Presentation Slides for Prairie Island 2023 End-of-Cycle Meeting
ML24127A240
Person / Time
Site: Prairie Island  Xcel Energy icon.png
Issue date: 05/07/2024
From:
NRC/RGN-III/DORS/RPB3
To:
Shared Package
ML24057A300 List:
References
Download: ML24127A240 (1)


Text

Prairie Island Nuclear Generating Plant Annual Assessment Meeting 2023 Reactor Oversight Process Nuclear Regulatory Commission - Region III

Agenda Introduction Reactor Oversight Process Industry Performance Prairie Island Performance Results Northern States Power Response and Remarks NRC Closing Remarks Public Questions to NRC

Meetings Purpose Public forum for discussion of Prairie Islands performance in 2023 NRC will address the performance identified in the annual assessment Northern States Power will be given the opportunity to respond and inform the NRC of new or existing programs to maintain or improve performance

Security Safety Environment What We Do

Materials Reactors Waste What We Regulate

Radon Military X-Rays What We Dont Regulate

Defense In-Depth Regulation Compliance Continuous Training Assurance of Plant Safety Long-Term Maintenance

How We Regulate

Regulatory Framework

Significance Threshold Increasing Safety Significance Green White Yellow Red Performance Indicators Inspection Findings Green White Yellow Red Increasing Safety Significance

Action Matrix Columns Increasing:

Safety Significance Inspection Management Involvement Regulatory Action Licensee

Response

Regulatory

Response

Degraded Performance Multiple/Repetitive Degraded Cornerstone Unacceptable Performance

Industry-Wide Performance 0

10 20 30 40 50 60 70 80 90 88 6

0 0

0 As of 02/14/2024 0

Industry-Wide Inspection Findings Finding data current as of 02/14/2024 0

50 100 150 200 250 300 350 400 450 447 5

9 0

0 Calendar Year 2023 data

Industry-Wide Performance Indicators 0

1000 2000 3000 4000 5000 6000 7000 Green White Yellow Red 6240 0

0 0

Calendar Year 2023 data

NRC Annual Assessment Summary Northern States Power operated the plant safely and in a manner that preserved the public health and safety and protected the environment.

Prairie Island was in the Licensee Response Column of the NRCs ROP Action Matrix for the last quarter of 2023.

No cross-cutting themes were identified, the following cross-cutting attributes were associated with the findings, Field Presence and Design Margins Prairie Island Nuclear Generating Plant

NRC Inspection Activities 2913 hours0.0337 days <br />0.809 hours <br />0.00482 weeks <br />0.00111 months <br /> of inspection and related activities*

2 resident inspectors on site - residents make four quarterly inspections per year and walk through the plant every day additional regional inspections for Inservice Testing (ISI), Radiological Protection (RP), and Security major team inspections Biennial Problem Identification and Resolution 1 refueling inspection and 2 forced outage inspections

  • see presentation notes Prairie Island for 2023

Northern States Power Response and Remarks

NRC Social Media Channels NRC:

Facebook:

Twitter:

YouTube:

Flickr:

LinkedIn:

GovDelivery:

https://service.govdelivery.com/accounts/USNRC/subscriber/new 18

Contacting the NRC Report an emergency

  • (301) 816-5100 (call collect)

Report a safety concern

  • (800) 695-7403
  • Allegation@nrc.gov General information or questions
  • www.nrc.gov Contact Prairie Island Resident Inspectors
  • (630)-829-9617

Feedback/Comments/

General Questions Public Meeting Feedback Form:

1.

Navigate to https://feedback.nrc.gov/pmfs/

2.

Enter meeting code number: 20240595

End of Presentation Nuclear Regulatory Commission Region III Lisle, IL May 8, 2024