ML16333A307: Difference between revisions

From kanterella
Jump to navigation Jump to search
(Created page by program invented by StriderTol)
(Created page by program invented by StriderTol)
 
(15 intermediate revisions by the same user not shown)
Line 2: Line 2:
| number = ML16333A307
| number = ML16333A307
| issue date = 11/29/2016
| issue date = 11/29/2016
| title = Arkansas Nuclear One, Unit 2 - Supplemental Information Needed For Acceptance Of Requested Licensing Action Amendment Request To Revise National Fire Protection Association Standard 805 Modifications (CAC No. MF8691)
| title = Supplemental Information Needed for Acceptance of Requested Licensing Action Amendment Request to Revise National Fire Protection Association Standard 805 Modifications
| author name = Wengert T J
| author name = Wengert T
| author affiliation = NRC/NRR/DORL/LPLIV-2
| author affiliation = NRC/NRR/DORL/LPLIV-2
| addressee name =  
| addressee name =  
Line 9: Line 9:
| docket = 05000368
| docket = 05000368
| license number = NPF-006
| license number = NPF-006
| contact person = Wengert T J, NRR-DORL 415-4037
| contact person = Wengert T, NRR-DORL 415-4037
| case reference number = CAC MF8691
| case reference number = CAC MF8691
| document type = Letter, Request for Additional Information (RAI)
| document type = Letter, Request for Additional Information (RAI)
| page count = 4
| page count = 4
| project = CAC:MF8691
| stage = Acceptance Review
}}
}}
=Text=
{{#Wiki_filter:UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 November 29, 2016 Vice President, Operations Arkansas Nuclear One Entergy Operations, Inc.
1448 S.R. 333 Russellville, AR 72802
==SUBJECT:==
ARKANSAS NUCLEAR ONE, UNIT 2 - SUPPLEMENTAL INFORMATION NEEDED FOR ACCEPTANCE OF REQUESTED LICENSING ACTION RE: AMENDMENT REQUEST TO REVISE NATIONAL FIRE PROTECTION ASSOCIATION STANDARD 805 MODIFICATIONS (CAC NO. MF8691)
==Dear Sir or Madam:==
By letter dated October 27, 2016 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML16302A227), Entergy Operations, Inc. (Entergy) submitted a license amendment request for Arkansas Nuclear One, Unit 2 (AN0-2). The proposed amendment would revise the National Fire Protection Association Standard 805 (NFPA 805),
"Performance-Based Standard for Fire Protection for Light Water Reactor Electric Generating Plants" (2001 Edition), Modifications for AN0-2, previously approved by the U.S. Nuclear Regulatory Commission (NRC) in a letter dated February 18, 2015 (ADAMS Accession No. ML14356A227). The purpose of this letter is to provide the results of the NRC staff's acceptance review of this amendment request. The acceptance review was performed to determine if there is sufficient technical information in scope and depth to allow the NRC staff to complete its detailed technical review. The acceptance review is also intended to identify whether the application has any readily apparent information insufficiencies in its characterization of the regulatory requirements or the licensing basis of the plant.
Consistent with Section 50.90 of Title 1O of the Code of Federal Regulations (1 O CFR), an amendment to the license (including the technical specifications) must fully describe the changes requested, and following as far as applicable, the form prescribed for original applications. Section 50.34 of 10 CFR addresses the content of technical information required. This section stipulates that the submittal address the design and operating characteristics, unusual or novel design features, and principal safety considerations.
The NRC staff has reviewed your application and concluded that the information delineated in the enclosure to this letter is necessary to enable the NRC staff to make an independent assessment regarding the acceptability of the proposed amendment request in terms of regulatory requirements and the protection of public health and safety and the environment.
In order to make the application complete, the NRC staff requests that Entergy supplement the application to address the information requested in the enclosure by December 9, 2016. This will enable the NRC staff to complete its detailed technical review. If the information responsive to the NRC staff's request is not received by the above date, the application will not be accepted for review pursuant to 10 CFR 2.101, and the NRG staff will cease its review activities associated with the application. If the application is subsequently accepted for review, you will
be advised of any further information needed to support the NRC staff's detailed technical review by separate correspondence.
The information requested and associated timeframe in this letter were discussed with Mr. David Bice on November 22, 2016.
If you have any questions, please contact me at (301) 415-4037 or by e-mail at Thomas.Wengert@nrc.gov.
Sincerely,
                                                                          ~*
Thomas J. Wenge , Senior Project Manager Plant Licensing IV-2 and Decommissioning Transition Branch Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-368
==Enclosure:==
Supplemental Information Needed cc w/encl:: Distribution via Listserv
SUPPLEMENTAL INFORMATION NEEDED AMENDMENT REQUEST TO REVISE NATIONAL FIRE PROTECTION ASSOCIATION STANDARD 805 MODIFICATIONS ENTERGY OPERATIONS, INC.
ARKANSAS NUCLEAR ONE, UNIT 2 DOCKET NO. 50-368 By letter dated October 27, 2016 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML16302A227), Entergy Operations, Inc. (Entergy) submitted a license amendment request (LAR) for Arkansas Nuclear One, Unit 2 (AN0-2). The proposed amendment would revise the National Fire Protection Association Standard 805 (NFPA 805),
"Performance-Based Standard for Fire Protection for Light Water Reactor Electric Generating Plants" (2001 Edition), modifications for AN0-2, previously approved by the U.S. Nuclear Regulatory Commission (NRC) in a letter dated February 18, 2015 (ADAMS Accession No. ML14356A227).
The NRC staff has reviewed your application and concluded that the information delineated below is necessary to enable the NRC staff to make an independent assessment regarding the acceptability of the proposed amendment request in terms of regulatory requirements and the protection of public health and safety and the environment.
* Most of the proposed modifications in Section 2.0 of the LAR replace cable rerouting with alternative electronic modification. Cable rerouting would eliminate the possibility for fire-induced failure while alternative electronic modifications will only reduce the possibility of fire-induced failures. Contrary to this observation, Tables 1 and 2 on page 25 of 30 of Attachment 1 of the LAR indicate that several alternative electronic modifications result in lower plant risk compared to the cable rerouting option. Provide supplemental information explaining why the risk decreases in some of the modifications summarized in Table 2 and increases for other modifications.
Enclosure
ML16333A307 OFFICE  NRR/DORL/LPL4-2/PM      NRR/DORL/LPL4-2/LA      NRR/DRA/APLA/BC NAME      TWengert                PBlechman              SRosenberg DATE      11/29/16                11/29/16              11/29/16 OFFICE    NRR/DORL/LPL4-2/BC(A) NRR/DORL/LPL4-2/PM NAME      DBroaddus                TWengert DATE      11/29/16                11/29/16}}

Latest revision as of 11:36, 30 October 2019

Supplemental Information Needed for Acceptance of Requested Licensing Action Amendment Request to Revise National Fire Protection Association Standard 805 Modifications
ML16333A307
Person / Time
Site: Arkansas Nuclear Entergy icon.png
Issue date: 11/29/2016
From: Thomas Wengert
Plant Licensing Branch IV
To:
Entergy Operations
Wengert T, NRR-DORL 415-4037
References
CAC MF8691
Download: ML16333A307 (4)


Text

UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 November 29, 2016 Vice President, Operations Arkansas Nuclear One Entergy Operations, Inc.

1448 S.R. 333 Russellville, AR 72802

SUBJECT:

ARKANSAS NUCLEAR ONE, UNIT 2 - SUPPLEMENTAL INFORMATION NEEDED FOR ACCEPTANCE OF REQUESTED LICENSING ACTION RE: AMENDMENT REQUEST TO REVISE NATIONAL FIRE PROTECTION ASSOCIATION STANDARD 805 MODIFICATIONS (CAC NO. MF8691)

Dear Sir or Madam:

By letter dated October 27, 2016 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML16302A227), Entergy Operations, Inc. (Entergy) submitted a license amendment request for Arkansas Nuclear One, Unit 2 (AN0-2). The proposed amendment would revise the National Fire Protection Association Standard 805 (NFPA 805),

"Performance-Based Standard for Fire Protection for Light Water Reactor Electric Generating Plants" (2001 Edition), Modifications for AN0-2, previously approved by the U.S. Nuclear Regulatory Commission (NRC) in a letter dated February 18, 2015 (ADAMS Accession No. ML14356A227). The purpose of this letter is to provide the results of the NRC staff's acceptance review of this amendment request. The acceptance review was performed to determine if there is sufficient technical information in scope and depth to allow the NRC staff to complete its detailed technical review. The acceptance review is also intended to identify whether the application has any readily apparent information insufficiencies in its characterization of the regulatory requirements or the licensing basis of the plant.

Consistent with Section 50.90 of Title 1O of the Code of Federal Regulations (1 O CFR), an amendment to the license (including the technical specifications) must fully describe the changes requested, and following as far as applicable, the form prescribed for original applications. Section 50.34 of 10 CFR addresses the content of technical information required. This section stipulates that the submittal address the design and operating characteristics, unusual or novel design features, and principal safety considerations.

The NRC staff has reviewed your application and concluded that the information delineated in the enclosure to this letter is necessary to enable the NRC staff to make an independent assessment regarding the acceptability of the proposed amendment request in terms of regulatory requirements and the protection of public health and safety and the environment.

In order to make the application complete, the NRC staff requests that Entergy supplement the application to address the information requested in the enclosure by December 9, 2016. This will enable the NRC staff to complete its detailed technical review. If the information responsive to the NRC staff's request is not received by the above date, the application will not be accepted for review pursuant to 10 CFR 2.101, and the NRG staff will cease its review activities associated with the application. If the application is subsequently accepted for review, you will

be advised of any further information needed to support the NRC staff's detailed technical review by separate correspondence.

The information requested and associated timeframe in this letter were discussed with Mr. David Bice on November 22, 2016.

If you have any questions, please contact me at (301) 415-4037 or by e-mail at Thomas.Wengert@nrc.gov.

Sincerely,

~*

Thomas J. Wenge , Senior Project Manager Plant Licensing IV-2 and Decommissioning Transition Branch Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-368

Enclosure:

Supplemental Information Needed cc w/encl:: Distribution via Listserv

SUPPLEMENTAL INFORMATION NEEDED AMENDMENT REQUEST TO REVISE NATIONAL FIRE PROTECTION ASSOCIATION STANDARD 805 MODIFICATIONS ENTERGY OPERATIONS, INC.

ARKANSAS NUCLEAR ONE, UNIT 2 DOCKET NO. 50-368 By letter dated October 27, 2016 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML16302A227), Entergy Operations, Inc. (Entergy) submitted a license amendment request (LAR) for Arkansas Nuclear One, Unit 2 (AN0-2). The proposed amendment would revise the National Fire Protection Association Standard 805 (NFPA 805),

"Performance-Based Standard for Fire Protection for Light Water Reactor Electric Generating Plants" (2001 Edition), modifications for AN0-2, previously approved by the U.S. Nuclear Regulatory Commission (NRC) in a letter dated February 18, 2015 (ADAMS Accession No. ML14356A227).

The NRC staff has reviewed your application and concluded that the information delineated below is necessary to enable the NRC staff to make an independent assessment regarding the acceptability of the proposed amendment request in terms of regulatory requirements and the protection of public health and safety and the environment.

  • Most of the proposed modifications in Section 2.0 of the LAR replace cable rerouting with alternative electronic modification. Cable rerouting would eliminate the possibility for fire-induced failure while alternative electronic modifications will only reduce the possibility of fire-induced failures. Contrary to this observation, Tables 1 and 2 on page 25 of 30 of Attachment 1 of the LAR indicate that several alternative electronic modifications result in lower plant risk compared to the cable rerouting option. Provide supplemental information explaining why the risk decreases in some of the modifications summarized in Table 2 and increases for other modifications.

Enclosure