| | number = ML16188A192 | | | number = ML16188A192 |
| | issue date = 07/07/2016 | | | issue date = 07/07/2016 |
| | title = Fermi 2 Nuclear Power Plant - Request for Additional Information on Severe Accident Mitigation Alternatives for Review of License Renewal Application Environmental Review (CAC MF4064) | | | title = Request for Additional Information on Severe Accident Mitigation Alternatives for Review of License Renewal Application Environmental Review |
| | author name = Keegan E M | | | author name = Keegan E |
| | author affiliation = NRC/NRR/DLR/RERB | | | author affiliation = NRC/NRR/DLR/RERB |
| | addressee name = Polson K | | | addressee name = Polson K |
Line 9: |
Line 9: |
| | docket = 05000341 | | | docket = 05000341 |
| | license number = NPF-043 | | | license number = NPF-043 |
| | contact person = Keegan E N, 415-8517 | | | contact person = Keegan E, 415-8517 |
| | case reference number = CAC MF4064 | | | case reference number = CAC MF4064 |
| | document type = Letter, Request for Additional Information (RAI) | | | document type = Letter, Request for Additional Information (RAI) |
Line 18: |
Line 18: |
|
| |
|
| =Text= | | =Text= |
| {{#Wiki_filter:K. Polson UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 July 7, 2016 | | {{#Wiki_filter:K. Polson UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 July 7, 2016 Mr. Keith Polson Site Vice President - Nuclear Generation DTE Electric Company Fermi 2 - 210 NOC 6400 North Dixie Highway Newport, MI 48166 |
| | |
| Mr. Keith Polson Site Vice President - Nuclear Generation DTE Electric Company | |
| | |
| Fermi 2 - 210 NOC 6400 North Dixie Highway Newport, MI 48166 | |
|
| |
|
| ==SUBJECT:== | | ==SUBJECT:== |
| REQUEST FOR ADDITIONAL INFORMATION ON SEVERE ACCIDENT MITIGATION ALTERNATIVES FOR THE REVIEW OF THE FERMI 2 NUCLEAR POWER PLANT, LICENSE RENEWAL APPLICATION ENVIRONMENTAL REVIEW (CAC NO. MF4064) | | REQUEST FOR ADDITIONAL INFORMATION ON SEVERE ACCIDENT MITIGATION ALTERNATIVES FOR THE REVIEW OF THE FERMI 2 NUCLEAR POWER PLANT, LICENSE RENEWAL APPLICATION ENVIRONMENTAL REVIEW (CAC NO. MF4064) |
|
| |
|
| ==Dear Mr. Polson:== | | ==Dear Mr. Polson:== |
|
| |
|
| By letter dated April 24, 2014, DTE Electric Company (DTE or the applicant) submitted an application pursuant to Title 10 of the Code of Federal Regulations (10 CFR) Part 51 and 10 CFR Part 54, to renew operating license NPF-43 for Fermi 2, for review by the U.S. Nuclear Regulatory Commission (NRC or the staff). | | By letter dated April 24, 2014, DTE Electric Company (DTE or the applicant) submitted an application pursuant to Title 10 of the Code of Federal Regulations (10 CFR) Part 51 and 10 CFR Part 54, to renew operating license NPF-43 for Fermi 2, for review by the U.S. Nuclear Regulatory Commission (NRC or the staff). |
| As a result of the NRC Commission's May 4, 2016, decision regarding severe accident mitigation alternatives (SAMA) analysis (CLI-16-07, May 4, 2016, ADAMS Accession No. | | As a result of the NRC Commissions May 4, 2016, decision regarding severe accident mitigation alternatives (SAMA) analysis (CLI-16-07, May 4, 2016, ADAMS Accession No. |
| ML16125A150), the NRC staff has identified additional information that is needed to complete the environmental review. Specifically, the Commission held that documentation was lacking for two inputs (TIMDEC and CDNFRM) used in the MACCS computer analyses, and that uncertainties in those input values could potentially affect the SAMA analysis cost-benefit | | ML16125A150), the NRC staff has identified additional information that is needed to complete the environmental review. Specifically, the Commission held that documentation was lacking for two inputs (TIMDEC and CDNFRM) used in the MACCS computer analyses, and that uncertainties in those input values could potentially affect the SAMA analysis cost-benefit conclusions. The Commission therefore directed the NRC staff to perform additional sensitivity analyses. As a result, the staff has identified, in the enclosure, areas where additional information is needed to address the Commissions direction. |
| | |
| conclusions. The Commission therefore directed the NRC staff to perform additional sensitivity analyses. As a result, the staff has identified, in the enclosure, areas where additional information is needed to address the Commission's direction. | |
| | |
| As discussed with Lynne Goodman of your staff, we request that you provide your responses no later than 30 days from the date of this letter. If you have any questions on this revised environmental review schedule, please contact me by telephone at 301-415-8517 or by e-mail
| |
|
| |
|
| at Elaine.Keegan@nrc.gov. Sincerely, | | K. Polson As discussed with Lynne Goodman of your staff, we request that you provide your responses no later than 30 days from the date of this letter. If you have any questions on this revised environmental review schedule, please contact me by telephone at 301-415-8517 or by e-mail at Elaine.Keegan@nrc.gov. |
| /RA/ Elaine M. Keegan, Sr. Project Manager Environmental Review and Projects Branch Division of License Renewal Office of Nuclear Reactor Regulation Docket No. 50-341 | | Sincerely, |
| | /RA/ |
| | Elaine M. Keegan, Sr. Project Manager Environmental Review and Projects Branch Division of License Renewal Office of Nuclear Reactor Regulation Docket No. 50-341 |
|
| |
|
| ==Enclosure:== | | ==Enclosure:== |
|
| |
|
| Revised Schedule | | Revised Schedule cc w/encl: Listserv |
|
| |
|
| cc w/encl: Listserv
| | ML16188A192 OFFICE LA:DLR: PM:RPB2:DLR BC:RPB2:DLR NAME IBetts EKeegan JDanna DATE 7/ 7 /16 7/ 7/16 7/7 /16 |
|
| |
|
| ML16188A192 OFFICE LA:DLR: PM:RPB2:DLR BC:RPB2:DLR NAME IBetts EKeegan JDanna DATE 7/ 7 /16 7/ 7/16 7/7 /16 Letter to K. Polson from E. Keegan dated July 7, 2016
| | Letter to K. Polson from E. Keegan dated July 7, 2016 |
|
| |
|
| ==SUBJECT:== | | ==SUBJECT:== |
| REQUEST FOR ADDITIONAL INFORMATION ON SEVERE ACCIDENT MITIGATION ALTERNATIVES FOR THE REVIEW OF THE FERMI 2 NUCLEAR POWER PLANT, LICENSE RENEWAL APPLICATION ENVIRONMENTAL REVIEW (CAC NO. MF4064) | | REQUEST FOR ADDITIONAL INFORMATION ON SEVERE ACCIDENT MITIGATION ALTERNATIVES FOR THE REVIEW OF THE FERMI 2 NUCLEAR POWER PLANT, LICENSE RENEWAL APPLICATION ENVIRONMENTAL REVIEW (CAC NO. MF4064) |
| DISTRIBUTION: | | DISTRIBUTION: |
| HARD COPY: DLR RF | | HARD COPY: |
| | | DLR RF E-MAIL: |
| E-MAIL: PUBLIC RidsNrrDlr Resource | | PUBLIC RidsNrrDlr Resource RidsNrrDlrRpb1 Resource RidsNrrDlrRpb2 Resource RidsNrrDlrRarb Resource RidsNrrDlrRasb Resource RidsNrrDlrRerb Resource RidsNrrPMFermi2 Resource Listserv |
| | | --------------------- |
| RidsNrrDlrRpb1 Resource RidsNrrDlrRpb2 Resource RidsNrrDlrRarb Resource RidsNrrDlrRasb Resource | | D. Melendez-Colon E. Keegan J. Danna D. McIntyre, OPA C. Kanatas, OGC B. Dickson, RIII B. Kemker, RIII V. Mitlyng, RIII P. Chandrathil, RIII |
| | |
| RidsNrrDlrRerb Resource RidsNrrPMFermi2 Resource Listserv --------------------- | |
| D. Melendez-Colon | |
| | |
| E. Keegan | |
| | |
| J. Danna D. McIntyre, OPA C. Kanatas, OGC B. Dickson, RIII B. Kemker, RIII V. Mitlyng, RIII P. Chandrathil, RIII | |
| | |
| Enclosure REQUEST FOR ADDITIONAL INFORMATION ON SEVERE ACCIDENT MITIGATION ALTERNATIVES FOR THE REVIEW OF THE FERMI 2 NUCLEAR POWER REGARDING CLI-16-07 On May 4, 2016, the Commission issued a decision (CLI-16-07) in the Indian Point license renewal proceeding, in which it directed the Staff to supplement the Indian Point Severe Accident Mitigation Alternatives (SAMA) analysis with sensitivity analyses. Specifically, the Commission held that documentation was lacking for two inputs (TIMDEC and CDNFRM) used in the MACCS computer analyses, and that uncertainties in those input values could potentially affect the SAMA analysis cost-benefit conclusions. The Commission therefore directed the staff to perform additional sensitivity analyses.
| |
| | |
| The two inputs (TIMDEC and CDNFRM) are commonly used in the SAMA analyses performed for license renewal applications (LRAs). These two input values were generally based on the values provided in NUREG-1150, "Severe Accident Risks: An Assessment for Five U.S. Nuclear
| |
| | |
| Power Plants" and NUREG/CR-3673, "Economic Risks of Nuclear Power Reactor Accidents." The TIMDEC input value defines the time required for completing decontamination to a
| |
| | |
| specified degree. The CDNFRM input parameter defines the cost (on a per person basis) of decontaminating non-farmland by a specified de contamination factor. The CDNFRM values used in NUREG-1150 ($3,000/person for decontami nation factor of 3 and $8,000/person for decontamination factor of 15) stem from decontamination cost estimates provided in
| |
| | |
| NUREG/CR-3673, the same 1984 economic risk study referenced in support of the decontamination time inputs. These decontamination cost inputs are commonly escalated to account for inflation.
| |
| The NRC Staff believes the Commission's decision in CLI-16-07 may be applicable to the SAMA analysis performed for Fermi 2, inasmuch as that analysis may have also relied upon the NUREG-1150 values for TIMDEC and CDNFRM. We therefore request that DTE Electric Company (DTE) either justify why CLI-16-07 does not apply to the SAMA analysis performed for Fermi 2 or supplement the SAMA analysis with sensitivity analyses for the CDNFRM and TIMDEC values.
| |
|
| |
|
| DTE is requested to review the input values specified in CLI-16-07 for the Indian Point LRA, and (1) to apply the maximum values specified by the Commission (one year (365 days) for TIMDEC and $100,000 for the CDNFRM values for the decontamination factor of 15) or, in the alternative, (2) to explain, with sufficient justification, its rationale for choosing any other value(s) for its sensitivity analyses. In any event, DTE should execute sensitivity analyses for the release categories modeled that exceed 10 15 Becquerels of Cs-137 released. DTE is requested to evaluate how these sensitivity analyses may affect its identification of potentially cost-beneficial SAMAs. Finally, upon completing its sensitivity analysis, DTE is requested to submit the spreadsheet (or equivalent table if another method is used) that conveys the population dose and off-site economic cost for each release category and integrates the results into a Population Dose Risk and an Offsite Economic Cost Risk for Fermi 2.}} | | REQUEST FOR ADDITIONAL INFORMATION ON SEVERE ACCIDENT MITIGATION ALTERNATIVES FOR THE REVIEW OF THE FERMI 2 NUCLEAR POWER REGARDING CLI-16-07 On May 4, 2016, the Commission issued a decision (CLI-16-07) in the Indian Point license renewal proceeding, in which it directed the Staff to supplement the Indian Point Severe Accident Mitigation Alternatives (SAMA) analysis with sensitivity analyses. Specifically, the Commission held that documentation was lacking for two inputs (TIMDEC and CDNFRM) used in the MACCS computer analyses, and that uncertainties in those input values could potentially affect the SAMA analysis cost-benefit conclusions. The Commission therefore directed the staff to perform additional sensitivity analyses. |
| | The two inputs (TIMDEC and CDNFRM) are commonly used in the SAMA analyses performed for license renewal applications (LRAs). These two input values were generally based on the values provided in NUREG-1150, Severe Accident Risks: An Assessment for Five U.S. Nuclear Power Plants and NUREG/CR-3673, Economic Risks of Nuclear Power Reactor Accidents. |
| | The TIMDEC input value defines the time required for completing decontamination to a specified degree. The CDNFRM input parameter defines the cost (on a per person basis) of decontaminating non-farmland by a specified decontamination factor. The CDNFRM values used in NUREG-1150 ($3,000/person for decontamination factor of 3 and $8,000/person for decontamination factor of 15) stem from decontamination cost estimates provided in NUREG/CR-3673, the same 1984 economic risk study referenced in support of the decontamination time inputs. These decontamination cost inputs are commonly escalated to account for inflation. |
| | The NRC Staff believes the Commissions decision in CLI-16-07 may be applicable to the SAMA analysis performed for Fermi 2, inasmuch as that analysis may have also relied upon the NUREG-1150 values for TIMDEC and CDNFRM. We therefore request that DTE Electric Company (DTE) either justify why CLI-16-07 does not apply to the SAMA analysis performed for Fermi 2 or supplement the SAMA analysis with sensitivity analyses for the CDNFRM and TIMDEC values. |
| | DTE is requested to review the input values specified in CLI-16-07 for the Indian Point LRA, and (1) to apply the maximum values specified by the Commission (one year (365 days) for TIMDEC and $100,000 for the CDNFRM values for the decontamination factor of 15) or, in the alternative, (2) to explain, with sufficient justification, its rationale for choosing any other value(s) for its sensitivity analyses. In any event, DTE should execute sensitivity analyses for the release categories modeled that exceed 1015 Becquerels of Cs-137 released. DTE is requested to evaluate how these sensitivity analyses may affect its identification of potentially cost-beneficial SAMAs. Finally, upon completing its sensitivity analysis, DTE is requested to submit the spreadsheet (or equivalent table if another method is used) that conveys the population dose and off-site economic cost for each release category and integrates the results into a Population Dose Risk and an Offsite Economic Cost Risk for Fermi 2. |
| | Enclosure}} |
Letter Sequence RAI |
---|
|
|
MONTHYEARML16188A1922016-07-0707 July 2016 Request for Additional Information on Severe Accident Mitigation Alternatives for Review of License Renewal Application Environmental Review Project stage: RAI ML16256A6302016-09-20020 September 2016 Notice of Availability of the Final Plant-Specific Supplement 56 to the Generic Environmental Impact Statement for License Renewal of Nuclear Plants Regarding Fermi 2 Project stage: Other ML16244A0972016-09-21021 September 2016 FRN: License Renewal Application for Fermi 2 Nuclear Power Plant Project stage: Other 2016-09-20
[Table View] |
Similar Documents at Fermi |
---|
Category:Letter
MONTHYEARIR 05000341/20240122024-11-0101 November 2024 Commercial Grade Dedication Inspection Report 05000341/2024012 IR 05000341/20245012024-10-0808 October 2024 – Emergency Preparedness Inspection Report 05000341/2024501 ML24276A2032024-10-0303 October 2024 FEMA Level 1 Finding Transmittal Letter ML24268A0992024-10-0101 October 2024 Power Plant – Audit Summary for License Amendment Request and Regulatory Exemptions for a Risk Informed Approach to Address ECCS Strainer Performance IR 05000341/20240132024-09-30030 September 2024 Phase 2 Post Approval License Renewal Report 05000341/2024013 ML24240A1692024-09-18018 September 2024 Cy 2023 Summary of Decommissioning Trust Fund Status ML24257A1652024-09-13013 September 2024 FEMA Region 5 Fermi 2 Nuclear Power Plant Level 1 Finding September 2024 ML24254A3562024-09-0909 September 2024 FEMA Level 1 Finding for Fermi 2024 Biennial Exercise ML24240A3532024-08-27027 August 2024 Inservice Testing (IST) Program for the Fourth 10-Year Inspection Interval Update IR 05000341/20240052024-08-22022 August 2024 Updated Inspection Plan for Fermi Power Plant, Unit 2 (Report 05000341/2024005) IR 05000341/20244042024-08-21021 August 2024 Public-Fermi Power Plant, Unit 2 - Material Control and Accounting Program Inspection Report 05000341/2024404 IR 05000341/20240022024-08-14014 August 2024 Integrated Inspection Report 05000341/2024002 ML24199A2182024-07-25025 July 2024 Enrico Fermi Atomic Power Plant, Unit 1 - NRC Position on Continuation of Possession-Only License No. DPR-9 Past the Current Expiration Date (Docket No. 50-016) ML24169A4092024-07-18018 July 2024 Relief Request RR-A25, Alternative to Reactor Vessel Circumferential Shell Weld Examination IR 05000341/20243022024-07-0909 July 2024 NRC Initial License Reexamination Report 05000341/2024302 ML24173A1012024-06-14014 June 2024 Retake Exam Post-Exam Cover Letter & Comments ML24155A0852024-06-11011 June 2024 Operator Licensing Reexamination Approval Letter - Fermi Power Plant, June 2024 ML24151A6482024-06-0303 June 2024 Changes in Reactor Decommissioning Branch Project Management Assignments for Some Decommissioning Facilities IR 05000341/20244022024-05-30030 May 2024 Security Baseline Inspection Report 05000341/2024402 ML24143A1852024-05-29029 May 2024 – Regulatory Audit in Support of LAR to Adopt TSTF-505, Rev. 2, TSTF-439, Rev. 2, and TSTF-591, Rev. 0 ML24141A2072024-05-20020 May 2024 Plant—Information Request to Support the NRC Annual Baseline Emergency Action Level and Emergency Plan Changes Inspection 05000341/LER-2024-002, Primary Containment Isolation Valve Declared Inoperable for a Period Prohibited by Technical Specifications2024-05-16016 May 2024 Primary Containment Isolation Valve Declared Inoperable for a Period Prohibited by Technical Specifications 05000341/LER-2024-001, Automatic RPS Scram on High RPV Pressure While Attempting to Lower Generator Output During RF-222024-05-15015 May 2024 Automatic RPS Scram on High RPV Pressure While Attempting to Lower Generator Output During RF-22 IR 05000341/20240102024-05-0606 May 2024 NRC Inspection Report 05000341/2024010 ML24052A2772024-04-30030 April 2024 Issuance of Amendment No. 229 Regarding Revision of Technical Specification 3.8.1, AC Sources - Operating, Surveillance Requirement SR 3.8.1.12 IR 05000341/20240012024-04-30030 April 2024 Integrated Inspection Report 05000341/2024001 ML24107B1372024-04-18018 April 2024 Confirmation of Initial License Reexamination June 2024 ML24101A3732024-04-11011 April 2024 Request for Information for NRC Commercial Grade Dedication Inspection: Inspection Report 05000341/2024012 ML24100A8422024-04-0909 April 2024 Request for Information for an NRC Post-Approval Site Inspection for License Renewal Inspection: Inspection Report 05000341/2024013 IR 05000341/20234022024-04-0808 April 2024 Reissue - Fermi Power Plant, Unit 2 - Cyber Security Inspection Report 05000341/2023402 (Public) ML24088A2162024-04-0404 April 2024 Change in Estimated Review Schedule and Level of Effort for License Amendment Request for Risk Informed Approach to ECCS Strainer Performance ML24086A5732024-04-0101 April 2024 Response to Disputed Non-Cited Violation Documents in Fermi Power Plant, Unit 2 - Cyber Security Inspection Report 05000341/2023402-01 Withdrawal of Non-Cited Violation (Public) IR 05000341/20243012024-04-0101 April 2024 NRC Initial License Examination Report 05000341/2024301 IR 05000341/20244012024-03-22022 March 2024 – Security Baseline Inspection Report 05000341/2024401 (Public) IR 05000341/20240112024-03-0808 March 2024 Nbsp;Safety Conscious Work Environment Issue of Concern Follow-up Inspection Report 05000341/2024011 ML24002B1812024-03-0404 March 2024 Issuance of Amendment No. 228 Regarding Revision of Non-Conservative Technical Specification 3.4.5, RCS Pressure Isolation Valve (PIV) Leakage IR 05000341/20230062024-02-28028 February 2024 Annual Assessment Letter for Fermi Power Plant, Unit 2 (Report 05000341/2023006) ML24019A1842024-02-16016 February 2024 Exemption from Select Requirements of 10 CFR Part 73 Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting ML24045A1602024-02-14014 February 2024 Operator Licensing Examination Approval - Fermi Power Plant, February 2024 IR 05000341/20230042024-02-0505 February 2024 Integrated Inspection Report 05000341/2023004 IR 05000341/20230102023-12-0808 December 2023 Nbsp;Biennial Problem Identification and Resolution Inspection Report 05000341/2023010 ML23341A1852023-12-0808 December 2023 Acknowledgement of Response to NRC Inspection Report 05000341/2023402 and Disputed Non-Cited Violation ML23310A1492023-12-0808 December 2023 Issuance of Amendment No. 227 Regarding Revision of Technical Specification 3.8.1, AC Sources - Operating, Emergency Diesel Generator Voltage and Frequency Surveillance Requirements ML23334A1902023-12-0101 December 2023 Request for Information for an NRC Post-Approval Site Inspection for License Renewal Inspection Report 05000341/2024010 ML23335A0062023-12-0101 December 2023 Notification of NRC Baseline Inspection and Request for Information; Inspection Report 05000341/2024002 IR 05000016/20230012023-12-0101 December 2023 NRC Inspection Report No. 050-00016/2023-001 (Drss) - Enrico Fermi Atomic Power Plant, Unit 1 IR 05000341/20230032023-11-0707 November 2023 Integrated Inspection Report 05000341/2023003 and 07200071/2023001 ML23297A0512023-10-30030 October 2023 Issuance of Amendment No. 226 Regarding Revision of Technical Specifications 3.8.1, AC Sources - Operating (Exigent Circumstances) ML23311A3482023-10-20020 October 2023 DTE Electric Company (DTE) - Submittal of the Renewed Fermi 3 Michigan Department of Environmental, Great Lakes, and Energy (EGLE) National Pollutant Discharge Elimination System (NPDES) Permit No. MI0058892 ML23272A1552023-10-10010 October 2023 – Letter to Licensee and Federal Register Notification of Amendment to Renewed Facility Operating License and Proposed No Significant Hazards Consideration Determination (Exigent Circumstances) (EPID L-2023-LLA-0134) (Letter) 2024-09-09
[Table view] Category:Request for Additional Information (RAI)
MONTHYEARML24141A2072024-05-20020 May 2024 Plant—Information Request to Support the NRC Annual Baseline Emergency Action Level and Emergency Plan Changes Inspection ML24080A3912024-03-20020 March 2024 NRR E-mail Capture - Fermi 2 - Request for Additional Information for License Amendment Request Regarding Risk-Informed ECCS Strainer Performance Evaluation (Final) (L-2023-LLA-0092) ML24080A3902024-03-19019 March 2024 NRR E-mail Capture - (External_Sender) Fermi 2 - Request for Additional Information for License Amendment Request Regarding Risk-Informed ECCS Strainer Performance Evaluation (DRAFT)(L-2023-LLA-0092) ML23335A0062023-12-0101 December 2023 Notification of NRC Baseline Inspection and Request for Information; Inspection Report 05000341/2024002 ML23276A0052023-10-0202 October 2023 NRR E-mail Capture - (External_Sender) Fermi EDG Crankcase Trip LAR RAI Response ML23250A2732023-09-0707 September 2023 NRR E-mail Capture - Fermi 2 - Request for Additional Information for License Amendment Request to Revise TS 3.8.1, AC Sources - Operating, Surveillance Requirement 3.8.1.12 ML23241B0162023-08-24024 August 2023 Exigent License Amendment Request for Additional Information RAI-12 (EPID L-2023-LLA-0112) (Email) ML23235A1822023-08-23023 August 2023 Exigent LAR Request for Additional Information ML23115A1452023-04-25025 April 2023 NRR E-mail Capture - Fermi 2 - Request for Additional Information for Changes to TS 3.8.1, AC Sources - Operating ML22362A0712022-12-28028 December 2022 Notification of NRC Fire Protection Team Inspection Request for Information Inspection Report Numbers 05000341/2023010 ML22130A5162022-05-12012 May 2022 Information Request to Support the NRC Annual Baseline Emergency Action Level and Emergency Plan Changes Inspection ML21214A1492021-08-0202 August 2021 License Amendment Request: Request for Additional Information ML21126A0532021-05-0404 May 2021 NRR E-mail Capture - Fermi 2 - Request for Additional Information for Revised Relief Request RR A-39 ML21099A1012021-04-0909 April 2021 Information Request to Support Upcoming Temporary Instruction 2515/194 Inspection; Inspection Report 05000341/2021013 ML21078A4832021-03-19019 March 2021 Information Request for NRC Triennial Evaluations of Changes, Tests, and Experiments (50.59) Baseline Inspection; Inspection Report 05000341/2021011 ML20303A2872020-10-29029 October 2020 Notification of NRC Design Bases Assurance Inspection (Programs) and Initial Request for Information: Inspection Report 05000341/2021012 ML20239A9682020-08-12012 August 2020 NRR E-mail Capture - Fermi 2 LAR: RAI for Revision to Technical Specifications to Change the Surveillance Intervals to Accommodate a 24-Month Fuel Cycle ML20133K0502020-05-14014 May 2020 Information Request to Support the NRC Annual Baseline Emergency Action Level and Emergency Plan Changes Inspection ML20079J0972020-03-19019 March 2020 Notification of NRC Fire Protection Team Inspection Request for Information; Inspection Report Number 05000341/2020011 ML18206B0632018-07-25025 July 2018 NRR E-mail Capture - Draft Request for Additional Information Regarding Fermi LAR to Adopt TSTF -542 ML18129A3992018-05-0909 May 2018 NRR E-mail Capture - Request for Additional Information Regarding Fermi LAR to Adopt TSTF - 542 ML18065A3962018-03-0606 March 2018 NRR E-mail Capture - Request for Additional Information Regarding Fermi LAR to Adopt TSTF-542 ML18029A1262018-01-29029 January 2018 NRR E-mail Capture - Fermi 2 LAR to Revise TS to Eliminate MSLRM Reactor Trip and PCIS Group 1 Isolation Functions ML18022A9452018-01-22022 January 2018 NRR E-mail Capture - Fermi RAI for LAR Regarding TS to Eliminate Steam Line Radiation ML18022A1092018-01-19019 January 2018 NRR E-mail Capture - Request for Additional Information Regarding Fermi RR-A37 ML17346A8012017-12-12012 December 2017 NRR E-mail Capture - Final Fermi RAI for LAR Regarding Uhc (TS 3.7.2) ML17157B6702017-06-0505 June 2017 Notification of NRC Triennial Fire Protection Baseline Inspection Request for Information 05000341/2017012 ML17087A4572017-03-28028 March 2017 NRR E-mail Capture - RAI for Fermi 2 - LAR Regarding the Availability of HPCI and Rici at Low Pressure Conditions ML16357A1152016-12-22022 December 2016 Notification of NRC Baseline Inspection and Request for Information (Jvb) ML16188A1922016-07-0707 July 2016 Request for Additional Information on Severe Accident Mitigation Alternatives for Review of License Renewal Application Environmental Review ML16125A1742016-05-0303 May 2016 Request for Additional Information - Alternative Request PRR-007, Revision 1 ML16090A1032016-03-29029 March 2016 Ltr. 03/29/16 Fermi Power Plant - Notification of an NRC Triennial Heat Sink Performance Inspection and Request for Information Inspection Report 05000341/2016002 (Maj) ML16011A0442016-01-14014 January 2016 Request for Additional Information for the Review of the Fermi 2 License Renewal Application - Set 38 ML15237A0442015-09-0101 September 2015 Request for Additional Information for the Review of the Fermi, Unit 2, License Renewal Application-Set 37 ML15231A1612015-08-17017 August 2015 Ltr. 08/17/15 Fermi Power Plant - Notification of NRC Inspection and Request for Information (Txb) ML15149A3642015-05-28028 May 2015 Information Request to Support NRC Annual Baseline Emergency Action Level and Emergency Plan Changes Inspection (Mxg) ML15134A0722015-05-21021 May 2015 Request for Additional Information for the Review of the Fermi, Unit 2 License Renewal Application-Set 35 ML15139A4612015-05-20020 May 2015 Request for Additional Information for the Review of the Fermi 2 License Renewal Application-Set 33 ML15132A4272015-05-18018 May 2015 March 27, 2015 Summary of Telephone Conference Call Held Between the U.S. NRC and DTE Electric Company Concerning Requests for Additional Information Pertaining to the Severe Accident Mitigation Alternatives Review of the Fermi, Unit 2 ML15126A0042015-05-15015 May 2015 Requests for Additional Information for the Review of the Fermi 2 License Renewal Application-Set 34 ML15114A3692015-05-0606 May 2015 Request for Additional Information Associated with Near-Term Task Force Recommendation 2.1, Seismic Hazard and Screening Report ML15099A0162015-04-22022 April 2015 Requests for Additional Information for the Review of the Fermi 2 License Renewal Application Set 32 ML15092A9452015-04-0909 April 2015 Request for Additional Information for the Environmental Review of the Fermi 2 License Renewal Application - Severe Accident Mitigation Alternatives ML15085A5132015-04-0202 April 2015 Request for Additional Information for the Review of the Fermi 2 License Renewal Application - Set 31 ML15077A1082015-03-26026 March 2015 Requests for Additional Information for the Review of the Fermi 2 License Renewal Application - Set 27 ML15082A0462015-03-26026 March 2015 Requests for Additional Information for the Review of the Fermi, Unit 2 License Renewal Application - Set 29, ML15078A3372015-03-26026 March 2015 Request for Additional Information for the Review of the Fermi, Unit 2 License Renewal Application - Set 28 ML15072A0812015-03-19019 March 2015 Request for Additional Information for the Review of the Fermi 2 License Renewal Application - Set 25 ML15051A4202015-03-13013 March 2015 Request for Additional Information for the Review of the Fermi 2 License Renewal Application - Set 23 ML15062A3362015-03-13013 March 2015 Request for Additional Information for the Review of the Fermi 2 License Renewal Application - Set 26 2024-05-20
[Table view] |
Text
K. Polson UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 July 7, 2016 Mr. Keith Polson Site Vice President - Nuclear Generation DTE Electric Company Fermi 2 - 210 NOC 6400 North Dixie Highway Newport, MI 48166
SUBJECT:
REQUEST FOR ADDITIONAL INFORMATION ON SEVERE ACCIDENT MITIGATION ALTERNATIVES FOR THE REVIEW OF THE FERMI 2 NUCLEAR POWER PLANT, LICENSE RENEWAL APPLICATION ENVIRONMENTAL REVIEW (CAC NO. MF4064)
Dear Mr. Polson:
By letter dated April 24, 2014, DTE Electric Company (DTE or the applicant) submitted an application pursuant to Title 10 of the Code of Federal Regulations (10 CFR) Part 51 and 10 CFR Part 54, to renew operating license NPF-43 for Fermi 2, for review by the U.S. Nuclear Regulatory Commission (NRC or the staff).
As a result of the NRC Commissions May 4, 2016, decision regarding severe accident mitigation alternatives (SAMA) analysis (CLI-16-07, May 4, 2016, ADAMS Accession No.
ML16125A150), the NRC staff has identified additional information that is needed to complete the environmental review. Specifically, the Commission held that documentation was lacking for two inputs (TIMDEC and CDNFRM) used in the MACCS computer analyses, and that uncertainties in those input values could potentially affect the SAMA analysis cost-benefit conclusions. The Commission therefore directed the NRC staff to perform additional sensitivity analyses. As a result, the staff has identified, in the enclosure, areas where additional information is needed to address the Commissions direction.
K. Polson As discussed with Lynne Goodman of your staff, we request that you provide your responses no later than 30 days from the date of this letter. If you have any questions on this revised environmental review schedule, please contact me by telephone at 301-415-8517 or by e-mail at Elaine.Keegan@nrc.gov.
Sincerely,
/RA/
Elaine M. Keegan, Sr. Project Manager Environmental Review and Projects Branch Division of License Renewal Office of Nuclear Reactor Regulation Docket No. 50-341
Enclosure:
Revised Schedule cc w/encl: Listserv
ML16188A192 OFFICE LA:DLR: PM:RPB2:DLR BC:RPB2:DLR NAME IBetts EKeegan JDanna DATE 7/ 7 /16 7/ 7/16 7/7 /16
Letter to K. Polson from E. Keegan dated July 7, 2016
SUBJECT:
REQUEST FOR ADDITIONAL INFORMATION ON SEVERE ACCIDENT MITIGATION ALTERNATIVES FOR THE REVIEW OF THE FERMI 2 NUCLEAR POWER PLANT, LICENSE RENEWAL APPLICATION ENVIRONMENTAL REVIEW (CAC NO. MF4064)
DISTRIBUTION:
HARD COPY:
DLR RF E-MAIL:
PUBLIC RidsNrrDlr Resource RidsNrrDlrRpb1 Resource RidsNrrDlrRpb2 Resource RidsNrrDlrRarb Resource RidsNrrDlrRasb Resource RidsNrrDlrRerb Resource RidsNrrPMFermi2 Resource Listserv
D. Melendez-Colon E. Keegan J. Danna D. McIntyre, OPA C. Kanatas, OGC B. Dickson, RIII B. Kemker, RIII V. Mitlyng, RIII P. Chandrathil, RIII
REQUEST FOR ADDITIONAL INFORMATION ON SEVERE ACCIDENT MITIGATION ALTERNATIVES FOR THE REVIEW OF THE FERMI 2 NUCLEAR POWER REGARDING CLI-16-07 On May 4, 2016, the Commission issued a decision (CLI-16-07) in the Indian Point license renewal proceeding, in which it directed the Staff to supplement the Indian Point Severe Accident Mitigation Alternatives (SAMA) analysis with sensitivity analyses. Specifically, the Commission held that documentation was lacking for two inputs (TIMDEC and CDNFRM) used in the MACCS computer analyses, and that uncertainties in those input values could potentially affect the SAMA analysis cost-benefit conclusions. The Commission therefore directed the staff to perform additional sensitivity analyses.
The two inputs (TIMDEC and CDNFRM) are commonly used in the SAMA analyses performed for license renewal applications (LRAs). These two input values were generally based on the values provided in NUREG-1150, Severe Accident Risks: An Assessment for Five U.S. Nuclear Power Plants and NUREG/CR-3673, Economic Risks of Nuclear Power Reactor Accidents.
The TIMDEC input value defines the time required for completing decontamination to a specified degree. The CDNFRM input parameter defines the cost (on a per person basis) of decontaminating non-farmland by a specified decontamination factor. The CDNFRM values used in NUREG-1150 ($3,000/person for decontamination factor of 3 and $8,000/person for decontamination factor of 15) stem from decontamination cost estimates provided in NUREG/CR-3673, the same 1984 economic risk study referenced in support of the decontamination time inputs. These decontamination cost inputs are commonly escalated to account for inflation.
The NRC Staff believes the Commissions decision in CLI-16-07 may be applicable to the SAMA analysis performed for Fermi 2, inasmuch as that analysis may have also relied upon the NUREG-1150 values for TIMDEC and CDNFRM. We therefore request that DTE Electric Company (DTE) either justify why CLI-16-07 does not apply to the SAMA analysis performed for Fermi 2 or supplement the SAMA analysis with sensitivity analyses for the CDNFRM and TIMDEC values.
DTE is requested to review the input values specified in CLI-16-07 for the Indian Point LRA, and (1) to apply the maximum values specified by the Commission (one year (365 days) for TIMDEC and $100,000 for the CDNFRM values for the decontamination factor of 15) or, in the alternative, (2) to explain, with sufficient justification, its rationale for choosing any other value(s) for its sensitivity analyses. In any event, DTE should execute sensitivity analyses for the release categories modeled that exceed 1015 Becquerels of Cs-137 released. DTE is requested to evaluate how these sensitivity analyses may affect its identification of potentially cost-beneficial SAMAs. Finally, upon completing its sensitivity analysis, DTE is requested to submit the spreadsheet (or equivalent table if another method is used) that conveys the population dose and off-site economic cost for each release category and integrates the results into a Population Dose Risk and an Offsite Economic Cost Risk for Fermi 2.