a few seconds
Battery Charger Modification - 6
- PBNP prototype Ametek battery charger testing
- PINGP has known voltage variations outside nameplate rating
- Informational testing January 2011
- Confirm engineering design review of the control circuit operation
- Equipped with internal control function
- Demonstrate charger capabilities, operation, shutdown, and automatic restart during anticipated voltage transients outside the nameplate rating of the chargers.
Battery Charger Modification - 7
- Factory Acceptance Testing (April 2011)
- Per Ametek quality assurance program
- Specified in NSPM purchase order
- Formal documentation of charger capabilities
- shut off and reset setpoints
- other operating requirements
Battery Charger Modification - 8
- Ametek SCI battery charger controls accommodate AC input voltage variations
- SR 3.8.1.10 footnote specifically states
- modification will be installed to automatically shed and repower the 12 Battery Charger from its bus
- SR 3.8.1.10 footnote requires revision to allow installation of the Ametek SCI battery charger
Battery Charger Modification - 9
- Issue Ametek contract for Unit 1 chargers
- Unit 1 30% EC Design Review meeting
- Unit 1 90% EC Design Review meeting
- Battery charger shipped to PINGP
- Start Unit 1 2011 outage
- Unit 1 outage installation and post-modification testing
- Unit 1 integrated SI test
Basis for Alternative Modification - 1
- Battery charger considerations:
- Required logic internal to charger
- Modification performed in controlled shop environment
- Testing performed in advance of installation
Basis for Alternative Modification - 2
- Plant design considerations:
- Simpler design
- Spare breaker on Bus 16 preserved
- Maintenance sources at the 480V level preserved
- Relay setting or logic design coordination not required
Basis for Alternative Modification - 3
- Plant modification considerations:
- Simpler installation
- Focus Engineering and procurement resources
- Reduces procurement risk
- Avoid:
- new power cable installation
- additions to the load sequencer cabinets
- Reduces outage work time and outage testing time
Requested Schedule Basis - 1
- Refueling outage schedule
- Request review and approval by May 6, 2011
- Current footnote specifies resolution by end of Unit 1 2011 refueling outage
- Testing performed after modification
Requested Schedule Basis - 2
- Battery charger replacement decision January 2011
- LAR submitted approximately one week after decision
RAI discussion - 1
- 1. Provide a comparison of the major electrical parameters including the minimum voltage requirement of the alternating current (AC) input breaker, drop out, reset for the existing and proposed new battery chargers. Discuss in detail the electrical parameters for the proposed new charger that are different than the existing 12 charger and how these parameters were determined to be acceptable.
- 2. Discuss whether the description of existing and new battery chargers will be provided in a future revision of the PINGP Updated Final Safety Analysis Report (UFSAR).
- 3. Confirm that the proposed new battery charger can recharge its associated battery to the fully charged state within 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> while supplying its normal loads after a battery discharge to the bounding design basis event discharge state in accordance with PINGP UFSAR Section 8.5.3 and Technical Specification Surveillance Requirement 3.8.4.2.
RAI discussion - 2
- 4. Industry operating experience has shown that momentary overvoltage or undervoltage transients experienced during switching, fault or lightning-related perturbations can trigger a self-protecting lockout feature in battery chargers resulting in disabling the chargers. Provide details on the magnitude and duration of transient and sustained overvoltage/undervoltage conditions resulting from grid perturbations (or the emergency diesel generator system) that have been evaluated for operation of the proposed battery charger.
- 5. Technical Specification SR 3.8.1.10 NOTE 3 states that the 12 Battery Charger is not required to be energized during performance of SR 3.8.1.10(c) until the completion of Unit 1 2011 refueling outage. The license amendment request proposes a footnote stating that the battery charger equipment will be modified during or prior to the Unit 1 2011 refueling outage. State why NOTE 3 was not modified to apply only until the new equipment has been installed and tested.
RAI discussion - 3
- Proposed response schedule
- Two weeks from receipt of letter
Summary
- TS require 12 Battery Charger modification during Unit 1 2011 refueling outage
- Battery charger replacement modification assures battery charger function performed
- does not involve shedding per TS footnote
- This LAR proposes to revise footnote to allow battery charger replacement modification
- Expedited review and approval requested